Kathleen Quirk
executiveAppreciate it, and hello everybody on this morning's call, which is Freeport-McMoRan's conference for the second quarter. We're glad you could join. FCX put out its results before now, and you can find both the press release from today and the slides on our site, fcx.com. There's a live webcast of this call, and to tune in, simply visit the homepage of our website and select the webcast link for the conference call. Analysts and investors are on the line, and members of the financial press were also invited to listen in. A recording of the webcast will be posted to our website later on today. Before we get started, we want to remind everybody that the press release issued today, along with some of the remarks we'll make on this call, contain forward-looking statements, and things could turn out differently in a material way. Please take a look at the cautionary language in our press release and presentation materials, as well as the risk factors outlined in our SEC filings. Joining me on this call are Richard Adkerson, our Chairman and Chief Executive Officer; Mark Johnson, our Chief Operating Officer for Indonesia; Josh Olmsted, our Chief Operating Officer for the Americas; Mike Kendrick, who leads our molybdenum business; Rick Coleman, who leads our construction and growth projects; and Steve Higgins, our Chief Administrative Officer. I'll begin with a quick recap of the numbers, and after that Richard will take over to walk through the outlook using the slide deck you've all received. Following our prepared comments, we'll do the usual thing and take your questions. Earlier today, FCX announced second quarter 2021 net income attributable to common stock of $1.08 billion, which works out to $0.73 per share. That figure includes net charges of $56 million, or $0.04 per share, which are broken out on Page VII of the press release. Adjusted net income attributable to common stock came to $1.14 billion, or $0.77 per share. Adjusted EBITDA for the second quarter of 2021 was $2.7 billion. A reconciliation of the EBITDA figures we calculated is available on Page 35 in the slide deck materials. The second quarter was a strong one for us. We sold 929 million pounds of copper and 305,000 ounces of gold, which came in well above the same quarter last year, though compared with our recent estimates those sales were down roughly 5% for copper and 8% for gold, mostly because of when shipments out of Indonesia occurred. Our guidance for the year matches what we had previously projected. Strong pricing gave our second quarter results a boost. At $4.34 a pound, our average realized copper price for the second quarter stood 70% above the average from the year ago quarter. For the second quarter, our average net unit cash cost came to $1.48 per pound of copper. That was a bit higher than the $1.42 per pound we had projected entering the quarter, though the difference was mostly tied to nonrecurring charges stemming from a new 4-year labor agreement at Cerro Verde. Cash generated by operations was exceptionally strong this quarter, hitting $2.4 billion, a total that included $0.5 billion from working capital sources. On top of that, cash from operations far exceeded the $433 million in capital expenditures we made during the quarter. As of the end of June, our consolidated debt was $9.7 billion. Consolidated cash and cash equivalents also totaled $6.3 billion at the close of June. Net debt finished the quarter at $3.4 billion, meaning we hit our target net debt level a number of months earlier than planned. At this point I'd like to hand things over to Richard, and we will walk through the slide materials that everyone has been given. Please go ahead, Richard.
Richard Adkerson
executiveAlright, thank you all for being here. We're genuinely happy to share what has turned into a series of truly impressive operational results for our organization. And given this excellent favorable forecast for our enterprise, all of us feel quite excited about it. I hope each of you remains in good health throughout this pandemic. Vaccines offer a chance for us to safeguard ourselves along with those close to us, and we're putting in significant effort to motivate our employees worldwide to seize this chance fully whenever they can. Our crews are operating safely. We continue to be vigilant with the COVID measures that have proven so successful. Given the recent global uptick in infections, we're renewing our focus, intensifying our commitment, and bringing back certain measures we had relaxed in order to protect our workforce and communities. Our second-quarter outcomes show truly robust implementation of our strategies, along with very strong and advantageous pricing for what we sell. Kathleen brought up the shipping matter. Supply chain challenges exist worldwide. We managed to — essentially we hit or somewhat surpassed what we aimed to produce. Everything we made, we were able to transport. We would have surpassed our revenue goal. Additionally, as is typical in mining, we encountered some isolated problems impacting output. Absent those, and with the shipping situation, we'd have achieved a substantial exceedance of our earlier guidance. Crucially, the underground development at Grasberg is advancing right on timeline; this is an extraordinary and, I'd call it, a landmark achievement for our firm and for the mining sector as a whole. Our colleagues in Indonesia are performing extraordinary and exceptional work. This is creating worth for our investors and delivering lasting, sustainable, inexpensive benefits going forward. Output. We're turning a profit across the Americas. Copper pricing — output within the United States is climbing. Our Lone Star initiative in Eastern Arizona is genuinely thrilling. We have multiple continuing opportunities that add value in the U.S.; ahead of us. And I personally feel very optimistic regarding upcoming expansion in the U.S. The South American crews in Peru and Chile are handling the pandemic well. We're bringing back output that we had reduced 12 months ago; we've delivered these exceptional financial outcomes thanks to the diligent effort and the investments we've been committing over many years. We are currently producing considerable cash flow, which will remain viable for many years ahead; during this quarter by itself, we generated $2 billion in cash flow after capital expenditures. That is simply extraordinary given our position merely 12 months back. Kathleen pointed out, and it's worth noting, that we hit our debt goal a number of months sooner than what we had projected earlier this year. We closed out the quarter having $3.4 billion in net debt, and that falls inside the target range we established of $3 billion to $4 billion. Over the past twelve months, we've reduced our debt by about 60%. Today we're aligned with the financial policy that our Board established earlier this year and communicated to the market — one that changes where we allocate capital by increasing the cash we return to shareholders while still making disciplined investments to grow the business going forward. This policy lets us maintain a robust balance sheet with investment-grade credit metrics while continuing to fund rising shareholder returns and long-term investment in the company. On Slide 4, you'll see how we're devoting considerable focus and resources to sustainability. That's long been a core part of who we are as a company. We support ICMM's sustainability principles. We're in the process of getting all of our operations certified under The Copper Mark. That's a relatively new framework for the industry, put together by the International Copper Association, and its purpose is making sure production is responsible and aligns with UN sustainable development goals. At this point, we're ahead of everyone else in the industry, with 6 operations already certified. In Q2, we submitted 5 additional operating sites for the program, and we've made a commitment to have every one of our sites validated against this rigorous framework. Earning and maintaining trust