Applied Digital Corporation (APLD) Earnings Call Transcript & Summary
October 7, 2026
Earnings Call Speaker Segments
Matt Glover
executiveThanks, Pascal. Hi, everybody, and thanks for joining Applied Digital's conference call for the first quarter of fiscal 2027. Before management starts speaking, we want to remind all of you that certain things we say today might count as forward-looking statements under securities laws, and they carry a number of risks and uncertainties. Because of that, we caution that many factors — quite a few outside our control — could lead actual results and events to differ materially from what those forward-looking statements describe. For a more detailed look at the risks, uncertainties, and assumptions tied to our forward-looking statements, please review the disclosures in the earnings release and the public filings we make with the SEC; aside from situations where the law requires it, we disclaim any obligation or undertaking to update forward-looking statements so they reflect circumstances or events arising after the date such statements are made. We also talk about non-GAAP financial metrics, and we encourage you to carefully read our disclosures and the reconciliation tables to the applicable GAAP measures in the earnings release as you weigh these metrics. For detailed disclosures and descriptions of our business, plus uncertainties and other variable circumstances — including, but not limited to, the risks and uncertainties identified under the caption Risk Factors in our annual report on Form 10-K and our quarterly reports on Form 10-Q — we refer you to our filings with the SEC. You can access Applied Digital's SEC filings at no cost by going to the SEC website, www.sec.gov. I'd also like to remind everybody that this call is being recorded and made available for replay via the Investor Relations section of Applied Digital's website. I'll turn the call over to Applied Digital's Chairman and CEO, Wes Cummins, Wes?
Wesley Cummins
executiveThanks, Matt, and good afternoon to all of you. We appreciate you being on the call for our Fiscal First Quarter 2027 Earnings Conference Call. With fiscal 2027 now underway, I want to give you an update on where we're headed, how we plan to get there and, above all, how we're executing. Right now, we hold roughly $36 billion of contracted revenue spread across 5 campuses, 3 states and 2 geographic regions of this country that look quite different from one another. What we're focused on is turning that contracted portfolio into profitable growth, while we keep selectively chasing new opportunities throughout our extensive land and power portfolios. Over the last year, the main yardstick of success was how aggressively we grew our campus portfolio and the total contracted value tied to those campuses. Looking at the near to medium term, we anticipate continued expansion of our existing campuses along with selective additions of new locations, with heavy emphasis on execution and getting contracted capacity online for our customers. Looking out over the next 12 months, our plan is to bring more than 600 megawatts into service, compared with the 250 megawatts brought into service during the past 12 months. Now let me get into our vision and strategy, neither of which has changed. We aim to become the category leader in designing, building, deploying and operating our purpose-built AI factories. To get there, we have to strike the right balance on several fronts. Picking the right customers, pairing those customers with a funding strategy that maximizes our financial returns and delivering consistently on our bills. We think we're well positioned on all 3 fronts. Our proprietary, proven data center design has been embraced by the leading top-tier hyperscalers. We have a finely tuned supply chain, strong energy partnerships and a track record that shows we can meet our lease commitments. One important point: our data center design differs from what many of our competitors are doing. A number of competitors' facilities are built mainly around the GPU's typical 5- to 6-year life cycle. Our approach has been different — we're building for the long haul, with horizons of 30-plus years. In our view, our AI factories are engineered to be far more adaptable as compute architectures, network configurations and electrical and mechanical requirements change over time. Both our design and our investment strategy rest on a set of core principles meant to stretch the useful life of our AI factories and campuses far past any single generation of compute architecture; that matters because we believe the customer signing long-term leases with us expects these facilities to keep serving their needs well past the initial lease term. Consequently, we believe our design and build strategy, along with our franchise model, is highly differentiated and will produce outsized returns for our stockholders over the long term. Our primary focus stays simple: build large, sustainable AI factory campuses and sign durable, high-quality long-term contracts. We target take-or-pay contracts of at least 15 years with proven Tier 1 investment-grade hyperscalers that lead the AI industry and are well positioned to convert their investment into sustainable and profitable growth. When we decide which customers to build for, a key measure we look at is whether they can turn their AI spending into earnings that last and hold up over time. That group is fairly small, yet it accounts for tremendous demand and major potential spending over the long haul. According to these customers, what they appreciate is how well we design, how solid our invoices are, and how strong our world-class team is. Beyond putting pen to paper on new deals, growing the campuses we already have is among our top priorities. On top of that, we see a chance to command premium pricing as demand rises and we capture the economies of scale that come naturally with big AI campus builds. Progress has kept coming on growth chances with the customers we already serve, and at the same time talks have moved forward regarding more campuses; right now our expectation is that roughly 250 