JSW Energy Limited (533148) Earnings Call Transcript & Summary
July 22, 2026
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and welcome to the JSW Energy Ltd Q1 FY27 earnings conference call, brought to you by JM Financial Institutional Securities Limited. Just a reminder that every participant line is in listen-only mode, and you'll have a chance to ask questions once the presentation wraps up. <<operator_script>> At this point, I'll turn the conference over to Mr. Sudhanshu Bansal of JM Financial Institutional Securities Ltd. Thank you, and the floor is yours, sir.
Sudanshu Bansal
analystThanks, Rao. Hi everyone. I'm speaking for JM Financial, and I'd like to welcome all of you to JSW Energy's 1Q FY27 earnings call. Joining us on today's call is the company's leadership team, headed by Shri Sharad Mahendra, sir, Joint MD and CEO; Mr. Chandrasekaran Prabhakaran, CFO; and Mr. Vikas Chaudhary sir, Head Investor Relations and ERM, together with the other team members. I'll now turn the call over to Sharad sir for his opening remarks, and after that we'll open the floor for the Q&A session. Thank you so much, sir, for kindly being present and for giving us the chance to host the call. Over to you, sir.
Sharad Mahendra
executiveThanks, Sudhanshu. Good afternoon, everyone, and thanks for being with us today for JSW Energy’s Q1 FY27 earnings call. I trust you and your families are doing well. We’ve kicked off FY27 on a remarkably strong footing, and I’m very pleased to walk you through some of the key highlights. For JSW Energy, Q1 FY27 has been a landmark quarter. We achieved — excuse me — we achieved one of the biggest single-quarter capacity additions in our company’s history and among the largest anywhere in the sector, bringing 873 megawatts online during the quarter, which lifts cumulative capacity additions to nearly 1.1 gigawatt to date once you include the capacity brought online during July up to now. Within that, 150 megawatt came from the early commissioning of Tidong Hydro, which had originally been slated for October ’26; it also added an incremental EBITDA of INR20 crores to INR22 crores in quarter one on its own and lets us capture the hydrology season currently under way. Acquired only in January 2026, this speed of commissioning speaks to the integration and execution capabilities of our teams on this project. That momentum has held firm into quarter two as well, and in July to date, as I mentioned earlier, we have already brought online roughly 225 megawatt of organic renewable energy capacity, which takes our capacity additions from April ’26 through today to approximately 1.1 gigawatt, as I said earlier. For more detail, please refer to slide number 7 of our results presentation.
Sharad Mahendra
executiveWe’re still solidly on course to hit our FY27 annual target of 3 gigawatt capacity addition along with INR20,000 crores of capex, and we’ve already delivered close to 36% of the FY27 capacity guidance while exceeding roughly 87% of the total capacity added during all of FY26. Slide 21 covers this. Another major milestone for us was the deleveraging we achieved by successfully completing an INR10,150 crores capital raise recently — the biggest growth capital raise in the Indian power sector. That came together through a mix of approaches that show strong market confidence in JSW Energy’s growth story. It had three parts. First, a preferential allotment to promoters of INR3,000 crores, of which INR1,125 crores has already come in, and the rest is expected before June 2027. Second, a partial stake sale in JSW Steel that monetized 2.5 crore shares from our total 7 crore shareholding, worth INR3,150 crores, and third, a QIP of INR4,000 crores anchored by marquee global and domestic institutional investors. All together, that leaves us with an ample liquidity cushion of about INR12,880 crores in cash balances, comfortably funding the equity portion of our estimated INR20,000 crore FY26 capex — FY27 capex, sorry — and 2030 growth plans with headroom for future growth.
Sharad Mahendra
executiveOur balance sheet discipline keeps getting stronger. On a trailing 12-month basis, net operating leverage improved to 4.95 from roughly 5.2 in FY26, even while we ramp up growth investments. By 2030, we are committed to bringing net leverage under 5 times. I'm also glad to report that, reflecting our strong green focus and long-term commitment to carbon neutrality, our growing renewable portfolio allowed us to avoid about 16 to 7 million tons of CO2 emissions in fiscal '26 and roughly 4.5 million tons in quarter one of FY 2027. That figure rests on the prevailing Indian grid emission factor. Now, before diving into our detailed quarter one performance, let me offer a few sector observations. India's power sector got off to a strong start in FY 2027, with quarter one demand up 8.5% year on year — a sharp turnaround from the muted 0.9% growth in FY 26. This strength was broad-based, driven mainly by prolonged heat wave conditions, delayed monsoon progression and higher cooling appliance usage, which pushed up residential and commercial consumption. That momentum has carried into July as well, with month-till-date demand growth in July at a robust almost 12%.
Sharad Mahendra
executivePeak power demand hit 271 gigawatt in May, which already exceeds the FY26 full-year peak of 245 gigawatt. Then again, on July 16, we recorded another peak of 270 gigawatt, and demand is projected to reach 300 gigawatt in the near term. We see this as early validation of the medium-term structural story we have consistently articulated. India's industrialization, urbanization and rising per capita consumption underpin a clear 5% to 6% long-term CAGR in power demand. Moreover, the ongoing crisis in West Asia highlights the strategic importance of India's energy self-sufficiency agenda under Atmanirbhar Bharat, which further strengthens the case for accelerated electrification and sustained long-term demand growth. India's growing global economic structure, contributing approximately 8% of the world GDP on a PPP-adjusted basis, together with its continued high GDP growth outlook, should support sustained power demand growth. On the merchant market, this improving demand backdrop is now clearly visible. Day-ahead market prices, which averaged around INR3.86 per unit through FY26 on muted demand, have formed meaningfully in quarter one of FY27, rising to INR5.10 per unit from about INR4.40 per unit in quarter one of FY26, a nearly 16% year-on-year increase. Against this improving landscape, let me take you through our performance for the quarter.
