JSW Energy Limited (533148) Earnings Call Transcript & Summary

January 28, 2025

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 59 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to JSW Energy Limited's Q3 FY ’25 post-result earnings conference call. <<operator_script>>. Kindly be aware that this conference is being recorded. I’m now handing the conference over to Mr. Vishal Periwal of Antique Stock Broking. Thank you, and over to you, Mr. Periwal.

Vishal Periwal

analyst
#2

Yes, thank you, Sagar <<inaudible>>. Good evening, everyone. To begin with, I apologize for the small delay in getting the call started. I'm welcoming all of you on behalf of Antique Stock Broking to the earnings call following the results for JSW Energy Limited. Joining us from the company are the leadership team, headed by Mr. Sharad Mahendra, Joint MD; Mr. Pritesh Vinay, Director, Finance, and CFO; along with Mr. Bikash Chowdhury, Head, Investor Relations and Strategic Finance. As is our practice, the management will give a short briefing on the quarter that has just ended, and after that we'll open the lines for Q&A. So, Sharad, sir, the floor is yours.

Sharad Mahendra

executive
#3

Okay. Thanks, Vishal. Good evening, everyone, and thank you for being with us today. I'm glad to walk you through what has happened and what's new over the quarter that just ended. As we've been observing, the dynamics in this sector are shifting toward energy security — serving both rising base load and peaking load demand — along with adopting low-cost storage solutions for energy so that intermittent renewable power can be integrated. For developers such as us, with a presence across every mode of generation, this creates a mix of opportunities and will keep delivering power that is affordable and sustainable. Turning to the economy, GDP growth for the current fiscal has been estimated by RBI at 6.6%, with a projection of 6.9% for quarter one of FY ’26, driven mainly by robust economic activity and expectations of higher government expenditure in the quarters ahead. Before I get into our quarterly performance, I'd like to give an overview of where the power sector currently stands. During the first nine months of the current fiscal, power demand for the country grew at 4.5%. In the third quarter, demand growth moderated to 2.7%, though we should remember that this comes on a higher base — 9.9% growth was witnessed in the same quarter last year.

Sharad Mahendra

executive
#4

But structurally, we still anticipate robust power demand over the medium term. Peak demand in this quarter came to 224 gigawatts in December ’24, compared with 220 gigawatts during the same quarter a year earlier. For FY ’24 overall — that is, the prior year — peak demand reached 250 gigawatts, versus 243 gigawatts in the current fiscal. Consistent with that demand growth, the country’s generation rose 5.3% year-to-date in FY ’25 and 3.7% in quarter three. All India thermal PLF was 66.7% for the quarter, against 66.9% in the equivalent quarter last year. Intermittent renewables accounted for 12.4% of total generation in the quarter. On generation capacity, the country’s total installed capacity has now reached 462 gigawatts, and 20 gigawatts have been added so far this fiscal. Renewable capacity addition over nine months in FY ’25 totals 19 gigawatts, led by 16 gigawatts of solar installations. Turning to the quarter, net capacity addition was 9.3 gigawatts, compared with 2.9 gigawatts added in the same quarter last year. Additions in the quarter were driven by 7.9 gigawatts of renewable capacity, led by 7.1 gigawatts of solar, while wind contributed 800 megawatts during the quarter.

Sharad Mahendra

executive
#5

Now turning to bidding activity. During this fiscal year, auctions totaling roughly 38 gigawatts of utility-scale capacity have been bid, which keeps up the pace we saw a year ago. For quarter three, the auctions held amounted to 16 gigawatts. The nine-month figure stood at 38 gigawatts, and quarter three alone accounted for 16 gigawatts, with customised solutions for hybrid and FDRE projects clearly dominating. Turning to coal. At this moment, API 4 coal is priced at $100 per ton, against an average of $110 per ton in quarter three of FY ’25 and $116 in quarter three of FY ’24. Domestically, adequate measures have been taken to maintain a strong coal supply. We have observed a low e-auction premium for domestic coal procurement, particularly in Odisha and Chhattisgarh. Moving to merchant markets, we have seen robust volume growth. The past quarter recorded an increase of approximately 16% in total cleared volumes on the power exchange, while day-ahead volumes rose 14% year-on-year. These higher volumes, driven by greater firm power availability and improved hydro generation, have brought prices down. Day-ahead market prices fell 26% year-on-year to INR3.71 per unit, compared with INR5 per unit in quarter three of last year.

Sharad Mahendra

executive
#6

Increased activity on the exchanges resulted in reduced realization within the merchant market, and that weighed on the dark spreads from our short-term sales. Even so, our short-term realization still stands at a premium compared with average exchange prices. That said, we continue to feel confident about robust power demand over the medium term. Turning to acquisitions, on December 27, we announced the purchase of O2 Power, a leading renewable energy platform whose capacity is 4,696 megawatts. Valued at INR12,468 crores, this acquisition represents a significant milestone for JSW Energy. O2 Power’s assets span seven resource-rich states, with 2.3 gigawatts of capacity set to be operational by June ’25 and a further 2.4 gigawatts at various stages of development. This transaction will strengthen our renewable energy portfolio and expand our footprint in this space. As we guided earlier, the additional capex for the 2.4 gigawatts of under-construction and pipeline projects is expected to fall between INR13,000 crores and INR14,000 crores. Along with that, this platform also brings total connectivity — which, we recognize, is a major challenge in the country right now — of 900 megawatts of transmission capacity already in place on top of 4.7 gigawatts, and more than 800 megawatts of additional connectivity sits at various stages of approval.

