Good day, ladies and gentlemen, and welcome to the Q1 FY26 earnings conference call for Torrent Power Limited. Please be reminded that every participant line will remain in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you require any help at any point during this call, just press star then zero on your touch-tone phone to signal an operator. Kindly be aware that this conference is being recorded. I'll now turn the conference over to Mr. Saurabh Mashruwala, Executive Director and CFO. Thank you, and the floor is yours, sir.

Saurabh Mashruwala

executive
#2

Thank you very much. Good evening, everyone, and I appreciate all of you joining Torrent Power's earnings call for Q1 FY26. To start, I'll walk you through how the quarter performed, and after that we'll open the phone lines for the question and answer session. We'll go through the company's performance at the PBT level. To begin, reported PBT for the quarter came in at INR 985 crores, versus INR 1,315 crores in the same quarter a year earlier. That's a decline of INR 329 crores — down INR 329 crores — which works out to 25% lower on a reported basis. PBT for the quarter includes a non-recurring loss of INR 59 crores arising from a non-cash adjustment tied to foreign exchange fluctuations. PBT for the same quarter last year includes a non-recurring credit of INR 102 crores from receiving a favorable tariff order for our licensed distribution area, which mainly covers carrying costs and allowances. Once you adjust for the non-recurring items — roughly — adjusted PBT for the quarter stood at 144 crores, compared with 1,213 crores in the comparable quarter of last year, lower by about 169 crores, a reduction of 14%. The company's underlying business stayed resilient. That said, the quarter was primarily affected by lower merchant gain, partly offset by improvement in the other businesses thanks to positive operational parameters.

Saurabh Mashruwala

executive
#3

The company stayed in a strong position to handle cyclical swings, backed by its diversified operations. Here are the key factors behind the performance, broken down by business. I'll walk you through four factors. First, there was a reduction of 333 crores in gain from the sale of merchant power as well as LNG. Power demand stayed subdued because the monsoon arrived early. On top of that, LNG prices stayed elevated, which hurt sales of merchant gas with capacity of 1.5 gigawatts. Overall, PLF for thermal generation fell from 60% in Q1 of FY25 to 39% in Q1 of FY26, driven by lower long-term as well as merchant sales. Second, the distribution business contributed INR 82 crores more, mainly due to two factors. First, operational parameters improved, such as lower distribution losses and higher collection efficiencies. Second, the licensed business contribution also got support from an increase in ROE as well as ROCE, thanks to capitalization of assets, as well as higher rate of returns on equity, as well as new tariff regulations. Third, the renewable business contribution rose by INR 31 crores, mainly due to interest income on delayed payment under the LPS scheme. Higher PLF was partially offset by lower contribution from the new solar project of 300 megawatts of TPLD as well as MSKVY.

Saurabh Mashruwala

executive
#4

Fourth, interest costs fell by INR 547 crores because debts were repaid using money from the QIP proceeds — that's due to the QIP proceeds. That wraps up the explanation of how we performed financially over the quarter. Now moving ahead, we'll give you a quick update on the pipeline projects. In the quarter, the company successfully won a contract under SECI 18, tying 300 megawatts of merchant capacity at a competitive rate of INR 3.97 per unit. With the 360 megawatts MSEDCL project being progressively commissioned, the company's aggregate installed generation capacity came to 4.9 gigawatts as of 30th June 2025, made up of 2.7 gigawatts of gas, 1.8 gigawatts of renewable capacity, and 362 megawatts of coal-based capacity. Pipeline projects as the quarter ended include 3.1 gigawatts of renewable projects, three gigawatts of pumped storage projects, and two transmission projects — Khavda as well as Solapur. More details on the pipeline project are summarized in our latest investor presentation, which is available on the website. I'd now like to ask the coordinator to open the line for the Q&A session. We want everybody to stay safe and healthy. Thank you so much. Back to the operators.

Operator

operator
#5

Thanks a lot. We're moving into the Q&A portion now. If you'd like to pose a question, just hit star and one on your touch-tone phone. Should you want to drop out of the queue, press star and two. We ask that participants use their handsets when asking a question. Ladies and gentlemen, we'll pause briefly while the queue is put together. Our first question comes from Mohit Kumar at ICICI Securities. Go ahead, please.

