executiveThanks very much, Operator. Good afternoon, all — we appreciate you being with us today, and welcome to Energy Vault's Second Quarter 2026 Financial Results Call. You can find our earnings release along with the investor presentation in the Investor Relations portion of our website, and we'll be referencing that presentation during today's call. Before getting started, I'd like to remind everyone that this discussion includes forward-looking statements, which carry risk and uncertainties. Actual results could differ materially from what those statements express or imply. For a discussion of the factors that might cause actual results to differ, please see our most recent SEC filings and the safe harbor language included in today's earnings materials. Except as required by law, we assume no obligation to update these statements. We'll also be covering certain non-GAAP financial measures. Reconciliations to the most directly comparable GAAP measures appear in our earnings materials. On a personal note, this marks my first earnings call as Energy Vault's Chief Financial Officer. The mix of our differentiated power infrastructure platform, a contracted asset base that keeps growing, strong execution, and a disciplined approach to capital adds up to a compelling opportunity for building long-term shareholder value. I'm thrilled to be joining the team at this important inflection point in Energy Vault's journey. With me today is Robert Piconi, our Chairman and Chief Executive Officer. Robert will walk us through the strategic and operational update, and after that I'll take you through the quarter, liquidity, backlog, and our increased full-year guidance. Robert, over to you.
Rob Piconi
executiveThanks, Nitin. And I want to extend a warm welcome to everybody on this Q2 earnings call. Also, to a friend, Nitin — it's a pleasure to have you with us. We're all really thrilled. Nitin came on board only last month, and we're excited about what he'll bring and about this crucial stage in the growth trajectory of our company. So, welcome, Nitin. I'd also like to remind all of you that an investor deck has been posted on the investor website. I think it would help those of you following along if you'd like to track things that way. In the time we have left, I want to walk through a handful of those charts, and then Nitin will come back on to cover the results. I'm hoping all of you have had an opportunity to look over the earnings release we put out, and since I think the numbers speak for themselves, let me flag two key things up front. The first is how we're carrying out our strategy — for anyone who has been following the company, that means showing up for our customers, and you can see it in our revenue. You can see it in revenue that's profitable along with gross margins, and you can see it in how good and how available the power solutions we provide are. Additionally, I think it demonstrates our commercial follow-through and our ability to seize the demand being generated by AI compute infrastructure. That's a topic we've talked about in strategic terms. Looking at the last 6 to 12 months, the focus has been on placing our company — with our deep expertise and our strong capacity to deliver alongside customers — not just in the U.S. but globally, as we've demonstrated. We're thrilled to see this beginning to show up in the current quarter's results, and, as we'll cover in our raised outlook, in both this year and the next. What we've been putting into place is now showing up clearly in the figures we just released. You can see it in faster expansion, better margins, more cash coming in, a much bigger backlog, and — this matters — far clearer sight lines on both the revenue we'll book soon and the recurring profit we'll earn over the long haul. Turning to Chart 3, the deck's opening page, I want to flag three key points before walking through any of the numbers. Number one: our view for '26 and '27 has gotten notably stronger. That shows in the backlog, which climbed roughly $650 million, landing at about $2 billion. We're looking at a solid 40% gain from one quarter to the next alone, and when you compare it to a year ago, that figure has more than doubled. Beyond that, our expectation is that over the coming 12 to 18 months, roughly 40% of that backlog will convert into revenue at appealing margins. With this, we gain considerably more and better visibility into the delivery ramp that lies ahead — spanning, I'd say, both this year and the very strong Q4 we're set to deliver, much like we did a year ago, and also when we consider 2027. Next, we're turning demand for AI data centers and high compute platforms into actual signed contracts. We brought up the Crusoe win roughly half a year back, when we were first moving into the module data center arena. On top of that, we put out news not long ago about a 1.25 gigawatt deal — the biggest contract this company has ever signed — backing an integrated power generation plus storage solution for hyperscale data centers. Those combined moves have handed us far better visibility into the delivery ramp sitting in front of us today. Number three, we've bolstered our capital formation and project financing strengths. The company noted Nitin's hiring as our incoming CFO, coming over from BlackRock, where he'd built a solid career spanning energy infrastructure among other sectors. I also brought up Cory Magnuson taking the President of Asset Vault role in Q2. Every one of these moves layers in deep capital markets, structured finance, IPP, and project finance know-how right at the moment when the size of the opportunity is speeding up. That's significant, since the coming growth phase isn't merely about landing additional projects. It's about funding the correct projects efficiently, safeguarding our returns, getting those assets online in a predictable way and at the quality levels we've achieved so far, and turning that execution into cash flow along with long-term shareholder value. Go to Chart 4, and we'll get into a few of the figures at a high level — Nitin will walk through them more thoroughly shortly. Take a look at the figures we cite right away regarding megawatt count. Back in May, the last time we were together, we talked about the 1.1 gigawatt across the prior three months. That matters since those gigawatts sit under our control. A portion are operating, a portion are under construction, and a portion have now reached a ready-to-build state. Those 1.1 gigawatts are in the process of converting — I'll display the chart along with several others here that address the timelines for their coming online — yet the result will be $180 million in recurring annualized EBITDA, something that has sat at the heart of our strategy for the last two years. Even more significant, take a look to your right at the backlog, and we'll go into greater depth, with a few charts here where we'll actually set out what makes up that backlog, separating long-term recurring from the nearer-term chances we have to convert revenue. That figure has reached $2 billion now, a sizable sequential increase, and as you can see, it has doubled compared with a year ago, providing us with considerable visibility. When it comes to revenue, our top line has grown twofold versus the prior year. Again, that reflects strong execution against the backlog we assembled last year across projects in both the U.S. and Australia. One of the most striking results, in my view, when we reviewed Q2 was our gross margin. Gross margin really matters since that's the money, the cash coming off revenue, that lets you cover operating expense down the road. And we've made it better both quarter over quarter and year over year, with adjusted gross profit reaching 38.6%. The reason we focus on adjusted gross profit is that it represents the cash gross profit, which leaves out certain non-cash depreciation items tied to our build, own, and operate portfolio. Yet even GAAP gross profit climbed to 31% in this quarter. Once more, simply a solid outcome. What it tells you is that we're performing well. We're performing well out in the field, steering clear of problems that can arise when you're constructing big energy projects, and doing so with high quality and high safety. And I believe in the end, this needs to appear in cash and grow our cash. Let me walk you through what we've accomplished over the past six quarters. So this marks our sixth consecutive quarter of rising cash.