Sharad Mahendra

executive
#7

That provides us with a really solid runway to speed up capacity additions going forward. The O2 Power assets are high quality, with a blended tariff of INR3.37, and most of the utility-scale projects are contracted with strong offtakers such as SECI, SJVN, and NTPC. To put the full 4.7 gigawatts at a blended tariff of INR3.37 in perspective, solar makes up 64% of that total capacity while wind accounts for 36% of the total 4.6 gigawatts, and this capacity yields that blended tariff of INR3.37. On January 10, we also closed the acquisition of a 125-megawatt wind project from Hetero Labs and Hetero Drugs Ltd. at an enterprise valuation of roughly INR630 crores. That portfolio carries a blended tariff of INR5.22 per unit and an average remaining plant life of 15 years. Taking this into account, our installed capacity today is 8,242 megawatts. In another strategic step, we bid for KSK Mahanadi Power Company under IBC proceedings, and we have now received a Letter of Intent for a 3,600-megawatt thermal power plant in Chhattisgarh, close to the coal belt. Once the transaction closes, this asset, together with O2 Power, will begin generating cash flows from day one.

Sharad Mahendra

executive
#8

KSK Power ranks among the biggest thermal power plants being transferred through the IBC process. Thanks to its strategic location, fuel supply agreement, and efficient operations, the plant will deliver dependable power, which further strengthens our leadership position in the energy sector. At present, 95% of KSK Power's operational capacity of 1,800 megawatts is committed to Uttar Pradesh and TANGEDCO, Tamil Nadu, through long- and medium-term PPAs. Turning now to how we are progressing toward 10 gigawatts by FY ’25 — we have completely revived JSW Energy Utkal Limited, as we speak, previously called Ind-Barath Thermal Power Plant, by synchronizing its second unit of 350 megawatts on January 15. We remain on track to hit 10 gigawatts of capacity by the end of FY ’25. During the quarter just ended, we added 377 megawatts of capacity to our organic renewal projects, all of it wind, which amounts to 47% of the country's wind capacity addition of 800 megawatts in the third quarter. We are right now building 1.1 gigawatts of wind projects for SECI and Group Captive, and our Kutehr hydro plant, with 240 megawatts of capacity, is coming along well for commissioning in the current fiscal FY ’25 itself. Now, for an update on projects beyond the 10 gigawatts, aimed at reaching 20 gigawatts before FY ’30 — our total under-construction capacity stands at 7.8 gigawatts, which goes beyond the 10 gigawatts I mentioned, with signed PPAs, and we have 3.9 gigawatts of capacity where we expect PPAs to be signed shortly.

Sharad Mahendra

executive
#9

On top of that, we hold 8.3 gigawatts of capacity in transactions under acquisition, and roughly 4 gigawatts of that is bolt-on capacity. Taking everything together, our locked-in generation capacity now stands at 28.3 gigawatts. Turning to our energy storage projects, our SECI Battery Energy Storage project of 1 gigawatt-hour is presently on hold, since CERC has not permitted adoption of the tariff. For some background: the bidding for this project was carried out transparently and in line with the Ministry of Power's bidding guidelines on August 25, 2022, and JSW came out as the L1 bidder in the e-Reverse auction. Eight developers took part in total, and a Letter of Award was issued to us in January ’23. The fixed capacity discovered was INR10.8 lakhs per megawatt per month, inclusive of the VGF — the viability gap funding — that the government was providing for this project. Being the first project of its kind, it was structured on a BOOT basis after 12 years, with residual battery capacity of no less than 75% <<inaudible>> of the project capacity. The developer, that is JSW Energy, had no guaranteed offtaker for 40%. Under the arrangement, SECI was to sign a Battery Energy Storage Purchase Agreement with the BESS developer selected through bidding, and a Battery Energy Storage Sale Agreement with the end procurer, on a back-to-back basis.

Sharad Mahendra

executive
#10

Back in March ’24, the company executed a Battery Energy Storage Purchase Agreement covering the inaugural project of 500 megawatt-hour — structured as 250 x 2 — drawn from the allotted 1,000 megawatt-hour. Then, on January 2, 2025, which falls in the current year, CERC issued an order declining to allow tariff adoption, noting that the tariff proposed did not line up with prevailing market prices, and attributing that to a delay by SECI in signing the Battery Energy Storage Purchase Agreement along with the Battery Energy Storage Sale Agreement. We have filed an appeal against that order with APTEL, and we are confident it will be examined, since plenty of precedents exist in this area of tariff adoptions — tariffs having been adopted before. So an appeal has been filed, and we await the outcome. Turning to storage, our PSP project — awarded in October ’24, under which we are building 12 gigawatt-hour of pumped storage plant at Bhavali in the state of Maharashtra, tied up with MSEDCL — we have signed the PPA. We have 48 months from October ’24 to finish the project. The energy storage facility agreement covers supply of energy storage capacity across a period of 40 years, under which the company is entitled to a fixed capacity charge of INR84.66 lakhs per megawatt each year.

