JSW Energy Limited (533148) Earnings Call Transcript & Summary

January 23, 2024

BSE Limited IN Utilities Independent Power and Renewable Electricity Producers earnings 47 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and welcome to the JSW Energy Q3 FY 2024 earnings conference call, which ICICI Securities Limited is hosting. Just a reminder that every participant line will be in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you require help at any point during the call, please signal an operator by pressing star then zero on your touchtone phone. Kindly note that this conference is being recorded. I'll now turn the conference over to Mr. Mohit Kumar from ICICI Securities. Thank you, and over to you, sir.

Mohit Kumar

analyst
#2

Thanks, Ray, and good evening, everyone. ICICI Securities welcomes all of you to this Q3 FY 2024 earnings call for JSW Energy Limited. We're fortunate today to have with us Mr. Prashant Jain, our Joint Managing Director and CEO, along with Mr. Sharad Mahendra, Joint Managing Director and CEO Designate. Also joining us are Mr. Pritesh Vinay, Director Finance and CFO, and Mr. Vikas Choudhary, Head, Investor Relations and Treasury. We'll begin with some short opening remarks, and after that we'll move to Q&A. Prashant, sir, over to you.

Prashant Jain

executive
#3

Thank you, Mohit. Good evening, ladies and gentlemen. To begin with, this marks my final conference call with all of you, so I want to open by expressing my gratitude to each one of you, and also to JSW management for providing me this opportunity. Joining me now is Mr. Sharad Mahendra, who will take over from me effective 1st of February. If we turn to the quarter just ended, power demand was very robust at 10% in quarter three, and across the first nine months it rose by 8%. We recorded a peak demand of 222 GW in the month of October for the first time. Installed capacity in the country now stands at 428 GW, with total capacity addition of 12 GW during the first nine months. Of that, close to 8.7 GW was RE capacity added over the nine months, and in the quarter, 2.1 GW of RE capacity was added. Another trend we have observed during this first nine months, and which carried into quarter three, was lower hydro generation. In the quarter, it fell by 30%, and over the first nine months, it declined by 17%.

Prashant Jain

executive
#4

Merchant tariffs have begun to pick up now, though during the quarter they were subdued at INR 5, and that was down 13% year-on-year. But as we speak, merchant tariffs have risen. They now sit in the range of INR 6.5-INR 6.7 per kWh. Thermal coal is displaying a very declining trend. In the month of October, it was ruling at 130 and kept sliding down to $100 by December end, and then right now it is ruling at $94-$95. So it is showing a declining trend at this point of time. In terms of the company, total generation was up by 43%, which came primarily from all accounts. We saw long-term sales go up, short-term sales go up, and RE generation also went up. And, EBITDA was up 69% at INR 1,229 crore, primarily for the same reasons. The interesting part was, as we promised, we have been talking about the Mytrah turnaround. On a pro forma basis, Mytrah did INR 1,260 crore of EBITDA, which was equivalent to what it did in the 12 months in the previous year. The Mytrah turnaround is looking to be quite robust going forward.

Mohit Kumar

analyst
#5

Eleven.

Prashant Jain

executive
#6

Eleven — sorry, my apologies for that — INR 1,160 crores. Total capacity stands at 7.19 GW operating, and we remain on track to reach 9.8 GW by December 2024, consistent with what we've laid out. We're glad to report that unit number 1 at Ind-Barath was commissioned during the month, and it's performing quite well. As we speak, that unit is carrying over 150, 160 MW of load, and we expect full load to be reached within the current month. All the power we're producing is being sold through short-term sales, and we feel quite encouraged by the trends as we move forward and through the rest of the quarter. Unit two should also be commissioned during this quarter, and the RE capacity addition program continues on schedule. We then expect to complete, in quarter one and quarter two, both the SECI projects and the group captive projects — that is, SECI 9, SECI 10, along with the group captive projects. The hydro projects will be commissioned as well. With all of that, we will hit this 9.8 GW. As for Strategy 2.0, we are pursuing it aggressively on both the group captive side and the SECI bids.