Rob Piconi
executiveI believe this really shows how focused and disciplined the company is about strengthening that cash position and improving the balance sheet, since we have plenty of appealing investments we want to put money into. Quarter over quarter, it rose 26%, and compared with the same period a year earlier, it was up over 150%. Let me now move to the backlog. On Charts 5 and 6, we've added a bit more detail so people can get a sense of not just what the backlog looks like today, but also how it will shape up by year-end. On Chart 6 as well, we've split that backlog apart and labeled it as either build-and-transfer or build and operate. Slide 6 strikes me as especially significant, since it lays out a fuller breakdown showing that 40% of the backlog consists of build-and-transfer work, which drives revenue conversion and cash generation sooner, whereas roughly 60% comes from the build, own, and operate piece, which generates recurring revenue and earnings visibility over the long haul. At $2 billion right now, that's about 3x what it was at the close of 2024. What matters more, though, is that mix, with around 60% linked to long-term recurring revenue from assets we own and operate, and 40% — a share that has risen since the prior quarter — backing near-term project delivery and revenue conversion across the coming 12 to 18 months. I'd call that precisely the outcome we were after. As we carry out this shift by building and transferring some assets while running others under the build, own, and operate approach, we inevitably sacrifice revenue along the way. That's precisely where we hoped to see solid conversion in our build-and-transfer business, so that revenue and cash growth keep building throughout that process. And that is precisely what we are delivering and demonstrating to you today. Combined, these give us an earnings model that is far better balanced, far more predictable, and in the end, far more valuable. A moment on Chart 6, since it's brand new. What you're seeing is our build-and-transfer breakdown in megawatt hours; these are storage projects, which we describe in megawatt hours rather than megawatts. On the revenue side there, the total within that backlog comes to roughly $700 million out of the $2 billion backlog. More specifically, we're also showing advanced contract negotiation, which accounts for approximately another $0.5 billion that we anticipate executing and closing on. Then, looking at revenue for both this year and on into 2027, we have about $1.2 billion in total underway, so that's very exciting. It reflects some of the growth we're capturing as our commercial teams execute. Also, another point I want to highlight there — over on the right side, what you're seeing are the gross margins tied to that revenue. As was shown in the earnings release, and we'll get into this further shortly, we're pushing our gross margin up, taking it toward the top of that range. Once again, strong demand is what's behind this, plus speed — that's why you hear the phrase speed to power. When you can move fast in this kind of market, and do so with a high likelihood of solid, predictable execution, what you get isn't just contracts won — you also gain the capacity to fuel that expansion and, in fact, profitable expansion, given our margin profile. The second element on this chart, Page 6, is the build, own, and operate segment, which we've broken out separately; that accounts for the remaining $1.3 billion of backlog. These revenue streams will run anywhere from 7 to 15 years. It's a big chunk of the backlog, and you want that to expand and to keep expanding. It gives us a great deal of forward visibility. And keep in mind, these streams carry gross margins anywhere from 70% to 80%; so as we construct these projects and they start operating, we've referenced $180 million in annualized streams, purely EBITDA, that will come from this — which I consider essential to our execution and to our longer-term approach of owning and operating energy infrastructure. We'll keep refreshing this chart to provide that visibility, both on the near-term revenue from build-and-transfer and as we deliver on build, own, and operate. Moving to Chart 7, as I believe you saw in the headline of our earnings release, we're boosting and lifting our guidance ranges, beginning with revenue, which we're raising from the $225 million to $300 million up to the top end and even beyond the high end of that range — $270 million to $310 million. Same as last year, when we executed in Q4 on a very large scale, surpassing $150 million in last year's Q4, we're set for another big ramp this year. That supply chain is locked in. It covers batteries. It covers some of the other high voltage equipment, spurred by some of the recent contract announcements. Then expect that margin range as well — you can see there we're raising it to the higher end and pushing that range up to 20% to 25%. As I think you just witnessed in the Q2 results I went through, we keep executing well. Those figures, I'd say — and when you take a look at our Q2, they stand for more than 2x the market when it comes to carrying out EPC contracts right across the board; and when you take a look at any of the other players in this space who are carrying out that work, that range makes us feel quite good, as does our capacity to keep delivering toward the upper end of it. Then, very significantly, when it comes to cash, we're restating but tightening toward the upper portion of the guidance. So we are raising the guidance on cash there, to $160 million to $200 million. And these contracts bringing revenue in the near term are going to help a great deal with that. We keep handling that effectively. And I believe the arrival of Nitin and Cory, with the project financing as well as the wider capital formation know-how and connections they contribute, is going to keep our balance sheet in a healthy state and growing. If you turn to Chart 8 in the deck, we are showing revenue here along with how it has grown across the past three years, but also showing that backlog growth; and we are presenting what we anticipate as backlog growth, even with a portion of the revenue recognition we expect in Q4 that is going to come close to $3 billion. And once more, that figure is not something we treat casually.