Mohit Kumar

analyst
#6

Hello there. Good evening, and thank you for the chance to speak. My first question is this: naturally, during this quarter we've taken a hit from weaker merchant prices as well as reduced offtake at the gas-based power plant. Would it be fair to describe us as assured of a set level of payment through October under the PPA that's currently in place? That being so, Q2 ought to improve relative to last year. Would that be a reasonable assumption?

Saurabh Mashruwala

executive
#7

Look, the main drag on this quarter comes from merchant sales, driven by the monsoon arriving early and higher gas prices. As for our NVVN tender, it runs from 15 March through 15 October, so it spans two quarters. Any supply that didn't get delivered under that NVVN tender will be carried out going forward in Q2. It's possible a bit could slip into Q3 as well.

Mohit Kumar

analyst
#8

Got it, sir. The second question concerns the RE portfolio. Could you lay out the CapEx figure that you provided for Q1?

Saurabh Mashruwala

executive
#9

For Q1, capital expenditure came in at roughly INR 350 crores.

Mohit Kumar

analyst
#10

What does that progression usually look like during the balance year?

Saurabh Mashruwala

executive
#11

On balance, there's a plan in place. We do have a plan. So our plan is for roughly 500 to 700 megawatts of capacity to come in. So as we go along, we'll be stepping up the CapEx for the RE portfolios.

Mohit Kumar

analyst
#12

Can you give us a rough figure for fiscal year 2026 and 2027? Would you be able to share that?

Saurabh Mashruwala

executive
#13

Pardon?

Mohit Kumar

analyst
#14

Could you possibly provide the overall CapEx figure—the expected number—for FY26 and FY27 for RE?

Saurabh Mashruwala

executive
#15

For 26, that should come in at roughly INR 7,000 to 8,000 crores this year, and a somewhat bigger figure the following year.

Mohit Kumar

analyst
#16

Got it, sir. Thanks. That helps a lot. Thank you.

Operator

operator
#17

Thanks. Our next question comes from Satyadeep Jain at Ambit Capital. Go ahead, please.

Satyadeep Jain

analyst
#18

Hello, and thanks. So, to start with merchant EBITDA for the quarter, I just want to get a clear picture — the PLF was low, but under the NVVN tender you have a minimum guaranteed offtake. So did this quarter see any EBITDA contribution from take or pay, where even if NVVN doesn't lift, you're guaranteed the fixed cost on whatever isn't lifted? I just wanted to check whether there was some contribution from that in this quarter.

Saurabh Mashruwala

executive
#19

Merchant contributions are definitely present, and that's thanks to NVVN. They've picked up a certain portion, but whatever is guaranteed will occur in the next quarter, and some spillover will also take place in Q3 as well. So the minimum guaranteed quantity is going to happen.

Satyadeep Jain

analyst
#20

I'm just trying to get a handle on this — there's some guaranteed offtake each day. I think last time around we were working through this, and what I took away was that if they don't take the minimum guaranteed offtake, which would be 2,300 MU, they won't pay you the full tariff, but you'll be guaranteed at least a fixed cost. So I'm just trying to get clarity on that this quarter.

Saurabh Mashruwala

executive
#21

So Satyadeep, I believe the point you're after is this: during this quarter, what did the minimum guaranteed offtake amount to, and what realization came from it correspondingly. Essentially, this tender runs through October, correct? Therefore, the guaranteed offtake they are obligated to take extends until October. Now, it isn't broken down into a demand for each day. So if, say, on some particular day demand isn't there, they might not commission, or they might not ask you to supply power. That can spill over onto another day. So essentially, what we're saying is that some offtake did occur under the NVVN tender, and the expectation is that NVVN will progressively take the minimum guaranteed offtake going forward. There's a possibility that a portion of the guaranteed offtake may also spill over from October into the following quarter as well.

Satyadeep Jain

analyst
#22

My take on the tender was that it identified particular crunch days — 111 of them — and on those crunch days a minimum PLF applies: 50% in non-peak periods and 100% in peak periods. So from an accounting standpoint, I figured that even when they fall short within this quarter, you'd have recorded some recovery of fixed costs, but that.

