Ferrovial N.V. (FER) Earnings Call Transcript & Summary

July 28, 2022

Bolsa de Madrid ES Industrials Construction and Engineering earnings 75 min

Earnings Call Speaker Segments

Silvia Ruiz

executive
#1

Good afternoon, everyone. Silvia Ruiz here, and I'd like to welcome all of you to the Ferrovial conference call where we'll be discussing the financial results for the H1 of 2022. As a quick reminder, you can find both the results report and the presentation on our website. Just like in earlier results periods, even though the main mobility restrictions have now been lifted, we want to point out that the financial information contained in our report continues to be affected by the COVID-19 outbreak. Because of the uncertainty about how quickly and to what degree activity will fully resume, there is no way to predict what impact the health crisis will have on Ferrovial's group information and performance in 2022. On top of that, the uncertainty brought about by the Ukraine-Russia crisis is weighing on global markets. Ferrovial will keep monitoring trading conditions closely, along with any further signs of a broader economic impact. Joining me today are Ernesto López Mozo, our CFO, and the CFOs of the various business divisions. Should you have any questions, you can submit them via the forum included in the webcast. During the Q&A session at the end of this call, we will read out your questions along with who they are from. With that, I'll turn things over to Ernesto.

Silvia Ruiz

executive
#2

Ernesto, you have the floor.

Ernesto López-Mozo

executive
#3

Thank you, Silvia, and good morning, everyone. I'll begin with the highlights from this year's first six months: toll road traffic has been robust, posting solid growth, and revenue growth has been even stronger, especially across the U.S. assets and the managed lanes. At 407 ETR, we observed an ongoing rebound that is likewise encouraging. Turning to airports, we have witnessed a vigorous traffic recovery worldwide and within our own portfolio as well. On the construction side, active management has helped offset inflationary pressure. We have also been engaged in M&A transactions. The first is the financial close of the New Terminal One at JFK Airport. What stands out here is that, at a moment when few deals are moving forward, this transaction secured successful financing with substantial oversubscription. At Dar es Salaam International Airport, we likewise completed the 60% acquisition. The services divestment continues. I should remind you that this is essentially finished. That is, Amey and a small BLM business remain up for sale. Those processes are still underway. As for our cash position, we hold a solid net cash position of EUR 1.5 billion, excluding infrastructure projects. What I mean is that consumption during the quarter went into some interesting and, I would say, value-creating opportunities such as the I-66 equity injection, and also into shareholder remuneration that has been accelerated.

Ernesto López-Mozo

executive
#4

We've completed additional buybacks, and cash dividends have also been paid. Regarding construction, cash has come in from U.S. construction projects as expected. From an ESG standpoint, I mean, we stay fully committed to disclosing all the different KPIs in full. We probably track more things than other companies in the sector do, I mean, particularly the water footprint and impact. Of course, we track our achievements when it comes to CO2 reduction. I mean, the most important thing is probably not being in the indices and awards, but also that the company is progressing to deliver infrastructure that is needed and in the most sustainable way, be it with design and also with traffic models that avoid traffic jams and congestion. Also at airports with a focus led by Heathrow when it comes to sustainable aviation fuel. If we move on to the next slide to begin reviewing how the different businesses performed, we start with toll roads, where we see strong growth in U.S. assets, as I mentioned in the introduction. I mean, the road division is growing more than 30% in revenues and EBITDA compared with last year, with solid EBITDA margins.

Ernesto López-Mozo

executive
#5

Specifically in the U.S., our revenue growth is running near 50%, and EBITDA growth is a bit above that level. During the first six months of this year, we received dividends from the managed lanes NTE and LBJ. On the subject of new investments, as I noted when discussing value creation, the I-66 in the introduction — we're eager to open that road. I should probably remind people, or perhaps some didn't even know how this road is configured. What I mean is that we're converting the existing three general purpose lanes into two plus two — that is, two general purpose lanes and two managed lanes, correct? The balance, I believe, is probably more interesting than on other roads when it comes to added capacity. As for the NTE 35, where Segment 3C is likewise progressing very quickly — I mean, we're speeding up production. Now, naturally, these works are impacting traffic, because we're currently linking the additional managed lanes to the existing ones in the final portion of construction. This creates traffic jams, and some traffic is now attempting to steer clear of that hassle. That hassle will be temporary, and we're eager to open another fantastic asset.

Ernesto López-Mozo

executive
#6

Turning now to the 407 ETR, growth compared with 2021 came in above 50%. Revenue per trip was also higher than in the first half of 2021, supported by a longer average trip length. On the financial side, the 407 carries substantial liquidity: over CAD 450 million in cash and equivalents, plus CAD 800 million of undrawn credit facilities. No meaningful debt maturities lie ahead. Given the performance we're witnessing and that liquidity, seeing extra dividends over the remaining months of the year would be natural. A CAD 200 million dividend was already approved at the July board meeting. As I mentioned, this performance and the strong financial position ought to permit some additional dividends during this year. Moving to the following slide, we get somewhat more detail on how traffic at the 407 has evolved. You can see it has been gradually approaching the 2019 levels. Naturally, the June figure was likely flattered by calendar effects — 2022 had 2 more work days than 2019. That explains why we presented this -16%.

