JSW Energy Limited (533148) Earnings Call Transcript & Summary
May 23, 2023
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to the JSW Energy Limited Q4 FY 2023 results conference call, hosted by Antique Stock Broking. Please be reminded that all participant lines are in listen-only mode. Once the presentation has concluded, there will be an opportunity for you to ask questions. If you require assistance during the conference, please signal an operator by pressing star then zero on your touchtone phone. Kindly note that this conference is being recorded. I now hand the conference over to Mr. Rohit Natarajan from Antique Stock Broking. Thank you, and over to you, sir.
Rohit Natarajan
analystThanks, Gavin. Good evening, everybody. To start, we want to express our appreciation to the JSW Energy management team for the chance to host this post-earnings conference call for QFY 2023 results. Joining us today from management are Mr. Prashant Jain, Joint Managing Director and CEO; Mr. Pritesh Vinay, Director Finance and CFO; and Mr. Vikas Chaudhary, Head of Investor Relations and Treasury. Management will kick things off with opening remarks, and after that we can move into the Q&A. Sir, the floor is yours.
Prashant Jain
executiveThank you. Good evening, ladies and gentlemen. For the power sector, the year just ended has been extremely interesting, to say the least. During this year we witnessed power demand growth of 9.5%, the highest in the last 30 years. That followed 8.5% power demand growth in FY 2022. This points to some structural shift where power demand growth is concerned. As we speak, total capacity in the country stood at 416 gigawatts, which implies net capacity addition of 16.6 gigawatts overall, the bulk of it — 15.3 gigawatts — being renewable. What we must note is that against that 16 GW of net capacity increase, net generation came to roughly 4 to 4.5 GW. Net demand rose by approximately 14 GW. That means 9.5 GW of excess capacity was absorbed, and the previous year looked similar, with 17 GW of total capacity addition, 15.5 GW of it renewable capacity. My point is that net capacity addition in the country is not sufficient relative to the rise in net demand, and that is also showing up as the sharp jump in power prices on the energy exchanges.
Prashant Jain
executiveThe second point that should also be noted is that there isn't sufficient volume in the merchant market, which is being cleared. Over the past year, the day-ahead market's total volume stood at 51 billion units, a decline of 21% versus the year before. Tariffs rose 36%, reaching INR 5.97 against INR 4.39 in the prior year. Thermal coal prices keep falling. During Q4, thermal coal prices dropped 37%, averaging $148. They have continued to decline in the current quarter as well. In April, average prices were $130; in May, $118. As we speak, prices have reached $102. On a lower calorific value basis, we are at a double-digit number. We keep observing coal prices moderating while power demand, interestingly, is rising in a very robust manner. Turning to the company, this year has been about delivering the promises. JSW Energy reported its second-highest EBITDA ever and second-highest PAT ever. The last time we witnessed such an EBITDA was 2015, during high merchant prices and power shortages, and we saw a similar PAT in 2016.
Prashant Jain
executiveOver the last 7 years, 8 years, this marks the highest operating EBITDA and profit after tax we have ever recorded. Our business has also changed compared with the prior year, when at that time 55%, 60% of our capacity was untied. We relied on the unpredictability of the merchant market, the power demand situation and the supply situation. As things stand today, 85% of our portfolio is fully tied up. That 85% I am referring to includes the Ind-Barath capacity as well, once it is commissioned. So we have very strong visibility on all our cash flows going forward. On the positive developments, we have now secured 2.4 gigawatt hour in the pumped storage bid and 1 gigawatt hour in the battery storage bid. These are the two projects we will be building. This gives us a first mover advantage in the energy storage space. India stands at an inflection point when it comes to energy storage requirements, because our baseload power demand today is 185 GW, while total installed renewable capacity is 173 GW. Once baseload power demand and renewable capacity become equal and renewable capacity overtakes it, at that moment the grid will begin to become unstable, and that is going to occur within the next 18 to 24 months.
Prashant Jain
executiveThe way it works is that when solar output is at its maximum, that's exactly when all the renewable generation, all the power, is flowing in. At that moment, you simply can't dial your thermal capacity down to zero. That's exactly where grid storage becomes essential. CEA has projected that 322 gigawatt hours of energy storage capacity will be needed by 2030. On that front, tenders have begun to appear, we're enjoying an early mover advantage, and we've already locked in or tied up 3.4 gigawatt hours of capacity that is now headed into construction. On these projects, we'll earn returns above the normative level. Beyond that, we've already secured roughly 72 gigawatt hours of hydro pumped storage projects, where the allocation is in hand and we're now pursuing the required approvals. One of these hydro pumped storage projects will enter construction this year. I'm also glad to share another notable milestone decision our board made today. We are launching India's largest green hydrogen project, with a capacity of 3,800 tons per year. This facility will be built to produce green steel for JSW Steel at Vijayanagar.
Prashant Jain
executiveThis project is going to be powered entirely by 100% renewable electricity, and it will use 25 megawatt of renewable power around the clock. On an installed basis, we'll need roughly 80 megawatt of renewable capacity, and pumping storage will be needed as well, plus battery storage. Commissioning of this project is expected within a time frame of 18 to 24 months. For a seven-year contract, this will be structured on a cost plus mid-teen ROE basis. Over the course of that seven-year period, the whole plant will be amortized. After that, it will run on a variable cost and ROE basis between the parties. This is set to be the biggest project in the country, the first one for green steel manufacturing, and the first project where the entire PPA is fully secured. That gives us a huge flip and advantage going forward, because as we've said in the past, we have built our own microgrid and solar and wind farm capacity together with the pumping storage, and we'll be able to move into the electron to molecules business. On top of that, we are also contracting all of the green oxygen that will be produced, which will be 8 times the capacity of the green hydrogen.
