ACME Solar Holdings Limited (ACMESOLAR) Earnings Call Transcript & Summary

November 4, 2025

National Stock Exchange of India IN Utilities Independent Power and Renewable Electricity Producers earnings 60 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and welcome to the ACME Solar Holdings Limited Q2 FY26 Earnings Conference Call. Please keep in mind that every participant line will be in listen-only mode, and you will have a chance to ask questions once the presentation wraps up. If you require assistance at any point during this call, just signal an operator by pressing star, then zero on your touch-tone phone. Kindly be aware that this conference is being recorded. I'll now turn the conference over to Mr. Rupesh Sankhe. Thank you, and over to you, sir.

Rupesh Sankhe

analyst
#2

Good afternoon, everybody. Speaking for Elara Securities, we're glad to have all of you join us for ACME Solar Holdings' Q2 FY2026 session. I'd like to take this chance to greet the ACME Solar leadership team joining us: Mr. Manoj Kumar Upadhyay, Chairman and Managing Director, and Mr. Indira, CFO.

Operator

operator
#3

My apologies for cutting in, Mr. Manoj, sir, but your voice is breaking up.

Manoj Upadhyay

executive
#4

Mr. Ankit Verma, who leads Corporate Finance, and Mr. Arun Chopra, who leads Finance and Accounts. Management will start us off with a short overview, and after that we'll open it up to questions. At this point I'll pass the call to Mr. Nikhil sir for his opening remarks. The floor is yours, sir.

Nikhil Dhingra

executive
#5

Thank you. Thank you, Manoj. And thanks to everyone for being with us today. I'm Nikhil Dhingra, CEO and Director on the board of the company. As Manoj said, I'm joined today by our Founder and Chairman, Mr. Manoj Upadhyay, Rajat Kumar Singh, our Group CFO, Ankit Verma, Head of Corporate Finance, and Arun Chopra, Head of Finance and Accounts. It's my pleasure to walk you through the highlights of our Q2 performance. Before we get into our performance, I'd like to briefly share some sector highlights. The renewable energy sector saw significant growth, with 35 GWs of new capacity added from January through October 2025, taking total installed renewable energy capacity, including hydro, to 247 GW. Thanks to this expansion, renewable sources contributed approximately 27% of India's total energy generation, a historic milestone for the sector. I'd also like to briefly touch on a few key regulatory updates that are instrumental in accelerating power demand and renewable energy installations. There has been a reduction in GST rates — a key reform by the government — on key solar and wind project equipment, from 12% to 5%, which directly impacts capital cost and enhances the viability of solar and wind projects, helping reduce the cost of power and, of course, increasing demand from a renewable perspective as compared to other sources of power.

Nikhil Dhingra

executive
#6

Next, the purchase obligations for renewable energy have been swapped out for a consumption obligation covering renewable energy, and a broader compliance base has been prescribed for designated consumers such as DISCOMs, Open Access, and Captive users. It lays out a progressive target for consumption so that a minimum of at least 43% RE consumption is reached by 2030. That, in turn, will have a positive effect on demand for renewable energy, in line with our 2030 renewable energy targets. Then, on the regulatory front, the CRC notified the Third Amendment of connectivity and DNA regulations, which matters a great deal to us, and in it the concept of solar and non-solar access was introduced so that battery energy storage systems can be accommodated in the grid. The purpose here is to handle the intermittent character of solar and wind power while keeping the grid stable. This amendment in particular permits battery energy storage systems to stall grid power for the use of existing connectivity infrastructure, which lets developers employ battery energy storage systems at their existing operational substations for merchant operations. And also, something very important: the Honorable Supreme Court, having taken note of around INR 1.5 lakh crore of regulatory assets, has directed every state regulatory commission and DISCOM to formulate time-bound roadmaps for liquidation of long-pending regulatory assets, and for outstanding regulatory assets to be liquidated within four years.

Nikhil Dhingra

executive
#7

That would introduce a lot of needed financial discipline into the way electricity tariffs get set. This ruling matters a great deal for India's regulatory environment, since it strengthens the statutory duty of regulatory commissions to make sure costs are recovered on time while keeping financial liability within the power distribution sector. Now, turning to how our company performed. During this quarter, our execution guidance for FY2026 called for commissioning 43 MW of renewable energy capacity, and we are on track to hit that. We have commissioned 378 MW of capacity to date, and the remaining 72 MW is at advanced stages of construction. We will most likely start in the early part of January with that. Beyond our earlier guidance, we intend to operate approximately 1 GW hour of battery energy storage system on a merchant basis starting from Q4 FY2026, which we expect to provide upside potential for annual EBITDA of around INR 170 crore, assuming a price difference of INR 5 between merchant power sales during peak hours and the cost of producing the same. With recent commissioning, our operational portfolio now stands at around 2,918 MWs, able to deliver annual steady-state project-level EBITDA of INR 2,025 crore-INR 2,075 crore, and an EBITDA yield of around 14%-15%.

Nikhil Dhingra

executive
#8

On the under-construction capacity side, the piece that's fueling our growth, we signed PPAs with Tata Power. This marks our first arrangement with a private utility — a private DISCOM. It covers 50 MW of FDRE, firm and dispatchable renewable energy, which in effect amounts to a battery of roughly 250 MW hour. On CapEx, it comes to about INR 10 crore per MW. We also signed 550 MW hour of standalone BESS projects with NHPC, located within Andhra Pradesh. Those two PPAs are now executed. With them, our total PPA-signed capacity reaches roughly 2.3 GWs, which we are in the process of executing. Over the quarter, we added new projects totaling 720 MW of capacity — made up of this 50 MW FDRE, whose PPA we managed to sign in good time, plus 670 MW of solar plus BESS — which pushes our under-construction portfolio to about 4.5 GWs, including the 2.3 GW of signed PPA capacity. Both of these solar and BESS projects — 220 MW RUMSL-Morena and 450 MW SGWEN — offer distinctive opportunities carrying strong strategic and financial merit, with a solid counterparty in place. To start with the 220 MW RUMSL-Morena Solar Park: this project was won at a competitive tariff of roughly INR 2.76 per unit, allowing four hours of peak supply along with two hours each in the morning and evening, while keeping maximum annual CO2 at 35%.

