Afcons Infrastructure Limited (AFCONS) Earnings Call Transcript & Summary

May 19, 2026

National Stock Exchange of India IN Industrials Construction and Engineering earnings

Earnings Call Speaker Segments

Kishan Mundhra

analyst
#1

Hello, and thank you, Alaric. Good morning to all of you, and a very warm welcome to the Q4 FY26 earnings call for Afcons Infrastructure. Joining us today is the management team: Mr. Paramasivan Srinivasan, our Managing Director; Mr. Ramesh Kumar Jha, the CFO; and Mr. Hitesh Singh, who leads Corporate Strategy. At this stage, I'll pass the floor to management for their opening remarks, and after that we'll open things up for the Q&A. So, over to you, sir.

Paramasivan Srinivasan

executive
#2

Thanks, Kishan. Morning, everyone. I want to welcome all the investors, analysts, and participants to the Q4 and Financial Year 26 earnings conference call of Afcons Infrastructure Limited. We appreciate the continued support and participation you show us today. The financial results and investor presentation for the quarter and year ended March 26 are now up on the stock exchanges, and I hope you've had an opportunity to go through them. Joining me today are Mr. Ramesh Jha, our CFO, and Mr. Hitesh Singh, who heads Corporate Strategy. Financial Year 26 turned out to be a difficult year for the infrastructure sector, and our overall performance for the year stayed well short of what we had expected. To every investor, I want to say sorry: for the first time since we began releasing quarterly figures back in 2010, we posted a loss this quarter. We see it as an exception—and honestly, it wouldn't be out of place to say here that these results have left me personally deeply upset, and I'm sure this is either an aberration or a one-time exception, and it will change. Revenue for the year came in at ₹12,322 crores, a 5.4% decline year-on-year. EBITDA was ₹1,439 crores, and even with that moderation in performance, we kept EBITDA at a healthy 11.7%; that remains among the better margins in the industry. Profit after tax came in at ₹257 crore, compared with ₹251 crore once we set aside ₹76 crore tied to a one-time hit from putting the new labor code into effect. Leaving that aside, PAT works out to ₹327 crores. Turning to the fourth quarter, revenue reached ₹2,777 crores and EBITDA was ₹170 crores. We ended the quarter with a net loss of ₹89 crores, which reflected project-specific developments, provisions, and one-time factors arising during the period. Across the year, ordering activity fell short of expectations in a number of segments, project conversion was delayed, tender evaluation stretched out, and execution was disrupted in certain projects. For the year, our revenue was further affected by ongoing liquidity limitations on the client side, and that held back execution momentum on certain projects for a longer period than we had expected. On top of that, some projects overseas saw temporary disruption in the fourth quarter because of geopolitical developments in the region. A handful of projects we had expected to ramp up in Q4 were also pushed back as a result of changes related to design and alignment. All of this together had a significant effect on revenue growth and profitability for the year. Even so, we still see these as mostly timing-related and external in nature, not structural problems in the business or in how we execute. Even with those obstacles, we're still advancing on a number of strategic and operational fronts. Over the course of the year, the HRRL Crude Oil Terminal Project at Mundra—which forms part of one of India's biggest integrated refinery and petrochemical complexes—was commissioned, a sign of our expanding abilities in industrial and energy infrastructure. We also had multiple infrastructure projects that Afcons finished during 26 go into operation and be inaugurated, among them sections of the Bangalore Double Decker Metro and Flyover Corridor tied to the elevated metro project currently in progress. This portion was constructed in Bangalore, one of the globe's most congested live-traffic settings, and caused minimal disturbance to the city's traffic; beyond that, trial runs succeeded on our Agra and Kanpur Metro project, and the Delhi-Meerut RRTS Corridor, on which Afcons handled two packages, now runs in full. Throughout the year, our delivery capabilities and institutional strength continued to earn recognition as well. Engineering News-Record USA ranked Afcons 8th worldwide in the Marine category and 12th among International Bridge Contractors, a result that strengthens our standing in technically demanding infrastructure segments. We also received the prestigious MIKE Award, marking our eighth straight year and, when MIKE and MAKE are counted together, the tenth year in total—a sign that knowledge management and innovation practices are now embedded throughout the organization. On our internal business, I'm glad to report that the proposal has come through for the rehabilitation and construction of the railway line project in Croatia, where we were named L1 last year. We anticipate the related formalities will wrap up soon. As we recently told the stock exchanges, the client has canceled the two Croatia road tenders in which we were declared L1, citing budgetary constraints. Although that news is disappointing, our confidence in the region's long-term opportunity remains intact. Regarding the Mumbai-Ahmedabad High-Speed Rail C2 project, the second shipment of the tunnel boring machine—which had been delayed for a number of months—has at last arrived on site. Assembly work is moving along nicely, and the main drive has already been placed down into the shaft. Tunneling is anticipated to begin prior to the close of the coming quarter. Turning to order inflows for the financial year, we booked fresh orders totaling ₹4,125 crores, not counting roughly ₹3,800 crores in variation and change orders on projects already underway. Order intake came in lower than we had anticipated, mainly because several sizable project awards were pushed back and because it took longer than expected to turn L1 positions into firm orders, with the fourth quarter especially affected. As you're likely aware, we have booked approximately ₹8,000 crores in orders and have declared L1 on roughly ₹7,000 crores of additional new orders during this financial year to date. We anticipate those L1 orders will be converted during the current quarter. As a result, the order booking guidance backlog from last year will be fully covered within the first quarter of this financial year; that said, we have witnessed encouraging movement on a number of these opportunities across both domestic and international markets over recent weeks. The opportunities we can pursue are still strong in our main areas — transportation, marine, underground, hydro, water, and industrial infrastructure. With roughly ₹15,000 crore of orders already certain this financial year, including L1, we anticipate securing an additional ₹15,000 crore in orders, which puts our total order booking guidance at ₹30,000 crores for the current financial year. Because geopolitical uncertainty persists, award cycles continue to stretch out, and project-related developments are still unfolding, we believe it is prudent to defer providing specific revenue growth or EBITDA margin guidance for Financial Year 27 until visibility becomes clearer. To wrap up, Fiscal 26 was plainly a difficult period operationally, but our belief in the company's long-term fundamentals remains the same. Our spread across industries and regions, strong ability to execute, a robust set of opportunities ahead, and a measured stance on expansion mean we are positioned well to navigate today's conditions and capture opportunities as sector conditions get better. With that said, I'll now turn things over to our Chief Financial Officer, Mr. Ramesh Jha, who will take you through the financial results in greater detail. Thanks to everyone.

