executiveHello everyone, and thanks for being with us on the Dominion Energy call covering results for the first quarter of 2025. The materials we've released, which include the remarks we prepared for today, feature forward-looking statements and estimates facing a range of risks and uncertainties. For a look at the factors that could lead to outcomes differing from what management estimates and expects, please see our SEC filings, among them our latest annual report on Form 10-K along with our quarterly reports on Form 10-Q. Later this morning, we'll go over certain ways of measuring how our company has performed that depart from what GAAP recognizes. You can find reconciliations of our non-GAAP measures against the closest comparable GAAP financial measures, the ones we're able to calculate, inside the earnings release kit. We'd love for you to stop by our Investor Relations website, where the webcast slides and the earnings release kit are available to review. On the line with us today are Bob Blue, our Chair, President and Chief Executive Officer; Steven Ridge, our Executive Vice President and Chief Financial Officer; and Diane Leopold, our Executive Vice President and Chief Operating Officer. Steven, over to you.
Steven Ridge
executiveThanks, David, and good morning to all of you. Following the wrap-up of the business review, we've laid out three priorities: first, hitting our financial commitments consistently; second, keeping major construction milestones for the Coastal Virginia Offshore Wind Project on schedule; and third, securing constructive regulatory outcomes that show we can collaborate with regulators and stakeholders to produce results benefiting customers and shareholders alike. Meeting these objectives lets our employees carry out the vital mission of delivering reliable, affordable, and ever-cleaner energy that powers our customers daily. On this call, we'll cover each of those areas, beginning with hitting our financial commitments. As you can see on slide three, the year has started well, with first quarter operating earnings of $0.93 per share. That figure reflects $0.03 from better than normal weather, $0.02 from RNG 45Z income, $0.02 from better than expected sales, robust rider investment growth, and a mix of O&M and tax timing benefits that we anticipate will normalize over the remainder of the year. First quarter GAAP results came in at $0.75 per share. We are reaffirming all financial guidance given on our fourth quarter earnings call, which includes 2025 operating earnings per share of $3.28-$3.52 per share, inclusive of RNG 45Z income, with a midpoint of $3.40. As a reminder, Schedule 2 of the earnings release kit contains a summary of every adjustment between operating and GAAP results. In addition, Schedule 4 of the earnings release kit lays out a summary of all drivers for earnings versus the prior year period. Moving to our financing plan, as slide four shows, we have sold roughly $1 billion of forward-settled common equity through our existing ATM program at a weighted average price of approximately $57, and we expect to finish $200 million of DRIP-related equity issuance by year-end. That aligns with our 2025 common equity guidance. Given our substantial growth capital spending program, we consider this pace of steady equity issuance under existing programs suitable for keeping our consolidated credit metrics inside the guidelines for our strong credit ratings category. We stay committed to balance sheet conservatism, and our previously communicated credit-related targets remain unchanged. Turning briefly to data centers, as a reminder from our fourth quarter update, we have approximately 40 gigawatts of data center capacity at various stages of contracting, including what now amounts to approximately 10 gigawatts of capacity contracted under electric service agreements. Since our last call, we have seen no evidence of slowing demand from data center customers throughout our service area; in closing, I'll restate that I have strong confidence in our capacity to deliver on our financial plan. The financial guidance was constructed to be suitably yet not excessively conservative so we can withstand unforeseen challenges that might arise. With that, I'll hand the call over to Bob.
