Torrent Power Limited (TORNTPOWER) Earnings Call Transcript & Summary
May 14, 2025
Earnings Call Speaker Segments
Operator
operatorThank you, and hello everyone. Good day, and welcome to the Q4 FY ’25 earnings call for Torrent Power Limited. Just a reminder that every participant line will be in listen-only mode, and after the presentation wraps up, you’ll have a chance to ask questions. If you need help during the conference call, please signal an operator by pressing star then zero on your touchtone phone. Please be aware that this conference is being recorded. I’ll now hand the conference over to Mr Saurab, Executive Director and Chief Financial Officer. Thank you, and over to you, sir.
Saurabh Mashruwala
executiveI really appreciate it. Thank you very much. Good day, and good evening to everyone, and thanks for being on Torrent Power's earnings call for Q4 FY ’25. To start, I'll walk you through how the quarter went, and after that we'll open the phone lines for the Q&A session.
Operator
operatorLadies and gentlemen, please remain on the line while we bring the management line back up. Ladies and gentlemen, the management line is now reconnected, so you may go ahead. Thank you.
Saurabh Mashruwala
executiveGood evening, everyone, and thanks for being on Torrent Tower's Q4 FY ’25 earnings call. To start, I'll walk you through how the quarter went, and after that we'll open the phone lines for the Q&A session. I'll begin by explaining the company's performance at PBT Wealth, and then we'll cover the tax expenses separately. Imports for the quarter came in at INR619 crores, versus INR617 crores in the same quarter a year earlier — that's up INR2 crores on a reported basis. As we shared last quarter, the 420 megawatt TPL solar project was commissioned during the prior quarter. That means the plant is currently in its stabilization phase and couldn't contribute optimally to the bottom line. As a result, consolidated PBD has taken a negative hit. So if you consider the plant running on a PDC basis, PBD for the quarter would have come in roughly INR35 crores higher. With that adjustment, adjusted PBD for the quarter was INR654 crores, compared with INR617 crores in the comparable quarter last year — an increase of INR37 crores. That works out to roughly 6% growth, and the business sectors driving this performance are as follows.
Saurabh Mashruwala
executiveTo start, the distribution business contribution rose by INR112 crores, largely driven by higher volumes plus an increase in ROE from capex capitalization, solar incentives, other ovarian incentives, and through a power. Across all our distribution areas, demand growth for the quarter came in at roughly 4%. These positives in distribution were partly offset by the following factors. First, merchant power and LNG sales contributed INR488 crores less. LNG prices stayed elevated through the quarter, trading in a $12 to $17 range. Merchant sales over the same period stayed weak because of high fuel prices and softer demand growth in the quarter. Third, more recently gas prices have begun — begun to show downward movement; with competitive gas prices combined with NVB and tenders and improved demand prospects, we believe the situation should be — should have gotten better going forward. We received the LOE from NVBN for the Digen project for 1150 megawatt, which sits in a 150 megawatt plant. So the operational PDF for the NVNVN tender runs from 16 March to 15th October, and the broad specification for the tender is unchanged from last year's tenders. HGS was a one-off, as explained; profitability for solar generation improved in the quarter by INR43 crores, partly offset by lower PLA for wind projects due to weather conditions, which had a negative impact of about INR30 crores.
Saurabh Mashruwala
executiveTherefore, the renewable segment delivered a net positive impact of INR13 crores. Turning to tax expenses, as mentioned earlier—and this wasn't part of the published accounts—tax expenses went down, largely because the liability reversal was a one-time, non-cash item. That wraps up the explanation of financial performance for the quarter. Now for the project update: during the quarter, 84 megawatts of the 60-megawatt MSC project was commissioned. As of 31st March ’25, the company's total installed generation capacity came to 4.8 gigawatts, made up of 2.7 gigawatts of gas capacity, 1.7 gigawatts of renewable capacity, and roughly 62 megawatts of coal-based capacity. At quarter-end, the pipeline included 3.1 gigawatts of renewable capacity, 3 pump capacities, and two transmission projects at the solar pour. More detail on our transmission pipeline projects is summarized in our latest presentation—the investor presentation, available on our website. Now I'd like to walk you through some key highlights from the year, covering the financials along with operating and strategic points. First, during the year the company carried out an equity raise of INR3,500 crores via QIP—the first such move in three decades by the Torrent Group.
