Torrent Power Limited (TORNTPOWER) Earnings Call Transcript & Summary
February 14, 2023
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to the Q3 FY ’23 earnings conference call for Torrent Power Limited. <<operator_script>> Kindly be aware that this conference is being recorded. At this point I hand the call over to Mr. Lalit Malik, CFO of Torrent Power Limited. Thank you, and the floor is yours, sir.
Lalit Malik
executiveThank you. Good evening, everyone, and thanks for being on Torrent Power's Q3 FY ’23 earnings call. To start, I'll walk you through how the quarter went, and after that we'll open the phone lines for a question-and-answer session. Let me begin with the company's performance at the PBT level, and we'll treat tax expense separately after that. Reported PBT for the quarter came in at INR977 crores, versus INR509 crores in the same quarter a year earlier — a rise of INR468 crores, which works out to 92% on a reported basis. Neither the current quarter nor the corresponding quarter of last year contains any non-recurring items. I'll now take you through the main points behind the INR468 crores improvement in PBT for this quarter. The operating profit improvement comes mainly from, one, better profitability at the gas-based power plant, driven by two factors. The first is a net gain of INR397 crores from the sale of LNG — as we discussed on earlier calls, with elevated LNG prices it makes commercial sense to sell the LNG rather than convert it into electricity; and the second is a gain of INR35 crores from a lower depreciation charge in DGEN, reflecting the one-time impairment charge taken in Q4 of FY’22 and a reduction in the depreciation rate in SUGEN.
Lalit Malik
executiveSo overall, taking all those major factors into account, the profitability of the gas-based power plants went up by INR435 crores. Second, turning to how the distribution business performed after industrial demand came back — it had been hit last year by the COVID-19 pandemic — the overall contribution from that business showed a clear improvement, rising by INR122 crores. The main drivers are listed below. A, a gain of INR45 crores from lower T&D losses; B, volume and rate gains of INR19 crores from the franchisee business; C, higher ROE and incentive of INR26 crores in license distribution; and D, a higher contribution of INR32 crores from the new acquisition of DNH and DD. Next, the company's renewable business saw its contribution rise, mainly because of three factors. One, profit of INR21 crores booked from an acquisition completed during the last three quarters; B, partly offset by roughly INR3 crores less from existing plants, chiefly because of lower PLF and because 50 megawatt of the SECI-1 wind power project was unavailable for part of the month due to an EHS tower failure. So in total, profitability of the renewable power plants rose by INR22 crores. Next, finance cost increased by INR71 crores, driven mainly by average borrowing rising by about INR2,700 crores, depreciation and amortization expense going up by INR18 crores, and other miscellaneous expense increasing by INR15 crores.
Lalit Malik
executiveNow turning to the after-tax figures. For the quarter, consolidated profit after tax came in at INR695 crores, versus a PAT of INR369 crores in the same quarter a year ago — that's an increase of INR326 crores, or 88%. That covers the company's financial performance for the quarter. Now let me turn to operational performance. In the distribution business, overall demand improved by roughly 3% year over year. T&D losses for the nine months ended December ’22 at Ahmedabad, Surat, Dahej and Bhiwandi stayed stable, while losses at Agra and SMK dropped notably, largely thanks to our sustained emphasis on loss reduction and recovery efforts. That wraps up the overview of the quarterly financial and operating performance. Moving ahead, I'll provide a quick update on current projects in the pipeline. First, commissioning of 150 megawatt of SECI-V has been pushed back somewhat because of a delay in construction of the EHV line from factors outside our control, and it is now expected to be commissioned by April 2023. The necessary application for extension of SCOD has already been submitted to SECI. Second, the TPLD 300 megawatt solar project has gained some momentum, helped by the recent decline in module prices.