depends heavily on responsible production, and that trust has come to us over the years through lasting partnerships with communities as we supply copper — a product society values — made safely, with care for the environment, and through innovation. Slide 5 is about electrification, and that's a big deal for copper. The metal is mostly used to produce and deliver power, and it's needed for just about everything involved in getting the world economy to low carbon. That includes EVs and the infrastructure that goes with them, plus clean power like wind and solar. Put simply, a green economy can't happen without copper. We're at the very beginning of this shift. Down the road, it will drive a lot more copper demand; and since Freeport is the biggest copper producer on the planet, we're in a strong spot to gain from that increased demand; on top of that, businesses everywhere are now answering COVID with forceful fiscal and monetary measures; that by itself is generating meaningful copper demand in the near term outside of China. And China's consumption is still robust. Economic indicators are giving off conflicting readings. Even with that, Chinese copper consumption remains robust. And at this point, as developed nations worldwide generate greater consumption through their economic recoveries—all while a key source of copper demand, the auto industry, is held back by the chip shortage—this incremental demand originating beyond China, which keeps growing in importance, along with the long-term expansion driven by emerging markets, is quite favorable for what we expect ahead. On top of that, copper use keeps widening thanks to technological progress in communications, artificial intelligence uses, greater connectivity via worldwide infrastructure programs, and attempts to boost health by employing copper against viruses and other infections. Slide 6 addresses that rising need, and the worldwide difficulty of simply keeping supply level—let alone expanding it—makes copper's future look compelling. Honestly, "compelling" undersells it. We are sincerely enthusiastic and thrilled about this. The dip in copper prices we've seen lately has not weakened our conviction at all, and it hasn't changed our positive longer-term outlook on copper either; we settled on this position years ago, and it reflects Freeport's strategy of focusing on copper because of its solid fundamentals, the nature of our assets, and our workforce. Short-term price sentiment can always be influenced by all sorts of moves at any moment. That said, beyond all of that, the facts are undeniable and they back a favorable fundamental picture for copper. Demand growth cannot be avoided. Keeping supply steady or expanding it comes with real difficulty. Major new copper investments will need our prices to sustain them. Growing demand plus tight supply signal a substantial structural shortfall ahead, which underpins significantly higher copper prices down the road. Our firm holds top-tier assets, unmatched industry expertise, and a deeply committed team, all of which will let us capture the upside from these fundamentals. The collection of assets within our copper operation is uncommon, perhaps even one of a kind, in this sector. Replicating these assets would be hard, maybe even unachievable. Thanks to robustly increasing output, built-in brownfield, low-risk expansion drawn from our extensive pipeline of undeveloped resources, our assets carry enormous worth in the current environment and will only gain more worth as these markets evolve — as market deficits show up going forward. Slide 7 underscores our expanding margins and cash flows. We've seen substantial volume increases over recent quarters, as all of you have noticed. That expansion is going to keep going.
Richard Adkerson
executiveWhen we look at 2021, on the copper side, we expect volumes to rise 20%, and gold volume to be up 55% compared with 2020. And as we turn to 2022, another increase of 15% to 20% over 2021 levels should come through. Much of the capital and execution risk tied to reaching those larger volumes now sits behind us. Thanks to modest incremental costs, our volumes will deliver expanding margins at copper prices between $4 and $5 per pound. Across '22 and '23, we've produced yearly EBITDA of $12 billion to $17 billion from copper, with capex running about $2.5 billion annually. Thinking about the past, execution risk around this underground development, political risk in Indonesia, and debt levels always created an overhang in our reporting. When you consider the last 3 years, every one of those major risks hanging over our company has been addressed and overcome, and this has been a genuinely thrilling and satisfying period for our company. On Slide 8, you can see the strong progress on the Grasberg underground ramp-up. I recently sat down with Mark Johnson and his team in Indonesia, and I congratulated them on the outstanding job they're doing even with COVID; during the second quarter, we hit just under 80% of our target annualized run rate for metal sales. Reaching full rates of metal production by year-end remains on track. What our Indonesia team has accomplished while handling the pandemic and a tough physical setting is simply outstanding. We put strong, carefully designed operating protocols in place. With cases rising again in Indonesia over recent weeks, we're assisting the government and our local community; we've brought in travel and other restrictions aimed at slowing the spread. Greater vaccine availability at our job site and across Indonesia gives us encouragement. Many of our workers — a significant number — have already gotten vaccines. Our aim is to offer vaccines to our entire workforce during the second half of the year, and we're backing nearby communities as they work to respond to COVID. Support from the government of Indonesia has been very strong, and our partnership with PT-FI state home shareholders on that shareholder mine is genuinely positive — everyone is collaborating and aligned. I've spent 30 years working in Freeport — more than 30 years; and our team's achievements make me personally proud and grateful, from when we started investing in the underground more than 20 years ago, to the transition away from the open pit that started 18 months ago, to handling COVID — what we've managed to do is simply remarkable. Planning and investment for this transition started in the 1990s. Experiencing this success now means something special to all of us at Freeport; we look ahead to ongoing long-term success at Grasberg by creating value in this world-class historic mining district through low-cost, high-volume and sustainable production. On slide 9, you can see the various ways we can pursue low-risk, brownfield growth throughout our worldwide portfolio. We're getting more and more excited about what's possible in the U.S., since we enjoy favorable community backing everywhere we operate there, a favorable tax environment, and many years of doing business responsibly; we're boosting output at Lone Star, Bagdad, and other mines. On top of that, we have promising new possibilities coming from advances in leaching technology that let us recover more from our legacy sites. Lone Star, our most recent mine, sits right next to our longtime operations in Southeast Arizona. Community support there is strong, and this new mine is exceeding its designed capacity. We're looking at expanding Lone Star's oxide ores; in fact, we're earning a great deal of money on what would typically be stripping work. We're doing long-range planning to develop what could be a world-class sulfide resource located under that oxide layer in our historic mining area; there's a chance — and a good probability — that we'll move ahead with building a new concentrator to double output at our Bagdad mine in Northwest Arizona. We anticipate kicking off that project next year. New leaching technology, which has me really enthusiastic, opens up major possibilities for additional growth throughout our global resource portfolio. We're assessing a compelling