Peter Trpkovski
executiveThanks so much, April. Hello, everyone, and thanks for joining today's conference call. With me on the line are Mike Bless, who serves as President and Chief Executive Officer of Century; Craig Conti, our Executive Vice President and Chief Financial Officer; and Shelly Harrison, our Senior Vice President of Finance and Treasurer. Once we finish our prepared remarks, we'll open things up for your questions. Just a quick note: the presentation for today can be found on our website, www.centuryaluminum.com. Our website serves as one channel we use to share material company information and to satisfy Regulation FD. If you'll turn to Slide 1 in today's deck, please take a moment to look over the cautionary statement there regarding forward-looking statements and non-GAAP financial measures that come up in today's discussion. With that, I'll turn the call over to Mike.
Mike Bless
executiveThanks, Pete. And thank you, everyone, for being with us this afternoon. We appreciate the time you're giving us. As usual, if you'd turn to Page 3, I'll walk you through a brief summary of the past 2 months. To start, the approach was to keep running without any stoppage, and most importantly, safety results have been very strong throughout the entire company over these last 2 months, and we're genuinely pleased and proud of that. Operating these plants in a safe and sustainable way is always harder when conditions differ from what people are used to. Even routine scheduling and carrying out the work has to align with our health and safety protocols, and human nature means people simply run the risk of paying attention to too many other matters rather than the task in front of them in a complicated setting like the one we face today. What all of that means is that we'll keep staying vigilant each day, and the key point is that the health situation at every location is still under control. With that said, we have absolutely no plans to ease off in the foreseeable future on any of the protocols we established back in March and April. And in fact, as you'd expect, we're ready at any moment to tighten things up if the public health situation around any of our operations requires it. In just a few minutes, Pete will provide some detail on industry balance pricing and other fundamentals, but let me offer a few quick remarks right now about what we're seeing directly on the ground. Our end-markets in the U.S. have kept getting better over the summer and into the fall. The majority of sectors are close to or even beyond where they stood in January and February, clearly prior to the health crisis's impact. For instance, the automotive and durable goods and machinery markets have completely bounced back. This all matches the data you've seen more widely. Packaging and consumer sectors have stayed quite strong. Construction, by contrast, has somewhat further to go, with residential quite strong and comparatively weaker activity on the commercial side. In Europe, we're observing more or less the same trends, though as you've seen the overall recovery lags that of the U.S.; it goes without saying that all of this is subject to how the public health situation develops over the coming months. Turning to our own specific customers, we see similar trends. Take our six largest value-adding product customers, for example — that group has broad exposure to automotive, to construction, to communications amongst other sectors. As we told you previously, the daily sales rate for that group of customers was down 35% in Q2 over Q1; in Q3, it was up 45% over Q2. So far, October and November order rates have risen another 10% compared with Q3. That means we're now running 60% above the Q2 low and, in fact, 5% higher than the first quarter. Naturally, there was some deterioration late in Q1 once the pandemic started to bite. Turning to the third quarter, financial results landed where we anticipated, since the lower realized metal prices we projected, combined with seasonally higher power prices, accounted for most of the sequential EBITDA decline. As everyone knows, pricing on our sales contracts lags by two to three months, so realized cash LME for the quarter came to $1,550 per ton. Seasonal power prices, as I mentioned, ran higher than usual through the summer. The majority of the remaining EBITDA decrease stemmed from our choice to resume catching up on cell relining at the Kentucky plants. You'll remember we halted every relining job at those plants in the opening months of the pandemic, and several other items combined actually lifted profit slightly. At today's commodity prices, naturally, the financial picture looks far stronger, and Craig will cover all of that in detail shortly. Let me offer a few comments on Mt. Holly. You've clearly seen the warn notice that, regrettably, we issued last week. The ruling from the South Carolina Court in the case between the city of Goose Creek and Santee Cooper shocked us. Of course, we discussed this with you throughout the year. To begin with, our analysis showed Goose Creek possessed every right under federal as well as state law to establish a utility and serve Mt. Holly. FERC then agreed completely in its August order, and crucially, that order stated the determination was reached by reference to federal and state law alike. Finally, the actual hearing before the judge, in our view, strongly indicated that