Sharad Mahendra

executive
#11

Now turning to how operations performed during the quarter. Net generation for the period was 6.8 billion units, a 10% rise year-on-year, helped by an 18% year-on-year jump in renewable generation. Contributing factors were additions to RE capacity as well as greater thermal output. For the tied-up portfolio, total net generation climbed 7% year-on-year in the quarter, whereas short-term generation, hydro included, grew sharply at 28% year-on-year. On the thermal side, net generation was 8% higher year-on-year, supported by 571 million units coming from JSW Energy Utkal Unit 1. Long-term thermal generation rose 4% year-on-year, and short-term generation was up 23% year-on-year. The average PLF for our thermal assets is 72%, against the country's average thermal PLF of 66.7%. The 18% year-on-year growth in renewable generation came notably from 928 megawatts of wind capacity added over the last 12 months, along with a strong 14% year-on-year rise in hydro generation thanks to better hydrology. Thank you, friends. That said, I will now hand over to Mr. Pritesh Vinay, CFO and Director, Finance, to speak about the quarter's financial performance. Thank you very much.

Pritesh Vinay

executive
#12

Thanks, Sharad. Good evening to everyone who has joined this call on the third quarter and nine months results. To follow on from Sharad's point: overall generation rose 10% Y-o-Y, yet total revenue was largely flat, and the main cause was that extra sales from the new RE capacity and Utkal Unit 1 were offset both by lower short-term realization at Ratnagiri and Vijayanagar and by a lower tariff at the hydro plant, owing to the depreciation policy change under the CERC tariff regulations. EBITDA for the quarter came in at INR1,115 crores, a decline of 9% Y-o-Y. Another thing that happened in the quarter is that we commissioned roughly 377 megawatts of incremental wind capacity, and that capacity has come in essentially after the monsoon's peak season.

Operator

operator
#13

Apologies for cutting in, sir. Sir, at the moment you come across as somewhat far away.

Pritesh Vinay

executive
#14

Yeah. Does that work better?

Operator

operator
#15

That's a lot better, sir. Please, go right ahead.

Pritesh Vinay

executive
#16

Yes. What I was saying is that during the quarter we commissioned 377 megawatts of wind capacity, and that came in after the peak generation season. Normally, it arrives in a lean season, and on top of that, it wasn't available for all 90 days of the quarter. So additional capitalization has come from the new capacity being commissioned, and that pushed both the finance cost and the depreciation higher. Because of that, profit before tax declined, and the reported profit after tax for the quarter came to INR168 crores, which is a drop of 27%. If you look at the nine-month performance, revenue was largely flat, while EBITDA also grew only marginally, largely flat at roughly INR4,600 crores, and profit after tax for the nine-month period came in at INR1,543 crores, which is up by around 12%. On the balance sheet, as the company keeps growing and putting additional amounts toward capex, net debt at the end of December was approximately INR26,500 crores, with cash and cash equivalents at just under INR5,000 crores. That's a sequential rise in net debt of roughly INR1,575 crores. The leverage ratio remains healthy. We reported net debt to TTM EBITDA of 4.5 turns.

Pritesh Vinay

executive
#17

The extra capitalization has caused debt at the operating companies to rise by roughly INR3,000 crores. So if you set aside capital work in progress — which accounted for around INR10,200 crores of net debt — net debt at the operating company came to INR16,250 crores, and that worked out to a net debt to EBITDA ratio of 2.8 times. The weighted average interest cost crept up slightly, thanks to annual resets on certain facilities and some lenders raising the MCLR, yet it remained comfortably under 8.9% as the quarter closed. On receivables, things are again largely under control. Total receivables came in at INR2,500 crores as of the end of December. Days sales outstanding, counting the amount not yet due, was approximately 96 days. Much of what was overdue at December's close has since been collected during January. That covers the broad picture on our financial metrics. I think I'll leave it there. Operator, please open the floor for Q&A.

Operator

operator
#18

Thanks a lot. At this point we'll open things up for questions. <<operator_script>>. Our first question is from Mohit Kumar at ICICI Securities. Go ahead, please.

Mohit Kumar

analyst
#19

Yes. Thank you, sir. I appreciate the chance to ask. My first question is this: with those 2 big acquisitions and a really big pipeline of assets still under construction, how are you thinking about leverage?

Pritesh Vinay

executive
#20

Mohit, that's a fair question. Let me restate the position we've held consistently over the past 2 years, ever since we began this growth journey: our strategic priority is safeguarding the credit ratings, and any growth opportunities we choose to pursue will be kept comfortably inside the guardrails on credit metrics so that the ratings stay protected. In particular, since you raised it in your question, I want to reiterate and draw everyone's attention to the fact that after what you're describing as 2 very large acquisitions — which I fully agree with — even following those, if you look at the flash issued by the credit rating agencies at the end of December, the agencies are comfortable keeping our AA with a stable outlook after digesting these 2 large acquisitions, because what is likely being under-appreciated is that these 2 large acquisitions also bring large EBITDA with them. They don't merely add leverage; they add EBITDA as well. So from an overall ratio standpoint, we would be comfortable. Naturally, we've also correctly spoken about the organic growth pipeline. And so, if you remember, roughly a year back, at this same time, we were discussing an acceleration of growth driven by a very supportive returns environment.

