VA Tech Wabag Limited (WABAG) Earnings Call Transcript & Summary
February 10, 2020
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to the VA TECH WABAG LIMITED Q3 FY '20 Earnings Conference Call. <<operator_script>> I will now turn the conference over to Mr. Rajiv Mittal, Managing Director and Group CEO. Thank you, and over to you, sir.
Rajiv Mittal
executiveThanks. Hello everyone, and good afternoon. It's a pleasure to have all of you join us for this call following the announcement of VA TECH WABAG LIMITED's Q3 FY '20 results. Our Group CFO, Mr. Sandeep Agrawal, is with me on today's call. We take great pride in having successfully commissioned the Koyambedu TTRO plant in Chennai, which the Honorable Chief Minister of Tamil Nadu inaugurated in November. This project is a landmark one — for the city of Chennai as well as for WABAG — and it also stands as the country's largest water recycle and reuse facility. Sewage at this plant is treated and turned into usable industrial water, which eases freshwater stress on the city. At our Dangote project in Nigeria, engineering work and equipment ordering are for the most part finished. The client has begun granting dispatch clearance for key equipments, and dispatches are presently underway. Most engineering approvals needed for construction have likewise been issued. On the Polgahawela, Sri Lanka project, the designs have been approved, and execution is now at an advanced stage. The treatment plant, intake structures and reservoirs have risen above ground level and are making good progress. Delivery of all 3 equipments is done. The transmission and distribution pipeline has moved ahead well and is in full swing, with multiple contractors working at sites in multiple locations.
Rajiv Mittal
executiveCommissioning on this project should get underway during the third quarter of FY '21. As you'll recall, WABAG took over operational management of the sewage network serving Agra and Ghaziabad. Under the One City – One Operator model, we signed the contract in November and began progressively assuming O&M activities in a phased manner starting mid-December. We're confident this model's success will encourage additional state governments to replicate it. Turning to progress on our MEA projects. At Jubail, the STP project in Saudi Arabia that MARAFIQ is implementing, 90% of engineering has been finished. Engineering is slated for completion by March. Purchase orders for long-lead items are placed and manufacturing clearances have been issued. The first batch of clarifiers has been inspected, and major process items are scheduled for inspection over the next 2 quarters. Every major water retaining unit and raft has been completed, and civil works is proceeding at full force. At our South Doha project in Qatar, detail engineering is almost done. All long-lead items are ordered, and manufacturing is underway. Nonprocess unit rehabilitation work is finished and in the process of being handed over. On process units, rehabilitation work is moving along well.
Rajiv Mittal
executiveAt the Zarat project in Tunisia, detail engineering is currently in progress, and long-lead item procurement is almost finished. Deep structure construction is close to being done, while building work on the remaining structures continues. Turning to GENCO projects, specifically TSGENCO, we secured an interim injunction order from the Supreme Court against the arbitration proceeding that Tecpro started. Those proceedings are ongoing, and we anticipate the High Court order being quashed very soon — or rather, a Supreme Court order to that effect. On APGENCO, the customer has cleared us to resume the pending work, and that work is now underway. As we mentioned last quarter, these sizable new projects, together with our recent orders in India, have begun accelerating further and should make additional progress over the coming quarters. Our order book remains robust at INR 11,500 crores — roughly 3x our annual revenue — which provides both confidence and visibility regarding the future. I'll now hand things over to Sandeep, who will walk you through the quarter's financial highlights. Over to you, Sandeep.