Prashant Jain
executiveThat will also be sold to JSW Steel. Another interesting item I wanted to discuss is the solar module manufacturing facility. During the quarter, we had informed that we received an NOI under the PLI scheme from the Government of India for a 1 gigawatt hour, 1 gigawatt per year capacity wafer, cell and module manufacturing facility. For this, we have been allocated INR 320 crore of the PLI. The total project cost is going to be INR 1,600 crore. In addition to that, we are finalizing the package from the state government. This project will be commissioned in 18 to 24 months period. This will enable us to completely backward integrate for our own captive requirement of the module manufacturing. Wherein we will be able to produce the latest technology module, solar PV module at the most competitive price there. Our positioning will further strengthen to remain a lowest cost renewable power producer in the country. The next piece which I also want to touch upon is about the Ind-Barath. We had completed the acquisition of the Ind-Barath asset. This is going to be one of the lowest cost completed project, less than INR 4 crore per megawatt.
Prashant Jain
executiveThere was plant, and that includes the FGD installation. What's interesting is on Coal India linkage prices — this project is going to rank among the lowest fuel-cost power producers, with fuel price at roughly INR 1.30 to INR 1.40 on a Coal India linkage price. Commissioning of the first unit is expected in the first half of the current financial year, while the second unit should be commissioned in the last quarter of the current financial year. We believe this will be hugely value accretive for us, given the high merchant power prices. On a conservative basis, our expectation is that we will make something in the INR 2-INR 4 range for fixed cost recovery, which will be very, very value accretive for this particular project. We also completed the Mytrah acquisition during the last quarter. This stands as one of the greatest examples and one of the largest acquisitions in the renewable space. Originally, we had envisaged that the EV would be INR 10,500 crore. Against that, we completed the transaction at INR 10,150 crore. For an installed capacity of 1,753 MW, this translates to INR 5.77 crore per MW of capacity, compared with today's replacement cost in excess of INR 7.4 crore-INR 7.5 crore per MW.
Prashant Jain
executiveThe normalized EBITDA for this asset comes to INR 1,650 crore, and that works out to INR 941 crore per GW. In today's competitive landscape, the best bid we're winning, including at JSW Energy, sits at roughly INR 840 crore to INR 870 crore per gigawatt, so compared with that INR 941 crore, this is a hugely value-accretive transaction. We've given guidance that from a normative — from an actual EBITDA of INR 1,200 crore, we'll move to INR 1,650 crore within a 12 to 18 month time frame, and of that, INR 400 crore, or to be precise INR 390 crore, was to come from the increase in generation along with grid availability and machine availability, while INR 60 crore was to come from improvement in operations and maintenance cost. I'm happy to share that over the last 45 days, we've already got 103 wind turbines up and running out of the 128 turbines that were down. The remaining 25 turbines will also be up and running by the first or second week of June. As a result, we'll be getting generation much, much ahead of what was earlier envisaged. The same situation applies when it comes to improvement in machine availability.
Prashant Jain
executiveMachine availability is already up by 500 basis points, and the performance ratio for solar generation has improved significantly as well. We expect that the guidance we provided — the 12 to 18 months time frame — will be met much, much ahead of schedule. Within the current financial year itself, we will hit the normative EBITDA run rate we forecast earlier, which is INR 1,650 crore. Even on a most conservative basis this year, compared with INR 1,200 crore EBITDA last year, I expect we will do between INR 1,400 crore and INR 1,470 crore EBITDA in the current financial year, because part of the high wind season that is going on right now will not be available to us for generation. I come now to a very important subject — our strategy, which we explained in 2021, when we gave formal guidance that JSW Energy will be a 10 gigawatt company by FY 2025 and a 20 gigawatt company by FY 2030. In that strategy, we laid out that our EBITDA will rise to 2.5x at 10 gigawatt and 5x at 20 gigawatt capacity.
Prashant Jain
executiveSince our performance has been extremely strong, we've already secured 10 gigawatts of operating capacity, and that will be finished during calendar year 2024. Beyond that, we'll also be completing a 1 gigawatt wafer, cell, and module manufacturing facility, plus 1 gigawatt hour of battery storage capacity. Thanks to all of this, our cash flows are improving dramatically as well. We're introducing enhanced guidance that reflects a 25% improvement. Under our revised strategy 2.0, by 2030 we will reach 20 gigawatts of generation capacity and 40 gigawatt hours of energy storage capacity, together with a green hydrogen facility of 3,800 tons per annum, and also 1 gigawatt of wafer, cell, and module capacity. All of this comes without any equity dilution — solely from internal accruals. What we're saying is that the earlier guidance had us at net debt to EBITDA leverage of 4 times by FY 2030. We will be bringing our leverage down to 3.5 to 4 times. Both our profit after tax and EBITDA will rise by 25%. We're giving guidance that our EBITDA will be 6 to 6.5x at 20 GW capacity in FY 2030, and our profit after tax will be 7 to 7.5x, which is likewise 25% higher at 20 GW capacity.
Prashant Jain
executiveIt's worth pointing out that on an achieved capacity basis for FY 2023, we've already hit a normalized EBITDA of 1.8x and profit after tax of 2x, compared with the guidance we gave. We're quite confident that we're not just performing better — we'll also be growing far more aggressively. We had guided to a capital expenditure of INR 75,000 crore. Now, all of this points to a total capex of INR 112,000 crore, out of which INR 35,000 crore has already been deployed, and the remainder will be completed within a 18 month timeframe. Another important thing I want to emphasize and place on record is that our balance sheet size will grow at 22% CAGR from FY 2023 to FY 2030, even as we de-lever the balance sheet and deploy only our cash flow. Our cash profit yields are going to improve on the basis of what we have delivered from here. With that, I'd like to hand the forum over to Pritesh to speak about the operating performance, as well as the gearing ratios and receivable cycles. Over to you, Pritesh.
Pritesh Vinay
executiveThanks a lot, Prashant. Good evening, everyone. I really appreciate you making the time to join this call on our Q4 and full-year results. Prashant has already laid out the macro backdrop regarding how the wider power markets performed across the year. With that in mind, let me quickly walk through how we did in the fourth quarter, and then I'll move on to the full-year numbers. Looking at net generation for JSW Energy in Q4, it rose 16% YOY to more than 5 billion units. That came from the extra renewable capacity — namely the 225 MW solar plant and the first batch of the SECI 10 project commissioned earlier in the year — along with greater power sales on the merchant side and from long-term offtake. On revenue, as reported, you'll note that the quarter's figure of INR 2,806 crores represented a 6% YOY increase. I should point out that Q4 of 2022 included a truing-up order at JSW Hydro for the Karcham Wangtoo plant, which meant a one-off exceptional impact of INR 525 crores was booked within revenues.
