JSW Energy Limited (533148) Earnings Call Transcript & Summary
October 17, 2025
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to the JSW Energy 2QFY26 earnings conference call, hosted by Motilal Oswal. Please be advised that every participant line will remain in listen-only mode, and following the conclusion of the presentation there will be a chance for you to pose questions. If you require assistance at any point during this call, kindly signal an operator by pressing star followed by zero on your touch-tone phone. We ask you to note that this conference is being recorded. I will now turn the conference over to Mr. Abhishek Nigam of Motilal Oswal. Thank you, and the floor is yours, sir.
Abhishek Nigam
analystThank you, Sharad. Hi everybody, good evening, and we appreciate all of you being on this JSW Energy 2QFY26 earnings call. Joining us tonight are Mr. Sharad Mahendra, our Joint MD and CEO, Mr. Pritesh Vinay, Director of Finance and CFO, plus Mr. Vikas Choudhury, who leads Strategic Finance and Investor Relations. So, let's not wait any longer — I'll pass things to Mr. Sharad Mahendra to give the opening remarks. The floor is yours, sir.
Sharad Mahendra
executiveYeah. Yeah, good evening, everyone, and thanks for being with us today on JSW Energy's Quarter 2 FY26 earnings call. This second quarter of the fiscal year we're in has represented a pivotal turning point for the power sector. We saw a 1.6% decrease in Quarter 1. We saw a substantial rise in power demand during Quarter 2, which posted 3.3% year-on-year, 449 billion units, and H1 demand up 0.8% on year. That resurgence came from a healthy pickup in industrial activity and better economic sentiment, along with support from a favorable base effect. Notably, this increase occurred despite an increase, sorry, despite a prolonged monsoon, which highlights how resilient India's power sector demand is. Peak demand for the quarter hit 230 gigawatts in August, staying in line with the levels recorded in the same quarter a year earlier. Sorry. India's total installed generation, excuse me, over the last 12 months, 48 gigawatts were added, with 33 gigawatts and 16 gigawatts commissioned in H1 and Quarter 2, respectively. Renewable energy keeps leading this growth, adding 25 gigawatts during the half year, 22 gigawatts from solar, and three gigawatts from wind. On thermal, installed capacity now stands at 245 gigawatts. Given the bidding of 15 gigawatts of projects awarded in FY25 and roughly 35 gigawatts of capacity under construction, all of these capacities will be commissioned over the next five to seven years.
Sharad Mahendra
executiveSo with that, India's overall thermal capacity by FY32 ought to come in at roughly 300 gigawatts. Across this half year, we've seen thermal bids from a range of states adding up to 11.6 gigawatts. As you know, we backed Salboni's 1,600 megawatts in the last fiscal year, and there's extra optionality of 1,800 megawatts for brownfield growth at KSK. Just recently, an LOA came through for 400 megawatts tied to our 700 megawatts Utkal plant, which today sits as open capacity. When that LOA turns into a PPA, it should give us even greater predictability in cash flow and bring open capacity down from 8% at present to 5%. Nationally, renewables made up 18% of all electricity generated this quarter, versus 15% during the same quarter a year ago. Wind had one of its best showings yet, with the country's PLFs climbing from 31.7% to 34.9%. Hydro output jumped as well, hitting 68 billion units, a 13% rise year on year, helped by improved hydrology and a favorable monsoon. The merchant market stayed soft, with day-ahead exchange prices averaging INR 3.92 per unit, falling both quarter on quarter and year on year, hit by record capacity additions and weak demand. As we mentioned on the prior call, we've proactively de-risked the portfolio by contracting our imported coal-based Vijayanagar plant with our group company, JSW Steel, and others.
Sharad Mahendra
executiveThis strategic step has cut our exposure to merchant volatility by a substantial margin and given us stable returns. In addition, the recent LOA for 400 megawatts at Utkal will lower our merchant market exposure as we move ahead. Even with the untied capacity we have now, our domestic coal-based exposure stands at 788 megawatts, out of roughly 1.1 gigawatts of total merchant exposure. That keeps the plant viable for generating attractive dark spreads even when merchant prices are lower. Coal prices kept easing, averaging $91 per ton in the quarter, compared with $110 per ton in Quarter 2 FY25. Since the quarter ended, prices have eased further, to about $81 per ton. That should work in our favor. Our imported open thermal capacity ought to post better Dark Spreads, helped by the cheaper fuel. Turning to RE bidding, the first half of FY26 recorded cumulative generation bids of nearly five gigawatts and storage bids of roughly three gigawatts. On the macro side, the recent GST rationalization has been a welcome reform. For renewables, it brings down capital costs and will feed through into more competitive tariffs. For thermal power plants running on domestic coal, scrapping the INR 400 per ton Compensation Cess along with the streamlined GST structure will lower fuel costs and enhance overall generation economics.
