Torrent Power Limited (TORNTPOWER) Earnings Call Transcript & Summary

November 13, 2024

National Stock Exchange of India IN Utilities Electric Utilities earnings 33 min

Earnings Call Speaker Segments

Saurabh Mashruwala

executive
#1

Thank you very much. Good evening, everyone, and thanks for being on Torrent Power's earnings call for Q2 FY '25. To start, I'll walk you through how we performed in the third quarter, and after that we'll open the phone lines for a Q&A session; we'll begin by explaining the company's performance at the PBT level, and then we'll take you through tax expenses as a separate item. Reported PBT for the quarter came in at INR 689 crores, versus INR 741 crores in the same quarter a year earlier, which works out to a decrease of INR 52 crores, roughly 7% for the reported business. PBT for the current quarter includes a nonrecurring credit of INR 67 crores arising from 2 factors: first, accounting of INR 99 crores upon receipt of a favorable order in the license distribution area, which mainly covers the carrying costs allowed — the carrying cost allowance — partly offset by lower generation from the wind power projects because wind turbines were forcibly stopped due to heavy rains and Asna cyclone witnessed in Gujarat during the quarter, which cut contribution by INR 32 crores. After adjusting for this one-off, PBT for the quarter stood at INR 622 crores, against INR 741 crores in the comparable quarter of last year, a decrease of INR 119 crores, about 16%. On a business-wise basis, the factors behind this performance are as follows: first, contribution from the thermal generation business fell by about INR 80 crores, mainly due to 2 factors. First, lower contribution from sale of merchant power and LNG of INR 35 crores. The country as a whole saw lower electricity demand during the quarter, largely because the monsoon was extended and widespread this quarter, in contrast to erratic monsoons in the comparable quarter of last year. So in a sense, the two quarters are not really comparable. Even with lower overall demand, the company managed to keep merchant volumes at almost the same level. Margins, though, were lower because the extended monsoon kept merchant prices subdued. Second, additional contribution from thermal generation was also hit by higher O&M expenses and lower incentive due to scheduled maintenance during the quarter. Second, a noncash adjustment from foreign exchange variation of INR 24 crores. Contribution from renewable generation, adjusted for the one-off, dropped by INR 29 crores because of lower PLF at existing wind power — wind and solar power plants, due to lower wind speed resources and radiation, respectively. There was also lower contribution from capacity of 274 megawatts commissioned during the quarter, as the project is in its stabilization phase. The operation license as <<inaudible>> business compensated each other, and the segment overall stayed stable in terms of profitability. Demand growth was flat during the quarter at 1% across all our distribution areas. The remaining deviation comes from other income, net finance costs and depreciation. That completes the explanation of financial performance during the quarter. Moving on to the project update. When it comes to renewable energy capacity, 274 megawatts was added during the year, which brings the company's total installed generation capacity to 4.5 gigawatts as of 30th September '24. That breaks down into 2.7 gigawatts from gas, 1.5 gigawatts from renewables, and 362 megawatts from coal-based capacity. In an auction run by MSEDCL during the quarter, the company was awarded pumped storage hydro projects totaling 2 gigawatts. As of the quarter's end, the pipeline includes 3 gigawatts of renewable power projects, 2 gigawatts of pumped storage hydro projects, and 2 transmission projects at Khavda and Solapur. More detail on this pipeline has been summarized in our latest investor presentation, which is available on the website. Turning to new ventures. First, the company's pilot project for green hydrogen blending with CNG in UP should be commissioned shortly. In addition, the company has received an allocation of 18 Ktpa of green hydrogen production under SECI's PLI tender at an average PLI of 28.89 kg. Technical feasibility has been completed, and a detailed business plan is being prepared. On the pumped storage hydro side, we have identified project sites with a potential of 8.4 gigawatts of pumped storage hydro in the states of Maharashtra and UP. The pre-feasibility study is complete, and MOU terms of reference have been granted for the full 8.4 gigawatts of capacity. An agency has also been appointed for the EIS study, as in <<inaudible>> years. We have received an LOA to provide pumped storage facilities to MSEDCL for an aggregate capacity of 2.2 gigawatts. That covers the quarter. I would now ask the coordinator to open the line for the Q&A session. We wish everyone to stay safe and healthy. Thank you very much. Back to the operator.