Lalit Malik
executiveAn LOA has been issued for procuring modules. In addition, MNRE has sent out a notification extending the SCOD through March 2024 for every project that was bid before March 2021. That gives us enough time to carry out the project. Next, the 300 megawatt SECI-XII wind project is holding steady as it was. The company won this project in Q1 FY ’23, and the LOA for it has already come in. A PPA should be signed in due course. Next, turning to the distribution segment. The company has submitted an application to obtain a parallel distribution license across various areas of Maharashtra, which include Thane and Palghar, Pune and Nagpur. MSEDCL is the incumbent licensee and will keep being a licensee. After the license is granted, consumers will be able to pick any one licensee for their power supply. That covers this quarter. I would now ask the coordinator to open the lines for the Q&A session.
Operator
operatorWe'll start with Mohit Kumar from DAM Capital, who has the first question. Go ahead.
Mohit Kumar
analystYeah, good evening, and congratulations on that strong set of numbers. First question is about the — could you share how long the contracts run for the LNG we have at present, and how much of it falls in this fiscal? And is any of it also available for the next fiscal?
Saurabh Mashruwala
executiveMohit, this is Saurabh. As we acknowledged last quarter, these LNG prices are elevated. We haven't signed any additional contracts during the past quarter, but broadly speaking, you know, we do have contracts in place — existing agreements with IOC and Reliance Gas — under which roughly 25% of the capacity is contracted for our SUGEN and UNOSUGEN power, right. We've also booked another three cargoes each quarter for the coming four years, and that will cover a further 25%. So all told, for the SUGEN and UNOSUGEN project, 50% of that capacity for the calendar year — the next four calendar years — is contracted.
Mohit Kumar
analystGot it, got it. And second, could you tell us what the EBITDA contribution from those businesses was for the quarter?
Saurabh Mashruwala
executiveYou can jot this down — gas EBITDA for this quarter comes to roughly INR678 crores, compared with INR300 crores a year ago, which works out to a rise of INR378 crores. Within that, as we explained, about INR395 crores is attributable to LNG, and INR397 crores to gas sales, while renewables in the current year stand at INR161 crores against INR114 crores previously, so that's an increase of INR47 crores. The licensed distribution business EBITDA is around INR427 crores versus INR352 crores, an increase of INR75 crores, and that figure includes Daman and Diu as well. The new area, which wasn't in the last quarter, along with franchise distribution across Dahej, Agra, Bhiwandi and SMK, contributed INR255 crores in Q3 of the current year compared with INR206 crores — a faster increase of about INR49 crores. And overall reported PBT EBITDA, I'd say, is INR1,528 crores against INR1,000 crores last year, up by INR528 crores, roughly 53%.
Mohit Kumar
analystGot it, sir. One final question, sir: over the past 2 quarters, what has shifted such that various private companies like ours are attempting to apply for a parallel distribution licensee? Is there some kind of understanding and amendment to the Electricity Act?
Saurabh Mashruwala
executiveNo. We see the opportunity because Maharashtra is a pretty solid region and it's a well-regulated one. The regulation there is really quite strong, I'd say the same as Gujarat. And on demand — if you look at the third of the three areas we've applied for the second license, like Palghar and Thane and Nagpur and Pune — in those areas we find industrial demand is almost 50%. So we see this region as attractive, and the regulatory framework in Maharashtra is well set up, I would say. So we see a good opportunity there to expand our — to build our network there, and gradually, gradually we're trying to — we want to capture the market in these three areas as well. This area — the three areas, if you look at them — some are almost larger — larger than Ahmedabad. And so — and Pune, for instance, Pune we already have City Gas Distribution — we hold a City Gas Distribution license in Pune. So we are — we have a small presence in Pune too, as well as Palghar and Thane, because of Bhiwandi and SMK area we are — it's very close to our area. So where synergies — there is a synergy, I would say, in the case of Palghar and Thane as well as Pune too.
Lalit Malik
executiveWe can also bring in efficiency gains from what we've learned before, and that's going to help the consumer.
Saurabh Mashruwala
executiveSo essentially, there's a two-part tariff, and on top of that there's basically a cost-plus tariff. It isn't structured like a franchisee-style distribution area. And while the T&D losses in the current distribution area aren't comparable to those in our franchise area, they are lower. So the two-part tariff is offered, and the cost-plus tariff is offered as well. That's another advantage we have.