Sharad Mahendra
executiveThe financial health of DISCOMs is going to be strengthened by these changes, and they support sustainability for the sector over the long term. Looking at regulation, we expect some changes stemming from the recent renewable consumption obligations framework as well as the new draft amendments to the Electricity Act, and these are positives for the sector. At JSW Energy, our strategic focus stays on energy security together with energy sustainability, with capital allocated in a disciplined way. Let me share the highlights of how we performed this quarter, a period marked by meaningful progress on several fronts. Generation in the current quarter rose a robust 52% year-on-year, climbing from 9.8 billion units to 14.9 billion units. In addition, H1 FY26 showed a 60% year-on-year rise in generation, going from 17.7 billion units to 28.4 billion units. This happened while the industry posted subdued demand growth of 3.3% year-on-year for the quarter and just 0.8% year-on-year in H1. Our generation base has been expanded by the acquisition and integration of KSK and O2 Power, together with organic capacity additions in solar, wind and hydro from our Kutehr unit and Ind-Barath unit 2. Across the past 12 months, we added 5.5 gigawatts of capacity — 3.3 gigawatts renewable and 1.8 gigawatts thermal — which contributed significantly to our EBITDA growth.
Sharad Mahendra
executiveThat figure covers 1.5 gigawatts of renewable and 1.8 gigawatts of thermal inorganic capacity. In the quarter just ended, we brought 443 megawatts of fresh capacity online, which lifted our installed base to 13.2 gigawatts. That is striking year-on-year expansion of roughly 71%, compared with 7.74 gigawatts during the same period a year earlier. Within those additions, I take particular pride in noting the commissioning of our greenfield Kutehr hydro generation plant at 240 megawatts, 148 megawatts of wind capacity coming online, and 56 megawatts of solar. Previously, we had commissioned 5 megawatts of agrivoltaic at Vijayanagar, and we have now commissioned our first 20 megawatt floating solar project, also at Vijayanagar. This demonstrates our capacity to deliver innovative, sustainable energy solutions over the long term. In addition, our 240 megawatt Kutehr hydro power plant ranks among the fastest greenfield hydro projects completed in India. We want to point out that even while confronting difficulties including COVID-19 disruptions, lockdowns, and extreme weather conditions, we carried out this project in under six years. The timing of commissioning let us take advantage of the high generation season in Quarter 2, producing an impressive 58% PLF from this plant across the operational days of the quarter. Going forward, our under-construction portfolio stays robust.
Sharad Mahendra
executiveRight now, we have 12.5 gigawatts of generation projects under construction, and every one of them is fully contracted through long-term power purchase agreements. Once those are finished, our installed capacity will almost double, reaching roughly 26 gigawatts. That figure takes in new PPAs we signed in the quarter — 230 megawatts under SECI FDRE 4, plus 100 megawatts of solar together with 100 megawatts of battery energy storage system. Turning to hydro, Karcham Wangtoo and Baspa beat their design energy generation by 16% in Quarter 2 and by 13% in H1 of FY26. As I mentioned before, the Kutehr plant we recently commissioned adds further strength to our hydro capabilities and opens up new synergies. We had previously guided to capital expenditure of ₹130,000 crores by 2030 in order to reach the Strategy 3.0 capacity we announced at 30 gigawatts, together with 40 gigawatt-hours of energy storage. Growth opportunities in this sector are enormous, and we are committed to going after them in a calibrated, strategic way. To bring predictability to execution and to reaffirm our steadfast commitment to delivering value to all our stakeholders, we keep taking deliberate steps toward organic growth, in both RE and thermal. That approach fits with our recent partnership with SANY for wind turbine manufacturing and with our decision to pause our solar module manufacturing plans.
Sharad Mahendra
executiveThere are three strategic developments from the quarter that I'm glad to walk you through. The first, and the most important, is our acquisition of GE Power India's boiler manufacturing unit. Through a scheme of arrangement with GE Power India, we will acquire its boiler manufacturing business. That deal meaningfully strengthens what we can do in-house, in terms of both technology and people — something very critical for equipment manufacturing — and it backs our plan to expand thermal power. The second is the majority stake in KSK Water Infrastructure. Following the acquisition of KSK Mahanadi, we have now successfully closed on acquiring a majority stake in KSK Water Infrastructure. This entity currently supplies raw water to our 1,800 megawatt KSK Mahanadi thermal power plant, and it is equipped to support an additional 1,800 megawatt, which ensures readiness for our future expansion. The third is the battery assembly plant in Pune. As we communicated previously, we are in the process of setting up a battery assembly plant in Pune with a rated capacity of 5 gigawatt-hour per annum. This facility, dedicated to supporting battery energy storage systems, is expected to be operational in the current quarter — that is, Quarter 3 of FY26. It will also enable us to meet domestic content requirements for BESS as and when they are mandated by Government of India.
Sharad Mahendra
executiveAs part of our ongoing strategic expansion, I'm happy to report that we've signed a definitive agreement to acquire the 150 megawatt Tidong Hydro Power Plant from Statkraft, at an enterprise value of INR 1,728 crores. This plant is very close to completion and is expected to be commissioned by October 2026. It has a 22-year power purchase agreement with Uttar Pradesh Power Corporation covering 75 megawatts, while the rest of the capacity offers attractive potential in the merchant power market. This acquisition will not only strengthen our hydro portfolio but will also bring in a highly skilled team with deep expertise in hydroelectric power. Their experience will be invaluable as we advance our pumped storage projects. We are already the largest IPP in the hydro sector, and this acquisition further cements our leadership position. In our energy products and service segment, we signed battery energy storage agreements for 680 megawatt-hour, bringing our total locked-in capacity to 29.4 gigawatt-hour. Also, the trial runs for our 3,800 tons per annum green hydrogen project at Vijayanagar are nearly finished, and we expect commissioning very soon in the current quarter of FY26, that is, Q3 of FY26. Looking ahead, we continue to integrate the recent acquisitions of KSK Mahanadi and O2 Power into our operations, significantly strengthening our capabilities.
