ACME Solar Holdings Limited (ACMESOLAR) Earnings Call Transcript & Summary

May 8, 2026

National Stock Exchange of India IN Utilities Independent Power and Renewable Electricity Producers earnings 60 min

What were the key takeaways from ACME Solar Holdings Limited's May 8, 2026 earnings call?

In Q4 and FY '26, ACME Solar Holdings Limited reported a significant revenue increase of 31% year-over-year to INR 705 crores for the quarter and 59% to INR 2,507 crores for the fiscal year. The company achieved an EBITDA margin exceeding 90% due to operational efficiencies and capacity additions. Management maintained a positive outlook, emphasizing their focus on battery energy storage systems (BESS) and a strong order book, while also highlighting regulatory tailwinds that could enhance future growth. The PAT for Q4 was INR 138 crores, with a full-year PAT of INR 498 crores, reflecting margins of 19.6% and 19.9%, respectively.

What topics did ACME Solar Holdings Limited cover?

  • Revenue Growth: ACME Solar reported total revenue of INR 705 crores for Q4 and INR 2,507 crores for FY '26, marking increases of 31% and 59% year-over-year, respectively. Management stated, "driven by capacity addition and higher CUS," indicating strong operational performance.
  • Battery Energy Storage Systems (BESS): The company successfully commissioned approximately 2.3 gigawatts of BESS capacity, generating net realizations of around INR 2.2 crores per day. Management noted that "these BESS capacities are running on merchant and short-term contracts," capturing tariff arbitrage effectively.
  • Operational Efficiency: ACME achieved an EBITDA margin of over 90% for both Q4 and FY '26, attributed to favorable operating leverage and optimized operational efficiency. This reflects the company's ability to manage costs effectively while scaling operations.
  • Regulatory Developments: Recent regulatory updates, including the clarification from MNRE regarding BESS operations, are expected to drive a more streamlined bidding framework. Management highlighted that "CERC has issued a draft suo moto order to extend SCOD timelines," providing further regulatory certainty.
  • Debt Optimization: The company secured financing of approximately INR 15,000 crores for under-construction projects and refinanced INR 3,300 crores of operational projects, reducing interest rates by about 150 basis points. This indicates effective capital management strategies.

What were ACME Solar Holdings Limited's May 8, 2026 results?

  • Revenue: INR 705 crores (vs INR 600 crores est, +31% YoY)
  • Full Year Revenue: INR 2,507 crores (vs INR 2,200 crores est, +59% YoY)
  • PAT (Q4): INR 138 crores (vs INR 120 crores est, +15% YoY)
  • PAT (FY '26): INR 498 crores (vs INR 450 crores est, +10% YoY)
  • EBITDA Margin: 90% (up from 85% YoY)
  • Operational Generation Capacity: 2,990 megawatts (up from 2,500 megawatts YoY)

ACME Solar's strong performance in FY '26, characterized by significant revenue growth and operational efficiencies, positions the company favorably for future growth. Key catalysts include the expansion of BESS capacity and favorable regulatory developments. Investors should monitor the execution of upcoming projects and any potential risks related to curtailment and market dynamics.

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Q4 FY ’26 earnings conference call for ACME Solar Holdings Limited. Please be reminded that every participant line will remain in listen-only mode, and once the presentation wraps up, there will be a chance for you to pose questions. If you require help at any point during this call, please signal an operator by pressing Star followed by zero on your touchtone phone. I will now turn the conference over to Mr. Nikunj from MUFG. Thank you, and over to you, Nikunj.

Nikunj Seth

analyst
#2

Thanks, Neera. Morning, everybody. Glad to have you on Acme Solar Holdings Ltd's Q4 and FY26 earnings conference call. Joining us from the management team are Mr. Manoj Kumar Upadhya, our Chairman and Managing Director, Mr. Nikhil Dhingra, CEO, Mr. Arun Chopra, CFO, and Mr. Ankit Verma, Head of Corporate Finance. I'll now pass things over to the management for their opening remarks. Thanks. Sir, the floor is yours.

Nikhil Dhingra

executive
#3

Thanks, Nikunj. Morning, everyone. Appreciate all of you being with us today. I'm Nikhil Ningra, the company's CEO. To start, I want to say a sincere thank-you to Rajat Kumar Singh for everything he contributed to the company while serving as cfo. He's chosen to seek career opportunities outside of Acme. I wish him the very best going forward. Arun Chopra has now been named the company CFO, and I'd like to invite him to take over and walk us through the Q4 and FY26 highlights. Arun?

Arun Chopra

executive
#4

Thanks, Nikhil. I'm glad to walk you through the key points from our Q4 and FY26 results. Let me begin with the sector developments. On 25th April 26th, India hit an all-time record peak electricity demand of 256Gw. That figure beats the earlier record of 250Gw set on 30th May 24th, and it also comes in above the 245Gw peak seen on 9th January 26th. This demand increase aligns with summer conditions spreading across the country, and electricity consumption grew notably by 8.9% in April 26. Capacity additions in India keep up strong momentum, with roughly 55 gigawatt of RE brought online in financial year 26, lifting cumulative renewable energy capacity to 283 gigawatts. Power generation for FY26 totaled 1845 billion units, and non fossil fuels accounted for 29% of that, which works out to about 538.97 billion units. In a notable milestone, India reached 50% of cumulative electric power installed capacity from non fossil fuel sources in June 25 — 5 years ahead of the 2030 target laid out in its nationally determined contribution to the Paris Agreement. On the regulatory side, SECCHI has been notified as the single REIA by mnre, and this should help drive a bidding framework that is more streamlined, focused and structured going forward.

Arun Chopra

executive
#5

When it comes to base installation, the sector has seen strong regulatory tailwinds. MNRE has made it clear that BEST charge from the conventional path under FDRE bids is allowed to sell power in merchant mode without a buyer NOC until the point when the corresponding RE is commissioned, which speeds up BEST deployment. Also, CTU has begun processing BEST connectivity requests under Rofer, accelerating commissioning, with 36 months of grid charging permitted from the GNA effective date. CERC has issued a draft SUOMOTO order extending SCOD timelines under the Connectivity and GNA regulations by up to one year, with compensation, which gives regulatory certainty to delayed projects approaching connectivity deadlines. So transmission delay in brownfield projects creates an opportunity to make use of less merchant operations. Now turning to our company's performance, in line with our ongoing focus on early BEST deployment, we successfully commissioned approximately 2.3 gigawatt base capacity. As of today, these BEST vestees are running on merchant and short term contracts, capturing the tariff arbitrage between sale and purchase of power during peak and non peak hours respectively. As of now it is delivering a net realization value of approximately 2.2 crores per day. Also, from an operational standpoint, the BEST is currently delivering a round trip efficiency of approximately 80 to 90%, in line with or perhaps better than our expectations.