Ramesh Kumar Jha

executive
#3

Thanks very much, and good morning to all of you. Before I turn to the figures, I want to restate that the number we post each quarter does fluctuate. Ours is a construction business. Margin in any given quarter moves around based on what kind of work gets executed and how much of it. So results for one quarter can look different from another, and they may not signal where the full year is heading or what the trend is; let me now go to the specific figures. Total income for Q4 FY26 stood at ₹2,777 crores. That works out to 18% below Q4 FY25, a quarter in which we had posted ₹3,387 crores. Across the whole financial year, we posted ₹12,322 crores, which represents a 5.4% decline versus the prior year, 25, when the figure was ₹13,023 crores. So looking at Q4 in particular, what we observed was that customer payments simply weren't arriving. For the bulk of our customers, the payment flow was far from smooth. We also kept providing working capital funding for projects during Q4, and given those conditions, we made the call to strike a balance between putting money into projects and preserving our liquidity. We did fund projects, but only up to a certain limit — we deliberately stopped short of going past a particular threshold so that we wouldn't become overexposed to any single customer. That cap ended up constraining our turnover on certain projects. On top of that, in Q4, following the war, we ran into POL and gas-related problems affecting project consumables, along with logistical difficulties. This was mainly in the overseas market, and it disrupted the progress we had planned. Typically, Q4 has delivered turnover that's at least 15% to 20% higher than what we see in Q2 and Q3, and customers paying on time supports that. The resulting economies of scale give us a meaningful profitability lift in Q4, which then shapes the full-year performance. This year, though, the effect ran the opposite way. That was among the factors that weighed on the bottom line during the year as well. For the full year, turnover came in at ₹12,372 crores, a decline from last year's top line. Planned turnover from a range of projects, both domestic and overseas, was not achieved this year. To sum things up at a high level, the revenue growth was mainly held back by payment problems, L1 orders that didn't get converted, certain fast-track projects that weren't taken up, and an unexpected geopolitical issue. Turning now to EBITDA: in Q4 we posted an absolute figure of ₹170 crores, which came in substantially below the ₹415 crores recorded a year earlier. As a percentage, Q1 stood at 6.1%. For the full year, EBITDA came to ₹1,439 crore in absolute terms, or 11.7%, versus last year's ₹1,662 crores at 12.8%. Compared with the prior year, that figure declined roughly 13.4%. In computing our EBITDA, the BG commission is treated as an operating expense. So the EBITDA we refer to is calculated after taking out the BG commission as an operating expense. Over this year, because interest rates fell overall, finance cost went up even though — and I will get into that once I reach finance cost; beyond that, when we calculate EBITDA, other income is counted as part of revenue. As we have said previously too, our other income is very closely linked to the business. Arbitration-related interest, gains on foreign exchange, and various other income streams come up repeatedly; since they're deeply woven into how we run the business, they should really be viewed as other operating income. For the full year, a substantial ₹374 crores sitting inside other income must be reclassified as other operating income. Moving now to profit before tax: over the entire year we posted ₹387 crores in PBT, equal to 3.1% of revenue. That's lower than FY25, when the figure stood at ₹710 crores, or 5.5% a year earlier. Turning to profit after tax, Q4 shows a loss of ₹89 crores. That said, for the full year, profit after tax stands at ₹251 crores, which works out to 2% of the top line, whereas in FY25 we had delivered ₹487 crore, at 3.7% of the top line. Quarterly profits were hit severely by sizable provisioning on one project. On another project, we absorbed substantial additional cost on marine operations. Both of these are essentially one-off events. Beyond that, in certain projects where we anticipated crossing the margin recognition threshold — typically across all projects, only once we hit a turnover threshold of around 10% do we begin recognizing profit. In a few recent projects, we were unable to cross the margin recognition threshold we had expected in Q4. We just barely missed hitting that threshold, which meant the margin wasn’t able to be recognized. Beyond that, the loss for the quarter was driven by under-recovery of fixed costs caused by lower turnover, along with increased finance cost resulting from working capital being tied up. For the full year, in addition to those factors that weighed on Q4 profitability, a one-off exceptional item tied to the labor code was another significant impact. Turning specifically to the increase in finance cost, we continued to encounter payment-related difficulties throughout the year. In FY26 our average borrowing cost came down versus FY25, driven by lower interest rates and, of course, by the improvement in our credit rating too, yet average borrowing during the year went up compared with the prior year. Consequently, total interest expense is higher, and that mirrors blockages in working capital. So although the average cost improved, interest on bank borrowing has gone up. Also, interest-bearing advances for the whole year FY26 came to roughly 40% of total advances from customers, and while in March 25 that figure was also around, let's say, 38% or 39%, the interest on customer advances didn't apply for the full year at that 40%, since it climbed gradually from about 20% in September 24 to roughly 38% or 39% by March 25. So for interest-bearing advances, last year there was no full-year effect, while this year nearly 40% of overall advances carried interest; that had an impact, and interest from customer advances went up in this financial year. As a result, interest on customer advances rose, pushing overall interest cost higher. We expect things to get better once a number of locked-up assets are realized — we're at a very advanced stage on many projects right now — and also when interest-free advances come in, mainly from international orders. On depreciation, we keep accounting for accelerated depreciation on our TBMs. Out of the total ₹454 crores, normal depreciation accounted for about ₹289 crores, which is 2.33%. The remainder comes from accelerated depreciation. On tax, the rate on Afcons profit is roughly 35%. That's higher than one would typically expect. It stems from some of the JVs where we paid tax in the 35% to 36% range. Also, in some overseas locations such as Bangladesh and Gabon, tax is levied on turnover. So in that scenario, when your profit doesn’t go above the threshold, you’re forced to write off the additional tax — and that’s what happened in places like Gabon and Bangladesh. On top of that, we needed to take a provision in one JV entity, and that reduced consolidated profit while also lifting the effective tax rate. Then, specifically regarding ROC, we’ve already discussed the larger provision in one project stemming from an arbitration development, added cost on a marine operation in one of the projects, and margin not being recognized in a few projects since the turnover threshold wasn’t met, along with fixed costs being under-recovered because of a lower top line. Every one of these factors has weighed heavily on profitability, and that naturally flows through to ROCE and ROE; for FY26 we posted ROCE of roughly 20 12% along with ROE near 5%, a fairly weak level. Turning to debt, gross debt held around the same level as September and December, at ₹3,538 crores, and net debt came in at ₹2,653 crores. Measured on a net basis, the debt-to-equity ratio works out to approximately 0.49 times net worth; those are the figures. Speaking for Afcons, I appreciate everyone taking part in today's call; I'll now hand things to the moderator to begin the Q&A session.

Shravan Shah

analyst
#4

Hello, sir, and thank you. Sir, you've attempted to lay out several explanations for why our results ranked among the weakest quarters in our entire history. I'd still like a bit more clarity on that. During our call on February 11th, after the third-quarter results came out, we sounded fairly confident that we could deliver revenue growth of at least 5% across the whole full year. That implies we would have posted something like 19% to 20% growth in the fourth quarter, whereas what we've actually seen is a 19% decline in the fourth quarter, along with roughly 5% degrowth for the full year as well. I'm simply trying to understand how, even midway through the quarter, we felt so confident, and then what went so badly wrong that we ended up missing so significantly on execution?

Ramesh Kumar Jha

executive
#5

That's right. Look, what we've been saying is that this rested on, say, 15, 20 years of experience. What happens is that in Q4, we've observed customers releasing all payments up to date. That's been our experience for a good while. This year was an exception where we saw a slowdown when it came to payment, and payments weren't forthcoming. That had an impact; we had to pick between growth and preserving liquidity; so we didn't take that aggressive call to chase top line growth. Then, in the middle of all that, the war began, and that hit supply chain management severely. You know that even this year we've done close to 30% from our overseas projects, even though the order book is lower when it comes to order book composition, domestic versus overseas, but when it comes to turnover, we keep doing around 30% from the overseas market. A number of the countries where we operate aren't that big economies where they've got larger amounts of oil reserves. Operations were severely impacted in the month of March. POL-related stuff and logistics-related stuff, we couldn't send material to the project site. This had a severe impact. Even in the domestic market, you're aware that many of our projects sit at remote locations. Availability of gas was a real problem.