Sandeep Agrawal
executiveThank you, Mr. Mittal. Good afternoon, friends. To start, you've had a chance to review the results update presentation that was shared and posted on our website. Let me now walk you through the main financial highlights covering the 9-month period that closed on 31st December 2019. Revenue from operations during those 9 months came in at INR 1,772 crores on a consolidated basis, and at INR 1,250 (sic) 1,255 crores on a stand-alone basis. EBITDA for the same 9-month period was INR 171 (sic) 172 crores, and on a consolidated basis INR 147 crores on a stand-alone basis. Profit after tax attributable to owners for that 9-month stretch reached INR 61 (sic) 60 crores on a consol basis, and INR 57.4 (sic) 57 crores on a stand-alone basis. As expected, momentum on our key projects has begun building, which let us deliver solid results and cash flow. Our sustained focus on managing cash and receivables is now bearing fruit as well, and we intend to sustain that same momentum. Net working capital is down by close to INR 270 crores compared with a year earlier — a drop of nearly 22%. That reflects our ongoing efforts and actions to strengthen the working capital position.
Sandeep Agrawal
executiveAt the group level, net debt as of 31st December 2019 was INR 285 crores, compared with INR 433 crores on 31st March '19 — that's a 34% decrease in the company's net debt over the 9-month period. Keeping up our efforts and our focus on generating positive cash flow, we produced operating cash flow of INR 187 crores for the 9-month period, which led to free cash flow of INR 143 crores at the consolidated level for the 9 months ended 31st December 2019. That comes directly from our ongoing emphasis on receivables, working capital and cash management in this difficult economic environment. We remain in close contact with our bankers and appreciate their ongoing support in extending nonfund lines for the new projects, which will further strengthen the company's cash and working capital position. With that, we are now opening the floor for question and answer.
Operator
operator<<operator_script>> Our first question comes from Vikas Jain at Financial Quotient.
Vikas Jain
analystI'd like to offer my congratulations and compliments on a strong quarterly result. Beyond that, it's good to see that we've now managed to generate free cash flow, which had been a troubling item for a few quarters in the past. That's a positive for an investor. I have 2 questions. The first is that there has been some news regarding Andhra Pradesh Generation Company. While I understand Mr. Mittal did address the subject, I don't believe I was able to grasp where things stand on the outstanding debt and the repayment plan from APGENCO. So if you could provide some insight on that.
Rajiv Mittal
executiveVikas, the status hasn’t changed at all, and that’s exactly what I covered in my remarks. In essence, the receivable sits in 3 buckets. The first is TSGENCO, where all the work has been completed and the funds were set to be released, but Tecpro’s RP sought arbitration with TSGENCO. That is where the whole thing came to a halt. And that is a matter our client, TSGENCO, and we jointly put before the Supreme Court. We managed to hold that off, so it has been held off. The proceedings are now before the Supreme Court to quash the move to take TSGENCO, our client, into arbitration. As soon as that wraps up, I think within 2 or 3 quarters, we ought to be in a position to recover roughly INR 138 crores, which is essentially ready for disbursement once the Board approves and the Supreme Court rules. The second piece is the NCLT one, which we have walked all of you through repeatedly, and I’ll say it again: INR 69 crores that sits directly with Tecpro’s RP. Since we belong to a consortium, Tecpro gathered that money on our behalf and never remitted it to us. So it is treated as a trust or <<inaudible>>.
Rajiv Mittal
executiveWe therefore hold priority regarding the security of the financial creditors. That means we have the first charge on retrieving this money. Their own auditor also certified that this amount is present in Tecpro's books. Yet when the order was passed at NCLT, they conveniently omitted any mention of it; we raised that at NCLAT, and they have once more instructed NCLT to review the matter and issue the order on it. So today we are back at NCLT seeking a favorable response, and we hope to receive one very soon. Third, you know APGENCO — a project where we still have some work left because of elections and new governments, and they wanted every project reviewed, which happened. Fortunately, our project made it through. We have received official intimation that we may continue working and complete the project. We therefore expect to finish our remaining work within the next 8 months, after which we will receive our first retention. And 1 year after that, our second retention will come. That is the update on the GENCO projects.