Prashant Jain

executive
#7

I'm glad to report that over the recent three months, the tariffs we've been observing in the SECI bids have shown quite encouraging trends, and that has strengthened our confidence to move on this front right away. So now we're bidding aggressively on the quantitative side across the various bids coming before us. For Strategy 2.0, we'll be looking at both group captive and the SECI bids, along with other credible third-party bids that are in the pipeline over the next two to three months' time frame, and that will then form the next pipeline. As for the storage projects, the pre-development activities are proceeding on schedule. I expect that after the election, a substantial number of storage bids will be coming our way going forward. As you may already be seeing, there are growing trends toward more and more wind bids arriving, and people are — various states are seeking those kinds of opportunities to tap additional power going forward. So storage will also be coming to the forefront going forward. With that, I'd like to open the forum for questions and answers.

Prashant Jain

executive
#8

Thanks.

Operator

operator
#9

Thanks a lot. We’re moving into the question-and-answer portion now. If you’d like to ask something, you can press star and one on your touchtone phone. Should you want to drop out of the queue, press star and two. We ask participants to use handsets when posing questions. Ladies and gentlemen, we’ll pause briefly while the queue is put together. To ask questions, please press star and one. Our first question comes from Anuj Upadhyay at Investec. Please go ahead.

Anuj Upadhyay

analyst
#10

Thank you for the chance to speak, sir. Could you give us an update on the capacity you have for manufacturing modules? Since there's an expectation that it will be moved to Rajasthan. Any news on that would be useful.

Prashant Jain

executive
#11

Thanks, Anuj, for that question. Actually, this is another interesting piece, and it's something we've been observing in the business dynamics, and it also speaks to JSW Energy's agility. In the last quarter, panel prices have been approaching single digits, as we speak right now, and at present they're at roughly 10 cents to 11 cents. So we've been fully prepared to do the groundbreaking, but we've placed the project on hold at this moment to reassess the business viability for a while longer. So I don't think that at the panel prices prevailing right now, it would make sense at this moment even with 40% duty being paid. So we would prefer to wait a while longer and then evaluate it once more. So at this moment, we've put it on hold.

Anuj Upadhyay

analyst
#12

All right, that helps. And is there anything on the front side as well? My understanding is that your plan is to commission a single project, which is mostly captive — feel free to correct me if I've got that wrong — one over the next two to three years.

Prashant Jain

executive
#13

Yeah. So on the captive side, I believe within the next one quarter we'll be announcing the formal signing of the agreement, and that's the approvals process, which is currently going on. However, we've already begun the pre-operative activities, so we'll be able to commission it on schedule, which we have to outline. So in one quarter, we should be in a position to formally sign the agreement.

Anuj Upadhyay

analyst
#14

Much appreciated, sir. Best of luck to you, sir.

Prashant Jain

executive
#15

I appreciate that.

Operator

operator
#16

Thank you. Anyone who would like to pose a question should press star and one on their touchtone phone. Ladies and gentlemen, if you want to ask something, just press star and one. Our next question comes from Nikhil Abhyankar of ICICI Securities. Please go ahead.

Nikhil Abhyankar

analyst
#17

Thank you, sir. I appreciate the chance to ask this, and I wish you the best of luck in your future endeavors. My question concerns the captive thermal capacity you hold. You'll have roughly 700 additional coming starting next year. So are we considering comparable opportunities in stressed assets to add thermal assets going forward?

Prashant Jain

executive
#18

Thanks for that question, and thank you for the kind wishes. We're seeing a substantial number of opportunities on the brownfield expansion side, in thermal space as well. One opportunity we see is right at the Ind-Barath location itself, where there's a chance to set up as much as another 4,000 megawatts of thermal capacity. Those projects are at the drawing board stage right now, and very soon we'll be moving ahead for the necessary approvals. As soon as we have those approvals in hand, we'll be starting those projects, and we'll do it in a phased manner. The second opportunity is Rajasthan, where we can add another 1,100 to 1,200 megawatts of capacity. The state of Rajasthan has already announced that particular project, and with the new government in place, that expansion could get started very soon — will get started very soon. So those are the two locations, and they're going to be pit head, and there will be no cost involved because we have all the land, water, and other infrastructure in place. So we could — we will be able to put up the new plants at a very competitive price, and very quickly.

Nikhil Abhyankar

analyst
#19

Got it. So my understanding is that these projects weren't part of your 2.2 project, correct?

Prashant Jain

executive
#20

You've got that right.