Sharad Mahendra
executiveGiven the substantial capacity we brought online, our installed base is now roughly 14.6 gigawatt in total, and renewables make up approximately 61% of that, alongside 5.7 gigawatt of thermal capacity that delivers dependable dispatchable baseload. That balanced portfolio stays at the heart of our strategy—letting us take a meaningful part in India's clean energy transition while keeping the grid reliable through firm contracted thermal capacity. On the organic side, we keep assessing selected value-accretive acquisition opportunities that fit our strategic priorities and reinforce our growth platform. Along those lines, we executed a definitive agreement to acquire Maruti Clean Coal and Power Limited, which runs a 300 megawatt thermal plant located in Chhattisgarh. That plant holds a long-term power purchase agreement of 195 megawatt net with Rajasthan Discoms, with residual PPA life of 14 years. Beyond that, the plant supplies 5% power at variable cost to Chhattisgarh Discom. The remaining 64 megawatt is sold into the merchant market, while the coal is assured via a long-term fuel supply agreement with SECL and linkage under the Shakti scheme. Also, regarding our organic thermal growth, kindly turn to Slide 22. All key clearances have been received by our first Salboni plant. 100% of land has been acquired. Equipment orders are placed, and site work is now in full swing.
Sharad Mahendra
executiveRegarding the KSK brownfield expansion, the land, water, rail, transmission infrastructure, and environmental clearances are all already secured. Turning to vertical integration—a priority we've consistently discussed. On the thermal side, we raised our stake in the Toshiba JSW Power Systems joint venture to 10.7% from 2.4% previously. The purpose is to de-risk our equipment supply chain and build thermal capacity at one of the industry's lowest capital costs. Together with our ongoing acquisition of GE's boiler business, which we expect to close this quarter, we've now fully de-risked our thermal growth ambitions, giving us complete control over our build-out for both current projects and future opportunities. On the wind side, we commissioned our wind blade manufacturing facility at Halol, Gujarat, on 8th of June, with an annual capacity of 450 blades—enough to support roughly 600 megawatt per annum of wind installations, strengthening backward integration in the segment and supporting a lower LCOE. The second blade manufacturing facility, at Chitradurga in Karnataka, is expected to be commissioned in the current year, with work presently at an advanced stage. On the 5 gigawatt-hour battery plant, which we commissioned in quarter four of FY26, we've received our first large external order of INR440 crores. This engagement marks a step forward in the country's strategic expansion in the energy storage segment, reinforcing our commitment to building capabilities across the energy value chain.
Sharad Mahendra
executiveTo sum up, the first quarter of FY27 has confirmed the momentum we established across FY26. We're moving quickly on execution, making our balance sheet stronger, going further with vertical integration, and staying solidly on schedule to deliver Strategy 3.0 within the timelines we set. Now, turning to operational performance in the quarter. Net generation in quarter one FY27 was down slightly, 5% year-on-year, at 12.9 billion units, mainly because of lower output at Mahanadi and at our hydro plants. Our hydro portfolio added capacity year on year with Tidong and Kutehr coming in. Even so, generation across the portfolio as a whole fell by almost 26% year on year because of weak hydrology throughout the entire basin. National hydro generation declined 7% year-on-year. The Sutlej Basin was 39% lower year on year, and the Ravi Basin fell 24% year on year. This comparison needs to be seen in context. An early monsoon arrived last year, whereas this year winter ran longer in various areas of the Himachal Basin and snow melt started much later. With the monsoons now here, though, water flow has normalized. Generation in July to date has been excellent. With Karcham, Baspa and Kutehr all running above 100% PLF, we expect these plants to catch up and hit the design energy for the full year.
Sharad Mahendra
executiveIn addition, we keep getting capacity charges for plant availability even when output falls below the design energy. On the thermal portfolio, Mahanadi generation took a hit from a one-off evacuation availability of roughly 17 days during the quarter, and that is now fully normalized. Extreme wind conditions caused this. It led to an impact on the transmission line. The year-on-year loss came to roughly 184 million units, or a 7% decline year on year. This, however, will be classified under force majeure provisions. As a reminder, we enjoyed a strong quarter of merchant sales at Utkal last year. Quarter one was exceptional. Generation this time was broadly similar, but it was sold under long-term contracts instead. Looking ahead, the Utkal plant should deliver higher EBITDA thanks to stable operation and power supply under the PPA with Karnataka and Assam. On the whole, our thermal generation fell 6% year on year to 8 billion units. On coal prices, they rose year on year; using a specific index such as API-4 as a reference, it was $90 in Q1 of FY26 versus $113 in Q1 FY27, an increase of almost 25%. Our ongoing shift toward domestic coal has kept us resilient against this adverse fuel price movement.
