Vardhman Special Steels Limited (VSSL) Earnings Call Transcript & Summary
July 23, 2026
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to the Q1 FY '27 Earnings Conference Call of Vardhman Special Steels Limited. This conference call may contain forward-looking statements about the company, which are based on the beliefs, opinions and expectations of the company as on date of this call. These statements are not the guarantee of future performance and involve risks and uncertainties that are difficult to predict. [Operator Instructions] Please note that this call is being recorded. I now hand the conference over to Mr. Sachit Jain, Chairman and Managing Director, Vardhman Special Steels Limited. Thank you, and over to you, sir.
Sachit Jain
executiveThank you so much. Good morning, ladies and gentlemen. Thank you very much for showing an interest in a company and being with us that are here today. We closed the good quarter. And overall, so the highlights of the quarter have been: first, of course, we signed the technical intent agreement for the forging units with IT steel Japan. So the forging project is going on as scheduled. And it looks like this project cost is going to be a bit lower than what we had estimated. And we'll update once we have a fix on the numbers. But clearly, the project cost will be less than what we had estimated. As far as this quarter is concerned, volumes have been good and price revisions have taken place because costs have gone up. Some prices have been agreed, some are in the process of agreeing, meaning the OE have agreed to a particular amount, but it's likely to increase in price because other companies have not expected that kind of increase. Anyway, that will happen when it happens. Demand scenario is good. We are, in fact, finding it difficult to meet the requirements of the customers. So we are scrambling how we can make sure that we're able to increase capacity further. We have applied to the Environment Ministry for approval to capacity to 316,000 tonnes. But that would happen when it will happen. Meanwhile, some of the other things that we have been doing is the new reinforcing stabilized. New SDN will be commissioned by September, October of this year. And new commissioned by September, October of this year. After this, the bottlenecks in our small flow of production will get removed. Currently, we continue to have pile up of material that is very, at the customer want, but because of lack of testing capacity you're not able to go through. Even dealing, we need to get some dealing but you have done a job work from outside. All those things would come in-house and we've been able to improve the product mix and quality of sales April 2nd half of this year. Solar plant, we've got a full quarter of savings we've had INR 2.3 crore units this quarter and roughly 43% of our total power consumption is coming from solar. There have been further changes in the government policy, which means we can enhance the solar project. We expect it about a year or 1.5 years' time, may be going ahead and we'll be increasing the capacity by almost 50% of our solar plant. So that will add to the bottom line and to reduce the carbon footprint. Already, our carbon footprint is 0.5. So it answers as the best most the companies in terms of carbon footprint and approvals. So there is -- there isn't any other company which has needed us in carbon footprint, it has the comes. This enables us to the very strong position for this year. Overall, EBITDA numbers are within our range of 8% to 11% level. We would like to remove part of the EBITDA for your calculation purposes because some of the EBITDA and other income is from the earnings we have got from the surplus front of change have we got in many markets. That is really not business in constantly have removed at that and calculation. And if we remove that, our EBITDA per tonne for this quarter comes to INR 1,700. So I'm getting this confidence that for next year, we can improve our range. Today our range -- but next year, we should be able to increase the rate for 1. So we can see profitability improving and give a result of cost reductions and bigger production fixed cost being spread over a bigger volume. That's all for me in the opening remarks. One last thing. As far as the new steel plant discussion, we are partly reconcerning the plant to reduce carbon footprint further and improve energy efficiency. So things were scrapping, which was not a site and some other equipment that we had not anticipated earlier, including testing needs, there we had planed only 1 continuous testing line for the new brand. But seeing the way market is changing and demand for continuous testing in automatic testing lines, we will have to need more -- need to add more lines, which means the project cost is to increase as well as the capacity and protect at this plant. So again, details are still being worked out. I think by next Board meeting, they will be able to have a tier picture and will present a refined project with increased capacity and try to keep cost per tonne similar to where we have indicated, maybe a little higher because of Iran war, metals have gone up by way as well as rupee depreciated. So the cost of pressure is going to be also based on. So those are the work out, and we will have a better estimate in the next quarter. As of now, we are still on track to commission the project financial year '25-'26. That's all from me for now opening remarks. Thing to add some numbers and then we can have a -- thank you.
