Torrent Power Limited (TORNTPOWER) Earnings Call Transcript & Summary

February 4, 2022

National Stock Exchange of India IN Utilities Electric Utilities earnings 58 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Q3 FY '22 earnings conference call for Torrent Power Limited, brought to you by IIFL Securities Limited. <<operator_script>> Kindly be aware that this conference is being recorded. At this point, I'll turn the conference over to Mr. Harshavardhan Dole of IIFL Securities Limited. Thank you, and the floor is yours, sir.

Harshavardhan Dole

analyst
#2

Thank you, Steven. Hello, everyone. Speaking for IIFL Securities, I extend a warm welcome to all of you on the occasion of Torrent Power's 3Q FY '22 Earnings Call. First off, I want to congratulate the management on a solid performance and especially for raising the dividend payout. Many thanks, sir. Joining us today to walk through the results in detail and share the outlook on performance is Torrent Power's senior management team, which includes Saurabh Mashruwala, VP Finance; Rishi Shah, GM Finance; and Jayprakash Khanwani, AGM Finance. I'll now turn the call over to Saurabh bhai for his opening remarks, and after that the floor will be opened for Q&A. Over to you, sir.

Saurabh Mashruwala

executive
#3

Thank you, Harsh. Yes, a good morning to everyone, and thanks for being on Torrent Power's earnings call for Q3 FY '22. To start with, I'll walk you through how we performed this quarter, and after that we'll open up all the lines for a Q&A session. Let's begin with the quarter's performance at the PBT level, and we'll address ex expenses separately after that. PBT as reported for the quarter came in at INR 509 crores, against INR 399 crores in the same quarter a year ago, which works out to a rise of roughly INR 110 crores, around 28% on a reported basis. Now, there were no one-off items at any point during the current quarter, but as you'll remember, the reported PBT for the corresponding quarter of last year carried 2 one-off items. The first was a reversal of provision for doubtful debt in the franchisee distribution business of roughly INR 31 crores, driven by better collection efficiency and higher maintenance activity in that same quarter a year earlier. And the second was a net reversal of around INR 5 crores against the fuel cost. Taken all together, the net nonoperating credit came to about INR 36 crores for last year's Q3 FY '21.

Saurabh Mashruwala

executive
#4

When you factor in this one-off, profit before tax for the quarter came in at INR 509 crores, versus INR 363 crores in the same quarter a year earlier — that's roughly INR 146 crores more, an increase of about 40%. Next, let me walk you through the main points on the gain in adjusted PBT, which was INR 546 crores this quarter. The operating profit improvement stems largely from — well, there are actually 3 reasons, so I'll just detail one — the fourth reason. That fourth reason is better profitability at gas-based power plants, driven by 4 factors. Those 4 factors delivered a gain of roughly INR 85 crores for gas-based power projects. First, a gain of INR 107 crores from selling LNG. Because LNG prices were elevated during the quarter, it made commercial sense to sell the LNG itself rather than converting it into electricity. Second, higher profitability from the merchant power business contributed about INR 137 crores. We sold around 66 MUs and earned a contribution of 60, 70 paisa, which works out to roughly INR 44 crores of merchant gain, compared with 48 MUs sold in the same quarter last year at INR 240 crores contribution, and we then grew INR 7 crores.

Saurabh Mashruwala

executive
#5

We had a differential gain of roughly INR 37 crores this quarter. Whether we sell LNG or merchant power, those are somewhat interchangeable. So during this quarter, we sold LNG as well. We also sold merchant electricity. Those 2 gains, those 2 items, were partly offset by a contribution reduction of around INR 9 crores, coming from lower fuel savings because of lower PLF, which is partly offset by the lower O&M cost for our gas-based power projects. There was also an increase in O&M expenses of about INR 50 crores. That came from regular maintenance, which we typically do every 3 years. And the rest sits in fixed cost recoveries. So in summary, because of the above factors, gas-based power plant profitably has improved by about INR 85 crores on a net basis. The second point is moving to how the distribution business performed. Because industrial demand was restored — it had been impacted last year by COVID-19 — therefore, the reduction in T&D losses resulted in a gain of about INR 19 crores. Yes. Third item, there was a reduction in finance costs for the quarter of about INR 33 crores due to a lower rate of interest and a reduction in average cost of — average debt level.

Saurabh Mashruwala

executive
#6

Interest expense came in roughly 20 basis points lower this quarter versus the same quarter a year ago. As of 31st of December '21, our debt stood at a lower INR 7,528 crores, against INR 8,374 crores on December '20 — a reduction of roughly INR 850 crores. So we managed to bring debt down by around INR 850 crores. Turning to operating performance for the quarter, the distribution business saw demand normalize, rising about 4% year-over-year, helped by industrial and commercial units reopening following the COVID-19 second wave. Q3 '22's rebound showed roughly a 2% gain across the 3-quarter period, and for the full year we expect demand to close at the pre-COVID level of FY '20. Now to the PAT figures. PAT for the quarter came in at INR 369 crores, versus INR 320 crores in the same quarter last year — an increase of roughly INR 49 crores, or about 15%. That wraps up the overview of the quarter's financial and operating performance. I'll now move on to — give you an update on the projects currently in the pipeline.