Mohit Kumar
analystGot it, sir. Thanks, and I wish you the best, sir. Thank you.
Saurabh Mashruwala
executiveThanks.
Operator
operatorThank you. <<operator_script>> Our following question comes from Girish Achhipalia, who is with Morgan Stanley. You have the floor.
Girish Achhipalia
analystAppreciate the chance to ask. I’ve just got one question about the renewables acquisition announcement. There had been talk, I believe, of 350 solar and 750 wind. Where do things stand at the moment—is that development moving ahead, not moving ahead, or have you decided to call it off? Could you give us a bit more detail on that?
Saurabh Mashruwala
executiveWhich acquisition are you referring to?
Girish Achhipalia
analystThat ReNew Power project — 1.1 gigawatts, right?
Saurabh Mashruwala
executiveSo essentially, yes — this is the NBO stage. More progress therefore still has to happen, and those efforts are presently at the preliminary stage, the NBO stage as we speak.
Girish Achhipalia
analystAll right, that's fair. Thanks.
Operator
operatorThanks. We'll take our next question from Anshuman Ashit at ICICI Securities. Go right ahead.
Anshuman Ashit
analystThanks, sir, for the chance. Sir, I have a question about the LNG sale—the LNG trading that we've completed. So, sir, the profits we're booking from those LNG sales: are we adjusting them into a regulated business, given that we're purchasing the power from the market? So how is that adjustment being made?
Saurabh Mashruwala
executiveThis is essentially merchant LNG, so it’s essentially not tied to the regulated items, essentially.
Anshuman Ashit
analystRight. So that falls outside our regulated business. But the gas we were sourcing for SUGEN and UNOSUGEN — I'm just trying to get this straight — the contracts we hold are meant for generation serving that regulated business. Yet the sale we're making via trading, that isn't something we book or adjust within our regulated business?
Saurabh Mashruwala
executiveEssentially, what we’re relying on is merchant LNG.
Anshuman Ashit
analystAlright, sir. Alright. We aren’t drawing on the allocated sale, okay. And, sir, that applies moving forward as well. So this run rate of roughly INR400 crores for the quarter, since right now we have about three cargoes booked per quarter and the —
Saurabh Mashruwala
executiveThe cargo figures are for the calendar year—not on a quarterly basis. Each calendar year, so for calendar year ’23.
Anshuman Ashit
analystAll right, so will that run rate keep going at comparable levels when it comes to LNG sales and LNG trading?
Saurabh Mashruwala
executiveIt hinges on what opportunity is out there. As you know, the spot price we collect for LNG ran pretty high over the last 9 months. So we found it better to sell the LNG instead of generating power. And as you're noticing, those LNG prices are coming down. So it all depends on what opportunity is available.
Lalit Malik
executiveThat pattern might not hold going forward. Everything hinges on how things are priced and whether they're available.
Anshuman Ashit
analystSir, at what price point would we choose generation over trading?
Saurabh Mashruwala
executiveIt is a dynamic situation, so it depends on the price at which we are acquiring LNG and what the market price is. We cannot set any threshold on the LNG business. So fundamentally, this is a dynamic situation. We have to look at the opportunity that comes in and then act accordingly.
Anshuman Ashit
analystAll right, thanks, sir. And sir, how has the receivable situation been? So could you give us the figure as of the nine-month mark?
Saurabh Mashruwala
executiveWhat number are you referring to?
Lalit Malik
executiveReceivables.
Anshuman Ashit
analystReceivables.
Saurabh Mashruwala
executiveWhen it comes to the receivables figures, we don't have those available at this moment. So if you'd like, we can provide them to you offline.
Anshuman Ashit
analystAnd, sir, what’s the capex figure for the nine-month period?
Saurabh Mashruwala
executiveThat’s something we can provide.
Lalit Malik
executiveYeah, I believe the capex figure for the year-to-date nine months comes in at roughly INR2,298 crores. That's total capex, yes.
Anshuman Ashit
analystAll right. And sir, regarding the run rate — that figure you mentioned for next year — so for distribution, roughly INR1,200 crores for the license distribution business, and INR300 crores for the distribution franchise business?