Saurabh Mashruwala
executiveWhen it comes to power projects, we can provide power in the merchant market, including NVV, and for the first time at a section 11 gas-based power plant by the government contributed — which added substantially to the bottom line. Our distribution business kept setting fresh operational benchmarks, with distribution loss of 2.34% in the licensed distribution business. That is one of the lowest anywhere in the country — comparable to the global benchmark. In our franchisee business area, it reached its historical low AT&C losses of 6.94%, compared to 58.7% when it was taken over in 2010. On the strategic front, the company made meaningful headway in building on its strategic initiative by signing a first-of-its-kind India energy storage facility agreement to supply 2,000 megawatt storage hydroposite for 40 years. With net debt to EBITDA and net debt to equity of 0.40 and net debt to EBITDA of 1.41 times, the company holds a strong balance sheet position, with one of the best financial ratios among private sector players in the power sector, and is well positioned for the next phase of growth. That is all for today. I would now ask the coordinator to open the line for the Q&A session. We want everyone to stay safe and healthy. Thank you very much.
Saurabh Mashruwala
executiveOperating — I'll pass it over to the operators.
Operator
operatorThanks a lot. We're moving into the Q&A portion now. If you'd like to ask something, just hit RN1 on your touchstone phone. To drop out of the queue, press R&2. We ask that participants use answers when posing a question. Ladies and gentlemen, we'll pause briefly while the queue is put together — our first question comes from Mohit Kumar at ICICI Securities. Please go ahead.
Mohit Kumar
analystThanks for the chance to ask. Sir, my first question concerns capex — what figure did it reach in FY ’25, and how much has been budgeted for FY ’26? Could you also break that down by business?
Saurabh Mashruwala
executiveRegarding capital expenditure for license distribution, it came to roughly INR1,300 crores across the full year. Franchisees accounted for around INR275 crores, Transmission roughly INR250 crores, and overall capex stands at approximately INR1,98 crores — that is, excluding renewable capex, I'd put it at about INR2,500 crores. On the breakup, you're just asking about the capex breakup for FY ’26, and for capex in FY ’26 we laid it out: distribution capex of INR2,000 crores, INR75 crore for the license distribution business, and roughly INR250 crores for the distribution business. And I believe we've provided the investor PPD.
Mohit Kumar
analystGot it, sir. On the PPT, you mentioned the megawatt figures and the commissioning date, correct?
Saurabh Mashruwala
executiveI’m sorry—could you repeat that? I can’t hear you well because the volume is too low.
Mohit Kumar
analystOh, sorry — let me speak up. All right, so on to the next question, sir. I'll open the floor now. My second question concerns the contract that was signed in March. Is that a take-or-pay arrangement, and what minimum guaranteed volume did you agree to?
Saurabh Mashruwala
executiveThe guaranteed volume is pretty much consistent with what we've achieved over the past year. So the specs stay more or less unchanged as far as methodology goes.
Mohit Kumar
analystRight, got it. On the 1.2 gigawatt published oil project signed with Maharashtra — what's the latest there? Has the financial close been completed? Any detail you can share on that?
Saurabh Mashruwala
executiveIt's a 2 gigawatt project, not 1.2 gigawatts. And look, this is a project spanning four, five years. So right now we're working through the various statutory approvals, and also moving into the DPR. Land acquisitions are underway as well — that's where things stand at the moment with the approvals we need to obtain. So that process is continuing. The land acquisition work is continuing too.
Mohit Kumar
analystGot it, sir. Thanks, and best of luck to you, sir.
Saurabh Mashruwala
executiveI appreciate that.
Operator
operatorThanks, and now we'll take a question from Sumit Kishore at Axis Capital. Please go ahead.
Sumit Kishore
analystGood evening, sir. My first question follows up on that.
Operator
operatorPardon the interruption, sir. Before you proceed with your question, could I ask that you pick up your handset, please? Your audio is a bit — there's an echo on the line, sir.