expansion opportunity at our El Abra mine in Chile, where CODELCO is our partner. That project would need considerable capital and a lengthy lead time, but it's both appealing and sizable. A major expansion at El Abra in the future seems probable, though not at this moment. We're putting off the investment decision on this project until the mining policy questions the Chilean government is currently weighing become clearer. We're also assessing the development of an underground deposit, Kucing Liar, in the Grasberg district run by PT-FI. This copper-gold resource would involve a large block cave mine drawing on the considerable infrastructure we already have in place. We bring expertise and a lengthy record of success. Mark Johnson and his team have developed revised plans that reduce how capital-intensive the project is. The economics look stronger. It's a big operation. It would be a block cave producing roughly 90,000 tonnes per day. So that's genuinely huge — 6 billion tonnes of copper resource, 6 million ounces of gold — and it aligns perfectly with our plans. We have further chances to put money into projects that support our copper — our carbon reduction, our sustainability goals, such as investing to build clean renewable energy for our operations and communities; we're moving forward with plans for an exciting ESG-type project to recover metals by recycling electronic devices at our Atlantic Copper processing facilities in Spain. The bottom line is that we'll stay disciplined when allocating capital to new investments. Our focus will be on value-added projects backed by long-life reserves. We've built a lengthy record of success in project development. We've secured our license to operate along with positive relationships and community support wherever we have chances to invest. On Slide 10, we return to Lone Star, demonstrating that we are hitting and surpassing our targets. The initial blueprint called for 75,000 tonnes per day and 200 million pounds of copper. We have now gone beyond that, achieving the intended throughput of 95,000 tonnes per day. When run continuously, our takeout capacity supports producing 285 million pounds of copper. We are examining another expansion requiring a fairly modest outlay for tank houses and mining equipment, which would deliver 300-or-more pounds of copper — a 50% increase over what we first designed. That said, the project horizon is farther out; Lone Star presents a significant chance to turn into a foundational asset for our business. The possible resource stands at 10x our present reserve. While extracting these oxide ores, we are opening the door to the potentially enormous sulfide resource sitting beneath. A long-term cornerstone asset for our company. Slide 11 addresses the reference I made before regarding reaching technology and recovering extra copper from material already extracted. We are moving this forward; numerous opportunities exist for deployment. It is a thrilling, potentially high-value prospect featuring low incremental cost and a low carbon footprint. We are involved in several studies, both internally and externally, applying a variety of technologies to unlock that value from current stockpiles.
Richard Adkerson
executiveWe now figure there are 38 billion pounds of copper sitting in those stockpiles; that's material which has already been extracted from the ground. And should we manage to get back merely 10% to 20% of that material, it would amount to something like a major new mine, with variable capital and operating costs. A big chunk of this sits within our flagship Morenci mine, North America's largest mine, where artificial intelligence and data analytics are currently being applied to help us grasp what is happening with these leaching performance opportunities. Years ago, our team was instrumental in unlocking substantial values with the new SXEW technology. Now our focus is on bringing this leaching technology up to the next level through modern approaches. We've put together a cross-functional team of technical experts, metallurgists, mine planners, data scientists, geologists, business analysts, all collaborating to seize the full advantage of this truly exciting opportunity. Slide 12; we hold strong operating franchises in the U.S., South America and Indonesia, having gained the trust and respect of our partners, our customers, suppliers, financial markets, and even more importantly, the workers, communities and host governments in the places where we operate. We possess considerable large-scale project development and operating expertise. Team Freeport has every capability needed to take on new projects in a responsible, efficient manner. On Slide 13, I want to wrap up by acknowledging the people of Freeport. Everywhere in the world, their commitment, dedication, resilience, positive outlook, cooperative spirit is simply gratifying. Our team feels passionately about the part we will play in achieving a better and more sustainable future for everyone. Team Freeport possesses the capabilities and drive to keep meeting, and exceeding, our own high level of expectations along with those of our stakeholders; we're living in a great — a time of great challenge and exceptional opportunity for our business. At our team, we're meeting the challenges, embracing the opportunities. Our future is bright; we at Freeport are charging ahead responsibly, reliably and relentlessly. Kathleen, I'll hand the call back to you to discuss our financial results.
Kathleen Quirk
executiveAll right, thanks Richard. I'll begin at Slide 15 with a few quick remarks about how our operations are doing, then walk through the financial results, after which we can take your questions. Richard described the strong headway being made at Lone Star; our current emphasis is on maintaining those rates so the tankhouse there stays full — it holds a capacity of 285 million pounds of copper each year — while we evaluate possible incremental additions past that through fairly modest, appealing investments. Richard likewise brought up what we have planned at Bagdad. Studies are moving forward to double capacity at that site, and we're hoping to be able to qualify a project and get one started there in the coming year. Over at Morenci, we've begun raising mining rates, which had been cut back over the last 12 months. During the second quarter we averaged roughly 725,000 tonnes per day of mined material, and we're building up toward 800,000 tonnes per day by the close of this year, then 900,000 tonnes a day in 2023. We've also pulled forward from 2022 the restart of a portion of Morenci milling capacity. That too had been idled last year as a cost-cutting step. With copper prices having improved, these moves yield more profitable output. We're also quite optimistic about the chance to add low-cost production at Morenci via our leach technology programs. Down in South America, the teams keep working to bring production back to prepandemic levels. Our goal remains a full restoration at Cerro Verde in 2022; and in recent months we've been operating at roughly 95% of mill capacity. As you saw in our press release, during the second quarter the Cerro Verde team secured a new 4-year labor agreement with a significant percentage of the workforce; that came ahead of our labor agreement exploration, which arrives at the end of August of this year. We're quite happy with the win-win result of that agreement and are now working to finalize a mutually satisfactory agreement with the remaining employees. At El Abra in Chile, we're well along the path to restoring production levels that were curtailed last year. We're raising the stacking rate of material on the leach pads and proceeding to add a new leach pad to handle the higher rates. This is capital that had always been part of our plan, but was deferred last year as part of the capital conservation plans that we rolled out in April of last year. This enables El Abra to lift production on a sustained basis to about 200 million to 250 million pounds per annum for the next several years while we