operatorGood day, ladies and gentlemen, and welcome to the Q2 and H1 FY26 Earnings Conference Call of Afcons Infrastructure Limited, hosted by DAM Capital Advisors Limited. Please be reminded that every participant line will remain in listen-only mode, and following the conclusion of the presentation there will be an opportunity for you to ask questions. If you require assistance at any point during this conference call, kindly signal an operator by pressing "*" followed by "0" on your touchtone phone. Kindly note that this conference is being recorded. I will now hand the conference over to Ms. Bhoomika Nair of DAM Capital. Thank you, and over to you, ma'am.
Bhoomika Nair
analystThanks. Good afternoon, everyone, and a warm welcome to Afcons Infrastructure's Q2 FY26 earnings call. Joining us from management today are Mr. Subramanian Krishnamurthy, Executive Chairman; Mr. Srinivasan Paramasivan, Managing Director; Mr. Ramesh Kumar Jha, CFO; and Mr. Hitesh Singh, Head Corporate Strategy. At this point, I'll turn things over to Mr. Krishnamurthy for his opening remarks, and after that we'll open the floor for Q&A. Thank you, and over to you, sir.
Krishnamurthy Subramanian
executiveThank you, Bhoomika. Good afternoon, ladies and gentlemen. Connecting with our valued investors, analysts, and stakeholders is always a pleasure. I appreciate your joining us today and for your ongoing support of Afcons' journey. Our financial records and investor presentation have been posted on the stock exchanges, and I hope you've had a chance to look through them. With me today are Paramasivan Srinivasan, Managing Director; Ramesh Kumar Jha, Chief Financial Officer; and Hitesh Singh, Head Corporate Strategy. I'll start with an overview of how we performed financially in the quarter ending September 2025. During the first half of FY26, revenue reached ₹6,520 crore, a rise of 3.4% year-on-year, while EBITDA grew 6% to ₹846 crore. EBITDA margin was 13%, an improvement of 30 basis points. PAT for H1 came to ₹242 crore, up 7% from the prior year. In Q2 of FY26, we posted revenue of ₹3,101 crore, slightly above the ₹3,090 crore recorded in Q2 of FY25. EBITDA for the quarter was ₹401 crore, versus ₹427 crore during the same period a year earlier. The EBITDA margin for Q2 FY26 stood at 12.9%, roughly consistent with last year's figure.
Krishnamurthy Subramanian
executiveProfit after tax was ₹105 crore, versus ₹135 crore in Q2 of FY25 — sorry, versus ₹135 crore in Q2 FY25 — which works out to a margin of 3.4%. Even with near-term margin pressure stemming from the mix of projects under execution, our overall profitability for the first half of the first year improved modestly, as EBITDA margin climbed to 13%. Let me now move to the industry. The global infrastructure sector is still dealing with a dynamic and evolving landscape. Geopolitical uncertainties and macroeconomic headwinds have caused investment priorities to be recalibrated across several regions. Even so, we keep seeing healthy project pipelines in select international markets — especially Africa, the Middle East, and Eastern Europe — where governments are putting priority on connectivity, urban development, and water-related infrastructure. In India, the government's commitment to infrastructure development remains strong. Both central and state governments have a healthy pipeline of projects. So far, the current fiscal has seen a moderation in the pace of project awards. We do expect, however, that H2 will bring an uptick on capital expenditure toward roads, railways, urban transit, marine, hydro, and water infrastructure. Afcons' diversified portfolio, strong execution capabilities, and prudent risk management framework put us in a good position to navigate these near-term challenges and help us capitalize on emerging opportunities both in India and overseas.
Krishnamurthy Subramanian
executiveOur emphasis remains on executing intricate, high-impact projects that add real value to national development and the worldwide transformation of infrastructure. Turning now to some recent organizational news, we're happy to report that Mr. Pallon Mistry and Firoz Mistry, who represent the next generation of Shapoorji Pallonji Group, have come onto the board of Afcons Infrastructure. Bringing them in marks an important milestone, strengthening the promoter group's long-term dedication to Afcons and securing continuity in vision as well as strategic direction. We're just as pleased to welcome Mr. Santhosh Nair as an independent director. Mr. Nair carries with him more than four decades of experience across project finance, banking, and insurance. These fresh board additions will deliver invaluable strategic insight, bolster governance, and support Afcons' long-term growth initiatives. Turning to operations, Afcons kept meeting complex engineering challenges head-on and setting benchmarks in execution excellence. First, we hit a major milestone on the Mumbai-Ahmedabad high-speed rail C2 package with the final breakthrough of the NATM tunnel, with Union Railway Minister Ashwini Vaishnaw present. That wraps up 4.82 km of excavation through difficult geology. At Kanpur MRTS, we finished 6.53 km of TBM tunneling, and at Delhi MRTS — the DC-07 package — we completed 11.62 km of TBM tunneling, further cementing our leadership in underground works.