Pritesh Vinay
executiveOnce you adjust for that on a comparable basis, revenue this quarter, with net generation 16% higher, is in fact up 32% YOY. That's mostly because fuel prices were higher YOY, which meant, you know, fuel cost pass-through had an effect there too. Turning to EBITDA performance, again, after we strip out EBITDA for exceptionals, including last year's truing up liability, EBITDA for the quarter came in at INR 881 crores, up 7% YOY. Adjusted net profits for the quarter were INR 272 crores. To wrap up the full year, looking at fiscal 2023, net generation rose 5% to 21.8 billion units. Reported headline total revenues were INR 10,867 crores, an increase of almost 25%. Again, the hydro truing up impact last year was almost close to INR 600 crores. Adjusted for that YOY, revenues are up 33%. EBITDA adjusted for exceptionals for the year overall came to INR 3,817 crore, up 5% YOY. Adjusted profit after tax once exceptionals are taken off.
Pritesh Vinay
executiveWhen we were truing up liability exceptionals last year, this year we saw an exceptional gain of INR 120 crore during the first nine months, coming from the reversal of a loan that had been extended to a third party in earlier years. Once you adjust for that on a like-on-like, like-on-like basis, adjusted net profit came in at INR 1,348 crore, which was up 15% YOY. That covers the PNL side. Now moving to the balance sheet side — and here I'd like to put a few things in context. As you know, we closed the Mytrah acquisition on 29 March 2023, so from a consolidation as per books standpoint, the Mytrah assets were available to us for only two days of the year, through 31 March, while the balance sheet is consolidated as of that particular day. So to make sense of these numbers, we believe it's important to look at the pro forma basis on a combined basis. I'd request everyone — you have access to our presentation, which has been uploaded on the website. Please take a look at slide number 39, which explains the net debt bridge; that would give you more clarity on how to interpret the debt levels.
Pritesh Vinay
executiveWhen we look at the quarter and the nine months that closed in December 2022, the company's total net debt came to INR 9,840 crores. Within that figure, INR 6,475 crores represented net debt at the operating companies, while a further INR 3,365 crores consisted of project loans drawn for capital work in progress. If you look at the debt at the operating companies during the quarter, it rose by roughly INR 3,500 crores, reaching just under INR 10,000 crores. That additional debt came mostly from balance sheet borrowing we undertook at the existing thermal business to fund our growth — both for M&A and to put promoters' equity contribution into the projects currently underway. At the operating companies, net debt is now approximately INR 10,000 crores. Against underlying EBITDA of INR 3,800 crores, net debt to EBITDA at the operating companies now works out to 2.6 times. The next slice of debt to consider is the debt on the CWIP. The figure that was INR 3,365 crores has increased slightly and now sits just above INR 3,600 crores. For Mytrah, net debt of nearly INR 8,600 crores has come onto the books. On Mytrah, let me take a few minutes to explain how to look at its performance.
Pritesh Vinay
executivePrashant noted earlier, when he opened, that Mytrah's pro forma performance across 12 months for the year that ended in fiscal 2023 came in at roughly INR 1,187 crores. Headline net debt was INR 8,600 crores. EBITDA has not been normalized. As you know, we run a very active plan for asset optimization and performance improvement, which Prashant has already discussed. The signs are very encouraging, and this carries an EBITDA potential of INR 1,650 crores. Net debt of INR 8,600 crores against normalized EBITDA of INR 1,650 crores works out to roughly 5.2 times net debt to EBITDA for the Mytrah business. On a combined basis — Mytrah's normalized EBITDA plus the debt that already sits on the operating business — we have net debt of about INR 18,500 crores, which will be serviced by EBITDA of close to INR 5,500 crores. So the combined net debt to EBITDA comes to 3.4 times. As I said, combined EBITDA will be close to INR 5,500 crores across both businesses for the full 12 months of fiscal 2024, viewed from a run rate standpoint. That is on the net debt side. I would also like to spend a few minutes on Mytrah's financing itself.
Pritesh Vinay
executiveSo this transaction is quite complex, and a truly landmark and benchmark refinancing and debt sizing package was arranged right away. It's extremely uncommon — normally, with large-sized M&As, the standard approach involves bridge financing, buying the assets, and then spending six to 12 months establishing the permanent capital structure. In this case, we closed the deal on 29 March and drew the first tranche of the refinancing facility on 31 March itself. Regarding Mytrah's portfolio specifically, we've discussed the EBITDA improvement, but there will also be a substantial benefit below EBITDA. By implementing this refinancing and debt sizing package, we've achieved more than 240 basis points on the annualized weighted average interest rate. From a run rate perspective, that translates to roughly INR 240 to 250 crores in finance cost savings starting on day one. That covers the Mytrah financing. Now I'll take another moment to discuss the receivable cycle. I'll split this conversation into two parts.
Pritesh Vinay
executiveFirst, looking at the JSW Energy portfolio by itself, excluding Mytrah — if you look there, performance has been quite encouraging as well. If you check one of the specific slides we have on the receivables cycle: as of 31 March 2023, in terms of day sales outstanding, receivables came in at 60 days of sales versus 63 days of sales. You'll see headline absolute INR growth numbers that are higher, but that's due to the higher fuel cost, and hence the higher revenues, that we discussed. The right metric to focus on is base sales outstanding. Even within that, if you look, total overdues at year-end were roughly 20%, close to 20% of total receivables. We've seen a very, very healthy collection trend over the last month, month and a half since then. The receivable cycle remains healthy. If you look at the Mytrah receivable cycle, that's also a very interesting situation. In the investor presentation, we devOT
Pritesh Vinay
executiveApologies — that should be slide 10, not the one I indicated. When we submitted our binding bid during last year's Mytrah sale process, we were working off audited figures as of March 2022, and at that point Mytrah's outstanding receivables stood at nearly INR 1,500 crore. Over roughly the past 12 months — maybe 13 to 14 months by now — we've watched that receivables cycle shrink by close to INR 500 crores. We've also implemented a very robust, tightly focused collection efficiency program. Each month, what we bring in versus what we bill remains consistently strong. On the bottom left-hand chart of this slide, you can see three specific months presented on an index basis where our collections run 150%-220% above our billing. We're highly confident that we can bring the receivables cycle of the Mytrah portfolio down to healthy levels within 12 months as well, which would free up substantial liquidity for the system. Against that backdrop, consider the enterprise value Prashant mentioned of INR 10,150 crores, plus net current assets — this really shapes up as a very, very cash-accretive transaction for JSW Energy.