Rob Piconi
executiveThere are plenty of contracts in progress right now that leave us feeling very assured — and investors ought to feel the same way. Part of that relates to near-term revenue we'll recognize, but even more significant is our expectation that a growing share of that backlog will come from recurring revenue within our build, own, and operate portfolio. Let me move everyone to Chart 11, since I'd like to take a bit of time on our powered land portfolio. We've laid out a summary of some powered land projects we already have. Among those in progress is our Calistoga Resiliency Center — the 2-day, 48-hour backup serving the City of Calistoga, Napa. It backs Pacific Gas and Electric. There's a 10.5-year contract in place with them. That initiative is progressing according to plan, and its purpose is to safeguard the city in case wildfires or similar incidents cause the grid to fail. Moving to the right side, we have an update regarding Snyder and our AI campus. Just 2 months ago, we announced breaking ground with our Crusoe project. That refers to the module data center initiative. It starts at 8 megawatts and scales up to 25 megawatts for the initial deployment, and we're very enthusiastic; we also disclosed intentions to grow that site up to as much as 500 megawatts; achieving this will require a combination of generation, renewables, along with storage as we develop our new AI campus at that location. This is a facility we fully own, and it's something we're enthusiastic about because it can serve as a showcase site as well, since multiple storage technologies are already up and running there. When it comes to Mesa del Sol and the campus we have in New Mexico, we raised the topic of this powered land opportunity. In the earlier deck, we actually gave it an entire page, and that's where we got to the 75 megawatt milestone, which is the next one on the list. So that's what we'll use to start our update. I'm on track to get that going during our first quarter in New Mexico. We're planning significant growth because we hold ownership rights to the land surrounding it. We noted we'd picked up 225 megawatts of gas generation and reciprocating engine capability as well, and would eventually pair that with storage and solar, reaching up to 1 gigawatt across that area; we hold several sites in and around there that we're moving forward, and we're in numerous conversations with hyperscaler off-takers, with announcements anticipated in the months ahead as we reach the back half of the year. So we're enthusiastic about these bigger opportunities. They generate revenue streams of 15 years or more. We're putting money into the proper infrastructure and assets for them. And as the 1.25 gigawatt announcement of power generation plus storage combined — sited behind-the-meter — has shown, it works well enough, and I believe we're advancing our know-how and our execution in this space very, very quickly. On page 12, there's a chart we also presented for the first time during the last call, and it breaks down the specifics of the projects behind that $180 million in annualized recurring EBITDA. These are the 1.1 gigawatts of projects, and basically all of them are running within the same schedules we laid out previously. The first pair on the left are already up and running for 2025. They came online. Calistoga and Cross Trails are the ones I just mentioned, and we're hoping to have additional details on Sosa for you within the next several months. The Crusoe rollout has already been covered, and beyond that we have a number of other projects on the list, some in Australia and some in Japan, where we disclosed the acquisition that has now closed. Closer on the horizon, there are two efforts in particular — the 350 megawatts — and you should look for further updates on those over the next few months. Then there's the powered land project we have going in New Mexico. Everything lines up with our earlier report, as far as I can tell, and the team's strong execution has kept us on schedule through the many planning and construction phases, plus a great deal of the financing activity that's in progress right now. Page 13 also offers a detailed, year-by-year breakdown showing when we expect those megawatts to come online. The figures are annualized. To read this chart, you look at how many megawatts and gigawatts we're adding and the EBITDA tied to each, which is annualized at the moment those units begin operating. That's what this illustration shows. There's a year-by-year roadmap we've laid out for what we anticipate delivering — somewhere in the neighborhood of just under 5 gigawatts come 2030, alongside annualized EBITDA approaching the $2 billion mark. As with other things, we'll continue giving investors fresh updates on this, and in my view it matters that people track the megawatt additions closely as we roll out announcements about new projects during the back half of this year. Then, to bring things to a close and before passing things to Nitin, we're going to go through a few of the priority areas shown on page 15 for the latter half of the year. The main one, and the thing that ranks as job #1 around here — as you've heard repeatedly — is that everything starts with execution. Regarding the latter six months of the year, we've outlined further top-line expansion plus potential gains on both revenue and margin that we intend to achieve. This will be delivered the same way we've always operated—with strict discipline and real enthusiasm when it comes to taking care of our customers. On top of that, we actually see room for improvement beyond certain forecasts we currently have in front of us, which we anticipate finalizing over the months ahead, and we'll provide further detail when we share more updates in November. One more thing worth keeping an eye on is turning that owned-and-operated project backlog into megawatts we actually control. There are several additional projects we intend to add onto that 1.1 gigawatt; I believe this is essential if we're going to keep building and carrying out our strategy of creating recurring annualized EBITDA streams. Third, as you noticed in the announcement and in what we're doing with the sizable behind-the-meter modular generation and storage platform we told you about — once again, this transaction was entirely driven by speed to power. Having recently closed it brings in substantial revenue across both the second half and especially Q4 of this year, and also for 2027, as we stated. Based on the demand we're observing, especially considering certain wait lists and the lines you need to supply power to, our goal is to expand this platform and this partnership throughout numerous U.S. regions. So by way of this behind-the-meter approach, we believe we can get customers connected to power much more quickly. Number four, we are working toward additional optimization of the company's capital structure and, put simply, reducing our total cost of capital. That involves not only making the balance sheet stronger, but also building our own in-house team as well as a self-financing team instead of shelling out considerable fees and expenses to advisors from outside; this connects directly to several of the leadership announcements we've made during the past three months.