Nikhil Dhingra

executive
#9

The attractive tariff is backed by multiple cost efficiencies, among them the fact that ALCM does not apply, which means Chinese cells can be purchased under it. This was the last one to make that timeline. Lower GST rates — and again, this is the first one to capture those reduced GST rates. Free night charging from the DISCOM, which is also a first. In all our earlier PPAs, we were the ones bearing that charge. Here, the DISCOM provides free night charging, which at times carries a premium when serving morning peak demand, while the tariff stays the same on discharge and bundled infrastructure inside the solar park. All of that is part of this package, which makes execution easier and operation easier. With land and connectivity infrastructure at above 33 kV to be supplied by RUMZL, the project gains substantial CapEx savings. Also, there is an identified off-taker — in this case an off-taker that is very eager to sign the PPA as soon as possible. That is expected to speed up PPA signing. Taken together, these factors secure a strong risk-adjusted return for the project. On the analysis side, we estimate that once all project benefits are accounted for, the effective tariff for the bid should now come to roughly the equivalent of around INR 3.5 limit plus for a solar plus 2W configuration, delivering mid to high-teen risk-adjusted returns.

Nikhil Dhingra

executive
#10

Then second, the 450 MW SGWEN project with peak power that we won — roughly 2,200 MW hour of battery that we'll put in at INR 6.75. Again, this is a very attractive tariff. It involves supplying only during peak hours, four hours, to the off-taker. This is one of a new type of project that will definitely address demand, since the peak power deficit is a reality. Of course, the solar hour deficit no longer exists in most states, but a peak hour deficit does exist in most of the states. This addresses a problem that will attract more takers. We're seeing great demand for this project from various off-takers. We're very hopeful of signing this. SGWEN obtained consent from various buyers before winning the bid, which has been the situation now for all the upcoming bids. In this particular bid, solar generation will mainly be used to charge the battery, with surplus energy sold on the power exchange. Given the unique project design, the project is expected to deliver a strong EBITDA to CapEx yield of around 14%-15%, and strong counterparty demand is anticipated to drive early PPA signing. With these new wins, our total portfolio now stands at around 7,390 MW, including 13.5 GW hour of BESS capacity and 5,180 MW of PPA signed capacity.

Nikhil Dhingra

executive
#11

Additionally, during this quarter we've booked fresh orders for 2 GW hour BESS with suppliers around the world. That brings cumulative BESS orders to 5.1 GW hour as of today, and installation is anticipated to happen in phases beginning Q4 FY2026. As we mentioned in the prior quarter, we've now successfully commissioned the 10 MW hour pilot BESS facility at our IATS plant, which lets us evaluate how well it performs across various configurations and should assist us in lowering costs and boosting efficiency for our FDRE and BESS-rated projects. Turning now to our financial results, total revenue for this quarter came in at INR 601 crore, which represents a 104% rise year on year. One important thing to flag is that owing to commissioning happening a quarter early along with a delay in commissioning of one of the connectivity lines and the regulatory line, the 300 MW ACME SECI project is presently running under a temporary DNA/SCOA — essentially short-term open access. That said, the connectivity line is expected to be up and running by December, per repeated assurances from CTU and, naturally, confirmation at the very highest level. After that, the plant will move to LTOA, long-term open access, and reach its full revenue potential. EBITDA for the entire quarter landed at roughly INR 534 crore for us, once again higher by 180%, with an 89% margin versus 87% a year ago.

Nikhil Dhingra

executive
#12

PAT came in at INR 115 crore, and our PAT margin was roughly 19%. We're still keeping a tight focus on balance sheet discipline. Net operational debt to EBITDA is 4.3X, while net debt to net worth is 1.9X. On top of that, days of sales outstanding fell to a record low of 27 days, since central off-takers make up a bigger share of our operational portfolio — that's giving us substantial cash flows and earlier realization of revenues. Turning to capital optimization, we secured an interest rate cut of about 75 basis points on existing INR 2,080 crore of debt for our operational projects, thanks to the credit rating upgrade. In addition, one operational project was refinanced with INR 1,100 crore at an optimized interest rate of roughly 8.4%, and we expect that to come down further. On the greenfield front, we raised financing of about INR 7,000 crore this quarter for our 650 MW FDRE projects from SBI and REC, which will lower our cost on the ongoing greenfield rate, because we'll take a biased rate and then see what's possible with the bank financing. As for the credit rating, we had a very significant positive — ACME Solar has now been upgraded to AA.

Nikhil Dhingra

executive
#13

Both CRISIL and ICRA have assigned us an AA minus rating, and that's a really meaningful positive development for us in this quarter. On top of that, ICRA and CRISIL gave our 1,100 MW of operational projects an AA minus rating as well. So that's one thing that took place this quarter as part of the capital optimization efforts. Turning to operational metrics, to finish up, during quarter two we generated roughly 153.9 crore units, an increase of over 134% year on year. Our capacity utilization factor also rose to 24.1% from 22.2% a year ago, with plant and grid availability each coming in above 99%. With that said, I'll now open the floor for questions. We're happy to take them. Thanks a lot.

Operator

operator
#14

Thanks a lot. We're moving into the Q&A portion now. If you'd like to pose a question, you can hit star and one on your touchtone phone. Should you want to drop out of the queue, just press star and two. We ask that participants use their handsets when asking a question. Ladies and gentlemen, we'll pause briefly while the queue is put together. Our first question is from Mohit Kumar of ICICI Securities. Please go ahead.