Shravan Shah

analyst
#6

All right, understood, sir. So once more, we're midway through this quarter. First off, clearly, and do correct me if I've got this wrong, for the full year FY27 we aren't giving any revenue guidance. If that's true, then for this quarter, Q1, as things stand so far and considering whatever the constraint is, the payment-related problems, all of it, is it possible to see growth in Q1 FY27, this quarter? You

Ramesh Kumar Jha

executive
#7

Look, what we've communicated is that right now, given the geopolitical circumstances and since conditions remain unchanged, even within the domestic market we're receiving quite conflicting signals. We're being told energy prices will rise considerably, and we haven't observed any meaningful improvement in the payment situation. Although, as I mentioned before, we're at a very advanced stage of collecting some of those stuck payments, supply chain-related problems persist at the same time, so it wouldn't be prudent for us to provide any guidance as such for the full year or even for the Q1.

Shravan Shah

analyst
#8

Okay. Understood. The same applies to margin as well — although our usual long-term guidance is 11%, at this moment we won't really be providing any guidance on that front, right? Look, we're not saying

Ramesh Kumar Jha

executive
#9

We aren't providing any guidance on the margin side either, since we still need to see how things actually play out. In many overseas locations, we've observed that petrol and diesel prices rose considerably during the war period in March and April. Prices went up. In some places, such as Bangladesh, elections were taking place, and until those elections happened, prices stayed stable, but following the results, they increased. That's the kind of situation we're watching. You know that in many overseas locations, our contracts are fixed-price. We need to see how well we can recover this escalated cost from the customer. We've explained before as well that generally in overseas markets we try to maintain risk and contingency, but at the same time, we aren't very certain to what extent those risk and contingencies will be able to handle the escalated cost.

Shravan Shah

analyst
#10

Finally, sir, regarding inflows, I just want to make sure we have the right figure. How much value of inflow have we received in the LOA since 31st March? Naturally, we would also like to know whether you can give it in terms of the L1 as well. What I understand is Croatia, which would be roughly 7,800 crore, and the Vadhavan one, which is roughly 5,300 crore. It comes to something like 13,000 crore, so it would be better if you could specify the number. We are saying that by June we would be getting a 15,000 crore LOA. That is one point. Second, in addition, we will be getting 15,000 crore more in inflow, so the total would be 30,000 crore for the whole of FY27. Yeah.

Ramesh Kumar Jha

executive
#11

You’re right, and we’ve already told the exchanges that we were chosen as contractor for that project. On top of that, you know there’s social media chatter that for a couple of projects we’ve been declared L1. Because we haven’t disclosed that to the exchanges, I can’t give you the exact details, but you know there are projects where we’ve come out as L1.

Paramasivan Srinivasan

executive
#12

We also have an underground metro project for DMRC worth ₹373 crores, and that one is already secured by us.

Ramesh Kumar Jha

executive
#13

With that ₹8,000 figure, roughly 50% of it already has clear visibility behind it.

Shravan Shah

analyst
#14

To start with, understood. Regarding capex for the full year, now with FY26, I believe the TBM cost would be moving into FY27. How should one view the FY27 capex?

Ramesh Kumar Jha

executive
#15

FY27, we are looking at a capex of around ₹725 crores.

Shravan Shah

analyst
#16

Okay. That's it from my side. Thank you. Thank you.

Ramesh Kumar Jha

executive
#17

Thank you.

Ankita Shah

analyst
#18

Hello. Sir, I'm going back to your previous conference call, when you said that almost one third of your Q4 target had already been reached within the first 40 days. Most approvals connected to project delays had been settled. Execution was expected to normalize starting in 4Q, and margins of 11% looked sustainable. Given all of that commentary you provided, what was it that you didn't anticipate, which affected the remaining 50 days of project execution and margins? Which key projects were the ones that actually had an impact here, and that you didn't see coming?

Ramesh Kumar Jha

executive
#19

Look, first, we should recognize that Q4 is always going to be a sizable portion of any year. Then in March, we saw a significant drop, which was due to supply chain disruption and energy-related challenges, as I explained earlier. In many places, vendors were requesting advance payment before they would commit. Even when advance payment was given, in many places the goods were not available. That turned into a major constraint. As I explained, almost 1/3 comes from overseas markets, and those countries do not have that kind of energy reserves. That had a severe impact. Some projects, even in the domestic market, were badly affected in March; this is something we were not expecting. Also, some of the fast-track projects, we were expecting progress because of the kind of discussion we had, since these were all private customers as well. We were expecting things to ramp up, but then it did not pick up.

Ankita Shah

analyst
#20

Is it fair to read this as saying that a big chunk of that impact came from your international projects — the large part?

Ramesh Kumar Jha

executive
#21

A big part of this comes from the international project, and as I said earlier, look, payment needs to be something that keeps things moving. This got stuck. That has really limited how far we can put money in ourselves beyond a certain point.

Ankita Shah

analyst
#22

Okay, so what share of the impact comes from domestic projects versus export — I’m assuming everything was affected?

Ramesh Kumar Jha

executive
#23

In the domestic market, if you had to attach a rough figure, perhaps around 25% or so, those projects were affected.

Ankita Shah

analyst
#24

All right. Since conditions haven't changed, do you expect this problem to persist as we move ahead, at least through this quarter or with the visibility you may have across the next 6 months, based on what you've seen over the years? What's your take on the near term here?

Ramesh Kumar Jha

executive
#25

Look, this challenge is still very much with us, and we haven't really seen much of an improvement in the overseas market when it comes to energy availability. From what we're hearing — and you may have seen it in the media too — some very prominent leaders, world leaders, have spoken about a big disruption that's on the way. At this point, we're also not very certain how to say anything futuristic, but the situation hasn't changed drastically.

Ankita Shah

analyst
#26

Okay.

Ramesh Kumar Jha

executive
#27

That's why we're keeping the guidance as is, because as soon as we get some clarity, we'll be providing that guidance.

Ankita Shah

analyst
#28

All right. Sir, could you shed a bit more light on the international projects — where exactly are those projects located, and what kind of work are you carrying out there? You see,

Ramesh Kumar Jha

executive
#29

Over in Bangladesh, we have a few road projects under way, plus we've got a railway project going. And in the Maldives, we're working on one bridge connecting project.

Ankita Shah

analyst
#30

Beside

Ramesh Kumar Jha

executive
#31

Beyond that, we have a couple of projects tied to water in Tanzania; there is a water-related project of ours in Benin, in Ivory Coast, and then there are various countries in Africa.

Ankita Shah

analyst
#32

All right. What exactly has the problem been in these locations? Could you shed more light on it? Was it tied to the supply chain, or was it disruption at the local level that you observed? I'm not able to grasp that very clearly.

Ramesh Kumar Jha

executive
#33

Typically, in the majority of these projects, the material is sourced from the domestic market, India. From the Middle East. Dubai serves as a hub for us. Moving material turned into an issue for these locations. Normally, for executing our projects, we need a substantial amount of diesel, and we need a substantial amount of gas. Availability of these was absent. In many locations, we were required to pay in advance, and only after that would they commit to delivery.