Sumit Kishore
analystIs it better at this point?
Operator
operatorYes, sir, please go ahead.
Saurabh Mashruwala
executiveRight.
Sumit Kishore
analystAll right, so regarding Mohit, the first question. There's a capex figure for renewables of roughly INR206 million as the anticipated project cost. I'd like to know whether that's the remaining balance or what the CWIP already sitting there for renewables is. How much capex is left to spend on these projects? And roughly phasing it across FY ’25, ’26, ’27, will it lean more heavily toward FY ’26, since the commissioning timelines fall more in calendar 2026 and 2027?
Saurabh Mashruwala
executiveYes, that's correct. The capex we've outlined in the investor presentation is the total capex, and whatever we've completed so far is reflected in CWIP. So there's still balanced capex left—a meaningful portion still to go in terms of outflow. You're right to say that '26 would be a bigger number, since a lot of commissioning is happening in '26 and '27. So '26 could be a bigger number. On renewable capex, '27 would be lower—it should come in below that, depending on how we move forward with commissioning these projects. So as far as that goes, '26 will stay the heavy capex year.
Sumit Kishore
analystYes. And sir, if you could give us the CWIP figure for renewables specifically, that would just help us understand better what you might say, so sure.
Saurabh Mashruwala
executiveI'd put it at roughly INR2,500 crores — about INR2,500 crores of capex for renewables through March ’25, 25 — and we're going to spend a significant amount of capex in the current year, FY ’26.
Sumit Kishore
analystUnderstood. So far, you've incurred a little over INR206, which works out to roughly INR25 billion.
Saurabh Mashruwala
executiveThat's precisely right.
Sumit Kishore
analystGiven that power demand was a bit soft—fairly depressed in April—and then declined in May over the first 13, 14 days, what has the experience been so far? So how is your NBBM opportunity shaping up to this point? Is there acceptance?
Saurabh Mashruwala
executiveI realize there's a pass-through mechanism for variable costs, but with power priced so high overall, who is actually purchasing it — what has your offtake experience been? The contract duration has been extended, so the cutoff moved from June to October. In the prior year, it ran past June, into October. So at this point June is — May has already begun, as if summer had in fact started. Honestly, rain and other factors have been having an impact, I'd say. So with luck, the rain is now behind us. With luck, things will begin — begin to pick up. Summer will begin to pick up, and demand will begin growing and improving. So is it fair to roughly estimate that April and the portion of May seen so far would not have shown much offtake of this costly power?
Sumit Kishore
analystWould you say that conclusion is directionally correct?
Saurabh Mashruwala
executiveYeah, yes, it is happening. It's occurring during the peak period.
Sumit Kishore
analystRight, right. So in the second quarter, the benefit would be direct — that's clear — since last year this arrangement ran only through June.
Saurabh Mashruwala
executiveYeah, that's correct.
Sumit Kishore
analystYeah.
Saurabh Mashruwala
executiveYes, so as of now, we're looking at October—October 15, I'd say.
Sumit Kishore
analystRegarding that final question about UP privatization, what we're picking up is that the state is going to be split into 5 circles for the 2 areas being privatized. So is there any restriction on the number of circles a single private player is allowed to take?
Saurabh Mashruwala
executiveI believe they’re referring to five or six circles. Yeah. And the — it’s under the — it’s a documents being prepared at this moment. So perhaps they will ask every private sector player to take part in the tender. So additional details will be, they are putting together the additional details since they are holding — they are meeting — a meeting is taking place with the Ministry of Power also getting involved in the tender tendering process.
Sumit Kishore
analystUnderstood. Yet it’s impossible for the hit ratio to be greater for more than a couple of players — even 5, 60.
Saurabh Mashruwala
executiveThey'll attempt to assign it among each of the participants, and since ultimately the management benefit is needed to handle all six circles as one. So it's better for them too, and we'll try to spread it across the private players. And this is going to be a regulated cost-plus ROE model, just like Anal parts.