Mohit Kumar

analyst
#15

Yes. Good afternoon, sir. Thanks for the opportunity. My first question is this: do you see any risk that projects without a signed PPA could be cancelled? And do you expect a few of the projects currently under LOA to get a PPA in the next couple of months?

Nikhil Dhingra

executive
#16

Correct. Yeah, Mohit. So the central government has definitely ramped up the pressure to get a decision made so that states sign those PPAs that are still pending. That's the reason bids have come in low over the last six months — the government wants to finish clearing up projects that already exist before moving on to fresh bids. On top of that, new bids now arrive with a pre-debug locked in so that PPA signing doesn't get extended, because from the government's standpoint, they want connectivity utilization realized. They want that utilization improved so that no connectivity sits unutilized any longer than necessary. Letting that happen wastes a national resource. As for our own signing, we've got attractive tariffs across hybrid and across FDRE. We have conversations underway at a point where either the consent letter is arriving or the project sits at board stage. You could say we have four counterparties, split almost equally, with all four of them. With a couple of those we're quite advanced. Naturally, with, let's say, one or two of them, we're not advanced. What's happening now, given this urgency, is that some of them will get signed sooner and some may get signed afterward.

Nikhil Dhingra

executive
#17

If a decision gets made, let's say, but our tariffs are appealing, so we stay confident, since the instruction is not to pursue the legacy PPAs that aren't attracting any buyers. That kind of conclusion of no demand—we aren't seeing it in any of our PPAs, that no state wants them. States do want them, but the process is a multi-step kind of process at the state level, where first the DISCOM gives approval and the regulatory commission gives approval. We're talking with all the REAs wherever we have one. Unfortunately, in our cases, demand exists from states. As soon as we get clarity on any of these, we will act—we have no negative confirmation from anyone that they aren't attracting buyers. We're personally in touch with most of the states as well. We aren't seeing any lack of uptake for, let's say, any of these PPAs, because the tariffs are competitive, as we mentioned. For some of them, the tariffs aren't matched. For instance, with the FDRE at 4-hour peak power, no tender has come up that has beaten that tariff, because we have across that entire spectrum.

Nikhil Dhingra

executive
#18

The reason the earlier projects have some appeal is that they come with a shorter timeline, one in which the ISTS waiver hasn't expired yet. Buyers gain an advantage from purchasing those, since any new bid would definitely require them to cover the full ISTS charges. On top of that, there's an ALCM benefit, given the substantial gap between Indian modules and Chinese cell modules. Those are the advantages that make it attractive. The catch now is simply that early decisions rest with the states, because with energy demand picking up as it is, we're hopeful that a few of the larger states will move early on this. That's the current status on PPA signing.

Mohit Kumar

analyst
#19

Right, got it. Moving to the second question about transmission problems. It appears transmission projects are running into quite a few difficulties when it comes to commissioning. What's your view on the risk to the project currently under construction that could push back our commissioning timeline?

Nikhil Dhingra

executive
#20

Sure. Sure. We look at this for every footprint, specifically the connectivity timelines for the substations where our projects are being developed. To give you a few examples: for the Fatehgarh substations, their SCOAs are in place, so we're able to evacuate power from the SCOA. If you look at Nemat, if you look at BCANET 3, all of them are arriving within the timeline, with a delay of at most one, two, three months. They all sit within the PPA. Take our Nemat plant, which we signed with Damodar Valley Corporation through NHPC. That one is actually coming up early, since Nemat connectivity is already operational. It comes down to which substation you allocate to that PPA and whether that substation is on schedule. What we do is ensure the PPAs already signed have our best connectivities, and those fall well within that PPA's timeline. The largest delay we're seeing is a quarter beyond the signed PPA dates. As an extra mechanism to boost our revenue, as we said earlier, we have brought the battery installations forward. That's a separate item, but it's something we're doing on top of this to raise revenue.

Nikhil Dhingra

executive
#21

On the connectivity side, looking at our PPA schedules, we aren't seeing slippage of more than a quarter against the connectivity that's been allotted. It also depends on whether you've chosen to allot connectivities that are running late and are using the full time the PPA permits, or whether you're aiming for early commissioning. Then there's the question of what inventory of connectivities each and every kind of player holds. For our part, we have a good amount of connectivity coming up at different points in 2026. That gives us considerable flexibility wherever needed. Some connectivities we've taken on a flexibility basis with lag and with bank guarantees, which let you distribute the connectivities across PPAs. Only a very small number of connectivities do we hold on a letter of award basis, which tends to lock you in. Through our allocation and our connectivity inventory, we've been able to handle it — so if delays arise, say, they get assigned to later PPAs.

Mohit Kumar

analyst
#22

Got it. Thanks, and best of luck to you. Thanks.

Nikhil Dhingra

executive
#23

Thanks so much.

Operator

operator
#24

Thanks. Our next question is from Balasubramaniam of Arihant Capital. Please go ahead.

Balasubramanian A

analyst
#25

Good afternoon, sir. I really appreciate the chance. And this tariff that's below average as well.

Operator

operator
#26

Mr. Balasubramaniam, I'm going to address you directly, but your voice keeps cutting out. Could you please pick up a handset when you speak?

Balasubramanian A

analyst
#27

Is that clear at this moment, madam?

Nikhil Dhingra

executive
#28

Correct.

Balasubramanian A

analyst
#29

Yeah. Sir, the weighted average tariff for what’s currently under construction stands at about INR 4.2 per kilowatt-hour, and that’s somewhat higher than the INR 3.4 per kilowatt-hour of the portfolio we operate today. Is this trend sustainable, particularly with the push from FDRE or BESS? Or do you expect some tariff compression once the renewable market matures and gets more competitive?