Saurabh Mashruwala

executive
#23

No, no. We record revenue according to the sales that actually occur, correct? What you're describing ought to hold true when the period ends and they haven't taken the minimum guaranteed amount. At that point we'd need to decide whether we want to account for that or not. But right now, everything we've booked reflects the offtake they've completed. It reflects the actual offtake they've completed.

Satyadeep Jain

analyst
#24

All right.

Saurabh Mashruwala

executive
#25

This isn't from some projected figure — it comes from the real offtake, and against that we've recorded the revenues and contributions.

Satyadeep Jain

analyst
#26

That's great. One item caught my attention during the presentation — some of the merchant wind capacity you hold. It looks like you've moved that over into SECI 18. What's the thinking behind it? Previously, your plan was to retain a portion of merchant wind within the portfolio. It appears that has been scaled back. Is that accurate, and why the change?

Saurabh Mashruwala

executive
#27

We actually have two merchant projects in development at the moment. We secured this SECI 18 tender, and we moved the tariff to INR 3.97, which I would call quite good. So we've shifted that merchant capacity over to the SECI 18 tenders — that's the goal here. Since the tariff came in at a solid INR 3.97 under SECI 18, it makes more sense to move this merchant capacity to SECI and lock in a better rate. And we'll keep developing additional merchant capacity moving forward as well.

Satyadeep Jain

analyst
#28

If I could fit in one more quick question. Regarding parallel licensing, I believe a news report points to some CapEx opportunity in Nagpur. I think there's a hearing taking place. I just wanted to get a handle on where that process stands at the moment, and I think the news reports suggest maybe PAT losses for the first four years. I just wanted to understand the reason for that? I'm not sure whether it was misquoted or something. If that's the case, why would there be PAT losses during the first four years? Perhaps you could discuss this opportunity, those steps, and I'm not sure whatever the media reports say. I just wanted to hear your thinking on that.

Saurabh Mashruwala

executive
#29

We’re not able to say anything about what the media reported, but the reality is that the public hearing was held today — in fact, it took place today in Mumbai and was organized by the MSEB. So that happened today. At this point, they’ve reserved the orders. They’ll be published, and I’d say they’ll be announced in a couple of days, and after that we’ll find out the exact status regarding the parallel licensing. The public hearing was held today in Mumbai.

Satyadeep Jain

analyst
#30

The outcome of the public hearing is going to be announced in two days, so what happens after that?

Saurabh Mashruwala

executive
#31

It takes a couple of days — not two days, just a couple. Depending on how the public hearing goes, they'll hold the order back and decide whether the circle gets allocated to Torrent Power or not.

Satyadeep Jain

analyst
#32

So in roughly 2 days, you see, we ought to have that answer.

Saurabh Mashruwala

executive
#33

Right. That's what we're expecting the MERC — the Maharashtra State Regulatory Commission — to come out with.

Satyadeep Jain

analyst
#34

So this applies to all 3, correct? Pune, Nagpur — all 3 of those areas.

Saurabh Mashruwala

executive
#35

Yes, every one of those three areas.

Satyadeep Jain

analyst
#36

Okay, all right, and thanks a lot.

Operator

operator
#37

Thanks. Our following question comes from Sumit Kishore at Axis Capital, on the line. Go ahead, please.

Sumit Kishore

analyst
#38

Thanks. Can you help us understand the total merchant unit sales in Q1, and what contribution came from gas-based power plants during this year’s first quarter? Our understanding from last year was that in Q1 of last year, you had achieved merchant gains of nearly INR 6 million.

Saurabh Mashruwala

executive
#39

This quarter, we saw a merchant sale of roughly 714 MUs.

Sumit Kishore

analyst
#40

714?

Saurabh Mashruwala

executive
#41

We had 714 MUs, and that figure includes the NVVN tender as well. The contribution came to roughly ₹327 crores.

Sumit Kishore

analyst
#42

Understood — that's very clear. As for the second question, my apologies?

Saurabh Mashruwala

executive
#43

Yeah. No, you go ahead.

Sumit Kishore

analyst
#44

Yes. On your second question, I believe you told an earlier participant that capital expenditure for Q1 came to just INR 3.5 billion. I was thinking that your.