Pritesh Vinay

executive
#21

So to get ourselves better prepared, we went ahead and did a capital raise — an equity capital raise — right at the beginning of the fiscal year. That was done precisely with the aim of building a war chest and making sure the balance sheet stays healthy so that growth is protected. So I just want to restate that, yes, large acquisitions, but ones that come with a strong EBITDA generation and cash flow generation profile, and we will give strategic priorities in order to protect the ratings.

Mohit Kumar

analyst
#22

Got it. My second question concerns KSK Mahanadi. What's the plan there? Is there a plan to add capacity by 1 unit, or more than 1 unit, over the medium term? And what's the NCLT status for the other SPV — I believe all the SPVs are under NCLT, correct, water and rail? Could you help us with that?

Sharad Mahendra

executive
#23

Look, that process is already underway. As you correctly pointed out, the other two SPVs are also before NCLT, and those proceedings have reached an advanced stage. So all of that was taken into account when we went in for this. On KSK Power, we'd like to note that it is already at NCLT, hearings should happen shortly, and we anticipate a quicker, earlier ruling there. On the capacities — the balanced capacities we're discussing — we'd just like to point out that the operational capacity, which makes up 50% of the total and equals 1.8 gigawatts, is fully operational and tied up. On the balance capacity, we have to remember — I've said this before as well — that most of the balance of plant is finished: whether it's power evacuation, the water pipeline, or running the plant, everything stands ready for the full 3.6 gigawatts of plant capacity. And on top of that, for the remaining 1.8 gigawatts of expansion, a significant portion at one of the units is already done, and partial work has been completed at the other two as well. So we're quite confident that the one upside here — namely, raising the balanced capacity to bring the entire 3.6 gigawatts into operation — will come in significantly below the benchmark cost of building a new greenfield capacity.

Sharad Mahendra

executive
#24

So that's in place, and we'll be planning for it as and when the IBC process is finished.

Mohit Kumar

analyst
#25

Got it. Thanks, and best of luck.

Operator

operator
#26

Thanks. We’ll take our next question from Rajesh Majumdar at B&K Securities. Rajesh, please go ahead.

Rajesh Majumdar

analyst
#27

Good evening, sir, and thank you for the chance to speak. Sir, my question — the first one — concerns the recent CERC order, which in fact does not pay for infirm power. It is dated Jan 23rd, and it actually does not pay for infirm power during the period between a plant's commissioning and commercial generation. Since Ind-Barath 2 has only just been commissioned, and we also have so much thermal capacity being added at KSK Mahanadi, including capacity additions, what kind of impact do you foresee from this? And B, do you think it can change?

Sharad Mahendra

executive
#28

Look, yes, regarding this new regulation that has come in, it won't have any meaningful effect, because we need to look at what it states about there being a ramp-up of the unit. And whenever we're working on the project, the whole process, there has been — with Ind-Barath, there has been very solid learning while ramping up the first unit to full capacity. And we are in a position to ramp this unit up to full capacity and demonstrate it for 72 hours. So it won't take a significantly long time, and we're confident that we will reach this capacity at much earlier timelines, keeping in mind the learnings from Unit 1. So it won't have any meaningful effect. And whatever we capitalize before we do the COD, everything is well within the budgeted numbers that we have planned and budgeted for this commissioning and up to COD. So this is well in control. And in the same process, it will be followed whenever we go for the COD commissioning and COD. So if it's a very large timeline to stabilize the unit and reach full capacity to demonstrate, I don't see any significant challenge in that.

Sharad Mahendra

executive
#29

We've handled that assessment on our own.

Rajesh Majumdar

analyst
#30

Sir, regarding the KSK Mahanadi project in the NCLT — do you see that becoming an issue for the new 1,800 megawatts you envisioned, given that those would take considerably longer in terms of the gap between the commissioning date and the COD?

Sharad Mahendra

executive
#31

No, 1.8 gigawatts of balance — what exactly are you referring to?

Rajesh Majumdar

analyst
#32

Correct, that is accurate.

Pritesh Vinay

executive
#33

No, no, Rajesh — look, the top priority is bringing those assets under our control, correct? I'd ask that we don't get ahead of ourselves here, because first we have to be in the saddle and actually own the asset, and only after that will we need to evaluate possible expansion optionalities, offtake optionalities, techno-economics — a whole host of work — before we'll be in any position to press the button on expansion post acquisition, right? So I think commenting on that would be a bit premature, yeah?

Rajesh Majumdar

analyst
#34

No, no, I appreciate that. Thanks, sir. For my second question, sir, regarding O2 Power and KSK Mahanadi: could you share some detail on the EBITDA we could generate at, let's say, 1,800 megawatts for KSK and the full capacity of O2 Power, say FY ’27 or thereabouts — what additional EBITDA might these two acquisitions bring?

Pritesh Vinay

executive
#35

No, Rajesh. At this point, I don't believe so, because it's…

Rajesh Majumdar

analyst
#36

Yeah, maybe a bit of color on that.