Saurabh Mashruwala

executive
#7

To start, the 115-megawatt SECI V project has been granted an extension — from February '22 to September '22. That gives us a bit more time for commissioning. The EPC contract is already awarded, and commissioning of this project will probably happen sometime in FY '23. Next, the SCOD for the 100-megawatt GUVNL project has moved to October '22 from July '22. So again, additional time was given to us to commission that project. Third, the SCOD for the 300-megawatt TPLD project has likewise been pushed from December '22 to November '22. Now, the bidding process for the 300-megawatt AP project, where we hold L1, was canceled. As a result, this project will not be kicked off. We anticipate taking over the licensed distribution business of the Union territory of Daman and Diu. As was shared on the previous call, given the stay granted by the Bombay High Court and the tender process carried out by the Supreme Court, the Union Cabinet approved on 24th of November the formation of a company to privatize the electricity distribution business of Daman and Diu, along with the sale of equity shares in that newly formed company to the highest bidder, which is Torrent Power. Finally, the acquisition transaction executed with <<inaudible>> Reliance and BP is expected to be completed during Q4.

Saurabh Mashruwala

executive
#8

That covers everything for the quarter. At this point, I'd like to ask the coordinator to open up the phone lines for the Q&A session. We want everyone to remain safe and healthy. I'll now hand things over to the operator. Thank you very much.

Operator

operator
#9

<<operator_script>> Our initial question comes from Aniket Mittal with SBI Mutual Fund.

Analyst

analyst
#10

I’ve just got a few questions about the gas-based portfolio. So I believe we had the gas side through December ’21, but we’ve been using that more for LNG trading and the merchant curve instead of the long-term PLF. Could you just lay out your strategy going forward on that front? And how do we stand regarding gas supplies for the next fiscal year? That would be helpful.

Saurabh Mashruwala

executive
#11

Yes. Thank you, Aniket. Regarding gas, as you're aware, we've issued tenders. In fact, we now have a new <<inaudible>> IOC and Reliance arrangement covering roughly 25% to 30% of what the SUGEN and UNOSUGEN plants need at present. For the remainder, we need to — we're securing LNG through short- to medium-term contracts from the global market. So we issued tenders covering 5 years, specifically calendar year '22 through '27. We floated 34 cargo tenders, and to date we've contracted 3 cargoes per year for '23 to '27. That should address approximately another 25% of the requirement between calendar '23 and '27. Taking everything together, we're covering 50% of requirements. On current financials, we're waiting — since gas prices are elevated right now, though they've eased somewhat, we saw them drop to around $38 last quarter. At present they've fallen to roughly $22. So we anticipate prices will decline further after winter. That's what we — we've also heard that Russia has begun supplying additional European countries, which has affected the present LNG price on the international market.

Saurabh Mashruwala

executive
#12

After winter, we anticipate a decline in gas prices. And after that, we'll contract the gas for the next fiscal, I'd say. So that's the current position as far as gas is concerned.

Analyst

analyst
#13

All right, and just so I’m clear on the effect the lower PLFs had during this quarter. I believe you cited a figure of INR 9 crores. So does that INR 9 crore relate solely to the efficiency savings we lost? Is that the right way to understand it?

Saurabh Mashruwala

executive
#14

Right. Those are efficiency savings, since we gave up some fuel gain owing to reduced PLF and so on. At the same time, with a lower PLF, we often pick up savings on O&M cost as well, because my O&M cost will come down too. So to that extent, part of it gets offset — the fuel loss is offset by the drop in O&M costs. So INR 9 crores net of fuel gain, which we have a lot. And the lower O&M cost partly makes up for it.

Analyst

analyst
#15

Sir, could you just point out what the component of the efficiency loss was for the quarter?

Saurabh Mashruwala

executive
#16

At this moment, I don’t have the breakup. But the net impact comes to roughly INR 9 crores for the quarter.

Analyst

analyst
#17

Fair enough. And since fuel availability isn’t an issue and there’s no tie-up affecting our fixed charges, you don’t see any impact from that either, correct?

Saurabh Mashruwala

executive
#18

No. Nothing right now.

Analyst

analyst
#19

And just one final question. As we head into 4Q, looking at the January data, our SUGEN plant is running at a PLF of 25%, and UNOSUGEN is mostly shut. So would you say this fairly represents our current supplies? Or to put it another way, until, let's say, gas prices stay elevated and we can't tie up supplies, is it fair to assume SUGEN would run at a 25% PLF and UNOSUGEN would mostly be shut?

Saurabh Mashruwala

executive
#20

Right away, yes — since we need to secure gas for the coming fiscal year, which we figured we'd purchase, I believe, after winter. The price should be minimal, I'd say. So we'll begin tying the PLF for the next fiscal.

Analyst

analyst
#21

So up to that point, it would mostly be the PLFs.

Saurabh Mashruwala

executive
#22

Yes. Yes.

Operator

operator
#23

Our next question comes from Rahul Modi, who is on the line from ICICI Securities.

Rahul Modi

analyst
#24

Nice results given how tough conditions have been. One thing I wanted to ask about is the LNG you have right now — you said roughly 50% is already locked in. So for the gas-based projects, what's the average cost of the LNG you've contracted so far?

Saurabh Mashruwala

executive
#25

The LNG that's under contract is consistently tied to Brent pricing, and specifically to the slopes. So I'd say it isn't tied to where LNG prices sit right now. It's consistently tied to Brent. That price floats, and we get the chance to swap that floating portion into a fixed price when the timing is right. That's also what we did before. In the prior year, we converted every one of our cargoes to the fixed price. So at present, its floating price is tied to Brent.

Rahul Modi

analyst
#26

All right. So if you want to attach any figure to this so we can grasp it, how do you view it? You could share the slope you anticipate it heading toward, but...

Saurabh Mashruwala

executive
#27

We expect slope to land in the neighborhood of 11% to 11.5%, and as usual, slope will contract with the season.