Sharad Mahendra
executiveAlso, the amount of open capacity we have has now come down to less than 4%, and that gives our earnings some stability. I should also note that any movement in imported coal prices gets passed through, so there is no effect on JSW Energy’s power supply under the PPAs. Regarding the RE portfolio, our solar generation rose 29% and wind generation rose 3%, helped by a year-on-year capacity increase of 1,168 megawatt. Moving now to the financials for the quarter, many of you will already have seen these in the pre-call materials. Revenue for the quarter was broadly flat year on year, at INR5,437 crores. EBITDA followed the same pattern, edging up 2% year on year to INR3,103 crores. Our capacity addition for the year was 1,558 megawatt, and with new assets continuing to be capitalized on the balance sheet, both depreciation and interest expenses have risen accordingly. Year on year, depreciation was up 20% in quarter one, to INR890 crore, while interest cost rose about 16%, to INR1,519 crore — moves that are in line with the pace of capacity we are adding. Turning to the bottom line, profit after tax came in at INR533 crores, down year on year because of the higher capitalization impact as new assets are commissioned.
Sharad Mahendra
executiveIn line with that, profit after tax attributable to shareholders likewise declined, coming in at INR471 crores. Many of you know that notice has already been issued by us to exercise the call option covering the remaining 26% interest in Mahanadi. When that transaction completes, the outflow to minorities ought to reduce considerably. Moving to leverage — excluding the debt, sorry, excluding the debt linked to capital work in progress, our ratio of net debt to TTM EBITDA is approximately 4.95, which sits comfortably inside our financial guardrails and, as mentioned earlier, marks a substantial improvement over the 5.2 times reported in FY26. On liquidity, we stay well positioned, with cash and cash equivalents of roughly INR12,880 crores. In addition, our cash return on net worth, after adjusting for our JSW Steel shareholding, remains healthy at about 14%; it has fallen year-on-year mainly due to an increase in net worth from recent fundraisers. Overall, as I noted in my opening statement, this was a strong quarter, entirely consistent with our plans and with sharp focus on organic capacity addition and balance sheet deleveraging — both delivered decisively — and that momentum is carrying firmly into quarter two. That wraps up my opening remarks, and I am happy to take any questions from you.
Sharad Mahendra
executiveThanks.
Operator
operatorThanks a lot. We're moving into the Q&A portion now. <<operator_script>> Our first question comes from Sumit Kishore at Axis Capital. The line is yours.
Sumit Kishore
analystGood evening, and thank you for the chance to speak. First, a question about the macro situation as it relates to thermal. We've been observing that from 12:00 to 1:00 PM, a number of thermal power plants across the country are probably running under technical minimum. What has your experience been with your thermal fleet, and how do you expect this situation to develop in the times ahead?
Sharad Mahendra
executiveOkay, yes, Sumit, thank you. That's quite right, since this is the time when solar output reaches its highest point. Still, let me just say that in our case, aside from the load factor naturally coming down, what has happened — what we've seen through the whole quarter — is that thanks to the attractive tariffs at Mahanadi now, our backdowns, or curtailments, have been the lowest, on account of the merit order. The least we've hit, and in Utkal's case, the minimum load there which comes — for us the backdowns have possibly not dropped under 60% in most instances, though on a round-the-clock basis perhaps we are — perhaps, if you take July, when power demand has risen by nearly 12% so far, we've been running at over 85% PLF and above 90% availability. So we haven't seen any issue as far as the technical minimum goes. At other plants we don't require it, but we're building the capacity — the capability — to run even below 50%, which we've already accomplished at our Ratnagiri and Vijayanagar plants.
Chandrasekaran Prabhakaran
executiveSumit, let me just add that in those types of backdowns, we keep recovering our fixed costs. We really aren't affected. And if that situation comes up, we also have the flexibility to sell that into the merchant.
Sumit Kishore
analystAlright, so my second question relates to thermal. You've now brought in the 600 megawatt Mahanadi projects that are under construction, and when you put those together with Salboni Phase 1, how is the ramp-up going on BTG sourcing for those projects — especially the arrangement with GE tied to the acquisition you made, how is that shaping up? And what is your nameplate capacity today when it comes to in-house manufacturing of boilers, turbines, and generators? Also, since you plan to commission the 600 megawatt Mahanadi by FY28, how is that going to play out on the equipment sourcing side?
Sharad Mahendra
executiveOkay, Sumit, I’ll respond regarding both Mahanadi and Salboni, as you asked. Look, with Mahanadi, as we’ve stated, we’ve been saying perhaps since the first call following last year’s acquisition of this asset that for the fourth unit of 600 megawatts, nearly 40% — 30% to 40% — of the work was already finished. And the balance of plant was already in place when we speak of, naturally, the coal handling plant or ash handling or railway or the transmission network — all of it is already there. So what happens here is this unit is being completed via the very same suppliers who provided the material earlier, since part of the material for the turbine and other items is also available with us for the fourth unit. So we have placed the orders and the material is being dispatched and all. So we will be, as we’ve said, commissioning the next fourth unit in FY28. We are on track for that, and it will be through the Chinese suppliers only. For another two units, discussions are underway, and we will make the announcement at the right time very soon regarding what our strategy is for the fifth and sixth units to take it from 1.8 to 3.6 gigawatts.