Pritesh Vinay
executivePerhaps I’ll leave it at that, and operator, could you please open the queue for questions and answers.
Operator
operatorThanks a lot. At this point we'll open things up for questions. To ask one, just hit star and one on your touchtone phone. Should you want out of the queue, press star and two. We ask that everyone use their handsets when posing a question. Ladies and gentlemen, we'll pause briefly while the queue comes together. Our first question comes from Sumit Kishore at Axis Capital. Please go ahead.
Sumit Kishore
analystGood evening, Prashant and Pritesh. I have to say, the opening remarks and the growth outlook you set out for the company were excellent. My first question concerns the Government, which has set a monthly target of awarding 15 gigawatts of RE capacity in each fiscal year beginning with FY 2024. What's your sense of what's likely to happen in this fiscal year? That's my first question.
Prashant Jain
executiveFor me, that's a hard decision, because as a company we aren't putting more focus on these kinds of bids—we still see the rates being discovered in them as not remunerative enough for a firm like ours to take on the projects and hit the normative returns we're targeting. That's the reason we aren't following these bids at all. For me, it's a hard decision.
Sumit Kishore
analystSure. And a follow-up on that: since you're building a 1 gigawatt manufacturing facility for modules integrated all the way up to, you know, wafers, does that also mean you're creating a platform that lets you set up at least 1 gigawatt of solar capacity at JSW Energy each year after that?
Prashant Jain
executiveWe think we’ll have that kind of requirement, because most of what we’re planning is close to 1.8 to 2 MW of the capacity we’re going to build, which will be solar and wind combined, and the majority of the capacity that we’ll be able to use.
Sumit Kishore
analystAbsolutely. Looking ahead across the coming 3 to 5 years, beyond that 10 gigawatts of locked-in capacity, on the generation side, what kind of visibility do you have regarding group captive generation projects — which, as you know, is something the JSW Group requires, particularly JSW Steel?
Prashant Jain
executiveWe've put together a medium-term plan, and what we see is that going forward we'll have close to 6 GW of group captive requirement. Beyond that, we're also looking at certain C&I segment. On top of that, we're looking at the electron to molecule business as well. So that's how we view it: the generating capacity that we keep adding will mainly be within group captive or C&I customers, or certain very attractive tenders where the competitive landscape isn't substantial. The way we've been building our business is that it spans different kinds of energy product segments. Be it battery storage, be it pumped storage, hydro or solar, wind, thermal — wherever we find a great opportunity to deploy capital and generate industry-leading returns, and for us, minimum mid-teen returns matter most. That's how we've been deploying our capital, and we'll keep doing that. Beyond that, we're also scouting inorganic growth opportunities. If any good growth opportunity like Mytrah comes along, where on a normative equity base we'd get north of 16% equity IRR.
Prashant Jain
executiveFor us, the whole transaction is a 100% leveraged buyout. On a net worth basis, the entire thing is value accretive to us. That is how we are looking at it, and we will keep doing so.
Sumit Kishore
analystI just want to be sure I understand — the 6 GW figure you mentioned, covering group captive plus C&I, comes on top of that 10 GW of locked-in capacity, correct?
Prashant Jain
executiveRight. Right. What I'm steering you toward is this: by FY 2030, we're getting to 20 gigawatts of generation. Within that, close to 6 gigawatts is going to be group captive over the next seven years — that capacity will be coming online — and a further 4 gigawatts will come from a range of other opportunities.
Sumit Kishore
analystOne final question: MoEFCC recently granted an exemption for pumped storage hydro projects from Environmental Impact Assessment. Do you think this could, you know, accelerate your pumped storage hydro project schedule? Over the next 3 years, how much capital do you expect to commit to pumped storage hydro? And what would the actual balance sheet investment be over that same period?
Prashant Jain
executiveSunil, I've already covered this — our FY 2030 goal sits at roughly 40 gigawatt hours of pumped storage capacity. That translates to somewhere near INR 25,000 to 26,000 crore in overall capital expenditure between now and FY 2030. The first project breaks ground during this financial year — at the tail end of it — and we've already secured that arrangement with the Government of Karnataka. That's how we're looking at it. On the approvals front, yes, the Ministry of Environment and Forest has been offering quite a few exemptions when it comes to EC and geotechnical surveys. Those steps are genuinely welcome, and they'll genuinely help us move the project forward much more quickly. I'd also like to mention that we're the country's biggest hydropower producer, with the finest track record of running all these assets. Over the past three and a half to four years, we've been constructing the Kutehr Project, which will be the quickest project ever built, despite corona wave conditions and various other hurdles we faced along the way. We've developed a strong execution capability for delivering the project, which is mainly carried out in-house with small contractor teams, and that makes us increasingly confident that we're one of the best places in the industry to execute these projects.
Sumit Kishore
analystGreat. There’s more I want to ask, but I’ll go ahead and join the queue at this point. You have my very best wishes. Thank you.
Operator
operatorThanks. Ladies and gentlemen, if you’d like to ask a question, please press star one. Our next question comes from Vivek Ramakrishnan at DSP Mutual Fund. Please go ahead.