Mahesh Patil

analyst
#2

My first question concerns employee cost and other expenses in Q2. Compared with Q2 of last year, there appears to be a fairly significant rise. Employee costs have climbed 18%, and other expenses are up roughly 14%. Is there a particular reason for this, or any one-off items involved?

Saurabh Mashruwala

executive
#3

To begin with, there isn't any single item; the increases are normal, while the rise in O&M expenses tied to higher merchant sales is accounted for. There is the usual increase in staff cost. And the ForEx loss, a noncash item, was also booked by us under other expenses.

Mahesh Patil

analyst
#4

The foreign exchange item is approximately INR 24 crores that you mentioned, is that right?

Saurabh Mashruwala

executive
#5

Pardon?

Mahesh Patil

analyst
#6

The forex loss you referred to is 24 crore rupees, is that right?

Saurabh Mashruwala

executive
#7

Yes, 24 crore rupees. Actually, looking at the euro, it stood at roughly 90 rupees on 30 June, climbed to 94 rupees by 30 September, and has since dropped back to 91 rupees as of today. So with luck that will reverse. It is a noncash item in Q3.

Mahesh Patil

analyst
#8

All right — and sir, my second question concerns our Bhiwandi franchise area, where the agreement expires in Jan '27. And since we're nearly into 2025 now, are there any plans, and does the agreement contain related provisions, for a further extension?

Saurabh Mashruwala

executive
#9

So the provision — the Bhiwandi franchisee agreement — when we last renewed it in 2017, there's a provision that by mutual concern it can be extended for another 5 years; so when the time arrives in '27, we'll discuss the extension with MSEDCL again. But the agreement does provide an extension period of — a further period of 5 years, with mutual discussions.

Mahesh Patil

analyst
#10

So this is going to be discussed, something in FY...

Saurabh Mashruwala

executive
#11

When the time is right, we'll bring it up with MSEDCL.

Amit Bhinde

analyst
#12

I'd like to pin down the precise figure for merchant EBITDA in the base quarter, since as far as I recall, in Q2 FY '24 we had only about INR 25 crores of merchant EBITDA if I'm not mistaken; and the notes to accounts showed roughly INR 150 crores of revenue on that, which you disclosed previously. So if I take the difference as INR 35 crores, that would suggest negative INR 10 crores of merchant EBITDA. I doubt that's the situation, correct? We wouldn't be selling anything at a loss. So it would help if you could give us the exact figures.

Saurabh Mashruwala

executive
#13

In the last quarter, merchant EBITDA came in at roughly — merchant profit, I should say. It was around — near INR 40 crores, INR 42 crores; and at present, given the INR 35 crores reduction, that's about INR 7 crores for the current quarter.

Amit Bhinde

analyst
#14

For INR 7 crores, it's roughly like that. So we had — speaking in unit terms, DGEN produced about 180 units — million units. And beyond that, there were some minor sales you'd get from SUGEN, and so on. So would units come to roughly 200 MU?

Saurabh Mashruwala

executive
#15

300 MUs.

Amit Bhinde

analyst
#16

So 300 MUs were sold by you, and profits came to INR 7 crores.

Saurabh Mashruwala

executive
#17

Because of the monsoon season, the market stayed subdued. Monsoon always leaves its mark on Q2; and this quarter the monsoon has been extremely widespread and extremely heavy, whereas last year it was a very erratic monsoon, not one that was widespread. So demand in the last quarter, or the middle quarter, was very strong compared with demand in the current quarter. That has therefore affected merchant sales as well as our wind and solar PLF this quarter.

Amit Bhinde

analyst
#18

So when I consider roughly 300 million units sold and merchant EBITDA of INR 7 crores, we're earning only about 0.2 EBITDA per kilowatt — that's quite low, I mean...

Saurabh Mashruwala

executive
#19

Looking at the exchange price as well, it came in lower compared to — so even against the comparable period, it was somewhat higher than last year; therefore the monsoon affected this quarter both in merchant volumes and in wind and solar PLF.

Executive

executive
#20

So Amit, if we go back to Q2 of last year, the monsoons were erratic and not widespread, whereas in this quarter of the current year they were very widespread and very good, and because of that demand has been impacted. So even with that kind of demand, we were able to show that we can sell 300 MUs of merchant in this quarter at lower profitability.