megawatts of expansion leases will be signed by the close of the calendar year, at pricing substantially above what earlier leases carried. As we keep growing the campuses we already have and work to secure premium pricing, our belief is that these sites hold considerable embedded value that the market underappreciates. Over time, we anticipate that value will increase as we perform against our contract portfolio and stay focused on producing exceptional long-term returns for our stockholders. Now I want to shift to what we are doing in North Dakota, where multiple AI factories are under construction spread across 3 campuses. Our biggest operating region is North Dakota, and it stays central to our strategy. We have said many times that cheap power, plentiful energy resources, sparse population, and a helpful climate combine to make it among the most attractive places in North America for developing large-scale AI factories. Over time, we anticipate more Tier 1 hyperscalers will come to see those benefits. It is also where most of our investment has gone so far, both in the campuses already bolted in place and in those we are constructing, as well as in the communities we have partnered with. Within our industry, power is still the biggest single constraint, and we believe North Dakota is among the few areas where new generation can be brought online at meaningful scale. On that scale, we recently took a significant step toward growing our power position in North Dakota by signing a long-term power purchase agreement with Base Electron, an independent power producer in which we hold an approximate 10% equity stake. What the agreement covers is an approximately 1,200 megawatt natural gas facility that Base Electron is developing in Center North Dakota next to our Polaris Forge 3 campus, with deliveries expected to begin in 2030. This outcome is precisely the sort our model is built to produce. While plenty of operators sit in interconnection queues waiting for capacity they have no control over, we are signing up for dedicated generation sized to our campuses, under an agreement that can follow our tenants and on a timeline that lines up with our future development needs. We think having this dedicated supply really boosts our capacity to grow our North Dakota campus according to our own schedule instead of depending on the grids, and it provides us with better visibility into the power resources that will back our future expansion in the area. To give a sense of how quickly we're moving in North Dakota, we signed our initial lease with CoreWeave in May of 2025 for our first 2 buildings at Polaris Forge 1, and the first of those was under construction at that point. By the close of calendar year 2025, building number one was completely operational, able to sort over 40,000 liquid cooled NVIDIA GV-300. Building two, which had its groundbreaking in summer 2025, came online roughly 1 year afterward. As of right now, we've reached full ready-for-service, or RFS, at both of our first 2 buildings on the Polaris Forge 1 campus. Our third building is moving forward on schedule. The operational buildings cover 10 data halls and are backed by 250 megawatts of critical IT load; that amounts to a 150% rise in delivered capacity. At land alone, we think we're well ahead of our nearest rivals in delivered capacity. And with the anticipated initial operation of our Harwood North Dakota campus, we expect to have 300 megawatts of critical — total critical IT online throughout North Dakota by the end of this calendar year.
Wesley Cummins
executiveWe think the amount of capacity we've delivered puts us in the top tier of companies in our space, no matter where they're located. Within the U.S., outside of North Dakota, we're building out campuses in Louisiana and Alabama that carry significant room to expand. Those markets have attractive traits, such as available power and solid backing from state and local officials for adding national AI capacity. We see the fact that other leading hyperscalers are also building large-scale AI campuses in those areas as further proof of how strategically important they are. Our work in Louisiana and Alabama keeps moving forward, and we're still encouraged by how much customer demand exists across that region. We anticipate that revenue from this part of the country will start contributing in the first half of calendar year 2027. We recently made our first moves beyond the U.S. Although we remain squarely focused on carrying out our domestic projects, we think certain European markets could offer appealing chances to apply our know-how and grow our platform down the road as we keep turning Applied Digital into a leader in the category. As an initial part of that exploration, we signed an agreement covering as much as 1 gigawatt of potential power capacity in Finland. We see this as a careful first move. The deal brings meaningful long-term upside while capping our early exposure and guarding against downside risk, since our near-term execution priorities stay centered on the United States. Now shifting to our data center hosting business. The 286 megawatts of capacity we have for Bitcoin mining at our 2 North Dakota sites keeps running efficiently and delivers steady high-margin revenue with very little ongoing capital investment. Now on to ChronoScale, where our ownership stake is approximately 96%. Neo clouds remain one of the fastest-growing segments in this market. NVIDIA expects Neo clouds to finish this year with 8 gigawatts of installed capacity, up from 3 gigawatts at the close of 2025. In the quarter, ChronoScale announced plans with Microsoft for a 50-megawatt AI compute deployment in North America that features NVIDIA GB-300-NVL72 systems. That deployment should substantially grow ChronoScale's existing business with a Tier 1 investment grade customer and marks one more key step in scaling the platform. Thanks to recent new contracts, ChronoScale is on track to hit $1 billion of ARR in 2027, and momentum for more contracts keeps building. With that, I'll hand the call over to our CFO, Saidal Mohmand, for a detailed review of the financials. Saidal?
