Caledonia Mining Corporation Plc (CMCL) Earnings Call Transcript & Summary

August 13, 2020

NYSE American US Materials Metals and Mining earnings 44 min

Earnings Call Speaker Segments

Steve Curtis

executive
#1

Thanks a lot, and hello to each of you who has dialed into this call. As our hosts said, this marks our second quarter, the results for the second quarter of 2020. We're really glad to put these out and to have this chance to go over them with all of you. You can find the presentation on our website, so if you haven't yet taken a look, please head over there if you'd like to follow along. On the line with me today are Mark Learmonth, our Chief Financial Officer; Dana Roets, Chief Operations Officer; and Maurice Mason, who leads Business Development and Investor Relations. I'd like to jump straight in and, as always, point you to the disclaimer, and I'll treat that as read and understood. The main thing, and probably the one most prominent on everyone's mind, is COVID. If you went through this morning's results, you'll see that production for the quarter was really strong. It truly shows and makes clear that the mine has handled the COVID pandemic extremely well, and it has had almost no impact at all on what we do. I'm delighted to say that right now we have zero COVID infections. We keep applying the highest standards of protection, isolation, and distancing that are required. So yes, COVID's impact on our operation has been minimal. Mark will get into costs a bit later, and he'll explain that we've laid out some money on COVID, but that's a plus, not a minus. So without further delay, I'd like to have Dana walk us through some parts of operations, and let's go through a couple of slides in the presentation. So I'll pass it to Dana. Dana, are you with us? Dana?

Dana Roets

executive
#2

Sorry, I'm back, I was on mute.

Steve Curtis

executive
#3

Okay. All right.

Dana Roets

executive
#4

Turning to Operations Review, Slide 7. Quarter 1 got us off to a strong start this year. Then, as quarter 1 ended and quarter 2 began, the coronavirus lockdown hit. Fortunately, the coronavirus did not hit us hard; following a sluggish beginning while lockdown was in place, we recovered and finished the quarter on a strong note; the grade came in a bit lower than the target. Even so, we recorded a 6% quarter-on-quarter rise on a comparable basis versus a year ago. At the half-year mark, comparing 2019 with 2020, we are in fact up 12%; so on the whole, the outlook we began establishing last year carried from the second half of 2019 into 2020, and the team remains focused, which showed in production. Output is still anticipated to rise to 80,000 ounces starting in 2022. Tonnes milled likewise got better in quarter 2 thanks to, as I mentioned, the Nyanzvi initiatives. Another step we took was installing the oxygen plant, and recovery has improved considerably; we are now approaching 94%. A year ago, we sat just above 93%. Moving on to Slide 8, COVID-19. Over to you, Steve.

Steve Curtis

executive
#5

Thanks, Dana. So, as you’re able to see, and just as Dana has explained, the operation is performing well. We’re keeping things simple, and the operation is progressing toward completing the Central Shaft along with the equipping work happening this year. There’s been a bit of disruption when it comes to bringing certain highly qualified and specialist contractors to the mine, though that stems from travel restrictions and, with luck, it will be brief, after which the program should return to its usual pace. The program keeps going throughout this period and has carried on through the entire lockdown. And we’re eager for the equipping of the Central Shaft to be finalized. On COVID, I have nothing further to add. It gets discussed rather thoroughly on Page 8. So I think we should dive into the heart of the discussion, which concerns the financials. I’ll pass things over to Mark for that.