Amit Bhinde

analyst
#21

Anyway, I believe — at this point there's just one more figure I'd like to get clear on. Previously, back when Brent was sitting at about $85, we would typically state that our effective cost would come in at roughly INR 6.5 or thereabouts for gas cost. So with Brent having dropped so sharply now, where does our gas cost per unit actually stand?

Executive

executive
#22

You're taking $75 as the Brent figure. And approximately, that comes to $75 and roughly INR 4.50 — Amit, I think, so — I believe our long-term contracts are tied to Brent, so a 3-month dated Brent. For spot cargoes, though, they're usually a kind of fixed rate pricing. So I can't quite get a clear picture of what your question is. You can't compare Brent directly against the merchant cost of fuel. Long-term contracts are tied to Brent. For merchants, however, we usually book spot cargoes. And after that we tend to convert those into fixed rates as well. So in effect, we'll need to look at it on an MMBtu basis.

Amit Bhinde

analyst
#23

Right, okay, understood. I was simply attempting to compare that against the slope, since Brent was coming down, and so I figured we'd likely see reduced gas costs and probably lower pricing as well, to...

Saurabh Mashruwala

executive
#24

You're correct about that. That falls under our long-term contracts, which generally apply to the PPA we hold.

Sumit Kishore

analyst
#25

Only 1 question. Regarding your overall contracted capacity of 2,149 megawatts — would it be accurate to say that PPAs are in place for all of it, apart from the REMCL 100 megawatts?

Saurabh Mashruwala

executive
#26

So you mean renewable capacity when you say renewables?

Sumit Kishore

analyst
#27

Yeah, yeah. The 2,149 megawatts that are contracted, not counting the — I believe with REMCL it looks like PPAs have been signed across the board, correct?

Saurabh Mashruwala

executive
#28

On the renewable side, roughly 1.5 gigawatts of operational capacity is fully tied up. Around 3 gigawatts is under construction. Of that 3 gigawatts, roughly 200 megawatts remains untied, largely because of the merchant piece. The remainder is tied up, with PPAs signed or LOIs received.

Sumit Kishore

analyst
#29

All right, so my reference was to Slide 15, where contracted capacity stands at 2,149 megawatts. Of that total, REMCL alone indicates an SCOD of 24 months from the PPA.

Rishi Shah

executive
#30

Sumit, I believe that's correct. For REMCL, the PPA remains pending. And as Saurabh clarified regarding airpower, because this is merchant capacity that we're setting up, no PPA exists. Beyond that, we have already signed PPAs for every other contract. And REMCL ought to get — should be, let's say, within 2 months or so.

Saurabh Mashruwala

executive
#31

In a month or 2 months, it will be signed.

Anuj Upadhyay

analyst
#32

I just wanted to hear your thoughts about Section 11 being brought back. It's been extended for thermal, though not for the gas base station. So I'd like to know how you see this. And it would be helpful, sir, if you could say a bit more about the PSP tie-up you recently did with Maharashtra.

Saurabh Mashruwala

executive
#33

On Section 11, it's up — during the summer, it was imposed for the first time because of <<inaudible>>, correct? So there are prices we haven't got renewed either. So we'll have to wait and see how next summer turns out; but — and regarding the ESP capacity of 2 gigawatt, we have a 40 years contract and roughly INR 8,500,000 per megawatt — INR 8,500,000 per megawatt per annum is the fixed cost rate. And power will be supplied by the MSEDCL, so power is not something we need to worry about. And it's a 5-year — a total of 5 years of continuous supply, and 3 gigawatt is optional; we will schedule it; and it will be a cycle of about 25% in the cycle of the envisage is stipulated basically, meaning a maximum cycle of 25%. That is what the contract is, and there will be 2 gigawatt of contracts. We have signed for 40 years.

Rishi Shah

executive
#34

And Anuj, to build on what Saurabh mentioned regarding your earlier question about Section 11 not being extended to gas-based power plants: generally speaking, when I look at gas-based power plants across the country, aside from ours, many of them are a bit more expensive than coal-based plants. So on a FIFO basis, typically, if demand is higher, then Section 11 would generally be available to the gas-based power plant; but when demand is lower, I think the first call would be for the coal-based power plant to run under Section 11. And if it goes beyond a certain level of demand, then it would typically fall to the gas-based power plant, since the assessment would be made on the whole rather than on 1 particular plant. So all the other gas-based power plants are somewhat costlier compared with coal.