Sharad Mahendra
executiveTurning now to Salboni — as we said before, for the 2 x 800 phase 1, the turbine generator order has already gone to TJPS, Toshiba JSW Power Systems, work has already begun, and both the supplies and the commissioning are fully aligned with the PPA timelines. On the boiler side, this is the GE facility at Durgapur, which we are in the process of acquiring. It's expected to be done perhaps by the end of this quarter. Its nameplate capacity right now, on an as-is-where-is basis, is 1.1 gigawatt. That means if we're talking about an 800 megawatt boiler, it can produce 1.3 boilers in a year. But with some debottlenecking and a small investment — which we have already planned, it's a plan — this will go up to 2 x 800, meaning 1.6 gigawatt of capacity. That's because the TJPS, Toshiba JSW plant in Chennai already has a capacity of 2 x 800. So these two will be benchmarked together, and that will be that. So that's the strategy, and we are totally de-risked when it comes to the supply chain for boiler, turbine and generator across all our 800 megawatt expansion plants.
Sumit Kishore
analystAlright, one final question regarding your external order for a 200 megawatt, 400 megawatt-hour battery assembly facility. So how far has that battery assembly facility been scaled up? And what does this external contract signify regarding margins, and what value-add does JSW provide?
Sharad Mahendra
executiveLet me just give you the plant's readiness status. The trials are already done, and while the quantity may not have been large, we have supplied at least some orders to the third party as well. The plant is entirely ready to begin production and to meet the schedules in line with the schedule the buyer has agreed to. On the financial side, I'll ask Prabhakaran to tell you about the margins.
Chandrasekaran Prabhakaran
executiveSo I'd say, on the margin per dollar side, if you look at it, that comes out somewhere around $2.75 to $3. So, if you sort of take the total capacity that's running, that works out to roughly $15 million over a year. So that's the way we're looking at it — close to INR150-odd crores of EBITDA coming from this project.
Sumit Kishore
analystAlright, thanks a lot.
Operator
operatorThanks. Our following question comes from Apoorva Bahadur with IIFL Capital. The floor is yours.
Apoorva Bahadur
analystHello sir, and thanks for giving me the chance to speak. On this point about the fourth unit expansion, you said that orders have been placed with Chinese suppliers for the remaining equipment. Will we face any restrictions when it comes to tying this up with a state utility, or is our plan to use it in a merchant or captive market?
Sharad Mahendra
executiveNo, there are — look, those are just the guardrails. No such regulation exists, and a lot of states are exploring this — one important point is that more than one state is interested, particularly given how much solar there is now, and so much — this question came up right at the start about whether the technical minimum might come down, since some buyers prefer the lower 600 capacity tier because even if they must back down, it sits comfortably at 50%. So we don't see that. We're seeing a lot of interest, especially with how international coal prices are moving and where the currency is heading. Many imported coal-based power buyers want to swap it for domestic. So we're confident this will happen. And here, since we also have permission from the authorities for this partial import to complete the asset, the fourth unit, we don't see that as a challenge. And we're seeing a lot of interest when it comes to signing a power purchase agreement. But remember, even if it's merchant with the mine next door and the coal cost so low and the project — the cost at which we'll complete this project, another 600 megawatt, which will be significantly lower than the benchmark per megawatt cost of capacity addition, I think it will stay attractive either way, whether merchant or in long-term PPA.
Sharad Mahendra
executiveWe’ll take a call, but we’re absolutely confident that the PPA opportunities are going to happen.
Apoorva Bahadur
analystOkay, sir, got it. And second, regarding this best business return profile, I believe, sir, you pointed out that we're aiming for roughly $2.75 to $3 for each kilowatt hour of storage capacity. Do you foresee a glide path toward enhancing the value addition and margins here, or is this something you're viewing as an exit margin from this business?
Chandrasekaran Prabhakaran
executiveI believe this comes more from the assembly side, from what we're doing, and that's what we're looking at, and we keep exploring because the government has also introduced a PLI-type incentive for setting up cells and all of that. We'll keep evaluating that, but as far as what we've invested, I think this is the sort of return profile we'll have.
Sharad Mahendra
executiveAnd to build on what Prabhakaran mentioned, regarding value addition, the opportunities we've identified moving forward are, first, as you noted, that backward integration—perhaps rather than bringing in the cells, producing them within India, and for that we're holding discussions with a number of technology partners. And the second is on scaling up. As things stand today, the container size is 5 megawatt-hours. Looking ahead, we're developing the capability, once the product and the components are available, to go from 5 up to 7, 6, 7, 8, which makes it more cost-efficient for us and for the buyer as well.
Apoorva Bahadur
analystAnd sir, is there a long-term partnership in place with a Chinese supplier for bringing in the cells?
Sharad Mahendra
executiveAt this moment, no. As of now, no.
Apoorva Bahadur
analystFor this BESS, the warranties in this industry are usually provided by the OEM, correct? The cell manufacturer?
Sharad Mahendra
executiveYes.
Apoorva Bahadur
analystSir, I'd like to also bring up connectivity for our renewable capacity. I think the details you gave in the presentation are very helpful regarding this 3 gigawatts, with the remaining 1.9 gigawatt connectivity in FY27. First of all, is all of it operational? And second, what's the update for FY28? Do we have the full connectivity capacity operational in '28 as well?