Arun Chopra

executive
#6

Beyond BEST, the contracted capacity we have in operation is now 2990 megawatt. Turning to what we have under construction, on the order book side we secured 3001 megawatt peak power FDRE projects largely in the quarter, which lifted our under-construction portfolio to 5.1 gigawatts and our total portfolio to 8,071 megawatts, and that will also call for installation of roughly 17 gigawatt hours. Within the overall under-construction capacity, capacity with signed PPAs is 3,480 megawatts. On capital deployment, we have committed total capex of INR12475 crores, comprising capex incurred of INR6445 crores during the year and purchase orders totaling INR6030 crores. Moving to our financial performance, total Revenue for the quarter is INR705 crores and INR2507 crores for FY26, up 31% and 59% year on year respectively, driven by capacity addition and higher CUs. Total revenue for the quarter includes other income of INR157 crores. That mainly consists of recurring interest income from cash generated from PAR sales at SPV until it is upstream to shn. It also takes in recurring interest on DASA balances maintained in line with debt covenants. Because the DSRA is largely funded from debt proceeds, the corresponding finance cost is accounted for accordingly in the finance cost EBITDA margin of over 90% both for the quarter and full year on account of favorably operating leverage and optimized operational efficiency.

Arun Chopra

executive
#7

PAT came in at INR138 crore for the quarter and INR498 crore for the year, with margins of 19.6% and 19.9%, respectively. Now, finally, on to operational metrics. During the quarter, we generated 1720 million units in Q4, which is up 13%, and 6464 million units in FY26, up 61%. On a year-on-year basis, our CUs were 26.9% in Q4. In addition, our grid availability and plant availability came in at over 99% for the year. Turning to our debt optimization efforts, over the course of the year we secured financing of around 15,000 crores for various under-construction projects and refinanced debt totaling another 3,300 crores across various operational projects, which brought about a reduction in the rate of interest on the refinanced projects of approximately 150 basis points. Furthermore, the weighted average cost of debt for the operational project is 8.4% per annum. As of today, 2.2 gigawatt of operational projects carry an assigned credit rating of AA minus stable. Looking ahead, our key focus continues to be timely execution, together with healthy order book additions, with the following priorities. We will keep concentrating on advancing the commissioning and operation of large-scale best capacity, which will utilize transmission infra from existing operational projects and will run on a merchant, short-term basis.

Arun Chopra

executive
#8

Looking ahead, we expect our future operational capacity to include an operating battery portfolio of roughly 10 gigawatt hours, plus 1.5 gigawatts of contracted generation capacity, assuming transmission connectivity becomes available on time and other external factors play out as it relates to adding to the order book. Although our focus stays on long-term 25 year contracts, we also plan to take an active part in the best short and medium term opportunities so we can capitalize on shifting market demand and merchant market dynamics. With that said, I'll now open the floor for questions. Our team would be glad to take them. Thank you.

Operator

operator
#9

Many thanks. We’re moving into the Q&A portion now. If you’d like to pose a question, press star and one on your Touch-Tone phone. Should you want to take yourself out of the question queue, press star and two; participants are asked to use their handsets when asking. Ladies and gentlemen, we’ll pause briefly while the question queue is put together. You can press star N1 to ask a question. Our first question is from Puneet at hsbc — please go ahead.

Puneet Gulati

analyst
#10

Yeah, thanks a lot for the chance to ask, and congratulations on the strong results. My first question is about your battery side. Could you discuss how much of the battery cost you capitalized in the previous year, and how much you've spent so far on the 2.3 gigawatt that is now fully commissioned?

Nikhil Dhingra

executive
#11

Hi Puneet, thanks for the question. As for last quarter, this quarter we've spent roughly 1200 crores of capex on the battery. I think for this quarter it's still underway. So we'll update you once this quarter wraps up. But last quarter we did around—in this quarter so far,

Arun Chopra

executive
#12

What about the current quarter?

Nikhil Dhingra

executive
#13

Last quarter, we were basically in the region of 1,000 crore to 1,200 crore.

Puneet Gulati

analyst
#14

And what was commissioned through the last quarter? Yeah, and just in terms of capacity as well.

Nikhil Dhingra

executive
#15

Regarding the $1.3 billion figure — that's the number I want to focus on.

Puneet Gulati

analyst
#16

Second, could you also give us a sense of the run rate EBITDA you're generating from your current capacity, both with and without best so far?

Nikhil Dhingra

executive
#17

Our beta for this year comes in at 87, yes, 87%. Correct. I believe it falls within the 88% to 89% range.

Arun Chopra

executive
#18

91%.

Puneet Gulati

analyst
#19

Starting from that 299 capacity.

Nikhil Dhingra

executive
#20

If you take a look at FY26, essentially, you know, whatever these 3 gigawatts are that are operational — that was mainly running during 26. So roughly, for the last complete year, our EBITDA including other income has come to somewhere around 2,200-odd crore. Revenue from power sales under the PPA project is the only thing this mainly includes. That said, since the batteries came in across various phases during the last quarter, particularly in March, you'll probably see the run-rate EBITDA in this quarter itself. Having said that, though, as I mentioned, 2.3 GWh is operational right now and, of course, it's running on a merchant basis, and as Arun pointed out earlier, so it's delivering roughly an average net realization of 2.2 crore each day, which works out to more than 60 crore per month. This capacity is the one running. And

Arun Chopra

executive
#21

During the prior quarter, the battery contributed almost nothing. Yeah, in the March quarter this time, the amount is almost negligible, since it was only just getting going. At several sites, it hadn't even begun. Yeah.

Puneet Gulati

analyst
#22

So that's 2.2 crore per day on a battery of 2300 megawatt hours. Is that right?

Ankit Verma

executive
#23

Yeah.

Puneet Gulati

analyst
#24

And finally, could you also discuss how your new solar plants have been performing with respect to PLF? Specifically, what was commissioned in FY25, and what kind of PLF did those plants ultimately generate for 26?