Saurabh Mashruwala
executiveYeah, that number checks out.
Anshuman Ashit
analystThanks a lot, sir.
Operator
operatorThanks. <<operator_script>> Our following question comes from Nikhil Abhyankar, who is calling on the DAM Capital line. You have the floor.
Nikhil Abhyankar
analystThanks for the chance to speak, sir, and congratulations on a solid set of numbers. So sir, could you first tell me what our renewable capacity currently is and what capacity is under construction?
Saurabh Mashruwala
executiveWhen it comes to renewable capacity — commissioned capacity, I mean — I'd put that figure at 1,068 megawatts. And, as you — as we mentioned in the call, roughly 715 megawatts of capacity is currently under construction.
Nikhil Abhyankar
analystAll right, and sir, are we making any deliberate push to buy assets instead of building new ones?
Saurabh Mashruwala
executiveYeah, we're pursuing that opportunity, as you remember. Last year — during last year, we made an acquisition of roughly 235 megawatts, something like that, 281 megawatts. So essentially, we keep assessing opportunities when it comes to acquisitions and when it comes to new projects.
Nikhil Abhyankar
analystSo does that mean we won’t be developing any projects on our own?
Saurabh Mashruwala
executiveNo, we are. I mean, we are developing. There’s 715 megawatt of capacity in the construction.
Nikhil Abhyankar
analystAll right, and sir, could you provide the RPO obligation covering every license distribution and license area that we hold?
Saurabh Mashruwala
executiveRegarding RPO obligations — one moment. We’ll get back to you on those RPO obligations.
Nikhil Abhyankar
analystMy apologies. I missed what you said at the end.
Saurabh Mashruwala
executiveWe’ll follow up with you separately to provide that. As we mentioned, we’ll handle it offline.
Nikhil Abhyankar
analystYes, sir. And then on the parallel licensing front. So, sir, now that you've submitted applications for the license in three, four locations. So what are our plans? Will we be building new infrastructure, or will we be using it together with the existing distributor?
Saurabh Mashruwala
executiveNo. Look, the second licensee concept means you’ve got to build new infrastructure, like at Dahej. Dahej is an example where the original license was with the state DISCOM — and it was Dahej SEZ, I’d say. So we’ve put in a new network there at Dahej SEZ. We capture — I mean, all the customers at Dahej SEZ are with us rather than with the state DISCOM. So in a similar way, I mean, we basically have to set up the new network.
Nikhil Abhyankar
analystGot it, sir. And one last question, if you don't mind. If we are granted that — the second parallel license — then what sort of timeline would be needed for covering the whole city area so we can build out our own infrastructure?
Saurabh Mashruwala
executiveThis is something for the long term — I'd say it isn't going to happen. It can't happen over a very short stretch of time, I mean. Setting up the network probably takes five years plus.
Nikhil Abhyankar
analystAlright. Got it, sir. Nothing further from my side.
Operator
operatorThanks. We’ll take the next question from Rahul Modi at Nippon India Asset Management. The line is yours — please go ahead.
Rahul Modi
analystGood evening, sir, and thanks for giving me the chance to speak. Sir, I just want to pick up on what the previous person was discussing. So whenever you're establishing a new license, whenever you're establishing a new network, does that come under the regulatory regime, or is this going to be our capex, and how would risk mitigation work here — obviously, the aim being greater efficiency and, you know, a much improved power supply mechanism. So in what way does the capex — how would it operate within the regulatory regime, if you could explain that?
Saurabh Mashruwala
executiveIt's a regulatory regime like the kind we only have in places such as Ahmedabad — Ahmedabad, Surat, areas of that sort.
Rahul Modi
analystAll right, so that basically means — take the case of a person who already has INR1,000 crores invested, they hold an asset base, and then you create a further INR300 crores. So is the customer billed on that INR1,300 crores?
Saurabh Mashruwala
executiveNo, no. Going by what's in our regulatory filings, that's what we've incurred, since it follows the same process we carry out in the Ahmedabad and Surat area. So we have to file the ARR, and after that the tariff gets set by the regulators.