Mohit Kumar
analystDefinitely, that’s extremely appealing. All right, and then last of all, regarding pumped storage hydro, has there been any movement on the 2 gigawatt for that? I mean, this is — but is there any progress you’d want to call out?
Saurabh Mashruwala
executiveRegarding the progress, I mentioned earlier to Mohit that it's currently going through a range of regulatory approval processes. The planned acquisition process is underway right now. So the first thing is — the first thing is to secure the various approvals and reach a landing position, and after that, construction activity and ordering will begin.
Sumit Kishore
analystAlright. Thanks a lot. My best to everyone.
Saurabh Mashruwala
executiveThanks.
Operator
operatorThanks. Just a quick note for everyone on the line: you can hit star and one whenever you'd like to pose a question. Our next question is from Satriev Jain at Ambit Capital. Go ahead, please.
Satyadeep Jain
analystHi, thanks. First, one more point of clarification on the pumped storage project. The energy storage facility agreement was signed recently, according to the release. If I have it right, that agreement required the capacity to be commissioned within 48 months of signing. So, given that you're still in the land acquisition process and construction, it doesn't appear it will be commissioned within 48 months. I just wanted to understand: is that commissioning term that was set out initially flexible?
Saurabh Mashruwala
executiveIt's too soon for us to say anything about the timeline. So we're working — we know we're aware of the timeline. So we're working on the project right now across a various commissioning timeline. So is it fair to say the capex outlay on this won't start in the next two years?
Analyst
analystNo, sir.
Saurabh Mashruwala
executiveA land acquisition is going to take place—it will happen. So we begin committing the capex, since the PPA is in place, which means capex commitments will start from this current year itself.
Satyadeep Jain
analystAlright. Second, regarding the tender, I just wanted a bit of clarification. I know earlier questions were also asked about the sign. The tender specifies 111 crunch days, and there is a minimum contract—a minimum guaranteed offtake based on those crunch days. So I'm guessing it started around two months ago. That means there would have been some crunch days during the last two months. How has your offtake been on the specified crunch days that were mentioned? Because if it—since the 111 crunch days will be spread out over the six months, if I understand correctly.
Saurabh Mashruwala
executiveYes, it's spread over six months. We're discussing the minimum offtake. It could be greater as well, but how did it go in the—so how many crunch days have there been so far during the last two months out of 111? It's hard to say anything about the current quarter where crunch days are concerned and all of that. Still, if you look at April and May—April, we observed some improvement in demand; in May, I think on account of weather conditions, it has fallen again as far as demand is concerned—where overall demand goes. But if you actually examine the exchange data, there are stretches when prices are reaching INR10, which signals that demand exists—greater demand alongside reduced supply. So there has been offtake under the tender intermittently, but giving you precise figures for the current quarter as such would be difficult. I'm trying to understand—if I work through the math, the tender calls for 2,900 MU across the whole tender, and since you took part with the capacity, it appears you have a minimum guaranteed offtake of 2,300 MU through October, but that will depend on crunch days each month.
Analyst
analystI just want to get a handle on this — demand has been fairly soft. As for the NBV, the tender, under the tender NBVN, would be required to take a minimum offtake on each crunch day, and they can't make up for it afterward. So I just wanted to ask: is that how it works, and does that basically mean that on every designated crunch day they're taking that minimum guaranteed offtake? That's what I'm trying to understand.
Saurabh Mashruwala
executiveNow, when you consider the demand picture, there was demand in the last one-week, but apart from that — well, the demand during the last one-week was weak. So there's also a bit of variability or some flexibility that's available to NVV and to the generators as well. So it isn't set in stone that on a given day you must pick up this much and on another day you must pick up that much. Under the tender there is some flexibility, and people will make use of it. But there's a minimum guaranteed offtake of 2,300 MU — if they don't take it up in a particular month or quarter, then they have to make it up later. So is that the understanding? This applies to the six months period — the minimum guaranteed; if they don't do it, then typically they have to pay the fixed charges for 20 — for whatever amount they have contracted for. It's basically a commitment for the Six-Month: if they don't offtake, if they don't pick up 2,300 MU, then they have to pay you a fixed charge, which is mentioned in the standard.