Bob Blue
executiveThanks, Steven. Turning to safety performance, our Dominion Energy colleagues endured a devastating incident on March 31. At Wateree Station in Eastover, South Carolina, Ryan Barwick, a material fuel handler, lost his life after sustaining severe injuries while unloading a rail car. Losing this dedicated member of our team has caused us deep sorrow, and our thoughts and prayers continue to be with his loved ones — family, friends, coworkers, and community. Our number one core value is safety; it sits at the center of who we are as a company, and we'll keep making improvements until we reach the sole safety figure that is acceptable, which is zero injuries. Moving on to the Coastal Virginia Offshore Wind Project, I want to begin by covering a few project highlights found on slide five. This project stands at 55% complete, just months away from delivering electricity to customers for the first time in early 2026, and it remains on track for full completion at the close of next year; it offers the quickest and most cost-effective path to bring nearly 3 gigawatts of power to Virginia's grid, which would bolster America's AI and cyber leadership along with the biggest data center market anywhere in the world, would back U.S. shipbuilding at customers such as Huntington Ingalls — the biggest military shipbuilding firm in the United States and among our largest customers — and would support some of the nation's biggest and most critical military and defense installations; it enjoys strong bipartisan backing from Virginia's government and congressional leaders, local communities, military and defense stakeholders, the commercial marine sector, and civic, educational, environmental, labor, and community partners alike. It has produced roughly 2,000 direct and indirect American jobs and driven $2 billion in American economic activity. Lastly, it has the support of Virginia law and has been approved by the State Corporation Commission along with federal agencies. In summary, this initiative fits with our goal of ensuring American energy dominance, and it's one component of our comprehensive, all-of-the-above approach to energy that's designed to satisfy growing demand at a reasonable price. Since the last time we provided an update, progress has continued at a consistent rate. Slide six illustrates that every one of the project's 176 transition pieces — that's 100% — has been rolled, 86% have come through steel welding successfully, and half are now complete, a figure that takes in the 59 we've managed to install since that work began on December 31. We expect the final transition piece to be finished in October. More than 80% of the 176 monopiles for this project have been completed and shipped successfully to Virginia — that figure includes the 78 that went in during the latest installation season. As for the 32 monopiles still outstanding, we expect those deliveries to continue at a steady pace in the weeks ahead. Installation of the first offshore substation took place on March 10, while the remaining two offshore substations remain on schedule for delivery this summer, with installation set for the fall. At Siemens Gamesa, work on the project's 176 wind turbines is moving along very well and staying on time. Components for 28 complete towers are done, and an additional 45 towers are in production right now. On top of that, 36 nacelles have been completed or are waiting on final testing, and 28 blades have finished the casting process. Last, and as you can see on slide 10, Charybdis — the installation vessel we built in America that complies with the Jones Act — should be put into service and start heading toward Virginia within the coming four to eight weeks, keeping to schedule so it can assist with turbine installation this summer, just as we planned. Before moving on to tariff exposure, I want to point out that, apart from any tariff effects, what we're paying for project components has stayed consistent with what we told you previously. The project's unused contingency right now sits at $222 million, the same as in our prior update, and that equals roughly 6% of the costs still ahead of us. Let me now turn to the subject of tariff exposure. It's difficult to get a full picture of how tariffs could impact the project's ultimate cost, since the amount we ultimately pay depends on whatever tariff rules and rates may be in place at the time a particular component gets delivered. Given that this uncertainty remains, we've set out on slide 11 the potential tariff exposure broken down by distinct tariff categories and illustrative time periods. To begin with, the project had realized actual tariff expenses of $4 million through the close of the first quarter. Next, assuming today's tariff policy stayed in effect until the second quarter ended, that figure would rise to roughly $120 million. To wrap up, let's say the present tariff approach stays in place until the close of 2026, which is when we anticipate the project will be completely operational — under that scenario, the total tariff hit would come to about $500 million. Just so everyone's clear on this, the portion of that figure falling on Dominion Energy is approximately $130 million. Of course, if tariff policy shifts going forward, those projections could change. We submitted our quarterly offshore wind construction update today to the Virginia State Corporation Commission, and in that filing we increased overall project costs by about $120 million — an amount that lines up with what we estimate for tariff costs already incurred, plus what we expect through the end of the second quarter, as reflected in the table included in today's materials. So as a result, this quarter we recorded a modest charge tied to expenses we don't anticipate recovering from customers — that's in line with the settlement on cost-sharing we reached with regulators in Virginia as well as our agreement with Stonepeak covering a 50% partnership on sharing costs. Both cost-sharing and risk-sharing continue to work as intended, protecting customers along with shareholders. Under the cost-sharing settlement that Virginia regulators approved, the project's revised cost of $10.8 billion ought to increase the typical residential bill by about $0.04 cents per month over the life of the project. Even when you factor in RECs, the project's revised LCOE of $62 per megawatt hour remains highly competitive when measured against alternatives for new generation, including solar, battery, and gas-fired generation. I want to be clear. CVOW remains one of the most affordable sources of energy for our customers. Moving to the regulatory landscape, let me give a quick update on our Virginia biennial review filing, which we submitted at the end of March. The filing highlights Dominion Energy Virginia's reliable and affordable service. If approved, this would be the company's first base rate increase since 1992. Also, across the last 10 years, what homeowners pay us has climbed roughly 40% more slowly than inflation. In our filing, we also put forward a proposed new rate class aimed at large energy consumers, data centers among them, plus fresh safeguards for customers so that they keep covering the entire cost of their service and so that other customer groups are shielded from stranded cost. Those safeguards feature a 14-year contractual obligation to pay for the power they ask for even when their usage falls below what they requested. That aligns with the worries and suggestions laid out in last year's JLARC report and matches what has been proposed in other jurisdictions across the country. Slide 13 displays the commission's procedural schedule. On a separate note, Dominion Energy Virginia submitted a filing on March 3 with the State Corporation Commission seeking a certificate of public convenience and necessity to build and run the Chesterfield Energy Reliability Center, a gas-fired electric generating facility that forms part of our all-of-the-above strategy for energy supply. Should it win approval, this project of about 1 gigawatt is projected to cost around $1.5 billion and to enter service in 2029. Funding for it appeared in our latest capital update.