Krishnamurthy Subramanian
executiveFor the financial year 2024-2025, NHPC selected our Pakal Dul Hydroelectric Project as the best-rated construction project among all the other projects currently underway. Afcons keeps earning honors, and has kept earning them, from respected organizations like ET Now Infra, Construction World, and Construction Week — they've named us among the industry's best companies and have also given awards to several of our flagship projects for outstanding quality and execution. To wrap up, I want to restate how dedicated we are to operational excellence, to creating value for stakeholders, and to growing sustainably. Thanks to ongoing backing from our promoters, confidence from our clients, and the hard work of our people, we're strongly positioned to carry forward Afcons' legacy and help shape what infrastructure looks like going forward. Thank you for placing your trust in us. That's all from me — I'd now like to invite our Managing Director Paramasivan to give his remarks.
Paramasivan Srinivasan
executiveThank you, Mr. Subramanian, and good afternoon to everyone. I'd like to warmly welcome all of you joining us on this earnings call. To build on what Mr. Subramanian shared regarding the shifts in our board composition, I'm very pleased to report that Mr. Shapoor Mistry has been promoted to Chairman Emeritus, while Mr. Subramanian has assumed the position of Executive Chairman of Afcons. On behalf of the whole Afcons family, I offer him congratulations on this appointment. In addition, he was honored with a Lifetime Achievement Award at the Construction World Global Awards 2025 — a well-deserved recognition of his exceptional leadership and his contributions to the infrastructure construction sector. Now let me move on to the business environment and how we performed operationally. The first half of financial year '26 brought with it a set of challenges. Work on certain projects was temporarily affected by an extended monsoon and natural calamities. Ongoing liquidity problems with some clients compounded these headwinds. That said, we are working actively alongside clients and authorities to make up for lost progress and rebuild momentum in the second half. Ordering activity has been sluggish during the first half of the year, though we anticipate a substantial pickup in the second half. Order inflow for the first half came in at ₹1,268 crore, and our pending order book remains robust at ₹32,681 crore.
Paramasivan Srinivasan
executiveWe do anticipate that a portion of those L1 orders will convert into actual business during this quarter. Our project pipeline remains robust at roughly ₹3.6 trillion, spanning multiple segments and geographies. We've consistently said that for our industry—particularly for companies such as ours, where the strategic focus differs considerably—comparing the order book on a quarter-to-quarter basis might not be meaningful. It's fair to say that with this strong pipeline and the tendering activity currently underway, we will meet the full order book guidance. Internationally, we anticipate receiving the letter of award for the Croatia railway project prior to the close of the third quarter of this financial year, with LOAs for the road projects coming afterward. We are likewise actively engaged in identifying and pursuing appropriate opportunities across the Middle East—continuing the renewed engagement that started earlier this year—as well as in Africa. As these projects materialize, overseas projects will account for close to 30% of the pending order book. At home, competition has intensified, especially in metro projects. Afcons remains selective and disciplined, concentrating on work that fits our technical strengths and sound risk framework. We're also observing a gradual shift in the government's infrastructure approach, with an increasing proportion of projects being offered through HAM, annuity, and BOT models.
Paramasivan Srinivasan
executiveTo seize these opportunities as a preferred EPC player, we're holding the engagements that are necessary. On the operational side, I'm glad to report that the first consignment of the tunnel boring machine for our C2 project has come in from China. The second consignment, though, has been sitting at the port awaiting clearance for the last two months, and we are actively pursuing the matter with all the concerned authorities and ministries so that it gets released at the earliest. In the Jal Jeevan Mission, especially in Uttar Pradesh, delays in fund flow keep affecting progress. We're in active dialogue with clients to speed up the release of moneys. Despite our best efforts, given the headwinds faced in the first half, including delays in the conversion of L1 orders, our revenue growth for financial year '26 will be below the earlier guidance. We estimate revenue growth to moderate to 10% plus. We had earlier expressed 20% plus, now we are reducing our guidance to 10% plus. In conclusion, while the first half tested our resilience, our fundamentals remain strong. With a healthy order book, with a robust opportunity pipeline, and deeply committed team, Afcons is well positioned to regain momentum in the second half and continue to deliver long-term value to all stakeholders.
Paramasivan Srinivasan
executiveAppreciate it once more for the trust and the ongoing backing. At this point I'll pass things along to Mr. Ramesh Jha, who serves as our CFO.