Anuj Upadhyay

analyst
#35

Right, understood, Rishi. So is it reasonable to think that since Section 11 can mainly only be applied during the peak period, let's say the 4 months of summer, and then perhaps it might be stretched, say, into September, October, and possibly the following year too, DGEN at most could run at a PLF of roughly 35% to 45% in the best case, I'm saying, or is even that a bit on the high side?

Rishi Shah

executive
#36

Anuj, I think it's very hard to give you specific numbers, because we too would just be making an estimate; but what I can say is that if you look at our Q2 numbers, DGEN has posted a higher PLF than in Q2 of last year. Our merchant volumes are also greater than last year, even though prices were lower. So whether or not Section 11 is imposed, I think we are able to run our plants without Section 11; as far as profitability goes, I think it depends on what prices are available in the market. And even at such subdued prices, which we saw in Q2, we have managed to make profits. Now those profits may not be significant compared with what we saw in Q1; but typically, running plants in Q2, when demand is pretty low, that also is, I think, a positive sign. I think that's what I can tell you; as for percentage CLF, it's very difficult to give you any guidance on that.

Sumit Kishore

analyst
#37

I just wanted to ask one more follow-up. Against the expected project cost for the renewable portfolio of INR 19,316 crores, what total CapEx have you incurred up to now; and yes, that is my first question.

Rishi Shah

executive
#38

So, Sumit, we don't have those figures for what we've spent against INR 19,000 crores. As a rough ballpark figure, I think we would have spent about INR 1,500 crores — but I can give you the exact figures off-line. Right now, we don't have that available.

Saurabh Mashruwala

executive
#39

Cumulative number, we don't have right now.

Sumit Kishore

analyst
#40

All right, so how much total CapEx have you incurred at a consolidated level in the first half of the year — that 15 billion is only for RE.

Rishi Shah

executive
#41

Pardon me, are you referring to the consolidated H1 CapEx that we've spent?

Sumit Kishore

analyst
#42

Right. So the RE CapEx you've incurred so far for the under-construction project comes to INR 15 billion. And what would the total H1 consolidated CapEx be, if you have that figure?

Rishi Shah

executive
#43

Sure, I can give you that. For renewables during H1, we've spent roughly INR 650 crores on the renewables side. Taking license and franchise together, the amount spent is around INR 700 crores. Then there's some INR 40 crores — INR 30 crores, INR 40 crores remaining on the other CapEx side. So looking at the overall CapEx figure, it's about INR 1,400 crores that we've spent in H1.

Sumit Kishore

analyst
#44

All right. All right. There's just one thing I wanted to get clarified: when I look at capital work in progress in the BSE filing, as of 30th September 2024, it stands at INR 2,143 crores. And as of March 2024, it was INR 2,472 crores. It looks like CWIP has declined over the first 6 months. So I wouldn't have expected that it should have gone up.

Rishi Shah

executive
#45

No. I think, Sumit, that's because we've also commissioned somewhere around 270 to 247 megawatts of capacity for our TPL-D 300 megawatts project. That accounts for part of it, and part of it is also because our license distribution would continue capitalizing on commissioning certain projects.

Sumit Kishore

analyst
#46

Yes, that's very clear.

Saurabh Mashruwala

executive
#47

That's solely due to the capitalization.

Mahesh Patil

analyst
#48

My question concerns the other income for the quarter, which appears to have risen to roughly INR 125 crores on a consolidated basis. So is there any colour you can give on this? What has driven the increase in other income?

Saurabh Mashruwala

executive
#49

Just a normal increase. It isn't — I'd put it this way: INR 125 crores is a normal increase.

Mahesh Patil

analyst
#50

No, thank you.

Sagar Gandhi

analyst
#51

I have a question about the renewable portfolio. We're planning to grow it to 4.3 gigawatts over the next 3 to 4 years, so could you point out or give us a broad view of any challenges you encountered when evacuating that upcoming capacity?

Saurabh Mashruwala

executive
#52

If you look at the renewable portfolio, the main challenges are synergies around land acquisitions and evacuations; but where our portfolios are concerned, roughly 80% of the land is in possession and all core connectivity approvals are in place — because those are the things — we work on those first, and then we take part in the project. So that's where things stand as far as we are concerned.

