JSW Energy Limited (533148) Earnings Call Transcript & Summary

November 3, 2020

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 52 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the JSW Energy Q2 FY '21 Results Conference Call, which Axis Capital Limited is hosting. <<operator_script>> Kindly be aware that this conference is being recorded. At this point, I hand the conference over to Mr. Abhishek Puri of Axis Capital Limited. Thank you, and over to you, sir.

Abhishek Puri

analyst
#2

Yes. Thank you, Aisha. Good evening, ladies and gentlemen. Speaking for Axis Capital, it's my pleasure to welcome everyone to the JSW Energy Quarter 2 FY '21 Earnings Conference Call. Joining us today is the entire management team, represented by Mr. Prashant Jain, Joint Managing Director and CEO, along with Mr. Pritesh Vinay, the company's Chief Financial Officer. Prashant will start us off with his opening remarks covering operational highlights and the key updates for the sector. After that, we'll move to the Q&A session. So with that, I'll turn the floor over to you, Prashant. Over to you, sir.

Prashant Jain

executive
#3

Thank you, Abhishek. Good evening, ladies and gentlemen. I trust everyone is safe and well. This quarter we observed a rather interesting trend, driven mainly by the economic recovery reflected in the various headline numbers. Power demand during the quarter fell by 0.9%, against a negative growth of 16.2% in the quarter before. We also saw improvement in power demand month on month. In July, it was negative 4.2%. In August, negative 2.4%, and in September, positive 4%. Starting from the 20th of September, we began to see power demand rise by double digit. Apart from the south, power demand was performing quite well everywhere else. In October, we saw power demand growth of 12%. In November as well, it is tracking along the same lines -- at a similar run rate of 12% to 13%. Another interesting fact we observed is that in the year prior, during October, power demand had degrown by 10% on a higher base of 2017/'18, when October power demand was very high, because two years back, in the month of October, power demand was so strong that we were selling power at that time in the spot market at INR 15 to INR 17.

Prashant Jain

executive
#4

And a year ago, the issue was an extended monsoon. This year too, despite that extended monsoon, and with a lower base effect, we observed greater power demand during October. So to be precise, it isn't just the lower base effect — there's also positive economic activity, which showed up in PMI as well as in various other headline numbers, whether automotive sales, steel sales, cement sales; power demand was very, very robust. A second interesting trend we noticed concerns PLF and net generation: on the surface, the overall headline figure looked like negative 1% net generation for the quarter year-on-year. But on a long-term portfolio basis for thermal generation, power net generation rose 20%. And overall, long-term PPA backed net generation increased 10%. So this likewise substantiates that actual power demand growth is rising substantially. And distribution companies have been purchasing increasingly more power from the long-term portfolio versus the prior year. To give you a bit of color as well — for instance, last quarter our PLF, the actual PLF, stood near 80% in Barmer, compared with 62%, 63% a year earlier.

Prashant Jain

executive
#5

And much the same thing happened at the other distribution companies as well. Taken together, then, it shows this recovery is genuine and it is broad-based. On the thermal side, PLF under long-term PPAs also rose year-on-year, from 65% to 78%. On the financial side — looking at financial performance — revenue fell 8%, mainly due to some long-term customers shifting to job work, along with weaker merchant sales. EBITDA for the quarter was negative, down 5% at INR 985 crores, though profit before tax was flat, and profit after tax was the same. In the quarter, we repaid debt of INR 822 crore. And in the first half, it was lower by INR 1,300 crore. The closing debt position, therefore, stood at INR 7,671 crore, which works out to a net debt-to-equity of 0.59 and debt-to-EBITDA of 2.43. Our average interest cost declined to 8.33%. We are witnessing the end of the deleveraging cycle in this financial year. Our view is that deleveraging will carry on through the end of this year. However, with our recent entry into renewables, we have received the NOI from SECI for an 810-megawatt wind power project, and we expect to sign the PPA in the current financial year.