Nikhil Abhyankar

analyst
#21

They weren't—

Prashant Jain

executive
#22

Those are the additional capacities that are going to come online.

Nikhil Abhyankar

analyst
#23

So overall, we're looking at 5.2 giga of thermal capacity being added?

Prashant Jain

executive
#24

I'd frame that as blue sky thinking — that this kind of opportunity exists. But everything will unfold gradually, since, you know, there has to be substantial security, there has to be the environment, and clearance plus other approvals are required. So we need to address each and every item, because right now, seriously speaking, what we're saying is that the country faces a power shortage, and demand for power is growing at double digits. And so there's a huge expectation that more and more PPAs on the thermal side will happen, yet PPAs are not happening. So to achieve financial closure on any thermal project, a competitive bid has to be announced by the state government, and that must be done. But we are getting ourselves ready — shovel ready, approvals ready — and then, as and when we see PPAs happening, we will be able to latch on. And then, most importantly, what we are preparing ourselves for is that we sit at a location where our variable cost will rank among the lowest in the country for future projects.

Prashant Jain

executive
#25

That's the approach we're taking.

Pritesh Vinay

executive
#26

So Nikhil, if I could jump in here — the key word Prashant added is "phase." It's going to be phased and modular, and not, you know, 5,200 MW all at once, right? So with all the factors Prashant mentioned, they're coming together, and in a modular fashion, you take one phase, do it, and then you subscribe.

Nikhil Abhyankar

analyst
#27

So will we be aiming to lock down all of that capacity — anything extra we bring on as well — or would we rather hold a portion of it as merchant capacity too?

Prashant Jain

executive
#28

Honestly, that's going to depend on the situation. As you know, right now that capacity sits on a merchant basis, but in the end, with capacity that large, relying on a single merchant isn't a good idea at all.

Nikhil Abhyankar

analyst
#29

Okay.

Prashant Jain

executive
#30

So I think a balanced portfolio is what we need to build. As things stand today, if you look at it, we had 700 to 800 megawatts of open capacity, and that has now gone up by another 350 megawatts, with a further 350 coming by the end of this quarter. So we're talking roughly 1.4 gigawatts of open capacity, which is already a fairly large amount. So ultimately, you know, against a balance sheet size by the end of calendar year 2024, you're looking at 14%-15% being open capacity. That's quite a large capacity.

Nikhil Abhyankar

analyst
#31

Mm-hmm.

Prashant Jain

executive
#32

So I think we need incremental evidence that more PPAs are getting signed. But near term, there may be room to add another 500 to 1,000 MW — though not past that.

Nikhil Abhyankar

analyst
#33

Got it, sir. I have additional questions, but I’ll rejoin the queue. Thank you.

Operator

operator
#34

Thanks. Ahead of the next question, a quick reminder for everyone that pressing star and one will get you into the question queue. Our next question comes from Rajesh Majumdar at B&K Securities. Go ahead.

Rajesh Majumdar

analyst
#35

Good evening, sir, and congratulations on the strong set of numbers. So, sir, I had a couple of questions. The first one concerned the discussions around Amarkantak and whether JSW Energy is putting in a bid for this project. I've been hearing reports that the bid is going from 41 in the previous bid, which we saw from Adani, and there are some rumors to that effect. That was my first question.

Prashant Jain

executive
#36

Rajesh, thanks for that question. As I’ve said before, we’re a growth-oriented company, so it’s always reasonable to assume we have interest in every location. Whenever an opportunity exists, we’ll be examining it at all times and assessing it on an ongoing basis. So include me in for any opportunity you’re hearing about.

Rajesh Majumdar

analyst
#37

Okay. So when you provide a range for debt to EBITDA, you're clearly factoring in any fresh acquisitions or expansions you'd want to pursue on top of the 2.0 plan we've already laid out, correct? Or, if something really attractive comes along, debt could run a bit above that level—more than what we've baked into this plan?