Pritesh Vinay

executive
#37

KSK's historical figure is out there—last financial year, fiscal 2024, they posted EBITDA of INR2,600 crores. That's essentially public domain information, so I'm glad to share it since there's no NDA breach involved there. For O2, we've given guidance on steady-state EBITDA. Once we reach 2.3 gigawatts of operational capacity, which we expect around the middle of this year, that portfolio should produce roughly INR1,500 crores of EBITDA on an annualized run-rate basis. There's a specific slide we included in the deck uploaded when O2 was acquired. So at 2.3 gigawatts, you'll see a steady-state run rate of approximately INR1,500 crores. At 4.7 gigawatts, the anticipated steady-state EBITDA run rate comes to about INR3,750 crores. Beyond that, we can't add anything more.

Rajesh Majumdar

analyst
#38

Understood, sir. Just a quick bookkeeping item from me. Could you tell me what the merchant tariff came in at for Q3?

Pritesh Vinay

executive
#39

Regarding the merchant tariff, we don’t disclose it, but you’ll be able to work it out. Let me walk you through how to do that. In the total generation shown in the appendices, you’ll see the split between total and long-term, and the difference is short-term volume. There’s an EBITDA bridge where we discuss the EBITDA impact from that. You know how the coal price indices have moved. So you’ll be able to gross it up, yeah?

Rajesh Majumdar

analyst
#40

Thanks very much, sir, and thanks again.

Operator

operator
#41

Thanks. Our following question is from Sumit Kishore with Axis Capital. Go ahead, please.

Sumit Kishore

analyst
#42

Good evening. To start, regarding that 7.8 gigawatts beyond the 10-gigawatt target for FY ’25 for which you hold PPAs, where do you stand on transmission evacuation and land for those projects?

Sharad Mahendra

executive
#43

Yeah, Sumit, that's a really relevant point — I'd say so, since everybody is asking about connectivity and land, which the industry is facing as a challenge. But we acted on it, and for the majority of the capacity, the PPAs we're working on, we're fully ready, whether it's land or connectivity. And to get around the connectivity issue, a significant portion of this total 7.8 gigawatts sits within the state, for that same state, through STU connectivity, which is available in most states. So that was the step we had started acting on about nine months, a year back. So that's why our readiness — and we are absolutely certain that the 7.8 gigawatts of the PPA signed, these projects will be completed within the time frame as per the PPA terms, and connectivity and land will not be a challenge in both these cases.

Sumit Kishore

analyst
#44

So the majority of these projects aren't going to need CTU?

Sharad Mahendra

executive
#45

For the most part, wherever the CTUs are located, there are small capacities in places where CTUs exist and are available. That said, all 7.8 gigawatts is fully secured when it comes to connectivity as well as the land. So as far as land and connectivity go, there is no difficulty for the 7.8 gigawatts of projects to be finished within the timeline set out under the PPAs.

Sumit Kishore

analyst
#46

Sir, my next question is really about the industry as a whole. With battery economics continuing to evolve, what new trends are you observing when it comes to sizing wind and solar for FDRE projects? In what ways is that shifting how wind and solar get sized in FDRE projects?

Sharad Mahendra

executive
#47

Once more, that's a really good question, and on the point of FDRE, what we've observed over the past six months is a modest shift — it's really about improved planning for projects so the right solution reaches the end buyer, matched to their needs. In FDRE, most cases earlier involved a hybrid of wind and solar, perhaps paired with storage, typically at one single location, and that was limiting the options. Now, in fact, in the C&I space we've also signed where, to optimize and extract the best generation and the lowest cost per unit of investment, wind sits in one state connected with CTU and solar is in another state, together with battery if needed, or if it's a hybrid, and we deliver the solution to that same customer. So that's one case we've seen — a move from co-located to diversified hybrid solutions, with storage included, is one we're seeing. Another thing witnessed over the last six to eight months, if you've been tracking the kind of bids coming out, is that with so much solar capacity being added — and whatever capacity addition the country has seen, roughly 20 gigawatts in maybe the first nine months, 19 gigawatts to 20 gigawatts, with 16 gigawatts being solar.

Sharad Mahendra

executive
#48

Even with growth of 4.5% in the evening peak hours and early morning peak hours, which is moderate, the demand and supply situation is going to get even more challenging. Demand is going to keep growing. So because of that, solar plus battery energy storage projects are now coming up as the solution, and they have a two-pronged advantage. The first is solar during the daytime, charging the battery, and then releasing during the evening peak hours when demand is higher. The second is better utilization of the country's grid infrastructure, because a solar project blocks capacity for 24 hours and only uses it for eight hours. So this is better utilization of the country's assets, which are also their transmission assets, and it is a solution for peaking. So these are some of the changes we are seeing. Of course, states are now working very seriously on a solution for peak hour requirements, because five years from now the gap is going to be significant even with continuous demand growth of 5% to 6%. For that, pumped storage, as a longer-term solution, a storage solution, is again now getting due importance and preference, and states are coming up with their bids for pumped storage as well.

Sharad Mahendra

executive
#49

So these are major shifts we’ve observed over the past six months.

Sumit Kishore

analyst
#50

Yes, sir. For my last question, I'd like to focus on your energy storage projects—specifically stand-alone BESS, SECI XV, and Group Captive. So, following the CERC order, has anything slowed down in your work to commission the SECI stand-alone project, given that it includes a merchant component? And how are the rest coming along on commissioning? And could you give us some detail on the pricing you'd expect, or the capex for the battery capacity you build?