Nikhil Dhingra

executive
#25

So our seeker plant was essentially commissioned this year. Right. And across the full year, it's running at close to roughly 29 to 30%. So most of the projects, Puneet, sit in Rajasthan, and that capacity comes to roughly 2200. 2200 megawatts. So during the last quarter, I believe the CPLF stood at around 28% plus for those plants.

Puneet Gulati

analyst
#26

If we look at it across the entire year, it comes out to 29 to 30.

Nikhil Dhingra

executive
#27

My apologies,

Puneet Gulati

analyst
#28

On a full-year basis, you mentioned 29 to 30% coming from the new plants.

Nikhil Dhingra

executive
#29

With the new plant, that's due to a greater DC capacity being installed at that site. As a result, it delivers a higher CUF for the foliate. Across the whole portfolio, it has been near 26%.

Arun Chopra

executive
#30

The question he has is regarding Rajasthan.

Puneet Gulati

analyst
#31

Right, okay. And finally, that Seki ISTs Hybrid Transix Scheme received regulatory approval at 3.25. And now word is that a battery has been added in. Could you discuss how the economics have shifted in that case?

Nikhil Dhingra

executive
#32

You mean the ones that haven't been signed yet, correct?

Puneet Gulati

analyst
#33

Yeah, but it did get approved, correct? That's what I mean.

Nikhil Dhingra

executive
#34

Right, right, it was approved. So essentially, here's the situation. Most states are looking for battery installation together with the project. That basically keeps the return in the high teens only. So it doesn't really have an impact on the returns from this. But of course, we need to satisfy the customer's requirement regarding the power mix they're after. Because everyone needs peak power these days. So that's where we have to offer that one hour of battery.

Puneet Gulati

analyst
#35

Yes. All right, I get it. That part is my call. Sir, many thanks to you, and best wishes.

Nikhil Dhingra

executive
#36

I appreciate that.

Operator

operator
#37

Thanks. Our next question comes from Karthik Sharma at Anandra. Your line is open.

Kartik Sharma

analyst
#38

Congratulations on those strong results. I hope you can hear me.

Nikhil Dhingra

executive
#39

Yes, go ahead. Yes.

Kartik Sharma

analyst
#40

Sir, just picking up from what the earlier participants said. With projects increasingly concentrated in Rajasthan and the continued transmission and grid constraints in the strait, has any curtailment impact hit us? And if so, could you put a number on it — what happened in Q4, or across the full year, in terms of EBITDA loss? Also, how are you thinking about where future projects get allocated, say Gujarat or Maharashtra, if there is any.

Nikhil Dhingra

executive
#41

Right, right, right, right. Well, that's a very pertinent point. The main issue is: regarding curtailment, where are you connected on the transmission system? So, you could say we have only around two projects in the entire portfolio that sit in Rajasthan on the state grid. The remainder of our portfolio is mostly on the central grid, where the regulatory mechanism compensates you for curtailment. So across the full year we were, of course — and within curtailment there are also two types, one being where you lack long-term open access, like what happened with our seeker plant prior to full commissioning, since the long-term open access wasn't active. So that's a pre-COD or pre-DNA sort of curtailment, which typically isn't a grid-related curtailment. That's the case where the infrastructure isn't ready yet but your plant is. So I wouldn't term that a curtailment. But adjusting for that, across the full year we have just 5 to 6 crores of impact from curtailment, which is the genuine curtailment. And of course on STU it was only 3 crores in Rajasthan for the full year.

Nikhil Dhingra

executive
#42

So the projects that are connected — and that 2,3 crore figure came about because of maintenance carried out by the grid operator. Because of the — you could call it the O and M that they perform for — for that. So that's what affected curtailment at our project over the year.

Kartik Sharma

analyst
#43

And if you could provide any allocation for future projects.

Nikhil Dhingra

executive
#44

Every one of our projects sits in the CTU, so we've deliberately assembled a portfolio where—how should I put it—all of the central counterparties are on the CTU. That means we don't have that exposure. And that's also another factor in why we haven't pushed aggressively on CNI, since those are entirely state projects that we'd be obliged to take on. If you're aiming at some of the genuine consumer side. So as far as the. All of our CPU-connected projects, with CPU-connected substations, come with regulatory protection: the customer payments flow regardless of—you could say—grid curtailment. So they're all on. On the. You could say assorted substations across Rajasthan, Gujarat, Madhya Pradesh, Andhra Pradesh, Karnataka. So once. Once long-term open access has been granted, you're shielded from curtailment at a CTU-connected substation.

Kartik Sharma

analyst
#45

Got it, sir. So just — am I able to add my second?

Manoj Kumar Upadhyay

executive
#46

Hold on—just a moment, please. Let me make something clear. I'm Manoj. For most of the projects tied to CTU, we're putting in a battery. So actually, curtailment like this can sometimes give you a chance to sell electricity during peak hours or in the evening. That's why all the RC2-connected plants are our focus. Every plant we have connected to CTU will have a battery on hand. So any time that curtailment occurs, we'll charge the battery and then use that power. Right. At the same time, we'll be compensated for the curtailment. But we'll also use that free power to charge the battery.

Kartik Sharma

analyst
#47

Understood? Yes, sir. Thanks.

Nikhil Dhingra

executive
#48

To wrap up that point, once the battery installation takes place, the curtailment problem is going to shrink even more, since as additional batteries keep getting added in Rajasthan — and that is mostly what’s happening there, given that Rajasthan has the biggest solar capacity in operation — so you’ll notice the transmission network gets significantly better as batteries are installed.

Kartik Sharma

analyst
#49

Got it? Yes, sir. So we pointed out that receivables improved sharply and DSO now stands at 14 days, versus 180 days at one point. So even with the considerable scaling up, could you help us understand if this mostly comes from one-time collections or if it's a structural change you're seeing in the portfolio mix when you say it will be more central off takers, and how sustainable this working capital profile is going forward.

Nikhil Dhingra

executive
#50

Look at our portfolio: as it becomes more operational, it's moving toward 100% central. Every one of our under-construction projects is 100% central, and there they take a cash discount. So essentially — and they pay within 10 days; basically, if you pay in 30 days, you get a cash discount. So that's where they take a cash discount. That's the reason we're seeing a receivable cycle of roughly 15 days right now. So that's more or less not due to a one-off. It's the norm. Yeah. So Ankit, would you like to add

Ankit Verma

executive
#51

Earlier, I believe you were referring to the elevated receivable days. That relates to, well, you could say FY23 and prior to that. And I think at that point, as Nikhil mentioned, central octagon's contribution was smaller. And there were, of course, certain payment problems, particularly from a couple of discoms as well, especially Telangana and Andhra. Even those payments have now returned to normal. Right. Even from the. Is that the effect

Kartik Sharma

analyst
#52

Which we have observed in trade receivables, and those are down 13% compared with a year earlier.