Sanjeev Singla
executiveGood morning, ladies and gentlemen. The -- on the numbers for the quarter, this quarter we have achieved 59,000 tonnes of sales higher than funding part of last year by 6.5%. And revenue from divisions is at INR 486 crores, higher by 12%. So a combination of growth. One is because of higher volumes and secondly, increase in sale prices. Our EBITDA this quarter is for the quarter ever, INR 68 crores per quarter. And INR 41 crores in the PAT. Overall, EBITDA, INR 7,650 per tonne. So air -- and over that in this quarter as against wastewater and INR 20 crores in the corresponding quarter of last year. And now we can open for the question answer session.
Operator
operator[Operator Instructions] The first question is from the line of Sharan Singh from Capital Arc.
Unknown Analyst
analystCongratulations on the good side of numbers. and I wouldn't ask that we had projected that our revenue would grow in exports -- could you please quantify how much the exports were in this quarter.
Sachit Jain
executiveWe don't hear that part at your question, please? So.
Unknown Analyst
analystWe had projected that our core sales on areas you put a count of our sales was in export?
Sanjeev Singla
executiveSales and exports, how much is exports? So export is still accounting for about -- and another 5% is going as indirect exports to -- which is going to 5G through the trading arm in India.
Sachit Jain
executiveSo the finding is that our estimates of direct exports of steel of. But more and more customers are wanting to buy from India, but they are wanting to buy components and post products from India. So a larger part of our business is a lot of our customers are exporting products to Europe and the U.S. So what we will start doing, I think, is that to the valid point the question you raised, from next quarter, we try to calculate an estimate that how much of our product is actually getting indirectly exported out of India is competence.
Unknown Analyst
analystThat's very helpful. And sir, I had another question. So with the partnership with IT, could you quantify how much of the business is like -- what is the business concentration per client? Because Toyota is a partner. Is this cost growth in our...
Sachit Jain
executiveBusiness we are very well diversified across customers. But our increased focus as we go forward, the concentration with Maruti and the customer will be our target. If we're able to achieve that, that's a separate issue. But we will try to continuously increase business with Maruti more than as a bigger share of our customers. As of now, it's a small percentage. That's about 10%. So we don't have any concentration risk.
Unknown Analyst
analystOkay, sir. And sir, if I can ask another question.
Sachit Jain
executivePlease come back because there's others on the line.
Operator
operatorThe next question is from the line of [indiscernible].
Unknown Analyst
analystTwo questions. One is -- and I joined late, so it is at cost of repetition, I'm sorry, then the status of the expansion of the existing plant from 3% to 3.6%, if you can share any update on that? And second is on the land acquisition for the 5 million plan that we are planning.
Sachit Jain
executiveSo the new plant is 5 lakh tonnes, not file we will get into big dry territory, we have no plans to be overall is a big, big, big for the a small area. So land is in the last stage is getting finalized, and machinery goes through the last year are getting finalized. So hopefully, by August end or latest by mid-September, we should be able to finalize leveraging.
Unknown Analyst
analystGot it. And on the EC application from 3% to 3.6%.
Sachit Jain
executiveWe made the application. And so on probability next 3, 4 months, we should get the approval. I think the -- but again, you haven't got until you have got it. So interest gross till that time will be close to our final productive capacity because we never imagine even in a richness level. So I must have publicly thanked my team who have done great work is figuring out how to keep improving productivity to reach this level. Now all this is helping us in plant -- the planning of this plan. As I said, what was to be a 5 lakh ton plant is going to be significantly bigger than that. Of course, we have a base of more investments in that. But -- and cost per ton is going to be lower than what we estimated in the new pro once we have better estimates next quarter than happiness.
Operator
operator[Operator Instructions] The next question is from the line of Anand Kumar Sharma, Investor.
Unknown Attendee
attendeeCongrats for the great set of numbers. Sir, my question is regarding this net project 5 projects while you have said that by first quarter, we will be able to start with the production of this forging unit. And what will be the diminution of the cost, you can you explain -- give some light on that? And what are the other projects apart from this sporting project, what are the other products -- what are the other products?
Sachit Jain
executiveFor project is likely to get commissioned by last quarter of '27, '28. And then to fill up the project, the plant will take 6 months to 1 year because it's a totally new product. Customers need to come at CD plant and then approve it and then business will start coming. So revenue for that will start coming from the year -- maybe in the end of '29. Project cost, as I said, lower than estimated, and we have been able to negotiate better terms and some equipment that we have seen equipment, we are able to find India substitutes for that. And so overall, those costs are being estimated. And in the next 3 months, we next quarter will have a far better grip of the total savings. But as of now, we can say there is -- from this INR 475 crores that we had estimated, there is a substantial savings from that. Saving is more than 10%.