Ramesh Jha
executiveThank you, sir. Good afternoon, everyone. Before I get into the numbers, let me restate that our quarterly figure fluctuates. The company operates in the construction business. Margin in any given quarter shifts depending on the nature, type, and quantum of work we execute. Quarterly results can differ from one quarter to another and might not be indicative of the annual result or of any trend that could be derived from them. Turning specifically to the numbers, for the half year ended, we have delivered ₹6,520 crore of top line against last year's H1 top line of ₹6,303 crore, which shows a growth of 3.4% on a half-yearly number. In Q2, we achieved a top line of ₹3,101 crore vis-a-vis ₹3,090 crore in the previous year's Q2. That is also a modest 0.4% growth in top line over the previous year's Q2. Now, this modest growth is a manifestation of stretched payment across projects and a few specific projects where certification and payments are getting delayed. Jobs where we were declared L1 quite some time back are still not awarded. Moving on to the EBITDA, for the half year ended, we have done EBITDA of ₹846 crore, which translates in terms of percentage to 13%, and there is a growth of around 6% from the previous year's EBITDA number for the half year.
Ramesh Jha
executiveDuring the quarter, we achieved ₹401 crore. Also for this quarter, we recorded an EBITDA percentage of 12.9%. When calculating EBITDA, BG commission is treated as part of operating expenditure. The EBITDA figure we refer to is after excluding BG commission from operating expenditure. At the same time, other income is included as part of revenue in our EBITDA computation. As we have explained previously, other income should be viewed in the context of our business. Arbitration interest, foreign currency exchange gains, and miscellaneous incomes are recurring and highly integral to our operations, so they need to be treated as other operating income. For the first half, other operating income is approximately ₹161 crore. Now that we have delivered 13% EBITDA in H1, our full-year EBITDA ought to exceed our usual annual guidance of roughly 11%. Typically, we have spoken of an 11% EBITDA margin that we will deliver each year, since construction is full of contingencies, and our effort is always to save on those contingencies and optimize the margin. On many occasions, saving on those contingencies may not be possible. That is why we provide guidance of 11%.
Ramesh Jha
executiveFor this half year, we've already achieved 13%, and we expect that figure to come in higher. On profitability, profit before tax for the half year stands at ₹333 crore, equal to 5.1% of the top line, and that reflects 2% growth YoY. For the quarter, it's ₹149 crore, or 4.8% in percentage terms. On profit after tax, we've delivered ₹242 crore, which is 3.7%. That's up 6.8% from the prior year, and for the quarter we've posted ₹105 crore, or 3.4%. Half-year profits improved thanks to some upside from an arbitration award and also from better margins on a few projects. We were able to save on certain material costs and lift margins on some projects. That is showing up in the improvement in profit after tax. At the same time, let me restate a few of the other points. During this quarter, we took a sizable amount of provisioning on one project, and that's where you'll see our other expenditure running quite high, both for the quarter and for the half year. Even with that, we've delivered this level of profitability.
Ramesh Jha
executiveThe cost of finance has gone up. Our average borrowing cost in H1 FY26 is better than in H1 2025, and also better than what we achieved across the whole of the prior financial year, March '25. During H1, average borrowing rose. Even though we improved the average interest cost on bank borrowing, the total interest cost still increased. Also, interest-bearing advances for the period ending September '25 have moved to roughly 40% of the overall advance component we carry. In September of the previous year, that figure was 20%. The interest-bearing portion of the total advances we hold from customers has simply doubled. As a result, interest cost from customer advances has risen significantly. That is why the overall finance cost has climbed, even though, as I mentioned, we lowered the average interest cost along with BG commission and LC commission, and we also reduced some of the other interest. Overall, finance cost has gone up. We anticipate improvement once our L1 orders materialize, since a large part of that is international orders where advances carry no interest. These profitability numbers come despite our continued accounting for accelerated depreciation on our TBMs.
Ramesh Jha
executiveRoughly 4% of the top line comes from total depreciation. Within that, accelerated depreciation accounts for close to 1.5%. Whatever profit figures you're examining, they come after that accelerated depreciation. As for ROCE and ROE numbers, the ROE figure is likewise after this is taken into account; ROCE for the first half stands at 15% and ROE is around 11%. Naturally, this ought to be viewed on an annual basis. Turning to net working capital, it has gone up. We're seeing delays in certification of work completed and in release of payments across some projects. That has pushed up uncertified work done, which in turn has caused a jump in working capital requirements. I won't go into specifics about any particular project, but many projects have shown payments getting stretched. A few projects have certification and payment issues. Now, on debt, in H1, operations had to be funded. Debt has moved to ₹3,472 crore on a gross basis and ₹2,714 crore on net basis. Measured on net debt basis, the debt-to-equity comes out at about 0.5 times the net worth. On behalf of the Afcons team, I thank everyone for attending this call. Now, I request the moderator to open the floor for Q&A.
Operator
operatorThank you, sir. We'll now start the question-and-answer session. If you'd like to ask a question, you can press "*" and "1" on your touchtone telephone. Should you want to take yourself out of the question queue, you can press "*" and "2". We ask participants to use handsets when asking a question. Ladies and gentlemen, we'll wait a moment while the question queue assembles. The first question comes from the line of Mr. Aditya from Investec India. Please go ahead.