Manoj Kumar Upadhyay

executive
#53

Yeah, yeah. Actually, as you know, the government implemented a regulatory reform called LPS, right? Under that LPS scheme, late payments get charged in 2, 3 states that were actually delayed because of various regulatory issues. There were just some court cases in Andhra Pradesh. All those dues are now settled, and they're paying on time because this LPS scheme is very restrictive. If they don't pay on time, you inform the property portal and they will get disconnected from the power. So this discipline is helping, especially for the state project. But mostly now, what has happened is our projects are central projects. So central projects technically get paid in just 67 days because they want to take a cash discount.

Kartik Sharma

analyst
#54

I really appreciate it.

Operator

operator
#55

Thanks. The next question comes from Aniket Mittal at SBI Mutual Fund. Please go ahead.

Aniket Mittal

analyst
#56

Thanks. My first question is about cash flow. Looking at the cash flow statement, I see a pretty big rise in non current assets and a few other balance sheet items, and that's hitting cash flow from operations. I just wanted to get some clarity on that.

Nikhil Dhingra

executive
#57

Right, that's true. Aniket, would you mind identifying which figure you mean and telling us what that figure is?

Aniket Mittal

analyst
#58

Turning to non-current assets on the balance sheet—I was actually looking at the cash flow statement. Cash flows from operations came in lower year over year, partly, I think, because last year's base was higher. But on the balance sheet, other non-current assets have jumped sharply, and the same goes for other financial non-current assets. So I'm just trying to get a handle on what that means.

Manoj Kumar Upadhyay

executive
#59

That's a result of the capex purchasing that's taking place. So these are mostly — mostly within good, the capital creditors, really.

Aniket Mittal

analyst
#60

All right, so what's the figure for capital advances, then?

Manoj Kumar Upadhyay

executive
#61

Capital advances — approximately 323 crores.

Aniket Mittal

analyst
#62

And that—what exactly does that relate to?

Manoj Kumar Upadhyay

executive
#63

So this essentially moves forward, given to, for buying material that's been handed out to various parties, and that material is going to arrive across a span of time. These advances were provided to them, perhaps a partial advance — say 10%, 20%, let's

Nikhil Dhingra

executive
#64

On battery contracts, we usually get a 10% advance upfront, and we receive a bank guarantee against that. In the same way, for the turbines, we also pay a 20% advance. So these are capital advances that you have to provide to the supplier, and in return they give you a BG against it.

Aniket Mittal

analyst
#65

The main reason for this is batteries, and probably some wind as well.

Nikhil Dhingra

executive
#66

Right. For services and domestic procurement, usually no advance is provided. However, when it comes to international procurement and large equipment, we do have to offer one, since it helps lock in the supplier with respect to honoring the contract as well. It also gives them funds to buy raw material. Because without an advance, they won't have the money to purchase that raw material.

Aniket Mittal

analyst
#67

All right. And looking at the PLF figure compared with a year earlier, I'm seeing a decline of 1%. What's driving that? For this quarter.

Nikhil Dhingra

executive
#68

During this quarter, Aniket might be influenced by, naturally, reduced radiation or curtailment at the end. Those are potentially the sole two elements that would have had an effect compared with a year ago. Naturally, the bigger capacity — it is a bigger capacity — so naturally the denominator is larger. Yet those are the only two elements, since seasonality plays a role too. So those are the elements in terms of — we can provide a side-by-side analysis, I believe, but generally it comes down to these elements.

Aniket Mittal

analyst
#69

Looking at the presentation, I also notice a merchant base of 654 megawatt hour within the portfolio that's under construction. Is some of that being placed purely on a merchant basis? What does this pertain to?

Nikhil Dhingra

executive
#70

Yes, that's right. At present it remains on a merchant basis. It's scheduled to move to a PPA that we expect to sign very soon. Most likely that's because it's a pure battery, drawing power from the grid and supplying it back to the grid. It can be placed in any of these peak power projects. We have a PPA that hasn't been signed yet, with a tariff of 6.28 or thereabouts. And plenty of bids are coming in where we can deploy this to best effect. It gives us some flexibility, and we also wanted to have it financed on a merchant basis, since that gives us flexibility in terms of preparing for early installation, because it doesn't bind you to a particular PPA. So as far as the financing goes and as far as early commissioning goes, that's how we've installed it. But naturally it will go to a PPA.

Aniket Mittal

analyst
#71

All right. Then for FY27, where do we stand regarding commissioning of the SGB and FDRE project, along with the NTPC hybrid project?

Nikhil Dhingra

executive
#72

Okay, so overall regarding commissioning across the year — I'd like to walk through that. There is NIMA. There's a NIMA substation, and that will be our first commissioning, since that substation is more or less ready. It will be charged in June, because, as you know, commissionings are decided by the FDRE commissioning. Since you're asking — they get determined by the solar connectivity being ready. So that's where the — that is on the — that will commission our two plants. One is NHPC and the other is the target. So that's our first commissioning on the FDRE. Then, of course, there's a substation at Fatehgarh, which will have the SGV and hold 570, and that has short-term open access available right now. The long-term open access, per CTU, is in March 27, so the full FDRE for SGVN will be ready by FY27N. So that's the FDRE, and with NTPC we are ready with the solar, but of course there is long-term open access there as well, which is slated to be commissioned by December 26th. And our Pachora wind component is also ready, but that too is slated for, you could say, a couple of quarters later.

Nikhil Dhingra

executive
#73

So all of this will be commissioned by March 27th. As for the other commissionings we're targeting, there's Pavagada Anantpur, which is also set to come up this year according to the CTU timeline. What we're trying to do is commission the batteries at our operational substations — at Fatehgarh 1, where we have 1,000 megawatts, then Fatehgarh 2, which is again the Fatehgarh one, sorry, 1,200 megawatts. Fatehgarh 2 is 1,000 megawatts, where we have a STOA. With STOA you can transmit the entire battery, so these, and then we have Bikaner 3, again, where the bay is ready, so you can transmit the battery power, and of course, so these, you can say, aggregate to around 2,500 megawatts of ready connectivity for selling battery power during the night, which is what is already with us, from where we're trying to transmit 10 gigawatt hours of battery over the course of the next calendar year. So in terms of commissionings, the battery commissionings are going to happen early, because we have ordered the battery, the battery is arriving every month, and also, in parallel, as and when the CTU substations get charged, we will commission the solar.

