JSW Energy Limited (533148) Earnings Call Transcript & Summary

January 23, 2026

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 54 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the JSW Energy Q3 FY26 Earnings Conference Call, brought to you by Investec Capital Services. Just a reminder that every participant line will stay in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. <<operator_script>> Kindly be aware that this conference is being recorded. At this point I'll turn the conference over to Mr. Anuj Upadhyay of Investec Capital Services. Thank you, and the floor is yours, sir.

Anuj Upadhyay

analyst
#2

Good evening, everyone. Speaking for Investec Capital, I'd like to welcome all of you to this conference call for JSW Energy, where we'll be going over the Q3 FY26 results. Joining us is the company's leadership team, headed by Mr. Sharad Mahendra, Joint MD and CEO; Mr. Chandrasekaran Prabhakaran, CFO; and Mr. Bikash Chowdhury, Head IR and ARM. With that said, I'll now turn the call over to Mr. Sharad, sir, so he can give his opening remarks and carry things forward. Over to you, sir.

Sharad Mahendra

executive
#3

Thanks, Anuj. Good evening, everyone, and thanks for being with us today on JSW Energy's Quarter 3 FY26 Earnings Call. Before we get into discussing the results, I'd like to wish all of you and your families a very happy new year. I'm also very pleased to welcome our CFO, Chandrasekaran Prabhakaran, who came on board with us at the start of January from JSW Steel. Prabhakaran carries more than 25 years of rich and varied experience in corporate finance, accounting and governance, built through senior leadership positions at large listed conglomerates. He has been part of the JSW Group since November 2014 and most recently held the role of Deputy Chief Financial Officer at JSW Steel Limited. His appointment also shows the group's strong focus on leadership development and internal succession planning. Prabhakaran will work closely alongside me as we carry on our journey of strengthening the company and lifting it to new heights together. Power demand growth in the third quarter of this fiscal has been flattish, mainly because of an unusually long and intense monsoon season along with cooler temperatures, which cut the need for cooling and irrigation sub power demand, resulting in muted overall growth.

Sharad Mahendra

executive
#4

Even so, we genuinely hold the view that demand growth over the long run is firmly intact, and that the present softness is mostly a phenomenon tied to weather. On an encouraging note, power demand growth in December ’25 came in strong at 6.5% year-on-year, powered mainly by vigorous industrial activity. For the first 20 days of January as well, power demand growth is strong at 6%. Across the year-to-date period through December ’25, overall power demand growth registered a modest 0.5% year-on-year. One more notable trend last quarter was the December peak demand of 241 gigawatt, an all-time high, which likewise stood as the peak power demand for that quarter. By comparison, peak power demand in the same quarter of the prior fiscal was far lower, at 224 gigawatt. That highlights the fundamental strength of power demand once weather conditions return to normal, underscoring continued structural growth notwithstanding near-term volatility. Viewed from the power sector angle, bidding momentum over the year has been mixed, mirroring a clear shift in where the sector’s priorities lie. There is widening recognition of the need for reliable and firm power, with thermal capacity increasingly coming to the fore. On the thermal side, bids from various states totaled 12.8 gigawatt across the first 9 months of the current fiscal, underscoring renewed appetite for dependable base load capacity.

Sharad Mahendra

executive
#5

On the other hand, renewable <<inaudible>> has eased, with just 10.4 gigawatt during the first 9 months of this fiscal. Also, storage bids totaling 7.6 gigawatt were seen across the first 9 months, versus 1.6 gigawatt of storage bidding in the same period of FY ’25. In addition, during the fiscal's first 9 months, an estimated 10 to 12 gigawatt of renewable generation PPA was signed. Taken together, the bidding landscape shows a clear shift away from plain vanilla renewable energy toward a better-balanced mix of thermal storage and firm power solutions, in line with what grid stability and energy security will require going forward. Even with this wider slowdown in bidding activity, our growth pipeline stays firmly intact. We have already secured roughly 18.7 gigawatts of incremental generation capacity and 29.6 gigawatt hour of storage, which will push our installed capacity past our stated target of 30 gigawatt in generation, and we are confident of reaching our 40 gigawatt hour in storage by 2030. In the quarter, the merchant power market stayed soft, with day-ahead prices on exchanges falling on both a sequential and a year-on-year basis. Even so, our merchant realization came in at a 20% premium to average exchange prices for the quarter.

Sharad Mahendra

executive
#6

Strategic tying up of multiple back-to-back short-term contracts made this possible. Also, it is encouraging to see merchant tariffs improve by roughly 30% during the first 21 days of January versus the average tariffs in the prior quarter. Even with the subdued merchant market environment last quarter, the effect on our business has — has stayed limited. Such resilience mirrors the proactive derisking steps we have taken over time, such as prudent portfolio diversification and a disciplined contracting strategy. At present, our open capacity is roughly 8%, and it will drop further to around 5% starting 1st of April 2026 after securing a 400-megawatt 25-year power purchase agreement for our Utkal plant in Odisha with Karnataka DISCOMs. In addition, we have signed a 115-megawatt short-term power purchase agreement from our Utkal plant with Assam DISCOM for 2 years, which further lowers our exposure to merchant markets. With this, almost more than 95% of our total plant capacity will be tied up in long term. Consequently, our portfolio keeps delivering stable and healthy returns, highlighting the strength, resilience and flexibility of our business model even in a challenging market environment. Now I would like to share the key highlights of our performance this quarter, during which we have made meaningful progress across several fronts.