Sharad Mahendra

executive
#51

Look, first, there isn’t any slowdown. We’re seeing plenty of bids come in, people are taking part, and short-duration battery energy storage is the top option at the moment, because it’s needed quickly. So that’s the first point: no slowdown. Beyond that, as I mentioned in my opening remarks, we now have a situation where the decision has been challenged. So I don’t think — we need to keep in mind that when anyone assesses and compares what price was discovered at that time, for that project, tariff adoption has not happened yet, and we have challenged it. And whatever tariff discovery exists today, right now, it looks very high on the face of it, but we have to look at two significant differences between that project and the current projects that are coming, which also have good viability: this one had viability gap funding of more than maybe 40%-45% in terms of the tariff discovered that we obtained. And besides that, this is a BOOT model, where after 12 years the asset gets transferred. Now the bids coming in are not on the BOOT model in most cases.

Sharad Mahendra

executive
#52

So it isn’t really an apples-to-apples comparison with what today’s project cost is — what the cost is — the tariff discovery that’s there. So that’s what we’d like to say regarding capex and all. These numbers are very dynamic. The tariffs being discovered depend on what the design is, what the storage is, what the loading is. So this is dynamic. So that’s what I’d like to mention for this thing you just asked.

Sumit Kishore

analyst
#53

Okay, so on the last call, you said that the 1 gigawatt-hour BESS would be commissioned by June ’25. I just wanted to check — is that plan still on track?

Sharad Mahendra

executive
#54

Given how this has unfolded, it could take perhaps a few — contingent on how quickly the ruling arrives, it might take perhaps a few months either way, and that's it. Once this legal issue is resolved, we'll be in a stronger position.

Sumit Kishore

analyst
#55

Since that capacity can be swapped around with your other…

Sharad Mahendra

executive
#56

Yes, yes, definitely. Every one of these is a containerized solution, and that is completely out of the question. Within Group Captive and our other sites, we have a sufficient order book to utilize those same assets. So that poses no challenge whatsoever.

Sumit Kishore

analyst
#57

Sure. Thanks.

Operator

operator
#58

Thanks. <<operator_script>>. Our next question is from Nikhil Abhyankar of UTI Mutual Funds. Go ahead, please.

Nikhil Abhyankar

analyst
#59

Thank you, sir. Sir, my first question concerns generation at Mytrah. Did we see a dip in Q3? And was that because of machine availability, or was it due to lower wind?

Sharad Mahendra

executive
#60

So look, Mytrah’s generation came in a bit lower, and the main reason is that wind speeds were somewhat under what we had anticipated — but that’s very much a temporary, short-term thing. We don’t see any lasting effect from it. On the machine availability side, though, there was no issue at all. Machine availability is still running at nearly 98% to 99%. So availability is holding up; it’s just the wind. Availability stays in that 97% to 98% range.

Nikhil Abhyankar

analyst
#61

All right. And sir, following the announcement of our O2 acquisition, I believe they secured a SECI award for FDRE VI covering 200 megawatts x 4 hours, and the disclosed tariff comes to roughly 8.5. Will that project be transferred over to us as well?

Sharad Mahendra

executive
#62

And when that takes place, then yes — absolutely — yes, it's in place.

Pritesh Vinay

executive
#63

That's a component of the platform.

Sharad Mahendra

executive
#64

It's a component of the platform. So 4.7 will then turn into more than 4.9 gigawatts.

Nikhil Abhyankar

analyst
#65

Alright. And sir, just one last question about capex. How much had been spent through nine months? And what do you expect capex to be in FY ’26?

Pritesh Vinay

executive
#66

Nikhil, during the first nine months, we've spent roughly INR6,200 crores in total capex. And for the full year, we expect to finish at close to INR10,000 crores. If you remember, we said before that we anticipated INR15,000 crores of total capex this year. But naturally, the current batch of projects we intend to finish is finishing up. And we had expected a larger investment in the organic future projects. But given the constraints Sharad mentioned earlier — and some of you have raised questions on this too, and it's a reality in the sector regarding connectivity and so on — what we've done instead, as you'd have noticed from our strategic actions this quarter, is to press the pedal on the inorganic side, right? The aim is to keep delivering growth at a certain CAGR. So, since organic seems somewhat challenging to scale up once everything is considered, we've gone ahead and pressed the pedal on the inorganic route. And this also buys us time for better planning and for taking long lead time actions well in advance, so we can maintain the organic growth trajectory going forward, yeah.

Nikhil Abhyankar

analyst
#67

Got it. So with transmission constraints in play, should we anticipate any delays to renewable capacity additions across the 28 gigawatts we have locked in?

Pritesh Vinay

executive
#68

So it's the reverse, correct? What we've actually said publicly is that our goal was to become a 20-gigawatt generation company by 2030. We shared this, I believe, in 2023 — May 2023 is when we shared it with the market. Now what you're seeing before you is already a platform just shy of 30 gigawatts, and hopefully we should be able to deliver all of that well ahead of 2030, right? So clearly, growth is accelerating. And there will need to be calibration. There will need to be — since it's block and tackle, project by project, location by location. We actually haven't quantified anything past 10 gigawatts on an annual basis. But if I were to just do rough math, assuming that at least by the June quarter, if we're able to consummate both KSK and O2, plus our own reaching the 10-gigawatt mark, we'll be a 14-gigawatt operating platform by June ’25, right, which is a few months from now. So — and then we'll take it from there, right? When we come back with our annual fiscal year results, we would have gone through the business planning exercise for the next year, and we'll be in a better position to give you an organic capacity accretion target for fiscal ’26.