Ernesto López-Mozo

executive
#7

Either way, every bit of this gain has been achieved while a substantial number of staff are still based at home. On the chart at the right of the slide, you can see how modest the office return has been. 27% really is fairly low. And we have to keep in mind that right now this is voluntary. When you poll various employers across the region, and likely worldwide, they lean toward having people in the office for good interaction. Working from home, honestly, is somewhat more of a perk. Employees, naturally, sit at the opposite end of that spectrum, though it will take quite a while before we know where things land. From a productivity standpoint, and a culture standpoint too, employers clearly would rather see more presence in the office. As I mentioned, at this point it is voluntary. All right, let's turn to the following slide. We like to regularly remind investors about the prospects of the regions where we operate, since the long-term performance of the asset also rests on growth in those areas and on the need to use the infrastructure, correct? Looking at the various news about the GTA, the expectations for real GDP growth and employment for 2022 are available and stronger than in other parts of the world.

Ernesto López-Mozo

executive
#8

Specifically with the 407, industrial real estate is an extremely tight market, and it continues to expand. As additional companies set up operations near the 407 and we witness more facility sprawl, this asset will deliver stronger results down the road, correct? It's worth reminding everyone of the long-term value drivers. Moving to the following slide, we can go over traffic and performance for the managed lanes in Dallas-Fort Worth. We observe here that traffic was quite strong this quarter relative to Q1 of the year. Naturally, the earlier portion of the quarter was stronger. Right now it's somewhat softer when it comes to matching or exceeding 2019. I'd say consumer confidence across the whole of the U.S. is likely at quite low levels, so people are somewhat bracing for a slowdown. Regardless, we view the country as truly dynamic and likely to bounce back fast from. Any downturn that might hit the economy. On revenues and EBITDA performance, we can see there's healthy growth, considerably higher in revenues than in transactions or traffic.

Ernesto López-Mozo

executive
#9

Naturally, inflation has played a role here, since it permitted raising the soft cap by 7%. Beyond that, managing tariffs has opened the door to additional increases, which generate greater revenues. The heavier mix of vehicles also works in our favor, especially for the 35, where the growth from those assets has been very impressive. If we turn to the next slide, there's a chart showing traffic and revenues. You can see that revenues across all these assets—including the I-77, which I'll get to shortly—have grown substantially compared with both the onset of the pandemic and the period before it. Traffic in 3C shows something of a slowdown. To make sense of that, it's probably best to look at the snapshot on the prior slide, where the congestion on certain lanes is clearly visible, simply because we're now interacting with the connections on this road. So let's move to the following slide. As with Toronto, we again want to emphasize the growth potential of the area. Dallas really stands out in the U.S., and so do other cities in Texas.

Ernesto López-Mozo

executive
#10

It's likely fair to say the state has served as something of a magnet for growth investment, headquarters, and relocation. That situation is holding up well and we expect it to carry on. Population and employment have been expanding over an extended period. We point to certain signals from labor statistics or the Bureau of Economic Analysis that may help you grasp what is driving the long-term expansion here. Moving to the following slide, where I discuss the I-77, this corridor is expanding as well. The region is growing. Perhaps the strongest element of this slide is the snapshot showing one of the toll rates. Obviously, that sits below Dallas-Fort Worth. I'm not suggesting it could match Dallas-Fort Worth, but what I mean is there is certainly space for further growth here. As I mentioned, the area is growing too. Population is rising. Employment is increasing in the area. This asset is also delivering very solid performance. Now, if we turn to the airport space and examine Heathrow, well, everyone knows about the traffic recovery. I mean, passenger volumes hit a 26 million level. Heathrow also put out the investor report in which they projected more than 54 million passengers for the year.

Ernesto López-Mozo

executive
#11

Heathrow has been getting ready for this return, let's say, to full capacity, bringing security officers on board ahead of time. That began in November. By the end of July, it will have the same staffing level, or headcount, in security as it did in 2019, prior to the pandemic, correct? Naturally, I mean, the constraint now sits more with ground handling, and ground handling falls short of what the current traffic flows demand. That is why Heathrow, together with airlines, has settled on a cap of 100,000 departing passengers per day, versus a capacity of probably 120,000 during the pandemic. Everyone is working to try to deliver additional capacity. As I mentioned, Heathrow had given warning about this, and also about the cutbacks required to deliver it, okay? The priority stays serving consumers, keeping them flying and with their bags. I mean, by the end of September, the situation will probably be more complete. We need to watch how airlines restore their ground handling capacity. On regulation, I mean, I have to be quite blunt here. I mean, we are disappointed by the H7 final proposals from the CAA. We think they fail to reflect the risk profile. Heathrow will now submit changes to those proposals.