Prashant Jain

executive
#6

On top of that, for our Kutehr 240-megawatt power project — as we mentioned before, we're entering into a PPA with Haryana, and we've received the regulatory approval for it. The PPA will now be signed. That project has kicked off. With this, projects on the ground total 1,050 megawatts. As we explained earlier, we intend to become a 10 gigawatt company over the next 3 to 5 years. We expect roughly 1,000 to 1,500 megawatts of capacity to keep coming each year. And we expect to reach 10 gigawatts primarily through renewable sources. So our renewable portfolio will rise from the current 35% to 65% to 70% over the next 3 to 5 years. On the receivable side, JSW Energy outperformed the industry. Our receivables for the quarter, compared with the prior year — September '19 — fell 3% year-on-year, while our overdue receivables dropped 17% year-on-year. But month-on-month, in October, overall receivables declined a further 35%. So our receivable position is quite good given the challenging environment we've been seeing.

Prashant Jain

executive
#7

That has also led to a considerable reduction in leverage on our balance sheet, and those factors also speak to the quality of the PPAs that JSW Energy holds. And looking ahead, we expect this type of trend to persist. With that, I'll wrap up my opening remarks, and we're happy to take any further questions.

Operator

operator
#8

<<operator_script>> Our first question comes from Mohit Kumar, who is on the line from DAM Capital.

Mohit Kumar

analyst
#9

Sir, two questions from me. First, regarding the 810-megawatt facility, do we have any clarity on the capital cost as well as where it will be located? And what PLF are we expecting? What sort of timeline are you looking at? Second, on the Ind-Barath project, is there any update you can share with us?

Prashant Jain

executive
#10

Now, on that 810 megawatts — it's a hybrid budget, and within it we can include solar for as much as 20%, alongside the wind. We expect the project to cost roughly INR 4,700 crores to INR 4,800 crores. Timelines run 24 months starting from the PSA date, and we anticipate the PSA being signed in Q4 of this financial year. The project will be built in Tamil Nadu. Connectivity approvals are in hand. We've also secured the land where this project is going to come up. Turning to Ind-Barath, that one sits in the NCLT approval process, and it's taking considerable time owing to a lot of litigation among creditors. Also, because of the pandemic — the ongoing pandemic — proceedings aren't moving at the pace previously anticipated. Even so, the process keeps going. That said, right now we have no kind of color on when we might see the light of day.

Operator

operator
#11

Swarnim Maheshwari from Edelweiss has the next question.

Swarnim Maheshwari

analyst
#12

And nice work on those results. Sir, for my first question, could you be specific about that 810-megawatt renewal bid? What threshold should we have in mind? You also mentioned <<inaudible>> that the land and all of it has been identified. Is the site hooked up to the closest substation as well? So is all of that sorted out on that front?

Prashant Jain

executive
#13

Yes. Like I mentioned, we've received the connectivity approval from PGCIL. So it's very well connected. And when it comes to returns, we anticipate earning the normative returns on the project, in the mid-teens.

Swarnim Maheshwari

analyst
#14

Second, sir, you mentioned that the deleveraging cycle is behind us. And clearly, since you've embarked on the CapEx cycle, is there any number you'd like to share — say 1.5x or 1.2, 1.5 being where you're looking for your debt equity by the end of FY '22 or '23? Would that also include the acquisition of Ind-Barath?

Prashant Jain

executive
#15

So think of it this way: right now, we have a clear path for 1,050 megawatts, which is Kutehr plus 810 megawatts. And with that — if we do it in Q4 of this financial year, we get the PSA signed for 810 megawatts, then 24 months you are talking about, by FY '23, you will be executing this project. And for the Kutehr project, we are looking at COD in FY '25 with that. If you look at it then, our debt-to-equity and debt-to-EBITDA will not see any meaningful impact compared with what we have on the current balance sheet, because the kind of free cash flow that will be coming up from our existing portfolio will be almost the same. So that will go up only when we undertake fresh projects during this time frame. And as and when that visibility comes, then we will be able to talk about it. But at this point of time, there will not be any meaningful change in the debt-to-equity and debt-to-EBITDA from where we are today on the current schedule.

Operator

operator
#16

Up next, we have a question from Aniket Mittal, who's calling in from Motilal Oswal Financial Services.

Aniket Mittal

analyst
#17

Can everyone hear me?

Prashant Jain

executive
#18

Yes, go ahead.

Aniket Mittal

analyst
#19

Sure. Sir, regarding that 810-megawatt project, you said the estimated cost falls somewhere between INR 4,700 crores and INR 4,800 crores. What blend between wind and solar were we looking at?

Prashant Jain

executive
#20

As I mentioned, solar can make up as much as 20%. That's the blend that's allowed, and we'll be at the final stage of the engineering work, but it will go up to 20%. You could say anywhere from 15% to 20%.