Goose Creek's position was the correct one. When the court's order at last came down 2 weeks ago, it unfortunately said the reverse. The city has requested that the judge reconsider, and should that be denied, Goose Creek has told us they intend to appeal. According to the city, they will ask the court to act swiftly, though fully resolving an appeal would probably require no less than a year. Just to step back — most of you tracking the company already know this, but as a reminder, under the arrangements in place these past couple of years, Mt. Holly has purchased 75% of its electric power needs from the competitive wholesale market and 25% from Santee Cooper's own resources. Mt. Holly likewise paid Santee Cooper transmission fees on the power supplied by third parties. Regarding the third-party power rate covering 75% of what the plant needs, it's extremely competitive, as we've mentioned; honestly, it matches exactly what we're charged at the Kentucky facilities. The remaining 25% that we purchase from Santee Cooper is unfortunately the real problem; it's priced at twice the delivered cost of third-party electricity, so the weighted average comes out entirely uncompetitive. Proof that market pricing is competitive is clear from how the Kentucky plants are doing. As you're aware, we doubled capacity at Hawesville and added filling capacity at Sebree over the past two years; that's over $100 billion in total investment. And running at 100% market power and full capacity, Mt. Holly's cost structure and revenue profile would actually beat the Kentucky plants'. Unfortunately, the reverse is true given today's blended power price. To give you a sense, Mt. Holly's year-to-date 9-month EBITDA shows a $10 million loss, and the plants will be unprofitable in Q4 as well. Turning to next year, importantly, the loss would be even greater. Over the 1 year, average metal prices should of course be higher, at least based on today's forward prices, but that's far outweighed by the need to start relining cells just to keep production at 50% of capacity. As you know, because of the uncompetitive power price, we haven't relined any cells at Mt. Holly in more than four years. During the last several weeks, we've been in direct talks with Santee Cooper, and we're also engaging all the relevant constituencies, including local, state and federal authorities. We're genuinely hopeful now that every party can come together and find a common sensible solution that's actually there. Above all, this means no harm done to any other Santee Cooper customer. What's at stake are 300 direct jobs and 600 to 700 additional jobs currently supported by the plant, plus half a billion of annual economic activity in South Carolina; that's with the plant at current hot capacity. So achieving that competitive price would let us restart the second potline and rebuild alignments and continuously operating, which, as I said, needs a rebuild. We wouldn't just preserve the current jobs, but of course, it would add another 300 jobs and an additional 600 to 700 support jobs, and then you'd get to realize the full billion dollar annual economic impact in South Carolina. It's obviously a complex situation, but one that can truly be solved overnight with a rational logical approach. And with that, I will turn it back to Pete.
Peter Trpkovski
executiveAppreciate that, Mike. Turning to Slide 4, I'll give you a quick rundown of where the worldwide aluminum market stands right now. During the third quarter, the cash LME price came in at an average of a bit more than $1,700 per ton — roughly 14%, or around $215 per ton, higher than what we saw in the second quarter, since the global economy staged a solid comeback over those three months. Market fundamentals keep getting better, and for October the LME price has averaged roughly $1,800 per ton, which sits just above today's level. Looking at regional premiums in the third quarter, they came in at an average of about $0.13 per pound in the U.S., which is a 5% gain versus the second quarter, and roughly $120 per ton in Europe, which is 2% higher than the previous quarter. Right now, spot prices stand near $0.13 per pound in the U.S. Midwest and roughly $130 per ton in Europe. Compared with the third quarter of 2019, worldwide aluminum demand during the third quarter of 2020 fell roughly 3.5%. Outside China, we observed demand shrink by approximately 11.5% versus the same quarter a year earlier. That marks a big bounce back from the second quarter, as manufacturing activity in the U.S. and Europe kept gaining ground. In China, demand rose 3% relative to the year-ago quarter. Global output was approx — was up — pardon me — up around 2% in the third quarter versus a year earlier; China's production grew roughly 4.5% compared with the same quarter last year, though that was offset by an approximately 1.5% drop across the rest of the world during that period. With demand still firming up in our markets, the LME price has kept climbing back to pre-pandemic levels; we keep seeing support and strength in the LME price, thanks to a softer U.S. dollar, low interest rates and a global manufacturing upturn led by the U.S., China and Europe. Taking a quick look at our main raw materials, the alumina index price averaged about $275 per ton in the third quarter, which is essentially where the spot price sits today; and with that, I'll pass the call to Chris.