Mohammad Saidal Mohmand
executiveAppreciate that, Wes — and hello, everyone, this afternoon. Over the course of this quarter, we closed out the financing package for our very first campus. If you go back to the beginning of this year, there was still one tranche left to place, tied to the final 150-megawatt building at Polaris Forge 1. Then in June — something we discussed on our last call — we got that tranche done: a $1.59 billion offering of 7% senior secured notes due 2031, priced at par. With the money from that offering, construction on the third HPC building at Polaris Forge 1 is now funded, and we've also repaid the $300 million bridge facility that we arranged in May. So with that wrapped up, the full 400 megawatts for the CoreWeave campus at Polaris Forge 1, plus the 200 megawatts of contracted capacity over at Polaris Forge 2, are now fully funded. The pricing on that deal is worth calling out here. When we placed our initial notes tied to Polaris Forge 1 a year ago, the coupon was 9.25%. This tranche landed at 7%. In our view, that pricing reflects the credit enhancements we secured with CoreWeave earlier this year, as well as growing investor confidence in our platform. And we're earning that confidence by executing — delivering our buildings on schedule and within budget — and we expect the first <<inaudible>> Polaris Forge 2 to come in on schedule and within budget as well. This win strengthens the market's belief in our ability to get things done. It moves us closer to the goal we laid out before—keeping our cost of capital on a downward path, starting with individual projects and later refinancing buildings we already operate into cheaper markets like ABS. At the corporate level, we added more flexibility too. During June, we expanded our revolving credit facility to $430 million in commitments, and there's still another $120 million accordion we can tap. Going forward, the next campuses that will need financing are Polaris Forge 3, Delta Forge 1 and Delta Forge 2. All three are leased to the same Tier 1 investment-grade hyperscaler through 15-year take-or-pay agreements. In our view, that fact changes how potential creditors approach the financing talks. Keep in mind that when tenants hold a Tier 1 investment-grade rating, a wider set of capital sources becomes available, and in our view that leads to better terms. Our approach hasn't changed — first preferred equity provided by Macquarie Asset Management, followed by debt at the project level — and that structure allows shareholders of Applied Digital to retain a majority ownership position at every site. Conversations are already underway with <<inaudible>> lending institutions, and because of the credit strength of this customer, we feel very confident about our capacity to finance these campuses on favorable rates and terms; let's now move on to the quarter. One reminder: ChronoScale's is part of our GAAP consolidated results, though it is left out of our non-GAAP financial measures. During the quarter, our total revenue came in at $341.9 million, which represents a 322% increase compared with $80.9 million in the same period a year earlier. Within that, the HPC hosting business contributed $262.6 million, broken down as $65.8 million in base rent, $183.5 million from tenant fit-out services, and $13.3 million in tenant recoveries. As for our data center hosting segment, which operates our two Bitcoin hosting sites, revenue there reached $37.8 million, unchanged from the prior year quarter. We continue to be very pleased with this business, since it produced $13.3 million in operating profit within a single quarter while using approximately $111.9 million in segment assets. This quarter's segment operating profit was over twice the $6 million recorded in the previous quarter, driven by favorable power pricing. This quarter, ChronoScale generated $41.5 million in revenue, and roughly $23 million of that came from selling GPU hardware. Cost of revenues for services and other amounted to $245.7 million, primarily consisting of $176.1 million plus tenant fit-out services performed inside our HPC Ocean business, $22.4 million connected to ChronoScale's GPU hardware sales, $19.8 million for energy, and $17.6 million of depreciation and amortization. Data center rental and other cost of revenues reached $43.9 million, mostly driven by $22.4 million in depreciation and amortization expense related to our operational AI factories at the Polaris Forge 1 campus, plus expenses that are reimbursed through tenant recoveries, along with $7.8 million in personnel and other operating costs that support our facilities. Selling, general, and administrative costs totaled $114.7 million for the quarter. The bulk of that figure consisted of $65.4 million in stock-based compensation, $16 million for professional services mostly connected to transactions, $15.6 million in personnel expenses, and $4.8 million in lease expenses. There's one thing worth flagging for the quarter. Within our stock-based compensation expense, $41.3 million related to onetime performance stock units. On top of that, we recorded a $67.5 million noncash loss stemming from the change in fair value of our Babcock and Wilcox warrants and the common stock investment. As the B&W stock price fluctuates, both of those are marked to market every quarter. Net loss from continuing operations attributable to common stockholders was $221 million, or $0.76 per share. On an adjusted basis, our net loss came to $4.1 million, which works out to $0.01 per diluted share. Adjusted EBITDA hit $64.4 million, compared with just $500,000 during the same quarter a year ago. Net operating income — NOI — applies only to the HPC hosting side of our business, and it landed at $58.8 million, a margin of 89%. Turning to the balance sheet, our view is that the position remains strong. When the quarter ended, we held about $2.9 billion in cash and cash equivalents, along with $0.7 billion in restricted cash, set against debt of roughly $6.4 billion. It's worth noting that more than 80% of that principal does not come due until fiscal 2031 at the earliest. Stockholders' equity came in at around $1.6 billion. We still intend to maintain a balance sheet that ranks among the strongest in the sector throughout most of the build-out period, and we'll take steps consistent with that goal. With that said, I'll turn things back over to Wes so he can wrap up. Thanks.