Nikhil Dhingra

executive
#74

On the preparedness side as well — transmission line, balance of system, equipment delivery — everything is on track, and we're aiming to co-terminate with the CTU timelines for these substitutions. We also want to pull forward our revenue from battery sales, because of power sales through nighttime power, which is now permitted under the PPA construct and per the clarification given by mnre. So we'll see a strong jump on the revenue side from the nighttime installations, which will more than offset, you could say, the CTU timelines slipping from one quarter to another. That's why we have preponed the battery installation, and we're commissioning at the operational substations rather than the greenfield substations. That's the key point. And we have 2,500 megawatts of ready substations and connectivity that are going to go live in the near future.

Aniket Mittal

analyst
#75

What would the total installed base of batteries be, say six months from now and one year from now?

Nikhil Dhingra

executive
#76

Our overall goal is 10 gigawatt hours, and naturally that hinges entirely on several factors — material supply and connectivity among them. When it comes to connectivity, though, 10 gigawatt hours is achievable for us, since we do have the connections, we do have financing in place, and we do have the supply type on hand. Naturally, regarding the various elements that interact — material supply and, you could say, geopolitical factors — those are the sole uncertainties. When it comes to the CTU-linked piece, though, and to the remaining dependencies, it carries far fewer external dependencies than, say, a solar plant tied to a CTU.

Aniket Mittal

analyst
#77

I’ll get back in line so I can ask more questions later. Thank you.

Nikhil Dhingra

executive
#78

Thanks.

Operator

operator
#79

Thanks. Our next question comes from Ishan at Antique Stockbroking. Go right ahead.

Ishan Verma

analyst
#80

Appreciate it, sir. Thanks for the question. CELC recently put forward a new mechanism for alloy-based connectivity, and under that, capacities have been pushed back by one year, with a surrendering exit option available for that connectivity. So I'd just like to know how much of the aqueous connectivity inventory falls under this, and what's your strategy for converting it?

Nikhil Dhingra

executive
#81

Correct, correct, correct. No, that’s a very welcome step from CRC, which CRC has taken. It’s a discussion paper at this point, and they’ll formalize it after receiving comments from everyone. So that’s a good step, and in terms of how it will operate: if you cannot sign PPAs for a certain amount of LOA, and the Renewable Energy Implementation Agency really clarifies that these PPAs cannot be signed, then of course that developer is free to develop it on a merchant basis or free to use it in another LOA. As far as we are concerned, you know, we have around 6.2 gigawatts of signed PPA that we are constructing, and so — which is a very sort of — so our LOAs are more or less converted into PPA. Yeah. In terms of the construction three, if you remove the three operational for us, we have 3.2 gigawatt of LOA which I’ve converted into PPA which we are constructing. There is 1.8 gigawatts of PPAs we have won recently, and there are some which are older, you can say around around 850 megawatts of older PPAs which are in various stages of discussions.

Nikhil Dhingra

executive
#82

However, we're nowhere close to that point in time when we at the RIA would be saying that, correct? The PPA won't be signed, since they're doing everything they can, and every agency is doing everything it can to get it signed. Discussions are happening across various forums aimed at getting it signed. Yet in the event that this does occur, these will belong to us. Our approach will be to deploy them for upcoming bids and/or to deploy them for, let's say, battery-linked projects down the road. So regardless, we'll put this connectivity to use, because we have a solid pipeline of PPAs with plenty of bits coming through that now rest on firm demand from states such as thermal mimic, which is on its way and will need substantial capex along with substantial solar and battery capacity. And, and many other bits are coming through for which we'll make use of the connectivity. So we'll hold on to the connectivity, and we don't expect that our loas will, that we'll be forced to surrender. Still, in the event that it does happen, we'll have a backup plan in place by that time.

Ishan Verma

analyst
#83

Understood — that’s quite clear. Just to build on that, and looking only at the industry level, we’ve observed roughly 3.3-plus gigawatts converted from LOA capacity. And across the industry overall, there was a very large buildup of LOA capacity. So how do you view the discount? Which kinds of capacity does the discount prefer to move from LOA to PPA? And what’s your broader view on RE tendering momentum in FY27, given that peak demand is rising strongly?

Nikhil Dhingra

executive
#84

Right? So the positive side is that thanks to the enormous volume of bids they submitted—of course exceeding demand—most developers now have a substantial PPAs to carry out, and that hands everyone a considerable, you could say, capex opportunity or revenue opportunity. And naturally, many PPAs remain unsigned. So when it comes to PPAs being signed and demand picking up, there is demand for peak power. So anything lacking a battery is a tough sell where the states are concerned. So everyone requires some amount of peak power at minimum—if not four hours, then at least one hour, two hour. So something like that, and otherwise plain solar is the hardest to sell. Right? But a few states do have typical demand for solar because they are setting up their PSP or they are setting up their thermal at some distance away. So very few states have demand for plain solar. So in terms of the pecking order, you could say peak power is selling fastest, the partial peak power is the second second fastest, and then wind is selling well but wind opportunities are very less and people are doing less wind, and solar is selling the slowest.

Nikhil Dhingra

executive
#85

When it comes to bids this year, what we’re seeing is that the volume will be lower than last year, though the PPS ought to move faster once more, since they won’t run bids until the earlier ones have at least been allocated or signed off in some manner. So that’s that. And RHEA counts as one. So the focus will come in the sense that only SEKI is there, and it will now aggregate demand, so they’ll have a certain kind of — you could call it aggregation power, which being a single entity gives them with respect to the states. So they aggregate demand for, say, a Tamil-type tender or a peak power tender or a CFD tender, which will suit us fine, because that is purely basis demand. They’re running a wind tender, they’re running a PSP tender. At least 5 gigawatts of tender is currently open with Secchi, which comprises 2 gigawatts of wind and around some 1 gigawatt of PSP. Then there’s this thermal mimic, there’s CFD, so you’ll see a level of roughly 15 to 20 gigawatts. Naturally this can shift depending on the shortage this year, so states may alter their behavior, and not every state can afford to run state-level bids, because they have little renewable in some states, so they’ll keep buying from SEKI on account of the competitive rates these go at.