Manoj Upadhyay

executive
#30

Thank you for the question, sir or madam. Look, within renewables, since bidding is so dynamic, I'd ask that you consider return on capital employed, or EBITDA over revenue, or EBITDA over tariff as the measure — because with all these PPAs, say the peak power tariff of INR 6.75, it appears high from a top-line standpoint, yet the capital outlay is high as well. I wouldn't compare, I wouldn't take a weighted average of tariffs to judge whether everyone is moving upward, because a lot of batteries are needed there and a lot of solar is needed there to charge. The weighted average tariff can be misleading at times unless you make an adjustment for CapEx and unless you make an adjustment for what the component of it is, since each source either generates or stores. Wind, as you're aware, in some geographies produces a higher CUF where CapEx runs somewhat higher. The battery stores and captures the peak power benefit. Sure, the tariff has risen, but the PPA's configuration matters too. What are you providing there? Say in some place you have a lease-type project where you give lakh per MW of, say, INR 2.5 to 2.2 lakh per megawatt each month.

Manoj Upadhyay

executive
#31

The market has become a bit more varied, which affects how we run a weighted average tariff analysis when estimating revenue and CapEx, of course — but revenue ought to be viewed alongside CapEx. As for guidance, here's what we can tell you: any project we bid on will always carry a 14%-15% ROC rate. That's a commitment we genuinely intend to hold to. On tariff and revenue, my request is that you not view them on a standalone basis.

Balasubramanian A

analyst
#32

All right, sir. Regarding the BESS side, sir, I believe we currently have a 10 MW-hour pilot in operation, and it uses two distinct container configurations. What are the main lessons learned when it comes to efficiency — specifically round-trip losses, degradation rates, and how reliable the operation has been? The reason I ask is that previously we made the decision to import complete BESS containers, and that choice put reliability ahead of cost. I'd just like to hear the key learnings. Are there any long-term service agreements in place with our vendors, particularly around specific terms covering durations, performance guarantees, and degradation clauses?

Manoj Upadhyay

executive
#33

Right. Right. So, we have a combination of technical and contractual factors that let us essentially move the battery CapEx earlier, as we explained last time and the time before. On the contractual side, it lets us capture the arbitrage between peak power prices and the solar prices that prevail. You can charge using solar or the lower rates, then sell into the merchant market. That makes compelling business sense. Of course, the CapEx sits well within — in fact much below — the range we targeted when we bid for these projects. That makes the commercial case for getting the batteries early. On the technical side, we have of course been running battery operations within the group on the green ammonia side for four or five years now. Here we were trying to, let's say, work through the various combinations of the PCS, the battery management system, the inverters — how we can operate with a particular piece of equipment and without a particular piece of equipment. We are pleased to say we have managed to raise the efficiency. By efficiency, I mean lowering the CapEx while generating the same sort of energy.

Manoj Upadhyay

executive
#34

And so essentially, we’re getting the reliability in terms of the round-trip efficiency figures that we’ve contracted for, and in terms of the discharge rates that we’ve contracted and that we’ve purchased. All of these 10 MW-hour units have been built with some of the suppliers we’re going to be working with going forward. That lets us cut down the installation time as well, since we have these large batteries arriving starting early next month. It lets us shorten the installation time, understand any kind of surprises we might encounter with the different equipment, and also lower the bill of material for future projects. A few of the configurations we’ve tested let us bring down the CapEx for our ongoing projects where we haven’t yet ordered the various equipment. It’s been pretty successful. Of course, it will help us because in certain projects, you only need to charge batteries, so you have a bit more headroom. In certain projects, you’re installing batteries where solar is already in place, so that gives you less headroom. I can tell you, say, our Ramzal project, where we’re getting nighttime power from the customer — that gives us some added flexibility to try out this experiment.

Manoj Upadhyay

executive
#35

That depends on how the PPA is configured, since some of these tests we've completed can be applied there. Each one will be applied, and as and when that happens, it lets us strengthen our confidence in those configurations. As for the long-term agreement, as we said previously, we hold a 15-year long-term service agreement with the vendors we've contracted. Bet for. Naturally, we also pay them an annual maintenance fee, and they'll provide on-ground personnel, along with on-ground reserves, to guarantee the availability and the round-trip efficiency they've committed to. We've done the factory at both of our vendors. We've also carried out the factory test at the efficiency levels required prior to dispatch from the third party. They are in the rate and they are now getting.

Nikhil Dhingra

executive
#36

They’re in logistics, so they are on the way to arriving. Nitin, allow me to respond as well. My name is Manoj here. Let me give you one additional answer: we were testing the battery for the EMS requirement, where our aim was to see how the battery would perform under various discharge conditions—not only what is specified in the PPA, but also to support whether we need the battery for what is called ancillary support in the afternoon or in the morning for a short time. We were testing, and it was a very successful test that we did in two configurations. Both configurations helped us improve not only the long-term discharge but also very short-term discharge. That was the first. Second question, I think what you had is whether the round-trip efficiency is okay, what we have taken in the bid. Fortunately, we were able to improve by 4%-5% of the round-trip efficiency because of this configurational adjustment. What we wanted to achieve, I think, with these two golden containers—we call it golden containers because they come first, and we do the whole installation testing. With that, we are able to ascertain what we have bidded.

Nikhil Dhingra

executive
#37

And on top of that, a number of those gains that Nikhil brought up, we were able to realize them.

Balasubramanian A

analyst
#38

All right, sir. For my follow-up, I believe we've refinanced close to INR 1,100 crore at 8.4%. Does that carry a fixed rate or a floating one? What's the typical maturity on our debt? Do we face any meaningful bullet repayments coming due in the near term? And with interest rates expected to stay volatile, do we have a hedging approach in place?

Manoj Upadhyay

executive
#39

Okay, so every piece of debt we've refinanced carries an average tenure of 20 years, since that's the approach we've taken. On interest rates, we're effectively paying roughly 8%, as it's tied to an MCLR plus a spread of 10 basis points. That's the typical rate we're securing. Naturally, given that the rating upgrades have occurred, in this project where we've hit 8.4%, it's likely to come down to 8% shortly. That's the rate we're observing across all our refinancings for a double-A asset from bank financing. Were we to pursue bond financing, we might catch a somewhat better effective rate. Naturally, owing to the prepayment fees and owing to the short-term nature of mutual fund and financing, since typically mutual fund players are present only in the bond, insurance is currently not very heavily present for the long term. Infra-debt funds typically participate alongside banks in the long term only. We're able to capture them in the bank financing. 8% is a typical rate for all the refinance, and we're hopeful that we'll get all of our portfolio, whichever can be refinanced, to closer to that rate.