Ernesto López-Mozo

executive
#12

I mean, a few of those rest on assumptions that lacked evidence or were unsuitable regarding OpEx. I mean, one specific illustration is the OpEx required for the present circumstances. In addition, mistakes exist in financial modeling and in commercial revenue forecasting. I mean, certain revenues are projected to occur at times when the law does not permit them to occur, right? Such matters ought to be fixed and, naturally, the method for cost of equity should be reviewed along with a market-based approach. I mean, we ought to hope the CAA fixes mistakes. There is a major one that perhaps goes unnoticed. I mean, the CAA has recognized that the airport carried more risk than what was taken into account during earlier regulatory periods. They are proposing a mechanism for sharing traffic risk to avoid that. Okay, we prefer that sort of approach to the risk, the asset. And not, of course, that they arrive with an extra cut to the allowed return once you do the risk with the traffic risk-sharing mechanism. It is somewhat disheartening to observe that they do not compensate for past mistakes. You know, ultimately, what serves consumers' interest is to deliver all these terminals, Terminal five, Terminal two, the integrated baggage.

Ernesto López-Mozo

executive
#13

I mean, all of this requires very heavy investment, and you expect to get that investment back, right? It's pretty hard when the rules of the game change and those investments become unrecoverable. As I said, the proposals came in at the absolute low end of the range — the low part of it — and not near the middle, and with no RAB restatement, or regulatory asset base restatement, let's say. Ultimately, the asset has been depreciated without any usage. That's the same as writing it off. The airport ought to be given the chance — perhaps over a long period, it doesn't have to happen right away — to recover that investment. As I said, it's quite disappointing that the regulator has reached this point. Turning to the other airports, we can move on to Aberdeen, Glasgow, and Southampton. Here again, we're seeing a strong traffic recovery, and the COVID-19 impact was quite severe at the start of the year, but it has been recovering, and now it's in much better shape. If we look at the other assets, I mean, we completed the Dalaman acquisition, and there revenue is very close to 2019 levels. I mean, it's only 4% below, with traffic still 15% below in the H1 of 2019.

Ernesto López-Mozo

executive
#14

Retail and commercial income growth of 13% has powered this revenue result. On this asset, I should remind everyone that we consolidate it within the global consolidation. Moving to the next slide, we get to the New Terminal One. As I mentioned, this is a major project. I have not seen big projects of this kind reach financial close the way this one has. It is an asset that is genuinely required to provide capacity for international traffic at JFK. On this slide we give a bit more detail on the uses of funds required for phase A and then B1 and B2, which are expected to occur because, I mean, phase A is essentially achieved at levels comparable to pre-pandemic times, when there is travel demand that is not being served. We have these uses, and we also have the phase A funding detail, where you can see equity of EUR 2.3, and we have a construction bank facility of EUR 6.6. It is important to note that we do not anticipate equity injections for phase B; the operations alone will generate the cash flow to, I mean, cover those required funds. In terms of the phase indications, they have been quite successful, and we have investment grade confirmed by Moody's, Fitch, and Kroll.

Ernesto López-Mozo

executive
#15

On construction, things are already moving forward, correct? In the snapshot, we can see the green garage area that was shut down so prep work for demolition could begin. All right, we're looking forward to this project over the months and years ahead. Moving to construction, we've been actively managing inflation while keeping our focus on delivery. We truly have to deliver these infrastructure assets, these large projects. Ultimately, the margin comes out very similar. It's essentially the same as Q1, 0.8%. Here, the inflation effects on supplies are being addressed through various mitigating measures, correct? One of them, naturally, is that Poland and Spain have indexation or escalation formulas. That helps protect margins. From a cash flow standpoint, I mean, we're paying subcontractors or suppliers, but revenue arrives when the works are finalized, right? I mean, all these price review formulas, right? Margins today are reflecting this recovery, but cash is not, right? We aren't receiving that collection, which will come later. We also have claims, since COVID and price increases have caused disruptions and delays. Those are in process. Normally we don't recognize them unless the client has signed off. You get no benefit here from the accounting impact or from cash flow, right?

Ernesto López-Mozo

executive
#16

Once more, reaching that 0.8% without the margin benefit—and, naturally, the cash side—is impressive. On top of that, we were pushing more sales performance before the anticipated inflation spike and the broader uptick in U.S. construction, in chosen regions. That too is cushioning the inflation hit across these works. Naturally, in the recent EBITDA processes we build in inflation allowance, escalation and similar protections here. All right, as I mentioned, we're likely at a moment when both accounting and cash show the worst picture, and margins plus cash could improve from here onward. Naturally, through the rest of 2022, as we've stated for months, we anticipate the U.S. works will use cash. All right, moving to the following slide, where we go through the accounting results—we've essentially covered the operating numbers, and we can turn to the financial results. What I mean is, you observe a sizable betterment in financial expenses. Looking across the individual lines, results from infrastructure projects will carry more expense. This one concerns a specific asset we've addressed previously.

Ernesto López-Mozo

executive
#17

I mean, it's Autema, where our net worth is negative. In our accounting portfolio, it's essentially worth less. This particular item reflects the effect of an inflation derivative that isn't receiving hedge accounting treatment, correct? There's no impact on cash flow. At this point, in our equity assessment, it really has no impact on value either. As for the financial results from ex-infrastructure projects, you can see a substantial improvement there. That improvement comes from two sources. One of them is simply that interest expense is better. You get better remuneration on cash, and you have low cost on debt after repaying last year one of the older bonds in the portfolio. You have the benefit of pre-hedging from bond issues that did not take place. We're doing bank financing, and from an accounting standpoint, it has to be reflected. It's not hedge accounting, right? Ultimately, we're seeing better interest cost performance. Looking as well at the equity-accounted investees, we've turned the corner here, and we have a positive contribution, and therefore we end up with net income positive of EUR 50 million. If we move on to the next slide, this is where we see the evolution in the cash position, the net treasury position.