Vikas Jain
analystThank you. The next thing I want to bring up is a question, though <<inaudible>>. I realize this might not be the proper venue for it, but after trying other channels without getting any response, I have no option but to bring it up here. It concerns the interests of minority shareholders: if VA TECH WABAG would choose to release the conference call information in advance on the exchange website and on its own website, smaller investors would find it genuinely helpful to join the call and gain a closer view of how the company is progressing — and that is not happening. I have also dealt with the IR people, and I see no improvement in the process. The con call invites still are not posted on the BSE or NSE website, sir.
Rajiv Mittal
executiveWe’ll verify that, Vikas, and we’ll ensure that if anything remains on our side, we’ll fix it, and the con call speech will also be posted on our own website.
Vikas Jain
analystYes. Even though the con call speech does get updated, sir, having the con call invite, right, ahead of time helps people to join the con call. And if they don't ask questions, then at least go through the detailing of what you looked at — that's valuable information for even a minority shareholder. So it can be seen as a shareholder-friendly initiative as well, sir.
Rajiv Mittal
executiveSure, Vikas — we’ll look into that. And if anything needs correcting, we’ll take care of it.
Operator
operatorOur following question comes from Mohit Kumar with IDFC Securities.
Mohit Kumar
analystSir, I have a couple of questions. First, is it too early to provide revenue guidance for FY '21? And with the FY '20 revenue guidance standing at INR 3,000 crores, are you confident that you will meet the guidance for the full year? The second one concerns the -- there were 2 large projects, one being the Chennai 400-MLD desalination plant and the other being the Mumbai sewage project. Could you give us any timeline or a sense of where the tender stands and how things are progressing on those 2 projects?
Rajiv Mittal
executiveYes, Mohit. On your first question, yes, it's too early to give guidance for FY '21. Our tradition has always been to do that once the year ends. So you'll get that guidance on our next call. Second, about the Chennai and Mumbai projects — on Mumbai, you had the election. There was a change of government. And these are all fairly large projects. Every one of them got delayed, and that's where they stand today. They have all gone for re-tender, and my hope is that the delay will be at least 6 to 8 months. On Chennai, this is my trusty of raising this big JICA-funded 400-MLD project. I think they have just appointed a consultant. One would expect a PQ in the first quarter. And in the second quarter, we will see the request for quotations proposal. And in this financial year '21, they would finalize these orders. On the guidance you asked about, what we have given for this year of revenue INR 3,000 crores, yes, I think we are fairly confident. We have done this before. If you look at our FY '17 or FY '18, we achieved revenues of more than INR 1,000 crores in the last quarter.
Rajiv Mittal
executiveWe're also quite confident this will get completed. Naturally, it—much hinges on how the project unfolds, on what the supplier can deliver, and on how the site work is advancing, since we have several projects that will feed into this. So because of that, we believe—yes, we'll land very near our guidance.
Mohit Kumar
analystSir, do you have any thoughts on providing — could you give us the breakdown of receivables as of today?
Rajiv Mittal
executiveRegarding receivables, I think Sandeep will be able to walk you through that. And just keep in mind one thing: our receivables have not increased over 2 terms — particularly the billed receivables, which are more or less in that same range — and Sandeep has already explained how our working capital has come down. So basically, I think he can provide you with the detailed numbers.
Sandeep Agrawal
executiveSo receivables stood at roughly INR 1,548 crores as of 31st December. And back in March, we also had around INR 1,500 crores — about INR 20 crores, INR 30 crores, that was the receivables level. So we're pretty much at the same level.
Mohit Kumar
analystRegarding the breakup, sir, is it possible to do that on a plant-by-plant basis?
Sandeep Agrawal
executiveOn a plant-by-plant basis? I mean, when it comes to each plant, we'll get that information to you after the call.
Mohit Kumar
analystWhere does that big amount sit? Where are those, like APGENCO and all of them — you know, those large amounts?
Sandeep Agrawal
executivePlease reach out to us. We will certainly send you those details.