Lalit Malik
executiveWe’ll take the same approach here as well.
Rahul Modi
analystSir, does the network laying overlap at all? How does that work? I'm just trying to get a clearer picture here, because, you know, you're —
Saurabh Mashruwala
executiveThere's going to be some overlap, since you'll have parallel networking — the state DISCOM network will be present, our network will be present, and in the same way a parallel network will be there.
Rahul Modi
analystAll right. So, sir, take this cost that gets added on — for instance, what reason would the regulator have to permit it? Consider a city such as Pune, which may not be especially inefficient. Why bring in a parallel licensee and pile on the cost, since this isn't happening only in Maharashtra — you're seeing it in Maharashtra, yet it's occurring throughout India? So, just to get a clearer grasp of this idea, will it eventually push tariffs up and, obviously, deliver better service quality? Is that the correct way to look at it?
Saurabh Mashruwala
executiveConsumers will gain from improved service quality and cheaper electricity — those are the advantages they'll see.
Rahul Modi
analystAll right. And sir, since you said there’s an IOCL tie-up covering 25% and a further 25% with RIL, what approximate cost are we looking at with crude at where it stands now?
Saurabh Mashruwala
executiveIt's tied to the IOCL brand and also to Reliance, basically associated with the slope brand. So we won't really give you an update on the slope, but it's essentially tied to the brand.
Rahul Modi
analystUnderstood. So just so I understand where things stand right now, today we're supposed to — we have to use this power, what would the tariff be?
Saurabh Mashruwala
executiveWe aren’t going to make any remarks about that at this point.
Rahul Modi
analystAlright, sure — just one last question from me. Sir, does your target of more than 4,000 megawatts for renewables still stand? And if it does, when do you plan to reach it, whether organically or inorganically?
Saurabh Mashruwala
executiveThus, around 2025 and 2026 is when we arranged things so that this type of capacity could be reached.
Rahul Modi
analystAll right. That comes to 4,500 — or 4,000, if I'm not mistaken?
Saurabh Mashruwala
executiveYeah. Yeah, that's correct.
Rahul Modi
analystAll right, thank you.
Saurabh Mashruwala
executiveThe figure we had in mind for the coming 3 to 5 years was roughly 5,000.
Rahul Modi
analystAll right, thanks.
Operator
operatorThanks. We’ll take the next question from Akhilesh Bhandari at ICICI Prudential AMC. The line is yours — please go ahead.
Akhilesh Bhandari
analystYes, sir, thanks for taking my question. My first question concerns the parallel distribution network. So MSEDCL already has certain PPAs that it uses to supply power in those areas. So how is the allocation of PPAs going to work now? Do you get to pick and choose some of those PPAs, or do you go out and find the best PPAs? How does that work? And how are you also planning for the network?
Saurabh Mashruwala
executiveSo what you're describing is parallel licensing. That means we aren't required to use their PPA. We have to make our own arrangements for procuring power for the distributions. This isn't a form of network sharing. We'll have a separate network. Their PPA will be independent from our power procurement arrangement.
Lalit Malik
executiveYeah, it's sort of like — you've got your telecom channels, right? You could have RIL, you could have Vodafone, you could have this one. So basically, you end up with a parallel infrastructure and —
Saurabh Mashruwala
executiveTheir networks aren't something we're sharing. What we intend to do is build a separate network of our own.
Akhilesh Bhandari
analystI have one question about the whole arrangement in general, since duplicating the network and duplicating PPAs for a single area could make the overall system less efficient, piling on more cost structure when you're operating in a fixed cost environment. So to secure approval, must you demonstrate, say, some benefit — some fixed benefit to the consumer, such as a tariff reduction — in order to obtain that approval, or I mean, on what merits does the regulator base this decision? Just your thoughts on that?
Saurabh Mashruwala
executiveRight, so we've shown that reduced tariffs, fewer T&D losses, and improved services were, in a sense, something concrete that we needed to prove.
Akhilesh Bhandari
analystGot it, understood. Thanks.
