JSW Energy Limited (533148) Earnings Call Transcript & Summary

November 3, 2020

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 52 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to the JSW Energy Q2 FY '21 Results Conference Call hosted by Axis Capital Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Abhishek Puri of Axis Capital Limited. Thank you, and over to you, sir.

Abhishek Puri

analyst
#2

Yes. Thank you, Aisha. Good evening, ladies and gentlemen. On behalf of Axis Capital, I am pleased to welcome you all for the JSW Energy Quarter 2 FY '21 Earnings Conference Call. Today, we have with us, the whole management team represented by Mr. Prashant Jain, Joint Managing Director and CEO; and Mr. Pritesh Vinay, Chief Financial Officer of the company. We will begin with the opening remarks from Prashant on the operational highlights and the key updates for the sector. This will be followed by the Q&A session. So with that, I'll hand over the floor to you, Prashant. Over to you, sir.

Prashant Jain

executive
#3

Thank you, Abhishek. Good evening, ladies and gentlemen. I hope everybody is safe and doing well. During the quarter, we saw a very interesting trend, which was primarily in line of the economic recovery, which we were seeing in the various headline numbers. During the quarter, the power demand degrew by 0.9% as compared to the negative growth of 16.2% in the previous quarter. And we saw month-on-month improvement in the power demand. In July, it was negative 4.2%. August, it was negative 2.4%, in September, it was positive 4%. From the 20th of September, we started seeing the power demand going up by double digit. And other than south, everywhere else, the power demand was doing pretty well. And during the October, we saw the power demand growth was 12%. And in November, also, it is going in the same run -- at a same run rate of 12% to 13%. Interesting fact is also what we saw that the year before, in the month of October, the power demand degrew by 10% on a higher base of 2017/'18, where the power demand in October was very high because last to last year, in the October month, power demand was so high that we were selling power at that point of time in the spot market at INR 15 to INR 17. And last year, the problem was prolonged monsoon. And this year also, in spite of the prolonged monsoon, with a lower base effect, we saw the higher power demand in the month of October. So precisely, there is not only the lower base effect, but also the positive economic activity, which has reflected in PMI as well as various other headline number in terms of the automotive sales or steel sales, cement sales, the power demand is -- was very, very robust. Second interesting trend what we also saw is in the PLF and the net generation, optically, if you look at overall headline number was negative 1% net generation for the quarter year-on-year. However, on a long-term portfolio for thermal generation, the power net generation was up by 20%. And overall, long-term PPA backed net generation was up by 10%. So this also substantiate that the actual power demand growth is growing substantially. And distribution companies have been buying more and more power from the long-term portfolio as compared to the previous year. To give you a little color also, like, for example, last quarter, our PLF of -- actual PLF was close to 80% in Barmer as compared to last year, which was 62%, 63%. So -- and similar was the situation in other distribution companies also. So overall, it demonstrates that this recovery is for real and it is broad-based. Overall, thermal PLF under long-term PPA also went up from 65% to 78% year-on-year. Financially -- financial performance-wise, revenue was down 8%, primarily because of movement of some of the long-term customers to job work, and lower merchant sales. EBITDA during the quarter was negative, lower by 5% at INR 985 crores, but profit before tax was flat and same was profit after tax. During the quarter, we had repaid the debt by INR 822 crore. So -- and during the first half, it was lower by INR 1,300 crore. So the closing debt position was INR 7,671 crore, which translates to net debt-to-equity of 0.59 and debt-to-EBITDA of 2.43. Our average interest cost came down to 8.33%. We are seeing the end of deleveraging cycle during the financial year. We believe that this deleveraging will continue till the end of this year. But with our entry into the renewable space, recently, we have got the NOI for 810-megawatt wind power project from SECI, which we expect to sign PPA in the current financial year. In addition to that, for our Kutehr, 240-megawatt power project, wherein, we have spoken earlier that with Haryana, we are entering into a PPA for which we have got the regulatory approval. Now the PPA will be signed. That project has been started. With this, there is projects on ground are 1,050 megawatts. As we had explained earlier that we plan to become a 10 gigawatt company in the next 3 to 5 years' time frame. We expect that close to 1,000 to 1,500 megawatt capacity will keep on coming year-on-year. And we expect to become 10 gigawatt company primarily from the renewable sources. Therefore, our renewable portfolio will increase from current 35% to 65% to 70% in next 3 to 5 years' time frame. As regards to the receivable position, JSW Energy did better than the industry. Our receivable during the quarter as compared to the year -- last year, September '19, was down 3% year-on-year wherein our overdue receivables were down by 17% year-on-year. But on month-on-month, in the month of October, this overall receivables came down further by 35%. So therefore, our receivable position is pretty good as compared to the challenging environment, which we have been seeing. And which has also translated for a substantial deleveraging of our balance sheet and which also speak about the quality of PPA, what JSW energy is having. And and going forward, we see that this kind of a trend will continue. With that, I conclude my opening remarks, and we are happy to take further questions.