Mohit Kumar
analystJust one final question, sir. Regarding this Kankarbagh-Digha, what timeline do you have for getting the project finished?
Rajiv Mittal
executiveSo there are 2 phases to this. The first is a DBO contract worth roughly INR 1,000 crores. Then there's a HAM component of about INR 200 crores. The DBO runs 3 years, while the HAM project takes a bit more than 24 months.
Operator
operator<<operator_script>> The following question comes from Kirthi Jain, who is on the line from Sundaram Mutual Fund.
Kirthi Jain
analystSir, to start, congratulations on the better margin performance — congratulations on that first of all.
Rajiv Mittal
executiveAppreciate it.
Kirthi Jain
analystSir, your press release mentioned that we've managed some cost reductions in the Europe region. So how large is that cost curtailment? And how much further can you bring it down? On a quarterly basis, or over 12 months, how much more can you reduce it?
Rajiv Mittal
executiveLook, I think Sandeep will cover the figures. But broadly, Kirthi, there's nothing really new here. We've been doing this for years, since it all comes down to performing the work where we've got the right resources and the right cost structure. Now, over time, most of our projects in the Middle East and Africa are being executed out of Europe. So naturally, I think we have increasingly more people locally and fewer and fewer at the center, such as in Vienna and so on. So naturally, when you cut back on staff, particularly noncore people — those who aren't project managers, process engineers, and technologists — we can reduce them in Vienna and add more in local areas such as Africa or the Middle East. Naturally, costs will come down. But when it comes to the exact figures, I'll leave that to Sandeep to give you.
Sandeep Agrawal
executiveSo across the 9-month period, we managed to bring down total cost at the Europe level by roughly, let's say, EUR 1.5 million, and on a full-year basis, maybe another EUR 300,000 to EUR 400,000 could come on top. In percentage terms, then, that's roughly 8%, 8.5%.
Kirthi Jain
analystSo that's EUR 2 million in total, correct, sir?
Sandeep Agrawal
executiveOn a full-year basis, yes. At present, that figure stands at roughly EUR 1.5 million.
Kirthi Jain
analystAlso, how much are we able to bring, sir? Something like...
Sandeep Agrawal
executiveBeyond that, it really hinges on the situation. As I said before, you need to extrapolate your figures. So...
Kirthi Jain
analystAlright. Sir, regarding the O&M share — say, now that the NCR contract deal has been signed — when do we expect execution to begin? And when do you expect margins to improve further from here?
Rajiv Mittal
executiveAs I mentioned, regarding just the contracts, we've already begun taking over starting mid-December, both Agra and Ghaziabad, more or less on the assets that we've taken over. So I think building will start now. So within this quarter itself, you'll see a good amount of building activity during this quarter. And for — going forward, this 10 years, we hold this contract. It will be an annuity model. Month-on-month, we'll build and collect the cash.
Kirthi Jain
analystOkay. Alright, so — sir, looking ahead to next year, how do you see the order flow pipeline shaping up, sir, for Chennai and Mumbai?
Rajiv Mittal
executiveYes. Kirthi, as we mentioned, we already have sufficient orders to cover revenue for the next 3 years. That means we will be quite selective in this market, just as we have been previously. We will pursue only those orders where funding is firmly secured. In practice, that means concentrating solely on projects funded by the central government, ones backed by a sovereign guarantee such as the Namami Gange project, or projects with multilateral funding, which is where our focus sits right now. So nearly 95% of all large projects are either multilaterally funded or central government funded, and that share will keep rising. That will guide how we make our selections, and we will also maintain a blend of projects across India and internationally.
Operator
operator<<operator_script>> Our following question comes from Priyankar Biswas, who is on the line from Nomura.
Priyankar Biswas
analystCongratulations on the strong results this time around. So my question is this: when we were talking about that Tecpro resolution, it appears there has been some kind of High Court judgment. So what exactly does that High Court judgment involve? Could you expand on that for us?
