Torrent Power Limited (TORNTPOWER) Earnings Call Transcript & Summary
November 11, 2025
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to Torrent Power Limited's 2Q FY '26 Earnings Conference Call. <<operator_script>> Kindly be aware that this conference is being recorded. At this point, I hand the conference over to Mr. Saurabh Mashruwala, Executive Director and CFO. Thank you, and over to you, sir.
Saurabh Mashruwala
executiveThank you, sir. Thank you. Good evening, everyone, and thanks for being on Torrent Power's Q2 FY '26 earnings call. To start, I'll walk you through how the quarter performed, and after that we'll open the phone lines for a Q&A session. We'll begin by explaining the company's performance at PBT level, and then we'll cover the tax expenses separately. Reported PBT for the quarter came in at INR 979 crores, against INR 689 crores in the same quarter a year earlier. That's a rise of roughly INR 290 crores, or about 42% on a reported basis. PBT for this quarter contains a nonrecurring credit of INR 31 crores from receiving favorable orders in the license distribution business, which mainly comprises carrying cost allowances. PBT for the same quarter last year contains a nonrecurring credit of roughly INR 67 crores stemming from 2 factors. The first is accounting of INR 99 crores on receipt of favorable orders in the license distribution area, which mainly comprises carrying cost allowances, partly offset by lower generation from the wind power plant because of forced stoppages of wind turbines caused by heavy rains and Asna cyclone witnessed in Gujarat during the quarter, which led to a reduced contribution of INR 32 crores.
Saurabh Mashruwala
executiveOnce you strip out those one-off items, profit before tax for the quarter came in at INR 948 crores, versus INR 622 crores in the same quarter a year earlier — a rise of roughly INR 326 crores, or about 52%. Turning to the sectors, here is how each one contributed. First, thermal generation added around INR 293 crores, driven largely by stronger contributions from merchant power sales as well as LNG, to the tune of about INR 304 crores. Second, those merchant gains were partly offset by higher O&M expenses and a noncash adjustment related to foreign exchange variation of approximately INR 11 crores. Second, the distribution business, adjusted for one-off items, was up about INR 11 crores, mainly because of, first, better T&D losses at the distribution franchise units, partly offset by higher T&E in the licensed distribution area. Second, the licensed distribution business also got support from higher ROE and ROCE, reflecting capitalization of assets and a higher rate of return on equity under the new tariff regulations. And third, demand growth in our distribution business ran in the range of about 4% to 5%. The third item is renewable generation, which adjusted for one-off items fell by INR 20 crores, mainly due to lower PLF from the existing wind power plant on weaker wind resources, partly offset by the contribution from newly commissioned solar capacity of 381 megawatt.
Saurabh Mashruwala
executiveThe remaining INR 43 crores of the balance division comes mainly from, first, lower finance costs thanks to repayments made in Q4 of FY '25, partly offset by higher depreciation and other miscellaneous expenses. That wraps up the explanation of the financial performance for the quarter. Now on to the project update. First, in the quarter, on top of our existing renewable pipeline, a subsidiary of the company was awarded an LOA for 250 megawatts of FDRE renewable generation from our licensed distribution unit. The company obtained a Letter of Award from MP Power Management Company Limited for long-term power supply from a new 1.6 gigawatt coal-based power plant at a tariff of INR 5.83 per kilowatt hours. India's largest green hydrogen natural gas blending initiative in the City Gas Distribution sector was successfully commissioned in the quarter. With progressive commissioning of the 367 megawatt MSEDCL project, the company's aggregate installed generation capacity was close to 5 gigawatt as of 30th September 2025, made up of 2.7 gigawatt gas capacity, about 1.9 gigawatt of renewable capacity, and 362 megawatt of coal-based capacity. The pipeline project as of quarter-end includes 3.6 gigawatt renewable capacity, 3 gigawatt of pumped storage capacity, 1.6 gigawatt of coal plant and 2 transmission projects at Khavda and Solapur.
Saurabh Mashruwala
executiveOur newest investor presentation, which you can find on our website, contains a fuller summary of the pipeline project. That wraps up the quarter. At this point, I'd like to ask the coordinator to open the line for the Q&A session. We want everyone to remain safe and healthy. Many thanks. I'll hand things over to the operators.