Sharad Mahendra
executiveYes, I’ll get to that. As I mentioned, from April 1st of the current year through today, we’ve commissioned 1.1 gigawatts. We’ve brought on that new capacity. Just to clarify: of that 1,100 megawatts, 300 megawatts is currently under TGNA, and it’s experiencing curtailment. And we’re absolutely — that is in the process of being converted. The new capacity is being commissioned. And we’re nearly certain that before August 31st it will be converted to GNA. Once that conversion to GNA happens, there will be no curtailment. So that 300 megawatts that’s under curtailment, plus one earlier project I also mentioned last time — in Rajasthan, from O2 Power, which we acquired at 400 megawatts — that one is also under TGNA; its connectivity was supposed to be ready by the end of July, and now it’s expected sometime in September or October. So we’ll be waiting on that. Until then, both of those projects stay under TGNA. Now, the remaining 1.9 gigawatts that we need to commission this year — I just want to tell you that of that amount, 28% of the 1.9 capacity, so maybe more than 530 megawatts of the remaining 1,900 that we have to execute, is our group captive, which is a mix that includes off-grid too; most of those capacities are off-grid, where we have our own dedicated transmission line that isn’t connected to the grid — it’s insulated. So that 530 is entirely insulated.
Sharad Mahendra
executiveThere's another point as well: a big portion of what we're doing with utilities — there too, our connectivity is entirely in place and working, and that connectivity is a combination of STU and CTU, plus the C&I customers, meaning the C&I projects we're going to carry out this year. So those are the three mixes, but of the 1,900 megawatts we need to commission in order to hit the 3 gigawatt guidance we've provided, we are 100% secured on connectivity, and all of it is commissioned as well.
Apoorva Bahadur
analystThanks, sir. And what about ’28?
Sharad Mahendra
executiveRegarding FY28, we will certainly get back to you on that. We have. But yes, as I've mentioned before as well, the two areas we're focused on when providing guidance for the year — perhaps these two are the primary drivers on which we'll base it, so that there's assurance about the numbers being achieved. But we will definitely, at the right time, very soon, come back on FY28 as well.
Apoorva Bahadur
analystThanks, sir. If I could just fit in one final question about wind generation. PLFs seem slightly softer year over year. I believe last year was unusually strong. Similar to hydro, are you seeing them bounce back in July as well, or are they still trending downward?
Sharad Mahendra
executiveYes, we've witnessed a substantial rebound. And typically, as you can see, it's quite clearly established that patterns exist. When there's very heavy rainfall, temperatures fall, and wind speed is usually connected to that and gets better, which is something we've observed as well. As soon as the monsoon arrived, the wind speed season became a disadvantage. This time around, temperatures have been elevated, and for many of our assets, in wind we've even hit a PLF of 100%, whereas otherwise it's 90%, 100% in PLF, that's what we've achieved. So we don't view this as a chance. And in July, if you look, compared with earlier months, the PLF is already up by roughly 5% to 6%.
Apoorva Bahadur
analystOf course, sir. I appreciate it very much. I'll rejoin the queue.
Operator
operatorThanks. Our next question comes from Satyadeep Jain at Ambit Capital. Go ahead, please.
Satyadeep Jain
analystHi, thanks. On the storage projects, you’ve provided a few details. I believe this is the first time I’m actually seeing the two projects named specifically. So maybe, if you could — you did share some information on readiness, but perhaps you can go into more detail about the capex you’re anticipating and how confident you are in hitting that commission date you referred to.
Sharad Mahendra
executiveOkay, look, as I mentioned to you, we have signed two power purchase agreements. The first is the Bhavali project in Maharashtra with MSEDCL, totaling 1,500 megawatt, and the other is Kandhuara in UP at 1,680 megawatt — of that, a 1,500 megawatt power PPA has been signed with the state of UP. As for how prepared we are at Bhavali, we are completely set: the environment clearance has been obtained, land acquisition is largely complete, with a small portion still remaining, though that piece sits outside the core project area, so no impact will come from it. That work will proceed in parallel. Then the third item: stage 1 forest clearance has already come through. So we are at a very advanced stage. Ordering has already been done — for the full civil work, the order has gone to L&T. For electromechanical, the order has gone to Voith. So we are fully prepared in terms of — and mobilization is already underway, construction power has also already been — it has been awarded to us, and connectivity has already been established, which you can also see on the slide. So we are ready on that front.
Sharad Mahendra
executiveWhen it comes to execution and hitting the timelines, that isn’t something we view as a challenge—particularly given our track record and know-how in building greenfield hydro projects in the extremely harsh Himalayan terrain of Himachal Pradesh. At this site, the rock quality and the relative ease of carrying out the work make it considerably simpler than that. I won’t call it easy, but the difficulty levels are certainly much lower. The tunneling portion is far, far smaller than what you see in the Himalayan projects. So we have full confidence about meeting the PPA timelines. Naturally, if the state is late in making power evacuation available, that could be the only issue, but we don’t regard that as a challenge either. So for Bhavali, we are completely certain. For Kandhuara, as I mentioned, we have already obtained the EAC recommendation for EC from the Ministry of Environment and Forest, the application for forest clearance has already been filed, and the connectivity application has also been submitted to the UP authorities. Civil work and the construction award process are underway, and we expect everything to be ready perhaps in the last quarter of the current fiscal—ready to begin execution work at the site as well and to stay within the timelines.