Aniket Mittal

analyst
#21

15% to 20%. Sure. And sir, just to get a sense of the blended PLFs too. If you could — let's assume a solar mix of 15% to 20% and the rest being wind, what would your blended PLF be in that case?

Prashant Jain

executive
#22

For solar, the PLF is going to land somewhere between 26% and 27%, and then for wind it should come in somewhere in the 33% to 35% range.

Aniket Mittal

analyst
#23

Wind is going to be 33% to 35%. Okay. Okay. And just to get a grasp on this once more as well. Now we've obviously been awarded VLA. So when this exactly gives you an <<inaudible>>, is there a stop date? Let's say, for the next 6 months or so, or the next 4 or 5 months, if no discount comes up and we're not able to sign the PC -- PFC rather, do we -- I mean, does the contract get canceled or even go for a rebid, or do we a hand up and get out of the deal? Is there sort of a stop data is what I'm trying to understand.

Prashant Jain

executive
#24

No. Absolutely not.

Aniket Mittal

analyst
#25

Right. The concern on this side would be that — yes, we agree the LOA has been secured here. But if there's no visibility on the PPA itself arriving, then we'd probably — we might simply end up sitting on cash while the PPA never receives its LOA. I'm just trying to get a sense internally: is there a time frame?

Prashant Jain

executive
#26

Our visibility into PPAs is really quite strong.

Aniket Mittal

analyst
#27

Is there a specific discount you’d be able to secure for the PFC?

Prashant Jain

executive
#28

We can share it once it’s signed. Still, our visibility is very strong. That’s the reason we brought it up.

Aniket Mittal

analyst
#29

Sure. Sure. Got it. And sir, only regarding the accounting side, I was hoping to get some clarity — I believe there's been a shift in fuel cost driven by accounting, something to do with job work that's taken place, where I think one of your <<inaudible>> capital customers is going to be giving you a call. Just wanting to grasp the reasoning behind that. I mean, what exactly has happened here, if you could shed some light?

Prashant Jain

executive
#30

Pritesh, would you mind handling this one?

Pritesh Vinay

executive
#31

Yes, Aniket — my apologies, could you please ask that question one more time?

Aniket Mittal

analyst
#32

I was just trying to get a clearer picture from an accounting standpoint. And I believe in the notes you've said that one of your customers is now providing new coal, so both the fuel cost and the revenue look somewhat deflated. So could you just explain why that's happening?

Pritesh Vinay

executive
#33

Right. What's taken place is that a number of our group captive consumers have moved over to a job work model, and the reason is GST efficiency. What happens is this: when we, in our role as power generators, buy coal, GST has to be paid on it. Yet power — the sale of power in itself doesn't attract GST. So there's no route by which the procurer of power can claim input tax credit for the GST paid on that coal purchase, correct? Therefore, from a GST efficiency standpoint, if they buy the coal themselves and their end product is something on which GST applies, they're able to claim input tax credit for the GST they pay. So it's purely a GST efficiency route, since in any case, as far as JSW Energy is concerned, the economics don't change, because under the 2-part tariff the fuel cost is anyways a complete pass-through. So it's simply that rather than us incurring the fuel cost and then passing it on, they will incur the fuel cost directly themselves and be able to claim GST input tax credits.

Pritesh Vinay

executive
#34

That's the reasoning behind the job work model.

Aniket Mittal

analyst
#35

Alright, sure — and perhaps one more question. I'd like to get a clearer picture of Kutehr. My understanding is that we've granted a certain number of awards over roughly the last quarter. And the PPA itself is something that hasn't been finalized yet. Could you shed some light on what kind of CapEx you're anticipating for Kutehr? And when will we actually see that PPA get finalized?

Prashant Jain

executive
#36

The source approval is already through, and the PPA will be executed during the current financial year. So the signing is in progress right now. INR 2,750 crores is the total cost of the project. We expect commissioning to take place by September 2024.

Operator

operator
#37

Moving on, our following question comes from Murtuza Arsiwalla, who is on the line from Kotak Securities.

Murtuza Arsiwalla

analyst
#38

I’ve just got one question about this job.

Operator

operator
#39

My apologies for cutting in. Sir, could you please raise your volume a bit?

Murtuza Arsiwalla

analyst
#40

Has it improved at this point?