Aditya Jhawar
analystGood afternoon, and thank you. My first question concerns two sizable opportunities that may lie ahead of us: one is Vadhavan Port, and the other is the Dubai tunneling project. It would be helpful if you could share some specifics regarding where these two projects stand and how we should think about their timelines.
Paramasivan Srinivasan
executiveOn Vadhavan Port, the bid has already been submitted by us. The technical bid was opened yesterday. Once clarifications and other matters are handled, the financial bid could be opened. Results could be announced toward the end of the quarter or at the start of the next quarter. That is where things stand with Vadhavan. What is the other one?
Aditya Jhawar
analystWould that be for the breakwater, sir?
Paramasivan Srinivasan
executiveSorry, could you say that again?
Aditya Jhawar
analystThat one relates to the breakwater.
Paramasivan Srinivasan
executiveRegarding the breakwater — that's for the breakwater. As for Breakwater, information about the bidders and other such details is publicly available. On the DSST project, matters are still in progress. The deadline for submitting bids remains some distance off. We're holding active discussions with everyone involved. Past that, there's nothing further I can say at this point.
Aditya Jhawar
analystGot it, sir. Sir, my next question concerns the Mumbai High Speed Rail Project. Could you provide information about how much work has been completed so far and what revenues and margins we would have recorded up to this point? Has margin recognition begun on it, or is it likely to start once we progress a bit further in the project?
Paramasivan Srinivasan
executiveRoughly 15% of the project is now complete. A significant portion of the billing schedule, as you know, sits on TBM tunneling. We've already finished 4.8 km of NATM tunneling, and the lining work is underway. On the TBM side, everyone is aware of the delays tied to machine arrival. The first consignment has arrived, though it isn't the full shipment — the second set still needs to come in so we have everything. Once that happens, TBM tunneling gets started. The turnover will effectively rise as we make progress on TBM tunneling. That's where we stand. On profitability, things are tracking as expected — we don't anticipate any surprises there.
Aditya Jhawar
analystFar, given that 15% of the work has been completed, would we have booked any margins from the project by now, or does margin recognition begin a bit later?
Ramesh Jha
executiveNo — margin recognition generally begins at 10%. One key update here: the High Speed Railway Authority has agreed to treat the TBM arrival delay, along with other matters, as a force majeure condition, which makes the contractor eligible for compensation. They have formally notified us that force majeure has been accepted.
Aditya Jhawar
analystGot it, sir. Excellent. Thanks a lot. Thanks, Aditya.
Ramesh Jha
executiveI appreciate that.
Operator
operatorOur next question comes from Shirom Kapur at Jefferies Group. You have the floor.
Shirom Kapur
analystHello, sir, and thank you for taking my question. I'd like to ask about your L1s. Could you tell us how many L1s you currently hold, and would it be possible to break that down within Croatia between the road and railway work, as well as the other L1s, such as those in Maharashtra — if you could provide that split, please?
Ramesh Jha
executiveSo in Maharashtra L1, it's still those four jobs: Nagpur-Gondia Expressway package 1 at ₹2,599 crore; Nagpur-Gondia Expressway package 2 at ₹2,849 crore; Pune Ring Road — both packages together, package 5 and package 7 combined, come to ₹4,787 crore; Croatia, the first road project is 2,406; the second is 2,144; railway is 6,771. So with that, our total L1 project is roughly ₹23,000 crore. Out of this, we do expect a few of the jobs to land in the current quarter. On Maharashtra, I think on the last call as well, folks were asking — there's a fair bit of uncertainty, since for some of these projects, land acquisition work has only just begun. So within the government there's a debate over whether these projects should be rebid once land acquisition wraps up, or whether they should be awarded and then handled appropriately — that discussion is ongoing. We've been engaging closely with the government, but we'll have to wait and see what the final call is. Okay. That's where things stand on the Maharashtra projects. For all the other projects, we expect them substantially in the current quarter. One or two might slip into the next quarter, early next quarter.
Shirom Kapur
analystGot it, sir.
Ramesh Jha
executiveA portion of this may occur within this very month.
Shirom Kapur
analystUnderstood, sir. That helps. Regarding your guidance on order flow, do you remain committed to the ₹20,000 crore figure for the full year, or are there any revisions to it?
Ramesh Jha
executiveWe are hitting the ₹20,000 crore guidance at 100%.
Shirom Kapur
analystGot it, sir. One last thing, if I may, on the pipeline of prospects you referred to at ₹3.6 trillion: could you break that down for us by segment, and also split it between domestic and international?