Sharad Mahendra
executiveHaving already brought 2.3 gigawatts of capacity online during the first half of FY26, we're in a strong position to hit our goal of more than 15 gigawatts of generation capacity by the close of this fiscal year. Finally, let me restate how focused we are on executing well, allocating capital efficiently, and creating value for stakeholders. Given a under-construction portfolio of high quality that is largely tied up, we're confident we can keep up this growth trajectory and produce superior returns. Thank you, and at this point I'll hand things over to Pritesh, who will discuss the financial performance for the quarter. Thank you. Many thanks, Sharad, and a very good evening, everyone. As Sharad said, our installed capacity has grown significantly on a year-on-year basis. In September last year, operational capacity stood at 7.7 gigawatts, while we closed September 25 at 13.2 gigawatts. All of that drove net generation for the quarter up 52% year-on-year, which translated into total revenue up 55% at more than INR 5,300 crores. EBITDA for the quarter rose 67% to just under INR 3,200 crores. With newer assets capitalized onto the balance sheet, interest and depreciation are commensurately higher, and that has pushed profit before tax down 35% for the current quarter versus the prior year.
Sharad Mahendra
executiveApologies — profit after tax was actually lower by 17% versus a year earlier, at roughly INR 705 crores. What matters more to us, though, is that cash profit generation rose 27% year-on-year, exceeding INR 1,500 crores. Looking at half-year performance: across the first six months of this year, we've already surpassed the EBITDA produced during the whole of the prior fiscal year, with half-year EBITDA at more than 6,200 crores. Our profit after tax for the half came in almost 5% higher, near 1,450 crores, while cash profit after tax was above 3,000 crores. On the balance sheet side, net debt as of the September quarter-end was close to 62,000 crores. Sequentially, that's roughly 2,500 crores more than at June-end. CapEx spending this quarter totaled around 3,500 crores. We also capitalized certain ongoing projects, such as Kutehr and some RE projects, and as a result the net debt tied up in capital work in progress dipped slightly — by about INR 400 crores — over the quarter, landing at approximately INR 12,500 crores; so on operational assets, total debt against total EBITDA on a TPM basis was just under five times.
Sharad Mahendra
executiveOur weighted average cost of debt has edged down slightly, thanks to a reset on a few of the existing facilities, and it rose by almost 10 basis points on a sequential basis. We anticipate that this path will carry on over the coming couple of quarters as additional facilities hit their reset dates, so the softening of interest rates that we have observed in the markets will begin to show up in our borrowing cost too. The receivables trend remained quite healthy. Outstanding receivables totaled INR 3,500 crores at the end of September, which worked out to a day's sales outstanding of 64 days. That marked an improvement versus 70 days at the same point last year. On that note, I'll pause here, and operator, if you could take us into the Q&A, we can open the floor for questions, please. Thank you. Thank you very much. We will now start the question and answer session. Anyone wishing to ask a question may press star and then one on the touch-tone phone. If you wish to remove yourself from the question queue, you may press star and then two. Participants are asked to use handsets while asking a question. Ladies and gentlemen, we will wait for a moment while the question queue assembles.
Sharad Mahendra
executiveWe'd also ask that each participant limit themselves to just two questions, and if you have any follow-ups, please get back in the queue.
Operator
operatorMohit Kumar from ICICI Securities has our first question. The floor is yours.
Mohit Kumar
analystHello there. Good evening, sir, and thank you for giving me the chance to ask. My first question concerns the financials. Could you explain why EBITDA was lower at Karcham and Baspa in the quarter? EBITDA came in at INR 3.8 billion. That said, in our view generation was stronger than a year earlier.
Sharad Mahendra
executiveMohit, as you're surely aware, there's a Supreme Court ruling concerning the Karcham side and free power. So compared with last year, the extra free power that we used to sell in the merchant market is now being provided to the Government of Himachal Pradesh under the implementation agreement, correct? That's the main reason why, looking at EBITDA, you're seeing a year-over-year decline in the hydro business, right?
Mohit Kumar
analystRegarding Ind-Barath EBITDA, has it declined quarter over quarter? Is that mainly because of the merchant impact, or was there some one-off item?
Sharad Mahendra
executiveSo for Ind-Barath, what happened is that the units had a scheduled shutdown, and that's what you should keep in mind. That's the sole cause. Nothing else is behind it. All of the annual maintenance and annual overhauling has been finished. So in the second half of the year, with an eye on handling the seasonal demand, which typically looks better in H2, it was simply a seasonal annual shutdown—one that was planned.
Mohit Kumar
analystGot it, sir. For my final question: why are we acquiring the GE Power assets? Could we produce the entire boiler, or would it just be the pressure part of the boiler? And what's the plan for using this asset to build our own thermal power plant? Yeah.