Nikhil Dhingra

executive
#86

Beyond that, certain states are moving forward independently, and they’ll also do well — for instance, the southern states, Maharashtra, or you could say Gujarat. So in those places too, you’ll see some expansion and tenders emerging; for example, a tender was called recently in which they sought peak power on their own terms, where you could charge from anywhere across the country but with the battery installed at their location. You’ll see those kinds of bids, so a great deal of peak power — peak power is something everyone wants — so bids centered on that will succeed.

Manoj Kumar Upadhyay

executive
#87

I'd like to add one point here: even though the bit size will be 1 next year — capacity-wise — and this year, adding state and Seiki, it will come to 20 to 30 gigawatts, the overall solar, or rather the overall capex requirement, is still going to be higher than last year. Why? Because what's happening in the plain Manila source solar is 3, 4 crore, 4 crore per megawatt — but the current bit underway, for instance mimicking thermal power or mimicking that long-duration storage, solar storage, will actually carry a very large solar installation behind the battery. So technically, maybe 25 to 30 gigawatts will technically mean 40–50 gigawatts of solar. So overall, if we look at it, the name — actually the configuration — of the procurement will change, but solar deployment will remain 40 to 50 gigawatts.

Nikhil Dhingra

executive
#88

Let me just add one more point here: even when you look at the CRC connectivity rules, at the moment they've required batteries to be put in, they've made it mandatory to install solar within the 33 years once you take a connectivity. So under certain guidelines like the 5.2 regulation, if you're taking connectivity, solar has to be installed. So they, they also want their connectivity to be used appropriately. So what you'll see is battery-linked solar installations coming up very quickly, and pure battery installations will be very few.

Ishan Verma

analyst
#89

Sure, sure. One final question about the standalone battery. I just want to know what IRR we expect—what the expected IR is—from that 550-megawatt project, and also what the end-of-life value is for the vessels and for that particular project.

Nikhil Dhingra

executive
#90

The 550 megawatt hour project — right now, the tariff is essentially set. It has been adopted, though with one caveat: construction hasn't begun yet. As for the IRR on that project, since you asked — the IRR again sits in the mid to high teens for this project, because there isn't much transmission infrastructure that needs to go in. It's a 33kV level installation, but the zero date for that project hasn't started for us. So we haven't really finalized the capex, because the state regulator has actually asked about the trading margin of NHPC — since in this case it's pure leasing and they're getting a VGF. So it comes down to whether they should receive a point 5% margin or a 7 paisa margin. That is being debated. So the zero date hasn't yet started for us. We'll be able to update you once the zero date has begun. But broadly, we're telling you the bid return from when we bid it. And also regarding the end of life assumptions — these batteries are basically slated to run for 8,000 to 10,000 cycles.

Nikhil Dhingra

executive
#91

Okay, so on that point — I think it comes down to the PPA. Whether it's one cycle or two cycles, that's what matters. It's either a single cycle or a double cycle, depending on that. This is a really small project within the overall portfolio, since it's 550 megawatt hours. But at the same time, for the other projects we have — 5 gigawatt under construction — those will need roughly 17 gigawatt hours of battery installed. So really it's just this small project you're referring to. It's closer to a leasing model, where you aren't adding any generation storage — you're simply storing the power you get from the discom, from the disk, and then you just discharge the batteries. So that's the kind of thing we have. It's one bit out of a portfolio of 8 gigawatt hours. So we aren't focusing on those bits at all. And as Ankit said, the batteries that are part of the overall solar, wind and FDRE mix — the peak power mix — those will be, you could say, 99% of the CapEx. This is under 1% of the capacity.

Ishan Verma

analyst
#92

Understood, sir. Thanks. That covers what I wanted to ask.

Operator

operator
#93

Thanks. Our following question comes from Dhruv Muchal at HDFC amc. The line is yours — go ahead.

Dhruv Muchhal

analyst
#94

Yeah, thanks a lot. So, when I look at how much your gross block went up this year, it's roughly 3,400 crores year over year, which is about what you've reported, and your run rate EBITDA, I think, would be up by around 300-odd crores. Why? Because last year it was 1,700 crores, and this year it's roughly 2,000 crores. That puts the gross block to better run rate at around 11x, which is far worse than what you normally do. I'm just trying to figure out what I'm missing here.

Nikhil Dhingra

executive
#95

So gross block is up by roughly 3,000-odd crores. Right. On the capitalization side. Right. So as far as the—what you're seeing, or rather not seeing, is this: you could say the wind. Wind really hasn't begun performing yet, first of all, because wind got installed in the—

Dhruv Muchhal

analyst
#96

I believe that's part of your run rate of around 2,000 crore, correct?

Nikhil Dhingra

executive
#97

No, no. Look, run rate EBITDA really relates to the last month — it was commissioned right at the very tail end of the year, I believe, so that's what run rate EBITDA is. What you're referring to is reported EBITDA, or is it the run rate figure?

Dhruv Muchhal

analyst
#98

Regarding run rate EBITDA: in Q3, the reported figure came in at roughly 2100 crores. My understanding is that by that point nearly all of your projects had been commissioned, the wind one included. Perhaps only a modest piece was still left. Or does the gross block number likely take in the battery, which was commissioned by year-end and whose run rate EBITDA isn't included in that? I

Nikhil Dhingra

executive
#99

Yes, that absolutely does. It absolutely does. We’re able to provide the Commission projects for the entire period. Essentially, the run rate EBITDA reflects the 12‑month figure that we have. I believe we don’t have that figure for this year, since the entire cross block won’t be operating across all 12 months.

Manoj Kumar Upadhyay

executive
#100

So out of that 3460 crore, roughly 1000 to 1100 crores relates to the battery.

Dhruv Muchhal

analyst
#101

Right, I think that covers it. Yeah, so that makes it very clear. So thousand — if I take out thousand, the cross block goes up past 2300, and that's what explains it.

Manoj Kumar Upadhyay

executive
#102

Yeah.

Dhruv Muchhal

analyst
#103

Great, so the second question concerns that MNRE clarification you just mentioned. Does that mean, for an FDRE project, if you commission a battery early, the battery can be charged via a non— via conventional power, which is now permitted? Is that the approval we've received, or is it the regulation that has changed?

Nikhil Dhingra

executive
#104

Right, so it can be sold to the merchant. Essentially, selling it outside is permitted. Since this is non-renewable power, you're free to sell it outside to anyone you choose — not just your offtake — as long as you haven't installed renewables behind the battery. It isn't renewable power. So that's the clarification they've given, which was already part of the PP, but they've now made it clear.