Rahul Modi

analyst
#28

And when you talk about dollars, what kind of figure might that come to?

Saurabh Mashruwala

executive
#29

Regarding Brent — the floating price for Brent, that's correct.

Rahul Modi

analyst
#30

Alright. Alright. Sir, for the second question, could you share some updates on the solar projects we're already working on. And realistically speaking, sir, where do you stand going forward? Because clearly, when we undertook that, the various prices -- well, module prices have risen considerably now. So any thoughts on how viable those projects are at this point? And what's our strategy moving ahead?

Saurabh Mashruwala

executive
#31

As for new projects, we are taking part in the bidding. Since module prices have risen, we are bidding accordingly, with those higher module prices taken into account. That is where things stand — and we continue to participate. And we need...

Rahul Modi

analyst
#32

Regarding the tariffs that have already come to light and that you prevailed on?

Saurabh Mashruwala

executive
#33

We're just holding out for module prices to fall, since this problem affected everyone. So we're waiting, and the government is fully aware of the situation, and they've also pushed out the SCOD date. That gives us some extra time to get the contracts done for the modules. We're waiting for the chance to contract the modules.

Rahul Modi

analyst
#34

And sir, with this 40% BCD that's now been introduced, how will it get passed on through the tariff? Will our capacities qualify for a pass-through?

Saurabh Mashruwala

executive
#35

Which one?

Rahul Modi

analyst
#36

Regarding the customs duty that took effect on imports of modules starting 1 April, will that..

Executive

executive
#37

Generally speaking, Indian law gets passed through. I’d also add that when we placed bids for these contracts, module prices were at a totally different level. Over the last 9 to 12 months, they’ve gone through the roof. I think this is a big problem where international module prices are concerned. So unless those prices come down — meaning we’re going to examine this very closely — unless they drop, we won’t be in a position to proceed. So in effect, we’re focused on the module prices. Whenever they come down, we would want to carry out this project, provided it means international module prices are lower.

Rahul Modi

analyst
#38

Right, right. So sir, one more thing I wanted to ask, sir: with all these bids we've now done incrementally, the government is talking about taking an ALMM-style approach. So under these bids, are you compelled to use domestic modules regardless, or is importing still possible, or is that not mandated?

Executive

executive
#39

It's open. Yes, it's open. Domestic modules are an option for us too. That hinges on the price we're getting those modules at.

Operator

operator
#40

<<operator_script>> Our following question comes from Apoorva Bahadur with Investec.

Apoorva Bahadur

analyst
#41

Sir, I’d like to get some clarity on the gas availability front. Now that we’ve made the decision and sold the cargoes that were available, what availability will there be for our gas power plants in Q4 and for the financial year FY '22? And also, what kind of underrecovery are you seeing there on a fixed cost basis?

Executive

executive
#42

To address Aniket 's question, as we explained at the start of the call: yes, for gas we hold a fixed contract covering calendar '22, '26, and '27, and roughly 50% is already locked in. Right now, around 25% to 30% is tied up through IOCL as well as Reliance. So for Q4, yes, we lack tie-ups for gas beyond that. But we are waiting to separate — after winter, our view is that our gas price will decline, since in fact it has already begun falling. So following that, we will secure supplies for the next financial year.

Apoorva Bahadur

analyst
#43

Alright. Sir, what hit should we expect to fixed cost recovery in Q4? And how much lower was availability in Q3?

Executive

executive
#44

When it comes to fixed costs for SUGEN and UNOSUGEN, those get passed through. So practically speaking, there's no real heat on the P&L where fixed costs are concerned.

Apoorva Bahadur

analyst
#45

Okay. So even with no gas, we still managed to keep the plant availability up...

Executive

executive
#46

Right. Even without the gas — the gas itself is available. Actually, gas isn’t the problem. We can even source gas as well. So we can — the plant is available. We can access the plant’s availability.

Saurabh Mashruwala

executive
#47

Apoorva, this question concerns pricing, not whether gas is available. So there's plenty of gas at a given price. That means recovering fixed costs isn't a problem here.

Executive

executive
#48

Fixed costs depend on how available the plant is.

Apoorva Bahadur

analyst
#49

All right, that's fair. In UNOSUGEN, I don't think it'll pose an issue.

Executive

executive
#50

Correct. That's exactly our point. UNOSUGEN is not going to pose an issue. Power supply from the plant is available.

Operator

operator
#51

Sumit Kishore from Axis Capital has the next question.

Sumit Kishore

analyst
#52

I'd like to start with a question about how EBITDA breaks down by segment, both for the quarter and for the 9 months. Would you be able to provide those figures?

Saurabh Mashruwala

executive
#53

I can walk you through the EBITDA figures for the quarter. Sure — for the quarter we just closed, EBITDA came in at roughly INR 300 crores, compared with INR 218 crores in the same quarter a year ago. Renewables stood at around INR 114 crores, against INR 129 crores. Distribution was approximately INR 352 crores versus INR 327 crores. Franchisee was about INR 206 crores compared with INR 197 crores. On an overall basis, EBITDA reached INR 988 crores versus INR 860 crores. Those figures are before one-off items. On a reported basis, after one-offs, EBITDA was roughly INR 1,000 crores for the quarter, compared with INR 908 crores for the full year and for the comparable quarter of last year.

Sumit Kishore

analyst
#54

Alright, turning to your distribution franchisee segment. Across the cycle, we've observed a decline in T&D losses. Do you see room for further improvement, or have you arrived at levels you're comfortable with?