Ernesto López-Mozo

executive
#18

The figure has been declining, though there are solid explanations for that. We have shareholder remuneration above EUR 350 million, investments totaling EUR 230, and then working capital movement of EUR 248. Everyone should keep in mind that no factoring is being done at present. Our balance is essentially zero. From a financial cost standpoint, it simply doesn't make sense right now. Factoring is one more instrument available to us, but it isn't the most efficient option, correct? So none of these figures reflect any factoring benefit. Alright. That likely pertains to the net cash position. Moving forward, the clear takeaway from these results is that post-pandemic traffic recovery is underway. Macro uncertainties certainly exist, yet our assets have performed very strongly. They sit in growth regions where infrastructure is required. To put it plainly, they gain from inflation. It isn't just that a formula exists to pass it through. In many of them, you can exercise pricing power. In construction, the key to speeding up production delivery is infrastructure assets in today's environment is a challenge, though it has been handled very actively and margins have been preserved.

Ernesto López-Mozo

executive
#19

Like I mentioned during the discussion, this is likely the least flattering spot to be in, since margins and cash collections should both improve as we move ahead. Finally, we're eyeing appealing investment opportunities. Complex infrastructure projects in the U.S. are the top priority, and delivering those with a sustainable approach while demonstrating our capabilities there will be essential to succeeding down the road. Okay. Thank you very much for sticking with us, and we'll now open the floor to Q&A.

Silvia Ruiz

executive
#20

Thanks a lot, Ernesto. We'll be taking questions in just a moment, so please stay with us. Now let's open the Q&A. Our first set of questions is from Robert Grimes at Insight. First question: regarding tariffs for JFK Terminal one, the Ferrovial Airports CEO referred to a cost per enplaned passenger of $81 at Terminal four in its 144A issuance document. Is that a reasonable guide for what tariffs at Terminal one will be in 2026 at open?

Ignacio Castejón

executive
#21

Thanks, Robert, for that question. Ignacio Castejón here, from the Ferrovial Airports team. Regarding what you asked, naturally, every tariff or terminal at JFK serves as a benchmark for the NTO team. What I'd like to remind you of is this: the aim of the NTO project is to deliver a new facility offering best-in-class services for long-haul passengers. The appeal of this approach has been confirmed through agreements already signed with four airlines, which are committed to a specific tariff for the project. We are highly confident that we will be able to deliver the tariff we are expected to.

Silvia Ruiz

executive
#22

Robert Grimes has the next question: why was it that syndicated loans were used at the outset for New Terminal One at JFK rather than issuing Private Activity Bonds, the way the private consortium did at LaGuardia Terminal B? And is there any indication of what the loans' interest cost is?

Ignacio Castejón

executive
#23

Thanks, Robert. It's Ignacio Castejón here once more. So, the primary objectives behind drawing on bank facilities at that point were to capture the benefits of sidestepping a steep cost tied to the potential — perhaps in light of market volatility — new issue premiums arising from a fresh transaction, and likewise to steer clear of wider spreads when the financial close took place. That is the reason we tapped the flexibility offered by bank financing, so we could hold back and observe how the market evolved. As for your second question, that information is commercially sensitive, meaning I'm unable to address it right now. Thank you.

Silvia Ruiz

executive
#24

We have the next batch of questions from Luis Prieto at Kepler Cheuvreux. First up: you already posted a very strong revenue per transaction figure in managed lanes during Q1, but could you remind us of the main drivers behind that result in H1? Specifically, I'd like to hear your thoughts on how sensitive revenue per transaction is to a traffic slowdown should we enter a recession.

José María Velao

executive
#25

Thank you, Luis, for that question. José María Velao here from Cintra. When it comes to our Texas assets, during peak hours we're fairly near the soft cap, though there's still some headroom at midday and on weekends in the newer asset we acquired — that's NTE 35W. Still, it's worth highlighting that even under a soft cap scenario we have another mechanism for raising tolls, as I mentioned, such as the CPI escalation, which matters a great deal in the inflationary environment we're currently experiencing. As we know, the mandatory mode events represent a significant revenue inflow for the NTE. Across all our assets we're pursuing revenue optimizations, and we're working on those with the algorithm. We know our assets sit in Texas, in Dallas, and although we need to watch for the economy softening, we're operating in a very strong economy that's highly dynamic, as Ernesto noted in the presentation. We see a strong growth outlook, a solid population with high household income, and that will let us navigate any potential economic downturn better.

Silvia Ruiz

executive
#26

Luis Prieto has the next question. Could you give us a rough sense of how cost inflation is likely to affect the construction division across the full year? And in terms of the damage, what percentage do you think price escalation clauses could offset?