Operator

operator
#41

Yes, sir.

Murtuza Arsiwalla

analyst
#42

Alright, I just wanted to get a sense of this job work — could you help us put a number on its impact by simply working out the realization and the fuel cost? If you could help us size up what this job work did, how much power moved through the job work, or how much fuel cost would otherwise have been there that isn't there now?

Prashant Jain

executive
#43

Let me explain how you should think about this, Murtaza, since the implementation has come from the Ratnagiri plant. On fuel cost, obviously, we don't provide a station-by-station breakdown of fuel cost. You'll be able to work that out yourself. But as far as the power quantity goes, we can put a number on it — it was slightly above 600 million units. So take those 600 million units and multiply them by the fuel cost at the Ratnagiri station, and that gives you the impact of the job work, which drops out of both revenue and fuel cost. So it's EBITDA neutral.

Operator

operator
#44

Our next question comes from Sujit Jain, who is calling in from ASK Investment Managers.

Sujit Jain

analyst
#45

As usual, congratulations on a solid set of numbers. In my view, your results relative to other players in the industry have always been admirable. My question is a quick one about the cash sales we have. What is the total CapEx we plan on these 3, which, as you said, are Kutehr, then the auction won in SECI as well as Ind-Barath? And of that, what will be the equity portion?

Prashant Jain

executive
#46

As I mentioned, SECI 9 comes to roughly INR 4,700 crores to INR 4,800 crores, and that will be split 70:30, while Kutehr is INR 2,750 crore, to be funded 67:33, debt-to-equity. That's the approach we're taking on those. And for Ind-Barath, as we've discussed, the total project cost stood at about INR 2,500 crores to -- INR 2,500 crores, which we intended to finance with 25% equity and 75% debt. However, right now, in terms of timeline, we aren't certain what that timeline will be. So we'd prefer to examine the timeline once it -- once things crystallize. But for the other 2 projects, we do have clarity on the timelines.

Analyst

analyst
#47

Right. So total equity stands at roughly INR 3,000 crores, as you just noted? And should I assume a timeline running through FY '25?

Prashant Jain

executive
#48

Yes.

Analyst

analyst
#49

What's the cash balance right now?

Prashant Jain

executive
#50

At September's close, that figure stood at roughly INR 811 crores.

Analyst

analyst
#51

So you're bringing in roughly INR 2,000 crores of nearly free cash flow each year now, right? I mean, after subtracting the CapEx that's budgeted through FY '25 for these 3 projects. That means across the coming 4 years, INR 8,000 crores would be produced, and you already hold INR 800 crores, so close to INR 9,000 crores, while the equity need stands at INR 3,000 crores. The debt-to-equity level is quite manageable, as you just said, and it will stay manageable even once these 3 projects are executed, assuming nothing else is taken on. So given that, what's your thinking on payouts? Historically, you've paid INR 1 dividends amounting to INR 170 crores, INR 180 odd crores. But as we can see now, cash flow generation is upon us. And versus that, the planned CapEx is almost 1/3 of it.

Prashant Jain

executive
#52

As I said, we're aiming to become a 10 gigawatt company within the next 5 years. That means we'll be taking on a number of other projects so as to grow our balance sheet. And I also mentioned that our deleveraging cycle has been reaching its bottom. So we will be stepping up the balance sheet. We continue to follow a dividend distribution policy under which we've been paying out 20% of retained profit each year. And so the Board always takes a call if there are opportunities — then we try to deploy the cash toward a growth opportunity. Otherwise, we can also try to raise the payout. So the Board evaluates this from time to time. There have been times when the payout was above 20%. And — but the way I see it, there may be chances of aggressive growth opportunities going forward, because we're seeing rationalities coming into the competitive environment and the renewable space. And we've built enough capabilities, and we're undertaking these projects. And so we see that we'll be able to achieve growth of another 5 gigawatt in the next 5-year time frame.

Analyst

analyst
#53

Yes. I had another question as well, about the stake we hold in JSW Steel shares. What's the cost basis for that shareholding, which in FY '20 comes to roughly INR 1,000 crores? And what fair value for that holding is currently carried on the balance sheet?

Prashant Jain

executive
#54

So we're looking at just under 7 crore shares, and at today's market price that comes to more than INR 2,200 crores. That's where we stand.