Ramesh Jha
executiveMr. Hitesh, a colleague of mine, will walk you through that. Let me just break it down for you. Of that 3.6 lakh crore we've been discussing — the earlier trends were always there — the biggest portion sits in the urban infrastructure project. About 1.6 lakh crore of it is in urban infrastructure. When we say urban infrastructure, we essentially mean underground metro, elevated metro, and bridges as well. Then hydro and underground space, including water works, comes to roughly 94,000 crore worth of projects that we're seeing. Next, the road business, which covers roads and what you call surface transport, is around 65,000 crore, and marine and industrial is around 43,000 crore. That's the segmental breakup. As for the geographical breakup, it's roughly 1/4 and 3/4. So 1/4 comes from the overseas market, and 3/4 comes from the domestic market.
Shirom Kapur
analystUnderstood, sir, and thanks very much. That was quite useful.
Operator
operatorThanks. We’ll take the next question from Mr. Mahesh Bendre, who is calling in from LIC Mutual Fund. Please go ahead.
Mahesh Bendre
analystHello, sir. Thanks very much for the chance. Sir, on the previous conference call, you said you had guided for growth of 20% to 25%. Now we're discussing growth of around 10%. What has shifted over these last six months? See,
Ramesh Jha
executiveWe had given guidance of 20% to 25%, with 20% as the minimum. What has changed since then? First, some of the L1 orders I mentioned to the earlier questioner — we expected those to be converted in the first and second quarter, and for some of them we anticipated the work happening in the second half of the financial year. That's number one. Number two, on some projects there's no visibility regarding payment coming through. Take Jal Jeevan Mission: we were slated to finish that entire project in the current financial year. We had to halt it mainly because payment isn't forthcoming. We're stuck with ₹450 crore of receivables on that project. A few other Indian-funded projects abroad are also seeing somewhat less traction, because the country has defaulted to India on the committed repayments and other matters. Because of that, it's hanging by a thin thread. Along with this, there are issues relating to the environment, not related to us. Due to that, we need to take a cautious step based on our own assessment of the situation. Therefore, we had to consciously reduce certain value of the turnover in some projects.
Ramesh Jha
executiveWith the Jal Jeevan Mission, we'd have made strong progress by now and likely finished it within this financial year. There's still roughly ₹600 to ₹650 crore of work left for us to carry out, and the only reason we can't take it up is that the money isn't coming through. We've met people at every level, including the CM's level and all. So when that payment will actually arrive is something with a lot of uncertainty around it, and we have to protect the company's interests. With that in mind, we've decided to make some of these tougher calls, which could mean lower turnover, but there will be no compromise on our margin. The growth percentage might be affected, but we'll still be growing.
Mahesh Bendre
analystYes. Regarding the revenue we anticipated would be recorded in
Operator
operatorMy apologies for cutting in, Mr. Mahesh. We can't hear you. Would you mind repeating your question?
Mahesh Bendre
analystYeah. Can you hear me now? Hello?
Operator
operatorA bit. Yes, sir. Go ahead now, please.
Mahesh Bendre
analystYeah. Any revenue we might have booked during the last six months — could that revenue be booked in the first half of next year?
Paramasivan Srinivasan
executiveAssuming certain clients’ payment circumstances get better.
Mahesh Bendre
analystAll right. This has nothing to do with anything specific to the company. We deliberately slowed our execution down owing to the payment issue. Is that the right way to
Paramasivan Srinivasan
executiveRight. Right. We haven't slowed down — on certain projects, we've actually halted work. We've demobilized a few projects and issued notice to the client.
Mahesh Bendre
analystSure. Alright. Sure. Thank you. Thanks a lot, sir.
Ramesh Jha
executiveAppreciate it.
Operator
operatorThank you. One quick reminder for everyone on the line: if you'd like to pose a question, just hit "*" followed by "1" on your touchtone phone. Our next question comes from Mr. Shravan Shah of Dolat Capital. The line is yours.
Shravan Shah
analystHello, sir. So let's assume that for this year we'll be doing 10%. Starting next year, in the past we used to have something like 15%-plus. Given that we're doing 10% less, for FY27 can we expect something around 20%, or at this point is that also just a 10%-type figure that one can look at?
Ramesh Jha
executiveFor the upcoming financial year, we'd prefer to stick with the 15% guidance we gave before, since in the second half of the year, orders are going to bunch.
Shravan Shah
analystUp.
Ramesh Jha
executiveOrders are going to bunch up. The rate at which — yeah, go ahead. In the second half of the financial year, orders are bunching up. The speed at which it's arriving: if it lands in the current quarter, then work will begin in the next financial year, with initial-phase installation going ahead. If it arrives in the next quarter, then only post-monsoon will it get started. Depending on that, our guidance of 15% would remain.
Shravan Shah
analystUnderstood. Just to clarify the order inflow: when we mention ₹20,000 crore, that obviously excludes the L1 that we are. So
Ramesh Jha
executiveNo, not every one — Maharashtra's L1.
Shravan Shah
analystPardon me?
Ramesh Jha
executiveLevel 1 of Maharashtra, not counting Level 1 of Maharashtra.