Craig Conti
executiveAppreciate that, Pete. Moving on to Slide 5, where I'll walk everyone through what we saw in the third quarter. Consolidated global shipments came in 3% lower than the prior quarter, while realized prices fell 5%, driven mostly by reduced lagged LME in regional projects. Turning to operating results, adjusted EBITDA showed a loss of $31.4 million for the quarter, alongside an adjusted net loss of $64.4 million, which works out to $0.67 per share. The main adjusting items in Q3 consisted of $15.4 million tied to inventory net realizable value, $8 million related to unrealized impacts from forward contracts, and $1.2 million from early extinguishment of debt. Liquidity stayed strong, with $169 million available through a combination of cash on hand and credit facilities. As we'll get into with our cash spread in a bit, beyond refinancing long-term debt and pushing out the maturity on our revolving credit facilities, we repaid roughly $45 million in short-term borrowings during the third quarter, since our end markets kept getting better. Now let's go to Slide 6, where I can take you through the quarter-to-quarter bridge for adjusted EBITDA. Just as we projected on our previous call, reduced lagged LME prices and delivery premiums, together with the seasonal rise in power costs, made up most of the drop in EBITDA compared with Q2. Realized LME for Q3 came in at $1,550 per ton, a decline of $80 per ton from Q2, while realized European delivery premiums of $107 per ton dropped $34 per ton across that same stretch. U.S. Midwest premiums were basically unchanged from quarter to quarter. Domestic energy prices averaged more than 15% higher, and the norm full price, which covers roughly 30% of our Atlantic power requirements, rose by approximately $4.50 per megawatt hour. Lastly, as Mike noted earlier, we started catching up on potlines at our Kentucky plants that had been deferred — the ones we paused when the pandemic first hit, if you remember. That catch-up spending added $6 million of cost in Q3 and should normalize as we move through the fourth quarter. Now, looking specifically at Q4, lagged LME of $1,725 per ton is projected to rise $175 per ton above Q3 realized prices. The realized U.S. Midwest premium for Q4 is expected to reach $300 per ton, an increase of roughly $50 per ton, an increase of roughly $50 per ton, while the European delivery premium should come in at $125 per ton, up about $20 per ton compared with the third quarter. Realized alumina is anticipated at $290 per ton, up around $10 per ton from the previous quarter. All together, these pricing movements across LME, alumina, and delivery premiums should lift Q4 EBITDA by roughly $35 million to $40 million relative to Q3. One reminder: these forecasts include at least one month of un-priced LME and delivery premiums, and for those un-priced months we've used current spot values. On top of that, we're looking for pot reline spending to be more even, compared with the bigger amounts we needed to catch up on during Q3, since cell relines stopped by the middle of summer this year. That lower spending should lift sequential EBITDA by roughly $5 million in Q4. Last, realized power prices ought to climb, per current forward curve projections, especially in Europe, and that will drag Q4 EBITDA down by roughly $10 million compared with Q3. Keep in mind, power is purchased by us in the day ahead market, and 2 months of un-priced purchases are still baked into this incremental impact. All told, in isolation, we expect these items to add up to an EBITDA gain of roughly $30 million to $35 million against Q3 levels. All right. Moving to Slide 7, let's briefly review the key cash flow items from the past quarter; the quarter opened with $174 million of cash, and by the end of June it stood at $81 million. Costs tied to refinancing our $250 million note used $9 million during the quarter. As a reminder, the notes that were newly refinanced come due in 2025. Beyond that, we repaid most of what remained outstanding on our U.S. revolver, which drove the bulk of our $45 million repayment usage. Lastly, ordinary shipment timing produced a modest $5 million working capital usage in the third quarter. That wraps up our prepared remarks. Thank you for your time and attention. I'd like to hand the call back to April so the question-and-answer session can start. April?