Sharad Mahendra
executiveLook, one thing we need to keep in mind is what we've observed over roughly the last 18 months — the volume of thermal bids coming through and how the PPAs are getting signed. There's definitely been a bottleneck when it comes to getting timely supplies from existing vendors of boiler turbine generator equipment to match PPA timelines. So with that in mind, this facility runs on a technology that's very well established and is presently operating, though it isn't producing new pressure parts or components for new boilers — it's serving existing customers, and it has the full capability to make new ones. So yes, as always, whichever boiler plant it is, whether from another company or GE, it's mostly a mix of pressure parts manufactured within the plant. The non-critical items and other things are normally outsourced as well. That's how other companies like BHEL or others operate too. So all the critical parts, the pressure parts, will be manufactured here. And finally, our strategy was to make sure of timely boiler supplies for our plants — especially the Salboni plant, for which we have a PPA that we've signed.
Sharad Mahendra
executiveThe technology exists, the people with the skills to do it are in place, and the engineering team is in place. Those are the main reasons, the strategic reasons, why we have chosen this.
Mohit Kumar
analystGot it, sir. Thanks very much, and all the best to you. Thank you.
Operator
operatorThanks. We move to our next question, which is from Sumit Kishore of Axis Capital. Sumit, please go ahead.
Sumit Kishore
analystGood evening, and congratulations on the solid operating results for Q2. First question from me: during the last 12 months, fairly significant capacity has been added, mostly solar, as you noted in your opening comments, while power demand growth has stayed comparatively subdued. Given that setting, are you observing any cases of grid curtailment affecting RE capacity during solar hours? And is that probably going to become a risk for the sector going forward? That's my first question.
Sharad Mahendra
executiveLook, Sumit, the first thing is obviously this situation where so much capacity is being added—particularly solar during the solar hours—and the grid has begun to encounter a challenge with evacuating that capacity. Still, we need to keep in mind what the regulation states, which is based on connectivity. There's the T-GNA, that's temporary connectivity, and then there's the GNA. So I think if the scheduling system is proper, agile, vigilant, and timely and proper scheduling is taking place, this can be reduced or prevented. Up to now, at least, we haven't encountered any challenge of that kind when it comes to curtailments, and we will keep it that way. That said, yes, this is a situation to watch. A watch needs to be kept, though I wouldn't say permanently—temporarily, perhaps for the next one year, two year, three year, until the new connectivity, the work that's in progress, arrives, and the evacuation is in place. But it is safeguarded in the sense that if there's a PPA with an entity, and if the scheduling falls within the PPA terms, then even if curtailment happens on the grid, the regulation protects the developers, and they receive the money.
Sharad Mahendra
executiveThere’s a process involved, and the IR team can walk you through it if those details are able to be shared with you separately.
Sumit Kishore
analystRight. So your payments wouldn’t be impacted because that RE plant holds must-run status, would they? As long as the only — sorry, let me jump in here. Just to make things clear, what Sharad meant is this: as long as your asset is already running under GNA. GNA. Correct? However, should any asset be running under TGNA, then in the event of curtailment, no revenue protection mechanism exists, right? And your capacities sit under GNA?
Sharad Mahendra
executiveYeah. Yeah.
Sumit Kishore
analystSecond, there’s operating capacity. Usually you’ll have TGNA in place for partial commissioning of capacity. So the way to think about it, conceptually, is this: suppose I’m putting up a 100-megawatt plant, right, and only 30 megawatt or 40 megawatt or 50 megawatt has been commissioned — under T-GNA, evacuation of that power is permitted, correct? But your project SCOD is only reached once the full 100 megawatt is done. After the 100 megawatt hits SCOD, you shift to GNA. The T-GNA falls away. And that’s the point when, so to speak, the clock on your 25-year PPA begins ticking, right? So in effect, under T-GNA, you were already bringing in excess revenues before the PPA had even started. So no compensation mechanism exists for that, right? I hope that’s clear.
Sharad Mahendra
executiveYes, that’s quite clear.
Sumit Kishore
analystMy second question is this: during the first half of the fiscal, you've added over 1 gigawatt of organic capacity, and you'd mentioned a target of 3 to 4 gigawatts of organic additions in FY26. Your presentation also includes photographs of 3.4 gigawatts of solar and 2.3 gigawatts of wind that are under construction at various sites. So, I mean, is anything standing in the way of hitting that target? Because looking at the CapEx you incurred in the first half, it seems there should be a decent pickup in the second half if these targets are to be met. I mean, how should we think about CapEx and your capacity addition?
Sharad Mahendra
executiveSo, Sumit, first of all, regarding whatever project work is currently in progress there, nothing stands in the way of finishing and commissioning it, because connectivity and land — the two biggest execution challenges — are both fully secured. Work on those projects has only just begun. And of course, we typically see lower activity, and particularly this year in the first half, with the monsoons running long, the pace of projects and execution was considerably slower. Now, in the second half of the year, the projects need that capacity, which, as I also mentioned, will see the year close above 15 gigawatts. So roughly 2 gigawatts more may be added. So certainly, on CapEx as well, compared with what was seen in H1, it will be higher than that.
Sumit Kishore
analystAll right, that’s very clear. Thanks — I’ll join.
Operator
operatorThanks. We’ll take our next question from Ketan Jain at Avendus Spark. Ketan, please go ahead.
Ketan Jain
analystHello there, and good evening. Thanks for taking my question. First off, I'd like to ask about the Karnataka LOA for Ind-Barath. What terms would apply to realizing it, or did this come through a competitive bid? Also, how was the tariff set for that LOA?