Saurabh Mashruwala

executive
#55

Look, at the present level, for instance — in our distribution business, when it comes to T&D loss, there is always — we keep improving. As a matter of fact, on a YTD basis right now, for example, Bhiwandi is reporting roughly 12% in T&D losses. Agra sits at about the same level. And SMK, since it's a new circle, is at about 50%, a sustainable level. So there's room for further improvement across all these 3 areas.

Rishi Shah

executive
#56

To build on what Saurabh bhai said, if you look at T&D losses within our distribution licensed businesses, those sit somewhere around 4% to 5%. That means there's considerable headroom for us to bring losses down in these areas to those same levels too. So the runway is quite clear. Over a period of time, this should be achievable.

Saurabh Mashruwala

executive
#57

Each year, we’re able to demonstrate progress on T&D losses. That’s what we’re focused on at the moment, for Bhiwandi and Agra as well as SMK.

Sumit Kishore

analyst
#58

Could you lay out some kind of goal — for instance, by FY '23 or FY '24 — showing how T&D losses in Bhiwandi and Agra would trend as well, sir?

Rishi Shah

executive
#59

So, Sumit, I don't think we provide any target. But as a strategy or as a policy, we keep on reducing losses here. We don't give any targets or any estimates for the future. But if you look at my past history of last 5 years, we have been reducing the T&D losses 1.5% to 2%. But as we move along and keep on reducing this, the delta could come down. But there will be a reduction in trajectory. That is what we can take.

Sumit Kishore

analyst
#60

Alright, that's reasonable. And last, regarding this INR 107 crores gain on the sale of LNG, could you help us understand how much gas was actually sold? What did you pay to procure it, and at what price was it sold? And if you had used that landed LNG price to generate electricity, what tariff would that have worked out to?

Saurabh Mashruwala

executive
#61

Yeah. It's going to be hard to give you one. But here's what I can say: whenever gas is available for our merchant business, we either sell the gas or we generate power and sell that power. So we make our decision based on whatever opportunity is there, and we'll do one or the other — either sell LNG as well, or sell power as well, or we can do both too. So depending on what opportunities are available, we decide and then we implement it.

Sumit Kishore

analyst
#62

Alright, so looking ahead to next quarter, what's the gas availability going to be? Could you run through Q4 for us again? And would we be looking at another surplus of gas, given that prices for gas remain pretty high right now?

Saurabh Mashruwala

executive
#63

Regarding Q4, we aren’t in a position to provide any guidance right now.

Sumit Kishore

analyst
#64

Okay, I just wanted to get a sense of where you stand on overall gas availability as you head into Q4.

Saurabh Mashruwala

executive
#65

Like we talked about, we've got gas on hand for roughly 25%, 30% of capacity. So that's what — that's what we lean on to handle those sorts of volumes at — for Q4 right now.

Rishi Shah

executive
#66

And Sumit, to build on what Saurabh bhai mentioned, Q4 is usually a quarter where demand is lower as well. It begins to pick up around March or mid-March. So everything hinges on how demand looks in our distribution licensed businesses, the ones for which the PPAs have been tied up. So it's an interplay between the two of them — how much gas is available and how much demand there is. So it's a very dynamic scenario in which one eye is on demand and the other eye is on gas availability.

Operator

operator
#67

Nitin Arora from Axis Fund has the next question.

Nitin Arora

analyst
#68

It's really more of a clarification. Regarding the gas availability you're showing, you're saying there's no underrecovery because even if I show gas at $15 available at my gas plants, the regulator permits it. He allows showing gas prices at 3x, 4x pricing, and there's no underrecovery of fixed costs at your P&L. Is that what you're getting at?

Saurabh Mashruwala

executive
#69

The fixed costs are set by the regulator — SUGEN's fixed cost is determined, for instance, and the INR 228 crores fixed cost is determined as well; that's the piece we're discussing. What the recoveries mainly show is that the plant is available. As for buying power at INR 15 — we aren't about to do that, but the fixed cost remains available. We could even supply power at INR 15 if our distribution arm wanted it at a rate like that. However, we do have to demonstrate that the plant is available. On the basis of plant availability, the fixed cost gets passed through for SUGEN as well as UNOSUGEN.

Nitin Arora

analyst
#70

The reason I'm raising this question is this: if that's how it works, then the Gujarat regulator's CapEx of $7.5 for gas ultimately loses its validity, correct? Because once that regulator permits you to reflect availability at $15, then the $7.5 no longer factors in at UNOSUGEN in that manner. So that too ought to have been — moving forward, even if I were to show a dealer plant, I would still recover fixed cost as a result. Is that the proper way to view it, given that this regulator lets you remain at 4x the pricing?

Saurabh Mashruwala

executive
#71

UNOSUGEN is split into 62 PPAs. Availability has therefore been shown. Given that availability, the fixed cost gets passed through.

Operator

operator
#72

Our following question comes from Bhavin Vithlani, who is on the line from SBI Mutual Fund.

Bhavin Vithlani

analyst
#73

To follow up on what Nitin asked before: with UNOSUGEN, the regulator imposed a cap requiring it to be nearer to medium-term pricing, and clearly, gas prices too if you work backward. For SUGEN, though, it's quite straightforward — you must demonstrate gas, and then your fixed charges are paid. Offtake hinges on the market — on whether they discount prices. So with UNOSUGEN, what reverse-worked gas pricing emerges? Up to that point, you can be paid your fixed charges. Past that, however, fixed charges might not be on offer.

Saurabh Mashruwala

executive
#74

Look, when it comes to UNOSUGEN, even though the cash is available, we’re going to ensure that we won’t be supplying power past this category now. So...