Mike Bless
executiveHi David, your audio isn't coming through for us. Perhaps your microphone is muted. We're still not picking up any sound from you, David.
Peter Trpkovski
executiveHi there — I believe Lucas is waiting in the queue, so let's move ahead with his question, and with any luck David will be able to rejoin the queue.
Mike Bless
executiveLucas, we aren't able to hear you either. Nope, the audio still isn't coming through for us. That said, is there a backup line or some other option we might use so those questions can be asked?
David Gagliano
analystMy guess is that everyone listening could hear the questions being asked, aside from — only for whatever it’s worth, but even so, I just had — I truly wanted to dig in a bit more. It’s possible I missed this during the prepared remarks, and I apologize; however, regarding what’s happening at Mt. Holly, what comes next and in the near term? And what is sort of the — I suppose, what you’d call the drop-dead date when a choice must be made either to shut the facility down completely or take it to 100%?
Mike Bless
executiveAbsolutely, David, thanks; this is Mike. And I’m sorry to you, and I also appreciate that you stayed with it. Then, I think your question makes sense; so as I’ve mentioned, the next steps are — we’re talking with Santee Cooper. Clearly, they will — simply given how things stand, they will be a supplier or the supplier or a significant supplier during the year ahead; and so we’re having productive conversations with them, which is encouraging on its own, naturally. The response to — and that is really, that is really, right now, to respond to your question, what comes next. It’s hard to say where those lead; and the response to your second question, if we reach, let’s say, the close of November, excuse me, that’s when you truly must begin the early shutdown of the reduction cells of the pots. It’s obvious how these plants operate and how these businesses operate. Every day and week that goes by gets harder. There’s product that will be made in January and February, ideally, that we haven’t yet sold. We have customers who are extremely worried. We have employees, most importantly, and families in the community, who are extremely worried. We need to order commodities, and all of those things can be handled. It isn’t easy, but they can all be handled, and we have contingency plans for everything based on the hope and assumption that we can find a route to a competitive power price.
David Gagliano
analystAll right. Then regarding the potline that's being brought back up, and spending on pot relining — my guess is Hawesville, though I can't say for certain — could you walk me through once more what the plan looks like for Hawesville's sixth potline? And if Mt. Holly ends up closing, might that help offset things, or soften the impact? Thinking about that possibility.
Mike Bless
executiveSure. No, no. Let me take your second question — those two things aren't linked at all. That's an important point when it comes to restarting the Kentucky plant. There's a near-term problem, which Craig mentioned is now resolved, plus a medium-term one. The near-term problem is just that we halted cell relining — I can't recall exactly when, March or April — in the pandemic's early stretch. Partly that was due to the financial expense involved, but mainly we worried, at that moment, whether we'd have sufficient staffing just to keep the cells running, and taking risks wasn't something we wanted. Basically, we wanted nothing happening in those plants except the daily work of operating them — setting carbon, tapping metal, that sort of thing, and so on. So, as you're aware, roughly one-fifth of cells die annually on a set schedule, which represents their economic or practical lifespan. That means a few cells are dying each week. So a number of them piled up. We simply had a queue of them to work through. We finished that during the third quarter. And per Craig, it's now resolved. As for rebuilding that last potline, we're set to begin. You need certain long lead time supplies — collective cast houses plus other cell relining materials — and getting those takes a couple of months. If you asked what's holding us up, the answer is plain. We're simply waiting for things to settle a bit more. Had you asked us 2 to 3 weeks ago, we'd have said, start right after Christmas. As of today, I believe we'll all just engage in some watchful waiting regarding the situation across the next couple of months, and that likely needs no saying.