Mark Learmonth

executive
#6

Appreciate it, Steve. All right, moving over to Page 10. This is essentially just a brief bit of summary data regarding the results; so quarterly gold output came in at 13,500, which is 6% higher than what we saw in the same period of quarter 2. The figure that truly jumps off the page is the on-mine cost per ounce, and that went from $534 per ounce during quarter 2 of 2019 up to $811 in quarter 2 of 2020. I'd like to circle back and get into that quite thoroughly, because the very last thing I'd want anyone walking away from this discussion with is the impression that expenses are being kept in check. The key point, though, is that in the second quarter of 2019, that $534 figure was — is artificially recognized because of a variety of factors, and the quarter ends up looking artificially elevated for a number of reasons. I'll get into that with more specifics, and it genuinely connects to — into the entire pending cost per ounce. Average gold price, as you're aware, the gold price is elevated. So we gained from that dollar amount when it comes to realized gold price. Gross profit, that's a solid figure. It has risen from $7 million to $9 million. That genuinely mirrors the robust performance of the business. Net profit attributable to shareholders, $23 million in quarter 2 of 2019 versus $5 million for this quarter just ended, don't forget. Please don't forget that the $23.3 million in the second quarter 2019 included roughly $20 million of unrealized foreign exchange gain stemming from the swift devaluation of the Zimbabwe dollar last year. So honestly, when you're examining profitability, the number that carries real meaning is adjusted earnings per share, which climbed from approximately $0.24 up to $0.36, so that's roughly a 50% rise there. And that genuinely mirrors the underlying performance of the business. The adjusted earnings per share, after excluding certain business tied to foreign exchange gains, and excluding any profit realized on the disposable asset in South Africa, and excluding deferred tax; so we remove all those numbers and that, frankly, represents the underlying performance of the business. And if accounting isn't your thing, if you turn to cash, perhaps a more realistic approach, net cash rose from $7.8 million at the close of the second quarter of 2019 to $11.6 million at the end of June this year. And that leaves out another $1 million or so, the gold ETF, which we hold in South Africa on a short-term basis to shield cash in South Africa against additional devaluation of the South African rand. So in fact, $11.6 million in something like real terms is actually over $12.5 million. Turning to Page 11; we'll address revenue shortly. The royalties remain fixed at 5%. On production costs, I'm going to return to those with some detail shortly. 7.5 million, up to 11.4 million. So gross profit went from 7 million to 9.2 million. Other income. That's a substantial rise for the quarter. That basically mirrors the Export Credit Incentive scheme, brought in near the close of Q1 2020 and lasting through the bulk of Q2 2020. It got scrapped, I believe, during May; and we were essentially receiving an extra 25%. A 25% premium on gold that we handed over to the government. Honestly, it's circular on the part of the Zimbabwean authorities. Payment comes in local currency; it doesn't amount to much. We weren't exactly thrilled about it, and losing it didn't exactly break our hearts. In our view it's a highly distorting element within the Zimbabwe arrangement; and if anyone — I believe we'll dig into that further, if anybody wants to afterward. On other expenses, 1.3 million during the quarter; that 1.3 million mostly consists of $1 million in donations we gave toward a sort of COVID-19 initiative beyond the immediate mine area. So mining costs — production costs carry roughly $0.5 million of COVID costs at the mine, plus another $1 million for the local community, which we donated; then additionally, we laid out around $200,000 assessing that preliminary work on the solar project. Admin expenses came down somewhat since we aren't traveling as much. Foreign exchange is lower, at just $1.4 million. Regarding the — the asset base in Zimbabwe depreciates, so there's simply less to write down as the local currency depreciates, which explains why that tends to shrink. The cash settled share-based payment, 700,000. That mostly mirrors the LTIP scheme's higher value stemming from the elevated share price. So operating profit came to just under $10 million for the quarter versus $27 million for the previous — for the comparable quarter. Keep in mind that $27 million rise included $21 million of foreign exchange gain. Tax requires a bit of explaining. During the quarter, the tax charge stood at $3.5 million against an accounting PBT of nearly $10 million. That works out to an effective tax rate around 35%. Most of it is Zimbabwe tax, income tax in Zimbabwe. Zimbabwe's tax regime, especially earlier on, is a 25% — 25.75% rate. But we need to grasp that even though we — our Zimbabwe business uses the U.S. dollar as its accounting currency, tax calculations must be done based on Zimbabwe dollar accounts, meaning that losses, foreign exchange losses in U.S. dollar terms or foreign exchange gains in U.S. dollar terms get reversed in Zimbabwe dollar terms. So what did that do, especially in the prior quarter, versus the same period in 2019? It meant Zimbabwe tax rates were being applied to those big unrealized FX gains. As a result, in Q2 2019 we ended up with a working grade tax credit — that's the reason Q2 2019 shows a small tax credit rather than expense, something plainly unusual and not something we could sustain. The tax charge this quarter came to $3.5 million. Most of it is just ordinary Zimbabwe income tax. Beyond that, there are extra taxes tied to shifting funds between locations plus the holding tax. We also pick up a modest South Africa income tax charge related to the procurement function. So tax sits in Zimbabwe — that is, on company profit — and that explains why the total rate can look elevated, though it's elevated purely because of structural flows; that covers the P&L. Everything on Page 12 is simply context, there to help us follow how revenue climbed and what drove those revenue gains — mostly gold price, with tonnes milled and higher production playing a smaller role. Let me add a bit more color on what powered the strong revenue result. Page 13 covers production costs. Let's spend a bit more time here, since this is really where the answer lies for why on-mine costs per ounce went from $534 up to $811. Breaking production costs apart: wages and salaries is 2.9 million — 3.9 million, rising to roughly 4.9 million.