Sharad Mahendra
executiveLook, this tariff — again, this is a bidding process, and it's in the public domain. The tariff here is at the regional periphery at CTU. You could say at plant periphery. The tariff is INR 5.78. Understood. For this. So you can work out the calculations in terms of the fuel cost. Our Ind-Barath plant, the Utkal plant, is very close to the mine. MCL is only a few kilometers away from there, from where we are getting the bulk of the fuel. So the pricing is quite attractive.
Ketan Jain
analystGot it. And I wanted to ask as well — was there any one-off item in renewable EBITDA coming from either of the sector projects, or does all of it represent organic EBITDA?
Sharad Mahendra
executiveYeah, ideally organic. Yes, yes, yes, yes. No, nothing significant that's one-off, nothing that needs to be reported. Nothing.
Ketan Jain
analystGot it. Thanks. I’ll return to my remaining questions and give an answer.
Operator
operatorThanks. Atul Tiwari with JPMorgan has the next question. Go ahead, please.
Atul Tiwari
analystYes, sir. Thank you very much. My first question concerns the industry as a whole. We've just witnessed 5 gigawatts of RE builds during the first half. And clearly, we've all been hearing reports about curtailment and similar issues, and sluggish power demand is now a reality. So do you believe this represents the new normal — something like 5 to 10 gigawatts more in the second half — or is it still possible to hit that ambitious goal of 40 to 50 gigawatts of RE bidding each year?
Sharad Mahendra
executiveLook, that's a very — I'd call it a very, very relevant question that's come in. There are two things we need to grasp here. I don't view this as very, very temporary. What I'm seeing is two things that have played out, which is what we've observed over the last two years: the volume of bidding that has taken place, which is close to 100 gigawatt. So the build-up — close to 40 gigawatt of bids whose PPAs are still pending, and within which there are meaningful shares of plain solar and plain wind as well — combined with the grid challenges being encountered, we've seen one major, significant shift in H1 of the current year: plain vanilla solar or vanilla wind bids are barely present. They're just not there. What's coming is mostly either hybrid. Hybrid too is considerably less. It's FDRE, or otherwise the majority is solar plus battery energy storage to discharge during the evening hours. So we see this as temporary, a pause, because there's enough in the country to be executed going forward over the next three years — the PPAs that have been signed or the unsigned bids that exist. So we see that in the current year, the overall bidding volume, compared with what we've witnessed across the last two fiscals, is expected to be lower this year.
Sharad Mahendra
executiveBut like I said again, this is only temporary. Once the backlog begins to decrease and there's visibility on connectivity, I believe this will come up again, possibly starting from the next financial year — that's what is expected. Okay. My second question concerns the Salboni project. So is it fair to assume that the boiler will now be built in-house following the acquisition of GE Power's boiler assets, correct? Yes. Yes. Okay. And just, obviously, you'll hopefully be bidding for new coal-based capacity too. So what's the maximum boiler capacity you can handle in-house at this facility? Look, as I clearly said, when you see that the boiler plant isn't working, we say, okay, two or one boiler. It's not that it's one. It's a single unit, and it delivers one in a year. This has capacity for roughly 1.5 boiler worth of component manufacturing. And that doesn't mean it will deliver 1.5 in a single year. The span needed to complete one boiler is nearly 18 months in terms of supplies from the zero date. So there's a cycle involved, and we have time.
Sharad Mahendra
executiveIt is meeting the timelines. In Salboni, my commissionings are in 2030 as per the PPA terms. So effectively, once the plant is fully functional, you can say it will give a material worth 1.5 boilers, you can say, per annum this will be giving.
Atul Tiwari
analystAll right. So JSW Toshiba will supply the turbine generator for the plant. We have a joint venture with Toshiba — it's a long-standing one — and they've previously built and delivered this 800-megawatt TG in India as well, to NTPC and others.
Sharad Mahendra
executiveYes, so the turbine generator is going to come from Toshiba JSW — that's the joint venture company.
Atul Tiwari
analystSo at present, what's JSW Toshiba's yearly capacity?
Sharad Mahendra
executiveJSW Toshiba is comfortably capable of turning out 2 turbine generators annually.
Atul Tiwari
analystThat comes to roughly 600 megawatts.
Sharad Mahendra
executiveTo repeat what I mentioned, they haven't been manufacturing turbine generators over the last few years, even though the technology and equipment remain in place with them. Delivery will begin 3 years from now, which lines up perfectly with our own timeline. After that point, starting in year 3 onward, once the first unit has been delivered, they'll be able to supply 2 TGs annually.
Atul Tiwari
analystTwo turbine generators, each rated at 800 megawatts?
Sharad Mahendra
executive800 megawatts — that works out to 1.66 gigawatts annually, with room to reach 2.4 as well.
Atul Tiwari
analystAlright. Alright, that's helpful to know. Thanks.
Operator
operatorThanks. We’ll take the next question from Karan Gupta at Karma Capital. The line is yours — please go ahead.
Karan Gupta
analystYes, sir. Thanks for the chance to speak, and greetings to everybody. I have two quick questions. Could you discuss how the depreciation expense being recorded lines up with the economic life of the assets underneath? In other words, is it possible for these assets to keep producing cash flows even once they have been depreciated down to zero? And second, you have consistently mentioned netting ROEs. So when you look at those, is it on a cash basis or a net basis?
Sharad Mahendra
executiveCould you say the second half of your question again, please?