Ankita Shah

analyst
#34

All right, so that pushed costs higher. Has work at the site come to a halt, or are you still proceeding with it while payments from clients haven't come through? Let's see, one,

Ramesh Kumar Jha

executive
#35

Naturally, the effect on costs wasn’t all that serious, yet as a result of this, operations weren’t able to proceed the way we had anticipated.

Ankita Shah

analyst
#36

Sir. I'll get back in the queue. I have more questions. Thanks.

Jainam Jain

analyst
#37

Thanks for giving me the chance to speak. Sir, we’ve pointed out that payment from the customer side has been delayed. Is there any concern tied to a particular customer, or are we running into a problem coming from the government or from private clients?

Ramesh Kumar Jha

executive
#38

Look, we’re not saying there’s a concern here, but what we’ve observed is that elections took place in some of the states. Because of that, no decision was made. The customer certified the payments, they went to the treasury, and the money wasn’t arriving. We heard that some customers weren’t making decisions. Payments got certified, sent to their centralized finance team, and then we simply heard the payments would be released; they weren’t released, and actually they were released later in April. So we’re not saying we’re seeing any concern, and I think in the past we’ve discussed Jal Jeevan Mission, which is still ongoing in UP. They’ve taken a position that only where people are completing 100% will they release the payment; that’s contrary to the contractual condition, but that’s how it has been handled.

Jainam Jain

analyst
#39

Okay, so essentially some receivables spilled over from March into this quarter, and during this quarter we've seen some relief on the payments side, correct?

Ramesh Kumar Jha

executive
#40

This isn't something that only happens in the quarter. What we're really saying is that payments are taking longer to come in. So it's not that the payments are stuck—the running bill payments aren't stuck—but the way they used to arrive, or the way we expected them, isn't how they're coming now.

Jainam Jain

analyst
#41

Alright. Sir, for my second question, is there any plan to bid internationally on the ME side, given that Abu Dhabi has unveiled a project pipeline worth $55 billion?

Paramasivan Srinivasan

executive
#42

No, no, we’re definitely on it, and before long we’ll begin winning projects in the Middle East.

Jainam Jain

analyst
#43

Okay, sir, at the moment, could you share any numbers on the bid pipeline for this year?

Hitesh Singh

executive
#44

All right. For the next 2 years, the bid pipeline we monitor continues to look healthy; across segments, we're tracking close to ₹4 lakh crores. Within that, 70% comes from domestic and 30% from overseas markets. As MD sir mentioned earlier, the Middle East also appears to be a major opportunity once the war is resolved. That region is another one we're watching. Our pipeline contains a number of large-value projects, and we expect to convert them soon. On that basis, we feel confident in guiding ₹30,000 crores for order booking this year.

Jainam Jain

analyst
#45

Do we have any bifurcation for this bid pipeline of ₹4 trillion?

Hitesh Singh

executive
#46

I also have the breakdown. Of that ₹4 lakh crores, roughly ₹96,000 crores comes from the hydro and underground business, which also takes in our water business. About ₹90,000 crores is from marine and industrial — that will be a 50 to 50 split. Our rail and road business accounts for approximately ₹85,000 crores, and the remainder, roughly ₹1.3 lakh crores, comes from the urban infrastructure business, which includes metro, underground, elevated, and elevated corridor projects too. That's how the split looks.

Jainam Jain

analyst
#47

Sir. That answers my question. Thank you so much, and all the best.

Parvez Qazi

analyst
#48

Good afternoon, and thanks for taking my question. You said there was a sizable provision on one project in Q4. Could you tell us the quantum of the total provision we made across all projects in Q4? See,

Ramesh Kumar Jha

executive
#49

During Q4, we recorded a provision of roughly ₹160-odd crores across all projects.

Parvez Qazi

analyst
#50

What would have been this number for FY26? FY26,

Ramesh Kumar Jha

executive
#51

That figure comes to roughly ₹325 crores. Parvez, let me just walk you through it. What we did this year, in Q4, is put together an ECL provisioning matrix. Previously, the way we worked was that under the accounting standard, we'd review certain earlier periods to see what the write-off was, and on the basis of those averages we'd make a provision; then for certain specific projects where we felt there might be some difficulty, we'd create those specific provisions. This time, instead of staying with that individual assessment, that individual basis on which we used to provision, we've now built a matrix in which we've shifted away from the earlier basis, the management judgment provision, to a matrix where, on the basis of aging and on the basis of category, we've set up a provision matrix; provisioning will happen automatically, across all the receivables. Some additional provisioning was needed because we had to move to this new matrix system. Some extra provisioning was required, and that's what we've carried out.

Paramasivan Srinivasan

executive
#52

And there's also one project where an arbitration award came down and we had to decide whether to challenge it or not. We felt it was wise to set aside a provision, and we did provide for that. That figure is also a significant amount. Then in another project, costs have gone up on things like our marine spreads and similar items. While that may be compensated down the road, we decided to book the cost upfront, and later, when the compensation comes in, it would be recognized as a receipt at that point. That's how we've handled it, consistent with our usual conservative accounting policies, and that's what we've done upfront. Sure.

Parvez Qazi

analyst
#53

So to sum up, if you add all of that together — the extra provision from a new policy, a cost that came up in a marine project, or some provision for a potential claim where we need to settle on a strategy — what would the quantum of these one-time costs be in Q4, taking all these categories as a whole? Look,

Ramesh Kumar Jha

executive
#54

So taken together, my sense is the quantum might land somewhere in the region of ₹260, or ₹65 crores, roughly speaking.

Parvez Qazi

analyst
#55

Absolutely. For the second question, could you tell us the capex we incurred in Q4 and in FY26?

Ramesh Kumar Jha

executive
#56

For FY26, capex incurred by us comes to ₹1,069. Back in December, that figure stood at roughly ₹370-odd crores. During Q4, we ended up doing close to ₹700 crores.

Parvez Qazi

analyst
#57

Understood. I believe that covers everything on my end. Appreciate it, and best of luck. Thanks.

Ramesh Kumar Jha

executive
#58

Thank you.

Bhavik Shah

analyst
#59

Yes, hi there. First off, on the order book as it stands right now — could you walk me through how it breaks down between the fixed-price portion and the variable cost portion? And within that fixed cost piece, how much of it is likely to affect margins, in the sense that those margins may not be at our usual levels at present?

Paramasivan Srinivasan

executive
#60

As for the order book we already have, only somewhere around 10% to 11% sits in the overseas segment right now.

Bhavik Shah

analyst
#61

All

Paramasivan Srinivasan

executive
#62

13% comes from the overseas segment. Domestic accounts for all the rest. On the domestic side we operate a pass-through mechanism, while for international segments no such pass-through exists. So our exposure, and most of the projects we're discussing sit at the closing stages, apart from the fresh order booked in the current quarter, everything else is in the final stages of closure, so we do expect a limited impact when it comes to existing cost escalation or similar items; in the new Croatia project, past a certain level, that contract carries a pass-through mechanism. We have to absorb up to 10% additional cost. Anything beyond that is passed through. That's what's built into the new contract.

Bhavik Shah

analyst
#63

Sir, regarding every project you listed in Bangladesh, Maldives, Tanzania, and Benin that was carried out this quarter, how large is that amount? You said a big effect came from those projects, so what is the total value of them?

Ramesh Kumar Jha

executive
#64

Can you come again?