Analyst
analystRegarding whatever quantity they don't take up, that's absolute. And on the total return, I just want to get a sense of how it compares — I know the pricing looks a bit lower than NVV and the tender last year. How does it — I mean, if you're looking at profitability per unit, does it — how does that compare with Section 11 that you had, or perhaps the last tender, NVV and the tender for last year?
Saurabh Mashruwala
executiveI'd say on profitability, if you look at this year as well, it should be more or less in line with what we saw last year under NVV and tender. Section 11 probably isn't a great comparison for NVV and NVV and tender. So the right comparison, really, is against last year's NVV and tender.
Analyst
analystIsn't the pricing a bit lower than what NVD tendered last year, when it said per-unit profitability would be similar for you compared with last year's NV in tender?
Saurabh Mashruwala
executiveSo there would be a slight impact, though not really a major one, since you also pick up other gains in terms of your opportun — or your cost of buying gas could be lower compared with what you're being paid for. So you make some money out of that as well, and then there are operating expenses. So putting it all together, I think profitability from NVV in the current year and the tender should be more or less similar to what we saw last year, with a slight downward bias.
Satyadeep Jain
analystAll right. On this specific gas matter, since you had Section 11 last year, your minimum guaranteed offtake period is longer. And, well, demand has been up and down, but the offtaker is present and purchasing power at these elevated prices. Broadly speaking, are you picking up any interest in a medium-term PPA, given that — I mean, the buyer is already paying these high gas prices — is there any interest whatsoever from any parties in a medium-term PPA for gas, or, since demand is so volatile and it remains costly, have we simply not seen any interest at all?
Saurabh Mashruwala
executiveNo, I think at this point we aren't seeing any medium-term or long-term contracts offered for gas, simply because you can't control gas prices. So there's no price confirmation on gas, which means the offtaker would also be exposed to that variability. And since demand is also very, very variable, it's difficult to do a medium-term or long-term contract right now. So that's why, in fact, if you look at it, we've committed higher capacity from DJN compared to last year.
Analyst
analystAlright.
Saurabh Mashruwala
executivePreviously, it stood at 720 megawatts. We've just doubled that to roughly 1,000 megawatts. So we've raised our — all right, we've secured a bigger capacity for the — under the NVV and tender this year. The way to grasp it better is that capacity is also greater during the contract period, which explains why the minimum guaranteed offtake quantity is considerably larger. What I mean is, I'd say it's 2,300 versus last year. I simply wasn't able to follow whether — so I think you clarified — you did clarify that when demand isn't there, then if they don't pick up, they must pay that fixed — assured six.
Analyst
analystThanks a lot for clearing that up.
Saurabh Mashruwala
executiveThey’ve got a contract minimum guaranteed that they have to complete — they have to make that work physically, so I’d say that’s assured.
Analyst
analystAppreciate it.
Saurabh Mashruwala
executiveThanks.
Operator
operatorThanks. Atul Tiwari with J.P. Morgan is our next questioner. Go ahead, please.
Atul Tiwari
analystYes, sir. Thank you very much. Sir, I have just two questions. Under NVV and tender, what is the minimum guaranteed take-or-pay offtake for which the fit charges must be paid?
Saurabh Mashruwala
executiveThat's something we aren't disclosing at this point.
Atul Tiwari
analystAlright. Alright. Then for my second question, sir, it concerns this project. I'm just attempting to get a clearer grasp of it. Under the terms of the agreement, the commissioning period runs 48 months. So has that clock already begun, or does the start of that clock depend on the first approvals becoming available and the land being acquired?
Saurabh Mashruwala
executiveIt begins on the day the PPA is signed. It has begun.
Atul Tiwari
analystAll right, so the clock is running. But, sir, if the land is still being acquired — and with a lot of infrastructure projects, we see land acquisition can slip quite a bit, and clearly a private company has no control over that — how does this actually work in practice? Say, for instance, land acquisition is delayed by 2 years — then what remedy do you have under the PPA?
Saurabh Mashruwala
executiveIt's a bit early to say anything about land acquisition since we're still in the middle of that process. So I wouldn't say we expect — this launch happening today will lead to land being acquired. So it's early to comment.