Vivek Ramakrishnan
analystHi there. Great results — well done. I wanted to ask about the collections at Mytrah. How have you been able to speed those up, and has there been some kind of systemic shift such that going forward you won't see collections pile up either — or is this a one-off tied to the government scheme? That's all I had. Thanks.
Prashant Jain
executiveVivek, thanks for that question. You know, this is simply how we operate, and we take real pride in it — that's how we keep receivable cycling low across all our existing business as well. We're trying to replicate that same approach at Mytrah Energy. Of course, there's one thing I want to share with you and with everyone listening: there are structural changes taking place in the power sector. The Government of India has taken a number of very interesting steps that are helping recover receivables. At the same time, we also have strong relationships and very good management of receivables. Today, if you look at our presence, we're there pan-India and with every kind of DISCOM, and we're able to keep a very low receivable cycle. I can assure you that this receivable cycle will be aligned with JSW Energy's past performance, and it will be a permanent solution.
Vivek Ramakrishnan
analystAppreciate it, sir. Best of luck. Thanks.
Operator
operatorThanks. Our following question comes from Nikhil Abhyankar at ICICI Securities Limited. You have the floor.
Nikhil Abhyankar
analystThanks, sir, and thanks for the chance to ask. Sir, I have just one quick question. Could you walk us through the economics of the battery storage project? Since 50% of our capacity is going to be reserved for SHAKTI, how do we intend to use the rest of that capacity, and what will the cost economics of the storage look like?
Prashant Jain
executiveWhen it comes to storage, for that first tender we won, we've looked at two opportunities. The first one is the ancillary market, which has opened up, and we're seeing a very attractive trend in that ancillary market. We believe we'll be able to generate a better return than what we contracted with SHAKTI. The second thing is that we also have the option to bid in any of the energy storage bids that will come up in the future. Both options are available to us. Right now, we've considered the ancillary market, where the battery storage power will be scheduled in order to maintain frequency and demand. A new protocol guideline has come up, and based on it the ancillary market has opened up, and we will be generating a much better return than what we have contracted. Later on, we can either continue to remain with that or we can tie it up in any of the future bids.
Nikhil Abhyankar
analystGot it, sir. Sir, how much of our Ind-Barath plant is committed under PPA?
Prashant Jain
executiveWe won’t link that to what’s happening in the macro environment. We’ll hold on to it.
Nikhil Abhyankar
analystIs 100% going to be for merchant?
Prashant Jain
executiveYes. Since this will be extremely low cost. Suppose, for instance, that average tariff across the whole of last year came to INR 5.96. As I explained regarding a Coal India linkage price, the fuel price will be INR 1.30. Even if I pay a 100% premium on the Coal India linkage price in the e-auction market, my fuel price will be close to INR 2.20. That means I can make around INR 3.50 as a fixed cost into the merchant market. We will be keeping this capacity open for some more years. As and when we see the macro situation changing, we will be going into the long-term market.
Nikhil Abhyankar
analystGot it, sir. Has the coal partnership with CIL already been finalized?
Prashant Jain
executiveUnder the SHAKTI linkage scheme, coal can be obtained. We'll be putting in the bid, and there's also the spot auction that NCL is running. In and around the mines, there's sufficient coal available, and that can be handled either through the SHAKTI scheme or via the spot auction.
Nikhil Abhyankar
analystGot it. Thank you very much, and best of luck.
Prashant Jain
executiveThanks.
Operator
operatorThanks. Our next question comes from Anuj Upadhyay at Investec. You have the floor.
Anuj Upadhyay
analystYes. Thank you for the chance, sir. I just have a few points to clarify regarding Ind-Barath. You said a moment ago that all of the capacity is going to be built for the merchant. Please correct me if I'm mistaken, since my earlier understanding was that a portion of this capacity would be tied up on the module manufacturing side. Has anything changed there?
Prashant Jain
executiveAnuj, yes. Look, at first our thinking was that we’d build the polysilicon capacity in Orissa. That’s really the key point about how nimble our management is — we make calls based on how conditions shift. As things stand, the polysilicon market is getting crowded worldwide. Last year, demand totaled 800,000 tons. China is now adding a very large amount of polysilicon capacity. Within a 12 to 14 months timeframe, overall capacity will exceed 2.5 million tons, which is enough to make 850 gigawatts of solar panels. Last year, demand for solar PV panels was 260 gigawatts. Because of that, polysilicon prices that had been at $42 per kg have fallen to $16 per kg and are expected to drop below $10 per kg. That’s why we decided not to go into polysilicon capacity at this point of time. As a result, we’ve also held back from taking part in the PLI scheme for polysilicon to module capacity. Still, we could revisit the situation two years or three years down the line, but we don’t want to get stuck in the wrong cycle.
Prashant Jain
executiveThat is the reason we aren't considering any polysilicon manufacturing facility, at least for the near foreseeable future, until the demand and supply situation becomes favorable for setting up that kind of facility in India. So the entire capacity will stay open for the merchant tariff, since we are in a position to capitalize in this kind of scenario.
Anuj Upadhyay
analystAll right, so I just want to go back to that capacity figure you brought up for China — roughly 2.5 million, and sorry, that should be 50 gigawatts. Do you have any timeline for when it will be commissioned?
Prashant Jain
executiveWe’re looking at another 12 to 14 months, and then all of that capacity is going to come online in China.
Anuj Upadhyay
analystAlright. Regarding your capital expenditure plan, sir, you said roughly INR 75,000 crores of additional CapEx would be needed now across the coming 6 to 7 years, and that we won't be diluting anything for it. Could you expand a bit more on the sort of internal cash flows we could or probably will be generating to fund the equity CapEx on that capacity? Lastly.
Prashant Jain
executiveLet me take these individually, Anuj, since otherwise I'll lose track — you can put your question afterward, because if I don't go in order I'll forget.
Anuj Upadhyay
analystYeah, absolutely.