Bhavik Shah

analyst
#65

You mentioned the Bangladesh road rail projects, the Maldives project, the Tanzania water project, and the Benin project — all of these were slow moving during the quarter. Could you help us with the quantum of these projects?

Ramesh Kumar Jha

executive
#66

If we look at the total order book right now, the overseas portion is roughly 13%, let's say. As I mentioned before, although that overseas share sits at about 13% of the overall order book, when it comes to turnover during the year, close to 30% is being generated from the overseas market.

Bhavik Shah

analyst
#67

Alright. Sir, what we’re stating is that our order book stands at ₹32,500 crores. We’re also saying we have ₹15,000 crores of assured inflows, and there’s another ₹15,000 crores of inflows that we’re going to secure; that would bring me to roughly ₹60,000 crores of order book. Yet even with a ₹60,000 crores order book, we still can’t provide a revenue guidance for the year. Isn’t that somewhat misleading, or something like

Paramasivan Srinivasan

executive
#68

No,

Ramesh Kumar Jha

executive
#69

it

Paramasivan Srinivasan

executive
#70

It isn’t misleading in the slightest, since the infrastructure sector requires a certain level of appreciation that during the first few months, work goes into installation, design, and other stages. In heavy civil infrastructure projects, revenue by and large only begins building up from the second year onward. A number of the projects currently in our ₹30,000 crore, ₹31,000 crore order book have somewhat long gestation periods. For instance, if you look at it, there are four dams, each of roughly 5-year duration. There is a high-speed railway project of about 62 months, which is now being extended by another 12 to 15 months because of the tunnel boring machine. So these are long gestation projects. As a result, issuing a guidance based on the current order, particularly while uncertainty persists in the geopolitical situation, would be inappropriate. At the same time, on one hand there has been discussion of our own increases in petrol and diesel, which are minuscule to begin with and could rise in stages. All of this has to be properly factored in, and even now we find that in some places fuel is unavailable in certain overseas markets and in some domestic markets in remote locations, all of this. Given all these factors, providing a guidance may not be very appropriate. That is why we felt it was not appropriate to give a guidance.

Ramesh Kumar Jha

executive
#71

Look, we aren't claiming that we're withholding guidance. What we're saying right now is that we're simply pausing. We just want to get a clearer picture of how matters are unfolding, because what I'm getting at is this: costs could rise. If an order gets confirmed, you might take on some additional expense. The continuity carries on because of the payment flow; that's the area where we're noticing certain uncertainties. That's where we'd like to gain some visibility into how things are progressing.

Hitesh Singh

executive
#72

And Bhavik, while we are providing guidance of ₹30,000 crores, we also need to consider when the project actually arrives. The reason is that we are likewise observing the award cycle taking longer, so if a project lands in Q2 or Q3, revenue will be affected accordingly. That is another factor behind this.

Bhavik Shah

analyst
#73

Okay, sir, I understand. Sir, if customers, let's say, are stretching out their payments and aren't paying us on time, do we have any right to perhaps receive those payments sooner, or how are we currently negotiating with them? Because it will definitely affect our margins.

Ramesh Kumar Jha

executive
#74

That's right. Look, normally what happens with construction contracts—at least when the government is the customer—is that we aren't really negotiating the contract terms one by one. Once the tenders go out, the contract conditions for that project are fixed. Everyone bids on that basis, and then whoever wins has to abide by those same conditions. Now, a lot of times what happens is that if your payment is being delayed, you'll have a provision for charging interest to the customer. All of that is there in the contract. In practice, what happens is that customers, if they don't see visibility of releasing payment when they don't have funds, they won't certify the bills. Being a government entity, you don't want to get into a confrontational kind of mood with the customer, because that also isn't advisable. Up to now, the way we've operated is that we've tried to deliver projects in advance, we've tried to solve the customer's problem, and on the basis of that goodwill, because of those performance aspects, we were getting our things done. At this point in time, we are foreseeing that there are some challenges related to liquidity, and that is kind of creating this kind of a situation. Otherwise, we aren't having any bad experience with these customers, because we are quite focused on our customer selection.

Bhavik Shah

analyst
#75

Got it, sir. Got it. Wishing you all the best for the year. Many thanks.

Shrinarayan Mishra

analyst
#76

Thank you for taking the question. Sir, you mentioned that a few projects are having their execution delayed as a result of uncertainty around collections. Could you highlight which order book is dealing with this collections issue, so we can gauge how much impact we are facing? And related to that, for projects that are under 10% complete, what receivable is there on those projects?

Ramesh Kumar Jha

executive
#77

Look, I think if we’re being specific about projects, then apart from the UP Jal Jeevan Mission project and possibly the project in Gabon, there aren’t really any particular names we can provide. What we’re saying is that in any project, what we try to do is apply our own internal threshold: if a certain number of months of turnover isn’t realized, then beyond that point we won’t fund it. We try to manage the project from the project cash flow. If payments get stretched out, because many times it happens that they try to bunch things up, a 2 or 3 month bill will be held up. After that, we try to go slow. We don’t fund from our own pocket. Payment comes, then we try to manage the project, and that’s how things are going. This has an overall impact, which is what we’re trying to say. If we have to talk about a specific project, we’ve already talked about the UP Jal Jeevan Mission project, and we’ve tried to explain that there, contrary to the contract condition, the customer has taken the stand that whoever is completing the final connection, it means that one needs to complete 100% of those connections, and only then will they get paid. Wherever we have completed, say, 60%, 70%, 80%, the contract condition says that progressively the payment needs to be made. Now they have taken this stand that only after final connection 100% completion will they release the payment. In normal course, maybe we could have done maybe, say, anywhere around ₹60, ₹70 crores monthly turnover, but then now, given the kind of situation, we’ll be completing those wherever we have reached, say, 90%, those kinds of. We’ll try to complete that 100%, and we’ll get that money, and from that money, we’ll try to complete the remaining, maybe look at wherever we have done 80%. Likewise, we’ll go.

Shrinarayan Mishra

analyst
#78

So my understanding is that the collections issue is broad-based. It isn't confined to particular projects, correct?

Ramesh Kumar Jha

executive
#79

Absolutely.

Shrinarayan Mishra

analyst
#80

Okay. Also less than 10% completion projects, what are the receivables there, outstanding amount?

Ramesh Kumar Jha

executive
#81

Receivables aren't really a big factor in that case. Some receivables do exist, and you could probably say roughly 2 months of receivables would sit in projects like those.

Shrinarayan Mishra

analyst
#82

All right. Sir, regarding these interest-bearing advances we’re receiving, that share is going up. At the order book level, what percentage of the order book will carry interest-bearing advances? I’d like some sense, looking ahead, of where this figure will ultimately land; on one hand, we’re paying interest to the customer on advances, and on the other hand, customers are putting off paying us. We’re in a sort of deadlock. How are you going to handle this? It’s a major problem.

Ramesh Kumar Jha

executive
#83

No, I think look, we don't approach project selection that way, where we'd keep only, say, 50% in interest-bearing advances—because that isn't how we see it. What we examine is, for any given project, what margin threshold we're targeting. Generally, with these projects we're discussing, we're certainly paying interest, but these projects carry better margins for us. Unfortunately, we're at a point where we haven't crossed the threshold at which we recognize the margin in the project, and instead we're paying the interest. That's getting reflected. Then I think once the top line rises, we won't find ourselves in this kind of situation.