assess opportunities for a major expansion there. As Richard discussed regarding Grasberg, we keep delivering results and producing strong cash flows. So, if you remember, we entered Q2 holding much more concentrate than is typical for us, due to robust output volumes combined with some maintenance downtime at our port and weather-related problems late in the quarter. Sales during the quarter came in under what we had projected earlier. This really amounts to a short-term timing matter, and we anticipate being able to reduce inventory levels during the back half of this year. At Grasberg, we brought the second crusher at our Grasberg Block Cave successfully into service during the quarter, and that gives us enough capacity to ramp up to 130,000 tonnes per day. You have observed the results and the records that the Grasberg Block Cave delivered during the quarter. We are also working to speed up installation of our third SAG mill at that location. That has formed part of our strategy to enable greater throughput rates. In addition, we have spotted a chance to put money into a new mill circuit that would let us boost copper and gold output in Indonesia by achieving better mill recoveries once the early stages of this project are underway, and the economics look extremely appealing. Our worldwide team likewise stays concentrated on cost control and efficiency initiatives aimed at extending equipment lifespans, enhancing energy efficiency and maintenance methods through technology adoption. We have seen a certain amount of cost escalation this year, mostly driven by higher energy prices and, to a smaller degree, the effect on consumables from rising steel prices, greater freight expenses and sulfuric acid costs. We have had — partly counterbalancing those items, we have enjoyed the advantages of a weaker exchange rate in South America relative to the U.S. dollar. The cost increases have been counterbalanced by a substantial rise in molybdenum prices over recent months, and those have given us a very good hedge against some of these cost inflation items. We discussed on the slide, and you have seen in the release, our plans for — to fulfill our commitments in Indonesia regarding the new smelter. On Slide 16, we give an update on our plans to satisfy the commitment we reached with the Indonesian government in 2018 to build 2 million tonnes per year of in-country processing capacity for copper concentrate. We have been pushing forward with talks with our Japanese partners about expanding the current smelter at PT Smelting; that would satisfy part of the obligation. And there are multiple financial and operational advantages to enlarging this facility, which has been expanded quite efficiently in the past. After weighing different alternatives for the remainder of the commitment, we have determined that the strongest long-term choice is to proceed with our plans to build a new greenfield smelter in East Java close to the current facilities at PT Smelting. We recently signed an EPC contract with Chiyoda to build a 1.7 million tonne facility at that site; and we are now concentrating on finishing the project as efficiently and as promptly as we can; we show in the graph on Slide 16 on the right, the projected schedule of expenditures across roughly a 3-year span. FCX covers 49% of that spending. Not long ago, we finalized a fresh $1 billion bank credit facility for PT-FI so these projects can move forward, and we intend to arrange more debt financing, obtainable at appealing rates, to support these efforts. As noted, the anticipated long-term expense of funding the smelter ought to be balanced out by eliminating the 5% export duty in stages. At the bottom of Slide 16, a graph is displayed demonstrating that the economic effect isn't significant, since the smelter's cost would basically be canceled out through reduced duties, which we pay at present. A 3-year volume outlook appears on Slide 17. Those figures align with the guidance we gave before. We keep chasing extra incremental near-term growth possibilities while carrying out our longer-range development planning. Turning to Slide 18, we illustrate how substantial cash flow generation is under these volumes and cost estimates. The price assumption spans $4 to $5 for copper, with gold and molybdenum kept unchanged at $1,800 an ounce for gold and $16 a pound for molybdenum. From these graphs, you can observe that we'd produce EBITDA averaging above $12.5 billion yearly across '22 and '23 at $4 copper, rising to $17 billion yearly at $5 copper.
Kathleen Quirk
executiveWhen it comes to operating cash flows, after taxes and interest, the range would be $9 billion to $12 billion under those price assumptions. Just like we showed in the second quarter, we are producing free cash flow that is very significant, and we expect that pattern to keep going, with cash flow well above what we spend on capital. Slide 19 shows our projected capital: $2.2 billion for this year and $2.5 billion for 2022. As you will see, roughly $100 million of expenditures moved from 2021 into 2022, and that was a matter of timing. We have also pulled some capital forward from later years into 2022 to reflect when additional leach pad construction at Lone Star will occur, along with some highly attractive growth spending in Indonesia tied to mill recoveries. A period of outstanding free cash flow generation has begun for us. Volumes are growing, markets are strong, and our capital needs are low. On Slide 20, this looks backward, but across the last 12 months, net debt has come down by $5 billion, and $2 billion of that came in the second quarter by itself. Our credit metrics, as you can see, are strong, coming in at less than 0.5x EBITDA on a trailing 12-month basis. We expect those credit metrics to stay strong and keep improving. As Richard said, we hit our targeted net debt level a number of months ahead of plan, thanks to our long-lived asset base, a production profile that is growing, and strong markets. We will be able to keep strengthening the balance sheet, give shareholders increasing cash returns, and build additional values within our asset base. Slide 21 simply restates our financial policy. Our Board established a performance-based payout policy earlier this year, under which up to 50% of free cash flow goes to shareholder returns, with the remainder available for growth and further balance sheet improvements. Given that we recently reached our net debt target, we expect our Board to consider additional payouts to shareholders alongside our 2021 results. We look forward to reporting on our continued progress and to continuing to build additional values as we move ahead. Operator, at this point we would like to open the call up for questions.
Richard Adkerson
executiveKathleen, I'd like to emphasize what you said regarding managing costs. People everywhere are zeroing in on worldwide inflation and how it hits mining businesses; and like Kathleen mentioned, our energy expenses have risen, our grinding material expenses have risen too; yet Josh Olmsted and the Americas team have performed wonderfully in counterbalancing that. Mike Kendrick, who runs our molybdenum operation — both a primary production and a by-product operation — and with molybdenum prices higher, that offsets some of these rising costs for us. A strong gold price also benefits us. Danny Hughes heads up our supply chain group. So all of this together is assisting our company in truly softening a lot of these cost escalations, coordinating with logistics. I simply wanted to point that out since I believe it matters, considering everyone's worries about where inflation is heading; so let's move on to questions. Thank you.
Emily Chieng
analystCongrats on hitting that net debt goal so fast. Perhaps I'll pick up where Kathleen left off, regarding returning capital. Why would you hold off until the close of full year '21 to carry out that capital returns program? And along those same lines, do you yet lean toward a special dividend, a buyback, or maybe moving to a variable dividend approach?