Sharad Mahendra

executive
#7

Power sales for us posted robust growth of 65% year on year in quarter 3 of the current year, climbing to 11.1 billion units this quarter from 6.8 billion units a year earlier. Net generation for the 9-month period ended FY26 was up 62%, going from 24.4 billion units to 39.6 billion. It's worth noting that long-term PPAs made up 82% of total power sales and posted a 63% year-on-year rise in quarter 3, backed by our disciplined and robust portfolio derisking strategy. Looking at it mode-wise, we saw improvement across every sector. Our solar and wind portfolio next generation climbed 149% year on year, led by organic capacity additions and contributions from O2 Power. Thermal generation was up 55% year on year, mainly driven by contributions from KSK and capacity additions at our Utkal plant. Hydro generation, moreover, grew 27% year on year against a national average increase of 13% during the quarter, helped by improved hydrology and the contribution from our new Kutehr plant in Himachal. Let me reiterate that our quarterly power sales growth of 65% year on year stands out against the broader industry backdrop, which saw demand degrowth of 0.1% year on year in quarter 3. Over the past 12 months, we added 5.2 gigawatt of capacity — 3.1 gigawatt of renewable and 2.1 gigawatt of thermal — and that has been a key driver of our year-on-year EBITDA growth.

Sharad Mahendra

executive
#8

This expansion takes in inorganic capacity additions of 1.5 gigawatts in renewables and 1.8 gigawatt in thermal, which further strengthens both the scale and the resilience of our portfolio. Over the quarter, we brought on 125 megawatts of new renewable capacity, hybrid projects included, which lifted our total installed capacity to 13.3 gigawatts. That capacity addition works out to significant year-on-year growth of roughly 64%, compared with 8.1 gigawatt in the same period last year. Building on that robustness, we have been equally deliberate about shaping the quality of our capacity mix. On the capacity side, about 3.3 gigawatt — roughly 25% of the installed capacity we hold today — is secured with high-quality group captive and C&I customers. As we scale beyond 30 gigawatt, we expect that figure to rise further, to approximately 5.7 gigawatt. Importantly, these capacities are contracted at highly remunerative tariffs, with renewable tie-up at a higher blended average tariff of over INR3.65 per unit. Turning to our recent capacity additions. I’m pleased to share that the Kutehr plant has now fully stabilized and generated about 130 million units during the quarter. We have also continued to remain at the forefront of innovation. During the quarter, we successfully commissioned India’s largest green hydrogen plant at our Vijayanagar location, with a capacity of 3,800 tonnes of green hydrogen per annum, marking a significant milestone in the group’s decarbonization journey.

Sharad Mahendra

executive
#9

A lot of you might have gotten the chance to tour this facility when we held the green hydrogen plant visit earlier this month, and to witness for yourselves the headway we are making in this emerging area. I'm happy to report that, reflecting both our strong green emphasis and our long-term dedication to carbon neutrality, our growing renewable portfolio allowed us to avoid roughly 14 million to 15 million tonnes of CO2 emissions during the first 9 months of this fiscal year, calculated using the prevailing Indian grid emission factor. A further significant milestone in the quarter was the preferential allotment of equity shares to the promoter group, which brought a capital infusion of INR3,000 crores — consisting of INR500 crores via equity and INR2,500 crores via warrants, and those warrants will convert into equity within the next 18 months or sooner. What's more, in line with last year, shareholders have also approved a potential issuance of as much as INR10,000 crores via a qualified institutional placement. Turning to inorganic growth, the acquisitions we announced in the prior quarter — Tidong Hydro Power and GE Power India's boiler Manufacturing division — are moving along nicely. We anticipate closing the Tidong Hydropower transaction before this month ends, that is by 31st January.

Sharad Mahendra

executive
#10

On GE Power as well, we've now gotten the NCLT approval — that process is at the NCLT approval stage for the resolution plan our company submitted for Raigarh Champa Railway, which is the rail infrastructure at the KSK plant. I'm also glad to report a few significant strategic developments on the thermal side that came after the quarter — after Q3. We've placed an order with Toshiba JSW for 2 ultra-supercritical turbine generators, 800 megawatts apiece, for our Salboni thermal plant in West Bengal. That turbine generator package is going to be built and delivered in step with the project's construction schedule, which lets the plant be finished and commissioned on time. By procuring this critical equipment via our associate company, we're reinforcing supply chain certainty, getting better coordination through execution, and reducing risks that come from equipment constraints across the industry. This contract is a strategic move toward greater supply chain control and assured execution for the Salboni project. Also at the Salboni site, I'm happy to announce that we signed our second 1,600-megawatt PPA with the West Bengal DISCOM for a second thermal power plant there, bringing our total capacity at that location to 3,200 megawatts. That makes Salboni our biggest single-location asset. The project gains from being strategically close to the coal box and from synergies with the existing 1,600-megawatt unit that is under construction, which drives meaningful operational efficiencies.