Manoj Upadhyay

executive
#40

That's a big plus on our side, since all of this is floating. On your second question, the reason it's floating is that we can take advantage of the downside in interest rates, the down cycle in rates. Naturally, we completed one refinancing in the last quarter, which we discussed with Bank of America. That one was on an NTD, so it was fixed at roughly 8.5%, which we got done last quarter. That one is unfixed. We keep a mix of fixed and floating. For some of the projects coming up for refinancing, we'll try to see whether we can obtain a longer-term bond, because a three-year tenor is something we can do, but we'll make a decision on that based on the economics, since it means you have to refinance at a shorter interval. As for repayments coming due, no payment lacks a refinancing sanction already in place. We have refinancing sanctions in place for everything that is coming up for refinance.

Balasubramanian A

analyst
#41

Understood, sir. Thanks.

Nikhil Dhingra

executive
#42

Thank you.

Operator

operator
#43

Thanks. Our next question is from Capen Jen at Avengers Park. Go ahead, please. Mr. Capen, we can't hear you. Hello. Hi. Good afternoon, sir. Can you hear me now?

Nikhil Dhingra

executive
#44

Yes, sir. Yeah. Thank you. Sir, this follows up on the first question. A media article stated that of the 93 GW of capacity awarded in FY 2024 and 2025, 42 GW remains unsigned, with BPF still awaiting signature. The plan is to cancel those awards and re-bid them. How do you see this affecting the industry, and what impact does it have on our projects? Is it only solar projects that would be cancelled, or are the complex and FDRE projects also at risk of cancellation? Right. Right. So you're correct. Basically, their focus is mainly on the solar projects that were bid. And that's because those bids happened quite a long time ago as well. And as you know, the government has issued guidelines that no project should come up without storage in a central bid, and that is no longer happening since storage is now a key element of all upcoming bids. Regarding the take-up of these capacities at the states, there has been considerable traction over the last three to six months around improvement in PPA signing. For instance, SECI has effectively around 6 to 6.5 GWs of PPA left, and the status with the others is also similar, so this 42 GW may have come down.

Nikhil Dhingra

executive
#45

I think if you look at certain figures, they would have declined. Another point is the framework within which these have been carried out — that too is sometimes quite — the states are also in favor of it, namely which plant is being developed on what schedule, which lets them decide whether to grant an IFTS waiver or not. When you examine it, these represent major commitments for the state. Every one of these projects will bring in at least $100 million or so in revenue if you look at the overall bid, and perhaps above $200 million in certain cases if you look at a one and a half to two gigawatt bid. Major decisions for the state. Naturally, the bids were completed quickly, and naturally, inventory clearance takes time. The government's mandate is for the states to reach a decision. If there's no demand, suppose someone says they don't want to purchase plain solar, correct? They essentially have no demand for plain solar since, if they had surplus solar in certain states, they would essentially — but certain states still have demand. You see, a few of the states are not meeting their own renewables targets, and they face some shortage.

Nikhil Dhingra

executive
#46

They’re examining certain bids in which batteries are called in their state at every substation. We’re fairly optimistic that buyers will be found. It’s a question of timing. It’s a question of what the government decides. My sense is that every REA will make its own choice regarding each PPA. It won’t be very uniform, like out of 40, 20 got canceled or anything like that. Fundamentally, for a government, the decision concerns not allowing the connectivity to be wasted. All of this arises from the standpoint of, suppose someone holds an LOA, the dates for that connectivity have lapsed, yet they are still clinging to that LOA and are not building the plant either. That’s a situation the government genuinely wants to prevent, as I read it. That’s what, most likely, things will move toward. Not exactly. Wherever discussions are underway, wherever there’s a chance of something materializing, I believe time will be granted. Wherever someone is setting up a plant in anticipation and there is reasonable progress toward constructing the plant, those will be permitted to proceed. That’s how we’re looking at it.

Nikhil Dhingra

executive
#47

Got it — just for the projects we’re building. I believe there are 2 solar projects that don’t yet have a PPA signed. The first is ACME Sigma Urja and the other is ACME Omega Urja. That’s 300 MW, with 1 tied to NTPC and 1 tied to SJVN. Where do those projects stand right now? 1 of them doesn’t appear in the presentation we have now. Sir, is there a risk these get cancelled?

Manoj Upadhyay

executive
#48

Regarding that NTPC project, I believe we mentioned a couple of months ago that it was carried out through a pooling arrangement with NTPC. I think we also made an announcement via the SOC exchanges. As for that project—since the Ministry of Projects has essentially canceled that pooling scheme, they had been pooling thermal together with renewables. NTPC was doing that itself at its own plant, but I think that matter is now under litigation with Bengal. That project is, naturally, the reason why. Understood.

Nikhil Dhingra

executive
#49

That particular scheme isn’t in place right now, and we had announced it a couple of months ago, but it’s a special case. The 2.52 with SJVN is under consideration, since it’s being considered with some states that need it because it offers the most competitive tariff when it comes to solar. The decision on how they use that solar is now up to the states. A few states have expressed interest. If you notice, you can basically track all these PPA matters through tariff filings. If you look at—right, Punjab, right? Punjab’s tariff filings before the various regulatory commissions. Understood. You’ll be able to find out which states have signed, and which states are at what tariffs. If you look at this specific solar side, you’ll look at Punjab, which recently bought 2 GWs of solar, right? They want—that shows they may want more. They’re putting it before the regulatory commission because it’s a multi-state process. Some states have some—like Punjab has a particular demand. Even in summer, they need peak power for their agricultural load. There are some states, specific states, that need that power. That’s why SJVN is trying.