Analyst

analyst
#55

Yeah. So, I mean, are you thinking about cashing out on this and using the proceeds either for your own CapEx or returning it to shareholders? Our IPO happened in 2010 at INR 100. Over these 10 years, the stock has hardly traded above that level. And even now, it's still substantially under it. Our execution record has been impeccable, and we've run a tight ship. But when it comes to distribution, I think that's an area we probably need to look into more.

Prashant Jain

executive
#56

Sure, I hear what you're saying, and whenever a chance arises, we'll discuss it at the Board. And at the same time, if I'm not mistaken, close to roughly 44% of promoter shareholding is still below. Naturally, being lower isn't an issue. The place has been getting released lately. But that's really the heart of the matter when it comes to shareholder returns — there's probably some thinking there that I believe you all ought to consider.

Pritesh Vinay

executive
#57

Sujit, let me jump in on that. What we actually represent is the entity days of the energy limited. Commenting on the holding structure at the promoter entity level wouldn't be appropriate for us, since a completely different team handles that. That said, here's what we can discuss, and it's also clear from public disclosures in stock exchange filings: the structure of the financing mode has changed. So if you look at October to December 2019, pledges dropped significantly during that period, and that came about because of the change in the financing structure at the promoter entity level. Beyond that, we really wouldn't have visibility on that side.

Operator

operator
#58

Thanks. Our following question comes from Abhishek Puri at Axis Capital.

Abhishek Puri

analyst
#59

Just one thing here. I mean, looking at other comprehensive income, there's a profit of INR 634 crore from items not classified in P&L. Could you explain what that is?

Prashant Jain

executive
#60

Right, Abishek, that's essentially driven by how JSW Steel's shares moved, so yes, it's the MTM impact sitting in the OCI.

Abhishek Puri

analyst
#61

Understood. And then, second, I’d like to get a sense of what short-term contracts or tie-ups are available that we’ve already done for Vijayanagar and Ratnagiri. Also, are there any ramp-up plans currently in place for JSW Ispat, where we’ll be signing the contracts?

Prashant Jain

executive
#62

Let me frame it this way: where the merchant market is concerned, conditions remain quite benign. And the tariffs are simply not workable at all. That said, when it comes to the long-term PPA portfolio rising from 81%, we see 2 or 3 events that will crystallize this. First is the capacity expansion by JSW Steel at Dolby, which we expect to be finished by the close of this financial year. So that will take place. Also, for instance, the acquisition of Asian Color by JSW Steel will lift the PPA portfolio by a further 14 megawatt. And JSW Steel has a plan to expand capacity at Vijayanagar at some point in the medium term. Whenever that occurs, it will likewise enhance the long-term PPA portfolio. Another opportunity is the 5,000 megawatt RTC blended tender together with renewable energy, for which new guidelines were issued 2 days ago. So we anticipate the tender should be concluded by the end of this current financial year. That is one more possibility for growing the long-term PPA portfolio. Beyond that, in the spot merchant market, today's environment is fairly difficult. For the — at least for this current financial year, I don't foresee any improvement in the trend for merchant prices.

Prashant Jain

executive
#63

Yeah, in the year ahead, merchant prices will likely improve. So because of that, we could see merchant volume picking up in the next financial year.

Abhishek Puri

analyst
#64

That helps clarify things. I just want to raise one point. Regarding Telangana, we had a short-term contract in place. Did you record any revenues or volumes with them, or has that now expired?

Prashant Jain

executive
#65

That one has expired.

Abhishek Puri

analyst
#66

And was there some compensation that had to be made for earlier quarters, since they ended up picking up below the contracted amount?

Prashant Jain

executive
#67

That's still being discussed, and we're confident we'll get it. And as a matter of prudent practice, we haven't recognized it in our income statement up to now. But we're quite confident that we will get it.

Operator

operator
#68

Thanks. We’ll take the next question from Anuj Upadhyay on the line from Emkay Global Financial Services.

Anuj Upadhyay

analyst
#69

Sir, I just need one clarification. A few days ago, a media article said the company is looking to build close to 14 gigawatts of renewable capacity in and around Karnataka and Tamil Nadu. You talked about this 810 megawatts being set up in Tamil Nadu. So are we — or are we in advanced discussions with Karnataka about setting up another 500, 600 megawatts of capacity?