Bhavin Vithlani

analyst
#75

Of course, I get it. The next question concerns fresh possibilities in distribution. We noticed a few bids come in. Could you bring us up to date on those, and also on the distribution license you secured? And what other opportunities are you currently seeing on the ground where discussions are underway or some tender activity is taking place?

Saurabh Mashruwala

executive
#76

Right now, Daman and Diu is in the pipeline. So that’s what will be materialized going forward. Plus the union territories — the government — luxury plays a very small area, but it is on the horizon. The government invited the bid. So these are the opportunities available at this moment that we are looking at.

Bhavin Vithlani

analyst
#77

Okay. Do you have anything new about Delhi? Earlier news stories said Reliance was also looking to sell that one.

Saurabh Mashruwala

executive
#78

No, that isn't something the project had at this point.

Bhavin Vithlani

analyst
#79

Alright, just one final question from me. Regarding the renewable expansion you've laid out over a 5-year horizon, and considering where things stand right now, what sort of growth — specifically growth in IRRs — can we expect to see? Because as you pointed out, module prices have risen, and there's also a customs duty that was imposed in the Union budget. So in your view, what tariff level is needed to achieve a low double-digit IRR? And do you believe you can — that the opportunity exists for you to hit your IRR target?

Saurabh Mashruwala

executive
#80

Yeah. When it comes to renewable, we're pursuing both avenues — organic expansion and inorganic expansion as well. We're also examining various M&A — acquisitions too, on the renewable side, so that we can at least achieve roughly 12%, 13% IRR returns from those projects. And on top of that, we're also bidding for the projects as well, so that we can at least get about 11%, 12% in equity IRR. So that's what we're working on right now.

Bhavin Vithlani

analyst
#81

Okay, sir, just one last question if I may. Transmission was also an opportunity that you laid out as part of your long-term plans. Given the way biddings are underway, do you see some growth opportunities in transmission as well? And is there an organic opportunity in that segment too?

Saurabh Mashruwala

executive
#82

And we're actively engaged on that front as well. As a matter of fact, we've submitted bids for a few processes and projects too. Regrettably, we haven't managed to secure those projects successfully as of now. But keep watching us — we'll continue placing bids on transmission line segments as well.

Operator

operator
#83

The following question comes from Dhruv at HDFC AMC.

Analyst

analyst
#84

Sir, I just have one question about your franchisee business. On a year-over-year basis, we've seen a decent reduction in your AT&C losses — I mean, the figure, the AT&C percentage, almost 6% in Bhiwandi and about 2% in Agra. And sir, earlier, we understood that a 1% reduction in both is roughly INR 40 crores of incremental EBITDA or PBT. But if I look at the EBITDA number you've given for the franchisee, it's about INR 197 crores moving to INR 206 crores. In that context, it looks extremely low. And even your SMK, the loss has come down. So what could be driving this gap in the franchisee business?

Saurabh Mashruwala

executive
#85

If you look at a comparable figure—say Q3 '21 against Q3 '22—and if you recall the same quarter a year ago, last quarter as we discussed, we had roughly INR 31 crores in reversal of bad debt provision, and that is absent this quarter. So that's the reason that despite having lowered—despite my ability to bring down T&D losses, my bottom line hasn't—my absolute bottom line number hasn't gone up, owing to that one-time gain we recorded in the same quarter last year.

Analyst

analyst
#86

All right, all right. So once you factor in that INR 30 crores, it still looks low, because you should have gained at least around INR 50-odd crores from the loss reduction plus the SMK loss reduction. But — understood, that's a bit short...

Saurabh Mashruwala

executive
#87

Regarding Bhiwandi and SMK, we saw certain unfavorable rate variances, and the reason is that in Maharashtra, sales prices were lowered. So the sales price came down somewhat as well, and that played a part in the softer — it may also weigh on profitability.

Analyst

analyst
#88

Understood, understood. Sir, could you walk through that same math again — the benchmark you provided before? With the reset tariffs now, what does a 1% reduction translate to? If we cut losses by 1% in Bhiwandi and in Agra, what would that be worth? And of course, if you're able to break those two out separately, that would help.

Rishi Shah

executive
#89

Dhruv, those figures aren't going to move much. When you look at where we stand right now — INR 206 crores against INR 197 crores — and I subtract INR 31 crores from that INR 197 crores, you're left with a gap of roughly INR 40 crores. As we said before, a 1% reduction tentatively delivers INR 40 crores across the full year. So running that math, it lines up as well. What that tells us is this rate cut doesn't carry a meaningful impact when measured against the 1% reduction parameters.

Analyst

analyst
#90

Understood. Since Bhiwandi, your losses dropped by roughly 6%, and in Agra by roughly 2%. No, I'll likely take that offline. Sir, the second item concerned the gas — just to confirm, apart from 4Q, I mean, looking forward, 50% of your PPA capacity is tied up. And out of that 50%, 50% comes from IOCL and Reliance, which I believe is largely on fixed pricing. And the other 50% is Brent-linked. Is that broadly correct, sir?

Rishi Shah

executive
#91

That's correct.

Analyst

analyst
#92

Understood. And with the Brent-linked piece, you're attempting to convert that as well. Right now it's a floating blend. You're also looking to move it over to fixed Brent, as you likely did before.

Saurabh Mashruwala

executive
#93

Yes. Precisely.

Analyst

analyst
#94

Understood. And sir, the third item was that we also have this Petronet offtake agreement — I mean, the conversion of gas to — LNG to gas conversion. If that isn't used, we'd likely still have to take — I mean, the take-or-pay arrangement. So does that cost land on you, or is a pass-through of it possible?