Shravan Shah
analystLeaving out Maharashtra's L1.
Ramesh Jha
executiveLeaving out L1 from Maharashtra.
Shravan Shah
analystCroatia on its own would come in at roughly 11,500 to 12,000. That's what we're weighing, and adding ₹1,200 brings it to about 13 and 1/2, 13,500 crore that we've already got there, with the remaining 7 and 1/2 thousand crore being new money we're looking at.
Ramesh Jha
executiveRight, right.
Shravan Shah
analystAll right, regarding Vadhavan Port — the bid we submitted, that's the HAM one we're referring to, the HAM project? No,
Ramesh Jha
executiveThis is the breakwater for EPC.
Shravan Shah
analystAnd EPC — what kind of value would that be, roughly?
Ramesh Jha
executiveThe estimated value of that client comes to ₹5,120 crore.
Shravan Shah
analystUnderstood. Regarding our EBITDA margin guidance, we said at the outset that it would be better, obviously. Will it be something like 13% for this year, and then from next year onward, will we again be looking at guidance of around 11%?
Ramesh Jha
executiveLook, as we explained, on an annual basis the guidance we're trying to give is 11%, because we've explained there are many risks in projects. Our endeavor is always to improve, and we've demonstrated that as well. For even FY25 and even for this half year, we've done in the range of 13%. Since we've already done 13%, we expect the full-year number to be better than what we initially indicated. The exact number — let's leave it at this point in time, because it wouldn't be appropriate for me to give it for the balance six months. One thing I can reassure you of is that we don't have any bad project, or we don't have execution in the second half that will be less profitable. We are definitely going to improve from the annual guidance number we've given. For the next year, it's too early to give any guidance on profitability metrics, but on a sustainable basis, we'd like to do 15% top line growth and an 11% EBITDA number.
Shravan Shah
analystUnderstood. Understood. Finally, regarding capex, what amount would we be recording for this year, and at a broader level, what would it be next year, and also the balance sheet data points — mobilization advance, retention money, and unbilled revenue as of September? Let's see,
Ramesh Jha
executiveRegarding capex, for this year we've planned approximately ₹1,100 crore, and that's mostly the TBM for the C2 package — half of it has already arrived, and the second consignment hasn't started yet. Once that shows up, it's a sizable chunk. The remaining capex we had planned is tied to the project award. As soon as we secure the project award, we'll carry out that capex in connection with it. That's the picture for this year. My expectation is that out of the ₹1,100 crore we estimated, a portion will spill into next year, because if orders come in, say, Q3 and Q4, then procurement and the orders themselves will be placed according to our requirements. Some part will land in FY27. Originally, when we put together our budget for '26, we were envisaging roughly 700, ₹750 crore of capex for '27. Should something not get done this year out of that ₹1,100 crore, it will be added to next year's capex.
Shravan Shah
analystWhat would the mobilization advance, retention money, and unbilled revenue be as of September, sir?
Ramesh Jha
executiveLook, those figures are already uploaded—they're included in the presentation. Those numbers are already sitting there. Unbilled revenue, and naturally these retentions, fall in a comparable range to what existed before. The retention figure hasn't risen from, let's say, what we had in March or in June. It sits in a comparable range because on some projects, as we finish them, retention gets released, and on ongoing projects there's regular recovery of retention. Unbilled revenue, once again, is in a comparable range to what was there in, say, June or March. It's in a comparable range, that's where it is. The third item you asked about concerned mobilization advances. On mobilization advances, since the jobs haven't been awarded, we haven't gotten those advances. Quite the opposite—on the ongoing jobs, whatever advances we'd received before, recoveries are taking place. A sizable amount of mobilization advance—if we compare from, say, March '25 to September—the advances have declined owing to the recovery.
Shravan Shah
analystUnderstood, sir. Thanks.
Ramesh Jha
executiveThanks.
Operator
operatorThanks. Attendees, if you'd like to pose a question, just hit "*" and "1" on your touchtone phone. Our following question comes from Mr. Parvez Qazi of Nuvama Group. The line is yours.
Parvez Qazi
analystHello there, good afternoon, and thank you for taking my question. My first question concerns the pipeline of bids. You said our bid pipeline is strong. So for H1, I was hoping to get some detail on the additional bids that have, say, been added into this pipeline. Which segments saw new projects join the bid pipeline over the last six months, and some detail as well on geography — whether domestic or overseas — where these new projects originated? That would be great.
Krishnamurthy Subramanian
executiveParvez. The additions were mostly in the urban infrastructure area. Some projects the government announced have been added in. A few projects also came in on hydro and underground. That's really been the main shift. And as tendering keeps moving along, some announced projects were dropped, while new ones came in through the normal course of business. That's the change behind the increase. Domestic and overseas — the ratio was pretty much the same last time too. It was 1/4 and 3/4. That same ratio holds in the overseas market as well, domestic and overseas.