Ignacio Garcia-Bilbao

executive
#27

Thanks, Luis. Ignacio García here, Ferrovial Construction's CFO. What we can tell you is that the net impact we're seeing as of today, as you know, comes to roughly EUR 50 million. Naturally, during H2 of this year, we'll likely see an impact nearer that figure. That is, because of the contracts still sitting in the backlog, unless something shifts regarding protection of formulas, indexes, et cetera, right. You're also asking what percentage. Well, you know there remain plenty of uncertainties. We're aware that Poland has raised the cap — for road construction, from 5% to 10%. Right now they're thinking there could be a further increase for railways. And this will probably be extended to other administrations as well. In Spain, it's more or less the same. You know there are certain limitations. There are caps on the percentage that can be applied. There are also some — for instance, Comunidad de Madrid or Aena — that remain outside the indexation formulas. Energy is still out too. We construction companies keep fighting to get this cap raised, right.

Ignacio Garcia-Bilbao

executive
#28

I'm probably speaking in terms of net effects here, but the overall impact is twice the figure we've got. Regardless, even with inflation weighing in, we think the year-end margin — the EBIT margin — is going to come out positive.

Silvia Ruiz

executive
#29

Now we'll take questions from Augustin Cendre at Stifel. First one: the construction order book is down -4.1% year-on-year on a like-for-like basis. How did order intake move over the semester? Should we read that as a signal that activity is slowing?

Ignacio Garcia-Bilbao

executive
#30

Thanks, Augustin — Ignacio Garcia here once more. That information was included in the presentation we sent you: during July, we signed — or rather, we won — contracts worth EUR 1.8 billion. These are mainly in the geographies where we want to be: EUR one billion in Poland, EUR 400 million in Webber, and the remainder in Australia, namely Coffs Harbour. With that in mind, we shouldn't be seeing that decline in the backlog. The basic reason is that in Poland our income has risen because of the climate. As you know, we were close to signing certain contracts, but because of doubts over the indexation formulas they weren't signed, and that amounts to about PLN three billion. Now that those contracts incorporate these formulas with the new caps, we are beginning to sign. At this moment, we don't foresee a recession in contracting in the H2 of the year. Thank you.

Silvia Ruiz

executive
#31

Moving to the next question, from Augustin Cendre. What portion of the underperformance at Ferrovial Agroman stems from costs on the I-66 and I-285 contracts that haven't been provisioned? And as those projects near completion, should we anticipate a bigger negative effect on margins?

Ignacio Garcia-Bilbao

executive
#32

Thanks, Augustin. No — the reality is that these contracts are loss-making. What I mean is, every loss on these contracts has already been booked in the profit and loss account. It's fair to say that not all of it was provision. What I mean is, we lost EUR 60 million in this half year, more or less. What I mean is, it's fair to say we had internal fees, and this comes down basically to two things. What I mean is, one is the inflation we have suffered. What I mean is, these are fixed-price contracts, and we suffered that inflation. Also, please keep in mind that because of COVID and all the supply chain delays, what I mean is, we are trying to complete the jobs on time, what I mean is, and with acceleration. Also sometimes, what I mean is, taking on changes proposed by the client that are still not agreed — this will come into claims. Given the prudent approach we have to claims, we are not recognizing it in the results. As I said, what I mean is, the whole impact is already covered in June. Thank you.

Silvia Ruiz

executive
#33

Moving on to Marco Weaver at JPMorgan with the next batch of questions. First one: June LBJ traffic came in at -13% and 407 ETR traffic at -16% compared with 2019 levels — setting aside the favorable calendar effect, are any positive recovery trends showing up in July? What's keeping these assets behind? And is there anything new on work-from-home patterns in those regions?

Gemma Girera

executive
#34

Thank you. Marco, thanks for the question. This is Gemma. I'll begin with the 407 ETR. Yes, traffic is at -16%. If you look at the graph in the presentation, congestion and mobility in the region have improved, and the 407's performance is quite good. This month has the best traffic performance we've seen since the pandemic started. We're in July. Traffic performance is consistent with overall mobility in the area, but as Ernesto noted in the presentation, we need to watch the economic softening. Over the long term, Toronto has strong economic indicators, such as GDP and population growth in the area containing the 407 ETR, which is positive given the asset's long duration — very positive. Turning back to LBJ traffic, we've identified two things about what's happening there. First, the area where the LBJ is located is more exposed to residents and companies able to work from home, so they have greater flexibility, and that's affecting traffic performance. The second impact comes from ongoing construction works on the I-635 East.

Gemma Girera

executive
#35

That is a major contributor to the LBJ. Those two ideas are what lie behind the lag.

Silvia Ruiz

executive
#36

Moving to the next question. You brought up inflation protection steps for construction work in Poland and Spain. Could you indicate how much of the contracts are indexed to inflation?

Ignacio Garcia-Bilbao

executive
#37

Yes. Thanks, Marco. As I believe I said earlier, in Spain and Poland this applies only to public-sector clients. In Spain, we could say roughly 50% of both our backlog and our revenues come from public clients. As I noted before, only Comunidad de Madrid and Aena remain outside that section, right? I mean, they'll probably join sooner or later, no? That 50% would be the percentage. In Poland's case, the share of public contracts is larger, with the distinction I drew. What I mean is that roads carry a higher cap than railways, but 60% could be the share of protection in public contracts. Thank you.