Karan Gupta
analystRight. So on previous calls, management has consistently said that decisions about allocating capital rest on netting ROEs. So is that netting ROEs calculated on a cash basis, or is it done net of depreciation expense?
Sharad Mahendra
executiveThe first part of your question is about depreciation being straight-line, correct? So yes, asset economic lives usually exceed the depreciation period—with one very significant caveat: that assumes your operations, maintenance, upkeep, and overhauls are done properly, right? In India there are many instances, across various types of asset bases, where asset life can be extended through some nominal RNM—that is, renovation and modernization CapEx. Economic life can stretch past depreciation, right? That covers the first part of the question. As for the second part: the capital allocation decision stays the same. It's a levered equity IRR, right? Since we allocate capital against cash flows over the asset's life, right? And so, when it comes to a levered equity IRR, you'll be able to get there when you run the FC calculation, right? ROE, I think, is easy to grasp. It's more backward-looking, or reflects a specific point in time. But depending on where you sit in your Capex cycle or where the asset is in its life, your ROE trajectory—for an RE business, for instance—will typically be lower in the initial years, because the debt has yet to be repaid.
Sharad Mahendra
executiveUsually, when you get to that 10, 11, 12-year point, that's when debt is being repaid more quickly, so the accrual in the numerator — which is your reported profit after tax — is higher, right? That means ROE begins to cluster toward the later portion of the asset's economic life. Capital allocation decisions, though, rest on long-term cash flow forecasting. So it comes down to a net equity IRR on a levered basis. I hope that's clear.
Karan Gupta
analystYes, I really appreciate that. Thank you.
Sharad Mahendra
executiveI appreciate it.
Operator
operatorThanks. The next person to ask a question is Amit Pandey with Morgan Stanley. You have the floor.
Amit Pandey
unknownThanks for taking the question, sir. I was hoping to get your thinking on the 1,800 KSK Mahanadi plant. Will that be up and running by 2031?
Sharad Mahendra
executivePardon me for cutting in. Amit sir, could we ask you to state your question one more time, please? Sorry about that static.
Amit Pandey
unknownYes, absolutely. Sir, I'd like to clarify whether our goal is to have the remaining 1,800 megawatts at KSK Mahanadi up and running by 2031. Is that part of your plan?
Sharad Mahendra
executiveRight, so we've consistently said this is a 1,800 megawatt operational plant, and of that 1,800 megawatts, the balance of plant is completely ready. As for the fourth unit, 40% of the work is done, and six units of minor work have already been finished as well. So yes, we definitely intend to have this finished before 2031.
Amit Pandey
unknownRight. OK. Right. Understood, sir. Yes, that was what I asked. The rest of the questions are answered. Thank you.
Operator
operatorThanks. The next question is from Shrinidhi Karlekar of ASK Investment Managers Private Limited. You have the floor.
Shrinidhi Karlekar
analystYeah, hi there, and thanks for the chance to ask. Sir, I'd like to get your view on what's actually behind the pickup in state PPAs across the different states, and how the pipeline is shaping up?
Sharad Mahendra
executiveLook, on state PPAs — one pattern we've been seeing in the thermal segment is that states want PPAs signed for new thermal capacity, and they're favoring having the plant built inside the state. Driving investment and jobs locally is among the strategic shifts we're observing across states, whether you look at recent bids in Bihar, Madhya Pradesh, or West Bengal, or the latest ones in Assam or UP. Those are five big states, plus Maharashtra makes six. Apart from Maharashtra, what we've seen is that each state has insisted the unit be set up in that state itself, which we think is actually good given the grid challenges we've been seeing so far, and this will help. That's the trend we're observing — states are backing this. On the RE side too, two factors are pushing some of the states that are friendly toward solar or wind development, with Karnataka among the leaders along with Maharashtra: building within the same state shields them from ISTS connectivity, which is a challenge, and also from the connectivity charge obligations, which had been free and which we began implementing this year from first June.
Sharad Mahendra
executiveIncremental transmission charges will show up annually. So those 2 factors are pushing states that are RE-friendly to build capacity inside their own borders.
Shrinidhi Karlekar
analystOkay. And sir, would you say the pipeline remains robust, or was that just a stretch of a year or two in which we witnessed a large number of bids when it comes to thermal PPAs?
Sharad Mahendra
executiveLet me jump in here. The way this usually works is that you need to view things through a procurer's lens, correct? Each distribution utility carries out what's known as demand curve forecasting, right? Then, in line with that demand curve forecasting — which generally rests on a medium- to long-period average basis — they'll put together a resource adequacy plan addressing where this curve will go and which different modes of generation will serve it, right? After that, drawing on their own internal analysis and decisions, they conclude, okay, X% from this mode, Y% from that mode, and so on. And that's how, taking into account what the typical gestation period is for each mode, they proceed, right? So over the last 18 months, most of us active in the power market have been taken aback by greenfield long-term PPAs for thermal projects — those bids returning. So clearly, you're now asking us to crystal ball whether this trend will persist or not. Our track record when it comes to calling something like this is very poor. We wouldn't put trust in our own views here, right — on the light or not.
Sharad Mahendra
executiveBut I’d think the speed at which we’ve seen bids come in—so at least it’s less probable that the current states would require the states that have already submitted a bid, perhaps some brownfield or some extra from those, but the states that haven’t may return one year or two years from now, right? So there’s no visibility. Nobody provides guidances of that sort, right? You take it year by year. That’s how it goes.