Operator

operator
#4

[Operator Instructions] The first question is from the line of Mohit Kumar from DAM Capital.

Mohit Kumar

analyst
#5

Sir, I have 2 questions. Firstly, on the 810-megawatt, is there any clarity on the capital cost and the location? And what kind of PLF we are expecting? What is the kind of time line you're looking at? And secondly, on the Ind-Barath project, is there any update which you can share with us?

Prashant Jain

executive
#6

So as regards to 810 megawatts, it is a hybrid budget wherein we can do 20% -- up to 20% of solar along with the wind. And we are expecting that the project cost will be approximately between INR 4,700 crores to INR 4,800 crores. And the project timelines are 24 months from the date of PSA and we are expecting PSA will be signed in the Q4 of the current financial year. And we are going to set up this project in the state of Tamil Nadu. And we have got the connectivity approvals. We have secured the land also where we are going to set this project. As regards to Ind-Barath, that is under NCLT approval process, which is taking lot of time because of lot of intra creditor litigations. So -- and because of the pandemic -- ongoing pandemic, the proceedings are not happening at the pace at which it was earlier expected. But nevertheless, the process is continuing. But at this point of time, we do not have any kind of a color that by when we can see the light of the day.

Operator

operator
#7

The next question is from the line of Swarnim Maheshwari from Edelweiss.

Swarnim Maheshwari

analyst
#8

And congratulations for a good set of numbers. Sir, my first question is, if you can just specify on the 810-megawatt of renewal bid? So what is the threshold that we are looking at? And you did mention about [Technical Difficulty] land and everything is identified. Is the site also connected with the nearest substation? So is everything sorted out over there?

Prashant Jain

executive
#9

Yes. As I said that we have got the connectivity approval from the PGCIL. So that is very well connected. And as regards to the returns, we expect to get the normative returns in the project, in the mid-teens.

Swarnim Maheshwari

analyst
#10

Sir, secondly, you did mention that the deleveraging cycle is behind. And clearly, as you have embarked upon the CapEx cycle, so any number that you would like to share that, say, 1.5x or 1.2, 1.5 is where you're looking your debt equity to by the end of FY '22 or '23? This would also include the acquisition of Ind-Barath?

Prashant Jain

executive
#11

So look at this way that at this point of time, we are having a clear path for 1,050 megawatts, which is Kutehr as well as 810 megawatts. And wherein -- if we do it in Q4 of this financial year, we get the PSA signed for 810 megawatts than 24 months you are talking about, by FY '23, you will be executing this project. And for Kutehr project, we are looking at COD in FY '25 with that. If you look at then our -- there will not be any meaningful impact on our debt-to-equity and debt-to-EBITDA than what we are having at current balance sheet because the kind of a free cash flow, which will be coming up from our existing portfolio, it will be almost the same. So that will be going up only when we undertake fresh projects during this time frame. And as and when that visibility comes, then we will be able to talk about it. But at this point of time, there will not be any meaningful change in the debt-to-equity and debt-to-EBITDA where we are today on the current schedule.

Operator

operator
#12

The next question is from the line of Aniket Mittal from Motilal Oswal Financial Services.

Aniket Mittal

analyst
#13

Am I audible?

Prashant Jain

executive
#14

Yes, please.

Aniket Mittal

analyst
#15

Sure. Sir, just on the 810-megawatt project, but you've mentioned that the estimated cost is anywhere between INR 4,700 crores to INR 4,800 crores. What's the blend that we were looking at between wind and solar?