Prashant Jain
executiveSo your question covers both capital expenditure and cash generation. In the prior year, we produced roughly INR 2,700 crore to INR 2,800 crore of cash. That figure will rise in FY24 and beyond, since our EBITDA is climbing very fast — from INR 3,800 crore, next year's EBITDA will be at least 1.7x-1.8x, and a comparable situation is going to unfold. When you take on incremental debt at a 3:1 debt equity ratio, you are able to carry out capital expenditure of between INR 12,000 crore and INR 13,000 crore annually, and that amount will grow as cash flow rises further. So we will be putting to work close to INR 112,000 crore of capital expenditure, versus the mere INR 75,000 crore we had earlier indicated. Of that INR 112,000 crore, INR 30,000 to 35,000 crore has already been planned — for instance INR 16,600 crore for capacity expansion of the SECI and Group Captive project, INR 2,700 crore for Ind-Barath, INR 1,600 crore that we are now discussing for the wafer cell manufacturing facility, and INR 2,200 crore for the battery storage project.
Prashant Jain
executiveBeyond that, INR 10,200 crore — or INR 150 crore — relates to the Mytrah acquisition. Taken all together, that comes out to roughly INR 30,000 to 31,000 crore. The remaining INR 85,000-odd crore is going to be spent between 2024 and FY 2030. That's how the numbers work out.
Anuj Upadhyay
analystThank you, sir. And finally, regarding green hydrogen, what exact capacity are we looking at, and the selling arrangements — I mean, exactly who will this green hydrogen be supplied to? What sort of PSAs or selling agreements are we eyeing? Have you already tied up with a few customers?
Prashant Jain
executiveSo we've already secured that. The capacity there is 3,800 tons. It's going to be sold to JSW Steel under a take-or-pay contract. That runs for seven years. The full plant gets amortized across those seven years. Once the seven years are up, it moves to variable cost plus ROE. That's cost plus a mid-teen ROE. It works out to roughly somewhere in the $3 to $3.5 per kg range, that kind of figure, and that's what the contract will be based on. On top of that, all of the oxygen will be contracted as well.
Anuj Upadhyay
analystThanks, sir.
Operator
operatorI appreciate that.
Prashant Jain
executiveThanks a lot.
Operator
operatorMuch appreciated. Our following question comes from Dhruv Muchhal at HDFC Mutual Fund, who is on the line. Kindly proceed.
Dhruv Muchhal
analystHello, sir, and thanks a lot. If I understand correctly, you said the Group Captive on its own could provide roughly 6 gigawatts. That comes on top of the 1 gigawatt you already have, which is already in the pipeline — is that right, sir?
Prashant Jain
executiveThat’s true.
Dhruv Muchhal
analystGot it. For JSW Steel, they'd likely need power around the clock. Would that also be covered, along with perhaps some pumped hydro that could bring in extra investment, or battery storage—or is it just the 6 GW we're thinking about right now?
Prashant Jain
executiveYou're absolutely right. On top of that, storage facilities will be included as well.
Dhruv Muchhal
analystI think it's reasonable to assume that a big portion of this will be on—well, how should I put it—a regulated ROE-type return basis?
Prashant Jain
executiveYes, definitely.
Dhruv Muchhal
analystUnderstood, sir. Great, sir. That's everything from my side. Many thanks. Best wishes. Thank you, sir.
Operator
operatorThanks. Our next question comes from Mohit at ICICI Securities. Please go ahead.
Mohit Kumar
analystHello there, and good evening — I appreciate the chance to speak. My first question concerns the guidance, specifically the 3.5 times EBITDA figure, along with normalized EBITDA and normalized PAT. Could you clarify for us what normalized EBITDA and normalized PAT come to for FY 2023?
Pritesh Vinay
executiveYes, I’ll take care of that. Mohit, I’m not sure whether you came in a little late, but I’m glad to go over it with you once more. It’s really straightforward. Our own EBITDA on an annual basis comes to INR 3,820 crores, rounded, with Mytrah excluded. Then you add Mytrah’s normalized EBITDA, which is INR 1,650 crores, all right? That brings it to roughly INR 5,470 crores. That’s the normalized EBITDA.
Mohit Kumar
analystAll right. The PAT?
Pritesh Vinay
executivePAT is something you'll need to work out yourselves. On that INR 3,820 crores, you know, what PAT we've delivered — with INR 1,650 crores of EBITDA, you should be able to model it. There's INR 8,600 crores of net debt sitting there. You can derive it — Mytrah, you know, is a portfolio paying tax at roughly 25%-10%. From that, you'll be able to work out what the normalized PAT would be.
Mohit Kumar
analystOkay, so the second question concerns the solar module as well as the wafer expansion plant. Has the technology been finalized, have equipment orders been placed, and what timeline do you foresee for bringing that capacity online? And what's your plan for sourcing polysilicon — from within India or from outside India?
Pritesh Vinay
executiveThe plant is going to be located in Rajasthan. The technology has already been locked in. It's going to use TOPCon technology, and we're at the final stage of ordering the equipment. Polysilicon is going to come from China, since at this point that's the only place it's manufactured apart from Europe and the U.S., plus some small capacity in Korea. Nobody in India is producing it, and we don't know when it will be available. This facility should be up and running in roughly 18 months.
Mohit Kumar
analystOkay. At some point, do you think your ambition in solar manufacturing might grow to a bigger scale, or into polysilicon, or something along those lines?
Pritesh Vinay
executiveWe’ll proceed one step at a time, as we see it. We do not view ourselves as being in module manufacturing or the third-party business. Our focus is solely on energy and its derivative products—the electron-to-molecule business—and on storage products. That is where our concentration lies. Any backward integration we pursue, whether through PV cell manufacturing or other areas we have discussed, such as the wind licensing deal and similar items, serves only to reduce our supply chain cost. We are, and we intend to remain, the lowest-cost power producer, and we want to keep that competitive advantage. To preserve that advantage and stay competitive, we are working on the supply chain side. We do not want to commit our capital to third-party manufacturing or to entering those kinds of businesses, because we do not know how they will turn out in the future. We want to direct our capital deployment only toward the segments where we are efficient, and that is where we want to concentrate.