Prashant Jain

executive
#38

So Strategy 2.0 was laid out with those covenants in mind, and also, you know, with a certain amount of headroom kept in front of us. And all of it depends on the kind of cash flows we're generating and the kind of rating we want to hold on to by keeping certain debt-EBITDA ratios and other ratios in mind. And based on our own estimates, we feel our framework lets us do better than Strategy 2.0. And I'm also seeing that on cards, Strategy 2.0 could be achieved much, much ahead — and that's what, you know, Sharad is also a more aggressive leader than me, and I see that it's going to happen much ahead of the schedule. And once we finish Strategy 2.0 ahead of the schedule, the extra cash will let us do more capacity. And Strategy 2.0 was conceptualized without any capital raise or monetization at either Neo level or at the holdco level, and those are also opportunities at some point of time when the opportunity arises. So, if there are — there is a lot of headroom to grow beyond that.

Rajesh Majumdar

analyst
#39

Could you perhaps lay out a few of the ways you might monetize things? For instance, JSW Neo, or anything along those lines that you're considering?

Prashant Jain

executive
#40

As we've consistently said, we've kept value unlocking in mind and have looked to act on it at the appropriate moment. You know, this same question was put to me a year back as well. But looking at it now with the benefit of hindsight, had I gone ahead with that monetization 12 months ago, I would have been doing a disservice to the shareholders. And today, this is the valuation at which we stand, and this is where the power sector tailwind is arriving. So I think it's a dynamic situation, and we are always evaluating it at the board level. And at the right point of time, we will certainly do that, and that's what I can assure you. Then the most interesting and most paramount thing we will keep for us will be the interest of the minority shareholder — at what valuation, at what time we should do that.

Pritesh Vinay

executive
#41

Rajesh, if I could add something to what Prashant said, that will also tie back to the end use. For instance, take a look at how we deliver and execute — up to now, capital has not been a constraint for us, correct?

Rajesh Majumdar

analyst
#42

All right.

Pritesh Vinay

executive
#43

Like Prashant mentioned, a proper balance has to be found between value accretion and the capital requirement. So, at the intersection of those two considerations, we would certainly not be opposed to moving. Yeah.

Rajesh Majumdar

analyst
#44

Absolutely — glad that was useful. Thanks a lot.

Operator

operator
#45

Thanks. Anyone who’d like to ask a question should press star and one. Our next question comes from Sumit Kishore at Axis Capital. Please go ahead.

Sumit Kishore

analyst
#46

Good evening, and thank you for having me. To start off, I'd like to ask whether you can walk us through how things stand on the MOA and MOIs for SECI BESS and PCKL, as well as the MOUs signed with JSW Steel covering storage and RE capacity?

Prashant Jain

executive
#47

Yes. So Sumit, on BESS, our expectation is that it gets formalized during the current quarter. They've already closed a portion of that capacity, while the remaining part they're working to close in this first quarter. So we think it will get done. And the bright spot on our side is that battery prices look quite attractive right now. So that should work out quite well. For PCKL, we've been given to understand that the signing will happen by the end of next quarter. And as I said in my opening remarks, the full JSW Steel capacity — covering both storage and the Group Captive — will be com-signed within one quarter.

Sumit Kishore

analyst
#48

All right, so.

Prashant Jain

executive
#49

Combining this quarter with the one after it, all the rest will be up and running.

Sumit Kishore

analyst
#50

So you were saying that something might get signed even for JSW Steel, storage, and RE capacity?

Prashant Jain

executive
#51

Yes. We anticipate—

Pritesh Vinay

executive
#52

That initial phase.

Sumit Kishore

analyst
#53

The first thing to figure out is the size of the first phase relative to the whole.

Pritesh Vinay

executive
#54

So we’re going to make that announcement, you know, once the battery agreement is signed. That exact configuration is still being finalized. Sumit, if you look back at what we disclosed previously, we stated that 6.2 GW of RE generation is required.

Sumit Kishore

analyst
#55

Absolutely.

Pritesh Vinay

executive
#56

And there was storage capacity as well.

Sumit Kishore

analyst
#57

Just one thing, yes.

Pritesh Vinay

executive
#58

However, that timeline ran through 2030. So clearly, it would be unrealistic to expect the whole arrangement to be finalized today, correct? Since there remain, as you know, both offtake and, and, and—

Sumit Kishore

analyst
#59

Alright.

Pritesh Vinay

executive
#60

All of that, correct? So a significant portion of it is going to sit in phase one, and we’ll make the appropriate disclosures once the boards at both companies have, you know, given that the green light.