Sharad Mahendra

executive
#11

So with that, our secured thermal capacity now sits at 10.7 gigawatts, and total locked-in capacity comes to 32.1 gigawatts—giving us plenty of visibility toward our ambitious 2030 goal of 30 gigawatt. Now turning to the financial performance, which I'm sure most of you have already had a chance to review. Third-quarter revenue rose 61% year-on-year to roughly INR4,255 crores, tracking the strong growth in capacity and generation. Alongside that, EBITDA for the quarter climbed 98% year-on-year to INR2,202 crores. As newer assets kept getting capitalized on the balance sheet, interest and depreciation were correspondingly higher. Depreciation more than doubled, while interest cost surged by nearly 2.6x year-on-year in quarter 3. The company has recognized a deferred tax asset, and as a result, profit after tax is up 150% to INR420 crores for the quarter. Even more significantly, our cash profits rose 12% year-on-year to approximately INR570 crores during the quarter. On the deferred tax front, our JSW Energy Utkal has signed a 25-year power purchase agreement with Karnataka DISCOM for supplying 400 megawatts of power, starting 1st April 2026. Given the reasonable certainty of sufficient future taxable profits from this PPA, the company has recognized a deferred tax assessment of INR557 crores on carried forward business losses and unabsorbed depreciation.

Sharad Mahendra

executive
#12

Also on our KSK asset, we recognized a deferred tax amount of INR189 crores this quarter, tied to carried-forward business losses and unabsorbed depreciation. In addition to that, keeping in step with the labor code changes announced recently, we've taken a conservative approach. We've provided INR65 crores for this, and it's one-off in nature. Moving to leverage. Net debt finished the quarter at INR63,771 crores, compared with INR61,960 crores as of September 30th September ’25. If you exclude capital work in progress, the pro forma leverage ratio comes to roughly 4.9x. Net leverage should decline once we fully receive the proceeds from the preferential allotment that was recently completed. Beyond that, liquidity is still strong, backed by cash and cash equivalents exceeding INR7,100 crores. On cost of debt, as we guided earlier and consistent with the recent rate cuts, we keep seeing a sustained decline in the weighted average interest rate. In the quarter, our cost of debt fell by roughly 11 basis points quarter-on-quarter, from 8.79% to 8.68%. We expect that downward interest cost trend to persist as and when our bank loans go through their interest resets.

Sharad Mahendra

executive
#13

After adjusting for our investment in JSW Steel shares, cash return on net worth stayed strong at roughly 19% to 20%. Slide #14 is the one to look at for this. And then on receivables, total receivables as of the end of December came in at about INR3,000 crores, which works out to debtor days of 73 days — a sharp drop compared with the 96 days we saw in the same quarter of last fiscal year. The main point here is that the substantial capacity additions we have made so far are now starting to show up in higher energy generation as well as cash flows, and we expect that momentum to keep improving from here. That wraps up my opening remarks, and we can now open the floor for Q&A.

Operator

operator
#14

Our first question is from Sumit Kishore with Axis Capital.

Sumit Kishore

analyst
#15

To start off, I have a question about the Salboni project. Can you lay out for us what the PPA terms look like for those four units of 1,500 megawatt each, and then also for the 1,600 megawatt EPA you'll be signing afterward with West Bengal? For this mega project, how is the CapEx expected to be phased? And in what way do you — how do you plan to phase the commissioning of the units? That's my first question.

Sharad Mahendra

executive
#16

Look, on the PPA timelines — first of all, Sumit, thanks so much. The PPA timelines run from the notice to proceed date. I believe that date is 48 months for the first unit, or first phase, and then the second unit comes another 6 months later, so 54 months. So all of the planning sits within those same timelines. We will definitely finish Phase 1 inside the PPA timelines that exist. We're sure of that because our supply chain for boiler, turbine and generator — which is a challenge the country is seeing, as I also said in my remarks — is all under control. So that's what we wanted to show. And on CapEx, we will be announcing, but yes, you can benchmark what we've said in the domain — maybe Phase 1 is about INR16,000 crores of investment for 2 into 800, which we announced earlier, so we'll be around that number only.

Sumit Kishore

analyst
#17

All right, so how would the tariff structure work in this case — what's fixed versus variable, and what does that look like in detail?

Sharad Mahendra

executive
#18

So there are two initial bids here. The tariff sits in the INR3.65 range, which we've already made public. Then the second one is INR4.06. That's a fixed charge alone. INR3.6 applies to Phase 1, and INR4.06 applies to Phase 2. Fuel gets passed through.