Prashant Jain

executive
#16

So as I said, it is up to 20% of solar. That is the permitted blend and we will be in a final stage of doing the engineering, but it will be up to 20%. Anything between 15% to 20%, you can say.

Aniket Mittal

analyst
#17

15% to 20%. Sure. And sir, just to get an understanding on the blended PLFs as well. If you could -- let's assume in a 15% to 20% solar mix and the remaining of wind mix, what would be your blended PLF over here?

Prashant Jain

executive
#18

Solar, the PLF will be in the range of 26%, 27%, and then wind will be in the range of 33% to 35%.

Aniket Mittal

analyst
#19

Wind will be 33% to 35%. Okay. Okay. And just to get an understanding on this again as well. Now we've obviously been awarded VLA. So when this exactly gives you an [indiscernible] is there a stop date? Let's say, for the next 6 months or so or the next 4 or 5 months, if no discount comes up and we're not able to sign the PC -- PFC rather, do we -- I mean, does the contract get canceled or even go for a rebid or do we a hand up and get out of the deal? Is there sort of a stop data is what I'm trying to understand.

Prashant Jain

executive
#20

No. No.

Aniket Mittal

analyst
#21

Okay. Because the worry would be over here that -- yes, agree that we've gotten the LOA here. But if there's no visibility on the PPA itself coming, we just probably -- we may just sort of end up holding on cash and the PPA never gets LOA. I'm just trying to understand internally, is there a time frame?

Prashant Jain

executive
#22

We have a very strong visibility of PPA.

Aniket Mittal

analyst
#23

Any particular discount that you would be able to sign the PFC?

Prashant Jain

executive
#24

We'll be able to disclose it as and when we sign it. But we have a very strong visibility. That's why we talked about it.

Aniket Mittal

analyst
#25

Sure. Sure. Understood. And sir, just on the accounting aspect, I wanted to understand, I think there's a change in the fuel cost that's happened because of accounting in terms of, I think, job work that has happened where I think one of your [indiscernible] capital customers would will be giving you a call. Just trying to understand the rationale behind it. I mean, what's happened over here if you could show some light?

Prashant Jain

executive
#26

Pritesh, can you take this question?

Pritesh Vinay

executive
#27

Yes, Aniket, sorry, can you just repeat that question again, please?

Aniket Mittal

analyst
#28

I was just trying to understand more from an accounting perspective. And in the notes I think you have mentioned that one of your customers is now supplying new coal and hence the fuel cost as well as the revenue seems a bit deflated. So if you could just understand why this is happening?

Pritesh Vinay

executive
#29

Yes. So what has happened is that some of our group captive consumers have changed to a job work model from a GST efficiency point of view. What happens is that, for example, when we, as power generators procure coal, we have to pay GST on that. But power -- by itself the sale of power does not attract GST. So there is no way to claim input tax credit on the GST that was paid on the coal purchase by the procurer of power, right? So from a GST efficiency point of view, if they procure the coal on their own, and then their end product is a product on which GST is applicable, they get to claim the input tax credit for the GST that they pay. So it is purely a GST efficiency route because anyways, as far as JSW Energy is concerned, there is no change to the economics because the fuel cost anyways under the 2-part tariff is a complete pass-through. So it is just that instead of we incurring the fuel cost and then passing it on, they will directly be incurring the fuel cost on their own and be able to claim GST input tax credits. That is the rationale for job work model.

Aniket Mittal

analyst
#30

Okay. Sure. And maybe one more question. If you could just help me understand Kutehr. I believe there are certain amount of awards that we've done in the last quarter or so. And the PPA by itself is something that's yet to be finalized. If you can just throw some light what sort of CapEx are you expecting on Kutehr? And when do we see the PPA actually getting finalized?

Prashant Jain

executive
#31

So the source approval has already happened and then PPA will be signed in the current financial year. So it is under process of the signing at this point of time. The total project cost is INR 2,750 crores. And we are expecting that the project will be commissioned by September 2024.

Operator

operator
#32

The next question is from the line of Murtuza Arsiwalla from Kotak Securities.

Murtuza Arsiwalla

analyst
#33

Just a question on this job.

Operator

operator
#34

Sorry to interrupt. Sir, I would request you to please speak a little louder?

Murtuza Arsiwalla

analyst
#35

Is it better now?

Operator

operator
#36

Yes, sir.