Wesley Cummins
executiveThank you, Saidal. Before we take questions on the call, I'd like to wrap up with a topic that seems to surface in just about every discussion we have with investors these days: the rising level of scrutiny directed at data center construction nationwide. Across various markets, we're observing additional local moratoriums, stricter selling requirements, extended permitting timelines, and stronger pushback from communities. To some, that might look like a threat to our business. Our perspective is different. In our view, it actually raises the strategic worth of our campuses that are already powered, operating, and backed by the communities around them. We think the logic here is simple. Once our campuses are up and running, we believe the bulk of the toughest work is behind us. The land is under control, power and interconnection are secured, permits are in hand, and fiber, workforce, and local supply chains are established. And maybe most critically for us, the community recognizes who we are and has seen how we conduct ourselves. That's why we believe growing at existing campuses is fundamentally different from beginning anew in a fresh market; we're already witnessing this pattern throughout our portfolio. Customers have told us they're seeking extra capacity in locations where they trust it can genuinely be delivered. As building new data centers gets harder in certain markets, we think the scarcity premium attached to established, community-supported power and campuses goes up; in our view, that trend creates substantial barriers to entry and can underpin stronger economics on expansions and renewals. And over the long haul, greater terminal values for our assets. To put it plainly, we believe each new restriction imposed elsewhere makes what we already possess harder to duplicate and more valuable. This matters as well when we consider the long-term worth of these assets. Our leases carry 15-year base terms, yet the land, power, interconnection, and community backing behind these campuses can endure much longer than any individual lease. When a base term expires, and we see a tenant with tens of thousands of GPUs deployed and a powered liquid-cooled campus confronting a straightforward decision—renew with us or attempt to locate comparable power and approvals elsewhere in a market where new sites are increasingly hard to get approved—we believe that tips the scales toward renewals, supports stronger renewal pricing, and lets our tenants keep refreshing their technology inside the same facility for decades. That's why we have confidence in the durability of our leases and believe the terminal value of these campuses is significantly higher than a traditional real estate model would suggest; we also believe that value ought to keep rising as new supply becomes more difficult to build, and locales have told us the reason our communities want us to expand is that we have worked hard to earn their trust. Our approach has always been simple: do it the right way. In North Dakota, MDU's ratepayers have saved roughly $45 million from the time our Ellendale project started, thanks to our use of spare grid capacity and the way we help distribute fixed costs over a larger load. Over in Harwood, we funded more than $100 million in substation and grid improvements on our own dime, and the whole community benefits from those. Our approach, moreover, already satisfies the rate payer protection pledge that Governor Armstrong signed on to with 21 other governors. We've also been told by local leaders that the economic impact on these communities has been considerably positive, along with the strong national spotlight, which includes Fox Business News coverage and the all-in podcast. Ellendale stands out as a prime illustration. From the moment our partnership with the community started, local tax revenues grew about tenfold, going from roughly $400,000 annually to close to $4 million. Schools, infrastructure and emergency services are being supported by these tax dollars. Construction workers at our sites average 6-figure incomes, and a great many of those dollars remain in the local economy. It was an honor that the Mid-Arica Economic Development Counsel just named Polaris Forge 1 its Project of the Year, honoring the campus for economic impact, community investment, partnerships and technological innovation. That award is as much the Ellendale community's as it is ours. and our gratitude goes out to everyone who keeps making Polaris Forge 1 a reality; we put money directly into our local communities too. Via Applied Digital Cares, we just pledged $350,000 to 5 organizations in Oliver County, where Polaris Forge 3 is located. That covers paying for the new Sheriff Deputy, a new life pack for the county ambulance, repairs to 2 fire trucks, computers so that each student in grade 7 to 12 at Center Statin has a device, plus repairs to the community center and pool in <<inaudible>>. As Governor Armstrong phrased it, North Dakota wins when companies like Applied Digital decide to be more than an employer. We don't merely build in communities — we build alongside them, and that's the reason they welcome us back to expand, and we think every one of our campuses holds substantial embedded value that will keep building over time. To wrap up, we think we're in the right place at the right time and doing this the right way. Now more than ever, our own destiny is in our hands across the full stack. We own the land, we design, we build and operate the AI factories. Through ChronoScale, we reach all the way to GPU compute, and through partners like Base Electron, we have visibility into the power of the feeds at all. Should demand keep following its present trajectory, and should we keep executing and delivering for our customers and our communities the way we have been. We think we're capable of growing our operating portfolio to 3.5 to 4 gigawatts by the end of calendar year 2030. With that, operator, we're happy to open the call for questions.