Shrinarayan Mishra

analyst
#84

Where does this figure end up going? That's the follow-up to the very same question. I'm not raising any new question here.

Ramesh Kumar Jha

executive
#85

Go ahead.

Shrinarayan Mishra

analyst
#86

I realize you don't take this into account when you bid for orders, but if interest-bearing advances rise as a share of your order book, your ROCEs and ROEs will be affected, correct? How confident are you about hitting the guided ROC and ROEs should the projects be delayed?

Ramesh Kumar Jha

executive
#87

That will definitely have an effect on ROE, but the cash is coming to you. From the customer side, your capital employed isn't sitting there. As for ROCE, my understanding is that interest expense falls below that line, so ROCE won't be affected.

Shrinarayan Mishra

analyst
#88

Okay. Anyway, I'll ask for a question. Fine. No,

Ramesh Kumar Jha

executive
#89

To add a bit more on that, I think we've noted that, generally speaking, our order book from overseas markets has typically been around 30%, or one-third, of the order book, which currently is lower, but hopefully we'll get back to that point, and then, since overseas is interest-free, that can make a significant improvement to the situation.

Shrinarayan Mishra

analyst
#90

All right. I'd still find it helpful if you could express this figure in terms of segment or order book, since that would provide forward-looking information. Thanks.

Shirom Kapur

analyst
#91

Hello, sir, and thank you for the chance to ask. I just have one question about your visibility into order flow. For the ₹30,000 crores you're guiding to this year, what gives you confidence on that remaining ₹15,000 crores you referred to? You mentioned visibility is in place for roughly 50% of it. On the other 50%, where does your visibility come from? Will it lean more toward the international side or the domestic side? Which areas will these projects come up in? Has the bidding already opened, or is this more of a situation where you could share some additional color on that remaining 50%?

Paramasivan Srinivasan

executive
#92

Half of that balance — 50% — comes from domestic work as well as international work, and on some of the international projects we're already negotiating and closing. So we do expect those to move faster. On the domestic side too, we've already put in a number of bids, and a few more are in the pipeline. So we'd say there's clear visibility on the balance ₹15,000 crore order book as well; it wouldn't surprise us if some more of it lands in the current quarter itself, and we're keeping our fingers crossed on that.

Hitesh Singh

executive
#93

Shirom, this spans multiple segments. We have solid visibility in marine, urban infrastructure, hydro, plus certain surface transport projects too. That visibility also extends across the different segments in which we operate.

Shirom Kapur

analyst
#94

Got it, sir. And then just secondly, on working capital, right? Of course, there's been plenty of discussion about payments being delayed, and as a result we've seen your receivable days rise this year. How do you see that playing out in FY27 when it comes to receivable days? It's climbed by more than 300. Maybe over the next 1, 2 months you can't offer any guidance. Broadly, what target number are you aiming for in FY27 on receivables and overall working capital days? Now

Ramesh Kumar Jha

executive
#95

Look, when it comes to receivable days, I mentioned just now on this call that a fairly large sum of money is tied up, and on that front we're working with a number of customers; we're at a very advanced stage. We expect a sizable amount to be unlocked before June, and that will give us some improvement in the figure we're watching, because right now this net working capital number stands at around 143 days. On the last call, we had talked about targeting somewhere around, say, 120 odd days. With this, and to be very honest with you, we were looking at getting these monies monetized before March. That's what we were discussing, but it didn't happen. Hopefully before June this is going to happen, because now we are on the verge of closing many of these. We know that some of the payments have already gone through and they're releasing the payments. Still, I'm just taking another, say, 40 days or so, and it will definitely happen; with that happening, we'll go back to around 120 days. Then from there on, there are a number of stuck payments, and we are not going, as I have told you on projects, we are not overexposing ourselves. I think at bare minimum we can look at 120 days. From there on, we need to see improvement, but I don't want to commit at this point in time because we are hearing very contrary news about payments and all. We need to see how it actually works out.

Shirom Kapur

analyst
#96

Understood, sir. Could you say something about the Maharashtra L1 tenders? Has anything new come up there? They were headed toward rebidding. Do you have any remarks on those Maharashtra tenders where you held L1 previously? Is there any update on them?

Paramasivan Srinivasan

executive
#97

Yes. Earlier, L1 status applied to both the Pune Ring Road and Nagpur-Gondia, and both are headed for rebid, which we had already communicated during the previous quarter, saying a rebid was likely. At this point they have informally told us and also requested that we collect the EMD guarantees and everything back. Both of these are going to rebid. So we have taken them out of our L1 status as well, those jobs.

Shirom Kapur

analyst
#98

Sir, there's still no visibility on the timelines for the rebidding process, correct? When that might come up, and how is competitive intensity shaping up in those projects going forward?

Paramasivan Srinivasan

executive
#99

We think the Pune Ring Road might be put up for bidding during this quarter, around June or so. That's because land acquisition for Pune Ring Road is nearly finished. As for Nagpur-Gondia, I believe we'll have visibility once the land acquisition there is fully done. Bidding for Pune Ring Road may open before long.

Shirom Kapur

analyst
#100

Got it, sir. Thank you so much. All the best.

Paramasivan Srinivasan

executive
#101

Thank you. Thank you.

Mudit Bhandari

analyst
#102

Hello, sir. I was hoping to get a clearer picture regarding the 79% of our order book that comes from government, since most of our present issues originate from that side. I realize you don't give any specific breakdown, but could you offer some range on how much of it stems from the central government, or from particular states such as UP, which you named as one of them, or from any PSUs where it appears in many

Hitesh Singh

executive
#103

Are those figures accurate? Yes. Looking at our pending order book, nearly 50% comes from state government sources. Government business accounts for roughly 80% overall, and within that, state government makes up 50% while the central government supplies the other 50%; that's the way the split works. Among the state government portion, we hold projects in Maharashtra, Uttarakhand, Madhya Pradesh, Rajasthan, UP, and Bihar. So our pending order book has exposure spread across a number of states. As for payments that are stuck, the main one, as our CFO already explained, comes from Jal Jeevan. Elsewhere there are some liquidity concerns, but nothing specific that needs to be highlighted or called out.

Mudit Bhandari

analyst
#104

Okay. Understood, sir. Thank you so much.

Balasubramanian A

analyst
#105

Good afternoon, sir, and thanks very much for the chance to ask. Regarding the Chennai Metro or TKY JV, there's that ₹659 crore variation stemming from unforeseen geological conditions. Could you explain exactly what that is, and whether those geological conditions really were unforeseen given the initial soil investigation? I'm just trying to understand how we should view it — whether it will come through as a provision, or whether there's any possibility of shortening it?

Ramesh Kumar Jha

executive
#106

Look, that would depend on the particular project, and we'd rather not get into it here. Since you've brought this up, I'm not speaking about that project specifically, but about what generally takes place: in any contract, where a clause permits variation accounting, and we've incurred some variation following the customer's instruction, then we do account for that variation. In the ordinary course, what happens is that customers often settle the amount for those variations across the board. In certain cases it turns out that we don't arrive at any agreement with the customer regarding the settlement amount. When that happens, regardless of what we may claim, in our books we recognize revenue only up to the cost we're incurring. What we're looking at is simply a reimbursement, and that's the amount being reflected, in the specific project you mentioned.