Murtuza Arsiwalla

analyst
#37

Okay. Just wanted to get a sense on this job work, could you help us quantify the impact of it simply computing the realization and fuel cost? If you could help us assess the impact of this job work, the quantum of power that went through the job work or the quantum of fuel cost that would have been there, that's not there?

Prashant Jain

executive
#38

So I'll tell you, Murtaza, how to look at it because this has been implemented from the Ratnagiri plant. So obviously, on the fuel cost, we do not break up the fuel cost station wise. You'll be able to derive that. But the amount of power we can quantify, it was just north of 600 million units. So 600 million units multiplied by the fuel cost of the Ratnagiri station, that is the impact of the job work, which goes away both from the revenue as well as from the fuel cost. So EBITDA neutral.

Operator

operator
#39

The next question is from the line of Sujit Jain from ASK Investment Managers.

Unknown Analyst

analyst
#40

As usual, complements on a good set of numbers. I think now your performance compared to other players in the industry has always been commendable. My question is quickly on what is the cash sales that we have? What is the total CapEx that we plan to on these 3, which is, like you said, Kutehr, then the auction that is won in SECI as well as Ind-Barath? And of which, what will be the equity portion?

Prashant Jain

executive
#41

So as I outlined, that the SECI 9 is around INR 4,700 crores to INR 4,800 crores, which will be done 70:30 and Kutehr is INR 2,750 crore, which will be done 67:33, debt-to-equity. So that's how we are planning to do that. And Ind-Barath, what we have talked about that the total project cost was around INR 2,500 crores to -- INR 2,500 crores, and which we were planning to fund by 25% to equity and 75% debt. But at this point of time, the time line-wise, we are not sure that what will be the time line. So we would like to look at the time line as and when the -- it crystallizes. But the other 2 projects, we are having a clarity on time lines.

Unknown Analyst

analyst
#42

Sure. So the total equity, like you just mentioned is about INR 3,000 crores? And I take a time line up to FY '25?

Prashant Jain

executive
#43

Yes.

Unknown Analyst

analyst
#44

And what is the current cash balance?

Prashant Jain

executive
#45

It was about INR 811 crores at the end of September.

Unknown Analyst

analyst
#46

Okay. And you're generating close to INR 2,000 crores of almost free cash flows now for every year? I mean, minus the CapEx that is planned up to FY '25, these 3 projects. So over next 4 years, INR 8,000 crores will be generated, you already have INR 800 crores to close to INR 9,000 crores against which the equity requirement is INR 3,000 crores. The debt-to-equity level is very manageable, as you've just mentioned, and it will remain manageable even after executing these 3 projects, assuming you don't take on anything else. Then in that case, what is your thought process about payouts? You have, in the past, given INR 1 dividend payouts of INR 170 crores, INR 180 odd crores. But now as we can see, the cash flow generation is among us. And against that, the planned CapEx is almost 1/3 of that.

Prashant Jain

executive
#47

So as I mentioned is that we are aspiring to be a 10 gigawatt company in the next 5 years' time frame. That means we are going to undertake number of other projects in order to grow our balance sheet. And also, I mentioned that our deleveraging cycle has been seeing the bottom. So we will be leveling up the balance sheet. We continue to follow a dividend distribution policy wherein we have been making a payout of 20% of the retained profit every year. And so Board always takes a call in case there is a -- there are the opportunities, then we try to deploy the cash for the growth opportunity. Otherwise, we can try and increase the payoff also. So Board evaluates time to time. They have been the time where the payoff has been more than 20%. And -- but the way I see it is that there may be the chances of aggressive growth opportunities in time to come because we are seeing the rationalities coming in the competitive environment and renewable space. And we have built enough capabilities, and we are undertaking these projects. And so we see that we will be able to achieve a growth of another 5 gigawatt in next 5-year time frame.

Unknown Analyst

analyst
#48

Yes. And I also had a question on our holding on JSW Steel shares. What is the costing of the share, which on FY '20 is about INR 1,000 crores holding? What is the current fair value holding that is sitting on the balance sheet?

Prashant Jain

executive
#49

So we have close to 7 crore shares. So at the current market price, it will be north of INR 2,200 crores. And so that's the position.