Prashant Jain

executive
#61

Somewhere in the range of 25% to 33%, you can see that that's going to be... Yeah, so roughly 20 to 25% to 30% might fall within phase one. And, Sunil, we should also recognize that, you know, after December 2024, we've been building up the execution pipeline, which is extremely, extremely important for us. And that's exactly where we are — you'll see everything getting signed and closed over the coming 90 to 120 days.

Sumit Kishore

analyst
#62

Understood. And specifically when it comes to the hydro projects, is water flow proving to be a recurring problem at this point for 3 quarters? Should we be concerned about that? Or is the EBITDA — which is down 6% year-on-year for the quarter — simply a temporary factor?

Prashant Jain

executive
#63

It was a very difficult decision, but seasonality has always been a factor. We've observed it, and we're near reaching the design energy—just a little bit short. And then the interesting part, Sunil, is that these are two-part tariff projects; if a structural change in hydrology occurs, the design energy will be recalculated and revalidated, and we will recover our fixed cost. Also, all of these are old, depreciated projects, so there won't be any impact on the DISCOMs or anyone else.

Sumit Kishore

analyst
#64

Right. But I mean, no big shift in hydro levels is expected, is there?

Prashant Jain

executive
#65

Nothing—no structural change at all—but I'm just offering a hypothetical response to a hypothetical question. If it were to occur—a permanent structural change involving, well, lower generation—then Design Energy would be revised downward, and EBITDA would be preserved through an increase in the per-unit cost, and that is what the regulation provides for.

Sumit Kishore

analyst
#66

So your ROEs are going to stay as they are?

Prashant Jain

executive
#67

That's right.

Sumit Kishore

analyst
#68

One final question, if I may. In recent months, there haven't been many bids for firm dispatchable renewable energy power. Do you have any sense of which direction bidding activity is heading for renewable projects that include storage? And what sustainable tariffs are you seeing in those kinds of bids?

Prashant Jain

executive
#69

So there are a couple of things you need to look at. First, there's the inflationary pressure that's been building. Project costs have risen somewhere between 9%-13%, driven by higher commodity prices, construction expenses, and various other factors, and the cost of capital has climbed as well. As a result, you can see that wind tariffs are sustainable somewhere between INR 3.5 and INR 3.60-INR 3.70. Those are the figures that I, I feel are sustainable. And of course, solar prices depend on panel prices. So at today's price, I don't know how long they're going to hold. Current tariffs are okay at current panel prices, but I'm not sure what will happen with panel prices going forward. So if panel prices start rising, solar tariffs will have to rise too.

Sumit Kishore

analyst
#70

Alright.

Sharad Mahendra

executive
#71

And, just to add as well, on Sharad's side, in this FDRE, you basically need to look at the fact that it's firm dispatch, which is a combination of wind, solar, and storage. And whatever bids have come in, or are in the offering, when they've been examined, it's seen to be wind dominated, because of what the states require and the peak demand that exists. And also the right mix — some states, for instance, are asking for at least 90% delivery. So it's early to say, because at present, to get to 100% or 90%, the cost again, since it's wind dominated and storage dominated, becomes slightly higher-priced power. How far will it go? But this is evolving at the moment, and it says the states are modifying — some bids are minimum 80%, where the storage requirement comes down too, which optimizes the cost. So a right mix is being worked out. But yes, going forward, this is what we'll see — a mix of hybrid and FDRE, and that's what we're also preparing ourselves for.

Sumit Kishore

analyst
#72

Thanks a lot for taking my questions. Prashant, I wish you the very best in the times ahead. Thank you.

Prashant Jain

executive
#73

Thanks, Sunil.

Operator

operator
#74

Thanks. We’ll take the next question from Aniket Mittal at SBI Mutual Fund. Please go ahead.

Aniket Mittal

analyst
#75

Yes, sir, thanks for the chance to ask. I have just one question. You said the module manufacturing plant is being reconsidered because module prices have fallen. At what module prices would you say you'd begin taking another look, or at what point would the project become viable for you?

Prashant Jain

executive
#76

It's not something we're doing purely on a mathematical basis, Aniket, because we really have to look at the business environment and everything surrounding it. So we have been. We're seeing a lot of turbulence in the market right now, and suddenly a trend like this was completely unexpected for us. Panel prices went from $0.27-$0.30 back down to close to $0.10. So we're just trying to reassess where things stand. It isn't only panel prices that have led us to think this way — it's also the velocity at which this turbulence has occurred. We want to understand what the core reasons behind it are, and then we really need to examine it.