Mohit Kumar
analystSir, on the second point, hydrogen again. I see you've secured some approval from the Government of Karnataka regarding green ammonia. Will that only constrain our green hydrogen for the foreseeable future? Have you settled on which technology you'll deploy to produce green hydrogen? Is any part of this connected to Fortescue?
Prashant Jain
executiveThis has nothing to do with Fortescue. First, that agreement has lapsed. Second, we've laid out in detail how ready we are to move into the electron-to-molecule business. You have to recognize that right now, on a global basis, no ecosystem exists for green ammonia or green hydrogen — not for long-term contracts, not for transportation arrangements. All of it is still being figured out. In that sort of setting, everything remains a plan. We're moving forward and executing a project by securing arrangements for green steel production. All our resources are in place. Under our current contract with JSW Steel for 1 gigawatt at Vijaynagar, 25 megawatt of round-the-clock power will be drawn from there and used to produce green hydrogen. The technology is already finalized. Final equipment ordering is at a final stage. After this approval from the board by both the companies, we'll enter into the contract with the equipment suppliers and have this up and running within a 18 months time frame. These are what we'll be deploying not only toward green ammonia, but also toward CO₂ capture, making green methanol. It's sustainable aviation fuel, a green chemical complex — all of that we have been working on.
Prashant Jain
executiveAll of that is still some time off, once the full ecosystem has matured properly. Those elements are being worked on by a range of Indian policymakers along with policymakers globally, and the transport and port ecosystem plus the railway ecosystem are in the process of being built out; we are moving in the right direction and securing a first mover advantage in green hydrogen.
Mohit Kumar
analystCould I ask, sir, whether that's alkaline or PEM technology?
Prashant Jain
executiveYeah, it's going to be alkaline technology.
Mohit Kumar
analystThanks, sir. Thanks. Many thanks. Appreciate it. Yes, best of luck to you, sir. Best of luck.
Prashant Jain
executiveThanks.
Operator
operatorThanks. Our following question comes from Atul Tiwari of Citigroup. The line is yours — please proceed.
Atul Tiwari
analystYes, sir, thank you very much. Sir, regarding Ind-Barath's situation when it comes to coal supply — does it already hold a linkage with Coal India, or has that linkage not yet been tied up? I ask because you mentioned a price in the INR 1.6 to INR 1.4 range.
Prashant Jain
executiveNo, no. What I was doing was describing the competitive landscape for you. At Coal India linkage prices, selling into the merchant market isn’t possible. You must sell into the merchant market. Either you obtain the coal, you take it into the SHAKTI B(ii) scheme — that’s the quarterly auction or the spot auction. Those are the only 2 ways you can source the coal, and in them you must pay the premium on top of Coal India linkage prices. That’s how I’m explaining the competitive landscape to you. Even if I’m paying a 100% premium, what will my variable cost be and what will the selling price be? That’s how I explain it to you.
Atul Tiwari
analystAll right. Even with that 100% premium applied, fuel cost won’t exceed INR 1.4. That’s the figure you cited.
Prashant Jain
executiveNo, no — what I meant was that with the 100% premium, the fuel price will come in at about INR 2.25 to INR 2.30 at the. Since INR 1.30 to 1.40 applies without the premium, neither the royalty nor the Clean Energy Cess will change while I'm paying that premium.
Atul Tiwari
analystRight, sir. Got it. Thanks — that clears things up a lot.
Operator
operatorThanks. Our next question comes from Rohit Natarajan at Antique Stock Broking. The line is yours — go ahead.
Rohit Natarajan
analystThanks for giving me the chance to ask. I'll start with the battery energy storage solutions segment. Regarding the MoU we've signed, you mentioned a capacity charge of roughly INR 1 million per megawatt each month, and that it applies to two cycles. Could you walk us through the other 40% that will be sold on the open market? What would that IRR look like? And what levelized cost of storage do you have in mind?
Prashant Jain
executiveRegarding the ancillary market return—which I went into in response to your earlier question—it will be near or above what we're getting into the SECI contract. Overall, we expect to do better than the mid-teen equity IRR on this project.
Rohit Natarajan
analystAlright, just so I understand how it breaks down between the battery package and the BOS charge — what does that look like? Is it roughly $130 per unit for the battery and $170 per unit for the BOS? How does that split look right now, at this point?
Prashant Jain
executiveI'm going to hold off on sharing those kinds of figures right now. I hope you understand these are newly developing projects and developing trends. We've explained to you our overall project cost, and we've also discussed what kind of equity IRR we'll be developing and getting. However, at some point, as the technologies mature and this market deepens, we'll be glad to share those kinds of numbers.
Rohit Natarajan
analystOkay. When it comes to hydro pumped storage, what would be a realistic timeline for construction and commissioning that we should consider across every project currently in your pipeline?
Prashant Jain
executiveOnce you've got the PPA signed and every statutory approval is in place, the projects generally take somewhere in the range of 36 to 48 months, that kind of timeframe. These projects are quite straightforward, since there's no tunneling involved. You've just got an upper barrage, a lower barrage, plus one powerhouse and a steel penstock to build. They're very simple projects indeed. The government is also helping by giving very quick approvals for this type of project. After the statutory approvals and the PPA, 36 to 48 months is a safe period to consume.
Rohit Natarajan
analystWhen you sign these PPAs, is there a specific tariff figure you have in mind?
Prashant Jain
executiveWhat we have here are structures that differ from the tariff peak and similar matters. Essentially, these are lease-type contracts that are being executed. It doesn't worry me whether you're using it for 1 cycle, 2 cycles, 3 cycles, based on what's needed, or multiple cycles that the grid or utility taking it on lease can draw on according to its own specific requirement. That isn't our concern. This is build, own, and operate and lease back. My job is to construct a project, guarantee a specific efficiency, and maintain a specific availability. Beyond that, at what price and on what time cycle the power arrives, and at what cost the utility is consuming it, is up to them. Some might be drawing the power entirely free, others might be using some, purchase power. It varies from utility to utility, grid to grid. That's how this business will look over a period of time.
Sumit Kishore
analystThanks. That covers everything from my end.
Operator
operatorThanks.
Prashant Jain
executiveCould we have the final question, please?