Shrinidhi Karlekar
analystOkay, got it — that’s clear. If I can, just one more question. You’re building that BESS assembly plant in Pune. I’m wondering whether it’s mostly for captive requirements, or do you also intend to serve demand from outside?
Sharad Mahendra
executiveAnd look, our captive portfolio matters a lot too. It's meant for captive use, but the capacity we've put in place is 5 gigawatt hours per annum, and ramping that up doesn't happen overnight. Perhaps by the second year of operation, we should get to full capacity. So we'll be open on that side as well, because of how MNRE has been concentrating on ALMM for solar modules and now cells too, which is under discussion, and for wind as well, which is already there. In the end, there's a Make in India push even in this space. So we believe opportunities will exist to serve requirements from outside as well. So we'll be open both ways — for our captive needs, technically speaking, and if any requirement comes up, we can meet outside requirements too.
Shrinidhi Karlekar
analystGot it, sir. Thanks for taking my questions, and all the best.
Sharad Mahendra
executiveAppreciate it.
Operator
operatorThanks. We move to our next question, which is from the line of Darshan at Jefferies. Go ahead, please. Hi, sir. Congrats on a solid set of numbers. I just had one small clarification. When we turn to page 35 of the presentation, utilization for solar stands at 19% and for wind at 41%. Even so, those figures were identical in 2Q FY25.
Sharad Mahendra
executivePardon me, what was the question again? Can you hear me? Yes, yes, yes. What did you ask? So, when you look at the CUF for solar and wind in 2Q FY26, it comes in at 19% and 41%, compared with 24% and 26% as stated in this PPT. But if you check 2Q FY26 — no, no. You're confusing the rows. 99% and 91% is the hydro total. Solar stands at 24% versus 99%. And wind is 26% versus 41%. Yeah. So essentially, what you're asking for is that you want to understand the change over the prior year's quarter two? No, sir. For this current quarter, it's 19 and 41, correct? Solar and wind? Yes, yes. All right. Because looking at last year's quarter two presentation, it was 24 and 26. Okay. Okay. No problem. Thanks. Yeah. It's there.
Operator
operatorThanks. Next up we have Aniket Mittal from SBI Mutual Fund on the line. Go ahead, please.
Aniket Mittal
analystYes, sir, and thanks for giving me the chance. There are two quick questions. First, even though we are seeing wind PLFs recover, when I look at Mytrah's EBITDA figure, it has actually declined year over year. Since Mytrah's portfolio is fairly heavy in wind, I just wanted to get an understanding of why that is.
Sharad Mahendra
executiveCould you say that again? Mytrah, you're saying that this happened even with the PLF going up?
Aniket Mittal
analystSo wind PLFs are higher. Mytrah is a wind-heavy portfolio, but the EBITDA number on a YY basis is actually showing a decline in. How much?
Sharad Mahendra
executiveAnd by what amount?
Aniket Mittal
analystMy sense is it's a little lower — down by more than 51 crores, 50 crores.
Sharad Mahendra
executiveLet me give you the figure: five crores. Look, wind speed is more favorable. We need to look at the Mytrah portfolio as it was designed. This is an older portfolio whose machines begin at 850 kilowatt. So despite the better wind speed, they've also shown that the wind portfolio has delivered stronger results. But when you weigh how much benefit comes from higher wind speed versus what larger machines give us — whether 2.7 or 3 gigawatt — the incremental EBITDA from the wind portfolio in Mytrah is limited by comparison. On solar, though, we recognize that solar, owing to the prolonged monsoon, has generally had a lower skew. Yet if you look at H1, Mytrah's H1 EBITDA, compared with H1 of last year, when H1 solar was doing well, comes to 1,021 versus 892 last year. Right. Right. So we saw a very marginal effect, and it's mainly — even though solar is just 422 megawatt and the portfolio is wind-dominated — the impact from solar, given weaker radiation and the extended monsoons, is that solar across the country generally has not done well this quarter. So that effect amounts to only this minor change in the quarter.
Aniket Mittal
analystUnderstood. And regarding Barmer specifically — the year-over-year EBITDA decline there was quite steep.
Sharad Mahendra
executiveSo, Aniket, Barmer — if you remember, the same situation occurred with hydro last year. In businesses with regulated returns, once 12 years are up, the depreciation rate shifts, and as a result your capacity charge drops, correct? That's because the debt has been repaid and so on, right? So Barmer hit its 12-year mark last year. Which means starting this year, you get a step down in capacity charge recovery along the regulatory trajectory, driven by that depreciation rate change. You'd have noticed the same thing in Q1 versus Q1 of the prior year, right? So it'll play out across all four quarters of this year, and after that, this becomes the baseline going forward, right?
Aniket Mittal
analystYes, got it. I believe the gap on one Q came in a bit under that figure, which is why I see it that way.
Sharad Mahendra
executiveNo, so there would be backgrounds. There would be PLF changes. Station heat rates, SOX consumption, all of that would have an impact. Those pluses and minuses are going to occur. But at the fundamental level, the step change comes from this. Yeah?
Aniket Mittal
analystUnderstood. Those were my questions, and thank you.
Sharad Mahendra
executiveYeah.
Operator
operatorThanks. Our following question is from Mithil Jain of CRISIL. Go ahead, please.