Sumit Kishore

analyst
#19

At what heat rate does fuel get passed through?

Sharad Mahendra

executive
#20

We will give you those details, but that follows the guideline that's in place, which is a 2350 heat rate.

Bikash Chowdhury

executive
#21

Sumit, Bikash speaking. We'd be glad to get in touch with you about this — if you'd like a detailed walkthrough, we can provide a detailed presentation, and we'll be able to connect with you.

Sumit Kishore

analyst
#22

Bikash, my second question concerns — if I remember correctly, you had aimed to commission roughly 1.5 gigawatt during the second half of the year. The wider question is this: with grid constraints in play for this financial year, on an organic basis, how much RE capacity would you be able to close the year with? Then for the next financial year, you have a fairly sizable under-construction portfolio. So with grid constraints and other challenges, what is achievable in FY ’27 on an organic basis? And to finish off this question, there’s also a big ramp-up in CapEx that we expect to see in the coming financial year. So broadly, on an organic basis, how are you thinking about your CapEx this year and the next financial year?

Sharad Mahendra

executive
#23

Yes. Look, Sumit, first point: as we mentioned before, you’re right that 1.5 gigawatt of new capacity is being added in H2 of this fiscal year, and of that, 125 megawatt was commissioned by us in quarter 3. So we’re very much on track. And in the quarter we’re in now, the capacity additions that will happen — we will hit the guidance we provided for 1.5 gigawatt in the second half of this fiscal. And for that, grid connectivity and land, all of it — these projects are at an advanced stage. Second, for next year, whatever plans we have, we will definitely share the numbers at a later point. We’re in the middle of finalizing our plans for next year, but naturally, keeping in mind connectivity availability and land — as I’ve said for a good while now, we are fully insulated for the next 1 year to 2 years from the connectivity challenge. The reason is the 2 steps we took have secured us against this uncertainty the country is facing: one, most of our projects coming in the next 2 years are STU rather than ISPS interstate. Our intrastate and STU connectivity is available. And two, the O2 acquisition — all capacities that are going to come under it, 100% of the connectivity is available with us for the whole thing to reach the capacity of 4.7 gigawatt.

Sharad Mahendra

executive
#24

And on top of that, we still need to handle — there’s extra capacity connectivity available beyond 4.7 in O2 as well. So those are the elements that give us pretty much certainty we won’t run into any challenge on those fronts. As for the CapEx figures, once we finalize our plan for next year, which we’ll be doing soon, we’ll definitely make the announcement at the right time.

Sumit Kishore

analyst
#25

To wrap that up, regarding what you have there — roughly <<inaudible>>.

Operator

operator
#26

Sir, we can’t hear you. Sumit, could you please ask your question again?

Sumit Kishore

analyst
#27

So with the connectivity hurdles we're facing, could that be commissioned around the end of FY '28, roughly?

Sharad Mahendra

executive
#28

Yeah, look, regarding FY ’27 and FY ’28 — pretty much whatever plans we’ve got in place for hitting that 30 gigawatt target by 2030, we’re on track. And through FY ’28, we also have full clarity on connectivity, and we’ll be commissioning in line with the PPA, because for most of our capacity the PPAs are already signed. So we’re on track to finish everything within the PPA timelines.

Sumit Kishore

analyst
#29

Great. I’ll rejoin the line — thanks, and all the best to everyone.

Operator

operator
#30

The next question comes from Mohit Kumar of ICICI Securities.

Mohit Kumar

analyst
#31

Sir, my first question concerns the PPA you acquired for Utkal with Karnataka. I believe it's 400 megawatts — is the net capacity 400 megawatts, as a first sub-question? And second, could you help with the fixed tariff for that particular PPA?

Sharad Mahendra

executive
#32

All right. So, first, that 400 represents the net capacity. And the tariff here is INR5.8 at my plant bus.

Mohit Kumar

analyst
#33

And what about the fixed tariff on this, sir?

Sharad Mahendra

executive
#34

No, no — this is a fixed tariff of INR5.8. Sure, it can scale, but that INR5.8 tariff is what applies in year 1, and that's what we'll be receiving from Karnataka. It's one single tariff. It's a fixed-plus-variable, fixed, single-tariff bidding arrangement, which is what's in place.

Mohit Kumar

analyst
#35

That's 25 years — right?

Sharad Mahendra

executive
#36

Yes.

Mohit Kumar

analyst
#37

Got it, sir. My next question concerns Salboni. You have already placed the order for the turbine generator, of course. But when it comes to the boiler for 3.2 gigawatt, what's the plan there? Will we be awarding it to the GE facility that you acquired, or does that facility only supply the fuel component?

Sharad Mahendra

executive
#38

So, yes — as we said before, the GE boiler manufacturing plant in Durgapur is what we're in the process of acquiring, and we expect that process to wrap up and the plant to be fully ours by June or July of ’26. So those boilers will be built for our captive requirement in Durgapur only, and that facility has a capacity of almost about 1.5 boilers of 800-megawatt — material to manufacture equivalent to 1.5 boilers. And whenever it's needed, we'll expand capacity there as well. So our own requirement will be manufactured from the Durgapur boiler unit only.