Prashant Jain

executive
#70

Think of it this way, as we've been discussing: we're assembling a long-term portfolio of renewable resources. When we say resources, that means we need to secure specific sites where solar parks or wind turbines can be installed. So we're building that portfolio across a number of states. That comes in handy for us whenever we bid with SECI, and it also helps as we assess group captive opportunities, since JSW Group is a major power consumer. Within the group, total power consumption runs around 2,300 megawatts. Given the different RPO obligations, JSW Group on its own will need roughly 1,000 to 1,200 megawatts of renewable power going forward. So that's another opportunity as well. Beyond that, there's a sizable portfolio we intend to build. If you look back historically, at how the renewable business used to operate, the wind turbine OEM manufacturers would build up a portfolio of sites with potential for installing the builder lines. They would supply on an EPC basis to investors who were mainly acting as financial investors, whereas the JSW Energy approach has been one of very efficient project execution at a very low cost, low capital cost.

Prashant Jain

executive
#71

So because of that, JSW Energy has spent the last 12 to 18 months picking up promising sites of this kind, for solar and for wind alike. And by now we've assembled a fairly sizeable portfolio. That way, whenever we place a bid, we'll be in a position to deliver those projects on schedule and at a very low cost. So there are a number of locations we're working to pinpoint and develop across different states, Karnataka among them.

Anuj Upadhyay

analyst
#72

Okay, sir, just a quick clarification on what you mentioned a moment ago. Vijayanagar was also attempting to place a portion of its untied capacity at the group level. So even after fulfilling that RPO obligation you referred to via the upcoming renewable capacity, would there still be some room available to park our Vijayanagar capacities out there? Or would those more or less now be replaced by the renewable capacities going forward?

Prashant Jain

executive
#73

These two things stand apart and don’t overlap, since an RPO obligation is something you must fulfill. And the second piece is this: if you’re seeking to swap out part of your capacity by substituting thermal power with renewable power, those requirements are also mutually exclusive. So — and regarding what I said about the group captive angle for the RPO obligation, that’s a regulatory requirement. And constructing a portfolio — it can serve any purpose, whether for the SECI tender, for another distribution company, or inside the group.

Anuj Upadhyay

analyst
#74

Good point, sir. Finally, sir, regarding the recent difficulties we've observed in the wind sector specifically. In the last year — I mean, year-to-date, or if we look at the past 12 months, wind power generation has dropped by nearly 35% to 40%. Developers point to altered geographical conditions as the cause, and that's happening nationwide, which is now resulting in a very low PLF level at wind stations. So, sir, basically, how do we intend to address these kinds of challenges? Would the size alone be adequate enough, the one we're targeting, to meet these challenges? Or might there be some technology upgrade or advancement that we'll deploy to handle the situation? Because both — I mean, from our conversations with a few industry players, solar is generally more — I mean, less volatile than wind. And we've now entered renewables, and that too at a large scale for wind? So that's why there was some curiosity behind asking this question.

Prashant Jain

executive
#75

One point I'd like to make clear: the variation occurs for developers operating on a P50 and P75 CUF. However, when you're working with a P90 CUF, no variation exists. So our approach is very, very prudent and conservative. Whenever we evaluate any wind or solar resource, we examine the resources — or rather, by resources I mean the site, where sufficient data is available through multiple wind masts or additional solar radiation measurements. And for solar as well as wind, we always adopt P90 CUF, never P50 or P75. As a result, we don't anticipate any kind of negative surprises in any year, for either wind or solar.

Operator

operator
#76

Aniket Mittal from Motilal Oswal Financial Services has the next question.

Aniket Mittal

analyst
#77

Sir, just one question regarding receivables. I’d say you’ve done a decile on managing the price in receivables. So could you just give some color on — from the state perspective, where are we getting this money from? And how do we plan — or how do you see ending the full year with?

Prashant Jain

executive
#78

First, there's seasonality in how our billing cycle works, since if you look at quarter 1 and quarter 2, the seasonality pattern shows up because of our hydro. And, but if I could put it this way, the current financial year and the last financial year were extremely, extremely difficult for the industry overall. And yet during this pandemic period, the general risk and overdue position for the industry as such has worsened substantially, whereas compared with the prior year, when the sector's total overdue stood somewhere between INR 70,000 crores and INR 80,000 in September 2019. And right now it sits at roughly INR 140,000 crore, while our receivables have declined, which shows the quality of our PPA as well as the kind of power mix we have. So that is what, we believe that at the worst point of the cycle, we could bring our receivables down because we sit in the bottom quartile of the purchase basket for the respective discounts. And so we have managed to do this in an extremely, extremely efficient manner. Looking ahead, we expect this trajectory to keep going, because the incremental PPAs we are signing or the capacity we are constructing is in renewable state.