Unknown Attendee
attendeeSir, question is regarding the expansion in the grid for that. When you expect that to start command lines?
Sachit Jain
executiveNew steel plant, we expect to start in the -- by end of '29-'30. So 6 to 8 months to stabilize in and '30, '31, we'll start getting revenues from them.
Unknown Attendee
attendeeIs it is a new senior steel plant?
Sachit Jain
executiveThis is a new -- just in capacity expansion in the gifting capacity, the 3 lakh to 6. Once we get the approval, only then we will have to invest some money. So that will take some time. But until we get the approval, we can do nothing.
Sanjeev Singla
executiveJust to add that for the current year, we don't have any capacity constraint because whatever mutants are there for the current year. So we have enough license capacity. And once this approval comes, so it will be helpful in the next year.
Operator
operator[Operator Instructions] The next question is from the line of Deepak [indiscernible] Capital.
Unknown Analyst
analystI just wanted to understand now you mentioned you don't have any capacity constraint this year. So what's the volume growth you are targeting for 2027?
Sachit Jain
executiveThis year we are targeting about 255,000 tonnes for this year. Still the 270.
Unknown Analyst
analyst270. Okay. Okay. So I mean, in terms of growth, we are still quite nominal, right? I mean the target in terms of growth for FY '27 itself, it's not 7%, 8% bol. So what will drive our revenue growth. Will it be more value addition? So how should 1 look at revenue growth?
Sachit Jain
executiveSo I think, see, what we are looking at is we do not automotive. So the whole category of nonautomotive there were not interesting earlier. We didn't have the capacity to, we do not have a tic capability, internal equipment. So linked casting is move or any of these products. And in the casting something that we plan to establish the plant by third quarter of this year. And by fourth quarter, we hope to stabilize. So this year, we would have established that stabilize the casting. Now we intend to get into die steel. India today imports INR 1,000 crores worth of die steels. So that's a big area for us to grow into. So that is tight. Railways the big for axis, there's a big demand for steel for that. Windmill shafts there's a big demand out of it gets imported. So we have been going in or not able to import substitution, earlier we didn't have that capability. So by end of this year, we will have big capability. So we will start a second engine of growth. Today, we have only automotive steel at a engine Indian of growth. Tomorrow, we will have a second engine, which is not automotive steel. And once the 4 plant counter, then we have third engine of crores. And the fourth engine growth will come up -- that will come up maybe 1.5 years down the line, and we start working towards aerospace and steel for nuclear plant and so on. So that is a fourth lever of growth, which will take a few years for the gear is the thinking of going ahead. So just so we are constrained but our capacity 3 lakh tonnes, which is the license capacity. We can't go more than that. So we can keep saying that you are very conservative on only 78%, and that is our capacity, we can't promote that. We are also examining can we get imports from outside and roll it outside, across job work and develop that market. So we've been able to find a credible source and because we have to have complete supply chain for that. So if we are able to do that, and then we have expansive growth again. So meanwhile, what we will do is if we don't have growth possibility that we work on internal, how to keep improving margins and better product mix. Meanwhile, the new plant will come up. So once the new plant comes up, then again, then there is mine growth possibility.
Unknown Analyst
analystThat's very helpful, sir. And my second question is on your Japanese tie up. I mean we have done this. So what sort of potential is there? Can you throw some more light how we are looking at the tie-ups that we have done?
Sanjeev Singla
executiveSo for example, approval for Toyota, which has global approval. We got because of that. The approval for the localizing more customer like Maruti they're getting because of our partners. Then there are internal improvement in terms of overall quality, safety, assuming the other improvements that are happening. On India is expanding. DKM is expanding with a new plant in Aurangabad. So that from the public side. So anyway, the earlier -- so with the new plant coming up, we are looking at us for more steel because they are the only gene -- some sorry where very clearly, they need more green steel. We are the only company which can provide green steel to all the approvals. So as green steel becomes more and more important, we become the only player base provide that. And with our expansion coming up, we will be very well placed. And most companies have targets by 2030 to have a large part of Grantee coming in. Yes. And separate is a -- so still -- and I'm really confident we'll get this approval. But again, as in have not got this approval, we don't have it.
Operator
operatorThe next question is from the line of [indiscernible].
Unknown Analyst
analystSir, a couple of clarifications. Sir, in the opening remarks, you mentioned that the greenfield plant looking to increase the capacity from 5 lakh tonnes. And because of infection metals and depreciation or cost willing, -- is this the right understanding?