Mike Grondahl
analystYou've obviously got a first mover advantage in North Dakota. Could you speak a bit about how North Dakota is perceived as a market and what kind of receptivity you're getting from hyperscalers?
Wesley Cummins
executiveYeah, Mike, thanks for asking. So in North Dakota, the situation is that we already have 3 customers of our own there. We also know about a self-build project of about 1 gigawatt from the Tier 1 hyperscalers in that state; and we've been talking — that's separate from the ones we already have there — and we're in multiple discussions with other Tier 1 hyperscalers about more capacity in North Dakota. I'd say the answer is that eventually all of them will be there; and one of the most appealing aspects of that state, beyond the power, the climate, and the population density, is that they have a framework for how data centers are treated there. So everybody knows precisely what to expect as you move through a process in that state. And if you handle the development properly, it's an incredibly attractive state to be in, and I believe it will only become more so over the rest of this year in '27 and '28.
Mike Grondahl
analystUnderstood. So perhaps regarding Saidal, the bond market has been difficult, to put it mildly. Could you discuss what options you currently see for funding investment-grade hyperscaler debt?
Mohammad Saidal Mohmand
executiveAppreciate that question, Mike. It's an excellent one. As you may remember, we finished the Polaris Forge 2 and Polaris Forge 1 financings, which one could say aren't of equivalent credit quality, with excellent customers. They perform well, they're terrific tenants to have; so as we consider what lies ahead with Polaris Forge 3 and Delta Forge 1 and 2, since this involves high investment-grade hyperscaler, there are numerous possibilities past the high-yield bond market, which we've favored and we've served as an issuer in on earlier projects. For example, the project finance market is quite accessible for high investment-grade offtakes, plus there are some fresh innovations inside the investment-grade bond market. So from what we've observed, there's adaptability across different products we can access. Naturally, we evaluate those and identify a blend that suits our profile. But our attention is on a rate environment that might shift by roughly 50 to 100 basis points. First, we don't underwrite leases in which a 100 basis point change would genuinely affect our economics. Then second, we concentrate on terms allowing us to refinance within a year or 2 years with negligible penalties. So after that construction risk, which typically amounts to anywhere between 25 and 100 basis points of construction risk premium on a debt instrument. After we move beyond the construction phase, we can bring our costs down fairly swiftly into a more permanent financing. That's where our attention lies. We're agile, and it's wonderful having a high investment-grade hyperscaler with numerous options to pursue.
Nick Giles
analystYeah. Appreciate it, operator. Nice work on that recent execution. I just had a question about what was announced for Finland. In the release, I believe you emphasized that initial exposure would be limited. Could you say a bit more about that? What sorts of options does the present agreement include, and how do you expect the commercial side of that site to develop?
Wesley Cummins
executiveOf course, Nick. Thank you; regarding that site, we bought it, and after that, we hold the option. The site's first power is expected to arrive during 2028. After that, more power would follow — that's how nearly every location scaling to 2 gigawatts works, since you hit breakpoints where you secure approvals for added power capacity. Visibility into those approvals is fairly strong. Additional payments would come due at that stage, though we hold an off-ramp that lets us exit before those payments kick in. So the amount we're risking is quite small, and it gives us exposure to a market we view as increasingly appealing within Europe. And for roughly the past 12 months, we've been examining that market. We checked out somewhere between thirty and forty locations before settling on this particular one. In our view it's a solid location, and the timing worked out well because over the past four months, both our current clients and other prospects we've been speaking with have been inquiring more about capacity in Europe. So those two developments fit together quite nicely, and it hands us substantial upside flexibility while exposing us to very little in the way of financial downside.