Mark Learmonth

executive
#7

That shows we had more employees and more hours logged. Also, a modest portion—roughly $300,000—came about because during the lockdown we needed to alter how we worked so we could keep proper distance between people at the mining site. To accomplish that, fewer individuals could be sent underground. We had promised the workforce they'd be paid regardless of whether they showed up. Yet the employees who did report, quite reasonably, asked why someone actually descending into the mine and doing the job should earn the same as a fellow sitting idle at home. That pushed us to give a premium rate to those asked to come in throughout the lockdown. This added roughly $300,000 in expenses during the quarter. That covers wages and salaries. For consumable materials, the figure rose from 2.6 million to 3.7 million. Most of that jump came from higher costs tied to upkeep of the underground trackless equipment fleet deployed in the decline. We purchased second-hand refurbished machines, and those tend to be fairly pricey when it comes to maintenance. To tackle this, we found a contractor located in Johannesburg who, when the time is right, will come to the site and assist in boosting equipment upkeep while bringing maintenance expenses down. However, given the current COVID-19 situation, they cannot make the trip. Staff are unable to get to the mine either; so although we have a plan ready to deal with these higher costs, we simply cannot put it into action right now. The major driver behind rising costs, as you can observe, is electricity, which during 2019's second quarter came in under $0.5 million. This quarter it hit 2—a bit more than $2 million. What explains the jump is that the $447,000 spent on power in 2019 shows we were then paying in Zimbabwe dollars. As that currency lost value, our real per-unit electricity price dropped from $0.128 per kilowatt hour down to under $0.02 per kilowatt hour, and all of that showed up in the second quarter. Obviously, that could not last, and it gave us somewhat of a profit windfall, which has since settled back to a bit above $2 million, including roughly $300,000 for genset use; so that's the main factor driving the rise in on-mine costs. So truly, when you attempt to work out why on-mine costs per ounce went from $534 up to $811, there are essentially 4 pieces involved. The piece that came from those artificially depressed power prices during Q2 2019 — that's roughly $150 per ounce. Then genset usage in Q2 of '20 — the greater reliance on gensets in the second quarter of 2020 — added somewhere around $22 per ounce. Higher maintenance spending on the trackless fleet, approximately $64 per ounce. And COVID-19 related costs, covering certain consumables plus labor, about $38 per ounce. When you add all of that together, you go from $534 up to a bit more than $800 per ounce, and that essentially accounts for the reason the — the reason that per-ounce cost went up. These are one-off items, and they're things we have under control. So please don't hang up from this call believing we aren't keeping costs in check. Costs are still very much in check — that's down to these sort of exceptional events — and they sit inside guidance; we remain comfortably within our guidance band for the year. Cash flow — plenty of figures in this section. There are 5 points I want to make regarding the cash flow shown; first we need to strip out the very large unrealized foreign exchange gains of, what was it, $22 million. Point two, simply look at how strong the cash generated by operating activities is; in Q2 2019, it came to a bit more than $2 million for that quarter. The quarter we just closed came in at close to $4 million. Then for the six-month period, it's $14 million. So we keep producing solid cash from the business. You'll notice the cash — CapEx, 0.3. You can see the CapEx figure. It remains fairly elevated, $4 million or $3 million each quarter. During the second quarter of 2020, CapEx was — the CapEx outlay was somewhat hit by the coronavirus, which is the reason we couldn't acquire and accomplish as much as we'd have liked. That will be made up later in the year. But starting in early 2021 and after, we anticipate that working capital expenditure will shrink. You'll see the $1 million gold ETF purchase. That isn't truly an investment — more a matter of shifting money to a different pocket. So I do — I'd honestly say that this lifts the cash figure from 11.6 million effectively to a bit above 12.5 million. And looking at dividends, the dividends paid — that small red number five — dividends paid rose from $882,000 to slightly more than $1 million. That mirrors the 2 dividend hikes we've implemented so far this year, one during January and the other on 31 July. And it reflects the larger number of shares issued too. We issued roughly 700,000 new shares to Fremiro during January in that quarter, with the remaining 15% going to Blanket mine. Turning to page 15, I'm just attempting to highlight the key elements of our quarterly cash flow — cash generated from operations — and then how working capital and cash used in investing activities could impact that. There's nothing particularly noteworthy regarding the balance sheet. It keeps expanding as we put money into the project. Additionally, current assets usually have a tendency to rise as we accumulate inventories in order to be defensive given several supply chain disruptions. What's more, we're increasingly finding it necessary even to make prepayments in Zimbabwe, since supplier credit simply isn't available. So really, that covers everything on the finance side. Should anyone have particular questions, we can return to those during the Q&A session. Steve, I'm handing things back to you.