Saurabh Mashruwala

executive
#95

There are a few alternatives on that front. In fact, distribution is something we can handle as well. We can also collaborate with that PLL to distribute it — to distribute the cargo. And we have ways to bring in the gas too and sell it in the market, in the domestic market as well. That option exists as well. Another possibility for us is that we can complete the capacity too. There, too, an option is available. And fourth, yes, we can work with the <<inaudible>> as a pass-through on this front as well.

Analyst

analyst
#96

That means this cost really isn't something we need to worry about.

Saurabh Mashruwala

executive
#97

Yeah, not right now.

Analyst

analyst
#98

And sir, one final point on the solar bid: you said that if pricing stays elevated, you'd revisit the project. As I understand it, you have 2 projects currently under construction. One is the GUVNL 100-megawatt and 300-megawatt — the 300-megawatt project. So sir, just so I understand, suppose, for example, that in such an eventuality it gets canceled — what would be — I mean, would there be any penalty you'd have to pay? Or how would you exit that contract?

Saurabh Mashruwala

executive
#99

When it comes to GUVNL, I'd call that penalty of roughly INR 19 crores not material.

Analyst

analyst
#100

Right. And on the Torrent item — the one at 300 megawatts?

Saurabh Mashruwala

executive
#101

Yes. Our hope is that we’ll be able to put that project into effect.

Operator

operator
#102

Moving on, our next question comes from Devam Modi at ARDEKO.

Devam Modi

analyst
#103

Yes. I just wanted to get a sense of — what would the fixed cost recovery figure be for SUGEN and for UNOSUGEN?

Saurabh Mashruwala

executive
#104

UNOSUGEN comes to roughly INR 228 crores each year. As for SUGEN — hold on a moment — I'll give you that figure as well. Could we follow up with you on this after the call?

Devam Modi

analyst
#105

Certainly. Certainly. And that would be — from this fixed cost, since what you're mentioning, the figure — what figure is going to show up above EBITDA and below EBITDA?

Saurabh Mashruwala

executive
#106

That falls inside the EBITDA portion.

Devam Modi

analyst
#107

So that fixed cost recovery—will that show up only in EBITDA?

Saurabh Mashruwala

executive
#108

Yes. Yes.

Devam Modi

analyst
#109

Right, since as we understand it, the fixed cost would include some depreciation and interest costs. That's why — typically.

Saurabh Mashruwala

executive
#110

Roughly INR 625 crores. That figure — INR 625 crores — covers 25% for the SUGEN project. Depreciation was part of it, and interest too.

Devam Modi

analyst
#111

Right. So this whole figure is going to move through revenue — what I mean is, that entire figure will come through in revenue. It'll sit above EBITDA, and that's what you're saying.

Saurabh Mashruwala

executive
#112

That's right. Precisely.

Devam Modi

analyst
#113

So that comes to — across both plants together, it's about INR 210 crores a quarter in fixed costs that get recorded, and that sits above EBITDA?

Saurabh Mashruwala

executive
#114

Yes. Indeed.

Devam Modi

analyst
#115

Absolutely. And regarding renewables, sir, what sort of scale could we realistically reach over the coming 3 to 5 years? And ultimately, is there any thinking about monetizing that through an investor or something similar, given that you're capping them at roughly, say, 11% to 13% IRR, while you could place that capital at around, say, 8%, 9% IRR going forward, as many plants are discussing right now, or along those lines?

Saurabh Mashruwala

executive
#116

We're targeting as much as 5 gigawatts of renewable capacity by '24, '25. And when you consider the project running right now, plus what's in the pipeline, plus whatever SPV you're referring to, we're at roughly 1.5 gigawatts of capacity as we speak.

Devam Modi

analyst
#117

Including the...

Saurabh Mashruwala

executive
#118

Every pipeline project, yeah — and that covers the SPA we've signed as well.

Devam Modi

analyst
#119

Sure, and like house and all that, okay. You're bringing up another point as well?

Saurabh Mashruwala

executive
#120

Five gigawatts of capacity by '24 and '25.

Devam Modi

analyst
#121

Alright, so on the Daman deal — where exactly do things stand right now in terms of when we see the takeoff? And what are the project dynamics looking like over there, in terms of investment, time lines, and IRRs?

Saurabh Mashruwala

executive
#122

We're just waiting on the LOA from the government, since the cabinet already gave its approval back in November. So as soon as that LOA is in hand — and actually, we've already begun working on it — once we receive it, we'll take over the Daman deal, possibly by the end of November.

Devam Modi

analyst
#123

So the legal obstacle that used to be in place isn't there anymore. Is that how you understand it?

Saurabh Mashruwala

executive
#124

On the government side, my understanding is that they'll be issuing the LOA sometime this month — that's the current month. That's what we're expecting.

Devam Modi

analyst
#125

And what sort of figures should we be thinking about, or others, when it comes to the spend, and what kind of revenues or EBITDA? What are the numbers that a person can see over there?

Saurabh Mashruwala

executive
#126

It's essentially a full industrial build. That's all we're able to share at this point. It is entirely industrial. Nothing residential is connected there.

Operator

operator
#127

Moving on, we have a question from Aniket Mittal at SBI Mutual Fund.

Analyst

analyst
#128

It looks like nearly all of what I asked has already been covered. On the CapEx front, though, could you point out what the CapEx has been for the 9 months so far, along with our targets for FY '22 and '23, and if possible, break that down by segment?