Operator
operatorThanks. We’ll take the next question from Bhavin Vithlani at SBI Mutual Fund. The line is yours—please proceed.
Bhavin Vithlani
analystGood evening, sir. I have a few questions. Regarding the INR395 crores EBITDA from the LNG, what did that come to in the same period a year ago? And could you also share the figures for nine months of this fiscal year and the one before, please?
Saurabh Mashruwala
executiveThe nine-month figure comes to roughly INR641 crores.
Bhavin Vithlani
analystYes. Could you give me the same period from the prior year, please?
Saurabh Mashruwala
executiveLast year, that figure came to roughly INR107 crores.
Bhavin Vithlani
analystRight, understood. Second thing — at our franchisee we've noticed a big drop in AT&C losses. Earlier on this call you mentioned a rule of thumb. Has that changed now, I mean for each percentage point of AT&C reduction at the franchisees? How much extra profit actually flows through to EBITDA or PBT?
Saurabh Mashruwala
executiveAt this moment, their assumptions haven’t changed at all. That same assumption can keep going.
Bhavin Vithlani
analystAbsolutely. The third question continues from the previous participant. So in Ahmedabad, our license areas cover roughly 350-odd square kilometers. And cities have expanded many times over as time has passed. Are we also applying for the expanded version of the city, which in theory might be the easiest one to attempt since you're already there?
Saurabh Mashruwala
executiveAt this point, it’s too early to discuss that. That said, yes, the city is growing. We’re expanding. Demand rises by 5%, 6% each year.
Bhavin Vithlani
analystRight. No — the question really had to do with the fact that as the city grows past the boundary of your licensed territory, that area could end up within the state DISCOMs' jurisdiction. In theory, is that also a possibility we could take as something that might come our way?
Saurabh Mashruwala
executiveIt's an opportunity, though for the city — yes, for us it is an opportunity.
Bhavin Vithlani
analystAnd here's my final question. There've been press stories about promoters putting in bids at the NCLT regarding Reliance Capital. Now, looking back, our record has been spotless when it comes to avoiding any related-party dealings. Is it fair to expect that this will carry on in the same way?
Saurabh Mashruwala
executiveAt this moment, we aren’t in a position to comment on Reliance Capital.
Rishi Shah
executiveBhavin, this is Rishi — I believe what you're really asking about is whether there's any connection at all between Torrent Power and Reliance Capital?
Bhavin Vithlani
analystNo. The related party transactions up to now have been quite straightforward. There aren't any loans. The only things related parties get are dividends or remuneration. Should we expect that to keep going, or could this entity be used as well?
Saurabh Mashruwala
executiveSure, sure.
Rishi Shah
executiveSo this deal is being contemplated at the parent level rather than at any operating company level, and that discipline would certainly be upheld going forward as well, which is what we've observed over the last 20 years.
Saurabh Mashruwala
executiveThis deal has nothing to do with Torrent Power. It stands on its own, separate from Torrent Power. There is no connection at all — it isn't tied to it anywhere.
Bhavin Vithlani
analystOkay, so that question was just about Torrent Power and the parties connected to it. That’s really reassuring. Thanks a lot. Those are the things I wanted to ask.
Saurabh Mashruwala
executiveThanks.
Operator
operatorThanks. Our next question comes from Harsh Dole at IIFL. Go ahead.
Harsh Dole
analystHello, and thank you. My question really concerns the same topic of parallel distribution licensing. It is encouraging to hear that we are being fairly aggressive when it comes to new areas. First, have you heard of anyone applying for a license or a parallel license in Ahmedabad and Surat, which are our bread and butter? And if someone does apply, what is going to be <<inaudible>> to make sure the incremental growth is not lost? The second part is basically our timelines. Can we expect the network rollout, and which regulatory approvals are necessary, and at what stage are we? Thanks.