Steve Curtis

executive
#8

Thanks, Mark. Thanks a lot. Like we mentioned at the very start, this was an excellent set of results. The sector we're in is performing well. The gold price is favorable. And the takeaway here is that the mine continues to run at a level that produces enough cash flow for us to finish the Central Shaft project — which is exactly what we've spent the past 5 years doing. So I'm hoping that point comes across clearly to everyone. Mark already covered dividends, but allow me to expand a bit on the solar project. Our Board has given final approval for us to move ahead with building a solar facility that will let us supply baseload power to Blanket during the daylight hours. This is a strategic move aimed at shielding Blanket from unreliable and rather poor-quality electricity; most of our power does come from the Zimbabwe grid. But as we've seen before, that grid is aging and has its share of issues; beyond that, the entire southern African region faces a power shortage. South Africa itself is short on power, and Zimbabwe does buy electricity from South Africa. So even though COVID has dampened economic activity across the region, we know that will turn around and power demand will keep climbing higher. That's why we've decided to go ahead with a solar project. We'll begin with an initial 12 megawatts. And as I mentioned, that will supply the baseload for the entire operation. Down the road we could expand it, but doing so would require putting other arrangements in place to sell surplus power into the national grid, and we'll get there if it makes sense; we're not going with batteries for the night time, purely from a cost standpoint, so in effect, we'll keep running on a mix of grid power, diesel generator power where it's needed and the solar power. And the solar power would supply roughly 27% of what we need each day. So that's exciting; we're hoping that by this time next year that facility will be up and running. We have cleared ground. But once again, the COVID travel restrictions will stop the right contractors from getting on site. Still, we're viewing that as a temporary sort of hurdle in the process. The next part of the discussion is really just the outlook, and for those who know us well, you're aware that in the shorter term we're working on raising production from our current levels of 55,000, 56,000 ounces, up to 80,000 ounces, as Dana said, from 2022 onwards; and that comes from our ability to reach deeper levels that the Central Shaft gives us access to. So Dana and his mining teams are building the new mine underneath the existing mine, and the Central Shaft with a much increased capacity will allow us to extract higher tonnages and from multiple levels. So that is very exciting. Reserves and resources exist at depth, and as we go further down, deep level exploration will keep going. Given how the ore bodies are formed, successful and complete exploration requires you to be at a deeper point within the mine. So indeed, reaching 80,000 ounces is what we're aiming for. As we've said previously, and we keep actively searching across the Zimbabwe landscape for fresh opportunities where we could put some of the cash Blanket will produce to work; what we want are brownfield operations where exploration can be carried out, or something with a resource already defined that we think we could bring into profit using the in-country know-how we possess. This kind of process requires time, and we've been pursuing it for quite a while. So a huge amount of ground has been covered, though we hope an announcement can be made in the not-too-distant future. COVID is creating a bit of indigestion there too. The shaft we mentioned, and there's a slide covering those in the deck. That's purely for information purposes; but to restate before I finish, I'm on Slide 23. And truly, the wonder of this entire program is that once Blanket lifts its production to 80,000 ounces, the cash generation and the free cash flow will be substantial. The CapEx will come down; and we — you can choose the gold price, and we expect Blanket will manage to produce at sustaining costs somewhere between $700 and $800 an ounce; and at 80,000 ounces you can see that delivers a decent amount of free cash flow, which Blanket will dividend out to shareholders and, with us as the major shareholder, Caledonia will benefit from that; and we can determine where to put that money to work for the greatest shareholder advantage; so I believe that addresses everything we truly wanted to discuss; and I think what we ought to do now is open up the floor to questions, and we invite people to please keep posing their questions to us and the team; so I'll hand it over to our host.