Rob Piconi
executiveAnd then last, when we take a worldwide view, further footprint growth is something you should anticipate across those important expanding markets. So our attention has stayed squarely on just the biggest, and what I'd call the most appealing, storage markets, having just brought in that acquisition in Japan, while pushing further in Australia will matter, and here at home in the U.S., carrying on with building and growing because of the enormous demand we're seeing for AI compute infrastructure. Having said that, I'll hand things back to Nitin so he can walk through several specifics of our financial results.
Nitin Dahiya
executiveThanks, Robert. I'll go over the financial results for the second quarter, then liquidity and capital discipline, then backlog, and finally our revised outlook for the full year. Second quarter revenue came in at $17.4 million, versus $8.5 million in the same period last year — that's a 104% increase, and it was driven by advancement on our projects in Australia. GAAP gross profit reached $5.4 million, up from $2.5 million a year earlier, which works out to a 116% increase. GAAP gross margin landed at 31%, an improvement of 140 basis points. Adjusted gross margin — the figure that strips out depreciation and amortization tied to projects we own and operate — rose by nearly 900 basis points compared to a year ago. This gross margin result matters, since it shows the expansion we're delivering isn't just about higher volume. Margins were exceptionally strong this quarter, and the mix of projects along with continued execution keeps supporting solid economics as we scale. Adjusted operating expenses totaled $23.7 million, against $16.2 million in the prior year. That rise mainly reflects commercial support, project development, and legal costs related to growing the owned and operated and AI infrastructure platforms; over the coming 12 months, we anticipate realizing the benefit of this elevated OpEx through contract activity. Given that, we stay committed to controlling the OpEx we can manage while still investing in growth where it makes sense. On a GAAP basis, net loss for the quarter was $29.7 million, down from $34.9 million in the same period last year; GAAP EPS showed a loss of $0.17, versus $0.22 a year ago. Adjusted net loss came to $24.6 million, compared with $18.4 million last year. Moving to adjusted EBITDA, we posted a loss of $17 million, versus a loss of $13.6 million in the prior year period, as higher operating expenses were partially offset by greater gross profit. Now to liquidity. As of June 30th, total cash and cash equivalents, restricted cash included, stood at $148 million. That's roughly $31 million more than the previous quarter and $90 million above the prior year. I want to stress that we keep our attention on maintaining sufficient liquidity as the business expands. With the company shifting toward a bigger owned and operated portfolio, keeping parent-level liquidity adequate and fine-tuning the capital structure of each project are essential to delivering shareholder value. Our plan is to rely heavily on project-level financings, tax equity among them, and to deploy corporate capital only where it's suitable, with clear return thresholds and disciplined allocation. Such discipline matters even more as our opportunity set grows; we aim to expand in a manner that directs capital toward projects offering stronger risk-adjusted economics for the parent, all while keeping the capital stack resilient. Backlog, as we've mentioned before, stood at roughly $2 billion as of August 10th, which is more than double what it was a year earlier. Owned and operated projects account for about 60%, with third-party projects making up 40%. This growth in third-party backlog significantly enhances near-term visibility through '26 and '27. Also, when it comes to the owned and operated segment, it builds up a larger foundation of contracted revenue that lasts longer once those assets begin commercial operation. And, as we mentioned before, the extra information on Slide 6 ought to help you understand more clearly how each of these pieces is anticipated to shape the company's future earnings mix. Turning to guidance, we're raising our full year 2026 revenue outlook to $270 million to $310 million, up from an earlier range of $225 million to $300 million. This guidance increase is a result of stronger commercial execution and better visibility into contract timelines. That being said — sorry — having said that, revenue recognition by quarter can be uneven due to project timing and milestone accounting. So on that point, I'd note that a very large portion of second half revenue is anticipated to be recognized during the fourth quarter. We're tightening our full year GAAP gross margin range to 20% to 25%, compared with 15% to 25%. And for year-end cash, we're now aiming for $160 million to $200 million, versus $150 million to $200 million before. Taken together, the higher revenue outlook, adjusted gross margin, and solid liquidity show the platform's expanding financial capacity as we keep growing the owned asset portfolio. Looking ahead to the second half, our priorities are simple. Execute the backlog, keep margin discipline, make sure liquidity is sufficient, and put capital to work where returns are highest. With that, I'll turn the call back to Robert for some closing remarks ahead of Q&A.