Sagar Gandhi

analyst
#53

So with the 3 gigawatt of renewable capacity we have under construction — I mean, it's in the pipeline — are you saying that every bit of it already has transmission access, or that the transmission access will be in place by the time this portfolio is ready?

Rishi Shah

executive
#54

Well, Sagar, what we do is we keep acquiring land. If you look at the last 2 years, the 3 gigawatt we're looking at was effectively built over the last 9 months; but even before that — despite the fact we weren't winning some bids, we continued acquiring land, which gave good PLF for solar or wind. Alongside that, we also kept applying for connectivity approvals. So effectively, for this 3 gigawatt that's under construction, what has happened is we have around 80% of the land already available. As far as evacuation goes, Stage 1 connectivity approvals exist for all the projects we have — and we also keep looking at additional land parcels and connectivity approvals so that, as and when we keep getting new projects, we'll be able to use those connectivity and land parcels that are there or that we've acquired over a period of time; so effectively, we've identified these 2 as a major — potentially major — roadblocks for a renewable project, and we try to mitigate those risks by keeping that land and evacuation ready without any project in hand; so as and when a new project comes in, we're ready with it.

Sagar Gandhi

analyst
#55

Also, sir, my second question concerns the green hydrogen area. So although a lot of companies are working out how to manufacture electrolyzers, what have we done in that segment? And what's our overall roadmap there?

Rishi Shah

executive
#56

You mean green hydrogen, correct? So basically, under the PLI scheme we've secured 18 KTPA of green hydrogen. At present, we're attempting to identify a commercial endpoint regarding the price at which we could sell just now and what costs we'd incur to produce, so until we can obtain a clear answer on that, no capital has been committed by us for it. As and when — so we're working on it, and as and when we get a clear answer on both those points, I think we will commit the capital. But giving you any perspective on that at this moment is difficult.

Sagar Gandhi

analyst
#57

Sure. Sir, is there any partnership you've entered into on the electrolyzer side that you'd like to highlight?

Rishi Shah

executive
#58

Electrolyzers?

Sagar Gandhi

analyst
#59

Yeah, right. Since that's a step that comes before making green hydrogen. What kind of capability do we have? Or are we partnering with some global companies to build that capability?

Rishi Shah

executive
#60

No, that's right. So I think that would be a second stage. Whenever we decide to put that capital into green hydrogen, we'll then be looking at electrolyzers, securing electrolyzers and renewable capacity. But like I said, we're still working on the end use and on what's an economically viable end use and the selling price. So once we have a clear view on that, until then, we won't be placing any orders as of now.

Mohit Kumar

analyst
#61

I came in a bit late, so I might be asking the same thing again. My question concerns the pumped storage hydropower plant. So where do things stand on placing the orders, and what timelines are you looking at? What kind of after cost do you expect?

Saurabh Mashruwala

executive
#62

On pumped storage, the feasibility study is done. We have received the TOR from the MOEF, and an agency has been appointed for the EIA study. A Letter of Award for 2 gigawatt capacity has also come from MSEDCL — the cost will be roughly about INR 4.5 crores to INR 5 crores per megawatt. That is our current estimate.

Mohit Kumar

analyst
#63

We surely have pinpointed the site, correct? So what timeline are you considering? I believe the—I believe the PPA gives you 48 months, is that right, to commission?

Saurabh Mashruwala

executive
#64

Yes, 48 months for the commissioning period <<inaudible>> PPA.

Mohit Kumar

analyst
#65

So has the PPA been signed at this point? Or does it still need to be executed?

Saurabh Mashruwala

executive
#66

Apologies. We can't hear you clearly.

Mohit Kumar

analyst
#67

Has the PPA been signed yet, or does it still need to be executed?

Saurabh Mashruwala

executive
#68

No, I believe it will be signed at some point.

Saurabh Mashruwala

executive
#69

I really appreciate everyone taking the time to be on Torrent Power's earnings call. Many thanks to all of you. I hope each of you stays safe and well. Thank you very much.

Operator

operator
#70

Thank you. That brings this conference to a close on behalf of Torrent Power Limited. We appreciate your participation, and you can disconnect your lines at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Torrent Power Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Torrent Power Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Torrent Power Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.