Silvia Ruiz

executive
#38

We'll take the next set of questions from Marcin Wojtal at Bank of America. Could you give us an update on the new managed lane opportunity in Atlanta? And when do you expect that project to be awarded?

José María Velao

executive
#39

Thanks for the question, Marcin. Chema here — Chema again. Yeah, that project is something we're actively working on. We're highly motivated about it, since it's the target we've set. Right now, during these weeks, we're handling the prequalification. Our expectation is that the bid process will come at the end of the year. Everything is going according to expectations.

Silvia Ruiz

executive
#40

Moving on to the next question. At what point might we anticipate the NTE 35W project making its first dividend distributions?

José María Velao

executive
#41

So, as you're aware, we're building Segment 3C right now, and until those construction works wrap up, we won't get any dividends for the 35W. The expectation is that we'll complete this construction on September 2023. Likely toward the end of the year, we'll see some dividend.

Silvia Ruiz

executive
#42

Regarding the final question from Marcin: could you comment on how the mandatory mode in Managed Lanes is affecting the financial results?

José María Velao

executive
#43

All right. As you’re aware, the mandatory mode—simply to maintain a solid standard of service on our highways—prompted us to raise the tariff despite the fact that we’re under a soft cap. The effect on revenues is fairly significant—but it’s fairly significant, you know, for one, this occurs only during specific time windows and on specific stretches of the highway. Broadly speaking, the effect isn’t that large, yet it’s comparatively meaningful for us, especially at our asset, the NTE, which is the asset currently going through this type of mandatory mode.

Silvia Ruiz

executive
#44

Now, some more questions from Stéphanie D'Ath at RBC. For 2023, 2024, and 2025, could you tell us when you'll share the key assumptions on traffic, revenue, and margin for the JFK investment?

Ignacio Castejón

executive
#45

Thanks a lot, Stephanie, for asking. Ignacio Castejón here, from Ferrovial Airports. Unfortunately, right now the only thing I can tell you, Stephanie, is that this information is still very confidential, so it is commercially sensitive. Thank you.

Silvia Ruiz

executive
#46

Next question — so you're confirming that you're walking away from the construction guidance you gave for 2024?

Ignacio Garcia-Bilbao

executive
#47

Yeah, thanks Stéphanie. Right, we can verify the 3.5% EBIT for 2024. Just keep in mind that the inflation effect sitting in our backlog right now is what's hitting our P&L today, and it's mainly going to hit us during 2022. As for new contracts, we're definitely factoring inflation in.

Silvia Ruiz

executive
#48

Are you anticipating that 407 ETR will return to where it stood before the pandemic by 2023?

José María Velao

executive
#49

Thank you. Thanks, Stéphanie, for asking that. Chema here again. We aren't giving any guidance on how our assets will perform going forward. As for pre-pandemic levels — getting back to where we were before the pandemic hinges, in this case, on how mobility and congestion move along the corridor. In the graph in the presentation you saw that when the alternative route gets more congested, 407 ETR becomes more appealing to users, and its market share goes up. That's why we are narrowing the gap over this last quarter. So we need to watch how the return to the office develops over the coming months, keeping in mind that at some point there should be a shift from voluntary to mandatory office presence. That could have a positive effect on congestion and on mobility, and on general mobility in the area. No, esta es la. Vamos a la ahora.

Silvia Ruiz

executive
#50

We'll take the next set of questions from Tobias Woerner at Stifel Europe. First up: regarding Schedule 22, what timeline would you expect for the force majeure to come to an end?

José María Velao

executive
#51

Thanks, Tobias. As you're aware, this initial big contract we secured is going to conclude by way of one of two scenarios. Scenario one: you raise the toll rate—sorry, the tariff—on any stretch of the highway. Scenario two: we reach a traffic volume matching the average of 2017 and 2019 traffic. We'll watch how the asset and the traffic perform over the next few months, and we'll see whether that occurs going forward.

Silvia Ruiz

executive
#52

Moving to the next question. At the half year, the net cash position of EUR 1.5 billion appears to sit toward the lower end. Could you remind us what the key contributors to this performance were, please? And should we expect the net cash position to rebound in the H2 of the year, in line with or above the one seen in the H2 2021?

José María Velao

executive
#53

Right.

Ernesto López-Mozo

executive
#54

Okay, thank you, Tobias, for that question. So really the explanation — the 1.5 — I can point to the slide I went through during the presentation, but I'd like to remind you that shareholder remuneration has been the main driver, meaning both dividends and buybacks, and investment as well. I mean, we're putting money into the I-66. I covered that asset, which we're looking forward to, and it's speeding up toward the year-end opening, and we're also stepping up the CapEx in the managed lanes, correct? In the presentation, you have the pending capital commitments there, right? That ties to the second part of the question. That's what we'd expect for the H2 of the year, right? On investment, we'll keep investing and remunerating shareholders, right? There's the piece of the cash outflow in construction in the U.S. that's tied to working capital unwinding in those projects, right? All of these pieces will stay in the second part of the year — remuneration, investment, and the cash outflow in construction in the U.S. On the positive side, I mean, we could get dividends from the infrastructure assets, in particular the 407 that we mentioned. We also might be looking at possibly other works being closed and receiving some advance payments to offset this.