Saurabh Mashruwala

executive
#129

Yeah, on the CapEx side, license distribution for 9 months comes to roughly INR 730 crores. Franchisee is around INR 227 crores — INR 225 crores. And then, Q4 CapEx tends to be — it's always higher than the 9-month figure. So Q4 — and around INR 1,000 crores, actually, we've already spent. So you could look for roughly another INR 400 crores of CapEx in Q4. And as we — with the guidance of about INR 1,500 crores of CapEx each year that we intend to spend for the next 2 years, INR 1,250 crores toward license distribution and INR 250 crores toward the franchise distribution area. That said, more or less, we're on track where CapEx is concerned.

Analyst

analyst
#130

Sure. Just one question — could you highlight, I know you already gave the T&D numbers, but specifically what collection efficiencies you're seeing at both Agra and Bhiwandi? The reason I'm asking is that I believe there's roughly INR 130 crores of excess provision you made earlier, which I think we were hoping to recoup over the coming few quarters. If you could shed some light on that.

Saurabh Mashruwala

executive
#131

Out of that INR 130 crores provision, we've also managed to collect some, since we keep revisiting it each quarter. At least over the past year, we reversed a lot — a significant amount, I'd say, in Q3 and Q4 of last year. So there's still something outstanding that we're hoping to collect over the course of the coming year.

Analyst

analyst
#132

What would the amount still pending be?

Saurabh Mashruwala

executive
#133

The pending amount would be roughly — SMK would be roughly — SMK is the highest. Could I get back to you on that?

Analyst

analyst
#134

Okay, sure, no problem. Perhaps just one final question here. What I want to get a handle on is more from a circle standpoint. So with the fact that our PLF for SUGEN rules having dropped off, and considering the whole circle of Ahmedabad and Surat, I assume that to satisfy most of our demand you'll now be depending on the short-term market. So what share of your total demand, let's say, is now being sourced from the short-term market? And what rates are you paying there, right? Just so I understand how you see your power purchase cost burning. Because at the end of the day, your tariff is fixed at this point in time, right? So if you could shed some light on that?

Saurabh Mashruwala

executive
#135

Tariff isn’t fixed. Tariff is always a variable, since I have the opportunity to recover the additional power purchase cost through the <<inaudible>> mechanism. So...

Analyst

analyst
#136

Yes, of course. I completely get it, and you'll probably get that back later on. But if you wouldn't mind giving us some detail — I mean, on the reliance on the short-term market, how much of total demand are you now sourcing from there? What kinds of bilateral contracts have you executed? And at what average cost are you buying?

Saurabh Mashruwala

executive
#137

We will, in fact, provide that figure — what percentage we're sourcing from the short-term market — in a few minutes. So we just need to look at the numbers, and then we'll let you know.

Operator

operator
#138

We'll take our next question from Anuj Upadhyay with HDFC Securities.

Anuj Upadhyay

analyst
#139

Sir, could you tell us the price at which we're sourcing gas from Reliance and IOCL?

Saurabh Mashruwala

executive
#140

For Reliance, that's tied to Brent with an 8.5% slope. And IOCL as well — it's Brent-linked, on roughly a 12% slope, I'd say.

Anuj Upadhyay

analyst
#141

Okay, and just one quick follow-up regarding what was asked earlier about UNOSUGEN's availability. So, when showing availability for UNOSUGEN, are we using domestic gas — I mean, domestic gas prices to demonstrate that availability, since the imported one is quite expensive on that front? So is it the domestic gas that's been shown to — the price gap for domestic gas being used to show availability for UNOSUGEN? Just some clarification on that.

Saurabh Mashruwala

executive
#142

As far as UNOSUGEN goes, both were brought in as domestic gas. We also have the option to purchase imported gas while demonstrating the availability.

Anuj Upadhyay

analyst
#143

And as far as the blended rate goes, what does that come to?

Saurabh Mashruwala

executive
#144

That blended rate doesn’t exist. Whatever is available domestically — from Reliance, for example — we can show, and the balance will be the imported one. The regulator sets the blended ratio.

Operator

operator
#145

Our next question comes from B. Vijay at Spark Capital.

Bharanidhar Vijayakumar

analyst
#146

Yes. Are you able to hear me, sir?

Saurabh Mashruwala

executive
#147

Yes.

Bharanidhar Vijayakumar

analyst
#148

Right, so with regard to those 3 cargoes we've booked for gas, when does delivery begin, sir?

Saurabh Mashruwala

executive
#149

Starting with calendar year '23 and continuing after that.

Bharanidhar Vijayakumar

analyst
#150

That dates back to April '23.

Saurabh Mashruwala

executive
#151

Yes, April 2023.

Rishi Shah

executive
#152

For the 2023 calendar year.

Saurabh Mashruwala

executive
#153

Calendar year '23, so that's January '23.

Rishi Shah

executive
#154

The calendar year begins in January '23 and goes forward from there.

Bharanidhar Vijayakumar

analyst
#155

Right, so this year we've got Reliance and IOC at 25%, and for the other 75% we're open — we haven't sourced gas yet.

Saurabh Mashruwala

executive
#156

That's right. Precisely.

Bharanidhar Vijayakumar

analyst
#157

All right, all right. And could you provide, for this quarter, sir, the merchant sales broken out by unit count along with the average selling price?

Saurabh Mashruwala

executive
#158

We moved roughly 66 MUs, and for the quarter we brought in about INR 60, 70 paisa in quantum.

Bharanidhar Vijayakumar

analyst
#159

Okay. Okay. And last, a question about EBITDA by segment. Could you provide that for the 9-month period?

Saurabh Mashruwala

executive
#160

For the nine-month cumulative figure, I don't have that available at the moment. So we can provide that number offline.