Operator
operatorYes, and Sumit Kishore from Axis Capital will ask the final question. Please proceed.
Sumit Kishore
analystAppreciate the chance to follow up once more. So Pritesh, I’ve got one question for you. For 2024, what weighted average cost of debt ought we to apply? And when it comes to the additional debt you take on, what’s your approach going forward? Will it be entirely local borrowings, or will there be some blend of local and foreign borrowings?
Pritesh Vinay
executiveSumit, that's a really interesting question. The weighted average interest rate is the simpler thing to discuss, since we're already at that level. It's already reflected in the presentation. As you can see, we stood at 8.36% as of the end of March. Once you factor in the weighted average portfolio after the debt sizing is implemented and the Mytrah refinancing is fully drawn down, that figure ought to come in at a print of roughly 8.5% to 8.6%. On a weighted average portfolio basis, from a run-rate perspective, you're looking at something nearer to 8.45%, correct? Now, if I had to hazard a guess for the coming year — the underlying assumptions being that we're at the peak of the repo rate cycle — do you think the bank MCLR catch-up to the repo rate increase is finished, or how many more legs are left in it? Just to give some thought to that sort of thing. Being conservative, from a worst-case standpoint, I would expect perhaps an additional maximum of 15 basis points of increase from there, probably on that.
Sumit Kishore
analystSo, 855, 860.
Pritesh Vinay
executiveCorrect. Perhaps 8.6% is the level we'd end up at, you know, based on these sorts of underlying assumptions, and should any of those assumptions shift, then that figure would shift too.
Sumit Kishore
analystWe’re talking about incremental debt.
Pritesh Vinay
executiveThat's one point. As for the second half of your question: looking at how we approach financing, when it comes to growth projects — the organic ones — across our whole portfolio, we've opted for 100% long-term project financing, depending on what kind of project it is and so on, with a door-to-door tenor of, say, 20 years and an average life of between 16 to 17 years. Those have been arranged at very, very fine and tightened interest rates, given the years of this credit standing in the bank loan market. So, extending that logic, given the favorable INR liquidity and rates environment vis-a-vis the FX markets, we have been 100% dependent on INR markets. As it happens, if you recall, two years ago we completed our maiden green dollar bond offering, and that was done precisely with this view in mind — to lock in low levels of rates on a hedge to basis for the next 10 years, because one was anticipating a tightening of the rates market. Looking ahead, if you're asking what the mix is likely to be, the way it appears, at least in the near to medium term, it appears that the INR market is still likely to be much more favorable from a rates and credit spreads point of view.
Pritesh Vinay
executiveRegarding what little visibility we have from an FX-denominated market, I'd venture another guess that INR liquidity will be the path ahead, at least for roughly the next 12 months. From the feelers we have, as we secure more bids, we're actually flooded with a greater number of banks eager to gain exposure to our growth project than we can take on. So that's the situation at present.
Sumit Kishore
analystAll right, all right. Then my follow-up: regarding your Ind-Barath project more specifically, would you likewise sell the generated power through the electricity exchanges, or would it lean more toward bilateral contracts? In the same way, for pumped storage hydro, does the approach also involve covering the peak demand requirement and capturing the higher prices? Would you sell power on the electricity exchanges in both of these projects — the merchant thermal project being set up today, or being commissioned after having been shut down, and pumped storage hydro?
Prashant Jain
executiveWe don't expect to be building any merchant capacity, whether merchant pump hydro or otherwise. Ind-Barath is really an incidental opportunity for us — there was a PPA in place when we made the bid, but we weren't able to revise that particular PPA, and the macro situation is shifting. So that's why we're trying to seize the advantage of being an agile company in this business environment and create shareholder value. Let me be very clear: every project going forward, whatever investment we make, will be a long-term tied-up business — that's how we want to play. There are certain things that come up in certain constructs where we see enormous economic value. Part of the capacity could happen — for instance, if we're building, say we have a 1,500 megawatt project in Maharashtra, two projects, and one project of a similar capacity is in a southern state. That gives us close to 12 gigawatt-hour of storage capacity on 8-hour storage. If I get a bid for 6 gigawatt or 7 gigawatt and I tie it up, and then another bid of 3 gigawatt, then my 3 gigawatt capacity is open while I'm constructing the project, and once I've commissioned the project, I can play into the peaking market.
Prashant Jain
executiveThe moment I can lock that down, I want to lock it down. That said, we won't add any capacity that rests solely on the merchant. There may be some incidental situation in which we can deploy certain capacity on a strategic basis for a stretch of time, but we'd like to lock down as much as 100%.
Sumit Kishore
analystOkay, my final question concerns the 72 gigawatt hours you've secured in pumped storage hydro. Looking out roughly 3 to 4 years, how many environmental approvals and other pre-project approvals do you anticipate finishing within the next 1 year, 2 years, 3 years? If you could give us some sense of that.
Prashant Jain
executiveOn an approval basis, it's reasonable for us to assume that within the next 18 months, we'll have every approval in place across all the projects. But when it comes to execution and deploying capital, we're only talking about 50% of that by FY 2030, since we really need to see how many bids come in, whether they'll be in a competitive landscape, along with the capital requirement and execution issues. That's the way we see it.
Sumit Kishore
analystAppreciate it. That covers everything I wanted to ask.
Operator
operatorI appreciate that.
Sumit Kishore
analystI appreciate it.
Operator
operatorThanks. At this point, I’d like to pass the conference to Mr. Rohit Natarajan for the closing remarks. Sir, the floor is yours.
Rohit Natarajan
analystWe appreciate the chance the management has given us. Before we wrap up this call, I'd like to check with the management whether they have any closing remarks they'd like to make.
Prashant Jain
executiveNo, I believe that covers everything. Should any questions come up, don't hesitate to reach out to our investor relations team at any time. Thank you.
Rohit Natarajan
analystI really appreciate it.
Prashant Jain
executiveI appreciate that.
Operator
operatorThanks. That brings this conference to a close on behalf of Antique Stock Broking. We appreciate your participation, and at this point you're free to hang up.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.