Balasubramanian A

analyst
#107

Sir. Thank you.

Bhavin Modi

analyst
#108

Thank you for the chance to ask. First question from me: from what I understand, the work we're doing now is proportionate to the payments we're getting. Is it fair to expect debt levels to decline from this point? We're already at ₹35 billion in debt, which is the pre-IPO level. How should we think about how debt moves going forward?

Ramesh Kumar Jha

executive
#109

Look, what generally happens is that during Q1 and Q2, the debts rise. We've said that funding will come from the project alone, but project collections won't cover all expenditure every single time. Main operations, yes. And then often we have salaries to pay, rent to pay, that sort of thing, so we're not fixated on it. There may be some marginal movement in the debt figure, up and down, that's certain. One thing we can say for certain is that in this financial year, FY27, we'll see a sizable reduction in the debt number. That's what we stated before as well, that we have always tried to keep debt at a level that's comfortable for us and comfortable for our stakeholders. This time, it's not an alarming number. On a gross debt basis, our debt to equity is around 0.65, and on a net debt basis it's below 0.5, which, in my view, is a fairly comfortable situation. That said, we'll bring it down to the level where we were, say, in FY25 or so.

Bhavin Modi

analyst
#110

All right. On the second question, sir, which again ties back to this: sure, our net debt to equity sits at a comfortable 0.5x, but over the last 2 years, sir, cash flow from operations came in negative, and we were in fact covering the interest cost by taking on additional debt, which is a vicious cycle. So what gives us confidence that net debt, or the debt levels, will come down? Now

Ramesh Kumar Jha

executive
#111

Look, this is a call, and it’s a calibrated one. Concerns like that might come up if your debt were at an alarming level; previously, we’ve run with debt equity of more than roughly 1.3, 1.4. Right now, even measured on gross debt, we’re at about 0.65. That isn’t an alarming level, and our position is very comfortable. We hold sizable cash and bank balances. We also have sizable undrawn bank limits available to us, and we have very sizable advances we can draw on at any point. I don’t think we’re in that kind of situation; as for finance cost and everything, versus what we planned for the year, we’re marginally higher, but it isn’t as if some extra cost is coming out of nowhere and it’s due to borrowing.

Bhavin Modi

analyst
#112

Okay. Got it, sir. Thank you.

Paramasivan Srinivasan

executive
#113

No, we can take more questions.

Ramesh Kumar Jha

executive
#114

we are seeing that Three more are there.

Paramasivan Srinivasan

executive
#115

We'll continue

Ramesh Kumar Jha

executive
#116

and close it.

Avnish Tiwari

analyst
#117

Hello there. Could you walk us through how cost inflation pass-through works on the domestic projects, and with the delayed payment situation you're dealing with, do you see any risk that passing inflation through on those domestic projects could be jeopardized?

Paramasivan Srinivasan

executive
#118

Every one of our domestic projects includes an escalation clause. That clause may differ between customers, but it is built around steel, cement, labor, fuel, other factors, and so on. On that basis, when increases occur, in certain cases they are fully covered; in certain cases, coverage is 90%; in certain cases, it goes beyond 100% covered. That is how the formula works. So generally, with any kind of increase in domestic contracts, we have had no problems regarding cost increases, apart from occasional situations when there is an abnormal increase, such as what happened in 2004 and '05, when the price of steel suddenly rose abnormally. It climbed from 17,000 to 65,000 across a period of 1 year. Unless a situation of that kind arises, things are normally manageable within the escalation formula. On the international side, most contracts are fixed-price, aside from a few exceptions here and there. For international pricing, we have a well-developed escalation formula. Ordinary price increases get absorbed through that formula, which we build internally into the pricing itself, we do that; in Croatia, which is our biggest contract to date, is a case where we need to absorb up to 10% of cost increase. Beyond that, there is a pass-through. So everywhere we are properly provided for. We will see a comparatively limited impact.

Avnish Tiwari

analyst
#119

My second question concerns the minimum wage hikes we're seeing, along with some of the protests happening in northern states. Are you also running into higher costs, and to any extent shortages or protests at any of your sites in India? Let's see,

Ramesh Kumar Jha

executive
#120

That kind of situation isn't showing up for us. Whatever increases come from minimum wages and labor code provisions, all of that has already been factored in by us. We are proceeding in line with the revised code.

Hitesh Singh

executive
#121

Avnish, the labor problems are pretty widespread, so we're working out how that availability can best be handled. We do have an availability problem on the labor side, but there aren't any protests or anything of that kind.

Avnish Tiwari

analyst
#122

Great. Thank you.

Shravan Shah

analyst
#123

Hello, sir, and thanks for giving me the chance to ask. Sir, you mentioned that we've submitted bids for a couple of projects and those bids haven't been opened yet. Could you tell us the number, and also how much of that is in India versus outside India?

Paramasivan Srinivasan

executive
#124

It wouldn't really be appropriate for me to talk about bid values, amounts, and that sort of thing. Broadly speaking, we'd say we have reasonable confidence in hitting that ₹30,000 crore order book guidance. On the domestic versus international split, it's roughly about 40 to 60 or thereabouts. Domestic would be around 60; international would be around 40. Which orders we land could also shift that percentage.

Shravan Shah

analyst
#125

Understood, sir. Sir, I just want to clarify the capex figure we mentioned — ₹1,069 crore — yet in the cash flow that figure is considerably lower. Clearly, the cash outflow would be occurring, or would have occurred, in Q1 FY27. Regarding depreciation, whatever the capital work-in-progress is, I expect most of it would relate to the TBM. How should one view this ₹100 crore of quarterly depreciation we saw in Q4 — in a broader sense, how might one see it inching up for FY27? FY27,

Ramesh Kumar Jha

executive
#126

The figure should come out about the same. It could edge slightly higher, since, as you noted yourself, with the capex and the TBM we have added roughly 1,000 crore, that amount will flow into the gross block, and so there will be some additional depreciation as a result. It should track FY26, with a bit of an increase for all those additions.

Shravan Shah

analyst
#127

Right. Sir, could you break down that other income figure for FY26 — the ₹374 odd crore — the same way it's presented in the annual report? There are two heads I'm trying to look at. One is clearly the interest income, another is clearly the arbitration one, and then there's the other interest, so what would the balance be? I can subtract that balance myself. If you have these two numbers for FY26, what would the interest on arbitration awards be, and what is the other interest within other income?

Ramesh Kumar Jha

executive
#128

That is interest on arbitration is ₹19 crore, and other interest is ₹61 crores.

Shravan Shah

analyst
#129

So all told, out of that roughly ₹374 crore, the interest portion comes to just ₹80 crore, is that right?

Ramesh Kumar Jha

executive
#130

Yes.

Shravan Shah

analyst
#131

Alright, alright, alright. One additional point regarding what we said in the earlier response about that ₹260, ₹265 crore amount being a sort of one-off provision sitting in the 4Q. So far in Q1, is there any broad sense of how much—because the way we view arbitration is as a normal part of our business, that provision ought to be treated as a normal part of business rather than as a one-off. It depends on how one looks at it. I'm just trying to see whether so far we've made any kind of provision in Q1 up to now, or whether one is likely to be there?

Ramesh Kumar Jha

executive
#132

No, no, no.

Shravan Shah

analyst
#133

Okay. Okay. Okay. Got it, sir. Thank you.