Bob Blue
executiveNow, moving on to South Carolina: lawmakers in both the House and Senate are still reviewing possible energy bills there. Those measures would tackle the state's future generation requirements, permitting changes, and recovery of regulated investments. We appreciate how much time the legislature has already devoted to this important matter. In our view, these efforts back the goal we have stated — helping South Carolina's strong and expanding economy succeed. Broadly speaking, we keep producing favorable results across every one of our regulated service territories. Moving to Millstone next: that facility keeps running well, supplying more than 90% of Connecticut's carbon-free electricity, and 55% of its output sits under a fixed-price contract running through late 2029. Our hedging program keeps substantially reducing risk on the rest of that output. As a lot of you know, New England — Rhode Island in particular — has seen legislative activity lately, meant to allow additional nuclear power procurements down the road. We've stayed in touch with numerous parties there, searching for the greatest value for Millstone. Beyond procurement sponsored by the state, we also keep assessing whether we might support incremental data center activity; our strong feeling is that any data center possibilities must be chased in a collaborative way alongside Connecticut stakeholders. We'll share updates as matters evolve. Before wrapping up my comments, I want to pause and acknowledge Diane Leopold. She made her retirement announcement late last year, and she leaves on June 1. This earnings call will be her final one. Among the sharpest, most committed, and most skilled individuals in our company and our sector, Diane stands out. Across 36 years working in the utility business, she has shown best-in-class performance in practically every area — operations, business development, financial planning, and corporate strategy — plus the building of multiple multi-billion dollar energy infrastructure projects. Luckily, Diane has developed a deep, talented bench ready to carry on her legacy. Working alongside her for the past 20 years has been my honor and privilege, and I'm confident I speak for Steven, David, and the whole Dominion Energy team when I thank her and wish her the best in retirement; so with that, let me wrap up our remarks on slide 15 by restating where Steven opened this call, centered on our three priorities: consistently hitting our financial commitments, continuing to reach major construction milestones on time for the Coastal Virginia Offshore Wind Project, and securing constructive regulatory outcomes that show we can cooperate with regulators and stakeholders to produce results benefiting customers and shareholders alike. Execution is our 100% focus; we stay dedicated to providing reliable, affordable power to our customers. With that, we're ready for your questions.
Nick Campanella
analystHello there, good morning. I appreciate you fielding my questions. Many thanks for all the information you've shared.
Bob Blue
executiveGood morning, Nick.
Nick Campanella
analystGood morning. Hey, I really appreciate how much information you've shared regarding the CVOW project, particularly the parts tied to tariffs. When it comes to the turbines and the companies supplying them, is there anything you're able to share about what you've discussed with them that gives you assurance this tariff situation won't hurt their capacity to deliver for you — whether that's from your own talks or simply the delivery timelines? I realize you pointed out that Siemens is making significant strides, but perhaps you could say a bit more about how confident you are overall. Thanks.
Bob Blue
executiveSure, I'll share a few thoughts. If Diane has something to contribute, she's welcome to. She visited there not long ago, and on our previous earnings call she made a commitment to address every question today. What our suppliers tell us is that each of them is doing exceptionally well. Among those who began most recently — Siemens Gamesa is the one who started most recently — they're meeting their targets. They kicked off right on schedule. Their output is at the rate we had anticipated; we have a great deal of confidence in our capacity to obtain the materials and components required. We've already revealed what the tariff consequences would look like under the tariff policy currently in place. Nothing has really shifted when it comes to delivery timelines or capability.