Mohit Kumar

analyst
#39

Got it. For my final question, sir: how far along are we in turning our LOA into a PPA? Naturally, we have a solid PPA pipeline, yet a number of the LOAs on the RE side have sat there for a good while now. So what sort of dialogue is going on with the counterparties?

Sharad Mahendra

executive
#40

Right. So look, on the renewable energy side — that's what I'm referring to here — our overall capacity that's logged in stands at 12.6 gigawatts, and that capacity is already under contract, with the PPAs already signed.

Mohit Kumar

analyst
#41

Yes, sir. My question really concerned the LOA pipeline, which has been sitting with us for a fair amount of time.

Sharad Mahendra

executive
#42

Right, so roughly — look, there's overall capacity of about 4.5 gigawatts that still has pending items. A few of those we expect to have signed before long, and the rest we're waiting on, but bearing in mind that between contracted capacity and capacity with PPAs signed, the gap is such that we're 100% certain the 30 gigawatt figure we're citing for 2030, that remains on track.

Bikash Chowdhury

executive
#43

So Mohit, to add to what sir said, with the capacity we have now plus what's under construction, we're at 27.5 gigawatt, right? And the pipeline is 4.5, and the details of that pipeline are there. So you know as well as we do when that pipeline will get converted, right? There's a lot of capacity like this that is pending closure. So as and when they close out, we'll let you know. And we're more than certain that we'll reach 30 gigawatt by 2030.

Operator

operator
#44

We now go to Rajesh Majumdar with 361 Capital for the following question.

Rajesh Majumdar

analyst
#45

Yes. So following up on what was asked earlier, I had a question about the overall size of bidding. You're saying locked-in contracts are fine. But do you expect the total bidding space to shrink, especially in renewables next year, in terms of overall market size? If so, and if we keep our market share roughly where it is, then the additions would be capped at about 2.5 to 3 gigawatts per annum, excluding the locked-in capacity. Is that a fair assumption?

Sharad Mahendra

executive
#46

Yeah, I think — look, we need to recognize there are a couple of challenges, 2 or 3 of them, that we're dealing with. If you look at the current year, the greenfield capacity, as I mentioned, is very low when it comes to the bidding that's happened over the first 9 months. There are unsigned PPAs — roughly 40 gigawatts of bids where PPA signing is still pending — so that's also slowing down fresh bidding. Second, the uncertainty is around connectivities; we're seeing really strong greenfield capacity addition this year in the RE space. But whether those same numbers carry on for the next 2 or 3 years is a challenge, because starting FY '27, we're seeing that securing fresh connectivities will be one of the major bottlenecks out there. So with all these factors together, we definitely see a moderation in the bidding we'd been seeing through last fiscal, and that's likely to continue.

Rajesh Majumdar

analyst
#47

Even so, you're saying that you'll be — your assumptions call for roughly 4 gigawatts of additions each year. So that's still what you think.

Sharad Mahendra

executive
#48

As I mentioned to you, if you look at the operating capacity we have right now, we'll close out the year somewhere around — whatever figure I give, 14.5, 15 gigawatt — and then roughly another 12 to 13 gigawatt of capacity is already committed.

Bikash Chowdhury

executive
#49

And to add as well, this is Salboni — 3,200 megawatts — in 2030 and ’31. So it lands more toward the end; that’s when they’ll come up, correct? So what we’re saying is it isn’t the capacity split by a number of years.

Rajesh Majumdar

analyst
#50

Yes. No, that makes sense to me. Right. Okay, understood. For my second question, sir, regarding KSK Mahanadi, how much does the tariff reduction affect EBITDA each year? And a related point on 3Q: we're seeing stand-alone revenues fall 30% — does that reflect this, or is there another reason?

Sharad Mahendra

executive
#51

No. Look, one factor is the revenue decline — we need to recognize the severe weather there, the reserve shutdowns, and the backdowns ordered by the states, particularly UP in the north, and that has led to lower revenue generation. But we have to recognize that this capacity is tied up. My plant availability is there. So for me, this won't have any meaningful impact on my — on this, we will receive my fixed charges according to plant availability. So that's one point — we are 100% certain that this is not a challenge. You had one more question.

Rajesh Majumdar

analyst
#52

KSK here, on the tariff cut. The reduction in tariffs.

Sharad Mahendra

executive
#53

On the tariff reduction — okay. Of course, going forward in FY ’27, per the PPA terms, one of the discounts brings a tariff reduction of close to about INR1.25, so that will definitely have some impact. But operational efficiencies — as I said earlier, during the year we have been building up a lot of them, and they have come during the year and kept on coming — so that will give us an annualized benefit next year. To some extent, we will definitely be reducing the impact of this tariff reduction from that side. And also the sale of the reserve shutdowns and other things, backdowns from the plants, which we have started. So we are expecting that there will be some impact on the overall EBITDA, but it will be minimal.