Shareholder

analyst
#9

Speaking as someone who has held shares for a very long time, I couldn't be happier with the way you all delivered given the tough conditions. So thank you to the entire team, very much. If it's alright, I have 4 questions. The first one, and most of these are technical in nature, is for Mark. You said roughly $300,000 went toward genset power this quarter, which by my math is up 2%. Should we expect that figure to rise? How do you see it going forward, until the point when, obviously, solar power brings it down? That's the first part.

Mark Learmonth

executive
#10

Alright. Nir Venda Halom, a shareholder — I'll take that one, and afterward you can address the remaining three questions. We have no way to forecast our genset usage, since we simply must respond to circumstances as they develop. And the reason — a major factor behind why we started some of this wasn't merely that it offers a solid economic return, but rather that it shields us against a scenario where the grid fails entirely, for any reason, leaving us forced to operate the gensets continuously. And in theory, we could operate the gensets continuously. But then you run into the challenge of acquiring that quantity of diesel within such a brief window, which would make it logistically extremely hard; therefore we cannot forecast how much diesel we'll consume. On a typical 24-hour basis, the solar project we're installing would supply roughly 27% of what Blanket needs in electricity each day. Grid power and gensets will cover the remainder, depending on whether grid power keeps being available. I'm afraid a superior answer isn't something I can offer, I'm afraid.

Shareholder

analyst
#11

All right, that's okay. So, regarding capital expenditures, approximately what share of that CapEx sits in development and is in the process of ramping down and declining? And could you give a rough estimate of the cost per meter for development, meaning final development?

Mark Learmonth

executive
#12

Probably, Dana is best place to answer that. Dana, if you could?

Dana Roets

executive
#13

When it comes to our capital or our development, we're in a very solid position. Looking at development, the cost runs roughly $600 per meter; moving on to trade development, that figure comes to approximately $1,000. Then there are our decline developments, which are done using trackless equipment, costing around $1,500 per meter. In percentage terms, yes, going forward we'll be doing approximately 400 meters of development each month; that works out to about 5 pillars. So — and that amounts to 5,000 tonnes a thousand. Let's say, 5 million of development. And I would say that, looking ahead, that isn't the whole — our capital.

Shareholder

analyst
#14

All right. No, that's genuinely useful. So that sort of sets up what I want to ask next. From what I gather, when I look at the 43 to 101 and the production history, you folks had a really huge bonanza in AR. I believe that's the AR Main orebody. And as I understood it, the AR Main orebody is a fairly wide orebody; but I'm just wondering, looking ahead, as you build up to 80,000 ounces, which mining methods will you be employing? You're using trackless machines. But I'm aware that a few of the other orebodies in the region, and I suppose a number of the historical orebodies, are much narrower. Do you have an approximate split regarding what will be sort of trackless? Or will you move into conventional shrinkage stoping? Could you give us a bit of color on that?