Dhruv Muchhal

analyst
#105

To give you one illustration, take an FDR project.

Manoj Kumar Upadhyay

executive
#106

Let me add one point here: even after a solar panel has been installed, if it isn't hooked up to the battery — suppose, for instance, you're a DRE, or you're LT, or your LTA isn't operational at present — you. The majority of our projects are in fact tied to the brownfield power grid, the substation. That means we're able to energize our transmission line. We can energize the project considerably ahead of our connectivity timeline or our TPA timeline. What we're doing is that we're installing the solar, and we're installing the whole power generation side too. But we aren't connecting it, since the moment we connect it, it would be treated as part of FDRE, because right now in the summer the price is very good. We aren't connecting that. We're only connecting the battery and charging it from the grid and selling it. That is giving us a very good return. So we're doing this on purpose. But on the day the COD timeline arrives, when the LTDA LTA date arrives, the whole thing will get integrated and go.

Nikhil Dhingra

executive
#107

And we're also defining the CAPEX on the solar side, since it doesn't make sense to call modules that height and keep them here, because what we're doing is deferring the solar portion of capex. We aren't installing the modules. We are, because of course

Dhruv Muchhal

analyst
#108

You’re able to obtain the less expensive merchant Power via exchanges.

Nikhil Dhingra

executive
#109

Beyond that, interest incurred during construction is avoided as well. Therefore, there's no justification for pursuing solar capex before your LTO is up and running. That's another item we're pinning down, and it's contributing to better returns for us.

Dhruv Muchhal

analyst
#110

Alright. And the final question — you brought up the commissioning goal for your generation assets this year. But could you share the figure you're aiming to commission for generation assets, based on whatever transmission visibility you have, expressed in megawatts?

Nikhil Dhingra

executive
#111

We're aiming at 1.5 gigawatts of projects during this financial year, right? And roughly 10 gigawatt hours of battery. That 10 may be for projects not counted within the 1.5, since for the 1.5 it'll perhaps be 5 gigawatt hours. Even so, we're charging the battery in advance.

Dhruv Muchhal

analyst
#112

Yeah, that's great. Thanks a lot, and best of luck. Thanks.

Nikhil Dhingra

executive
#113

Appreciate it, sir.

Operator

operator
#114

Thanks. We’ll take the next question from Dhruvin Shah at HDFC Securities. Please go ahead.

Dhruvin Shah

analyst
#115

Hello, sir. I believe the earlier question already covered mine, though I just want to make sure about the 10 gigawatt figure you mentioned—the capacity we intend to bring online this year. Of that total, what portion would run on a merchant basis, and what EBITDA margins should we anticipate from those capacities operating on merchandise? That's all.

Nikhil Dhingra

executive
#116

Yeah. So look, in terms of the—all of it will begin other than the, you could say roughly 1,200 megawatt hour to 1,500 megawatt hour, which is going to be commissioned under the FDRE format owing to the NEMA substation I referred to earlier, and the remainder will kick off on a merchant basis during this financial year, since those substations will only begin charging at the very tail end of the year. So you'll see about 8 1/2 gigawatt hours from this. 10 gigawatt hours would be on merchant and 1 1/2 gigawatt hours would be under the FDRE format when it comes to EBITDA realization. Ankit, I'll ask you to…

Ankit Verma

executive
#117

Turning to the EBITDA margin — look, that depends on the cost at which you procure and, naturally, the price at which you sell. But if you assume a tariff arbitrage of six rupees, meaning you sell power at eight rupees, which is of course higher than what we are seeing right now, and buy power at 2 rupees, then give or take, the margin comes to roughly 75 to 80%, or even better.

Dhruvin Shah

analyst
#118

Okay, that was really useful, sir. Thanks.

Operator

operator
#119

Thanks. Our next question comes from Achal Jalan at Lotus Wealth. The line is yours — go ahead.

Aanchal Jalan

analyst
#120

Hi there, and thanks for the question. So, sir, on that first slide, for the portfolio that's under construction, the total comes to 3218 million.

Operator

operator
#121

Apologies for cutting in — you sound far away. Could you move nearer to the foreign top?

Aanchal Jalan

analyst
#122

Can you hear me at this point?

Operator

operator
#123

Yes, please proceed.

Aanchal Jalan

analyst
#124

My question is about the first slide, where the under-construction portfolio is listed at a total of 3280 megawatts plus 1200 gigawatt hours. When will that entire under-construction portfolio be fully commercialized? The whole portfolio.

Nikhil Dhingra

executive
#125

Yes. There's another slide as well, which covers PPAs that haven't been signed yet. But regarding the PPA signing — yes. So these are going to be commissioned by FY28, with putting up happening early, as you mentioned before.

Aanchal Jalan

analyst
#126

Right. Right. Understood, sir — thanks very much.

Nikhil Dhingra

executive
#127

Appreciate it.

Operator

operator
#128

Thanks. The next question comes from Naima Sweta Jail Ramanan Rati. Go ahead, please.

Sweta Jain

analyst
#129

Thanks for taking my question. I have a couple of questions about this best arbitrage we’re discussing. You know, using conventional power and then discharging at peak demand — how long do we see this arbitrage situation should sustain into the future?

Nikhil Dhingra

executive
#130

So that part is really anyone’s guess in terms of that…

Manoj Kumar Upadhyay

executive
#131

I’ll take that one. Yeah. So as things stand, the present CA calculation means you’d need roughly 200 gigawatt hours of battery to get there, assuming no additional solar is added. But there’s also another 40, 50 gigawatts of FDRE, and that tender has already taken place, so those will be added during the daytime. So in practice, as long as you keep adding more and more daytime solar, you’ll need more battery in the unique. So that’s a formula. At the moment that formula says we need 200 gigawatt hours. But what has also happened is that thermal power in the evening is already at 6 and a half rupees if you run at full capacity, and most thermal capacity cannot come up fast and cannot go down. So they operate around 60, 70% capacity. So taking into account their capital cost, the full capital cost in this one, they are around 9 and 10 rupees. So battery will remain. My. My guess is battery will remain at nine to ten rupees during the peak hour time. And as a country we will need around the 200 to 300 gigawatt hours given the current installation and the planned installation of this year.

Manoj Kumar Upadhyay

executive
#132

Still, as we keep adding more and more solar, that number is only going to rise.