Ernesto López-Mozo

executive
#55

The divestments we’re carrying out might bring in some extra money as well. I mean, we’ve said before that this year was the year for investing, and that probably drives some cash outflow while the underlying businesses continue growing and delivering dividends and more in the future. I mean, I wouldn’t guide to any specific number in the H2.

Silvia Ruiz

executive
#56

Now we have the next batch of questions, and these come from José Manuel Arroyo at Santander. What's the primary driver behind the 407 ETR's average trip distances running longer by +6.6%? Is it heavy vehicle traffic?

José María Velao

executive
#57

Thanks, José Manuel, for asking. Along the 407 we're noticing a quicker rise in long-distance journeys, particularly the ones leaving the 407 East, and that there's traffic following the tolls on 412 and 418. Broadly speaking, this is a trend — we're observing a growing share of long-distance vacationers or second-home users who drove more in 2022 than they did in 2021.

Silvia Ruiz

executive
#58

Moving to the next question, from Dallas-Fort Worth. Regarding the disruptions from building NTE 3C, when did those begin, and how long will they continue? Also, is that disruption the only thing holding back traffic on NTE 35W in June, or do other factors play a part?

José María Velao

executive
#59

Thanks once more, José Manuel. It all began in June, since that’s when we started diverting traffic, and that’s producing some bottlenecks on the northbound side at the exit from Segment 3B. As we’re seeing, the effect falls mainly on light vehicles. There’s an image in the presentation that shows quite clearly what’s going on at that northbound exit on Segment 3B. It began in June. We expect it all to wrap up once construction is finished. We’re doing all we can to minimize the impact. For us, finishing 3C is the priority. That’s a very important project for connectivity and for increasing the length of our highway. To answer your second question, that’s basically the impact. There’s no further impact, other than our needing to keep watching the economic softening.

Silvia Ruiz

executive
#60

Could you give us an update on how the Amey sale and the Chile mining divestment are progressing?

Ernesto López-Mozo

executive
#61

Appreciate the question, José Manuel. So, at Amey, we've got multiple bidders aiming to close the deal. The asset is doing really well, correct? We're making progress. Pensions, risk, and that kind of thing tend to be the usual discussion points. They're moving along nicely. Chile mining is slower because of macro and political factors. What I mean is, the country is voting on a constitution. Macro is uncertain, so that process is somewhat slower, but we're continuing with both.

Silvia Ruiz

executive
#62

Felipe Leite from CaixaBank BPI has the next question. Could you explain why working capital saw such a large outflow in Q2 of 2022, and what you expect for full year 2022?

Ernesto López-Mozo

executive
#63

Sure, thank you, Felipe, for that question. So it's really a mix of things — three, I'd say. Within construction, there are two. The first is the cash going out as we wrap up those large U.S. projects, I-66 and I-285 — those are significant ones. To a comparable extent, there's some working capital being consumed at Budimex. What I mean is Budimex could probably release part of that over a longer period, since they've completed substantial works that still need to be collected. As I mentioned, the primary factor is that working capital outflow in construction, but on top of that we also have some reversal of previously favorable working capital at Amey contributing to this. They've been carrying out contracts for the defense ministry, and the advanced payments are currently being unwound, correct? That has had an effect. As I said, the main item we'd describe as the more significant one is the cash flow outflow in the U.S., and for Budimex we'll have to wait and see at year-end.

Silvia Ruiz

executive
#64

Pablo Officieri from Aster Asset Management has the next question. He's asking whether, at this point, you have any plans to refinance the 2.124% hybrid bond — EUR 500 million in total — whose call date is February 14, 2023.

Ernesto López-Mozo

executive
#65

Yeah. Thanks, Pablo, for asking. Yes, I mean the hybrid does, I mean it serves a purpose within the company's capital structure, and the plan is to refinance it once conditions are favorable. At the moment the markets are distorted, so issuing a hybrid right now makes no sense. We're keeping an eye on that to see when a good opportunity might arise, but at present there's no point.

Silvia Ruiz

executive
#66

Our next question comes from Daniel Gandoy at JB Capital. Would you be able to give us an update as well on the equity commitments still pending for infrastructure projects during the second half of 2022?

Ernesto López-Mozo

executive
#67

Thanks, Daniel. I’ll handle this one. This is Ernesto. All right. We have a number of significant investments. On I-66, EUR 225 million is still outstanding. Other toll roads come to EUR 81 million. Then there are airports, with JFK at EUR 56 million and Dalaman at EUR 124 million. We are, I mean, at roughly EUR 485 to 86 million before making any investments in the second part of the year.

Silvia Ruiz

executive
#68

Augustin Cendre from Stifel has the next question. Regarding Dalaman International Airport, is the aeronautical revenue per passenger subject to regulation? What level is it at today, and how do you see it developing going forward, considering the Turkish lira's decline against the euro?