Rob Piconi
executiveExcellent. Thanks so much. Once more, I'd like to express gratitude to everybody — especially the people who work here — for the dedication and the way they carried things out while we turned in yet another robust, highly impressive quarter. To me, that's a terrific sign of what's ahead, and when we think about the back half of the year, Nitin already touched on a few of those main areas of emphasis, and what you should keep expecting from this team is intense dedication to the people we serve, plus an equally intense dedication to pursuing solely those growth chances that are biggest and most appealing. We brought up a major achievement, a historic moment for this organization, when we signed the biggest deal we've ever had, worth slightly more than $0.5 billion. Naturally, we're fond of those kinds of partnerships, and not merely because of how large they are, but because of the potential to deepen them as time passes. That explains why, on the whole, we've stayed extremely picky about which customers we take on; we don't reach too broadly toward essentially every buyer — instead we concentrate on those who can become partners we develop considerable confidence with, starting with early engagements, then growing together afterward. And you should keep hearing that same message from us throughout this year. Also, I'm especially upbeat about what this is producing for the coming year, given the backlog we've now built up, and above all, how much of that backlog falls within the upcoming 12 to 18 months, which I believe places us in an extremely powerful spot when we think about 2027. I should note that during our next earnings call in November, we'll share additional detail on our outlook for 2027 and what to anticipate at that point. With that said, operator, I'll hand things back to you so we can begin the Q&A.
Justin Clare
analystI'd like to begin with the 1.25 gigawatt hyperscaler agreement, and I'm curious how we ought to view that $500 million to $600 million of revenue regarding how it breaks out across 2026 and 2027, if you're able to share. Also, I'm wondering whether the margin profile you expect there lines up with the 20% to 25% you guided to for 2026. And you also mentioned the projects in advanced discussion. So yes, if you could speak to what margins might look like there.
Rob Piconi
executiveSure. Yes, glad to, Justin. On the breakout, you can figure that some portion of that $500 million to $600 million lands in our Q4. That's a deal we announced recently that had been in the works, so for three to four months; so we can deliver part of that in Q4; and obviously, I think you can assume it won't be most of it, but some portion will be there. And the bulk of that revenue, I'd say, comes in 2027. When it comes to margins, we feel really good, which is why we raised to the upper end of the range, of the 20% to 25%. You saw the results we just reported that started with a 3. I think we feel very confident about not just the range we just provided, but, to your question, about having that persist within the range we laid out into 2027.
Justin Clare
analystUnderstood. Alright, that helps. Now, regarding that same 1.25 gigawatt deal, you called it a platform that can be repeated. So I'm curious whether you could discuss, past that first deployment, what the pipeline of opportunities looks like? Perhaps which storage applications are starting to appear, and where demand seems strongest. Also, I'd like to know whether talks have expanded past that first hyperscaler, or whether right now you're mainly concentrating on just that single customer?
Rob Piconi
executiveCertainly. There are several things to address there. Broadly speaking, as we stated, what we've built is a modular platform, and it involves a partner whose name we're keeping confidential at this point, though it is a major EPC in power generation; the release noted that this initial chunk, the 1.25 gigawatt, ties to Caterpillar gas generation. More broadly though, this is a platform, and getting it deployed comes down entirely to speed to power; these platforms sit behind-the-meter, which means grid power isn't something we depend on for them. We install these, and the plan is to install them as 250 megawatt modular solutions. So the math toward 1.25 is something you can work out. Beyond that, we see a substantial opportunity to take this platform — with this partner as well as independently in the market — and grow it. You've heard the phrase speed to power. I've used it before; there's a great deal of opportunity where, across the coming 12, 24, 36 months, as grid investments get made, as transmission lines must be constructed, as all those capacity upgrades are currently being carried out, those efforts will require three, four, to five years. Thus, since we've now built a platform combining energy storage, gas generation and, notably, I should highlight how strong our software is and the role it plays, because that software handles load optimization and coordinates delivery of that power at five nines quality. That matters a lot, as you're aware, considering what customers expect. And that's something we intend to — answering the latter half of your question — that's something we can grow and roll out; we're quite enthusiastic about it. And as you'd expect, given the announcement we've made and some of the planning work completed, especially when we consider next year and the customers we currently have, we see considerable room to deploy this solution.