Atul Tiwari
analystAlright. Do you have any sense of how much time the land acquisition will take? I mean, is most of the land already acquired — 90% acquired — or not, or is it only 20% acquired? Where do we sit on that spectrum?
Saurabh Mashruwala
executiveAssul, I believe there are several phases when you mention land acquisition, correct? So we've pinpointed the land. Discussions are underway. Some things have already been completed. Now this isn't a binary event. It will be — it will be a process that moves stage by stage. So we're fairly far along when it comes to the final acquisition, but you can't claim the whole thing has been done. And there are — there are various kinds of land. So I think we ought to be able to secure the land in a very short time. But right now, if you want an answer on it, I think we haven't obtained the land as of now.
Atul Tiwari
analystAll right, all right. And is it fair to assume that the financial closure will obviously take place only once land acquisition has been completed, right? Is that the correct understanding, or are you hoping to do FC even before that?
Saurabh Mashruwala
executiveAtul, all of this is happening at the same time — acquiring land, looking for different construction parties when it comes to, say, turbine suppliers, seawheels suppliers, financial closure. Those are all things you undertake when you're getting — when you get a project or you win a bid. So financial closure has multiple — again, multiple layers to it. There could be a sanction where I can say disposal can take place if these CPs are finalized or these CPs are done, and some portion of disbursement can take place. So when it comes to all these different work streams, there are multiple layers to it.
Atul Tiwari
analystAlright. Understood. Thanks.
Saurabh Mashruwala
executiveThanks.
Operator
operatorThanks. The next person in the queue is from Avendus Spark. Please go ahead.
Analyst
analystYeah. Can you hear me okay?
Operator
operatorSure, go right ahead.
Analyst
analystRight, yeah — I missed the beginning of the opening remarks. Could you tell me what merchant EBITDA was for this quarter, and also for the full year FY ’25, so merchant 88 crores merchant negative.
Saurabh Mashruwala
executiveOh, hi there. No, I didn't get that. So you're saying this INR88 crores applies to the 4Q. For Q4, versus the prior quarter — the comparable quarter a year ago — it's down by INR88 crores.
Analyst
analystRight. Last year’s figure — I have INR85 crores — so this quarter it’s essentially nothing, or minus 3 here. Okay. So for the full year, merchant EBITDA will come in at about INR750-odd crores — INR740 crores for FY ’25?
Saurabh Mashruwala
executiveAround a year.
Analyst
analystAll right, let me clarify the NVVN tenders. From what I understand, we saw a benefit in the first quarter of FY ’25 from both NVV and second-leven opportunities. What you’re telling us now is that it’s not that — it’s only NVV and tenders. Is that the correct understanding?
Saurabh Mashruwala
executiveYeah, at this point, right now.
Analyst
analystAlright. And in the first quarter — sorry, this year's first quarter — we earned a spread of roughly INR4 per unit. So what you're saying is it may land around that level, with a lower price on the spread. Is that the correct way to see it? It's not possible to comment on that. Okay. Another question: how does this tender differ from the one last year — for instance, is the revenue fixed?
Saurabh Mashruwala
executiveOkay, along those same lines, so I’d say there isn’t much of a gap. What I mean is, I don’t know how things stood last year — in other words, whether there’s a set tariff or whether it works as variable cost plus a certain margin. You’ll receive a fixed RV according to the tenders. And you’ll receive some differential amounts, since our variable cost is lower, which means we also earn a margin on that variable cost.
Analyst
analystAll right, all right. And what would that fixed charge amount to for each unit? You want us to share that figure. We won't be sharing that figure. Got it. Okay. That's all I have on my end. Best of luck, everyone.
Operator
operatorYes, thanks. The next question is from Aniket Mittal of SBI Mutual Fund. Please go ahead.
Aniket Mittal
analystYes, sir. Thanks for the chance to speak. In the presentation, I notice a rise in the merchant capacity that you intend to build out. It's nearly doubling, going from roughly 200 to 400 megawatt. I'd just like to get a sense of the thinking behind that, and what kind of realizations do you expect on this merchant plant?