Saurabh Mashruwala
executiveSo, Harsh, take a look at the situation. In areas like Ahmedabad and Surat, we're efficient, right? Our services are superior, our tariffs are competitive, and our T&D losses are lower. So this sort of parallel licensing will be more appealing where the state DISCOMS are operating. For instance, the area we've applied for is one where MSEDCL operates, and it's an inefficient area. So there's no reason for any distributor to enter an efficient area and compete against us, because they won't be able to compete with us given the sheer efficiency of the private sector players. So this type of model will only work where the state DISCOMS are operating and, basically, I'd say they're inefficient. Their tariffs are inefficient, their tariffs are higher, the T&D losses will be higher. So in those kinds of areas, this type of model will work — not in an Ahmedabad-type model, I would say.
Lalit Malik
executiveI mean, in Ahmedabad and Surat, our T&D losses are already the lowest. So for anyone looking at it, there's limited room for further efficiency gains there. On the other hand, working with the government could present an opportunity.
Saurabh Mashruwala
executiveI'd say that makes for a distinguishing factor between the private-sector companies operating today and the public-sector operator, state DISOM.
Harsh Dole
analystGot it — thanks, that's much appreciated. If you could speak to the timeline and which regulatory approvals are required, and tell us what phase we're at?
Saurabh Mashruwala
executiveAs for timing, it's hard to give you a date because the application is already in. So MERC will follow its usual procedure. For instance, they'll ask for comments from the public and they'll — they'll listen to any objections. So all of those public — those standard steps, they'll carry them out. And in line with that, they'll conduct something like a public hearing. And they'll weigh every consideration, the technical capability of the new entrants basically, the financial capability of the new entrants, all these factors, they'll assess them and after that they'll reach their decision.
Harsh Dole
analystThanks for that, and I’d like to fit in just one additional question if that’s alright.
Saurabh Mashruwala
executiveYes, that's correct.
Harsh Dole
analystBroadly speaking, we've observed that capital costs on renewable projects have risen, and interest rates are what they are. So, in your view, do the tariffs on new projects that have been bid out generally carry an adequate margin of safety to meet our capital allocation standard, or is there some rethinking happening in that bidding strategy?
Saurabh Mashruwala
executiveNo. As we’ve said every year, we expect these upcoming projects to load at the IRR level. That assumption still holds. Take the 300-megawatt TPLD project, for instance: the model size rose to around 0.28, so to speak. Now it’s coming down to roughly 0.19. So we’ve contracted it. We’ve committed — we’ve contracted because it’s reaching our IRR range. So for the 300 megawatts, we’ve contracted with the model, and we’re moving forward with implementation. So things are returning to a normal level, I’d say. That’s why we’re exiting these projects.
Harsh Dole
analystAlright, thanks a lot. Appreciate it.
Saurabh Mashruwala
executiveThanks.
Operator
operatorThanks. Our next question comes from Bharani Vijaykumar at Spark Capital. Your line is open, please go ahead.
Bharani Vijaykumar
analystYes, good evening. Sir, in the quarters ahead, what portion of this LNG sale is expected to take place? Will we be in a position to sell that merchant LNG from the 3 cargoes we've secured?
Saurabh Mashruwala
executiveWe won’t be in a position to provide any guidance for future periods on that.
Bharani Vijaykumar
analystSo my question is this: during this specific quarter, are we still carrying that out?
Saurabh Mashruwala
executiveThat’s exactly my point — we won’t be in a position to provide guidance for future periods. It all hinges on which opportunities are open to us at any particular moment.
Bharani Vijaykumar
analystSo at this moment, 50% of the gas is available for generation — is that right, sir?
Saurabh Mashruwala
executiveRegarding this calendar year, yes—50% gas is available for the SUGEN and UNOSUGEN project.
Bharani Vijaykumar
analystAnd those three imported cargoes we’ve booked — they’re available through December 2026, right?
Saurabh Mashruwala
executiveThose three cargoes we booked are mainly aimed at covering our summer needs. So what we're targeting is Q1 of next year.
Lalit Malik
executiveIt’ll be that way annually.
Saurabh Mashruwala
executiveEach year, then, there are 3 cargoes available across the coming 4 years; 3 multiplied by 12 gives 12 cargoes, I'd put it. For this year, though, those 3 cargoes serve to satisfy the summer requirement.