Nikhil Dhingra

executive
#50

SJVN is examining this. Bids have been invited by certain states. Madhya Pradesh, for instance, was looking at it. They have issued the call and are submitting the tariff as well. What happens in some cases is that states conduct their own bidding. That depends on each individual state. I wouldn't characterize this as having a low probability. It could get signed. We need to pursue it, and it's a case-by-case, state-by-state matter. Understood. Just one final question, a bookkeeping one regarding CapEx. I believe we've spent roughly INR 14,000 crore during the first half. Our target was approximately INR 12,000 to INR 14,000 crore. Are we on schedule for that CapEx? Look, we have placed orders for batteries. As we mentioned, we've ordered about 5 GW of batteries. LTs have been opened. You cannot reflect CapEx on the balance sheet before the goods actually arrive. It is extremely, extremely lumpy. Once the batteries come in, you'll see this CapEx double or rise, since a battery typically costs around INR 10,000,000 or so once fully installed, in CapEx terms. INR 5,000 crore of CapEx will be incurred once we complete these 5 GW of batteries, which are coming up in phases beginning in January onwards. You could say INR 5,000 crore goes toward batteries.

Nikhil Dhingra

executive
#51

Modules are, of course, the final piece to arrive. With Indian modules, they now generally represent 50%-60% of total CapEx. That's uneven as well, correct? At the plants being commissioned in June, you'll notice modules beginning to arrive there from January to February. On modules, you could say roughly one to 1.5 GW is what's aimed at around June. You'll see that will once more carry a substantial CapEx attached. INR 12,000 crore might be divided toward June, but I believe we're broadly on track regarding the CapEx plan. Orders we've placed align with the INR 12,000 crore. Delivery schedules remain on track. For instance, battery has been moved earlier. As I mentioned in the connectivity response, there may be a quarter of connectivity delay, so at most a quarter of CapEx delay could also occur. Got it. Thank you. Thank you in every respect, sir. Thank you.

Operator

operator
#52

Thanks. Our following question is from Puneet at HSBC. You have the floor.

Puneet Gulati

analyst
#53

Yeah. Thanks a lot for giving me the chance. My first question is this: you mentioned how transmission is split between solar and non-solar hours. In what ways are you attempting to make use of the non-solar portion? If you could elaborate a little more, is it possible to use that with the plants you already have, or would you need to build extra capacity?

Nikhil Dhingra

executive
#54

Okay, thanks very much for that question. Look, the non-solar connectivity represents a really important GMA amendment that has come through. What it's essentially designed to do is make use of connectivity that's already operational yet isn't being fully utilized, given how intermittent renewables are and given, say, the six to eight hours during which solar operates. It lets you essentially set up a plant — a pure plant — that generates during non-solar hours. You're able to put solar there, and you're able to put batteries there for charging. That battery gets charged by the solar, and you can essentially discharge it at any point during non-solar hours. You can also sell that solar output afterward — let's say even the solar you've installed to charge batteries. That too can be supplied through that connectivity, provided there's room available in it, since solar follows a sinusoidal wave pattern. With that non-solar hour connectivity, you can use the output from that solar, at times when you aren't charging the batteries, to supply through the grid via that connectivity. The goal is essentially to use connectivity to the maximum extent possible. That's exactly where these guidelines prove really helpful. On top of that, they've permitted you to charge it from the batteries from the grid.

Nikhil Dhingra

executive
#55

If someone prefers not to install solar panels for charging their batteries, they have the option to draw power from the grid instead. Through this mechanism, they are permitted to do so. As we mentioned in the introduction, that has also been addressed in this amendment. These are the ways connectivity can be used.

Puneet Gulati

analyst
#56

So for that, a digital solar plant would have to be built. You can't rely on the solar plants you already have, since those are overbuilt and optimized. There's no room for that in this case. Is that a fair assumption?

Nikhil Dhingra

executive
#57

Yes. Batteries are something you can install. As for how you use the solar plant you already have, here's the idea: suppose your plant is 300 MW, right? In summer, if you're producing beyond 300 MW — say, because of extra utilization, or say there's some curtailment or some kind of situation where that power isn't being used — then what you can do is get counterparty approval and route that surplus power into the battery. That's permitted too. So basically, take 300, but say for 1 hour of the day you're generating above 300. That power is able to go to the battery, and that power can, basically, you can also sell it outside the PPA. That is allowed. Naturally, to do that you need to be going above the rated capacity, since up to that rated capacity the counterparty holds a right of first refusal.

Puneet Gulati

analyst
#58

Alright. Got it. On to the next question.

Manoj Upadhyay

executive
#59

Let me make one thing clear — I want to clarify this. If your question was about whether clipping power is something you can charge for, then yes, clipping power can be charged. However, you need to obtain an OC from the party that currently holds the PPA.

Puneet Gulati

analyst
#60

Is there an obligation to provide that clipped power to the PPA holder at the identical price, or are you also able to sell it at market price?

Manoj Upadhyay

executive
#61

No, no. There's no need for that. No need at all, since this is clipping power. You're able to charge the battery and then supply it to the market in the evening, or wherever else you might need it. They don't hold rights beyond 300 MW plus, though naturally you do have to apply to them. Under the PPA, their right of first refusal extends only up to the rated capacity.

Puneet Gulati

analyst
#62

Got it. And second, you mentioned that a GST cut could help as well. Is anyone from the discount side coming back and asking for a reduction, or is that not part of the discussion at all?

Nikhil Dhingra

executive
#63

Looking at it, that legal change is beneficial, though obviously whatever advantage arises must be handed back, naturally, subject to the rules. Our focus is more from the demand side — it gives renewables an edge compared with thermal or any other source, since those are largely steady, yet renewables enjoy this benefit of a meaningful GST cut. Whenever states consider future capacity additions, they'll have greater cause to purchase renewable power. In that sense, this GST change is helpful. Naturally it assists in lowering upfront CapEx, but tariffs will be modified to reflect any GST reduction. That's the situation, so it applies wherever the PPA permits. It's a benefit for the future, not one for right now.