Ramesh Kumar Jha

executive
#134

Thank you.

Shrinarayan Mishra

analyst
#135

Appreciate the question. Sir, I was hoping to get some detail on that Croatia order where road projects were cancelled because of budget constraints. As for the railway projects, do you think collection problems could arise down the road, or how do you view that situation?

Paramasivan Srinivasan

executive
#136

ECB has already approved the entire amount,

Shrinarayan Mishra

analyst
#137

and

Paramasivan Srinivasan

executive
#138

They already have the funds on hand. So we don't see any problems. Also when it comes to the road projects, there is ECB approval for funding up to a certain value. Since there were a series of tenders, not just these two tenders alone, other tenders existed too. As all of them were higher between 20% to 40%, 45%, they decided they would cancel the tenders and revise the estimate, obtain the approval from ECB, and then go for a fresh bid. That is why it got cancelled. This one has already been approved with ECB and all the others.

Shrinarayan Mishra

analyst
#139

Understood. Understood. Sir, regarding L1 orders, do you think any additional orders might also face the risk of being cancelled?

Paramasivan Srinivasan

executive
#140

No.

Shrinarayan Mishra

analyst
#141

Okay. Okay. Thanks.

Ankita Shah

analyst
#142

Sir, just a quick follow-up about the inflow side, given the project pipeline you have and the L1 positions that are still pending as of today. How much visibility do you have on inflows for 27?

Paramasivan Srinivasan

executive
#143

You mean order inflows?

Ankita Shah

analyst
#144

New order inflows, yes.

Paramasivan Srinivasan

executive
#145

On new order inflow, we've guided to ₹30,000 crores, and of that we've already taken in ₹8,000 crores, with roughly another ₹7,000 crores where we're L1, plus a further ₹15,000 crores. So the full ₹30,000 crore figure is what we're guiding to for the year.

Ankita Shah

analyst
#146

Right, okay. For the most part, would those orders come from India, or are you also considering other regions for the same thing?

Paramasivan Srinivasan

executive
#147

It will be a mix of both.

Ankita Shah

analyst
#148

Equal split?

Paramasivan Srinivasan

executive
#149

Roughly about 60% domestic, 40% international for the balance of the orders.

Ankita Shah

analyst
#150

Understood. For International, will the geographies be comparable to those where you currently operate, or are you also looking into new regions?

Paramasivan Srinivasan

executive
#151

No, mostly it will be similar geographies.

Ankita Shah

analyst
#152

Right, so in the Middle East, looking at rebuilding or reconstruction work that might materialize, how large do you figure that opportunity could be, in your assessment?

Paramasivan Srinivasan

executive
#153

Abu Dhabi has already committed $55 billion, and other opportunities of a similar kind may well emerge. Bahrain has been hit fairly hard. Right now it's simply too early to say, since we still need to see how the reconstruction timeline itself plays out. It might only get under way starting in the second half. So as things stand today, we haven't built the reconstruction piece into our assessment.

Ankita Shah

analyst
#154

Okay. Sir. Sure, that's it from my side. Thank you, and all the best.

Paramasivan Srinivasan

executive
#155

Thank you.

Shirom Kapur

analyst
#156

Hello, sir, and thank you for the chance to follow up. I just want to get some clarification: those ₹8,000 crore of orders you referred to, are they confirmed already and included in your order book? If you could shed some light on which orders those are, because if you could

Paramasivan Srinivasan

executive
#157

Let me explain. Sure. Of that ₹8,000 crores confirmed, ₹373 crores has already been included in our order book. As for Croatia, we haven't yet put that into the order book. Within that ₹8,000, the orders consist of ₹373 crores from DMRC and ₹7,544 from Croatia.

Ramesh Kumar Jha

executive
#158

In our pending order book, we haven't included the pending order book from the 31st.

Paramasivan Srinivasan

executive
#159

March. 31st March, this are first quarter.

Ramesh Kumar Jha

executive
#160

Yeah.

Shirom Kapur

analyst
#161

Okay sir, so that comes to ₹8,000 for you. You had said that for half of the three ₹30,000 crore order book, there is clear visibility in place.

Paramasivan Srinivasan

executive
#162

We have two more orders, and we're already L1 — Vadhavan, as everyone knows, is worth roughly ₹5,300 and odd crores. There's one additional job in which we hold L1, and that accounts for the remaining amount.

Shirom Kapur

analyst
#163

So that would come to roughly ₹1,700 crores, which brings it up to the full ₹15,000 you mentioned? Yeah.

Paramasivan Srinivasan

executive
#164

Yes.

Shirom Kapur

analyst
#165

Okay. Understood. Thank you.

Abhinav Nalawade

analyst
#166

Hello, sir, and thank you for giving me the chance to ask. I have just a single question. You brought up the Pune Ring Road project launching in Q1. How large might that opportunity be?

Paramasivan Srinivasan

executive
#167

They're probably waiting on the cabinet's approval. It's likely to be about the same size as whatever they did before. What they're doing differently this time is that rather than starting with a basic number and then going above the estimate and all that, they've updated the estimates and are calling for the bid.

Abhinav Nalawade

analyst
#168

Understood. Thank you, sir.

Paramasivan Srinivasan

executive
#169

Thank you.

Siddharth Surin

executive
#170

Thank you, sir, for the chance to ask. I have two questions. First, there's this reference to the Lombard guarantee, which came up as one of the note items. I just want to understand whether that had any effect on earnings for the quarter; that's the first one. The second concerns the buildup of contract assets. Earlier you guided that there would be a liquidation, which we can see in the buildup of these contract assets, as billing would be certified and so forth. From the commentary, we understand that this is taking some time. Could you still provide some guidance on when we might see the short-term contract assets liquidated in the future? Yeah.

Ramesh Kumar Jha

executive
#171

Regarding your first question about Gabon, that bank guarantee invocation has already been paid by us, and under that contract we weren't recognizing any margin in any case, and whatever needed to be provided for, we've already provided for those expenses. As we said before, the project was roughly 92% complete. At present, under that contract, we aren't recognizing anything going forward. Turning now to your second question about liquidating some of the contract assets, as I explained, on some of the receivables we were looking at a liquidation in March itself, and it couldn't go through; we're looking at those liquidations perhaps by June, and we should see a sizable liquidation of around ₹1,000 odd crores. Once that gets realized, we can also look at bringing down the number of working capital days, which currently sits at an elevated 143, 100%.

Siddharth Surin

executive
#172

Thank you, sir.

Ramesh Kumar Jha

executive
#173

Thank you.

Avnish Tiwari

analyst
#174

Hello there. I just have a quick follow-up question. Regarding those delayed payments that you dealt with on government projects, did you encounter the same thing on the private side in India as well?

Paramasivan Srinivasan

executive
#175

Private side, we have not seen that. In

Avnish Tiwari

analyst
#176

the government side, it's mostly state versus central or across the board?

Paramasivan Srinivasan

executive
#177

I think it is across the board.

Avnish Tiwari

analyst
#178

Okay. Thank you very much.

Ramesh Kumar Jha

executive
#179

Thank you.

Paramasivan Srinivasan

executive
#180

I appreciate it, everyone—analysts, investors, and our industry friends—and we're looking forward to an exciting stretch ahead. Keep your investment in place. Thank you. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Afcons Infrastructure Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Afcons Infrastructure Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research