Rajiv Mittal
executiveThat point I made in my speech — perhaps you didn't catch it. There's a High Court judgment, and in it Tecpro was attempting to launch arbitration proceedings against our client, TSGENCO. Along with TSGENCO and ourselves, we filed an appeal in the Supreme Court. Right at the outset, they placed a stake on that, and the process is ongoing. The goal is to quash this arbitration requirement that Tecpro initiated, and our understanding is that within the next 1 or 2 sittings it will be quashed, so that we can recover our money.
Priyankar Biswas
analystAnd sir, regarding those O&M projects you mentioned — that's One City – One Operator — so once things are in steady state, what might the monthly billing be?
Rajiv Mittal
executiveSo it's pretty much around INR 12 crores or so, roughly, that'll be the monthly billing.
Priyankar Biswas
analystAll right. Do you have any detail on what the margin profile would look like here? I mean, I get that the overall margin profile at present sits at roughly 8.5% to 9%. So for this, when could it reach that comparable level?
Rajiv Mittal
executiveYou're aware that O&M margins always beat this level. Still, we'd rather not bring that up here. But O&M margins will definitely be stronger than our usual EPC margins, or the margins at the company level. We expect much better performance from these projects.
Priyankar Biswas
analystNo, sir. What I meant is that I'm approaching this more from an FY '21 or '22 standpoint. So I'm basically trying to gauge how much margin improvement we might see. That's what I was hoping to assess.
Rajiv Mittal
executiveLook, our other O&M business is something you've already seen. At least you're able to see the O&M business we operate today, and at a minimum we should take it at that level. And should you want anything beyond that, please reach out to our team. On a one-to-one basis, they'll be able to provide you with more detailed information.
Priyankar Biswas
analystSir, my final question concerns the fourth quarter. Which projects do you see delivering that INR 1,000-crore-plus revenue? I mean, which projects are going to drive it?
Rajiv Mittal
executiveLook, clearly the big-ticket items are going to be the large projects—and if you look at our investor presentation, we've already shown you a few of the major contracts sitting in our order book. One of them, the one we were just discussing, Agra and Ghaziabad—that alone should bring in at least INR 150 crores. Then there's Kankarbagh and Digha. We'll begin with the DBO portion itself, then move on to HAM, and after that we'll go to our MARAFIQ Jubail projects. And KMDA is expected to reach financial closure this time around. HMEL will go through. Dangote will go through. Jajmau will keep going. MRPL ought to come through. And Polgahawela in Sri Lanka should keep delivering solid revenues for us.
Operator
operatorOur next question comes from Siddharth Rajpurohit of JHP Securities.
Siddharth Rajpurohit
analystNice work on the consistent figures. Could you give us some detail on the HAM projects we hold? How much equity in total is needed for those, and what about the strategic investor we were seeking?
Rajiv Mittal
executiveSo essentially, from the time we started out close to 25 years ago, this company has operated as an asset-light business. We've mentioned this previously, and we'll keep saying it — you can note it down — that we will remain an asset-light company. So every required step has been taken to get the debt and equity partner secured; from the sheets, we've finalized things. We're now waiting on our customer to satisfy certain conditions precedent. The moment that occurs — and we expect it within the next month — we should have it, and we will reach financial closure on this project.
Siddharth Rajpurohit
analystRight. So we already had one investor lined up for...
Rajiv Mittal
executiveYeah, yeah.
Siddharth Rajpurohit
analystStrategic investor here. Sir, could you tell us what the equity investments would be, and how they'd be split across the next 2 years?
Rajiv Mittal
executiveLook, at this point I can say it won't matter much at all. The share of equity investment on our side is going to be quite small, and those are details we can walk you through one-to-one, but our equity investments will be quite small.
Siddharth Rajpurohit
analystAll right, sir. And sir, what would our sustainable EBITDA margin be?
Rajiv Mittal
executiveAt minimum, double digits.