Kathleen Quirk
executiveThank you, Emily; we hit the net debt target right at the close of June. So from here on, as we produce cash flows, up to 50% of them would be available for us to weigh extra payouts to shareholders. This will be under review by our Board. And we do anticipate adhering to the policy of distributing up to 50% of excess cash flow. No conclusions have been drawn about whether it will be extra dividends or repurchases of shares, and that is something to be weighed at that point. Yet the commitment stands to deliver robust cash returns to shareholders from our free cash flow. And we anticipate that across the coming months we'll keep generating free cash flow and that will carry on into next year and past that.
Emily Chieng
analystGreat. That's useful. And a quick one, if I can fit it in. Just regarding Grasberg, I think that at the close of Q1, you hit 75% of your total output there. Could you remind us where we stand now, and where you anticipate being at the conclusion of 3Q? And that 100% production level, is that a fourth quarter average, or is it an exit rate?
Kathleen Quirk
executiveThe average was 78%...
Richard Adkerson
executiveAt present, we're sitting at a little below 80% on our goals for metal output. That puts us significantly ahead of where we planned to be. By the close of this year, we will reach 100%.
Kathleen Quirk
executiveThat figure represents the typical level across Q4, Emily, so our expectation is that we will achieve those run rates during that same quarter.
David Gagliano
analystI'd like to ask a bit about CapEx. Our capital spending does change — Kathleen, you mentioned it, but I missed part of what you said. Could you take us through how much of that incremental net increase — sorry, that $200 million — reflects ordinary cost creep as opposed to projects being pulled forward? And which projects are those again? A bit more detail would help; that's my first question. Since I only get one, there's another piece to this: could you discuss the modest revisions to the exit rate targets — the extraction exit rates — for the Block Cave versus the DMLZ zone? Block Cave moved higher. DMLZ zone moved lower. I'd like to hear what's driving those adjustments.
Kathleen Quirk
executiveRegarding capital, we moved $100 million from 2021 into 2022, and that was purely a timing issue; our spending has not proceeded as fast as the original budget assumed. So — $100 million stems from timing; in addition, we pulled forward certain capital that had been scheduled for later years, related to building new leach pads at Lone Star. Also — the sole new item we put into 2022 is the project we described concerning higher mill recoveries at Grasberg; and the outlay will occur across multiple years. The total comes to approximately $400 million; however, $100 million is planned for 2022. In the end, that will boost volumes. We anticipate roughly 50 million pounds of copper along with 50,000 ounces of gold. It's a highly attractive project with a quick payback; so that's a plus; and it will serve as one of the projects — just one among many, we hope — funded by our remaining 50% of cash flows. There truly weren't — as for the second question, there truly weren't any significant alterations regarding Deep MLZ and Grasberg Block Cave. We refresh the plans each quarter; and in fact only small differences existed between the two. And truly, the long-term plan for Grasberg and Deep MLZ matches the earlier forecast. And Mark, I'm not sure whether you'd like to add something there, but it's — was definitely quite consistent with our earlier forecast.
Mark Johnson
executiveCorrect. The sole small adjustment relates to the fact that from 2022 all the way to roughly 3 years ahead, the mine plan — or rather the mining rates — is capped by what the mill can process. What we've done is that a few tweaks were made, and since some GBC values during this period of constraint are rising, meaning GBC grades are going up, we replaced a portion of that GBC material, which carries the higher value, with somewhat lower-value material taken from the Deep MLZ.
Richard Adkerson
executiveDave, it's nice to hear from you. Let me begin by saying that the increased capital spending is a good thing. We've just emerged from a stretch where capital was tight. At this point we are investing capital — not enormous additional sums, and part of it is simply timing — in order to generate new value. The Deep MLZ stands out as a tremendous success, since we have managed to meet and handle the size and necessity problems we ran into before. So, picking up on Mark's comment, the foundation for our future success lies in those mine rates. We have to raise the mine rates, and we are accomplishing that successfully. We're also addressing this bottleneck at the mill through the construction of SAG 3 and other investments. But the foundation for our future success in hitting our mine rate targets — which has been essential for 15, 20 years — and our ability to accomplish that is something all of us feel truly wonderful about, and we congratulate our team for achieving it over the years.
Christopher LaFemina
analystI had intended to ask about Grasberg and the shipment problems there. Yet what you just said in response to the prior question makes me think of something different, namely your pipeline for organic growth. It's genuinely fascinating that every quarter, you appear to pinpoint a bit more incremental volume that could possibly be extracted from certain assets you already own. There's the mill project, the mill recovery project at Grasberg. There are possible modest expansions at Lone Star, requiring little capital, not many additional incremental volumes, yet there is potential growth regardless that many of us perhaps didn't know about; still, when I examine your production guidance for Grasberg or for the company as a whole, that guidance hasn't been raised to capture any of this possible growth; and my question about it is whether that's since the projects aren't yet included in guidance? Or is it simply that they're minor and there are many moving pieces, making it essentially a rounding error relative to what your guidance was? So how should we consider production past, let's say, 2022 or 2023? And how could this affect your guidance?
Kathleen Quirk
executiveYes. I'd say it's the second one, Chris. The Grasberg mill project wouldn't land, in terms of the recoveries, until 2024. And it falls inside the rounding. But I genuinely think we have some upside as we look ahead. I genuinely think we have some upside on a consolidated basis from these initiatives that might potentially arrive in '22 and '23.
Richard Adkerson
executiveChris, what I'd tell you is that this is a tricky operation. I mean, we arrive at these figures, we take a look, and we see how strong they appear; yet beneath the surface, surprises always pop up; and when it comes to — measuring grade presents a fresh difficulty; the column heights involved in the underground development are substantial. And so being in a position — we had better grades in quarter one, a bit weaker grades in quarter two. That is simply going to be a characteristic of what we must contend with. So there are simply many shifting pieces. Our people across the globe keep discovering methods to make incremental gains; those will show up in our figures eventually, and there will be plenty of shifting pieces. When it comes to shipping, those of you who've tracked us across a long stretch of time know that, that's perpetually a matter of timing at Grasberg. The port we have there sits at a very shallow spot, a shallow sea in that location; our historical loading operation there is comparatively complex. We must lighter concentrate out to vessels and weather shipping schedules. Logistics problems will invariably create a timing effect. Let me just repeat once more, what truly matters for us is mine rates, discovering methods to make incremental gains, and that's simply a continuous process that we observe.