Pritesh Vinay

executive
#69

Yeah?

Nikhil Abhyankar

analyst
#70

Absolutely, sir. Thank you, and I wish you all the best.

Pritesh Vinay

executive
#71

Thanks.

Operator

operator
#72

Thanks. Our following question is from Saket Yadav at India Capital. You have the floor.

Saket Yadav

analyst
#73

Hello. I’ve got a couple of questions regarding KSK Mahanadi. From what we understand, there are still lenders holding 26% of the stake. So I just wanted to clarify: is the bid you’ve submitted for the full 100% stake, or will those lenders continue to hold that 26%?

Pritesh Vinay

executive
#74

No, no — 26% is going to remain with the lenders, but the lenders hold a put option that becomes active after one year. And they have the right to exercise that put within one to five years. And obviously, no lender has any strategic intent to stay on as a minority equity investor in a non-core business, right? So their idea is to maximize their recovery and recoup all the losses, etc., of the past, right? So there is a plan. Step one is to get through the regulatory adjudication process of getting the asset in control, and then we will get into discussions with the lenders on the balance 26% stake.

Saket Yadav

analyst
#75

Okay, got it. Thanks. Moving on to my next question, which is also about KSK Mahanadi. I'd like to get some clarity, because I came across something indicating that somewhere between INR3,000 crores and INR4,000 crores is sitting with one of KSK Mahanadi's units. So what I want to know is whether the company will take that in, or whether it goes out to the lender?

Pritesh Vinay

executive
#76

No, no, no. Look, the RFP terms at the point the IBC process began stipulated that all cash accrued, receivables, EBITDA generation, etc. — every bit of it — goes to the lender. So any resolution applicant submitting plans for the CoC's consideration factored that in, correct — as an applicant, your only concern is how much money you're offering to the financial creditors and to the operational creditors. There was a specific scoring mechanism, and so, as an objective, as a winning strategy, your aim is to maximize the score and proceed on that basis. Therefore, until the plan is adjudicated — or, until the plan is implemented or consummated, whatever accrues up to then goes to the lenders. So, no surprise should arise on that front. Yeah?

Saket Yadav

analyst
#77

Got it, and thanks. Congrats on the acquisition, folks — wishing you all the best.

Pritesh Vinay

executive
#78

Appreciate it.

Operator

operator
#79

Thanks. Before we move on to the next question, we ask that everyone limit themselves to 2 questions per participant. Should you have any additional follow-ups, you're welcome to rejoin the queue. Our next question is from Swati Jhunjhunwala at JM Financial PMS. Please go ahead.

Swati Jhunjhunwala

analyst
#80

Yeah, hi. Thanks for taking my questions. Sir, my first question is about the green hydrogen. So, we were expecting to commission it soon. Can you give us any idea of the revenue and EBITDA we can generate from this?

Pritesh Vinay

executive
#81

No, Swati, not at this point, please. We will finish it, and as we mentioned when this pilot project was announced, the approach that has been developed is that we will earn a 15% equity IRR on this project, which is to be fully amortized across seven years. So that is how the economics will work. So once the project is completed, the project cost is frozen, and on that basis, using normative debt equity and the underlying equity IRR, the tariff will be determined. But I mean, okay, when you look at our total balance sheet, even if that number changes materially, I'm sorry to say that's going to be a rounding error, right? It's a very small project. So, it is not going to materially move the needle either way. Yeah?

Swati Jhunjhunwala

analyst
#82

Understood. Turning to commissioning: at present we sit at nearly 8.1 gigawatts, with a further 7.8 gigawatts being built. If by June we bring another 1.8 gigawatts online, that takes us to 10 gigawatts, and adding the 4 gigawatts from the acquisition, the remainder is under construction — so if you could provide even a rough breakdown between FY ’26 and ’27, that would be helpful.

Pritesh Vinay

executive
#83

A few minutes back, while answering a different question, I mentioned that when we return in May with the annual results — after completing our annual business planning exercise — we'll be in a position to provide FY ’26 capacity addition guidance, and from there the rest will just be basic arithmetic for you.

Swati Jhunjhunwala

analyst
#84

Got it. Okay, thanks.

Operator

operator
#85

Thanks. We’ll take the next question from Samarth Khandelwal at ICICI Securities. Go ahead, please.

Samarth Khandelwal

analyst
#86

Hello there. Can you hear me?

Sharad Mahendra

executive
#87

Yes.

Samarth Khandelwal

analyst
#88

Yes, sir. First off, congratulations on the KSK Mahanadi acquisition. Second, sir, my question concerns the battery energy storage system side. If I am supposed to—how should I interpret a 250-megawatt by 500-megawatt-hour battery project? Regarding how much time the solar project would need to charge that quantity of battery, how long would we be able to supply, and how many units would it be able to supply to the customer? What would the battery life be? How much would the capex be per megawatt-hour, if you could help me with that? Thank you.