Sachit Jain
executiveThat's right.
Unknown Analyst
analystOkay. Okay. Sure. And sir, you mentioned that FY '20, you'll be increasing the EBITDA per tonne guidance to 110 this year to 8,000 to 12,000. So can you quantify that or can you give me a color what will be the key drivers for this increase INR 5,000 per tonne.
Sachit Jain
executiveThe key drivers are 3. First, that we will have bigger production and therefore, the fixed cost will be spread over a bigger volume Two, there are operating costs that have come down and that is further coming down as we go ahead. We can see all those things happening as we go on. Third will be -- we still have job work and outside processing going on, which will start coming down from second quarter partly no, not a quarter -- third quarter do you see this coming down. Okay. Okay. So these are. And the fourth lever will be -- in a year's time, roughly, we have to see -- we have not given an exact forecast of where the new solar plant will come up. So when the new solar plant concerns, again, there'll be cost savings based on the.
Unknown Analyst
analystOkay. So this is just a downfield expansion on the solar plant which we have right now with similar cost savings?
Sachit Jain
executiveNo, because now the government has changed the rules, then not solar panel, the sales the expert panels are locally made the sales have to be also locally made. So the most of balance is now higher than. So the savings on account of the solar will be lower than in the first 3 years in.
Unknown Analyst
analystAnd sir, just 1 last question from my end. We are working with the European OEM to supply materials. Any update on that?
Sachit Jain
executiveI don't have an exact update, but that should happen by later part of this financial year.
Unknown Analyst
analystOkay. So we expect to start the commercial supply to them in H2?
Sanjeev Singla
executiveThe samples have gone all work is going on track.
Operator
operatorThe next question is from the line of [indiscernible].
Unknown Analyst
analystCongratulations on good set of I just wanted to know how does this EBITDA per ton drives into your company within the range given -- and what makes you the change of range this time? And what's the outlook going ahead?
Sachit Jain
executiveSo while we are -- we stick with the ranges because we deal with the auto OEs and the auto more changed the prices upwards or downwards based on not remit. So because of cost, raw material cost goes up, therefore, they would increase the price of the speed -- so that gives us a range. We remain protected within average. And they believe the rates get bumped up or lower depending on market circumstances. In addition to that, as we said earlier, with an increased production cost per tonne comes down with the current modernization that we have done current costs down, yields have improved. We have already said that earlier, but the new rating furnace, yields have improved and they have improved. Then outsourcing that we are doing, the job that we are doing that is going to come down. So these other factors and that gives us the confidence. And then with the improved solar plant coming up, that will add further. Once the solar plant is committed, then you would like to change the range to 9% to 12% rather than INR 8 crore. So for next year, it is -- and I hope all goes with the year after that, we 9% to 12%. Then the other kicker that's going to come in once we are able to establish our tight steels. And there we see these are all high-margin products. very difficult to make. Unfortunately, for us, -- is our partners, if they make it telcos. So it is very, very important for Dates to have a foreign know-how -- and we have our partners, IC, who know this business and who make -- they are the largest 4G company in Japan. They have about 50,000 or 70,000 tons of forging in Japan. They are about 50% market share in Japan. And they use their own diesel is therefore at testing in their own house. I know how is going to get us.
Unknown Analyst
analystGot it. And for our new come we've been in the plant what are the next steps to check, let's say, a strong multiyear perspective?
Sachit Jain
executiveTo track will be but has a land second is placing orders. Third is status of enamels. There is progress on the plant. Unlike a lot of problems for us because, one, we already have a reasonable funding available with us already cash has come in. And second, sometime next year, depending on when we need the funds, we will be doing a capital raising for the large shareholders, the largest shareholders, on Group and I they have given their commitments for putting it as much capital as required. And then we are also in touch with certain large institutions. There is an appetite to put money in the company. So creating ATP is not a problem. And then give obvious tax with banks to raise debt and also not a problem. So funding is not a problem. And lastly, Punjab government we detect this plant is very muticore. So government support is also fully assured.
Operator
operatorThe next question is from the line of Gagan Shaw, an Investor.
Unknown Attendee
attendeeJust 1 -- most of my question such 1 clarification. So you said the brownfield capacity will require the environmental -- so when we -- let's say we come by next quarter or 3, 4 months -- so what will be the ramp up to -- for the revenue to come kick in?