Christopher LaFemina
analystI apologize — regarding the shipment difficulties over at Grasberg, a lot of which are fairly routine, everyday sorts of matters, does COVID play a role in that too? Did it contribute during the previous quarter? Or should that not be counted as a cause of the shipping trouble?
Kathleen Quirk
executiveNo, that's not accurate. We were performing certain maintenance work on the ship loaders, and that set us back during the earlier part of the quarter; after that, weather struck us as the quarter came to a close; so honestly, that had nothing to do with COVID.
Richard Adkerson
executiveWe acted early — and this is merely an illustration. It wasn't significant, yet it does have an effect. There's a concentrate pipeline running from the highlands to the port. A scheduled maintenance plan exists. Certain events occurred, and we needed to move that planned maintenance forward. So it's nothing out of the ordinary; that's been typical for our operations in that location from the time we began ramping up Grasberg during the 1990s; and therefore it will be among the matters we must handle going forward. It simply isn't where our success is centered. Our success is centered on the ramp-up of the mine rate.
Alex Hacking
analystThere's a slide you have about the new leaching technology. This low-grade sulfide chalcopyrite leaching approach really interests me. It looks quite promising. Many impressive individuals are involved with it. It sounds like your team is trying it out. What do you think — I mean, first off, what's your perspective on this technology? Does it appear promising to you? And then, how would you assess the possible future effect on Freeport and the copper sector at large? Say 10 years from now, if this technology works out, what amount of extra copper do you figure Freeport might produce? And what amount of extra copper do you figure could be generated worldwide with this technology?
Richard Adkerson
executiveSo Alex, I appreciate the question; it's — let me be clear, this isn't a single technology at work. Multiple parties are pursuing a range of efforts to create various technologies. Our own R&D efforts are underway, and we're examining across the board how this could be relevant for us. I believe we're particularly positioned to benefit from it since we possess such a large number and size of past leaching operations, a few of which are now completely inactive, that we can consider applying these to. So we hold a unique opportunity in the industry. Others have some as well, but we hold a unique opportunity to do — to examine this from 2 angles. One involves employing the leaching technology. And incidentally, we're adding to that with this artificial intelligence, data analytics prospect to gauge the effect of all this, but to use this on an active and existing leaching leach pads that we have in great abundance; so that's one item. And then aspirationally, it might offer a method to recover material from mining operations that would otherwise need to be recovered via mill investments. And it could be, and this is looking forward, a chance to reduce capital by recovering low-grade sulfide deposits that would otherwise need to be mined and milled; so it's early stages. We lack complete answers. I simply want to convey to you how thrilling it is; it's an opportunity for us, opportunity throughout the industry; this isn't a shale oil-type game changer for the fundamentals of copper supply.
Kathleen Quirk
executiveTurning to Slide 11 — those 38 billion pounds shown there represent material already extracted, which sits outside our reserves and doesn't appear in any of our production plans. So even capturing a very small share of it could eventually add up to a sizable figure. Josh, would you like to share some thoughts from your point of view?
Josh Olmsted
executiveAlright, thank you, Kathleen. Yeah, like both Richard and Kathleen mentioned, the chance in front of us here is genuinely thrilling. What I believe is unlocking this even beyond the individual technologies we're examining, researching, and testing through different pilots is pairing those with the data analytics Richard brought up. Those analytics — plus the methods we've picked up during the past several years applying that tech on the milling side — have now revealed possibilities on the leaching side to us; combining that with the range of technologies is truly exciting for us, since it lets us examine things from an angle we'd never taken before; we've begun noticing some of those gains at Morenci through a portion of this pilot work, and that's what has us genuinely energized about what could lie ahead. Another point worth mentioning: as Richard noted, this isn't what I'd describe as a basic game changer or a step change for the industry, and it unfolds gradually. Still, it comes with quite low incremental cost, a low carbon footprint, and serves as an incremental addition as we move forward. Even so, it's truly exciting. There's a great deal of energy. Thinking about comparable things we witnessed with our agile efforts previously, we're observing similar patterns on the leaching side as we interact with different tiers of the organization. The employee engagement, the enthusiasm, the passion, and the ideas they contribute alongside the models we're building will, I believe, really unlock — or tap into, rather — these chances and deliver value ahead for us.
Richard Adkerson
executiveCorrect — Cory Stevens is the one heading this up. I sat in on a meeting with the newly assembled group. For Freeport, the headcount is substantial. Rick Coleman and his team are contributing as well. And I came out of it thinking this represents a fresh opportunity. Over the years, you've heard me speak about how promising the copper market's prospects look, along with the assets we hold, the reserves not yet developed, and the resources not yet developed. This goes past all of that. Naturally, it isn't reserves — and it isn't part of our resources either. So what we have here is an entirely new opportunity that might be meaningful for Freeport, and no one is positioned better than we are to capitalize on it.
Alex Hacking
analystThanks a lot for that detail. I had some other — my apologies, I meant to mention that I've seen a few remarks suggesting this might eventually account for 5% of worldwide copper output. So — yet from what you're saying, it seems you view this as something with a more distant timeline that stretches out the mine's life rather than something that could truly transform things.
Richard Adkerson
executiveIt's far too soon to make that call, Alex. Far too soon.
Carlos de Alba
analystPicking up on where growth might come from — could you give an update on that goal of 200 million pounds each year you had prior to the pandemic, which came from innovation and productivity gains in the Americas? Is that still another opportunity for growth on your end? Or has it — or is it by now part of the projects you've just been walking us through during this call?
Kathleen Quirk
executiveIt's part of them. That project has kept going. We brought it in-house. Some of it had been done by outside parties. And we — in order to reduce capital and operating costs, we moved from external to internal. And that agile approach to work, along with the use of artificial intelligence, is now part of everything we do. So it's in our plans. The one place I would point to where that isn't the case is Cerro Verde, since we haven't managed to run the mill at around 95% of the levels seen before the pandemic. Before that, we had plans to go well beyond 400,000 tonnes per day. And so, once the pandemic passes at some point, we'll be able to return to those initiatives at Cerro Verde, and those aren't in our plans. In the U.S., though, they are...