David Gagliano
analystOkay, alright. That’s helpful. Thanks.
Mike Bless
executiveThanks, David.
Lucas Pipes
analystHi there, good afternoon everyone. For whatever it’s worth, this is already my second conference call today that ran into technical problems, so perhaps something got into the system. I’d like to pose a different question regarding Mt. Holly. Doing a rough calculation, it looks like roughly $1 billion of economic activity may be at stake, weighed against tens of millions of dollars in electricity costs. Does that strike you as approximately correct? Then, second, picking up where David left off. I’m less focused on timing and more on what choices actually exist right now. Is the only path reaching a deal with Santee, or shutting things down, or — despite the municipal possibility having collapsed — are you still looking at a third, fourth, fifth possibility at this moment? I’d really value your response. Thank you.
Mike Bless
executiveThank you, Lucas. Regarding your first point, yes, that study was conducted by a professor at the University of South Carolina. It isn’t ours. To be precise, that research arrived at $985 million as the yearly economic activity generated in South Carolina by the plant. So your grasp of the situation — I thought you stated it, honestly, both briefly and effectively. On the second matter, you’re also correct about the back end — sorry, about your second question too. Right now, everything hinges on reaching an agreement that satisfies the supplier, that works with Santee Cooper, and that they regard as fair and equitable. Naturally, that would allow us to reach a competitive price so we can rebuild those potlines, bring the plant back to full capacity, and earn a sensible economic return, obviously across the cycle. That’s truly all there is. As for our partners at Goose Creek, naturally we’ll monitor with interest the legal proceedings, the reconsideration request, and then the appeal should the first not be granted. They’ve been wonderful partners; they’re significant neighbors. Their city is a charming place that directly abuts our site there. You may not be aware, but we hold close to 5,000 acres, with only 300 of that used for the plant itself plus the necessary buffer zones and dispersion zones. So there are quite a few intriguing possibilities that could unfold there in the coming years, and the city has been excellent partners and will remain so in many ways. As for your question, I can’t — I don’t wish to guess at what you may be thinking regarding third, fourth, or fifth options, but beyond that, that’s really all. I don’t want to make it too simple, since the present circumstances carry plenty of complications. Still, that’s where things stand as of today.
Lucas Pipes
analystThat's quite useful. My best wishes to you and everyone else too. Good luck. For my second question, I was hoping to gain somewhat better clarity regarding where Canadian import tariffs stand right now. During the last quarter there was some back and forth. I just want to confirm that I, and investors, grasp what the status quo is? And related to that, the Midwest premium has seen some volatility lately. Could you share your thoughts on that and where it goes from here? Many thanks.
Mike Bless
executiveCertainly. Appreciate the question. Regarding the first part, here's how things currently stand. An announcement came from the USTR — gosh, I can't — my best guess would be 4, 5, 6 weeks back. Let's say 4 weeks back, give or take; and per that announcement, Canadian imports of primary aluminum, unwrought, would get an exemption from the tariff once September 1 passed, provided that imports were at or under specific threshold amounts that USTR laid out in that release. As you saw, it was just under 100,000 tons per month, which would have been, which will be or would be, I should say, a substantial meaningful reduction in rate versus the other run rate across the last year. There was — either yesterday or 2 days ago, I can't remember now, the official — the current official proclamation confirming it came out, but it merely repeated what USTR released 4 or 5 weeks ago. You might wonder, will imports fall below that threshold? And the answer is nobody knows as of yet. Those figures for September won't come out for roughly another 2 weeks. So we shall see. The market, as you mention, one could examine how the Midwest moved and conclude that perhaps the market thinks imports are declining, metal is extremely tight. If you asked traders and customers, most importantly, they would tell you there aren't many problem units in the U.S., specifically, particularly, in the Midwest. You have seen the Midwest premium rise here to a posted level of just barely under $0.13, $0.127, $0.1275 and that's up from a low of mid-8's before the tariff returned on Canada and then came back off; so it has risen considerably since then. It's down from the recent peak it hit of roughly $0.15 and so the market for the delivery premium has, as you point out, gotten stronger here across the last 3 or 4 weeks.