Rajesh Majumdar

analyst
#54

How much of the 1,800 total capacity does the tariff reduction affect?

Sharad Mahendra

executive
#55

What capacity are we talking about? That's 1,000 megawatts, and it's tied up with UP.

Rajesh Majumdar

analyst
#56

Okay, sir. And my final question is: when should we expect the initial tranche of capital to come into the company, and also — do you believe that, with the promoter stake coming in, there’s a possibility of an improvement in our debt’s credit rating? Yes. That’s the last question.

Sharad Mahendra

executive
#57

Look, the way I've been putting it is this — you'll likely see it reflected when the December numbers close. We've got enough cash flow and free cash on hand to cover the CapEx we need going forward, along with the funds required. But like I mentioned, once we finalize our capacity addition plans for next year and work out the capital requirement, we already hold the enabling approval to raise funds. If, as the year unfolds, we feel the need, then without question we'll go ahead. For the moment, though, we're in a comfortable position, because the promoter equity infusion piece is already in place, and that gets us where we need to be. And certainly, we expect — as the market itself clearly expects — that having the promoter invest at current levels, at a price above where the stock trades now, counts as a positive for us, something the market is recognizing as well as the agencies.

Bikash Chowdhury

executive
#58

And just to build on the ratings piece — we hold one of the strongest ratings in the sector, at AA. But I do take your point, and we'll bring it to the rating agencies as well and work on an upgrade for our own benefit. Thanks a lot for that suggestion.

Operator

operator
#59

Apoorva Bahadur from IIFL Capital has the next question on the line.

Apoorva Bahadur

analyst
#60

Sir, I had a quick question on the Utkal PPA. You mentioned that it was a single-part bid — a single tariff. I just wanted to understand, if there's a back-down for the plant, how do we get paid? In other words, would the state pay the full INR5.8 tariff, or?

Sharad Mahendra

executive
#61

Right, so like I mentioned, the overall tariff comes to 5 — the precise figure is INR5.78, and within that, INR4.04 is the fixed portion while INR1.74 is the variable cost. And provided the plant availability is maintained according to the PPA, my fixed cost is guaranteed.

Apoorva Bahadur

analyst
#62

Alright, got it, sir. And one more thing regarding Salboni — for Phase 2, the tariff, the fixed tariff, sits roughly INR0.40 above what Phase 1 has.

Sharad Mahendra

executive
#63

Yeah, yeah.

Apoorva Bahadur

analyst
#64

From what I understand, when a plant is bigger, you often have utilities involved — utilities being the shared element — and usually the CapEx per unit, or per megawatt, comes down. So what caused this increase in tariffs, and was the state fine with that?

Sharad Mahendra

executive
#65

Yeah, we have to recognize — look, one thing: the initial phase of my Salboni project was a year ago, when that tariff was discovered, the fixed cost. After that, if you look at all the bids that have taken place, they've taken place even at a higher price. The state is looking at what the total cost is, and this remains one of the lowest tariffs the state is seeing this as 4 into 800. Blended, if you look, it becomes a significantly attractive tariff compared with the almost 12 gigawatt of bidding that has occurred over the last 1 year. In thermal space, this is one of the most attractive tariffs. So the state is absolutely comfortable, and regulatory approval is also in place keeping in mind what has prevailed. We need to know what has happened in other bids in Assam, whether it is Bihar or whether it is MP, you see the states. So this is a very good tariff that has been discovered.

Apoorva Bahadur

analyst
#66

Got it. Sir, I can see from your presentation that the BESS containerization and cell assembly plant is nearly ready to be commissioned. We also have some BESS PPAs that we need to execute. So for those PPAs, will we be importing the cells, then converting and containerizing them at our own facility?

Sharad Mahendra

executive
#67

Correct, that's right. That is precisely what we're doing.

Apoorva Bahadur

analyst
#68

All right, and have the orders for the cells been placed at this point?

Sharad Mahendra

executive
#69

Yes, we've placed orders for some, and materials will begin arriving since the trial production plant has stabilized. We've submitted our product for the required approvals, and we expect those to be in place by the end of March or early April. But in the meantime, we'll start production sometime in February — between February and March.

Apoorva Bahadur

analyst
#70

Sir, could you tell us what portion of cell capacity, or how many cell import orders, you placed?

Sharad Mahendra

executive
#71

I'll give you the precise figure as soon as I can — I'll follow up with you right now. That said, yes, we get it, and we've already run that sensitivity analysis. I can see where this concern about pricing is coming from, given that we're observing prices moving northward. So this trend has been on our radar. And because of that, we took the required actions at the appropriate moment.

Operator

operator
#72

The next question comes from Satyadeep Jain with AMBIT Capital.

Satyadeep Jain

analyst
#73

I just wanted to ask about the contracted capacity for RE within the PPA. Specifically for the PPA, could you provide an update on FDRE 4 and what's going on with it?