Paramasivan Srinivasan
executiveOn your other question about geography: at one point, we had essentially pulled back from the Middle East. After getting some clients to agree to certain changes in contract terms and other matters, we're now re-engaging in the Middle Eastern segment, and we do expect some good traction there going forward.
Parvez Qazi
analystYes, sir. Next, how would you characterize the level of competition for projects overseas? Is it your expectation that competition there will be lower than what we're experiencing in the domestic market?
Paramasivan Srinivasan
executiveYou can't make a blanket statement about how intense competition is overseas. Competition looks different depending on which geography you're in. It comes down to the client, the funding agency, and how many competitors are in the mix. So I don't want to offer a general answer to that, beyond saying that competitive intensity exists everywhere. You have to pick your client, and also the preferred mode here, the preferred country and the client, I'd put it that way.
Parvez Qazi
analystOkay, sir, and finally, just a couple of figures I was after. First, how much capex did we spend in Q2? And second, out of that 32,700 crore order book, how much of it is projects where the appointed date hasn't come through yet? Thanks.
Paramasivan Srinivasan
executiveOn capex, we've spent close to roughly ₹200 crore as of September. Regarding that ₹32,000 crore order book we hold as of September, you want to know whether appointed dates have been given for these contracts?
Parvez Qazi
analystSo do all of these projects fall under execution, or are there some where we've gotten the LOA but the appointed date hasn't arrived yet?
Paramasivan Srinivasan
executiveNo, every one of these projects is already being executed. There isn't a single project where we haven't received an appointed date or a notice to proceed.
Parvez Qazi
analystAbsolutely. Appreciate it, and I wish you the very best, sir.
Ramesh Jha
executiveThanks.
Operator
operatorThanks. Attendees, if you’d like to ask something, just hit “*” and “1” on your touchtone phone. Our next question comes from Mr. Balasubramanian A at Arihant Capital. Go right ahead.
Balasubramanian A
analystGood afternoon, sir, and thank you very much for the chance to speak. Sir, how much exposure do we currently have in UP Jal Jeevan Mission when it comes to receivables? As I recall, last quarter it stood at roughly ₹422 crore. What would be a realistic timeline for expecting those receivables?
Paramasivan Srinivasan
executiveOn Jal Jeevan Mission, our exposure stands at roughly ₹450 crore, at nearly the same level. We received some funds along the way — small amounts. From July onward, we essentially halted work there. Right before Diwali, the Chief Minister held a meeting and so on. Our exposure is unchanged. We still have unexecuted work remaining of about 600 to ₹650 crore.
Balasubramanian A
analystSir, how do you see the working capital cycle shaping up by the end of this year, given the impact from Jal Jeevan?
Paramasivan Srinivasan
executiveLook, with Jal Jeevan Mission, the effect is already accounted for. Since we aren't allocating additional funds there, my view is that from this point it can only get better. And broadly speaking, funding of projects is typically needed through H1. Now, as we move closer to the end of the year, the situation should steadily pick up, because customers have their own budgets and those need to be used up within the financial year. Payments will come in from the customer, and matters will unwind.
Balasubramanian A
analystSir, sir, of that ₹1,100 crore capex, what portion goes to these two tunnel boring machines, and when should we expect them to be effectively deployed into the projects?
Paramasivan Srinivasan
executiveLook, the precise figure isn't something we can provide, but that number falls somewhere in the range of 600 to ₹700 crore for these TBMs together with all the attachments they need. It hinges on when the second consignment sails out of China. Our hope is that it happens this month. Should it depart China this month, then I think around end March or perhaps April, we ought to begin the executions.
Balasubramanian A
analystSir, sir — if the TBM machines keep getting delayed, which other projects will that affect over the next two or three quarters?
Paramasivan Srinivasan
executiveAs for C2, that’s the sole project — the high-speed railway’s undersea tunnel. For every other project, our TBM is already on site.
Balasubramanian A
analystSir, sir, my last questions — what strategic initiatives will you take in order to bring down promoter pledging? What's the road map? I'm not clear on your question. Sir, what strategic initiatives are you going to take for reducing promoter pledging? What is the road map?
Paramasivan Srinivasan
executiveRegarding promoter pledging, no initiative is being taken on our side. That matter rests with the promoter, and it wouldn't be appropriate for us to comment on it.
Balasubramanian A
analystThank you, sir.
Operator
operatorThanks. For anyone who’d like to ask a question, please press "*" and "1" on your touchtone phone. Once more: if you want to ask something, press "*" and "1" on your touchtone phone. Our next question comes from Ms. Bhoomika at DAM Capital. Please go ahead, ma'am.
Bhoomika Nair
analystGood afternoon, sir. Sir, regarding this margin profile, we've observed a quite strong 1H margin of almost 13%, which is considerably above our guidance, so to speak. For this year, how do you expect margins to trend, especially in the second half? Given that some of these conversions from L1 to actual time to begin work are delayed, will that have an effect on the margins we've quoted for some of these projects, or are they escalation-based, fixed price? Could you just shed some light on that?