Prashant Jain

executive
#79

That's also extremely cheap power. So we have a lot of confidence — a lot — that this path is going to keep going.

Aniket Mittal

analyst
#80

Alright. Sir, regarding the receivables balance right now, what portion of that would be past due?

Operator

operator
#81

Thanks for waiting patiently. Management is back on the line with us. Our next question comes from Sarvesh Gupta of Maximal Capital.

Sarvesh Gupta

analyst
#82

Could you share some detail on how your cost of debt is shaped and whether it's trending lower? And what should we expect looking ahead? That's my first one. Then, second, you mentioned targeting a mid-teen sort of IRR on that 810-megawatt project. So are you saying that's roughly 15% pretax project IRR? And should that figure serve as the base case for the rest of the 5 gigawatt, 6 gigawatt growth you're aiming at across the 3, 4 years as well?

Prashant Jain

executive
#83

Yes. Usually, whenever we take on projects, we consider that type of hurdle rate. But in the past, our performance has exceeded it. Even if you look at the free cash flow yield across our whole existing portfolio — because sometimes I've noticed that people immediately work out return on net worth by dividing profit after tax by net worth and computing return on net worth, yet they overlook the fact that, despite the network with a lot of components, INR 2,200 crores comes from the steel shares and JPVL shares, which are not included in our profit after tax. If you calculate over the next 20 years, which is the life of our balanced PPN, the FCF yield will be north of 16%, 17% on our entire consolidated balance sheet. That means every project we have undertaken so far in our 4.5 gigawatt capacity has been earning more than 16%, 17% equity IRR. And that's the way we look at it. And then, for the additional 5, 6 gigawatts of projects we will be building, the hurdle rate will be close to 15%.

Prashant Jain

executive
#84

But overall, we'll outperform that, thanks to our prudent O&M practices. Plus, with a healthier balance sheet, we've been doing a great deal of financial engineering. That is also reflected in our cost of capital. If you look at our cost — the average cost of debt right now is 8.33%, and we see room for it to move further downward, even with a challenging business environment for the power sector in India. So going forward, in the reliability space, there will be plenty of opportunities to tap different kinds of capital markets globally, because for thermal projects there are limited avenues for sourcing capital. In the renewable space, such limitations don't exist. Therefore, given our track record and our balance sheet as well, we believe we'll be able to do that. It's also worth noting that a lot of the incremental improvement in our equity IRR has come from our past track record of very low operations and maintenance costs, which have been declining year-on-year despite wage inflation. So that's how we look at it.

Pritesh Vinay

executive
#85

And Sarvesh, let me build on what Prashant said regarding the weighted average cost of debt. For context, at the close of March, that figure stood at over 9.1%. So across the whole portfolio, a reduction of nearly 80 basis points has already taken effect over the past 6 months. And while we do anticipate a few additional resets on certain portfolios down the road, so a modest uptick remains possible going forward, yes. But I simply wanted to frame that properly.

Sarvesh Gupta

analyst
#86

One quick clarification: the 16%, 17% FCFE figure you mentioned — is that pretax or post tax?

Prashant Jain

executive
#87

No, that’s after tax. And when you calculate the NPV for the remaining 50 — 18, 19 years, and also FCFE, on the network you’ll end up with a similar type of figure. So that’s also something you should — look, then the usual ROE calculation you perform. And if you truly do it on a like-to-like basis or on an operating income basis, then you should remove shares that the company owns, which form part of the net of roughly INR 2,200 crores, INR 2,300 crores. If you take that out, then it will rise further by another 2%, 3%.

Operator

operator
#88

Thank you. Since nobody has any more questions, that brings this conference to a close on behalf of JSW Energy and Axis Capital Limited. We appreciate your participation, and you can go ahead and disconnect your lines now.

Prashant Jain

executive
#89

Appreciate it.

Pritesh Vinay

executive
#90

Thanks, Aisha.

Operator

operator
#91

I appreciate that.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.