Sharad Mahendra

executive
#74

On the battery matter — look, we're awaiting the regulatory approval for the FDRE. The letter has come in. Regulatory approval is what we're waiting on. That's where things stand. We've had no further communication from Rajasthan regarding this.

Satyadeep Jain

analyst
#75

As of right now, we haven't heard anything at all about cancellation or anything along those lines.

Sharad Mahendra

executive
#76

The award has been made — it's inaudible on the recording, but the award is done. We're waiting on the PPA; that has been signed. What we're waiting for now is the regulatory approval. That's it. There's nothing else. The PPA has been signed.

Satyadeep Jain

analyst
#77

That much is clear to me. Still, the FERC approval hasn’t come through yet, has it?

Sharad Mahendra

executive
#78

Correct.

Satyadeep Jain

analyst
#79

I'd also like to get some clarity on NEP. A lot of the government's attention has been going toward the distribution side. From what I understand, that's historically an area where you haven't been focused. So is there anything — are you starting to look at that incrementally at all, or is that simply off-limits for you?

Sharad Mahendra

executive
#80

Nothing is off-limits for us. We absolutely continue to watch for opportunities as the sector—as the segment—keeps evolving. Right now we see plenty of tailwinds in this area too. So in that sense, as we look at the various opportunities we're estimating, we're also observing what's happening in UP, which has come out with privatization. So we're keeping track, but definitely we have to come up with a concrete plan—but there's definitely no "no-go" for us.

Satyadeep Jain

analyst
#81

Just to confirm, you've done the evaluation — the decision will come later, but you've looked at every one of the privatization opportunities?

Sharad Mahendra

executive
#82

Yeah, we're in the middle of that process, because there's also a capital allocation strategy that works efficiently — so that's another piece that factors into how you prioritize and when to pull the plug.

Satyadeep Jain

analyst
#83

Okay. And regarding DSM, I just wanted to — since your portfolio is also very wind-heavy, you've obviously commented on that proposal for DSM as well. I just want to get a sense: the government is also discussing DSM being on par with thermal by 2030. Based on the historical schedule generation you've analyzed for your portfolio, what's the implication of DSM tightening?

Sharad Mahendra

executive
#84

Look, this is something that affects the whole industry, and that needs to be understood. So at the industry level, we've definitely taken this up — and the losses that exist industry-wide because of it are something that pooling and various other options, which, as an industry, we have taken up — and the wind association is also actively working on these DSM settlement mechanism. And loss of resistance, it would be — what we feel is that this loss of resistance would be relaxed, and let's wait for some more time on this. But yes, the industry has raised this with the Ministry.

Operator

operator
#85

Nikhil from UTI Mutual Fund has the next question on the line.

Nikhil Abhyankar

analyst
#86

Yes. I just have a couple of questions. We saw quite a bit of renewable generation curtailed during the quarter, and I wanted to get a sense of how much that affected our financials?

Sharad Mahendra

executive
#87

Look, regarding curtailment — that's something we have to keep in mind, again, since it stems from evacuation constraints, and it's seen mostly in Rajasthan. So here's what's happening: there are 2 kinds of curtailment. The first is against the G&A — in that case I have grid connectivity and curtailment still occurs for grid stability reasons. Financially I'm protected there, because I receive the full cost full — per the tariff, I get that. For a portion of our capacity — a small portion — which was commissioned early and whose connectivity is perhaps a few months ahead, we hold the TG&A, which is a temporary connection. Whenever the grid is under pressure, that temporary grid-connected connection gets curtailed, and there the financial impact shows up. So our share is quite small relative to the large capacity we run. So the impact on us has been negligible so far. And on the positive side, only about a week, 10 days ago, the new evacuation connectivity came online. With that, even curtailment has come down significantly, which has also benefited us from the temporary grid-connected portfolio.

Nikhil Abhyankar

analyst
#88

Got it. And sir, is there also any sense of why the wind PLS has come in lower, since across the industry those figures are somewhat stronger than the 16% we reported?

Sharad Mahendra

executive
#89

Look, the key point is that we need to look at the wind portfolio asset by asset. In fact, our wind PLF has ranked among the best, and it's significantly above where it stood last year. We should keep in mind that a big chunk of the capacity I acquired from Mytrah consists of machines ranging from 850-kilowatt units up to roughly 2 to 2.3 gigawatt — megawatt machines. So the PLFs there are low. Those are low PLFs by design, and all of that was factored in when the acquisition happened, with the valuation carried out accordingly. So when you look at it on a blended basis, our PLF might appear lower on that blended basis, but for all the fresh capacities we are commissioning, it's in line with, or slightly better than, what's there in the country. And going forward, as and when new capacity gets added, with the newer portfolio's share of wind rising within the overall mix, our PLF overall will improve as well.

Nikhil Abhyankar

analyst
#90

Got it. Sir, last question about the thermal bid. I mean, at INR4, I mean, the returns you'll earn are really strong. So is there any sense of how large our thermal portfolio could become, say, 5 or 6 years from now?