Sachit Jain
executiveSo if the approval on it, if approval comes in that we will up the sales targets for next year from we will come up to something like INR 290 because we can improve production up to a point without any further CapEx. Beyond that, we will need CapEx. So moment we want to finalize everything for the new CapEx and sign it immediately once the approval comes, and it will be roughly a bit over a year for new CapEx to come in. So we should be able to reach 330, 340 in the year '29,'30.
Unknown Attendee
attendeeOkay. And also, you mentioned that you're looking at the nonautomotive areas and for this year also. So should the potential upside also coming from there.
Sachit Jain
executiveTo just give you an idea, diesel prices are currently, our average prices are about 35,000 a tonne. The diesels are about INR 2.5 lakh tonne -- non-SR. And as we get into ESR, if they cross 3.5, 4 mtpa tonne. The 1 is the small but high is high. Of course, there's a lot of heat treatment and you need the pressing and other things or the other process we saw that the profit jump up that much. So the cost also has making. But the margins definitely are higher in those products and the sales value per tonne is higher.
Unknown Attendee
attendee[indiscernible]
Sachit Jain
executiveNo, no, we may want to start that process SP1 No, no. Again, I see -- so there is a forging plant tie steel is steel may be processed. For that, you're putting it in decost by second half of this year. In Q3, it would have been cast ready. Now then it is a stabilization process learning this thing and so on, actually take 6 months. So in the financial year '27-'28, we should have productivities as a regular or within the overall limit of seats.
Unknown Attendee
attendeeSo what it mix is going to improve.
Sachit Jain
executiveSo in terms of growth, the inflation bond will come up from FY '20 onwards, right? Over 27%, 28%, it will improve dramatically again, the sterling of sales that we have, that 7%, 8% kind of I think that limit has gone the. Just now we have a limit that we can't do more than that.
Operator
operatorThe next question is from the line of Anand [indiscernible] Capital.
Unknown Analyst
analystJust take the export volume guidance for -- and how much is towards 80 steel?
Sachit Jain
executiveExport volumes are small, it's about 7%. So don't track it specifically and it will not, we see very high at MAX, it will go up to about 10% -- so we -- as I said earlier during the call, we had earned have made a mistake in. At that time, it exports will take a bigger chunk. But today, we are finding we are not able to meet the requirements of our existing. So exports is not high on our agenda. Whatever is going -- growing organically will continue to grow a little bit. So out of this IT is about half -- yes. A little over half it over.
Unknown Analyst
analystSo go direct interactability 9% to 10%.
Sachit Jain
executiveThe numbers are small. I'm saying that no need for you drag that specifically is better that -- is that in half. So IT is about 40% of export. One thing, I think, which is a follow-up of all question that you raised -- so this nonautomotive which is better railways and so on. Initially, the volumes are going to be low. But what we are doing is we are creating and option that once a new plant comes up, then we have the capacity, once the business has been established and we have seeded the business to grow after that after becomes much easier, which will help us in filling up the capacity of the new plant faster. So that is the other objective of why we are pushing so hard on these products right now.
Operator
operatorThe next question is from the line of Devansh Gupta.
Unknown Analyst
analystJust 1 question in the deck, we have mentioned that for the long-term aerospace and everything else, it would be under a dedicated JV. So the question around that is there a shortlist of player identified? Or is that probably a key? And -- is it purely legal Tasman to be a separate subsidiary under a JV structure? Or is this a technology JV that we are like we have with the fixed take and they transfer the technology.
Sachit Jain
executiveWe are looking for more people. So this will be a non-JV the partner IT is strong in automotive steels. They're strong in stainless steels, including medical streams and as well as they are strong. So the volumes are not that great. because they use largely for external concern. For the advanced metal that we're looking at the Advanced Metals division, we will be looking for a partner outside. So that process of finding a partner will take its own time. It has been a couple of years, and we are heavy because, one, this is a slow process that finding the right partner with the right understanding is important. So this is just a directional thing that this is what we want to do in the future. For your forecast for the valuation, et cetera, we're getting a hang of the numbers test will be too small and the outer to think too much about them. But it will be a separate company. It will be a JV because nobody is going to pass their how with right the announcement.
Operator
operatorThe next question is from the line of [indiscernible].
Unknown Attendee
attendeeFirstly, sir, congratulations on great set of numbers. Most of the questions are answered already, but just a few questions. You mentioned that better realization came from OEM price revisions during the quarter -- could you help us understand whether these revisions are largely complete? Or should additional pricing benefits accrued during the year going forward?