Sharad Mahendra
executiveOn capex, we’ll revisit that, but as I mentioned, since we aren’t especially tied to any one project, perhaps providing a capex figure isn’t the right approach. Still, I can say this offers very strong returns — when we refer to benchmark returns of mid-teen IRRs, here I can say it will be significantly high-teen IRRs, and that is what we’re absolutely confident about, given the tariff and the cost at which most of the ordering has already taken place.
Satyadeep Jain
analystCan we safely assume roughly INR5 crore for each megawatt, something that any benchmark, any just…
Sharad Mahendra
executiveNo, you could say it's not very far from that number. It's not very far from that number.
Satyadeep Jain
analystOn the thermal capex you brought up for Mahanadi <<inaudible>> tied to the upcoming expansion, could you — is there any way perhaps to give some indication of what sort of capex we might expect for 600 and then the balance of the thermal?
Sharad Mahendra
executiveLook, I can tell you this: when we carry out the greenfield project we're also doing at Salboni, the one we've already placed the order for — the boiler we'll handle in-house. We've already placed the order for the civil portion. Work has begun. We have a fair idea of what it takes to complete a greenfield project there. Compared with that, for Mahanadi, when we finish it, I can say for certain that we'll be at least 25% to 30% lower by doubling the capacity from 1,800 to 3,600.
Satyadeep Jain
analystAlright, and finally on PGNA, what curtailment can you share for this quarter across those two projects overall?
Sharad Mahendra
executiveLook, we had total wind plus solar together, and curtailment for the quarter came to 69 million units. But like I said, this needs splitting into two parts. There were also curtailments on the GNA projects, where power was being supplied under the PPA. In that case it's treated as deemed plant availability, and we receive the tariff for that supply even when there's a backdown, since my buyer has scheduled on the exchange to draw the power. My plant is available even if the load center asks me not to put the power out — my buyer gets the power and I get my money for it under the GNA? Yeah, Prabhakaran, you can add.
Chandrasekaran Prabhakaran
executiveYeah, I'd say from a total revenue standpoint, it isn't material. For us this quarter, it comes to roughly INR15 crores. That's the EBITDA impact.
Satyadeep Jain
analystThanks for that. Appreciate the answer.
Operator
operatorThanks. Our next question comes from Nikhil Nigania at Bernstein. You have the floor.
Nikhil Nigania
analystHi, thanks for taking my question. This follows up on the earlier question about pumped storage projects. I was hoping to find out whether there's any news on the Karnataka tender, where the tariffs appear even more attractive than those in the other two projects you have?
Sharad Mahendra
executiveYes, Karnataka as well — we've received the letter for that one, along with some local clearances and so on, and those are at an advanced stage, they're under discussion, and we expect that to be sorted out soon too and the PPA will be signed. For this, the letter has already come in. But that's in lane. That isn't a clear this thing. They are not. That Narihalla project in Karnataka. Yes.
Nikhil Nigania
analystGot it. Is there any reason we didn't take part in that recent SECI tender, where the tariffs that came out were really attractive for pumped storage projects and just three bidders showed up?
Sharad Mahendra
executiveLook, in this particular tender, the requirement was that Forest Clearance Stage 1, or FC1, had to be in place. Only those could apply. That was the situation. So we didn't have any other site ready with Forest Clearance Stage 1 clearance. So we decided not to take part. But just to update you, we are now ready with another site of almost close to about 9 gigawatt hour, and whenever any opportunity comes, we'll be participating in that. But we haven't participated because we aren't ready with forest stage 1 clearance, which was a precondition.
Nikhil Nigania
analystOkay, that makes sense. And one final question from me: are there any plans to build a merchant battery storage plant?
Sharad Mahendra
executiveCould you say that again, please?
Nikhil Nigania
analystIs JSW considering building merchant battery energy storage plants at all?
Sharad Mahendra
executiveAs of now, no, but yes, we are looking into it, bearing in mind the gas situation and the requirements that are emerging, since the thermal capacity meant to handle the evening peak is still a few years off, and given how demand is growing. So there is an opportunity here, because this is also a location where a solar plant exists, solar radiation is strong, and connectivity is available. That same connectivity could be used after solar hours, so connectivity isn't a problem. And the solar capacity for charging the battery can be built at a very, very attractive cost, since only the DC side needs to be done. That cuts the capex on solar capacity charges significantly. So those are the things we are exploring, and at the right time we will certainly be exploring it when it makes sense, when our benchmark returns are protected. We'll definitely be looking into this to capture the evening peak advantage.
Nikhil Nigania
analystGreat, thanks. That covers everything I wanted to ask.
Sharad Mahendra
executiveThanks.
Operator
operatorThanks. Dhruv Muchhal from HDFC Asset Management has the next question — go right ahead.
Dhruv Muchhal
analystYes, sir, thank you. Sir, the PLF at your thermal plants came in lower this quarter compared with the prior year, for instance. That happened even though the demand season was very strong. Ratnagiri, for example, is lower, Vijayanagar is lower, and Rajasthan is lower as well, though that doesn't really matter much. Utkal is nearly the same even with a long-term PPA. My thinking was that with a long-term PPA you get a better schedule, so you can sell more in the short term, which means the PLF could have come in higher. With KSK, I understand there were issues. So I mean, is all of this happening because of the solar situation, you know, and we aren't looking at it the right way? I'm just trying to work out what drove this. Demand was very strong.