Saurabh Mashruwala

executive
#45

For renewables alone, it was 350 crores. Total CapEx comes to roughly INR 850 crores, while renewable CapEx stood at INR 350. So at the company level, CapEx amounted to INR 850 crores. Of that figure, INR 350 was renewable.

Sumit Kishore

analyst
#46

All right. Just so I get this straight — when we look at those figures on an annual basis, they're above INR 70-INR 80 billion, so is there any particular reason Q1 CapEx in renewable comes in this low, or how are we meant to interpret a number like that? It looks pretty low.

Saurabh Mashruwala

executive
#47

Yes. I’d say it ramps up in Q2 and H2, and that increase will be significant relative to H1.

Sumit Kishore

analyst
#48

And on top of the 2 gigawatt Maharashtra PSP, the total PSP you're now showing comes to 3 gigawatt. So.

Saurabh Mashruwala

executive
#49

For MSEDCL, 2 gigawatt is already tied up. Then there's 1 gigawatt we're planning on a merchant basis, and that will get tied up at some point. But right now, what we're developing is 3 gigawatt of capacity — PSP capacity.

Sumit Kishore

analyst
#50

So that 1 gigawatt merchant is situated at the identical site?

Saurabh Mashruwala

executive
#51

Yes, it's the same site, since that site has 3-gigawatt capacity. Of that total, we have 2 gigawatts committed with MSEDCL.

Sumit Kishore

analyst
#52

Understood. Understood. That covers what I wanted to ask. Thanks.

Saurabh Mashruwala

executive
#53

Thanks.

Operator

operator
#54

Thanks. We’ll take the next question from Suyash Jain at NDTV Profit. Please go ahead. Mr. Suyesh, are you there? Sir? Since the participant isn’t responding, we’ll move on to the next one. The next one. Our next participant is Ketan Jain from Avendus Spark. Please go ahead.

Ketan Jain

analyst
#55

Thanks. Sir, to build on what was asked before, you mentioned that merchant contributed roughly INR 327 crores to EBITDA. Is the LNG sale included in that figure as well?

Saurabh Mashruwala

executive
#56

On the LNG sale — essentially, when we refer to merchant, that covers LNG and MU sales as well.

Ketan Jain

analyst
#57

Both.

Saurabh Mashruwala

executive
#58

Both.

Ketan Jain

analyst
#59

Ajah. All right. Sir, do you have a figure? For the prior quarter and the prior year, what would the comparable number be?

Saurabh Mashruwala

executive
#60

We essentially don’t provide that breakdown. It can be swapped around based on what opportunities exist between the merchant and.

Ketan Jain

analyst
#61

All right, so for the first quarter of FY25, is there a number that's roughly comparable to that same INR 327 crores?

Saurabh Mashruwala

executive
#62

Right. For last year, the figure we've seen is INR 660 crores.

Ketan Jain

analyst
#63

660 crores. All right, thanks. Sir, my following question concerns what your average realization would be for this quarter, sir? Realization and EBITDA for this quarter, the average realization on the 700 MUs that we sold.

Saurabh Mashruwala

executive
#64

So what we've seen is 714 MUs sold in the merchant market, and the contribution from that is INR 327 crores. Around INR 450. INR 450.

Ketan Jain

analyst
#65

Roughly INR 450. All right, sir. Then one final question: we came across a news item, or a media report, saying your company has interest in looking at L&T's power asset. Do you have any comment on that, sir?

Saurabh Mashruwala

executive
#66

No, we’re not going to comment on that. We won’t be making any remarks on it right now.

Ketan Jain

analyst
#67

But does that mean we're considering thermal assets? On a routine strategic basis, are thermal assets always something we're examining?

Saurabh Mashruwala

executive
#68

That fits within our overall strategy. Yes, we’re also examining the thermal and coal assets — both developing coal assets and taking part in the IBC process. This is an ongoing effort. We pursue the majority of acquisitions on the renewable side as well as on the coal side.

Ketan Jain

analyst
#69

Got it, thanks. Appreciate the answer.