Sachit Jain
executiveSo for Q2, we are a further prices, price increase? So Q2 process will happen later. Q1, the price settlement has been completed with the -- but some of the it is still not complete. So it is likely to rise higher. So the Q1 price was or the settlement is likely to rise higher. If that settles higher than our asks for Q2 will come down a bit. So Q2 numbers will not change. We said that profit of Q1 will be spilled over into Q2.
Unknown Attendee
attendeeOkay. Sir, another follow-up question. So following the commissioning of our block and reletting furnaces, -- what is the current rolling capacity utilization and beyond operational efficiencies, are there any bottlenecks remaining before the plant reaches its designated utilization?
Sachit Jain
executiveYes. So the rolling mill after the commissioning of the cost block and the rehearing furthest has reached its capacity of 3 lakh tonnes of input -- and the way our team is working, we are confident that we will hit 330,000 tonnes of capacity of info. We are already considered a 10% higher production right? Again, as I said, this is constrained by life today. So it's running at full capacity utilization.
Unknown Attendee
attendeeOkay. Sir, last from my end, on the forging and machining project with steel, could you elaborate on customer qualification time lines, expect commercial production immediately after commissioning? Or will there be a gradual ramp-up before meaningful contribution?
Sachit Jain
executiveRail ramp up. So we're already talking to customers and we're starting -- again, we are very lucky that because our partners are already there. We are already sending steel to getting it once from there. and getting sending to customers for approval. So at least the process approval will have happened. So those things will shorten the process of wrapping up. But it will take time because it's a new business where we learn this business and the customer have to get confidence also. They're confident because IT is already an expert in this area. But this area and this letter of be some of the products that you will do for the customers is lead. And it has benefits, which is why their customers are also excited, but they have to see this in action.
Unknown Attendee
attendeeCorrect, sir. So over the next 2 to 3 years, we can expect the margins to improve literally because of the cost optimization as well as value-added grades are evolving. Am I right in that?
Sachit Jain
executiveValue-added grades will be a very small chunk. But again, I'm repeating 3 areas which will lead to margin improvement. One is volume increase and the sort of fixed costs 2 is operational improvements and therefore, some operational costs coming down. And third is job work reducing and therefore, those costs coming down. And in addition, we'll be the fourth part of solar, which will happen a year from now. So it will be the second half of '28. Impact on the value-added products should start happening in '28, '29. So '28; 29, we should try to mode by our range from 8 to 12, we able to move the at, say, year on stent to 12%.
Operator
operatorThe next question is from the line of Samuel, Investor.
Unknown Attendee
attendeeI have 2 questions on the line. First 1 congratulations on the great numbers. So 2 questions on the line. One is that what is our current order book stability from OEM customers. And secondly, what is your outlook on steel utilization over the next 2 quarters?
Sachit Jain
executiveSo one, we never have a strong business, there is no system of a very strong order book. We are completely booked out and we are reducing orders. So I mean put a strong order book or visibility, we are currently having trouble meeting the requirements of our customers. The demand is very strong. And no customer is the long-term order that on to have this bench coming in the third quarter or fourth quarter or depends on their volumes. So the customers are steady. It is all repeat business, which comes in. And the next volume increase is going to come from the commercial production beginning for the import substitution for Maruti, which will happen -- start having the fourth quarter of the financial year. So that's what I can see.
Sanjeev Singla
executiveAnd on the valuation for the next 2, we are asking for the price increase from first of July.
Sachit Jain
executiveSo 1 will be higher prices.
Sanjeev Singla
executiveYes, serialization will be higher in Q2.
Sachit Jain
executiveAnd Q3 depends on how raw material prices continue to function. So more or less, as of now, we don't expect a major change. So it may be either same or a little bit or a little bit lower. But Q2, definitely, we expect it to increase in basis.
Operator
operatorAs there are no further questions from the participants, I hand the conference over to Mr. Jain for his closing comments. Over to you, sir.
Sachit Jain
executiveLadies and gentlemen, thank you, once again for continuing to be very strongly engaged. The kind of question your -- you've been asking us means that you have deep interest in our company, and you're forcing us to think and find out answers and be ready for your -- for next quarter when you come back again. Thank you so much, and we hope to continue to perform steadily and improve steadily.
Operator
operatorThank you. On behalf of Vardhman Special Steels, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Vardhman Special Steels Limited transcript — plus 252,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Vardhman Special Steels Limited earnings transcripts and 252,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.