Siddharth Rajpurohit
analystDouble digits. Excellent, sir. Excellent, sir. Well done, and wishing you all the best, sir.
Operator
operatorOur following question comes from Kaushik Poddar, who is calling in from KB Capital Markets.
Kaushik Poddar
analystDuring your presentation, you mentioned that debt is being reduced. Could you share those figures with me one more time? That's question A. Then for question B: at what point do you expect your debt — you're going to be completely free of debt — when do you see yourself net debt-free?
Rajiv Mittal
executiveHere's the direction we're heading in, Kaushik. On the specifics, I'll hand things over to Sandeep. But here's what we know: thanks to APGENCO, for almost more than 20 years, we operated with no debt at all. Working capital needs were quite modest. Every bit of growth this company has delivered came without raising a single rupee from the market. And we've taken on no borrowings either. Our debt-to-equity ratio sits very low. Once APGENCO was executed, our debt levels rose. Still, as new projects move through execution, I'm confident it's just a question of time — perhaps a couple of years — before we manage to reduce that debt. As for the precise figures, I'll let Sandeep provide those to you.
Kaushik Poddar
analystSure, if he’s able to hand that over to me.
Sandeep Agrawal
executiveRegarding net debt, as I noted, we currently stand at INR 285 crores, compared with INR 433 crores in March.
Operator
operatorOur next question comes from Dhavan Shah, who is on the line from ICICI Securities.
Dhavan Shah
analystOkay, so my question relates to the other expenditure line. I believe that in the stand-alone account, other expenditure is roughly INR 33-odd crores, while on a consolidated basis it's about INR 26-odd crores. Could you explain what accounts for the gap between those 2? And regarding the ideal provision you've recorded in the stand-alone accounts, can you tell us the amount?
Rajiv Mittal
executiveGive me just 1 minute — I think we're just pulling out the sheet.
Sandeep Agrawal
executiveThe key gap between the stand-alone and group figures for other expenditure comes largely from a reversal of certain provisions for doubtful debts at the Europe level — meaning outside India. That's what brought the numbers down. Apart from that, everything is consistent. And within India, we've made provisions for our projects consistent with our ECL policy. That's the main variance you're seeing at this point.
Dhavan Shah
analystAt the subsidiary level, the provision comes to roughly INR 7.5-odd crores, and the whole...
Sandeep Agrawal
executiveYeah, that's about right.
Dhavan Shah
analystAll right. From what we calculate, roughly INR 200-odd crores appears to be sitting on the receivables side. You said cash flow generation came to about INR 187-odd crores, so could you share what cash flow from operating activities was before working capital changes? You also referred to the working capital changes, so that would be useful too. And is there any CFI as well — could you give us those 2 numbers on a 9-month basis?
Sandeep Agrawal
executiveI believe you're referring to the company's cash flow. So excluding working capital changes, it's essentially just EBITDA. Regarding the operating cash flow figure, I already mentioned during my call that we generated roughly INR 180-odd crores at the operating level, which comes after working capital changes; and approximately INR 143 crores as free cash flow, which went toward reducing borrowings.
Operator
operatorLadies and gentlemen, that wraps up our question-and-answer session. At this point, I'll turn the conference over to Mr. Rajiv Mittal, who has some closing remarks for us. Sir, the floor is yours.
Rajiv Mittal
executiveThanks to all of you for joining us on this Q3 FY '20 earnings call. The analyst presentation has been posted on our website. Should you have any additional questions, you can reach out to Stellar IR Advisors — our investor adviser headquartered in Mumbai — or you're welcome to contact us directly. Thanks again.
Operator
operatorMuch appreciated, sir. Everyone, that brings this conference call to a close on behalf of VA TECH WABAG LIMITED. We’re grateful you could be with us, and at this point you’re free to hang up your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete VA Tech Wabag Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to VA Tech Wabag Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in VA Tech Wabag Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.