Nick Giles
analystUnderstood; let's shift direction for a moment. During your prepared comments, I felt you placed real emphasis on how long these data center campuses last nowadays, and to me it sounded like a shift in tone, or perhaps you were calling attention to that point more than you used to; so I simply wanted to ask — what prompted — where did those remarks come from. Clearly, GPU refresh cycles remain a topic in these conversations. Still, if there's anything you'd point to on that front, I'd be grateful.
Wesley Cummins
executiveOf course, Nick. A few points, then. Since the beginning of designing what we deploy now — correct, which is why we refer to it as our fourth generation data center design — we've discussed this. Through this design, we made it exceptionally adaptable, drawing on every lesson we picked up via the processes we've been through alongside all of the hyperscalers; so 1 one, adaptable enough to suit any hyperscaler; yet two, we keep it adaptable in order to future proof as far as we can; and part of that shows up in our approach to the electrical side, part in the cooling. A significant piece involves how much room we place within the data hall, since the direction of travel favors greater power densities, and that holds for the foreseeable future. Yet should it swing toward far lower power densities, we still have room inside the facility to handle that too; so we simply engineered maximum adaptability. We've discussed this across several years now. What I observe in the market, though, is plenty of activity that is purely hyper-focused on how fast something can be brought online and performing something close to an unnatural act, I'd say, simply to get capacity online as fast as possible. And while I won't label that a good or a bad business strategy, I merely want to set it apart from what we do, which reflects a far more longer-term view of how we construct the data centers so they become very long-term assets. There's no way to fully know what tomorrow holds, but that's the perspective we hold as a company. That's how we design them; that's how we design them from a redundancy standpoint regarding both power and cooling, since we could build a somewhat cheaper product. We do have to ensure we can run this product for at least 15 years under our current leases within the SLAs, but our aim is to run them beyond that; yet this is really just more insight into the thinking and the longer-term mindset behind our data center design and building the operations, as opposed to some of the other things we see simply happening overall in the market.
Derrick Whitfield
analystGood afternoon, and congratulations on the commercial and execution momentum you keep building. Wes, I'd like to begin with that 1.3 gigawatts of U.S. capacity you've got on the market right now. On the previous call, you mentioned the market was healthy at the moment, and that you'd anticipate base rates getting better on a risk-adjusted basis. How would you describe the market you're seeing today, really since that last call? Everything unfolding on the regulatory moratorium side is working in your favor, but I'd just like your take and color on it.
Wesley Cummins
executiveAbsolutely; when we look at demand in the market, we aren't seeing — I wouldn't describe it as a major move one way or the other. Basically, it seems to me we're at MAX. That's how I've viewed it for roughly the past 2 years, and it continues to climb, yet demand remains very strong right now. People are still asking for capacity that won't come online until 2027 — honestly, by this point nearly all of '27 ought to be locked up under contract; we'll begin shifting attention toward '28 and '29; some volume is already under contract for '28, yet we're still fielding substantial interest there too; and truly, when it comes to these sites, we often mention North Dakota as an example, though Louisiana also represents a strong market for us; Alabama fits that same description — our track record with the community there has been excellent. Plus there's the assurance that we can keep securing permits for the power generation already operating at the campus. Then there's our supply chain, which has to hold up for us to keep delivering. To restate that point: we anticipate adding both lease expansions and new campuses, and the rates we expect to secure are significantly higher than those in the agreements we executed during the first half of 2026.
Derrick Whitfield
analystThat's great. For my second question, I'd like to revisit Finland. I understand you're still at an early stage with Europe's nascent AI sector, but could you give us your thinking, Bill, on how construction expenses could stack up against those in the U.S., considering labor, buildings, and equipment supplies?
Wesley Cummins
executiveRight. We've actually already run through that analysis, and on a dollars basis relative to euros, we anticipate the build cost will be quite comparable. To put it another way, if we translated the euros back, the dollar figure would come out approximately equal. My expectation is that Europe would see a longer, more stretched-out delivery schedule, simply because of how things operate there compared with what we're used to in the U.S. When we move into European markets, the aim is to duplicate the same approach on the supply chain, design, and build side as in prior years, and having completed that work, we're anticipating costs to be very much alike.
Rob Brown
analystGood afternoon, and well done on everything you've accomplished. I'd like to dig a bit deeper into North Dakota and what it would take to grow there, plus how Base Electron plays into that, considering your PPA. In what way does that begin to make expansion possible in that state, and which years feel the biggest impact from it?