Julien Dumoulin-Smith
analystThis is Leonard, filling in for Julien. Nice work once more on those strong results. So the existing 1.1 gigawatt portfolio supports the approximately $180 million in annualized EBITDA. Yet when you bring on additional projects and possibly expand that backlog from about $2 billion at present toward $3 billion, which area do you see generating the greatest added value? For instance, conventional BESS assets, powered land projects, or AI infrastructure deployments? Over the coming several years, where do you anticipate the biggest portion of EBITDA growth occurring, along with backlog expansion?
Rob Piconi
executiveYeah, look, I would say our approach hasn't shifted when it comes to building, owning, and operating assets over time; we believe, and continue to believe, and hold the conviction that this represents the optimal deployment of our capital for creating longer-term recurring revenue streams. I think the segments we're examining to produce the greatest profit from that will be heavily tied now to our powered land solutions and what we refer to as our powered shell, or the module data center solutions. Those we will own and operate. We also have delivery models involving supplying sets of batteries. We refer to it as our ESaaS model for battery delivery, through which we can own and operate those batteries as part of firming up grid power or firming up other forms of generation for customers. So it's quite an intriguing segment where I think owning and operating those megawatts over time, we believe, will deliver the longest-term value for shareholders. And no change, of course, to — take for instance the 1.25 gigawatt platform we recently announced. I mean, that's actually RevRec, so that's build-and-transfer. And I think that might have been somewhat of a surprise that we were growing our backlog and also now enlarging, shall we say, the backlog's size with additional near-term deliveries and build-and-transfer. But that's just how this market works, because we've established a very strong reputation for high-quality delivery and grid knowledge. We see considerable demand from customers who want to integrate various kinds of technologies and draw on our expertise, as we've accomplished that across multiple regions, multiple technologies, and under different business models; and the final point I'll leave you with is that we are being extremely selective about the projects we accept and the customers we accept. We prefer to concentrate, as I mentioned, on larger customers, ones that share our culture, share our way of working and our emphasis on high quality, our emphasis on the longer-term path to sustainability that remains, I think, front and center for us here. And we're being very selective about the most appealing projects in terms of where we allocate our capital.
Noel Parks
analystA few items. First, looking across what you own, what would you point to as the busiest site right now for construction or installation?
Rob Piconi
executiveOh, there are likely several, I'd say. One is in Sosa, Australia, where we're doing build-out work and operating under a build, own, operate model; another is Stoney Creek, which we've already announced, and early construction work is happening there. On the build-and-transfer front in Australia, though, our inaugural project — also among the biggest in that country — is with a customer named ACEN. At that site we're putting in a 200 megawatt battery project, and 200 megawatts of power is already being delivered from that facility. Right now we're completing the turnover and what Australians call the R2 — the R2 being the point at which the grid has formally signed off. That's a key milestone for us, since once we have it, we'll be able to compete for bigger projects in that market. So as I said, that one is still quite active on the construction side. Turning to the U.S. alone, you can picture the ramp coming in this year's second half. Check our guidance alongside current revenue, and you'll notice we expect another $250 million to $270 million in revenue during the second half. That covers certain sites where deliveries and installations are being wrapped up. Consumers Energy is an example, from earlier projects. Beyond that, work tied to what we recently announced has been proceeding for the past three to five months — this 1.25 gigawatt deal — and part of that revenue and related deliveries fall in this year; also, in Snyder, Texas, as we announced, construction has begun on civil activities plus considerable high voltage upgrades and coordination with the local utility at Snyder for the module data center work with Crusoe; so those three regions, I'd say, are the busiest for us worldwide at present.
Noel Parks
analystThanks, that's great. You brought up that for the 1.25 gigawatt project, you've been involved with it for — you said three, four, five months. I suppose what I'm wondering is whether that project, which presumably had a fair amount of lead time behind it, has been moving forward under an original plan for a behind-the-meter installation, or whether it's the kind of situation where they began development, then recognized how severe the grid constraints were, how hard interconnects are, and at some point along the way chose to shift course toward something that incorporates energy storage too.