Sharad Mahendra

executive
#89

Look, we need to grasp this: when we refer to 250 megawatts of battery energy storage capacity, and with a 2-hour discharge that gives us 250 x 2, which equals 500 megawatt-hour. Converting that into energy, and supposing we charge it using solar — so it's solar plus, or any type of input energy — we must assume that this 500 megawatt-hour discharge is what we have. There may be an efficiency loss between the input energy and the output energy, depending on battery design, how you design it, how efficient it is — perhaps 15%, 18%, 20%, whatever incremental energy for charging is needed. So out of 100, maybe 120 is the input, or 115, or perhaps the output will be 100 — that's the ballpark. Regarding battery life, battery life is something where — according to the PPA term, the project gets designed so that the minimum availability of the battery is always maintained. So normally you could use the term repowering of the battery perhaps once in four to five years, which forms part of the capex depending on what the requirement is, done to keep up the output. But the benchmark is that after 12 years — mostly most of the storage bids that have come in are for 12 years — after 12 years, at least 70% of the battery life is available even without doing the repowering.

Sharad Mahendra

executive
#90

So you let the battery degrade as it normally would, and even after 12 years, 70% of the battery life remains in energy terms. That's what I'm telling you. The capex figure, as I mentioned, hinges on many things. Handing over a capex number right away is difficult, since plenty of factors vary — whether it's connectivity, land, all of it. So here's the next point you can make: 70% of the battery life is still there after 12 years.

Samarth Khandelwal

analyst
#91

So would we be using a lithium-type or a sodium-type battery? And second, would we be billing the customer according to the number of units supplied, or according to how much the solar generates to charge that amount of battery?

Sharad Mahendra

executive
#92

It really comes down to how the bid is structured. In most cases, when a storage project stands on its own, it isn't priced per unit — it works as a rental or lease arrangement, charged per megawatt, per month. If you have 250 megawatts for two hours, the bid typically calls for 250 megawatts of capacity, so the rental is per megawatt, per month, and that is assured. The only caveat is that plant availability has to be maintained according to the terms. When a battery is involved, there are certain cases — some bids also come in energy terms — where it's combined with solar plus two hours of battery discharge in the evening, and based on the minimum number of units needed during the evening, those are per-unit bids as well. So it all hinges on the bid terms, which means it's either a rental model. That said, the majority are rental models.

Pritesh Vinay

executive
#93

And Samarth, on the other part of what you asked: up to now, we haven’t heard of sodium batteries being deployed in commercial large-scale operations. From what we understand — and it’s limited — those are only lithium-ion batteries. Operator, could we make that the final question, please? We have — or perhaps we can take one more question, yeah? Since Sharad and I need to hurry off to something else. Yeah?

Operator

operator
#94

Sure. Thanks.

Pritesh Vinay

executive
#95

Let’s take one final question, please.

Operator

operator
#96

Alright, we have time for one final question, and it comes from Ritwik Sheth at One Up. Go right ahead.

Ritwik Sheth

analyst
#97

Yeah. Hi. Good evening, sir. Sir, actually, this is really a clarification I wanted to ask. Earlier in the call, you brought up the O2 acquisition — the 2.4 gigawatts that's under development — and said it would need a capex of INR13,000 crores. Did I hear that correctly?

Pritesh Vinay

executive
#98

Yes. So, Ritwik, you’re correct about that. And there’s no need to depend on what you hear or on how well we speak. What I’d ask is that you visit our website or check the stock exchange filings — a presentation was put out when the O2 Power acquisition happened in the last week of December. On one specific slide, you’ll find two tables, and those will give you every number tied to it, yeah. Expected capex runs from INR13,000 crores to INR14,000 crores. That corresponded to a remaining 2.4 gigawatts.

Ritwik Sheth

analyst
#99

Understood. And regarding the KSK acquisition, what amount of pending capex would be needed in order to operationalize the remaining 1.8 gigawatts?

Sharad Mahendra

executive
#100

As I mentioned before, we'll be disclosing the figures once that process wraps up. But during due diligence—and I also noted this in my opening remarks—the plant's total capacity, when fully up and running, stands at 3.6 gigawatts, with 50% of that already operational. Still, the remaining portion of the plant, most of it, is ready to handle the full 3,600 megawatts, be it the transmission evacuation line or the water pipeline. Beyond that, there are three additional units that have reached completion in part. For one of those units, over 40% of the work is done. The other two units likewise have partial work finished. So the capex per megawatt at which the plant reaches full operation will be significantly lower than the benchmark greenfield cost for 1.8 gigawatts. That's what I can share for now—perhaps at the appropriate time, we'll come back with the precise numbers.

Ritwik Sheth

analyst
#101

All right. Certainly. Thanks a lot, and good luck to you, sir.

Sharad Mahendra

executive
#102

Appreciate it.

Operator

operator
#103

Much appreciated. At this point, folks, I’ll pass things back to the management team for their closing remarks.

Sharad Mahendra

executive
#104

Thanks, everybody. I believe it has — appreciate your joining us for this third quarter. And as I noted in my opening remarks, we expect things to improve in the year ahead based on what we're seeing and anticipating, and we're interpreting that perhaps more government spending as well as private investment is likely to rise now, which will certainly have a favorable effect on the power sector too. Many thanks for being with us.

Pritesh Vinay

executive
#105

Should you have any follow-up questions, don't hesitate to reach out to our IR team. Thanks so much.

Operator

operator
#106

<<operator_signoff>>

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.