Diane Leopold
executiveOne more point I'd make is that we've already bought every bit of the raw materials. At this moment, all of it is in fabrication. As Bob mentioned, the Siemens Gamesa equipment — the newest piece to go into fabrication — is actually running slightly ahead of schedule. Two weeks ago, the team and I visited each of those facilities: the nacelles, the blades, every one of them. All of it is either on track or somewhat ahead of schedule. Over the next few weeks, deliveries will begin.
Nick Campanella
analystAll right, that's useful. Regarding the monopiles, from what I understand, the season kicks off today. Any word on whether you'd be starting that right away, and what sort of pace should we anticipate over the coming months for installing monopiles?
Bob Blue
executiveCorrect. Monopile installation season begins today, and today is when we begin. For a bit of background, consider the past four months: we've put in 60 transition pieces, an offshore substation, plus the jacket holding it up, and deep water export cable. Getting monopile installation going again today is really just a continuation of the consistent offshore headway we've achieved since this project started. On the pace question, I believe we've mentioned previously that we reached a rhythm once we'd more or less completed the early work in the prior monopile season. We got to roughly 25 per month. That's a rhythm we should be able to sustain. Naturally, everything depends on weather, but that pace is very attainable.
Nick Campanella
analystAlright, that's excellent. And Diane, congratulations on retiring. Thank you very much.
Diane Leopold
executiveThank you. I appreciate it.
Bob Blue
executiveThanks, Nick.
Jim Kennedy
analystHey, guys. Good morning.
Bob Blue
executiveHello, James.
Jim Kennedy
analystTo pick up where we left off regarding CVOW, I was hoping to dig in a bit more specifically on what’s happening with permits. I’m wondering whether you’ve had any talks or engagements with state or federal authorities that provide somewhat greater incremental reassurance in the wake of the Empire Wind order? Any additional detail on the permitting front would be helpful. Thanks.
Bob Blue
executiveYes. So, James, the way we've been dealing with the agencies hasn't changed at all over the last several months. As you're aware, this project has all the permits it needs. Still, given how large it is, we make a point of touching base with those agencies on a routine basis. Those discussions have kept going. And based on what we laid out in our prepared remarks, we have a lot of confidence that things will keep progressing for this project.
Jim Kennedy
analystAlright. In the event that a stop work order was issued, could you provide a rough guideline regarding what a daily standby or demobilization expense might be?
Bob Blue
executiveYes. I believe that's a really key thing to ask about. Thanks for bringing it up. At that point, we would need to look at the particular facts and circumstances. I'm not able to address those since I don't have knowledge of what they'd be. Should that occur, we would handle it with full transparency. For every reason I mentioned during the prepared remarks, we don't believe it will be halted. Getting 2.6 gigawatts onto the grid is the quickest path to serve tech companies, defense, and security installations, and important American industries such as shipbuilding. It's providing employment for 2,000 people. A stop would lead to energy inflation. Virginia law grants it explicit authorization. It enjoys bipartisan backing in Virginia, especially from the Hampton Roads congressional delegation. Discussing figures for a pause or delay truly doesn't make sense. With that said, these investments are made prudently. Utilities have the right to recover costs that were prudently incurred. That's definitely the case here, subject to the cost-sharing and the SEC order, clearly.
Jim Kennedy
analystAll right, that's great. Now, regarding the tariff plan specifically, there is also some expenditure on solar and storage included in it. I suppose any sort of insight you could offer as you consider the effects of tariffs in that area along with the spending trajectory, and whether anything shifts. Thank you.
Bob Blue
executiveYeah. So when we look at how tariffs affect the various parts of what we do, what we're dealing with is something we can handle. We've been focused on our supply chain for a while now. The bulk of the vendors we use, or most of the materials we buy, come straight from suppliers here in the U.S. That's definitely the case when it comes to our solar sourcing. For a while we've been running an initiative aimed at broadening where we source from and making our supply chain more resilient. A portion of that kicked off during COVID, when we began considering these things. We look at holding more inventory and raising order thresholds so we can deal with longer lead times and make sure we've got more than one source available when that makes sense. In cases where it's feasible, we've been putting in some orders before the dates tariffs take effect, so we can soften cost increases. Thanks to those steps, we've managed to sidestep a portion of the effects. Clearly, our top priority is to steer clear of impact and keep what customers pay down. Across the whole business, we see tariff-related costs as something we can generally handle.