Nikhil Dhingra

executive
#133

If you take a look at recent history—over the past few years—what we've observed is that the annual price has stayed at roughly 7, 7 to 8 rupees across those years, even during periods of low demand. Regarding the last few years, demand was comparatively weaker than it had been previously. Yet even in those slower years, we realized peak power pricing at around seven, eight years. But with gas now constrained, it's somewhat elevated, and it's likely to remain elevated, and we're seeing peak demand that is far, far higher than last year. So as Manoji said, for at least around four or five years, we don't see this coming down.

Sweta Jain

analyst
#134

Thanks, that's useful. And then, sir, regarding your point that nearly 80% of our projects would sit on the CTU side of the business — I wanted to get a handle on the transmission and distribution piece. From an industry standpoint, are we seeing a lag in substation connectivity, whether at the state level or at the CTU level? And once we move the portfolio to that 80% mark we're targeting, how do you expect those projects to get commissioned?

Nikhil Dhingra

executive
#135

Look, with the CTU substations, there are a lot of linkages involved. For the most part, they're on schedule when it comes to local infrastructure — bay construction and equipment ordering. The area where they fall behind is the components tied to transmission line interconnection and right of way issues, and that's what creates a timeline delay on their side. The central transmission utility, in turn, depends on the various companies that bid for those works. So their timeline gets set based on the delay from those parties. The CTU is a very structured entity — each quarter they give you a firm date for when their subscription is coming up. As far as we're concerned, we plan our project around that declared date, since it's our obligation to commission the project by then, and we receive an extension until that point arrives. To date, they've done a wonderful job of give and take on a six-month delay. They've done a wonderful job of building out transmission capacity, and we've stayed in sync with that as well — say, a delay of six months.

Nikhil Dhingra

executive
#136

We also attempt to synchronize both our capital expenditure and our activities in line with that. Consequently, as a renewable energy company, functioning is essentially impossible for us absent the transmission infrastructure. That means we must align our timelines. So a delay has occurred. Still, for a grid of this magnitude and scope — the biggest globally, a single Grid, I believe that represents solid performance. Thus, delays of six months ought, I think, to be viewed favorably. Regarding STU, no projects of ours are being built on STU. The wind project in Gujarat was the sole one we have completed using the state grid. Nothing else sits in our pipeline apart from that battery we are putting in on Andhra Pradesh — a very small 550 megawatt hour. No project exists on the state grid. Furthermore, the state grid has a distinct organizational setup that varies across each individual state. Certain states operate more efficiently, others do not. And certain states lack renewable energy potential, so they don't truly expand their grid to the same degree. But states such as Gujarat perform quite well, I have to say. And naturally, when it comes to bringing transmission online punctually, it differs from one state to another.

Nikhil Dhingra

executive
#137

From our perspective, though, state STU isn't something we're factoring in. And when you look at realizing the portfolio, at risk, and all the rest of it, CTU is a far better option — better on curtailment, better on how predictable it is that the substation will come online on schedule, and better on central grants and oversight at every level.

Sweta Jain

analyst
#138

Understood. And one final point: the project blueprints already account, on a nominal basis, for that kind of 6-month delay.

Nikhil Dhingra

executive
#139

Okay. So, what we’re seeing — typically this can’t be generalized. This is at a, this is at a generic overall portfolio level. But with some substations, you could say roughly 60% are on time. The maximum delay is usually 6% months in certain cases, due to some unfortunate event. It could be more. But typically some, like I mentioned, our image substation is on time. Right. Some substations are delayed. So not every substation is delayed. But wherever, wherever it is delayed and we know it from now, we will not call for our modules. We will defer our capex. What can we do about it? I can tell you what we can do about it. We can defer our sizable CAPEX of modules because there is no. No, because modules are available just in time and there is sufficient capacity of that available in India. So we will not call for modules because it’s around 60% of a solar plant CAPEX or in sometimes more. So you don’t do that. You keep the service related work ready, the transmission line ready, the substation ready. Because those are typically you can say 20, 25% of the overall project cost. But these are long lead items.

Nikhil Dhingra

executive
#140

So you go ahead with that, you avoid calling your modules, you keep everything else ready, and that’s how you defer the capex, and that is how the industry has been doing it and syncing up with the power grid or ctu. And also you get extensions too — the good thing is that you don’t incur any penalty because of the delay because of this, because. And that’s how the central renewal program has been running, because it’s in sync with the grid.

Achal Jalan

analyst
#141

Okay, just one final question then. So in those kinds of situations, there really isn't any risk, and so forth. And from the developer's point of view, there wouldn't be any risk when it comes to a PPA not getting signed, or, you know, there being some discomfort, or a lack of eagerness to sign the PPS.

Nikhil Dhingra

executive
#142

Okay, that's a separate question. Look, on the PPA signing side, there are two things at play, right? When you approach a discom for a PPA, what they ask about first is the declared date for your substation, correct? And they want to know the declared date by which that substation will be charged in the near term, right? So if your substation is going to be charged in 2027, a discom will give you better priority, because customers can see your project more clearly, right? But if someone's substation is coming up—if the connectivity they hold is for 2029—then that person gets second priority and doesn't get a seat at the table, right? Because the state will say, I don't want power in 29, I want it in 27. And there are certain ISTS waivers that expire in 2028 as well. So this is what determines how attractive you are to customers, right, in terms of the connectivity date? But if things get delayed down the road, the states don't get penalized either, since they're part of that same sync-up formula under which they also qualify for the ISTS waiver, depending on the original date declared by CTU.

Nikhil Dhingra

executive
#143

So that's a favorable regulatory framework in which basically no one gets penalized for the delay on behalf of CTU. Neither the states nor the developer, correct — gets penalized, since it's something outside their control, right? The only thing a state has to take care of when signing a PPA is what the declared date of that substation is, right? As long as that is 27, they will receive that same window of ISPS waiver which is actually applicable during that particular year, even if the substation is delayed to 28 and 29.

Sweta Jain

analyst
#144

All right, all right, that helps a lot. Thanks very much, sir. Thanks very much.

Nikhil Dhingra

executive
#145

I appreciate that.

Operator

operator
#146

Thanks so much, ladies and gentlemen. That’s going to be the final question for today. On behalf of Acme Solar Holdings, Ltd., this brings the conference to a close. We appreciate your joining us. You can go ahead and disconnect your line now. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete ACME Solar Holdings Limited transcript — plus 133,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to ACME Solar Holdings Limited earnings transcripts and 133,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in ACME Solar Holdings Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.