Saurabh Mashruwala
executiveYeah. So we see a lot of potential there. Looking at the market as well, there's plenty of opportunity in the merchant market. So — and at some point we will tie up that open capacity. As of now, our plan is to build up merchant capacity, and over the course of construction and going forward too, whenever the opposite is available, we'll tie up that capacity. And Anikesh, if you look at the merchant capacity that has been added right now, it is wind capacity. So if you really look at it, prices have come down during solar hours. But if you really look at it during non-solar hours, prices have been fairly stable or on an upward sloping curve. So all of these are wind capacities that are being put up.
Analyst
analystAnd as Saurabh correctly noted, moving forward, should opportunities come up, we might also partner up on those capacities.
Saurabh Mashruwala
executiveSure. Over the medium term, do you intend to put more into merchant, given that we've been raising our targets on that step by step? At the portfolio level, is there a percentage mix for merchant that you have in mind? As things stand, this is our current plan at this point in time.
Analyst
analystAll right. The other piece was really about hydro, and just so we can grasp it a little more clearly — say from a capital expenditure standpoint — internally speaking, when do you figure spending on the palm dryder ought to begin kicking in? And also, internally, what capex figures are you actually projecting, particularly where the palm dryder is concerned, for FY ’26 and FY ’27?
Saurabh Mashruwala
executiveA portion of capex will occur, and beginning this year we’ll start incurring capex from the land acquisitions and some initial payment for the equipment. But the major capex, I’d say, will take place over the next two years.
Analyst
analystLet's say we're talking about 26 to 26, '27, and 27 to 28 — and I just wanted one clarification. That INR637 crores of one-off deferred tax: was it entirely taken care of in 4Q itself?
Analyst
analystYes, Q4 itself here.
Analyst
analystAlright, thank you. That covers everything I wanted to ask. Thanks.
Operator
operatorThanks. The next question is from Anuj with Investec. Go ahead, please.
Analyst
analystHi there, thanks for taking my question. Sir, how much capex do you expect in the transmission segment? You referred to FY ’26. As I recall, last year it came to INR250. From the presentation I’m looking at, we’re expected to commission 2 transmission projects totaling roughly INR1,200 plus-odd crore in FY ’26. So could you provide some guidance regarding capex on the transmission side for FY ’26?
Saurabh Mashruwala
executiveThe capex comes from those two projects. We're anchoring roughly INR250 crores of capex in FY ’25, and the remaining majority of the capex — I'd say the balance of the capex — would happen in the next current year, meaning ’25, ’26. So approximately INR900 crores to INR1,000 crores would fall in this year. Right, we can achieve that number.
Analyst
analystRight. And we aren’t seeing anything there involving delays or concerns about evacuations. Still, getting it commissioned under the present system is fairly firm. I wouldn’t call it material. Sorry, sir—not material, in my view. Okay, okay. Yeah, that’s all, sir. Thanks for that. Thank you.
Operator
operatorThanks. We'll take our next question from Gaurav at Axis Mutual Fund. Please go ahead.
Analyst
analystHi there, and thanks for giving me the chance to speak. Sir, quite a few opportunities are emerging on the thermal side from the state side. Are we also assessing those opportunities? In other words, would you like to elaborate on the core side, or is our attention fixed on PSP and renewables?
Saurabh Mashruwala
executiveRight, we're examining brownfield options in addition to greenfield ones. That's the analysis we're doing right now. So nothing has been committed on our end, though we are indeed assessing it.
Analyst
analystGot it. Thanks.
Operator
operatorThank you, thank you. Ladies and gentlemen, since no participants have any more questions, I'll now turn the conference back to management for their closing remarks.
Saurabh Mashruwala
executiveThanks, everyone, for being on Power’s earnings call. We hope — we hope all of you remain safe and well. Many thanks. Thank you.
Operator
operatorAppreciate it. That brings us to the end of this call for Torrent Power Limited. Thanks for being with us — you can go ahead and disconnect your lines now.
Saurabh Mashruwala
executiveI really appreciate it.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Torrent Power Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Torrent Power Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Torrent Power Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.