Sharad Mahendra

executive
#91

Look, at present, when you look at the thermal portfolio, completing a greenfield project can take perhaps 48 to 54, or 60 months. So what we're seeing right now is that we have 4 into 800 at Salboni, and we're absolutely working on that. Beyond that, at KSK, when we made the acquisition, there's another 300 into 600 of work already underway as one CapEx, because the balance of plant was fully ready and the parts work on the other 3 units was done. So this will add 1.8 gigawatt of capacity at KSK, and it will come at a much lower specific cost and CapEx compared with a greenfield project, and at tariffs, as you rightly said, that are what prevail in the market. So right now, over the next 5 to 6 years, we see Salboni coming in and the KSK addition, and perhaps if another good opportunity exists, we'll be open to it, but it's a process that takes its own time.

Nikhil Abhyankar

analyst
#92

Alright, have we begun capital expenditure on that extra 1.8 gigawatt at KSK?

Sharad Mahendra

executive
#93

Yes, we’ve begun work on the fourth unit, and when we acquired it, 30% to 40% of the work had already been completed. In addition, some of the material that was sitting at the port — which we were able to obtain following the NCLT order — has now been ordered, and enabling work has started. Very soon, the full work will get underway. We expect that in roughly 3 years’ time, we should be in a position to commission it.

Nikhil Abhyankar

analyst
#94

Is that commission for 1 unit or 3 units?

Sharad Mahendra

executive
#95

Both of those units, and after that, every 3 to 6 months, the remaining 2 units as well.

Operator

operator
#96

The next person to ask a question is Atul Tiwari with JPMorgan.

Atul Tiwari

analyst
#97

Sir, my question is about the industry. So you said that during the first 9 months, we've seen roughly 12 gigawatts of thermal bids coming from states. So in your view, how much more could come from the states over the next 1 or 2 years? Are we looking at a similar figure, or higher numbers? And potentially, what share could you capture on the new thermal projects?

Sharad Mahendra

executive
#98

Yes. Once again, this is a question — look, the Government of India has announced 97 gigawatts of capacity addition, with fresh capacity commissioning by 2034 — the ’32 to ’34 period. So in line with that, whatever the pipeline is and the balance, we do see some bids, and fresh bids definitely will be coming. A number of states have already indicated that they are preparing for the bidding. So we expect that giving an exact number will be difficult. But yes, definitely, there will be some fresh bids we expect — at least for the next 1.5 to 2 years, in thermal space, they will be coming. As for us, as I told you, we are absolutely full till 2031, ’32, but yes, any attractive opportunity with sufficient time lines and efficient capital allocation — we will be exploring all the possibilities and decide, because now we are secured from the material supply point of view, supply chain security with the acquisition of the GE boiler plant and placing the Toshiba into — with Toshiba JSW. So we are secured in terms of the suppliers of BTG, which has been a big constraint for the industry. So we will be evaluating the opportunities as and when the future bids come.

Atul Tiwari

analyst
#99

And sir, my second question concerns the consol PBT or PAT figure, leaving out the deferred tax sales. So obviously, your capacity growth has been quite strong, and generation and cash flows are good. But your PBT has been under pressure owing to depreciation and interest costs down in the second quarter, I believe, and this year, it’s a loss. So I mean, how do you think about those dynamics as you further ramp up CapEx and capacity over the next 1, 2 years? I’m asking because it does impact your reported ROEs post depreciation, et cetera. So is that a target in your calculation at all to get the reported ROEs to a 13%, 14%, 15% kind of number, or are you okay to continue at a very suppressed PBT level?

Sharad Mahendra

executive
#100

Yes. I’ll ask Mr. Prabhakaran to respond to your question directly.

Chandrasekaran Prabhakaran

executive
#101

So when you look at loans right now, we're ending up adding capacity. What happens at first is that as capacity gets added, initially — if you look at returns — they tend to be at a lower rate. And on the whole, once interest and all of this begin to come down, that's when you'll basically see returns at the PBT level. So with that in mind, since at first we're in that kind of phase — the execution phase — over the next 2, 3 years we'll have, and this quarter in particular, we'll have a lower PLF anyway, right, in terms of CVF, for both wind and solar. So that one is seasonal. But as and when we kind of stabilize, I think this should kind of even out.

Bikash Chowdhury

executive
#102

And building on what Prabhakaran mentioned, we've got roughly 5.2 gigawatts of capacity, split between wind and hydro, correct? So the third quarter is always a quiet one. That means we really ought to view it on an annual basis rather than focusing on just 1 quarter.

Operator

operator
#103

That's going to be our final question, everyone. At this point, I'd like to pass the conference back to management for some closing remarks. The floor is yours, sir.

Sharad Mahendra

executive
#104

Thanks, everybody, and I appreciate your joining us today. Once more, I want to wish each of you a truly wonderful 2026, and I look forward to seeing all of you again. Many thanks.

Operator

operator
#105

<<operator_signoff>>

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.