Lucas Pipes
analystThat's really useful. I appreciate the detail, and good luck — thanks.
Mike Bless
executiveThanks a lot. I appreciate it.
John Tumazos
analystWe saw that Century acquired many of those assets quite cheaply, frequently at a price equal to working capital. As a result, there's negative goodwill in most situations, or substantial markdowns versus actual worth. Of your $899.4 million in net PP&E, might you clarify what portion is Mt. Holly? What amount sits in Kentucky, what amount sits in Iceland, how much belongs to the carbon anode plant or real estate, so we can get a feel for the financial exposure if you shut down or walk away from Mt. Holly?
Craig Conti
executiveSure, John. Right. John, this is Craig. Thanks once more for asking. I won't go through the entire balance sheet, but simply to give you a feel for Mt. Holly, gross PP&E at that site falls between $150 million and $175 million; and that, again, is gross — on a net basis, it's approximately half of that.
Mike Bless
executiveJust to jog your memory, John — this is Mike speaking. I appreciate you asking that. The amount we handed over to acquire 50% of that facility 6 years back came to slightly more than $50 million. That should help frame the figure Craig mentioned.
John Tumazos
analystLet me just reason through this aloud. Down in South Carolina, those 5000 acres of timberland — if it were merely trees, you'd figure roughly $2,000 per acre, which comes to $10 million, and I'm presuming that's the buffer surrounding the loblolly pine. Yet the location sits on the bay, the surroundings are gorgeous, and it can be developed. So possibly this idle parcel carries greater value for building, and you're holding it as an aluminum smelter?
Mike Bless
executiveJohn, that — I take your point; the land is beautiful. It sits squarely within an area expanding very rapidly. Like I mentioned, Creek has been booming. The municipality is extremely well managed and has grown right up to — assuming you've visited the plant — the southern edge, extending from the south all the way to the western boundary of the property we own there. Other industry exists nearby too, including several solid partners and customers of ours. Therefore a sizable portion of that acreage, as you note, could be developed, yet at present we believe the finest application of the site is operating that smelter beneath a competitive electricity cost. I mean that's — that — with competitive power pricing, to put it purely in economic terms, you get the maximum NPV. If you could secure a power price canyon within the same ZIP code as what we pay to deliver at our Kentucky plants across a cycle, that facility generates attractive economic value. So that's the direction we're pursuing there. And in our firm opinion, that's what delivers economic sense for shareholders.
John Tumazos
analystMike, despite the downturn we're in right now and this difficult environment, your operating cash flow came in at $33 million, which exceeded the $11 million you spent on CapEx, and taking everything into account, that beats U.S. Steel and plenty of other businesses. You took on a modest amount of debt and completed a few re-financings — could you walk through the real-world rationale for being a slight net borrower across the nine months, even while cash flow stayed positive?
Mike Bless
executiveAbsolutely; wonderful question there, John, and I appreciate the remark. Two factors were at play. First, if you remember, during the second quarter — when exactly did we tap those revolvers? Early in April. Thank you, Craig. So it was April, near the start of Q2, that we pulled down funds from those revolvers. We figured we wouldn't require the liquidity, or the cash, so to speak — of course we always maintain liquidity, I guess, so that wasn't the right term; we figured the cash wasn't necessary, yet as everyone recalls, looking back at 2008 and 2009, with the anxiety following Lehman and worries over banks' capacity to fund and so forth, we simply — the borrowing costs, or funding costs, in that case are incredibly cheap. So we drew that cash down; and per what Craig mentioned, about 50% of it got repaid during Q3 and roughly — excuse me, the remainder will probably be handled shortly. Secondly, our single public debt item, one term debt issue, was approaching the one-year mark before maturity. Its due date was the 1 of June 21. And once more, this means recalling the April and May period. Nobody had any idea where things were headed. And we believed, once again, that erring on the side of caution justified having shareholders pay a small premium — an insurance premium, as we saw it — to refinance that note. That's precisely what we did. Naturally there are fees tied to that tender; we ran a tender for the outstanding issue — calling it was an option, but the economics favor tendering slightly more. And that explains why you observe him assembling the whole thing and mixing it together, producing that net position you accurately characterized.