Wesley Cummins
executiveAbsolutely. The way we see it, Rob, 23 is the main year when it comes to Base Electrons. Base Electrons is putting up 1.2 gigawatts in Center, and we expect them to add a substantial chunk of capacity on the eastern side of the state too. We'll support expanding the campus over at Harwood, and then potentially in the central part of the state near Jamestown. There's a new WBI pipeline — WBI is owned by MDU — that they've approved and are moving ahead on. It's been in development for years. So we'll take gas as an offtaker at Center and at Harwood for sure, and maybe in Jamestown. What we've done with that gas pipeline is set things up so we have nearly unlimited room to expand in Center. That site will sit nearer to where the pipeline starts than anything else, and as a rule these lines get narrower as they stretch outward. So Center gives us room for a truly substantial build-out. Everything here will tie into the grid ahead of the meter, and we'll add capacity at other spots around the state as well. On the hardware side, we're talking about purchased equipment. There's already somewhere around 2.4 to 2.5 gigawatts of generating capacity in place, though based on the future demand we're seeing in North Dakota, we anticipate it growing a great deal bigger.
Rob Brown
analystAlright. So a fast second question regarding the supply chain efforts that you've completed. Your execution against the plan has been very strong. In what ways have you reduced supply chain pressures, and how do you view things on the supply chain side?
Wesley Cummins
executiveCertainly. Supply chain, in my view, is constrained throughout the industry, with certain components tighter than others. The largest one—we've discussed this previously from a supply chain angle. What we did most significantly happened nearly 2 years back: we secured critical components within the supply chain alongside a number of our vendors. And with a few of those, we truly bought the entire factory output capacity from particular plants for, as I recall, a 4-year period, to guarantee those essential components were secured for us. So that has helped us enormously. We're striving to increase the additional volume we can absorb, since we believe that moving into '27 and '28 and '29, additional supply chain will be required to keep building toward the demand we observe in the market. Yet the crucial element for us was establishing those relationships, those vital relationships, a good while ago, to ensure we hold our positions within the supply chain for critical components.
George Sutton
analystWes, when you brought up "selective" regarding the upcoming build, I just want to confirm I've got the meaning right. My read is that you mean the caliber of the people you'll take on, rather than how much capacity you'll end up adding — would that be a fair way to put it?
Wesley Cummins
executiveYes, George, that's correct. Compared with where it stood 1 year ago, the company is now in a different position, and the amount of capacity we can build is limited. So we're applying more selectivity about which customers we'll build for, and you're correct about the credit quality piece of that.
George Sutton
analystSo when it comes to that 250 megawatts of expansion, you're essentially saying those will probably arrive at premium pricing. Could you help us understand what premium pricing means in your view? How wide-ranging is that description compared with the base rent, and what else could be part of it?
Wesley Cummins
executiveWell, George, that's what we're aiming for, and we won't dive into excessive specifics, though this has come up from us previously — namely, possibly extended term and considerably larger lease rates, I won't lock that down, yet you can safely assume certainly above 15%-plus growth in the lease rate, and it might also mean longer lease terms; that's the way we characterize it.
Darren Aftahi
analystNice work on the momentum. Regarding Finland, there were a few things I hoped to clear up. First, Wes, could you say more about the amount of power that will be there at the outset? Next, what sort of risk exists with the community or government in that area, whether short term or further out? And finally, was this site obtained on a standalone basis, or was it obtained with a particular customer or customers in mind?
Wesley Cummins
executiveCertainly. The spot we identified in Finland — that's how we see it. It resembled quite closely the communities where we develop in North Dakota. So at the community level locally, the receptivity has been really positive. Data centers have been received rather warmly by the nation overall. That's what we concentrated on when deciding on this site, along with the availability of land, the fiber, and this particular site sits roughly 30 kilometers away from a self-build belonging to one of the big hyperscalers. As for how the power is phased in, the initial 100 megawatts comes online in 2028, then keeps increasing all the way to 2031 until it reaches the complete gigawatt.
John Todaro
analystWhen we think about reaching roughly 4 gigawatts by the close of 2030, what exactly has to happen for you to get there? How much of that depends on Base Electron? And in Europe as well, it sounds like part of that arrives a bit later, in 2031, like you mentioned — so are there additional sites in your pipeline you still need to reach?
Wesley Cummins
executiveYeah, thanks, John. Let me be clear: I noticed you jumped straight to 4 gigawatts, but the figure we discussed was 3.5 to 4 gigawatts by the end of 2030. From a power standpoint, we have power in the pipeline. A portion of that involves the extra capacity from Base Electron arriving in 2030. But on the power side, we think it's already in the pipeline; this was really about how much further we can push our build and delivery. If you run the numbers the way we do internally, reaching the top of that range means delivering roughly 1 gigawatt per year in '29 and '30, correct? So if you build a bridge to the close of calendar year '28, you get to about 2 gigawatts. We believe, as a company, that's the level our construction and delivery can scale up to. So it comes down to those 2 factors together, though far more on our ability and capacity to build and deliver for customers.