Bharani Vijaykumar
analystI'm not following. So could you state plainly how much gas capacity we actually have covered for FY ’24 and FY ’25?
Saurabh Mashruwala
executiveSo half of the gas, 50%, can be used toward what SUGEN and UNOSUGEN need for the license distribution area.
Bharani Vijaykumar
analystSo that covers IOC Reliance Gas as well as the imported gas?
Saurabh Mashruwala
executiveThat's precisely right.
Bharani Vijaykumar
analystYes. All right. And if we don't turn it into electricity, you're allowed to sell that imported gas?
Saurabh Mashruwala
executiveYes. That opportunity is on the table. It really comes down to the cost of gas compared with the tariff we're securing. So essentially, it hinges on what opportunities are out there.
Bharani Vijaykumar
analystAlright, moving to the next question, which concerns the parallel distribution licensee. To build out that parallel infrastructure — taking Pune as an example — what amount of capex would be needed over the coming five years?
Saurabh Mashruwala
executiveIf I had to put a timeframe on it, I'd say 5 years — you could estimate roughly INR4,000 crores, INR5,000 crores of capex for a city like Pune over the coming 5 years, I'd say.
Bharani Vijaykumar
analystSo regulated equity makes up roughly 30% of that, let's say.
Saurabh Mashruwala
executiveCorrect.
Bharani Vijaykumar
analystAlright, last question here about EBITDA. Could you break out for us the EBITDA figure coming specifically from the new distribution franchisee territories, such as Dadra and Nagar Haveli, on its own?
Saurabh Mashruwala
executiveLook, we won’t be able to provide that. We’ve already supplied the combined figures — so for the combined license, that’s the EBITDA number we put out, and what we’re saying is it will come in at INR75 crores in the current quarter, and you can see the substitution from last month — measured against the same quarter a year earlier.
Bharani Vijaykumar
analystAlright, thank you, sir.
Operator
operatorThanks. <<operator_script>> Our following question comes from Rahul Modi with Nippon India Asset Management, on the line. Go right ahead.
Rahul Modi
analystSir, could you tell me how much in regulatory assets has been approved and how much is still pending approval? And at this point, how are you gaining comfort with the regulator regarding liquidation, I would say?
Lalit Malik
executiveThat comes to INR1,500.
Saurabh Mashruwala
executiveYeah, roughly INR1,500 crores has been given the green light.
Rahul Modi
analystAnd, sir, what about any liquidation targets for this and the unapproved portion?
Saurabh Mashruwala
executiveUnapproved is a contested item, I'd call it. It's something that's in dispute, I would say.
Rahul Modi
analystWhat figure would that come to?
Saurabh Mashruwala
executive600 crore rupees.
Rahul Modi
analystAlright. And sir, have any regulators given any indication? Are there any liquidation plans for this?
Saurabh Mashruwala
executiveWe’re cooperating with the regulator, so our hope is that it gets recovered within the next 2 to 3 years.
Rahul Modi
analystAll right, so, sir, what’s the trend been like? Has it stayed flat? Has it been rising, or has it edged down a bit?
Saurabh Mashruwala
executiveIt's going up — it's rising somewhat.
Rishi Shah
executiveI'd like to build on that, Rahul. If you set aside last year or this year, there had been a downward trend in regulatory assets. So essentially, regulatory assets were declining. This year, however, owing to elevated gas prices and higher overall electricity prices, those regulatory assets have risen. As a result, it's hard for me to say how long it will take us to liquidate these regulatory assets. Still, if you take this year out of the picture, the trend had been a decreasing one.
Rahul Modi
analystAlright. Great. That covers everything on my end. Thanks.
Operator
operatorThank you. <<operator_script>> Since no one else has any questions, I'll now pass things back to management for their closing remarks.
Lalit Malik
executiveThank you. We hope everyone stays safe and well. We appreciate it, and now we'll turn the call back to the operator.
Saurabh Mashruwala
executiveThanks.
Operator
operator<<operator_signoff>>
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Torrent Power Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Torrent Power Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Torrent Power Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.