Rob Piconi
executiveYes, a few thoughts on that. This is a group — the partner we're teamed up with ranks among the bigger distributors as well as EPC firms in the U.S., one that deploys, as an example and as we announced, Caterpillar gas generation, and beyond that does a great deal of balance of plant design and final integration. So as you'd expect, they serve many customers, and in particular a handful of really big ones. My sense is that historically, even though they might have engaged different players, you can take it that this is a relationship we've been cultivating. It always begins with an initial, shall we say smaller project, where each side gets acquainted, gets a feel for the other's company culture; when you're finalizing contracts, drafting deals, and dealing with attorneys, you build a sense of one another. That relationship simply expanded to the point where they became quite comfortable teaming with us and with their hyperscaler partner on a very large solution. And on that one, I must say our software was extremely important to the decision, along with some of the differentiation it makes possible — namely the ability to integrate across and with our power plant controller plus our other load optimization and orchestration capabilities. The fact that we can accomplish that not just on the gas generation side, but also with our storage, and truly matter a great deal in guaranteeing delivery of five nines power and what we referred to in the announcement as always on availability for the customer. So that relationship, clearly, you don't simply sign one of these overnight. So you can take it that it was at some development stage, beginning at smaller scale and then culminating in — as we announced, we announced this was a second of a framework agreement — so something we plan not only to execute well here this year, but as we move into next year, and as I said in the earlier question, we do expect to expand this solution and expand alongside this partner, given the enormous demand in the market.
Sid Rajeev
analystNice work on the momentum. Since you've got several projects running at once, I'm curious where things stand on funding for a few of the ones coming up soon, such as Sosa, Stoney Creek, and similar ones.
Rob Piconi
executiveSure. Looking at it through the lens of financing, and you named a pair of build, own, and operate efforts that are active, those are two of the projects on our list, one being Stoney Creek in Australia and the other being Sosa. So for those — the project financing on each of them is very much moving forward. And just as we've included them on the list and as we've gone as far as securing certain equipment to safe harbor it for Sosa, for instance, within the U.S., we had already picked up a portion of the high voltage equipment; therefore those financing pushes are each in motion and each moving ahead, shall we say, consistent with what we'd expect, since both sites we chose are appealing sites. I'll point to Stoney Creek, where we secured the LTESA in Australia. That stands for the long-term energy service agreement, which is a 14-year arrangement with the New South Wales government. So that's a sovereign offtake agreement that basically gives us a floor annually, tied to how the project performs; and we're likewise in certain final phases for extra financing on that project too.
Sid Rajeev
analystThanks. If I could, I'd like to ask one additional thing. In what way do Calistoga and Cross Trails perform? Though these are modest-sized installations, they give us a sense of how things are working. Are operations going without issues?
Rob Piconi
executiveEach is performing nicely. Availability for both sits comfortably higher than 99%. Regarding the CRC—meaning the Calistoga Resiliency Center—it functions as a backup setup. Some ancillary power and services do make use of it too, yet everything there is proceeding fine. And on the Cross Trails system, through this year so far, we're basically hitting 99.4% availability.
Tyler Bisset
analystTyler Bisset here, filling in for Brian. First off, could you talk about what the data center moratorium that recently happened in Texas might mean for your company, and also address when the 1.25 gigawatt announcement could potentially be recognized as revenue?
Rob Piconi
executiveAbsolutely. Yes. Basically, we factored that into everything as we planned, including all the guidance we just provided; so, if you examine the solution we announced — especially the power solution — take the behind-the-meter offering, for instance, which consists of parts that don't depend on the grid. So, from the standpoint of execution and what's under contract — with the second half of this year and into next year, it's entirely about execution — that's something we keep watching. I'd say that's a pattern in certain regions of the country, and that item, relative to what we just laid out, the backlog we've accumulated, and what we'll deliver this year and into next, would be, shall we say, already accounted for.
Tyler Bisset
analystThat's really useful. Then looking at Slide 10, it seems your powered land opportunity fell to roughly 1.5 gigawatts. I'm focused on 2030 and comparing that with the prior quarter; but it appears powered land dropped by around 1.5 gigawatts, from 1.8 gigawatts in the previous quarter. The BESS opportunity nearly doubled, reaching 3 gigawatts from what I believe was 1.9 gigawatts last quarter. Could you give us an update on the puts and takes behind those changes? My assumption is that the BESS opportunity increase largely comes from the acquired assets, but any extra detail would be useful.