Unknown Analyst

analyst
#50

Yes. So I mean, is there a thought process of liquidating this and using this cash either for your own CapEx or giving it back to shareholders? We have had our IPO in 2010 at INR 100. The stock has barely in that price in these 10 years higher than that. And even today, it substantially remains below that. We've had an impeccable track record in terms of execution and running a tight ship. But when it comes through distribution, I think there, we need to probably look into more.

Prashant Jain

executive
#51

Certainly, I take your point, and we will deliberate at the Board as and when an opportunity comes. And also at the same time, close to about, correct me if I'm wrong, 44% of promoter shareholding remains less. Of course, less is not a problem. The place is getting released of late. But that is crust of the problem where in terms of return to shareholders, it's probably -- there is some thought, I think that you guys should give into.

Pritesh Vinay

executive
#52

So Sujit, if I may come in here, we are actually representing the entity days of the energy limited. It will not be appropriate for us to comment on the holding structure at the promoter entity level because that is a completely different team, which is responsible for that. However, having said that, what we have -- can talk about as this, and this is also evident from the public disclosures in terms of stock exchange filings that there has been a change in the structure of the financing mode. And therefore, if you look at the period October to December 2019, there was a significant reduction in pledges that happened because of the change in the financing structure at the promoter entity level. But beyond that, we would not really have visibility on that side.

Operator

operator
#53

Thank you. The next question is from the line of Abhishek Puri from Axis Capital.

Abhishek Puri

analyst
#54

Just one point here. I mean, when I look at the other comprehensive income, there is a INR 634 crore profit from items not classified in P&L. Can you elaborate what is that?

Prashant Jain

executive
#55

That is, Abishek, basically because of the movement in JSW Steel shares, so the MTM impact on the OCI, yes.

Abhishek Puri

analyst
#56

Okay. Got it. And secondly, I just want to understand the availability of any short-term contracts or tie-ups that we have done for Vijayanagar and Ratnagiri? And any ramp-up plans that are available now in -- for JSW Ispat where we will be signing the contracts?

Prashant Jain

executive
#57

So look at it this way that as far as the merchant market remains very benign. And the tariffs are not at all viable. However, in terms of the increase in the long-term PPA portfolio from 81%, we see 2, 3 events, which will be crystallizing it. One is the increase in the capacity by JSW Steel at Dolby, which we are expecting by end of this financial year will get completed. So that will happen. Also, like, for example, acquisition by Asian Color by JSW Steel will be increasing the PPA portfolio by another 14 megawatt. And so there is a plan by JSW Steel to increase the capacity at Vijayanagar at some point of time in medium-term. As and when that happens, then that will be also improving the long-term PPA portfolio. Another opportunity is the 5,000 megawatt RTC blended tender along with renewable energy, which the new guidelines have been issued 2 days ago. So we are expecting by end of this current financial year the tender should be concluded. So that is another possibility to increase the long-term PPA portfolio. Other than that, in the spot merchant market, the current environment is quite challenging. For the -- at least for the current financial year, I don't see an improvement in the trend in the merchant prices. Yes, going forward, next year, probably there will be the improvement in the merchant prices. And therefore, we can see that the merchant volume may pick up next financial year.

Abhishek Puri

analyst
#58

I think that's helpful. Just one point here. In terms of Telangana, we had a short term contract. Have you booked any revenues or volumes to them or that is expired now?

Prashant Jain

executive
#59

That is expired.

Abhishek Puri

analyst
#60

And there was a compensation which was required from the previous quarters because they picked up lesser than the contracted value?

Prashant Jain

executive
#61

So that's under discussion, and we are confident that we will be getting that. And as a prudent practice, we have not recognized in our incoming statement so far. But we are quite confident that we will be getting that.

Operator

operator
#62

Thank you. The next question is from the line of Anuj Upadhyay from Emkay Global Financial Services.

Anuj Upadhyay

analyst
#63

Sir, need one clarification. A few days back, there was a media article which mentioned that the company is trying to set up almost 14 gigawatt of renewable capacity in and around Karnataka and Tamil Nadu. You mentioned about this 810 megawatts to be set up against in Tamil Nadu. So are we in -- or in advanced stage of discussions with Karnataka to set up another 500, 600-megawatt of capacity?