Steve Fleishman
analystYes, absolutely. Thank you. I'll second that — congratulations, Diane. You truly did an excellent job. Tom, my apologies. There'll be no more covert snacking on unhealthy treats throughout the workday.
Diane Leopold
executiveThank you, Steve.
Steve Fleishman
analystRegarding the tariffs first — so we're aware, if they do get modified — is it essentially the case that these agreements pass along most of the tariff cost to you? Should they rise or fall, we could attempt to estimate the effect. Is that roughly the way these contracts typically operate?
Bob Blue
executiveYes, Steve, that's an accurate way to describe it.
Steve Fleishman
analystAll right, and perhaps one more thing — I realize this is sort of a gubernatorial election year. Has any electricity-related subject, including CVOW, come up at all within the political arena from either party as a piece of that?
Bob Blue
executiveNo. Thus far in the race for governor, there hasn't been any conversation about CVOW or wind in general. What I can tell you is that our lieutenant governor, the Republican nominee, attended an event of ours — I'm not sure, 18 months or 2 years back — when the initial monopile showed up in Tidewater at the port. The Democratic nominee, former Congresswoman Abigail Spanberger, has likewise backed offshore wind. Even so, it hasn't become a subject in the discussion.
Steve Fleishman
analystAll right, regarding Chesterfield, I saw that the gas plant got approved — $1.5 billion for a gigawatt facility, and honestly that's beginning to look like a pretty low price these days. I just want to confirm that figure is accurate.
Bob Blue
executiveYes, that figure is accurate.
Steve Fleishman
analystUnderstood. That's all I had. Appreciate it.
Steven Ridge
executiveThank you, Steve.
Bob Blue
executiveThanks, Steve.
David Arcaro
analystHi. Thanks. Good morning.
Steven Ridge
executiveGood morning.
Bob Blue
executiveHey, David.
David Arcaro
analystCould you perhaps share a bit more detail regarding what you're observing when it comes to demand from data centers? You noted that it has, in a way, carried on from the prior quarter. What exactly is the level of interest among hyperscalers? Do you have any feel for the magnitude, and how far ahead, I suppose, are these customers making plans and seeking to situate themselves within your service territory?
Bob Blue
executiveSure, David — demand is still extremely strong. I'd say there's really been no shift at all compared with what we discussed during the previous call. Within our service territory, we're sharply focused on what you might call conventional cloud and inference needs coming from data centers, and their enthusiasm hasn't slackened one bit. The way I'd describe the timing is this: just as has been true ever since we began serving data center customers more than 10 years ago — which gives us more experience with those customers than anyone else in the industry — they want to move quickly. Moving quickly is always what they want. That's how their business works. It has always been how their business works, and we've served them well. So far, I see no reason that will be different going forward.
David Arcaro
analystYeah, understood. And at this stage, I suppose they're mapping these things out considerably past 2030 as well — at least when you look at the megawatts they intend to build and how those expansions will roll out across time?
Bob Blue
executiveYes, of course. I mean, simply considering what they would be increasing toward based on what they've already pledged gets you to that point in time.
David Arcaro
analystYeah, definitely. And then on a different note, I was just wondering — has there been any movement or additional visibility when it comes to Millstone and the possible contracting chances there?
Bob Blue
executiveSo, regarding Millstone, there's nothing new to share, just like we said during the prepared remarks. In Rhode Island, there has been some legislative movement. There's definitely interest there. When it comes to any step we might take concerning Millstone, we don't have an update on timing. The existing agreement covering 55% of the output, as you're aware, runs through August of 2029. We'll keep working on it, but there's nothing to report today.
David Arcaro
analystAll right, sounds good. Really appreciate it.
Carly Davenport
analystHi there, good morning, and thank you for fielding our questions. Perhaps a brief item regarding that biennial filing you mentioned earlier — the special rate design put forward for customers with high energy use. Could you describe that design a bit, and, drawing on what you've heard from data center clients across time concerning what an agreement would include, do you think it captures what customers are willing to accept when it comes to how long the term runs and certain other details?
Bob Blue
executiveYeah. You're talking about the 14-year contract term?
Carly Davenport
analystYep, correct.