Sharad Mahendra
executiveOkay, let me go plant by plant — and honestly it isn’t really down to solar generation or the backing-down that’s happening. I’ll begin with Utkal. At Utkal we had a planned outage, and taking it mattered so that we could lock in the annual availability of that plant, which becomes critical once the power purchase agreement has been signed. So a big chunk of quarter one had that unit offline — one unit. That’s why PLF at Utkal came in lower. That’s the first point. And if we look now, in June both availability and PLFs have come up considerably. Then in July, availability at Utkal runs above 91%, and the suppliers are in place. So we aren’t running into — as I said right at the start, when someone raised a question about PLF, our PLFs, even during the peak solar hours at Utkal, have not dropped under 58% to 60%. We’ve been running at nearly 60% PLF. So those aren’t the causes. The reason was that we took the outage to lift reliability and performance, since we could see ahead that this demand — the way May, June, or rather May, was shaping up — May got underway. We chose to do it also because in July we’re seeing power demand growth at 12 point, perhaps 12%, in July.
Sharad Mahendra
executiveSo we did that on purpose, and the plant is now back on track. Turning to Ratnagiri — at Ratnagiri, the PLF has been lower, and the reasons for that are, first, there is no impact on our financials. The reason is that this is again a two-part tariff, where we have to make sure we provide availability for our group captive — the large capacities under group captive — which we are doing. And one unit is with MSEDCL. So there too it was again a planned shutdown, because we have to ensure we achieve the annual availability of 80%, so that my fixed cost. So this is not without any impact. And also in the month of June, there was reduced demand, and extreme weather conditions too, when the rains started, when we saw that in Maharashtra. So that is all by design. As I told, MSEDCL — you are aware yourself of what happened, which we have recovered now. Availability has been 100% in July.
Dhruv Muchhal
analystOkay. So even looking at the solar PLF on your slide, it comes in at roughly 21%, and the prior year was 21% as well. Considering the ACDC you normally achieve, plus the weather this time around was likely fairly favorable too, I'm just curious — is curtailment the reason that figure sits low, or should it be moving toward somewhere around, I don't know, 24 to 25%?
Sharad Mahendra
executiveI mean, look, the thing is, if you look at the pattern across the country as well, solar’s second half tends to be stronger every year. After the monsoon. And then, of course, as I mentioned, that 4 megawatt capacity — which is, you could say, for me it’s almost maybe, maybe 12% to 14% of my total capacity — is where we’ve also been dealing with curtailment. Once all of that gets back to normal, then it comes to 21, but apart from that, PLFs have been much higher compared with this, even after the curtailment impact is included.
Dhruv Muchhal
analystSince your year-over-year generation capacity and renewable capacity are growing roughly 20% — from 5.7 gigawatt to 6.8 gigawatt — but RE generation is up only about 11%, and typically newer projects should deliver even better PLFs, I'm assuming. So sure, there could be a scheduling issue, with some projects perhaps landing at quarter-end, but that discrepancy looks quite large. So I was wondering whether some maintenance-related loss or something else is behind it? Even factoring in 69 million units of curtailment, that figure is still only 13% growth YoY.
Sharad Mahendra
executiveYes, I’ll get to that. If you look at our generation — solar generation overall — the PLFs we’re seeing are roughly 22% in quarter one, quarter two, but then quarter three, as I mentioned, 26%, and quarter four, 28%. That works out to an annualized 25% split by quarter, and if you check the historical data too, you’ll notice the same pattern. So instead of focusing on a short-term single-quarter PLF, I think we need to give it more time and wait, since the second half is considerably stronger.
Chandrasekaran Prabhakaran
executiveAnd I also want to mention that a bit of capacity we brought on very recently is settling down too, and that’s pulling it down a little when you look at it from the average standpoint. I just wanted to add that. Yeah.
Dhruv Muchhal
analystUnderstood. Certainly, sir. Excellent. That is everything. Many thanks, and best wishes. Thank you.
Operator
operatorThanks. Our next question comes from Rajesh Majumdar at 360 ONE Capital. The floor is yours.
Analyst
analystGood evening, everyone. Sir, I had a question about this Maruti Clean Power. Aside from the fact that it's inexpensive, what's the rationale for acquiring subcritical capacity of this kind? So what are the long-term plans for it, if there are any, and how does it fit into our overall scheme of things?
Sharad Mahendra
executiveSo yes, essentially the goal is — as I mentioned to you — the chance to improve on that and to capitalize on the running asset. Look, once the asset is ready, we are — it sits near the coal mine. The possibility of upside from a small capacity, a 60-odd megawatt capacity, which is also open either to going for a PPA or to benefiting from the merchant handling the evening, this thing. So overall, when we talk about the acquisition cost, where the opportunity lies, the tariffs we are recognizing, it's a blend of many things. Beyond that, our team has completed the technical due diligence, and following that there's an option of using part of the existing plant's resources, and investing and perhaps doubling the capacity or even more at the same plant, which is very, very near the coal mines, is also an opportunity to capitalize on. So it's a combination of a few factors that make this asset extremely attractive for us.
Rajesh Majumdar
analystSo what you're getting at is that we might see brownfield announcements about this down the road?
Sharad Mahendra
executiveYes, an opportunity exists. And we also do the — if you look at the multiple at which I'm buying this versus what's standard practice in the industry, it's very, very value-accretive EBITDA, so all those factors were taken into account as well. At the price we've paid, this is a highly attractive acquisition. We are in the process.