John Tumazos
analystMuch appreciated, and best of luck.
Mike Bless
executiveMany thanks to you, John.
Paretosh Misra
analystThanks a lot for fielding my question. I'm simply wondering, when you consider the coming year — at least its opening six months — is there anything significant shifting within your cost structure, setting aside, of course, every item you already give sensitivities for? And, I suppose, on a connected note, have you done any thinking regarding your alumina supply for the year ahead? What sort of pricing structure are you currently considering?
Mike Bless
executiveParetosh, thank you for asking. Would you like to — Craig, why don't you take the cost structure part?
Craig Conti
executiveSure. On the cost structure, I'll break that into a couple of parts. For the remainder of this year, it ought to look a lot like what we described back in April. When it comes to 2021, we genuinely rely on our Q4 call, scheduled for January, to set out any significant shifts. Looking at Q3 and Q4, as we discussed, we keep observing power forwards moving higher. That pattern might just as easily — well, our power forward sits fairly far out, so it might just as easily swing back. So I don't expect any significant shifts arriving in 2021 that we can see as of today, and I'll certainly follow up with you in January regarding the rest.
Mike Bless
executiveLooking at things from the operations side, the major factor would be if we can work out something at Mt. Holly. Like I've mentioned, within that cost structure there's been zero pot relining expense, Paretosh, across the past couple of years, and as — in contrast to a number of our competitors — GAAP permits that kind of treatment. And in contrast to a number of our competitors, we expense — we take that pot rebuild cost as an expense instead of capitalizing it, so there will be a substantial chunk of that hitting our cost of sales in the coming year, with a lesser figure in 2022, provided we're able to resolve the power issue. That, then, would be the biggest swing factor among the plants. As for your second question, yes, we've wrapped up negotiations covering the vast majority of — honestly, for all of our — the vast majority, let me say, of our alumina supply for 2021, and even more so than in 2020, the vast majority is going to be priced as a percentage of LME. I'm not able to give you the exact details, but we've settled on what we consider the fair value range for alumina as a percentage of LME. We've stated this previously, and I'll repeat it: we would not sign off on any contract priced outside that range we've defined as fair value.
Paretosh Misra
analystUnderstood. Excellent. That's useful detail. Then, I suppose the remaining — I'm not sure whether you addressed it, and I apologize if it was already covered. Could you offer any insight into the share premiums currently observed in the market? And also — I suppose, anything you've discussed lately regarding the coming year about how to approach that, that aspect of pricing?
Mike Bless
executiveYes, excellent question. Yes, what I mean is the brief, straightforward response is they've returned to roughly the level they sat at, honestly, 12 months back when we were wrapping up. Another contract existed for this year, for 2020. What I mean is commodity and billet premiums moved from around — all of these are delivery prices now above the Midwest, naturally. They sat at roughly eight to ten, give or take, 12 months back. They dropped to 0, genuinely 0 or very — marginally above 0, and today they've come back to high, high single digits. And that's roughly what we anticipate absent any significant shifts given the current situation.
Paretosh Misra
analystUnderstood. Okay, that covers everything I wanted to ask. Thank you, Mike, and best of luck with the talks at Mt. Holly.
Mike Bless
executiveI appreciate that very much. We truly are grateful for it.
Mike Bless
executiveAll right. Once more, we're grateful for the engagement — everyone's asking really solid questions — and I hope all of you are still staying healthy; we'll be in touch before long. Be well.
Operator
operatorThis concludes today’s conference call. Thank you for your participation. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Century Aluminum Company transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Century Aluminum Company earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Century Aluminum Company or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.