Operator
operator<<operator_script>> Mohit Kumar of ICICI Securities has our first question.
Mohit Kumar
analystTo start with my first question, sir: naturally, we delivered a robust performance this quarter. Part of that, I believe, stems from merchant sales under the short-term power purchase agreement signed in March. In the third quarter, are we still selling some portion under that agreement, or has it now ended?
Saurabh Mashruwala
executiveSo the bulk of that portion has already been delivered in Q2. That lets us say that most of it was supplied under the contract during Q2.
Mohit Kumar
analystGot it. So there’s almost nothing remaining for Q3, correct?
Saurabh Mashruwala
executiveYeah, I'd say possibly a piece of it — not material, though.
Mohit Kumar
analystGot it. Could you give us the split between merchant sales and LNG sales for the quarter — maybe some kind of broad indication?
Saurabh Mashruwala
executiveI'd say LNG sales aren't material. The bulk of the revenue contribution comes from merchant sales.
Mohit Kumar
analystAlright, sir, my final question concerns the coal-based power plant that you secured during this quarter. The capital cost appears to be somewhat on the higher side. Is that the maximum, or do you believe you can execute it at a considerably lower cost — perhaps nearer to INR 11 crores or INR 12 crores per megawatt instead of INR 13 crore per megawatt? Is that a possibility? And a related question: what is the fixed cost, the fixed tariff, that you bid for this particular power plant? Could you possibly provide a breakdown between the variable cost and the fixed cost quoted in the bid?
Saurabh Mashruwala
executiveRight, so that kind of rate is what we're seeing, and in fact equipment costs have basically risen now. So that's the cost we've budgeted as of today. Once we — so essentially this sort of cost is what's happening. And regarding your second question about variable cost and fixed cost, fixed cost comes to roughly INR 4.22, while variable cost is pass-through. That's the way the PPA — I'd call it the LOA — is configured.
Operator
operatorThe next person to ask a question is Sumit Kishore with Axis Capital.
Sumit Kishore
analystYou said you've taken a 500-megawatt FDRE project from TPL-D. What terms apply to it? How much of it is solar and how much is wind? Is there any other detail about the specifications that you're able to share with us?
Saurabh Mashruwala
executiveIt's really a mix of solar, wind and the battery. So roughly — solar comes to around 350, wind around 150 megawatts, and the tariff sits at about 4.87.
Sumit Kishore
analystSo, wind is at 150?
Saurabh Mashruwala
executiveYes, sorry?
Sumit Kishore
analystYou mentioned wind at 150, is that right?
Saurabh Mashruwala
executiveYeah, yeah. Wind comes in at 150, and solar is roughly 350 megawatts.
Sumit Kishore
analystWhat's the battery size?
Saurabh Mashruwala
executiveBattery storage would be another item there — roughly 100-megawatt-class batteries.
Sumit Kishore
analystA 100 megawatt system with 4 hours of storage, or...
Saurabh Mashruwala
executiveSo we're talking about 450 megawatt hours.
Sumit Kishore
analyst4.5 hours of storage?
Saurabh Mashruwala
executiveRight, so 112 megawatts of battery capacity works out to 450 megawatt hours.
Sumit Kishore
analystAll right, 4 hours. For my second question, your presentation noted that BTG was awarded for the coal plant. To whom was it awarded, at which project, and at what value?
Saurabh Mashruwala
executiveWe can't disclose that, but as for the project, a turbine contract has been awarded.
Sumit Kishore
analystSo TG has been awarded, but the boiler hasn't been awarded yet?
Saurabh Mashruwala
executiveNo, no — the whole of BTG is awarded.
Executive
executiveYeah, BTG and balance of plant are both being discussed — and BTG has already been awarded.
Sumit Kishore
analystSo does that go to one of the two domestic players?
Saurabh Mashruwala
executiveYes, you could put it that way — 1 of the 2 domestic players.
Sumit Kishore
analystAll right, so the next question is: what's the CapEx for the first half of the fiscal? And last time you mentioned that a significant portion of the CapEx you plan to incur for RE — almost INR 8,000 crores — will be incurred this year. So specifically, what progress has been made on RE CapEx as well?