Prashant Jain

executive
#64

Look at this way that we have been talking about that we are building a long-term portfolio of the renewable resources. And when we talk about resources means that we have to acquire particular locations where we can either set up the solar parks or wind turbines. And so we are building that portfolio in various states. And that's -- that becomes handy with us as and when we are bidding with SECI or we are also evaluating the group captive opportunities because JSW Group is a large power consumer. Within the group also, the total power consumption is in the region of 2,300 megawatts. Based on the various RPO obligations, the JSW Group itself will be requiring close to 1,000 to 1,200 megawatt of the renewable power in time to come. So that is also another opportunity. In addition to that, there is a big portfolio we want to build. If you look at historically, the way the renewable business was being done, the wind turbine OEM manufacturers, they used to build the portfolio of the sites where there is a potential to install the builder lines. And they used to supply on an EPC basis to the investors who were working primarily as the financial investors whereas the JSW Energy approach has been that we have been doing a very efficient project execution and at a very low cost, low capital cost. Therefore, JSW Energy has been acquiring such potential sites, both for solar as well as wind for past 12 to 18 months time frame. And we have built quite a bit of portfolio. Thereby, as and when we made a bid, we will be able to execute those projects well in time at a very low cost. So there are various locations, which we are trying to identify and build in various states, including Karnataka.

Anuj Upadhyay

analyst
#65

Right, sir. One small clarification, sir, on the thing you said just now. Even Vijayanagar was trying to park some part of its untied capacity at a group level. So in spite of meeting that RPO obligation, which you mentioned through the upcoming renewable capacity, would still there be some kind of room to park our Vijayanagar capacities out there? Or more or less, it would be now replaced by the renewable capacities going ahead?

Prashant Jain

executive
#66

Both are independent and mutually exclusive because RPO obligation is you have to meet that obligation. And second part is that if you are trying to replace some of your capacity by replacing the thermal power with renewable power, both are mutually exclusive requirements. So -- and what I mentioned about the group captive point of view for the RPO obligation that is a regulatory requirement. And building a portfolio is -- can be used for any purpose, either for the SECI tender or any other distribution company or within the group.

Anuj Upadhyay

analyst
#67

Fair point, sir. Lastly, sir, on the recent challenges, which we have seen in the wind sector as such. Last year, we have seen -- I mean, year-to-date, if we say, past 12 months, there has been almost 35% to 40% reduction in the wind power generation. And the developers are citing the reason because of the change in some geographical conditions and that's across the country, which are now leading to a very low level of PLF across the wind station. So I mean, basically, sir, how we plan to counter such kind of challenges? Is the size itself would be sufficient enough, which we are eyeing to meet these challenges? Or there could be some technology upgradation or advancement which we'll be using to tackle the situation? Because both -- I mean, as per our discussion with few of the industry players, solar generally is a more -- I mean, less volatile compared to wind. And we have now ventured into a renewable and that too in a huge margin for the wind place? So that's why there was some curiosity to ask this question.

Prashant Jain

executive
#68

I want to clarify one part is the variation is happening for the developers who are working on a P50 and P75 CUF.But if you are working on a P90 CUF, there is no variation. So we are very, very prudent and conservative in our approach. As and when then we are looking at any wind or solar resources, we are looking at the resources -- or the -- by resources, I mean, the location, where there is a sufficient data is available with the multiple wind mark or further solar radiation. And for both solar as well as wind, we are always taking P90 CUF, not P50 or P75. Therefore, we do not expect any kind of negative surprises in any of the year, both for wind and solar.

Operator

operator
#69

The next question is from the line of Aniket Mittal from Motilal Oswal Financial Services.

Aniket Mittal

analyst
#70

Sir, just one question on the receivables front. You've done, I would say, decile on controlling the price in receivables. So if you could just throw some color as to -- from the state perspective, where are we getting this money from? And how do we plan -- or how do you see ending the full year with?