Aniket Mittal

analyst
#77

Alright, on the timeline side — because with the PLI scheme, I believe there are specific deadlines you'd need to commission this by in order to claim the PLI benefits. And if you were to not move forward with it, are there any penalties as well?

Prashant Jain

executive
#78

So, Aniket, you're correct. There's a deadline that, if I remember right, is March 25 for this project — that is, if one wants to take advantage of the PLI concession. What's interesting is that, you know, if you look at all the developers who bid for the various segments, whether WCM or CM, even other developers who took part in WCM — the orders they've placed are only for CM, and not for ingot, wafer, or cell, you know? So there's a very active consultation going on between the industry and MNRE. MNRE is aware of this, you know. In some cases, there are also restrictions coming in from equipment suppliers in China, you know. So I think the government is also aware of this and will take a holistic view. On the penalty — there is no penalty, but, you know, the performance bank guarantee, the worst case is that it gets encashed. You know, that's not a very significant amount, but I think it's too premature, you know, given that there is — this isn't something specific only to us as a company, but it's specific to the industry, and let's see how the outcome of these discussions goes.

Aniket Mittal

analyst
#79

All right, got it. Thanks. Here are the questions we have.

Operator

operator
#80

Thanks. Our next question comes from Ketan Jain at Avendus Spark. Your line is open.

Ketan Jain

analyst
#81

Good evening, sir. I just had one question. When do you expect the first PSP project to go online?

Prashant Jain

executive
#82

As we mentioned, we expect the first Group Captive agreement to be signed within the next 1 quarter, and at that time we will be announcing the commission schedule.

Ketan Jain

analyst
#83

So this is about the 300 MW project — is that correct?

Prashant Jain

executive
#84

130 megawatts, which works out to 1 gigawatt-hour.

Ketan Jain

analyst
#85

All right, thanks — thanks — thanks.

Operator

operator
#86

Thanks. Our next question comes from Dhananjay Bagrodia at ASK Investment. You have the floor.

Dhananjai Bagrodia

analyst
#87

Hi sir, I just wanted to get a handle on something. You mentioned that PVC prices have dropped, and module prices are coming down as well — so what's happening with projects on the bidding side? How has that been playing out among competitors, and what IRRs are they looking at now?

Prashant Jain

executive
#88

That's a really difficult question you're putting to me regarding competitors and what IRRs they're targeting. Still, I can definitely speak to JSW. Our approach has consistently been to pursue projects on the basis of equity IRRs, and we feel quite confident that we'll carry through on whichever bids we're currently submitting.

Dhananjai Bagrodia

analyst
#89

All right. But is everyone observing intensity going up at this point? Because at present, as module prices decline, additional players are going to want to re-enter this segment, since they perceive the same opportunity that we do. Is that what we're seeing, or is it still viewed as being among four or five of the bigger players in this segment?

Prashant Jain

executive
#90

Well, no, no — I'd say the competitive landscape is shifting, and at this point you're not really seeing as many participations. If you've been tracking the bids carefully, the aggressiveness is declining, and people are growing increasingly rational, and a few of those bids are even becoming undersubscribed.

Dhananjai Bagrodia

analyst
#91

Okay. Is that also because the IRRs are coming in below the mid-teens on those?

Prashant Jain

executive
#92

It's the reverse, actually. In my view, the people who'd carry out these projects simply don't have sufficient equity at their disposal, since if investors are earning a solid dollar-based IRR in the U.S. market, what reason would they have to place their capital where the equity IRR, measured in rupees, comes in lower? As a result, financing is drying up for renewable projects on both the debt and equity sides, given that the attractive scenario existed when global liquidity was enormous and interest rates sat at very low levels. And with dollar-market yields where they stand today, securing adequate debt along with equity doesn't make sense for most of the platforms.

Dhananjai Bagrodia

analyst
#93

Right, right, got it. All right, so that means bigger companies like ours will really gain from this, with less competition now, and, sorry, module prices coming down as well. So we might see growth move even quicker. Would that be fair to say, given that things slowed down when prices rose?

Prashant Jain

executive
#94

Yes, that captures the entire concept, and doing so is something we'd be glad to pursue.