Saurabh Mashruwala
executiveRegarding the H1 figure, license costs came to roughly INR 780 crores. Franchisee was on the order of INR 100 crores. For transmission, we incurred approximately INR 275 crores. And on RE, renewable CapEx will be INR 2,500 crores that we incurred during H1.
Sumit Kishore
analystRegarding the INR 2,500 crores we incurred in H1, RE?
Saurabh Mashruwala
executiveYeah, RE.
Sumit Kishore
analystWhat was the total CapEx you incurred at the consolidated level in H1?
Saurabh Mashruwala
executiveThat comes to roughly INR 2,700 crores.
Executive
executiveWe're looking at INR 3,700 crores.
Saurabh Mashruwala
executiveWe recorded INR 3,700 crores.
Sumit Kishore
analystAll right, so that's INR 3,700 crores in total, and INR 2,500 crores of it is RE. Okay, understood.
Saurabh Mashruwala
executiveThat's exactly right.
Sumit Kishore
analystAnd lastly, in what you said at the start, I want to check whether I caught the figure correctly. You said the overall rise in merchant contribution for thermal came to INR 324 crores, is that right?
Saurabh Mashruwala
executiveApproximately INR 300 crores, give or take.
Sumit Kishore
analystIs it INR 300 crores?
Saurabh Mashruwala
executiveYes.
Sumit Kishore
analystSo that figure is the change compared with the same period a year earlier?
Saurabh Mashruwala
executiveRight, and yes — the change versus a year ago, measured against the prior quarter.
Sumit Kishore
analystAll right, all right, all right. So how many merchant units in total did you sell in the quarter?
Saurabh Mashruwala
executiveRoughly 650 MUs.
Operator
operatorThe next person to ask a question is Satyadeep Jain of AMBIT Capital.
Satyadeep Jain
analystStarting with the NVVN tender question. Since the tender has now concluded, can you tell us how much volume was actually lifted under it? And for whatever portion wasn't lifted, do you recover the full fixed cost in 3Q, or have you already recognized part of that fixed cost recovery in 2Q?
Saurabh Mashruwala
executiveAs we mentioned before, we have supplied materially, which is what we said in response to the first question.
Satyadeep Jain
analystApologies, sir, but I didn’t catch that. Whatever...
Saurabh Mashruwala
executiveAs we said in our earlier response — to the first question — we have materially supply under that contract.
Satyadeep Jain
analystGot it. So you met the whole—there wasn’t any volume, which was guaranteed under the minimum contract and wasn’t raised by the consumer? My understanding was that actual offtake came in below the minimum offtake, correct, and that’s the reason you have a fixed cost guarantee you recover if the customer doesn’t take the full volume.
Saurabh Mashruwala
executiveSo the bulk of the contract has been fulfilled — that's what we're able to tell you at this point.
Satyadeep Jain
analystSo you're not expecting any meaningful fixed cost recovery from this contract in Q3, correct?
Saurabh Mashruwala
executiveYes.
Satyadeep Jain
analystAnd second, I wanted to ask about the PSP project. The CapEx there also looks a bit high, at INR 7 crores per megawatt. If you consider INR 14,000 crore of CapEx against INR 1,680 crores of revenue under the contract, what sort of IRR would you expect on a project like this?
Saurabh Mashruwala
executiveHow can you claim that's the cost? What number of megawatts are you factoring in?
Satyadeep Jain
analystThat 2,000 megawatt project at INR 14,000 crores, correct? Works out to roughly INR 7 crores for each megawatt.
Saurabh Mashruwala
executiveThe overall project cost comes to INR 14,000 crores. And the capacity we're building out is 3 gigawatts. And 2,000 gigawatt -- 2 gigawatts is a -- we've signed off on a PPA. So -- but the capacity we're putting up stands at 3 gigawatts, and the project cost is INR 14,000 crores.
Satyadeep Jain
analystSo the INR 14,000 crores — that covers 3 gigawatts?
Saurabh Mashruwala
executiveThat's right. Precisely.