Manoj Upadhyay

executive
#64

No. Actually, to make this clear, every one of our current PPAs that is being implemented — we’re required to hand over this benefit to whichever party is implemented under the regime, in the 5% regime. That benefit goes to the customer.

Puneet Gulati

analyst
#65

Does that get passed on automatically, or would the discount need to apply because of that legal change?

Manoj Upadhyay

executive
#66

A discount is going to be necessary. That discount is going to be necessary.

Nikhil Dhingra

executive
#67

Certainly, that will need to be filed. We’ve already been in contact with the discoms. So essentially, as for the—I think there’s a technical matter where, at present, the discom isn’t named in certain PPAs; transmission is named, since it’s flowing under the guideline, but that’s a technical point. Still, to the extent the regulations permit, we’ll need to submit that change in law.

Puneet Gulati

analyst
#68

Got it. And one last thing — regarding those new capacities you brought online over the past 12 months, what sort of CUF have you been seeing on the solar side and on wind?

Nikhil Dhingra

executive
#69

So our Sikar plant, right? Once you adjust for curtailment, it's performing really well, and they've finished using domestic modules. Naturally, this is the first facility of ours to run on domestic modules. During, let's say, the June quarter, we've been hitting CUF levels above 30%. And of course, on the wind side, we've also put up wind capacity, as you're aware. The monsoon quarter turned out very strong for us. The second quarter, of course, was a normal one. As far as the business plan goes, we're on track. On wind, of course, it's still early days, since we only have 78 MW of wind. We've yet to see the full year, but by and large, things are in line with our predictions.

Puneet Gulati

analyst
#70

Can you speak a little to P90, P70 — are those hitting the goal?

Operator

operator
#71

Puneet, I’m going to cut in here.

Puneet Gulati

analyst
#72

Sure.

Operator

operator
#73

Should you have any additional questions, kindly get back in the queue.

Puneet Gulati

analyst
#74

I’ll come back on. It’s all good. Thanks.

Operator

operator
#75

I appreciate that.

Nikhil Dhingra

executive
#76

Yes, solar is right around P50 — solar is right around P50. Wind, too, sits at roughly P75. Wind is still early days, since we haven't yet observed the seasonal piece, as the seasonal factor in wind is quite large. Naturally, expectations during the monsoon are pretty high, and it has come through. We still need to see, let's say, the non-monsoon season. So far, it's at approximately P75.

Operator

operator
#77

Murtuza Arsiwalla from Kotak Securities has the next question. You can go ahead.

Murtuza Arsiwalla

analyst
#78

Yes. Hello, sir. I was hoping to reconcile something. I believe my question has been more or less answered. We discussed 720 MWs of project wins, yet when I examine how much the portfolio's size changed, it comes to just 420. My assumption is that this relates to the NTPC 300, which has been removed from the project portfolio. Correct.

Nikhil Dhingra

executive
#79

Thanks. That's right.

Murtuza Arsiwalla

analyst
#80

Yeah, sure — thanks a lot.

Operator

operator
#81

Thanks. We’ll take the next question from Yogesh Patil at Dolat Capital. Please go ahead.

Yogesh Patil

analyst
#82

Thank you for the question, sir. You walked us through the CapEx details for FY2026. Could you share some of the funding specifics — how the debt and equity portions break down for FY2026 CapEx, and for next year as well, given your operating cash flows?

Nikhil Dhingra

executive
#83

Okay, so on CapEx — as we discussed, our target was INR 12,000 crore. The way our CapEx splits is somewhere between 75-25 and 80-20, net equity. Recently we've been seeing 80-20, along with debt sanctions, but historically it's typically been 75-25 net equity. So for INR 12,000 crore, that works out to INR 9,000 crore of debt and INR 3,000 crore of equity. Under a 20-80 split, it would basically be INR 2,400 crore of equity and, you could say, around INR 10,000 odd coming from debt. That's essentially how each project breaks down. Naturally, we do have the debt. For 80% of our signed VP projects, loan documents are complete — the debt is ready to be disbursed. In certain cases the first disbursement has been drawn; in most cases we've taken that first disbursement. As for the remaining 20%, where the timeline is 2027, sanctions are being obtained this quarter as well. So that's broadly the number on the CapEx front. As we said, the bulk of the CapEx gets done once the LCs are opened. Take batteries, for instance — we've completed the CapEx to the extent that we've had the battery LCs opened.

Nikhil Dhingra

executive
#84

Also, at present, with the modules, you complete four to six months prior to commissioning. Suppose it begins in December or January — modules will arrive at the site as well. It is weighted toward the back end. That assists us in lowering the interest during construction element, completing the CapEx at the site, and it also assists in delivering equipment just in time. A few of the long lead equipment items, such as transformers and the GIS, were opened quite a while ago, and they are arriving earlier too. Certain equipment that is abundantly available and accounts for a big share — say, turbines and similar items — arrives just in time, roughly three to four months ahead of the target COD. Naturally, the entire execution is planned with that in mind.

Yogesh Patil

analyst
#85

Let me just follow up on that point. Given the roughly INR 12,000 crore of CapEx in fiscal year 2026 — our operating cash flows aren’t strong enough to support a cash flow of that INR 12,000 crore magnitude. In that situation, we’ll draw on the INR 3,000 crore of cash already sitting on the balance sheet. For the following year, where would the equity portion come from, since in fiscal year 2027 as well we’re planning CapEx of about INR 12,000 to 13,000 crore? To handle that, 30% or 25% equity to fund that CapEx. I just wanted to get some clarity on that point. If you could elaborate a little bit on that side.