Dana Roets

executive
#15

Correct — AR Main and AR South are the two thick orebodies we have, and of the pair, AR South generates most of the output, at a richer grade. That said, looking ahead over the coming 5 years, I'd say the Blanket orebody becomes the source of the majority of what we produce. It's a narrower orebody, though. Trackless mining therefore remains in place at AR Main and AR South. Turning to Blanket, we're shifting back to conventional methods. Certain zones could lend themselves to some long-haul stoping. Even so, that means handheld, conventional long-haul S26 equipment. So what lies ahead is a hybrid setup, with a greater shift back toward conventional mining. As for Eroica, there could be a few chances to apply trackless mining there too, but that's mining in itself.

Shareholder

analyst
#16

All right. Then for my final question, clearly, you don't know the timing for getting contractors back onto that site, but supposing it were possible to have them up there again in, let's say, roughly 1 month, my guess is that you'd have something in mind — what was the target base you had projected for commissioning the shaft?

Dana Roets

executive
#17

It appears we could still wrap up the shaft quite late in Q4. And that holds even with the delay as it stands; so provided we're able to bring the contractors back on site at this point, we would certainly complete it as part of the throughput or commissioning of the shaft.

Shareholder

analyst
#18

All right. And again, kudos to the team. I'm extremely pleased with the way you pulled it off. Nice work.

Howard Flinker

analyst
#19

There are a couple of things I'd like to ask. First, regarding those costs of 500,000 and 870,000 — are they before tax or after tax?

Mark Learmonth

executive
#20

Before tax.

Howard Flinker

analyst
#21

Before tax. And then, Mark, the line cut out on you while you were talking about that 11.5 million of expense versus roughly 7.5 million. Did I get that right — you figure something like 1.25 million, or maybe $1.5 million, of it is reducible?

Mark Learmonth

executive
#22

Let's step back to, what was it? So the production cost you're referring to was, what, 7.5 million in quarter 2 of last year, and this year it came in at 11.4 million. What I'm telling you is that roughly 1.6 million of that comes from electricity, and that piece isn't going anywhere. So yeah, yeah, repeat that, so the item — the cost that, in our view, we flagged would be the expense of the — keeping up the trackless equipment, that runs about $870,000, and factoring in all of the — with the COVID costs, assuming COVID eventually goes away, you'd expect those costs would not happen. Now gensets, we're still going to need the genset going forward, so I wouldn't claim the genset vanishes entirely. So I figured, yeah, let's say, 900 million to about 1.4 million ought not to recur.

Howard Flinker

analyst
#23

Howard Flinker (Flinker & Co., Analyst): All right. Once this present medical emergency is over — obviously, that might not be later today.

Mark Learmonth

executive
#24

Right. It won't happen during this quarter.

Howard Flinker

analyst
#25

Also, is the sale at the market done yet? Or does some of it remain?

Mark Learmonth

executive
#26

No, it's still in progress?

Howard Flinker

analyst
#27

Yes, that's right. Okay. And then — my last question has to do with taxes. Did I hear correctly that your tax rate is going to stay where it is now? Or is it that, given the way things move between tax credits and actually paying taxes, it ends up balancing at a rate a bit below the 35% we have today?

Mark Learmonth

executive
#28

No, I'd still say it stays at roughly 35%, since we still — Zimbabwe's tax is made up of income tax plus deferred tax, and those two should roughly offset each other at about 25%. So the only thing that changes is that once we stop putting in such heavy investment, we'll be handing over more income tax along with the deferred tax, yet we'll still face tax leakage when funds move out of Zimbabwe — meaning withholding tax on dividends paid. And in fact, that figure would likely rise, because as we begin earning more and begin sending more money out of Zimbabwe, obviously we'll be handing over more withholding tax on dividends distributed from Zimbabwe to the U.K., and we'll also keep facing income tax in South Africa on intercompany profits coming from the group's procurement operations. So from a structural standpoint — well, yes, since we keep procuring in South Africa. So one of the — that's one of the...

Howard Flinker

analyst
#29

My assumption was that the profits would get routed to Jersey or Guernsey rather than...