Bob Blue
executiveRight. Broadly speaking, what this filing creates is a new rate classification for customers — be it measured or contracted demand — at or above 25 megawatts, provided their load factor, whether actual or anticipated, is at least 75%. That covers about 139 customers, and roughly 131 of them are data centers. The core of this class is minimum demand charges. Whichever figure is greater — contracted usage or actual usage — the minimum demand charge lands at 80% for transmission and distribution and 60% for generation; for new entrants, that holds throughout the 14-year contract. There's a four-year ramp schedule leading into it. The point here is simply to give transparency and clarity regarding those customers, making sure the thinking around their paying a fair share is addressed and that the risks of stranded assets get reduced; a lot of that was already covered by provisions we had, but this strengthens them. We've held discussions with the data center customers. We spoke with them while putting this proposed new tariff together. I'm certain more conversations will happen as the case proceeds. I believe I can say with confidence that they grasp what we're trying to achieve here, and those discussions have been quite constructive. Great. Appreciate that color. I'd like to add a brief point related to what was asked before, regarding the discussions you're having with data center clients. Has there been any shift in how they sound or in their level of worry tied to the wider economic unpredictability we've been witnessing, and possibly any delay in certain new projects you anticipate will proceed? The brief response is no. Demand for more data center capacity within the area we serve remains strong.
Carly Davenport
analystGreat. Thank you for the time.
Anthony Crowdell
analystHey, good morning, team. Just two quick questions. One, I think slide 20, residential sales, look soft this first quarter. Just want to know if you could provide some clarity around that, and then I have a follow-up.
Steven Ridge
executiveHi Anthony, Steve here. So on the whole, our LTM Q1 revenue has performed quite well for us. It's running a bit above what we projected for the year, mostly because of really robust sales in the commercial segment, which covers data centers along with other commercial customers. We're not expecting that mild softness in residential to persist through the remainder of the year; we'll keep a close eye on it. All in all, I'd say we're genuinely pleased with where sales are headed; we'll share more details on that as additional quarters go by. Broadly speaking, the sales outlook across our service territories still appears very strong.
Anthony Crowdell
analystOkay, I'd like to build on what Carly asked about the biennial review, especially regarding the proposal for a new tariff aimed at large load customers. You folks have obviously been through several of these biennial reviews. Does adding a new tariff make getting approval potentially harder, or given all the discussions you had before submitting the filing and the conversations with the parties, could that actually be making it easier, helping get the tariff approved?
Bob Blue
executiveMy take is that labeling it as either an aid or an added obstacle would be tough to defend. Attention to rate classes and the way costs get shifted between those classes is a feature of rate cases stretching back to their earliest days. That it shows up here strikes me as unsurprising. What I would say is that this doesn't truly change how resolvable this case is, whether in one direction or another.
Anthony Crowdell
analystGreat. Thanks for taking my questions.
Steven Ridge
executiveThanks, Anthony.
Durgesh Chopra
analystHey there, good morning to all of you. I'm grateful that you took the time for me; and I'm keeping Ryan's family in my prayers too. Learning about what happened is genuinely devastating. Very briefly, Steve, our EPS for the first quarter of 2025 came in much stronger than we'd been expecting. You mentioned that the guidance contained enough conservatism. I'm simply attempting to figure out how Q1 earnings did versus the projection you had internally for the rest of the year.