Prashant Jain

executive
#71

So one is that there is a seasonality in our billing cycle because if you look at that quarter 1 and quarter 2 because of our hydro, the seasonality picture also come in. And -- but if you -- if I can say that, that the current financial year and the last financial year was very, very challenging for the industry as a whole. And -- but during this pandemic time, the overall risk -- overdue situation for the industry per se has deteriorated substantially wherein as compared to the last year, where the total overdue for the sector was in the range of INR 70,000 crores to INR 80,000 in September 2019. And as of now, it is around INR 140,000 crore, our receivables have come down, which demonstrate the quality of our PPA as well as the kind of power mix, which we are having. So that is what -- we believe that in the worst of the cycle, we could reduce our receivables because we are in the bottom quartile of the purchase basket for the respective discounts. And therefore, we have been able to do it in a very, very efficient way. Going forward, we see this trajectory to continue because the incremental PPAs, which we are doing or the capacity which we are building, that is in renewable state. That is also a very low-cost power. And therefore, we are very, very confident that this trajectory will continue.

Aniket Mittal

analyst
#72

Okay. Sir, the current receivable amount, how much of this would be overdue?

Operator

operator
#73

Thank you for patiently waiting. We have the management reconnected. The next question is from the line of Sarvesh Gupta from Maximal Capital.

Sarvesh Gupta

analyst
#74

If you can give some color on the profile of your cost of debt and is it coming down? And what is the sort of expectation going forward? So that is my first question. And secondly, you commented that on the 810-megawatt project, you would be targeting mid-teen sort of IRR. So these are like 15% sort of project IRR pretax is what you are saying? And is that the number that should be the base case for the remaining part of the 5 gigawatt, 6 gigawatt growth that you are targeting over the 3, 4 years as well?

Prashant Jain

executive
#75

Yes. Typically, we look at that kind of a hurdle rate whenever we are undertaking the projects. And -- but historically, we have been doing better than that. If you look at even the -- our free cash flow yield on our existing entire portfolio -- because sometimes I have been observing also, people have been calculating our return on net worth straight away by dividing the profit after tax with the net worth and calculating the return on net worth, but they do not look at that our -- in spite of the network with the lot of component, which is INR 2,200 crores is coming from the steel shares and JPVL shares, which are not part of our profit after tax. If you calculate for next 20 years, which is the life of our balanced PPN, FCF yield, it will be north of 16%, 17% on our entire consolidated balance sheet. That means whatever projects we have undertaken so far in our 4.5 gigawatt capacity, we have been earning more than 16%, 17% equity IRR. And that's how we look at it. And then whatever we will be building the projects for another 5, 6 gigawatts, the hurdle rate will be close to 15% rate. And -- but all in all, we will be doing better than that because of our prudent O&M practices. And also our healthier balance sheet, we have been doing in a lot of financial engineering. And that's what is reflected in our cost of capital also. If you look at our cost -- average cost of debt today is 8.33%, which we see will be -- there is a further scope to have a downward trajectory and in spite of a challenging business environment for a power sector in India. So going forward, with the reliability space, there will be a lot of opportunities to tap different kind of a capital market globally because for thermal projects, there is limited avenues to source capital. And for renewable space such limitations are not there. Therefore, given our track record and also our balance sheet, we believe we will be able to do that. Also, it will be mindful to note that a lot of incremental improvement in our equity IRR has been coming from our past track record of very low operations and maintenance costs, which has been coming down year-on-year in spite of the wage inflation. So that's how we look at it.

Pritesh Vinay

executive
#76

And Sarvesh, if I may add to what Prashant mentioned on the weighted average cost of debt. To put things into perspective, at the end of March, this was 9.1% plus. So almost 80 basis point reduction on the overall portfolio has already played out in the last 6 months. So while we do expect a few more resets on some of the portfolios going forward, so some modest increase is still possible going forward, yes. But I just wanted to put it in the right context.

Sarvesh Gupta

analyst
#77

Just one clarification. The 16%, 17% FCFE number that you were quoting, was that pretax or post tax?

Prashant Jain

executive
#78

No, post tax. And if you take the NPV for the balance 50 -- 18, 19 years, FCFE also, on the network you will be coming out with similar kind of a number. So that's what also you should, see then the typical ROE calculation what you do. And if you really do in a like-to-like basis or an operating income basis, then you should eliminate shares which is owned by the company, which is a part of the net of close to INR 2,200 crores, INR 2,300 crores. If you eliminate that, then that will be further going up by another 2%, 3%.

Operator

operator
#79

Thank you. As there are no further questions, on behalf of JSW Energy and Axis Capital Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.

Prashant Jain

executive
#80

Thank you.

Pritesh Vinay

executive
#81

Thank you, Aisha.

Operator

operator
#82

Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 248,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.