Mithil Jain
analystHello, sir. Thanks for giving me the chance to speak, and happy Diwali to all of you. My question concerns the unit economics of battery energy storage systems. First point: what is the present CapEx per megawatt hour for BESS? We've seen in various media reports that it has fallen from 105 kilowatt hour to 55 kilowatt hour. So what cost are we currently bearing in India — the landed cost for one megawatt hour of BESS? My second question relates to the tariff we charge for our standalone BESS and for storage plus solar tariffs. Thank you.
Sharad Mahendra
executiveHonestly, it's hard for me to give a direct answer here, because whenever you're looking at a sourcing or procurement call, a great deal hinges on A: what price is prevailing at that moment? How do you plan to negotiate against several suppliers? What sorts of framework agreements, if any, or volume commitments, if any, are you able to offer? So each player's bargaining strength is going to look quite different. Unfortunately, no single approach works for everyone. Yeah. And we should also recognize that when you're inquiring about the BESS supply and likewise regarding the BESS project, claiming that a standard tariff applies simply isn't feasible, since solar plus BESS depends on which geography it's installed in, whether it involves a two-hour discharge, a four-hour single discharge, or a two-hour discharge in the morning plus a two-hour discharge in the evening. That means the project has to be designed, and the battery container solution has to be designed, accordingly. Beyond that, for my energy plant, at what price am I buying this LPAC? So a great many factors come into play. So perhaps stating 110 to 55, or providing any straight-line figure, won't be feasible. Quite a few variables have to be settled before you can arrive at a number.
Sharad Mahendra
executiveAnd to finish addressing the second half of your question: this is a competitive bidding process, correct? So, as the saying goes, beauty lies in the eyes of the beholder. Therefore, I'm certain that the prices currently being discovered for standalone battery energy storage systems — where we're now seeing 15, 20, 25 bidders in a single auction — I'm certain that for some of those players, those figures make sense, right? That figure is publicly known, so you know what it is, correct? But it also hinges on risk appetite and returns. And just to conclude with what Pritesh said, which we have maintained from the very beginning and still maintain very clearly — our benchmark hurdle rate: any bid, if it is not giving... we are not going to build a portfolio merely for the sake of building one. Mid- to high-teens IRR is our hurdle rate that has to be maintained, and only then do we proceed.
Mithil Jain
analystYeah, okay. So just one thing — could you give us the upper and lower band of the Capex per megawatt hour? We need to check whether tariffs for BESS have now come in lower than PSP, or whether they're still in similar ranges, or PSP is a little cheaper than BESS. So broadly, what's your view on this?
Sharad Mahendra
executiveNo, sorry, that isn't something we can do here. This is a competitive market, and speaking publicly on these matters isn't in our interest. Yeah. What I would suggest, though, is that if you need any discussion or any additional information, you can reach out to our IR team. They will definitely be glad to supply whatever further information or any guidance that needs to be given.
Mithil Jain
analystYes, yes, of course. Thanks.
Operator
operatorThanks. Our next question is from Mahesh Patil at ICICI Securities. Go ahead, please.
Mahesh Patil
analystHi there. My question concerns our renewable LOA. Of the 2.6 gigawatt still awaiting a PPA, is it reasonable to expect that within the coming six months — meaning by the close of this year — those PPAs will get signed? What's your view on that?
Sharad Mahendra
executiveLook, as we also talked about a while ago, and I answered one of the questions on this, there are 40 gigawatt of bids still pending where the LOA has been issued and the PPA is waiting to be signed. So we can't provide any timeline on this — whether that's three months, six months, or one year. We're simply waiting for the right moment, should the opportunity arise. Even without that, though, we remain well on track to hit 30 gigawatt of capacity. We're absolutely confident of that. So we don't see — and for us, the total capacity for which we've received pure solar, which we view as a challenge, is only 900 megawatt out of our total four gigawatts, which is a mix of many things. But if you look at total solar, it's 900 megawatt of capacity that's pending, contracted but not signed.
Mahesh Patil
analystAll right, sir. But have you looked at the situation — the overall picture here? Has there been any improvement in that versus the previous quarter?
Sharad Mahendra
executiveMy apologies — could you say that question again?
Mahesh Patil
analystSir, my question was whether you’ve noticed any better overall picture — specifically around DISCOMs and the signing of PPAs — in the last quarter? Over the past four, five months, have you seen any improvement?
Sharad Mahendra
executiveWe aren't seeing any particular improvement. It's the same thing that's been observed in the slowdown in PPA signing over the last 6 months. On thermal, there's an uptick we're all seeing, and there's also more keenness on solar plus battery energy storage, both in the C&I segment as well as at utility scale.
Mahesh Patil
analystUnderstood, sir. Noted. Many thanks. Thanks a lot.
Sharad Mahendra
executiveOperator, that's all the time we had. If we could wrap it up, please.
Operator
operatorAbsolutely, sir. We’ll treat that as the final question for today. At this point, I’ll turn the conference over to management for closing remarks.
Sharad Mahendra
executiveYeah. Yeah. Thanks to all of you for joining us today. And on behalf of us, on behalf of JSW Energy, I want to wish you, all your family members, and those close to you a very, very happy and prosperous Deepavali and New Year. And thanks once more for being with us.
Operator
operatorThank you. That brings this conference to a close on behalf of Motilal Oswal. We appreciate everyone for being with us, and you can go ahead and disconnect your lines at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.