Steven Ridge
executiveYes. Yes; excellent question. What I'd say is that it landed only a bit ahead of our forecast. To be clear, the $0.03 tied to weather wasn't something we'd included. We also hadn't built in $0.02 from sales that exceeded our forecast, which connects somewhat to what Anthony asked about the overall sales growth trend. I'd point folks to schedule four, which lays out a reconciliation of growth quarter over quarter. Let me spend a moment walking through the primary drivers. During Q1 2024, we were at $0.55. Of course, that came before the full business review wrapped up, though a lot of it wasn't impacted. Relative to that period, we've picked up roughly $0.08 in favorable weather since then. I mentioned $0.03 that was above normal. On top of that, our weather results in Q1 2024 were much worse than usual; the schedule captures that. I raised sales earlier. We're roughly $0.04 ahead there; about $0.05 of benefit this quarter came from rate cases that became effective later in 2024, so they couldn't have appeared in the first quarter. Looking at it net, we received around $0.08 from regulatory rider investment growth. I specify net since the gross amount shows up as $0.16, but half of that growth was sold through the non-controlling interest on CVOW to Stone Peak. Therefore the net benefit is $0.08; we also saw roughly $0.08 of relief on interest expense; that largely comes from debt repayment, basically the entire effect of paying down debt using proceeds from most of the business review asset sales. There's about $0.06 of tax benefit relative to the same quarter last year. Two cents of that is tied to the production tax credit from our nuclear sales. That's entirely timing. Another two cents came from RNG 45Z, which we didn't have a year ago. The last two cents came from a small South Carolina tax matter. A court case got resolved in a manner we hadn't ultimately budgeted for. That gave a little bit of unexpected benefit as well. When you add everything up, it comes to approximately negative $0.01 of miscellaneous items. Again, I'd say weather and sales landed somewhat ahead of our expectations. We've gotten some timing benefits on tax and O&M that I expect will balance out across the rest of the year. Right now we're reaffirming our original guidance range, targeting that $3.40 midpoint. If we reach a point later where a revision looks justified, we'll go ahead and make it. So here we are, still early in the year, and things have kicked off nicely for us. Our focus is locked on hitting those numbers. Should 2025 turn out strong enough to let us take some risk off the table for future years, we'd be open to doing that too. There's also that negative $0.01 from miscellaneous items. As the year unfolds, we'll share more specifics, but honestly, we're feeling great about this plan.
Durgesh Chopra
analystThank you, Steve. That was really comprehensive. It seems like things came in slightly better than what you'd anticipated. Okay then. Diane, you'll be missed on the field trip, Diane. Best of luck to you.
Diane Leopold
executiveThank you. I'll be missing it as well.
Steven Ridge
executiveAppreciate the chance to talk.
Jeremy Tonet
analystHello there, and good morning.
Steven Ridge
executiveGood morning to you, Jeremy.
Jeremy Tonet
analystAnd Diane, I want to say the same thing as the people who spoke ahead of me. I hope things go great for you in your retirement.
Diane Leopold
executiveI appreciate that, Jeremy.
Jeremy Tonet
analystPerhaps to kick things off, could you share any news regarding what to expect as PJM wraps up its network cost upgrades? I'm just curious whether tariffs or broader inflation could push costs higher.
Bob Blue
executiveYes; regarding those PJM network upgrades — that's the one you mean, right? Yeah. I don't anticipate that happening. Beyond what we shared on the prior call, we have nothing new. Like we mentioned at that time, our information had improved compared with earlier, though it wasn't flawless; that remains the case today; the final figure will arrive in July, and we definitely don't anticipate movement either upward or downward at the scale of the change seen previously; July will bring more clarity.
Jeremy Tonet
analystUnderstood. I appreciate that. A major topic of interest in the market has been transferability — specifically, if it were repealed, how would that affect plans? Could you offer any perspective on that?
Steven Ridge
executiveSure. Jeremy, I don't want to go overboard with my answer, but I'll provide a bit of detail. Across our plan, from 2025 to 2029, we have roughly $175 million in transferred tax credits annually on average. The PTCs from our portion of the offshore wind project are what truly push us toward transferability. I suppose the bright side is that, should transferability change, tax equity becomes a fairly efficient substitute for the time value of those credits. We're feeling quite confident about our position. If a change did occur, I believe we'd have a strong countermeasure, though it's also something we're monitoring closely.
Jeremy Tonet
analystUnderstood. Thanks a lot. If I may, one final question — it's about the ATM and the idea of addressing 2026 equity requirements, potentially sooner, in 2025.
Steven Ridge
executiveYes. During 2025, we've taken an aggressive stance with our financing plan so that raising capital is largely off the table. The financing plan makes that clear. Getting ahead of things at a fairly appealing price was the thinking behind the ATM. Though we won't offer specific guidance, this is definitely something we'd keep considering — seeking chances to de-risk future financing. For example, that might mean entering the market for an ATM settled at the close of 2026. That's an option we have, and acting sooner rather than later appeals to us. It's good. Yes, we hear your point. As the market justifies, we'll make those moves opportunistically.
Jeremy Tonet
analystUnderstood. I appreciate that. I'll stop here.
Steven Ridge
executiveThank you.
Bob Blue
executiveI appreciate all of you spending part of your day with us on this call, and I hope the remainder of your day goes well.
Operator
operatorThat brings today's call to an end. We appreciate you joining the presentation, and you're free to hang up at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Dominion Energy, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Dominion Energy, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Dominion Energy, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.