Nikhil Dhingra

executive
#86

Okay, Yogesh. So look — as you mentioned, that cash sits on the balance sheet for the current CapEx. We also have un-drawn securitization proceeds — that's the debt proceeds, the refinancing proceeds — roughly INR 1,000 crore that hasn't been drawn. And there's some refinancing coming up; add another INR 1,000 crore to that. Once the project becomes operational and you move from a 9%-9.5% rate down to 8%, that causes the securitization or refile proceeds to get added to that project. To build on that number, we have the UC, the annual pact with depreciation — right, which is half a year — we've done roughly INR 275 crore-INR 260 crore kind of figures. Annualize that, and that's the annual cash flow we can generate, right, on this side. If you take, let's say, an 8%-10% margin, which is on the VPC side, that will also throw off some cash flows from that organic cash flow donation. Plus, of course, debt reduction will further — the interest rate reduction will further help those cash flows. On the CapEx itself, that INR 12,000 crore figure will let us do more projects, because effectively the prices of things have come down in terms of battery, in terms of solar.

Nikhil Dhingra

executive
#87

Naturally, as we mentioned before, we've moved to a configuration that's heavy on solar. That's also brought down the CapEx that needs to be spent. With the INR 12,000 crore figure, we'll reach a capacity that's considerably higher than what we had earlier. Because of that, and the battery — as we said, 1 GW hour will give us roughly INR 170 crore of cash flow — we think in terms of the equity drawdown. That's another source of revenue coming in early, which will help us improve the numbers we gave you relative to past profitability. One last thing, I'd like to also — just a minute — I'd like to also add that this year, most of the expenses were done through equity. Of the INR 12,000 crore, INR 3,000 crore was equity. I think the initial investment was all done through equity. Technically, what you're seeing is that INR 3,000 crore is left in this one. Just a small portion of that will go into these projects, and the remainder will be used for next year's project.

Yogesh Patil

analyst
#88

All right, the final item: other expenses rose sharply, and other income came in higher as well. What are your thoughts there?

Nikhil Dhingra

executive
#89

Okay, so on other income — we recorded a hedging gain, and that helped, because we'd hedged for batteries that have now begun dispatching. There was a gain on the hedging side, and that's what pushed other income up from the last quarter to this one. That explains the other income. As for other expenses, I'd say it's the rise in the ESOPs and other items that drove that increase.

Yogesh Patil

analyst
#90

Thank you. Many thanks, sir, and I wish you the best of luck.

Nikhil Dhingra

executive
#91

Thanks.

Operator

operator
#92

Thanks. Our next question is from Akash Mehta at Canada HSBC Life. Go ahead, please.

Akash Mehta

analyst
#93

Yeah. Hi. I was hoping to get some clarity on the grid curtailment side of things. I just want to make sure, actually — does this tie only to demand? Is it tied to transmission lines not coming online on schedule, or, I mean, and what kind of capacity is exposed to those kinds of issues going forward, both in the current quarter and in the last quarter that's already passed?

Nikhil Dhingra

executive
#94

Okay, look — the curtailment you're seeing anywhere is purely a result of transmission line issues. That's because every PPA includes a mustering clause for renewables. When you hold long-term open access, you're legally entitled to full evacuation or full payment for the power you've generated. What happens is, take our Seeker plant, which we mentioned, that got commissioned earlier — in June, right. The timeline for that line from the power grid was around September, and now it's been stretched to December. It sits below that last mile connectivity because land prices in the Delhi region were quoted higher than before, and there was an election there. That caused prices for that ROW, or a land parcel, in the transmission lines to fall in the Delhi region. Net relay in that. It's mostly down to the transmission line. The only project where we're impacted is this Seeker project, and that's because of early commissioning. We're better off doing early commissioning than not doing it. We run the maths — are we better off or not? Overall, we are better off doing that early commissioning.

Nikhil Dhingra

executive
#95

Naturally, that's going to affect annual revenue by 1.5%-2%. In the bigger picture, though, it works in our favor thanks to the early commissioning.

Akash Mehta

analyst
#96

Sure, go ahead. If we commission according to the PPA timelines and there’s no transmission availability for some reason, we get compensated. In this case, since commissioning happened early, we won’t receive compensation, correct? I mean.

Nikhil Dhingra

executive
#97

All right. Also, during early commissioning, look — if you have an LTOA, then your position is legally protected. With an STOA, naturally, you can seek compensation, though whether you get it hinges on the merits of the case. Under an LTOA, your odds of winning are 100%. Under an STOA, precedent has yet to be set. That is, naturally, what we attempt. We do attempt it, but no precedents exist at present, since this type of case is new. We will inform you once we receive a favorable hearing on it. With an LTOA, there are no problems. Our usual approach is shaped by the fact that it was extremely brief. It was a June 2025 bid in which projects had to be commissioned for June 2025. You could call it a one-off type of bid, where the interval between the PPA and commissioning was extremely brief, and on balance, commissioning it was sensible. Normally, you do not commission before you hold the LTOA. That is the point I was making — this is an exceptional situation rather than a normal one. In such a case, you recover the full damage. Under an STOA, we have yet to see precedent.

Akash Mehta

analyst
#98

Okay, I find that pretty useful. Yeah, that's all I had. Thanks.

Nikhil Dhingra

executive
#99

I appreciate it.

Operator

operator
#100

Thank you. Ladies and gentlemen, given the time limit, we'll treat that as the final question of today's call. At this point I'd like to pass the conference to Mr. Rupesh Sankhe for his closing remarks.

Rupesh Sankhe

analyst
#101

Thank you to ACME Solar Holdings Management for the chance to host this call. Our thanks as well go out to every investor and analyst who has joined us today. Thank you.

Operator

operator
#102

That brings our conference to a close on behalf of ACME Solar Private Limited. We appreciate your participation today, and you're welcome to disconnect your lines at this time. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete ACME Solar Holdings Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to ACME Solar Holdings Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in ACME Solar Holdings Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.