Satyadeep Jain
analystOkay. And finally, regarding wind and solar PLF, I didn’t quite follow, because everyone — including in Gujarat — is seeing greater wind PLF this quarter versus a year earlier, and then reduced solar PLF. What was unusual in Gujarat for you? I’m just trying to get it — was it something specific to the location?
Saurabh Mashruwala
executiveI think that, since the monsoon came faster, the PLF is somewhat weaker where wind is concerned. And for solar, thanks to the newly commissioned capacity, PLF is somewhat stronger than in the same quarter a year earlier.
Satyadeep Jain
analystSo the wind side—it was only the monsoon that hit, and that likely affected a few wind mills in Gujarat for you, while solar was probably just the new mills and the new plant?
Saurabh Mashruwala
executiveRight, right. Exactly — that's it. In Gujarat, we observed the monsoon arriving sooner than usual. It continued through Diwali as well, I'd say. So that's the reason wind resources took a hit, I would argue.
Operator
operator<<operator_script>> Atul Tiwari from JPMorgan has our next question.
Atul Tiwari
analystRight, thanks. Just a quick one from me. Now that the NVVN tender has wrapped up, is it fair to think that during the third quarter and at least the early portion of the fourth quarter there won't be any merchant sales — or are you still selling something into the merchant market?
Saurabh Mashruwala
executiveEverything hinges on how the market plays out. Should peak demand materialize, then without question there will be merchant sales. So we can’t state anything at this point, but I’d say it all comes down to market dynamics. And if you — you’ve noticed that LNG prices are declining. So it’s a matter of peak demand, sort of. So one needs to watch peak demand closely over the next 6 months, I would say.
Atul Tiwari
analystWhat's the landed cost of LNG right now for generating the power you need?
Saurabh Mashruwala
executiveAt $10, if you take that $10 per MMBtu of cost, then variable cost would come to roughly INR 6, something like INR 6, variable cost.
Atul Tiwari
analystAll right. So if merchant prices happen to exceed that amount, then it would make sense for you to...
Saurabh Mashruwala
executiveYes.
Operator
operator<<operator_script>> Ketan Jain from Avendus Spark has our next question.
Ketan Jain
analystSir, my first question concerns NPE per project. When is this thermal plant expected to be commissioned?
Saurabh Mashruwala
executiveThe first unit comes in at roughly 66 months starting from the PPA date, while the second unit runs 72 months from that same PPA date.
Ketan Jain
analystAll right, so that comes to nearly 6 years.
Saurabh Mashruwala
executiveCorrect, that's 6 years out from now. And actually, the PPA hasn't been signed yet. We expect it to be executed within the next 2 months. Once that happens, the clock on that timeline begins.
Ketan Jain
analystSix months. All right. My next question concerns renewable capacity additions. For the second half of FY '26, what are you targeting, and then progressively in FY '27? What level of renewable capacity addition do you expect?
Saurabh Mashruwala
executiveOn total capacity, what we've envisioned for the full year is roughly 500 to 600 megawatts for the current year. Of that, approximately 367 megawatts has already been commissioned, and we expect the remainder to come online in the second half. And most of the capacity from the upcoming project — apart from the newly won project — will be commissioned next year. Next year and the next 1.5 years, I'd say.
Ketan Jain
analystSo the entire balance portfolio capacity is expected to arrive in '27 and the first half of '28?
Saurabh Mashruwala
executiveYeah, yeah. The next 2 — 1.5 to 2 years, at most, I'd say.
Ketan Jain
analystGot it. Do you have any goal in mind for FY '27, sir?
Saurabh Mashruwala
executiveNot really, though we’ll do our best to speed up the commissioning. And actually, the commissioning date is included in the presentation as well.
Operator
operator<<operator_script>> Since no one else has questions from the participants, I'll now turn the conference over to Mr. Saurabh Mashruwala for his closing remarks.
Saurabh Mashruwala
executiveWe appreciate you all being here for Torrent Power's earnings call. We hope each of you stays safe and well. Many thanks.
Operator
operatorAppreciate it. That brings us to the end of this call for Torrent Power Limited. Thanks for being with us, and you can go ahead and disconnect your lines now.
Saurabh Mashruwala
executiveThanks.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Torrent Power Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Torrent Power Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Torrent Power Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.