Operator

operator
#70

Thanks. Before we move on to the next participant, we'd like to remind everyone to press star and one if they'd like to ask a question. Our next question comes from Bhavin Vithlani at Avendus Spark. Please go ahead.

Bharanidhar Vijayakumar

analyst
#71

Can everyone hear me?

Operator

operator
#72

Yes, sir, that's correct — you are.

Bharanidhar Vijayakumar

analyst
#73

Yeah. So could you bring us up to date on the UP Discom privatization — where does that process stand at this point? And when do we expect the bid to be opened?

Saurabh Mashruwala

executive
#74

It's still early, since the government is currently working on the RFP. That's what they're doing right now. So that's where things stand at the moment. That said, we're definitely interested in taking part in the tenders as and when they come up. But as of now, the UP government is still finalizing the proposal.

Bharanidhar Vijayakumar

analyst
#75

Alright. Alright, and the second thing I wanted to ask about is DGEN. When I look at the voluntary FY26 PLF you reported, which is 21%, that works out to roughly 2,300 million units of generation. So I'm just trying to get a sense of it — if we've sold about 714 in merchant, where do the remaining units go? Who are they sold to? Are they going to the distribution circle in Ahmedabad, Surat?

Saurabh Mashruwala

executive
#76

No. So I think you're looking at these MUs on a yearly basis.

Bharanidhar Vijayakumar

analyst
#77

Right, precisely.

Saurabh Mashruwala

executive
#78

Split four ways.

Bharanidhar Vijayakumar

analyst
#79

Number four, and that's right.

Saurabh Mashruwala

executive
#80

I think what you're doing there is looking at the MUs — you're working out annual MUs rather than quarterly MUs.

Bharanidhar Vijayakumar

analyst
#81

20%.

Saurabh Mashruwala

executive
#82

The calculation needs to cover 90 days.

Bharanidhar Vijayakumar

analyst
#83

Okay, my apologies. Yes, yes, that was an error. Just a moment. Yeah, you're correct. I was working it out for a different plan. Understood. Understood. And lastly, regarding the figure — how many units do we anticipate selling, or to phrase it differently, placing into the merchant market during the second quarter?

Saurabh Mashruwala

executive
#84

We aren't providing any estimates, I'd say. As you're well aware, that merchant market tends to be quite unpredictable. And beyond that, LNG prices are highly volatile as well. So for us to give you any estimates is very difficult.

Bharanidhar Vijayakumar

analyst
#85

All right, Rishi — of course, of course. Thanks very much.

Saurabh Mashruwala

executive
#86

Thanks.

Operator

operator
#87

Thanks. We’ll take the next question from Nikhil Abhyankar at UTI Mutual Fund. Please go ahead.

Nikhil Abhyankar

analyst
#88

Okay, so I just have one question — I want some clarity on the NVVN tender. Is it fair to assume that the fixed cost tied to that NVVN tender, which relates to 2.3 billion units of minimum offtake, will be fully booked by the end of Q3?

Saurabh Mashruwala

executive
#89

So the contract runs through October 15th as it stands, though if their demand means it isn't fully used by then, the government might extend part of it. Still, we can reasonably expect it to be fully utilized by Q3.

Nikhil Abhyankar

analyst
#90

Alright. It's being used to the fullest. Okay. And in the event that it isn't used to the fullest, are we going to receive the?

Saurabh Mashruwala

executive
#91

We're going to secure that minimum offtake fixed cost.

Nikhil Abhyankar

analyst
#92

Yes. Yes. Thanks. I have nothing further to add.

Operator

operator
#93

Thanks. Anyone who’d like to ask something can hit star and one at this point. Again, to pose a question, press star and one now. To pose a question, press star and one now. Ladies and gentlemen, since no more questions have come in from the participants, I’ll now turn the conference over to Mr. Saurabh Mashruwala for closing remarks.

Saurabh Mashruwala

executive
#94

Thanks, everyone, for being on the Torrent Power earnings call. We really appreciate it. We hope all of you remain safe and well. Many thanks. Thank you.

Operator

operator
#95

Appreciate it. That brings Torrent Power Limited's conference to a close. Thanks for being with us, and you can go ahead and disconnect your lines at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Torrent Power Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Torrent Power Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Torrent Power Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.