Analyst
analystAll right, so my second question concerns the debt. If you look at the — first of all, what does gross debt come to as of June 30th? Since net debt stands at roughly INR55,000, what would the gross debt figure be?
Sharad Mahendra
executiveYeah, just. Let's see. Prabha?
Chandrasekaran Prabhakaran
executiveSo gross debt comes to roughly 74,000, and cash sits at close to 12,900 — 12,900. Yeah.
Analyst
analystSo 74 and 12,900 invested. That makes net debt 55,000?
Chandrasekaran Prabhakaran
executiveYes.
Sharad Mahendra
executiveYes.
Rajesh Majumdar
analystAnd is there any portion of the cash raised during the quarter still left to come in, as far as the June 30th figure goes? Or has all of it already been factored into that 10,150?
Chandrasekaran Prabhakaran
executiveRegarding both the QIP and the JSW Steel share liquidation we completed, I believe those are already accounted for. There's roughly INR1,900 of preferential capital available from the promoters, since it can be brought in within 18 months of what we did. It could come in at any point.
Sharad Mahendra
executiveThat's the final date. The end date is June ’27. Should the requirement come sooner — though this one sits here and hasn't arrived yet — it's INR 1,875 crores.
Analyst
analystOkay. And when you break that down, you mentioned INR20,000 crore of capex for the year. So basically, that suggests gross debt will rise by a further INR6,000 to INR7,000 crore this year. Would that be a fair assumption?
Chandrasekaran Prabhakaran
executiveNo, the way we see it is, for instance, we've already completed roughly INR7,000 crore of fundraising, and operating cash flow will also be coming in, so together that can get us to around INR12,500 or so. The remainder is what we can sort of look at — the balance needed between whatever 20 minus 12,500 works out to, that's what the incremental piece could be.
Analyst
analystCorrect. And for the coming year, we're also planning to add roughly 3 gigawatts, or something along those lines?
Sharad Mahendra
executiveYes, it'll stay within that same range — it'll be in this range only. Yes.
Analyst
analystAll right, thanks a lot.
Operator
operatorThanks. Our following question comes from Atul Tiwari with JP Morgan. You have the floor.
Rajesh Majumdar
analystThank you very much, sir. Sir, my question concerns profitability at the PBT or PAT level, which has been rather suppressed across the past few quarters, clearly on account of higher depreciation and finance costs. And clearly, within your portfolio mix, quite a few projects are now very mature, correct — running for many years on the thermal side. Okay, so what I want to ask is whether this situation will continue through the coming few quarters, or is improvement at the PBT or PAT level likely to be seen? Since your ROEs have been suppressed considerably once depreciation is factored in.
Chandrasekaran Prabhakaran
executiveI think there are a couple of points to make here. First, if you look at the capacity additions we've been carrying out, they're mostly in the RE sector, correct? So last year we did close to 2.3, and this year we said 3. Now, the earlier ones — the ones we did about two to three years ago — those are the assets that will come into play, because at the start the interest cost, the debit to the P&L, will be a bit higher, since there's a moratorium during construction. And after that, when commissioning begins, the initial interest debits hitting the P&L will be higher. But over a period of — once the asset is in place, say stabilized for around four to five years, that's why we see that — because that's when we kind of feel EBITDA should translate into PBT and PAT. And that's generally how the industry works as well, right?
Rajesh Majumdar
analystAlright.
Operator
operatorThanks. Our following question comes from Dishant Jain at Quasar Capital. You have the floor.
Dishant Jain
analystHi there — can you hear me okay?
Sharad Mahendra
executiveYes, that's correct.
Dishant Jain
analystThanks for the chance to ask. Sir, this is a pretty basic question — and tell me if I've got this wrong, but what I heard is that on the thermal side, we keep getting the fixed charges even when the PLF is lower. So at what point do we book it, and when do we actually get those fixed charges from the customers?
Chandrasekaran Prabhakaran
executiveWhen you look at Mahanadi, the reason is this: if availability runs at around 85% for a stretch, that comes about because they essentially assess it across the full year. In this instance, to that same degree, once we begin billing and once we hit that capacity, then even though the income gets recognized at present, the collection itself will take place over the following two to three quarters, essentially.
Dishant Jain
analystSo the collection will come in over the next 2 to 3 quarters. And when do you recognize it, sir?
Chandrasekaran Prabhakaran
executiveThe accounting is taking place in the current quarter. For instance, in this situation, when we made that statement about whatever extent, since we see — we're essentially indicating that 85% of the minimum availability will be reached in any case. And as for the fixed charges we're entitled to receive, that has already been recorded in this quarter.
Dishant Jain
analystAlright, thank you, sir.
Operator
operatorThanks a lot. That wrapped up the final question. At this point, I'd like to return the conference to the management team so they can offer their closing remarks.
Sharad Mahendra
executiveThank you, Sunil ji <<inaudible>>. Yes, thanks to everyone. I appreciate all of you very much for joining us today and for the discussion. Also, should any further questions arise that you think went unanswered or that you would like to learn more about, please reach out to our IR team, and we will gladly take those up and get back to you on them. Thank you very much.
Chandrasekaran Prabhakaran
executiveHello, and thanks.
Sharad Mahendra
executiveAppreciate it.
Operator
operator<<operator_signoff>>
Read the full transcript via the API
You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.