John Todaro
analystAll right, got it. That helps. Then one more question specifically about ChronoScale — you signed those 50 megawatts. Clearly, it looks like you could begin scaling up substantially from this point. I'm just curious, when we think a few years ahead, should we basically anticipate ChronoScale reaching around 400 megawatts across Applied sites, similar to what CoreWeave achieved, or is it less than that — I'm just wondering whether ChronoScale follows that same trajectory?
Wesley Cummins
executiveYeah, thank you for asking; that's an excellent question. So as we examine that at present, and you'll have seen across the next month or thereabouts, our approach involves utilizing data center capacity at ChronoScale that sits apart from the big Applied Digital locations. Those locations get contracted to what we've described, namely Tier 1 investment-grade hyperscalers. Regarding obtaining additional capacity, we've identified a solid approach for locking in nearer-term grid capacity that isn't at that magnitude in one place, but spread across several places, yet I believe you might witness ChronoScale climbing to several hundred megawatts of capacity live beyond the main Applied Digital data center constructions by after '27 and '28; however, I'd like to split this into a 2-step set of strategies, where Applied Digital's approach stays unchanged — construct for premium tenants on a large scale. Then we leverage our expertise to assist ChronoScale in obtaining capacity at locations that are more — similar to that initial Microsoft deal of 50 megawatts, which are roughly 50 to 100-megawatt locations that got skipped since they don't reach gigawatt scale or the multi-hundred megawatt scale. Still, plenty of those exist nationwide that are grid-tied, and we believe we can assist them in getting those operational across the next 2 or 3 years, quite a significant quantity in fact during 2027. So that's really — I'm grateful you allowed me to clarify that point regarding the strategy.
Michael Donovan
analystWould it be accurate to say that your current relationship with Macquarie would carry over into Finland?
Wesley Cummins
executiveWell, when it comes to CoreWeave, things have gone as well as I could possibly have hoped.
Michael Donovan
analystMacquarie, Macquarie.
Wesley Cummins
executiveMacquarie — I believed I mentioned CoreWeave, since I intended to discuss that partnership. Macquarie is North America; that partnership operates within North America. I'm not claiming we couldn't establish a comparable arrangement, but the deal we currently hold covers only North America.
Michael Donovan
analystI'm grateful for that. And should you have a strong interest in CoreWeave, I won't stand in your way there. However...
Wesley Cummins
executive<<inaudible>> CoreWeave, that's what I've got regarding that.
Michael Donovan
analystGreat. Then building on what Nick asked. As Infra takes up a bigger portion of customer workloads, are you noticing shifts in the GPU, CPU, and storage mix? And if that's happening, do any of those shifts play into the premium lease rates you brought up or that you expect?
Wesley Cummins
executiveLet me tell you where a change is showing up for us. Over the last 18 months, we've seen a change in the tenant fit out, or the technical fit out, TFO; and here's what we're seeing — since we actually carry that out in nearly every lease we sign, we do that work. The TFO has grown far more adaptable than, I'd say. So if you go back a year, or particularly 18 months, the TFO told us precisely what would be installed in our data center; these days we honestly can't say. And it's turning into a bigger dollar figure for our customers, yet I believe they're putting a substantial degree of flexibility into the facilities so they can handle whatever workloads they choose to run, and that between — we used to always speak of it as GPU TPU, but I think it also applies to the CPU mix, the storage, every one of those elements, network topology; that's genuinely where we're seeing it.
Michael Donovan
analystThanks for that. And then just one more thing, if that's all right. You brought up economies of scale with respect to the builds you're doing at present. Is there any scenario in which you'd look at doing smaller modular build-outs?
Wesley Cummins
executiveThat seems like an ideal spot for ChronoScale; but first, let me make sure — do you mean the containerized options folks discuss for edge compute, or rather a containerized solution of 20, 50, or 100 megawatts?
Michael Donovan
analystRather closer to 20 to 50, and not so much the containerized variety, but or similar small <<inaudible>>.
Wesley Cummins
executiveThose are what we're examining. That's among the methods by which we're locking down data center capacity at ChronoScale — those sorts of modular builds at a reduced scale.
Wesley Cummins
executiveWe appreciate all of you being on this call, and we're eager to talk with you once more in January.
Operator
operatorThis concludes today's call. Thank you for attending. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Applied Digital Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Applied Digital Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Applied Digital Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.