Paramasivan Srinivasan
executiveNo, regarding margins, my CFO will answer. Regarding this matter, on the Maharashtra projects, if you look at it, an escalation mechanism exists starting from the day we submitted the bid. In fact, it begins 21 days prior to bid submission onward. Okay. As for the overseas project where we are L1, the contracting timelines and award timelines themselves are like this — 120 days from the date of bid opening, all of these are specified. So it's all already factored in, and we don't anticipate any impact on margins or related matters. On EBITDA guidance, Ramesh would respond. Look, Bhoomika, we've already discussed the EBITDA margin we achieved for the half year, 13%. As confirmed earlier as well, we don't have any bad project as such in this Q2 in the second half, or any less profitable activity to be executed in the second half. We expect our EBITDA margin to be better than what we indicated at the start of the year at 11%. It should definitely be better, because for the half year we've already done 13%. An exact number, we're not giving you, but I think we can expect that we should be doing better than what we had indicated.
Bhoomika Nair
analystYes, thank you. In this quarter as well, other income came in a bit higher. Did you book any forex gain or arbitration-related amount during this quarter?
Paramasivan Srinivasan
executiveLook, there is a forex gain in this quarter. Regarding the overseas project you asked about, what happens with an overseas project is that even though we don't get any escalation on the majority of the project, the exchange gain then arrives as an escalation measure, because continuously we're seeing, say, a dollar or a euro appreciate against the Indian rupee. In some of the projects, over a period of say 5, 6 years, we have seen the exchange difference itself become a very sizable portion of the contract. Likewise, things accrue. It is there in this quarter as well.
Bhoomika Nair
analystAll right. Could you share the amount of forex gain tied to the projects for this specific quarter?
Paramasivan Srinivasan
executiveGive me one minute on that figure. The forex gain comes to roughly ₹59 crore.
Bhoomika Nair
analystAll right, I understand. Just one final point, sir—I know we've covered quite a bit during this call regarding the increase in working capital and, as a result, the rise in debt as well. Although we'll receive some of those advances once certain orders come in, that ought to assist with bringing it down. Given the funds tied up specifically in these JJM orders, are we anticipating any relief at all during this year, or do you believe working capital will stay elevated to that extent?
Paramasivan Srinivasan
executiveOn the Jal Jeevan Mission payment side, we can't make a commitment at this point, but the Chief Minister personally has given his assurance that every outstanding amount will be settled, since he wants the project finished properly and on schedule. That's something I believe is being handled at the state level. So we do expect some momentum to build over the next 2 to 3 months. State-level finances right now are, I'd say, stretched. That's probably why there's been some delay. I'm not entirely certain. I can't really comment.
Bhoomika Nair
analystAlright.
Paramasivan Srinivasan
executiveBhoomika, just to add — look, back in September we were sitting at a comparable debt figure, so this isn’t a different number. You’ve already seen the way it played out by year-end. That’s the pattern. Typically, that’s how it goes.
Bhoomika Nair
analystGot it. That's a fair point. That's helpful. Thanks very much. Thank you. Thank you.
Paramasivan Srinivasan
executiveI appreciate that.
Operator
operatorThanks. Our following question comes from Parvez Qazi of Nuvama Group, who is on the line. You may proceed.
Parvez Qazi
analystHello, and thanks for letting me ask a follow-up. I believe you said earlier that this quarter we recorded certain exceptional expenses within other expenses. Could you share how much that amount came to?
Paramasivan Srinivasan
executiveParvez, what's your question?
Parvez Qazi
analystHow much did that exceptional expense come to?
Paramasivan Srinivasan
executiveThe figure is nearly ₹100 crore.
Parvez Qazi
analystAll right, of course, and thank you.
Paramasivan Srinivasan
executiveI appreciate that.
Operator
operatorThank you. Everyone, that wraps up the questions for today. At this point I'd like to pass the conference to Ms. Bhoomika, who will offer closing remarks. Please go ahead, ma'am.
Bhoomika Nair
analystYes. I’d like to express my appreciation to everyone joining the call, and especially to the management for the chance to host it. Thank you very much, sir, and I wish all of you the very best. Do you have any closing remarks from your side?
Paramasivan Srinivasan
executiveMuch appreciated. We're grateful for the ongoing interest and backing. We certainly hope each of you remains with us and benefits over the long term. Thank you.
Krishnamurthy Subramanian
executiveThanks very much, sir.
Operator
operatorAppreciate it, sir. That brings this conference to a close on behalf of DAM Capital Advisors Limited. Thanks for being with us, and you're free to disconnect your lines at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Afcons Infrastructure Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Afcons Infrastructure Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Afcons Infrastructure Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.