Rob Piconi
executiveSure. Incidentally, that's an excellent question. The first thing I'd mention is that there's also a shift in mix between the powered shell and the powered land. And some of this — it's also a strong strategic question, because what we're witnessing is substantial opportunity at the edge of the grid and around the modular data center side. That's why we have this shift and the rise in powered shell as a balance against powered land. Now, when you examine that on an additive basis, we find it's the same and possibly greater opportunity overall in that area. And I believe there's a chance to move somewhat faster at points of interconnect that are smaller and lower in total megawatts, 50 to 100 megawatts, without needing 800 or 1 gigawatt or multi-gigawatt. A handful of those exist, but I think when you consider how the sites are being deployed, how demand is being driven, and the economics, these powered shell and modular data center sites are growing quite attractive and potentially even larger in volume. And once more, I'll repeat this. I think this is the fourth time on the call, this matter of speed to power. I think if you consider deploying in smaller segments with modular data centers and consider the effect on the communities, which is front and center. So if you can, I think, reduce some of the bigger impacts and deploy in smaller, more modular ways at multiple points of interconnect, it can be a more integrated and holistic solution and coexistence with many of the local communities where we're deploying. The other development there is the — on the battery side too that you mentioned regarding our battery standalone storage, but beyond that, we have many solutions evolving in which we provide owned batteries rather than turning them over, offering them as part of an integrated power generation and storage solution to firm, whether that's firming the grid, but also firming up some of the other gas generation. We're providing and now aiming to close here. You'll hear more about these opportunities of us providing owned battery solutions to complement other generation and grid. That is what is driving the growth you can observe in what we refer to as our standalone battery energy storage. Yet these aren't the standard, conventional IPP standalone storage developments—rather, they are ones delivered as an incorporated component of solutions, especially aimed at the neo cloud market segment. So we will discuss that a bit further and give somewhat more detail regarding how that mix is changing.
Tyler Bisset
analystThanks for that. Let me slip in just one more question if I can. I appreciate the stronger cash position and the better outlook. My sense is that a good chunk of the improvement this quarter came from debt issuance, so I'm wondering how you're looking at your cash burn and other possible sources of cash coming in, like ITCs, for the rest of the year. Also, it appears you've only pulled down roughly $25 million of the preferred equity from OIC. That deal closed nearly 12 months ago, so I'm curious how you're thinking right now about putting that available capital to work and how we should expect that to play out over the next several quarters.
Rob Piconi
executiveSure. There are a few things to cover there. Regarding the ITCs, we closed one of them and it landed in the quarter last quarter. So we had three that were still outstanding. Two have been closed at this point. As for the third ITC that's left, it will come to about $15 million. We expect to close it within the next month at the latest, just the early part of September. So that will wrap up all the ITCs. The other part of your question concerns the cash and our — I think we had announced near the end of the quarter, because of what that backlog increase looked like. So we — I think we were quite transparent with the disclosure as well. We had the increase that you now see, which was $650 million in June. And since the character of that increase called for deliveries during this second half of the year, Q4 included, which is among the reasons we've raised guidance, okay? Because of that, we did draw on an AR facility. That's a facility we've kept in place for more than a year to handle all of the — basically some of the deposits we need to pay into the supply base so we can make sure deliveries happen into this fourth quarter; and all of that, just running the math and looking at the equation there, gives us the ability to deliver higher revenue and therefore the bump in our revenue range for this year; so this is all normal in terms of how we constructed our working capital and operating model for the business and what's, I think, really important about that is these things are all standard when it comes to debt facilities that you know we will draw from time to time and then repay on schedules using our cash. And that's also why I'll point to the increase in the activity, if you notice, we did narrow to the high end of our cash slightly for this year because of what the turn in the cash accretion of the deal we announced looks like, the 1.25 gigawatt that we're going to begin deliveries on in Q4. So I'd say there's nothing out of the ordinary when it comes to managing working capital, and that's why you've watched us lift our guidance on revenue, on gross margin, and even where cash is concerned for the close of the year.
Rob Piconi
executiveAll right. Operator, thanks. To wrap up: first, we're clearly in the kind of position we want to be in, since we're now executing against a really big jump in backlog. Our team was built for this, is executing well, and is delivering at the higher end and against expectations. We're sharply focused not just on this year's second half, but also on a great deal of commercial work. You'd have seen that in the results, and in terms of that growth and the backlog coming through, working through a lot of specifics, negotiating customer contracts, signing them, and thereby getting those items moving so we can start executing. I look forward to what the rise in backlog will mean for our 2027 too. As we move into the back half of the year and into that planning work, I think there's a lot of market activity. I'll say again that we're being quite selective about not only the region we target — we're highly focused on just the regions we've called out, and aren't planning any wider kinds of geographic expansion; we're in the right markets, in the fastest-growing markets, and there's simply so much activity, demanding a lot of, I think, innovation and speed to power, and you'll keep hearing that theme. And I think our capacity to deliver both creatively and with some of the innovation around our software across multiple solution sets — that's storage, that's generation — and to do so predictably for our customers is leading them to pick us for their growth needs. Lastly, as I said just before the Q&A period, once more, thank you to our employees, who've stayed very focused, vigilant, and passionate about delivering for our customers and about building the culture we create at the company; we've announced a few senior hires in reference, in terms of building the talent base to deliver on some of the results you've just seen, but especially some of the outlook we have. I'll keep thanking them for their focus and execution here as a company. And with that, operator, we'll close the call. I'll hand it back to you.
Operator
operatorThanks for joining us; that brings today's call to a close. You're free to hang up now. We appreciate you being with us, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Energy Vault Holdings, Inc. transcript — plus 131,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Energy Vault Holdings, Inc. earnings transcripts and 131,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Energy Vault Holdings, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.