Richard Adkerson
executiveUnlike putting up a concentrator, this isn't a single event. It keeps going. We're going to keep adding to it. Like Kathleen mentioned, Cerro Verde—home to the biggest concentrating milling operations anywhere on earth—has capped what we were able to accomplish there. And since our attention has been on ramping up mine rate at Grasberg, we still haven't delivered all of those new tools, skills, opportunities, and technology over to PT-FI, though that's coming down the road. So rather than a onetime thing, this will be a continuing piece of our business moving forward, and our teams have genuinely embraced it.
Carlos de Alba
analystOkay, got it. If I could also ask about the smelter financing—the plan remains to secure project financing for this venture initiative, right? So from a cash flow standpoint at Freeport, that wouldn't put at risk any possible boost in dividends or shareholder returns, is that right? You'd be obtaining the funds from banks or whichever source, and because of that, the cash flow the company generates still lets you folks pay dividends and repurchase shares.
Kathleen Quirk
executiveYes, that's right. Our dividend would be affected by the debt service, to the tune of 49% of it. However, the duty phaseout offsets that. So in reality, FCX's dividends aren't anticipated to take a hit.
Richard Adkerson
executiveAnd it's definitely — the cost of the smelter are tax deductible to PT-FI.
Carlos de Alba
analystWhen you say financing cost, do you actually mean return?
Richard Adkerson
executiveNo — what I'm referring to is operating costs, that sort of thing. Depreciation. Everything here sits at the PT-FI level. Carlos, you got it exactly right in your analysis. What I'm simply highlighting is that you receive the benefit of that 5% export duty relief. You have an operation in which depreciation and operating costs can be deducted for tax purposes under the consolidated Indonesian tax return of PT-FI, which ranks among the substantial taxpayers in Indonesia. Through taxes and royalties, the government captures nearly 50% of the economics at PT-FI; on top of that, they now hold 50% equity ownership. So 70% or more of Indonesia's economics flow to the government. FCX keeps the interest — basically the entire interest we held when we entered these negotiations, which I figured would stretch for years and that we couldn't pull off; yet what an incredible result for every party involved back in 2018.
Orest Wowkodaw
analystWith Chile and Peru possibly imposing much heavier taxes and royalties down the road, I'm curious whether that shifts your view on growth ahead, and whether Freeport might consider building deposits in other countries on newer frontiers, perhaps Ecuador or somewhere similar?
Richard Adkerson
executiveThat's a great observation. Copper supply today is 40% from Chile and Peru — 40%. And right now both nations are in the middle of political processes aimed at extracting more from mining companies for their governments; how it all shakes out is unknown, and finding out will take time. Peru just certified its new President. Chile is engaged in a lengthy process examining its constitution. We've already stated that the situation in Chile is leading us to hold off on a decision regarding a world-class expansion opportunity at El Abra. This will hit other miners too. What the end result will be is genuinely unclear. The bottom line: this should lend support to copper prices going forward.
Kathleen Quirk
executiveRegarding your second point, our U.S. holdings carry greater worth — and we have no intention of expanding beyond the regions where we already operate. Opportunities exist for us within the United States, as well as in other locations.
Orest Wowkodaw
analystAll right. And as a quick second question. I realize a stability agreement exists at Cerro Verde. My understanding is it runs until roughly — around 2029, I believe; yet with certain remarks coming from Peru's new President, how confident are you folks that it will actually be respected?
Richard Adkerson
executiveWell, looking back at history, other presidents in Peru have taken office over the years making comparable kinds of statements. Once they assume office, the fact of how vital mining is for propping up their economies turns out to be obvious. Right now we simply don't know. Alongside the remainder of the industry in Peru, we're making the case for how important copper mining is to that nation. Still, we'll need to navigate our way through the situation. Uncertainty is present. In Peru we lack major growth prospects, yet we hold a very sizable operation at Cerro Verde that matters greatly for our present and future copper output levels; therefore attempting to predict how all of this lands wouldn't be useful or illuminating; a robust stabilization agreement is in our hands, one that is fairly recent, having replaced an earlier version. It's more robust; even so, as has always been our practice, we'll engage with the industry. We'll seek to collaborate with the government and communities in order to aid Indonesia's poverty reduction efforts — I mean, Peru's poverty reduction efforts within that nation.
Abhi Agarwal
analystI simply wanted to ask one more thing, following up on what was asked before. Since your attention is on developing the Bagdad and Lone Star resources during the coming year, I realize it's still early, but at what point do you expect a decision can be reached? Also, are there any kinds of CapEx guidelines at this stage?
Kathleen Quirk
executiveFor Lone Star, we're approaching it step by step. We're already operating above what the design rate calls for; and we have plans along with studies examining whether another increment is possible, and those should be resolved within the next several months. As for Bagdad, it's a major project. And we're moving our engineer — our studies, feasibility studies forward. We're examining every facet of water and tailings. And like I mentioned, my hope is that next year we'll be in a position where we can qualify that project. Final capital expenditure estimates aren't available yet. We've been trying to identify mill setups that would carry lower capital intensity compared with a traditional mill, but that effort remains ongoing.
Abhi Agarwal
analystUnderstood; and allow me to fit in a single additional question, if I may. So when I look at Slide 7 — the deck's Slide 7 — and set it against the one from Q1, the EBITDA sensitivities are unchanged despite the assumptions for gold price and moly price having risen. So is that essentially because unit costs are assumed to be higher in '22 and '23? Or did I overlook something?
Kathleen Quirk
executiveNo. Some elevated costs are incorporated into our figures regarding the items we mentioned earlier, mainly energy. And the — more than compensating for the effect of those higher gold and molybdenum prices; but these are order of magnitude, rounded numbers, should be slightly above these numbers, but we simply carried on with the order of magnitude that we presented previously. But some cost inflation is being included in our revised forecast.
Michael Glick
analystI've got a single question. Regarding the drought out in the Southwestern U.S. — from what I can tell, conditions are quite difficult in that region. I'm aware that when it comes to water consumption, agriculture dwarfs mining by a wide margin. That said, could you address whether this might affect your operations or costs in any way, and also walk us through the water agreements you currently have?