Mark Learmonth

executive
#30

No, no. The reason is that the individuals who handle procurement actually reside and work in Johannesburg, so they must. They have to be in a position to go a short distance to the box burden and inspect a piece of kit. That being the case, doing it from some area isn't really feasible for us. So from a structural standpoint, we will keep on paying an overall tax rate above the basic rate of tax, both because of what it costs to use money around and because of tax leakage that arises in South Africa. That's simply not something we can change.

Howard Flinker

analyst
#31

One more thing I'd like to ask. About that $870,000 in maintenance expense — it wasn't clear to me what caused it. Does that keep going? Or is it additional spending simply so the equipment stays operational while it isn't actually in use?

Mark Learmonth

executive
#32

No. The reason is that we purchased — we reconditioned a piece of second-hand equipment. Dana is probably the best one to address that. So Dana, would you please talk about what the maintenance cost involved?

Dana Roets

executive
#33

Yeah. The situation was that right at the beginning, we purchased secondhand rebuilt machinery, since that was all we could manage financially back then. And we pushed that machinery pretty hard, honestly. Our tracking equipment came in 2015, so it's only been running for 5 years, and we reached a stage where 2018 proved extremely difficult for sourcing parts, and as 2018 wrapped up, getting access to the mine, and then the Zim dollar was introduced, and third, we received 35% of our currency in dollars. And obtaining parts was a real struggle; that got better through 2019; and more recently, it's gotten better still; but alongside that, we began bringing sufficient spare parts, critical spares plus new machinery into the country. Sadly, our aging fleet fell apart rather severely and lockdown occurred and we truly had a hard time getting technicians and parts into the country. The reason is that at the close of 2019, we brought in a South African maintenance contractor to assist us, because we'd also lost a few of our maintenance staff to Vietnam; that period was when things were genuinely awful and you were unable to pay people in the U.S. dollar. So we lost a few of them. And regarding skills, we brought in people from South Africa, then sadly lockdown hit, and we couldn't access the mine. So taking all that together, our trackless equipment ended up in a really poor state, and we needed to catch up on it. So I'd say we likely experienced a spike in those costs, and we're currently working to catch up and that ought to decline once more. And we ought to get more efficient...

Howard Flinker

analyst
#34

Howard Flinker (Flinker & Co., Analyst): So they don't run without interruption; it isn't 870,000 each quarter.

Mark Learmonth

executive
#35

No. And one more thing I'd like to mention — we've actually launched an initiative to swap out the worn-out, aging machinery for completely new machinery. So — that ought to bring down the maintenance expense too.

Howard Flinker

analyst
#36

Is South Africa still under lockdown, or is it over?

Steve Curtis

executive
#37

Right now, yes, it's still going on, though we expect the President to make an announcement at any moment about — possibly loosening things. It looks like some provinces have rounded a corner; and we — like I said, we're waiting to hear whether restrictions will ease. Still, aside from the highly skilled technical staff, supply chains are functioning just fine. And while travel bans create hurdles, moving personnel to the bank isn't out of the question. We did bring in a few extra workers for the Central Shaft roughly a month back. And through the mines, we cooperate with officials — the Ministry of Mines and the Ministry of Health, and we receive special permission to bring people in. It simply takes far longer than purchasing a plane ticket and hopping on a flight. But it can be done. And the authorities are giving us plenty of support to place the right individuals where they're needed.

Steve Curtis

executive
#38

All right, Judy — I'll close things out here and express my gratitude to everyone who took part in today's call. My hope is that each of you found the details you were looking for. Seeing that this call drew the biggest group of attendees we've ever had is really heartening. On behalf of myself and the team, thank you for being part of it. Let's keep following Caledonia's progress, and we'll keep on delivering. As Dana mentioned, our goal remains the same — finish the Central Shaft, and after that we'll carry out the ramp-up. There's more of this story still to come, so once more, thank you. I appreciate the team for being on the call, I appreciate everyone who called in, and I simply want to wish all of you good health and to stay safe. Goodbye for now.

Operator

operator
#39

Appreciate all of you being here on today's call. At this point you're free to hang up your phones. Host, please stay on the line.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Caledonia Mining Corporation Plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Caledonia Mining Corporation Plc earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Caledonia Mining Corporation Plc or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.