Bharanidhar Vijayakumar

analyst
#161

Yes, sir. And that goal of ours — getting to roughly 5 gigawatts total in renewables within the next 3 to 4 years — is that still in place? Or, given that module prices have gone up and so on, are we considering slowing things down a bit?

Saurabh Mashruwala

executive
#162

That’s still the case at present. That’s still where things stand right now. Even so, our goal is to climb to as much as 5 gigawatts by ’24, ’25. That’s what we’re currently targeting.

Operator

operator
#163

Swati from VT Capital has the next question.

Analyst

analyst
#164

Yes. Are you able to hear me?

Saurabh Mashruwala

executive
#165

That's correct.

Analyst

analyst
#166

Yes. So first, about that 5 gigawatt renewable capacity. What CapEx guidance are you able to provide, say, through FY '24 and '25?

Rishi Shah

executive
#167

Swati, it's really tough to provide CapEx guidance. It hinges on the type of renewable you're pursuing—solar or wind. So for '24 and '25, at present we have just a single project that's operational—or rather, under construction. Other than that, we have 2 acquisitions in the works, and we've already shared the specifics on those. Beyond that, offering a guidance as such on fresh projects would be hard right now, because we currently have no new projects in the pipeline.

Operator

operator
#168

Vishal Biraia from Max Life has the next question.

Vishal Biraia

analyst
#169

How much equity dilution should we expect from the new INR 1,500 crores of CapEx you're planning?

Saurabh Mashruwala

executive
#170

Vishal, no dilution of equity is involved in this case. My apologies — I didn't catch what you were asking.

Vishal Biraia

analyst
#171

It concerned the 5 gigawatts of renewables you intend to get to. So beyond the CapEx you'll need for the businesses already in place...

Saurabh Mashruwala

executive
#172

When you take a look at the balance sheet we have right now along with the cash flows we're currently generating, to get to 5 gigawatts, honestly, we don't really need any equity as things stand today — what I mean is, we're bringing in roughly INR 3,500 crores, INR 3,600 crores of EBITDA annually, and within that there's ample headroom for deployment. On top of that, our present balance sheet is also underleveraged. So for hitting 5 gigawatts, I'd say there's no need whatsoever for any equity dilution.

Operator

operator
#173

Our next question comes from Harshavardhan Dole at IIFL Securities.

Harshavardhan Dole

analyst
#174

Rishi bhai and Saurabh bhai, I had two questions. The first one was that we've seen a huge drop in interest outgo, which, as you explained, comes from both a reduction in debt and benchmark rates coming down. Now, is there any portion of that we can keep in the P&L, meaning it benefited in the third quarter as well as on a 9-month basis? And how much have you passed on through lower tariffs? That was part one. Part two was basically about the broader capital allocation strategy. It's good to see payouts have risen to 33%. But again, relative to our CapEx plans as well as the leverage on the books, do you think there's any headroom to push it up further? Or will this be an adequate level of dividend payout?

Saurabh Mashruwala

executive
#175

Harsh, regarding your first question about interest pass-through: for the 9 months of this year, whatever reduction has occurred, roughly 15% to 20% of that pass-through will take place. The remainder would stay in the P&L, simply because of the reduction in the debts that existed for other projects, or the repayments that have been made. As for your second question, on CapEx allocation, our stated policy is a 40% dividend, and we hope to meet that on a year-on-year basis. And if you look at the 5-gigawatt target as well, as I explained in the earlier question, our current balance sheet and current cash flows do not warrant any reduction in the dividend policy. An increase in the dividend policy will depend on how management — or how things — turn out over a period of time. So it's a dynamic scenario: if other opportunities are available in, let's say, license distribution or franchise distribution or in transmission assets, then we would want to deploy capital in those areas. And if they are not there, then we will look at the dividend policy at a future point in time.

Saurabh Mashruwala

executive
#176

But right now, 40% is still left. Looking ahead, we’ll need to see what sorts of projects are in hand or what visibility those projects have, and after that we can make a decision about the way forward.

Harshavardhan Dole

analyst
#177

Okay, that helps a lot. As for the specifics on your ramp-up plans for Dadra and Nagar Haveli, will you be sharing those publicly once you take over, or would you prefer to give us a briefing on them now?

Saurabh Mashruwala

executive
#178

We'd prefer to hold off until we have the LOA in hand, and after that we can go into detail regarding that area or that license.

Harshavardhan Dole

analyst
#179

All right. Moderator, assuming nothing else comes up, should we treat that as the final question?

Operator

operator
#180

Alright, sir. That brings the Q&A to a close. I'll now pass the conference to Mr. Harshavardhan Dole, who will offer his closing remarks. The floor is yours, sir.

Harshavardhan Dole

analyst
#181

Thank you. Thanks to Rishi bhai and Saurabh bhai and the Torrent Power management for letting us host this call. We truly appreciate your time, sir. I would also like to express thanks to the participants for dialing in and raising questions about how the company has performed. Rishi bhai, Saurabh bhai, would you like to offer any closing remarks?

Saurabh Mashruwala

executive
#182

Thanks a lot, Harsh, for the chance to introduce our company to all these different folks. Many thanks. I hope everyone remains safe and well. That's really all we can say. Thank you very much.

Rishi Shah

executive
#183

Thank you. Thanks to each of you.

Operator

operator
#184

Thank you. Ladies and gentlemen, on behalf of IIFL Securities Limited, that brings this conference to a close. We appreciate everyone for participating, and you are welcome to disconnect your lines now.

Harshavardhan Dole

analyst
#185

I appreciate that.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Torrent Power Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Torrent Power Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Torrent Power Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.