Richard Adkerson
executiveThe Colorado River's level is indeed something we're concerned about — it's a primary water source for what we do. That said, this isn't a fresh issue; we've faced it steadily across the years. Alongside communities, Native American groups, and those in farming, we've implemented measures to address it. So we don't perceive — we view this as a continuing effort requiring both resources and management attention from us. No crisis of any sort appears to be developing, in our view. Still, we'll collaborate with all parties in an effort to save water. Right now, our performance on conservation and water reuse is excellent, but this will remain a continuous management responsibility. Everything involved is already reflected in our present cost structure, and going forward we don't expect significant shifts there.
Michael Dudas
analystRichard and Kathleen, going back to the smelter and that 2024 completion date — Chiyoda, I'm certain this is a competitive situation, but is the contract fixed price? Is there enough of a buffer in there to absorb or account for all the possible changes tied to COVID and the supply chain problems that everyone is growing more concerned about? And do you feel comfortable that the government, together with PT-FI, is on board with that kind of contract structure, one that could get you to that target?
Kathleen Quirk
executiveOur estimate does include contingency. For every reason you just listed, it isn't a fixed price contract. We need the ability to help control the cost, and we didn't want a large amount of risk built into the capital that might or might not materialize; so this felt like the correct structure to us. The contract does involve risk sharing. When it comes to COVID, the government gets the situation. We experienced delays across the last 12, 15 months related to the project. And the present circumstances are also something we're watching very carefully; but we keep the government updated on a regular basis regarding the time line; and our commitment — together with Chiyoda — is to finish this as promptly as we can, while acknowledging that some things fall outside our control, such as the COVID situation right now.
Michael Dudas
analystThat $2.8 billion figure is quite a shift from what people might have expected 2, 3, 4, or several years back, isn't it?
Kathleen Quirk
executiveThe scope has changed, yes. Earlier, our plan involved 2 lines at the smelter producing 2 million tonnes in total, but that came down to 1.7 million thanks to the expansion opportunity at PT Smelting. So what we're looking at now is somewhat different in scope; and sure, certain cost factors have shifted. You're aware of all the — what those look like in terms of where construction costs stand at present. Still, we've carried out a fair amount of value engineering alongside Chiyoda throughout this stretch. Everyone involved is dedicated to keeping an open book and ensuring the smelter succeeds as much as possible while getting it online with maximum cost efficiency. Previously we were sitting in the $3 billion to $2.5 billion to $3 billion range, but with some ups and downs along the way, we're now just a bit above that.
Michael Dudas
analystThis open book approach to sharing risk is certainly the right path forward.
Matthew Murphy
analystSince you're nearing maximum throughput at Grasberg, I was curious whether you could shed some light on what underground mining costs look like, on a per tonne basis, where things currently stand, what you're targeting, and whether that matches your original expectations?
Richard Adkerson
executiveYes. We are hitting the level we aimed for. There's no doubt about it. Some of these broader factors have to be managed. Still, simply reaching those volumes, combined with the gold credit and copper's high grades, makes it possible. Mark, would you like to add anything here?
Mark Johnson
executiveYeah. Operating unit rates have gotten a great deal of attention from us. And where we'd like to be, we're pretty much there. I believe there are still a few chances to simply become more efficient with certain aspects of the mining. Clearly, over at GBC, the train haulage system has demonstrated a high level of efficiency; it runs entirely without people, and that's performing quite well. At Deep MLZ, the fracking is providing benefits. The cave, we can see, keeps maturing, with far less secondary blasting. So many of these items are calming down; though I'd say it fits squarely inside the forecast we'd put together. And in our view, additional opportunities remain for further improvement.
Jatinder Goel
analystI've got a single question regarding the administrative fines over in Indonesia. Right now, we're examining the 2024 timeline, and it appears you've also recorded a small provision in your books. Is there anything you can share about where things stand in that conversation with the government? And is there any acknowledgment that these penalties ought not to be imposed and ought not to be collected to the degree that media reports suggested earlier?
Kathleen Quirk
executiveYes; throughout the quarter we collaborated with the government along with this third party — brought in by the government and by us — to examine how our performance measured up against the plan, the schedule, and everything tied to the pandemic. And the — it appears the fine is going to land in the $16 million range, which we accrued in full during the quarter. Earlier, we had accrued $13 million. So it appears that matter is now behind us. Along with this, we also handed the government a fresh schedule showing what progress is anticipated going forward. And that's what future measurement will be based on. So our expectation is that this won't be a continuing issue. And it's — the resolution leaves us pleased.
Jatinder Goel
analystGot it, that's quite clear, Kathleen. Let me squeeze in one more quick question. Regarding moly, how long do you figure these elevated prices can hold up? And is there a lot of room for you to bring more volume out of your 2 trendy mines?
Kathleen Quirk
executiveAs for that second point, we're examining — our primary mines have been running under their capacity. We're evaluating possible ways to boost output at the Climax mine. When it comes to pricing, forecasting isn't something we do. Still, as Mike can share, the market has stayed extremely tight. That's holding true even through the summer months. Mike, anything to add...
Richard Adkerson
executiveMike Kendrick is in charge of our molybdenum operation, which is a strong operation with exposure to pricing, and we have the ability to adapt. Mike, would you like to say something about that?
Mike Kendrick
executiveAbsolutely. Kathleen hit the nail on the head — we are examining ways to grow output at Climax, and we're assembling a ramp-up strategy for it so we can react to what's happening economically. Then when it comes to pricing, the key thing to note, I'd say, is that by-product output accounts for the overwhelming share of molybdenum produced in the West; and at this point, it's becoming clear that those copper mines simply aren't entering operation. That ties into our broader narrative about how vital copper is, and beyond that, that locating resources, getting them up and running, and having molybdenum come along with them is no easy task. So in our view, there's something of an inherent link between the copper story and the molybdenum story. And a structural deficit certainly exists this summer, and only time will tell how it unfolds.
Richard Adkerson
executiveOkay, thank you all — these are thrilling days. The finest is still ahead, so stay with us. I appreciate it.
Operator
operatorThat wraps up today’s call, everyone. We appreciate your joining us. You’re free to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Freeport-McMoRan Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Freeport-McMoRan Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Freeport-McMoRan Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.