Ignacio Castejón

executive
#69

Thanks, Augustin. Ignacio Castejón here, from Ferrovial Airports. I just want to confirm that the tariffs — the aeronautical revenue per passenger — are set in euros under the concession agreement. The levels are EUR 15 for each international passenger and EUR 3 for each domestic passenger. Those are the levels as of today. Thank you.

Silvia Ruiz

executive
#70

Our next question comes from Nabiel Ahmed at Barclays. For the first one, what level of return to office do you think is required for traffic on 407 ETR to get back to where it was before the pandemic?

José María Velao

executive
#71

Alright. Mo, thanks for that question, Nabiel. As I mentioned earlier, the majority of businesses in Toronto are operating under voluntary hybrid arrangements, and that approach will stay in place at least through September. CEOs agree unanimously that being in the office matters for collaboration, engagement, and innovation, and staff members are getting a chance to recognize those benefits too. We'll be watching how the return-to-office situation develops over the next few months, given that eventually there will need to be a move from voluntary attendance to a mandatory office presence.

Silvia Ruiz

executive
#72

Moving on to the next question. Would you remind us when the NTE 3C works are scheduled and what benefits are expected once they're finished?

José María Velao

executive
#73

Sure, construction is progressing nicely, and we anticipate completion by September 2023. The upside is that we're boosting connectivity along the corridor — you know, in segment three and 3B. We're adding another 6.4 miles of managed lanes.

Silvia Ruiz

executive
#74

Moving to the next question. Could you walk us through the vehicle mix on I-77 versus the managed lanes in Dallas-Fort Worth? And what's the exposure there to commuting and heavies?

José María Velao

executive
#75

Right, we don’t give that kind of detailed breakdown for our assets. The sole detail I’m able to share is that roughly 40% of the business accounts—that’s all I can provide. A few managed lanes in Dallas have stronger exposure to heavies. Still, as we mentioned during the presentation, the 77 is doing quite well in both light traffic and heavy traffic.

Silvia Ruiz

executive
#76

Moving on to the next question. Would you be able to revisit the Ferrovial Construction losses for Q2? Are those provisions non-cash in nature? And what is your outlook on margins going forward?

Ignacio Garcia-Bilbao

executive
#77

Thanks, Nabiel. So Ferrovial Construction is essentially being hit by inflation, as I said — EUR 42 million of the EUR 50 million I mentioned. And also, I mean, the contracts in the US. But those US contracts — I-66 wraps up this year. I-285 is nearly done. I mean, it'll be completed next year, but they're approaching their end. The effect on cash outflows will be felt this year, and no provision is needed. I mean, the losses are already there and will be taken into the profit and loss account. Right? On inflation, one key point to note is that, even though compensation formulas exist, this gets covered at the end of the contracts. I mean, they'll be collected when the contract ends. You're suffering inflation today — even if in P&L the impact is smaller, you're still paying for that inflation right now. Unfortunately, it'll be collected or compensated at the end of the contract, and maybe not this year. That's also why you see our working capital destruction in construction in this half year. On margins, I said that in construction we expect to be positive by year-end, around the margins you're seeing now.

Ignacio Garcia-Bilbao

executive
#78

There isn’t any additional guidance we’re able to provide on that. Thank you.

Silvia Ruiz

executive
#79

We'll take our next question from Nicolas Mora at Morgan Stanley. Could you explain the reason client collections at 407 ETR came in so low relative to revenue during Q2 of 2022?

José María Velao

executive
#80

No, collection isn't an issue at all. What's going on is that collections lag by 1 month. You'll see June's collections show up the following month, in Q3, when measured against our revenues. That's the reason this figure looks so low right now.

Silvia Ruiz

executive
#81

Now we'll take the next round of questions, and they're from Robert Johnson at.

Ignacio Garcia-Bilbao

executive
#82

Just say hi.

Silvia Ruiz

executive
#83

Speaking from BNP Paribas Exane, my first question is this: in June, how far below the average level recorded in 2017 and 2019 was 407 ETR's peak hour traffic? Since the force majeure agreement covering 407 ETR stays in force until peak hour traffic gets back to those average levels from 2017 and 2019 — peak hour traffic, not total traffic — that metric matters a great deal for the pricing outlook. And does Ferrovial intend to disclose this metric going forward?

Ernesto López-Mozo

executive
#84

Yes. Appreciate the question, Robert. This is Ernesto. So, from what I understand — and we need to verify this — the force majeure agreement concerns average traffic rather than peak hour traffic, correct? That's the figure we need to compare against 2017 and 2019. Honestly, peak hour traffic is something that I'd describe as fluid. It shifts constantly, with varying patterns. We'll keep evaluating how those patterns may evolve and talk that through with you rather than just giving a metric right now that's likely already out of date. As patterns settle, we'll be discussing them going forward.

Silvia Ruiz

executive
#85

That brings us to the end of the question-and-answer session.

Ernesto López-Mozo

executive
#86

Okay, thanks everyone for joining this results conference call. If you're lucky enough to get some vacation time, please take it. We'll be seeing you before long. Bye.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ferrovial N.V. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ferrovial N.V. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ferrovial N.V. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.