Dhananjai Bagrodia

analyst
#95

That’s great. Thanks very much, sir.

Operator

operator
#96

Thanks. Our following question comes from Sudhanshu Bansal at JM Financial.

Sudhanshu Bansal

analyst
#97

Sir, so I have just two questions. First, during the previous quarter our average merchant rates were roughly INR 8 per MWh — so what is that figure this quarter? Second, regarding wind execution, how are you viewing it from an execution standpoint, specifically on land availability and grid connectivity? Thank you, sir.

Prashant Jain

executive
#98

All right. So the merchant tariff stood at INR 5 during the last quarter, and it did decline on a sequential basis — though the fuel price fell as well. That’s where things stand. And regarding wind execution, yes, we’ve run into a fair number of challenges, yet we remain on schedule to finish every project. We aren’t dealing with any connectivity problems, since most of the projects we’re handling are either for SECI, which is CTU connected, or, second, group captive projects, where we’re putting in our own dedicated transmission line. So the difficulties we face relate mainly to right of way, land, rains, and seasonality, because, as you know, with most wind projects you must build roads to transport the large blades. That movement happens only once, and each time you move a single blade there’s a right of way, and then again, two weeks or four weeks later, if you’re moving another item, you must secure the approval once more. Those are the sorts of things that constitute the main problems in wind. But we’ve developed the capability to handle matters of this kind, and that’s why, if you look at it, our execution ranks among the fastest.

Prashant Jain

executive
#99

And you can see that, I believe, in the SECI bids, we're the sole company that placed a bid for roughly 1,460-odd MW of capacity. SECI 9 and SECI 10 combined came to 1,260, and then another 300 was in SECI 12. So of that 1,260, which we're commissioning over the coming two quarters, I think in SECI 9 and 10 we'll be the only firm commissioning it. And as for most of the other bids, the competitors who took part besides us, perhaps another 100 or 200 MW will be commissioned by the close of this calendar year. That's what shows our ability to execute projects at the fastest pace and on schedule. So yes, it is quite challenging, but we're trying to build the capability to handle an even larger capacity each year by doing everything in-house.

Sudhanshu Bansal

analyst
#100

Yeah, that's right. I really do appreciate what you're able to execute — there's no question about that. So, on the equipment side, are you running into any challenges at all?

Prashant Jain

executive
#101

Beyond the inflation-related pressure, we aren't up against any other difficulty. So on the equipment front, we've been assessing constantly what better technology we can deploy and how to do it at a reduced cost, and that's exactly what we've been doing. So we keep bringing in new platforms and newer turbines. And that is the entire concept. Because at first we opted for the 2.7 MW platform, after that we chose 3.4 MW, and now we're looking at 3.6 MW. So in that manner, we keep securing the better platform, which delivers a lower life cycle cost for us. But apart from the inflationary pressure, we see no challenge.

Sudhanshu Bansal

analyst
#102

Thanks, sir, and all the best in whatever comes next.

Prashant Jain

executive
#103

I appreciate that.

Anuj Upadhyay

analyst
#104

Operator, could we have the final question now, please?

Operator

operator
#105

Alright, we’ll take one final question. The last question comes from Rohit at Antique. Go ahead, please.

Rohit Dokania

analyst
#106

Thanks. I appreciate the chance to ask this. My first question relates more to the capital side at JSW Steel. I think you mentioned the 6.2 gigawatt that's on the menu. Prashant, could you help us understand whether, if the steel capacity expansion is mostly tied to blast furnace, we would need that level of electricity consumption from green energy?

Prashant Jain

executive
#107

I think you should take into account that we're factoring in everything when we estimate the final requirement. Because in any case, with phase one, the whole concept is to use the off gases first and then swap out the coal. So that's phase one of decarbonization for any industry. So when you look at steel, they consume the gases internally, and after that, it goes toward power generation. And then for the balance power requirement, the option was either thermal or renewable. So the first phase was replacing coal and replacing the thermal power requirement. The second phase, at some point — which isn't included in this 6.5 GW of requirement — is using the gas for an alternate purpose, like making various value added products from the gases, off gases. And at that point, the power requirement rises further, and then their carbon footprint falls further. So, but that isn't included in this phase one requirement, which is 6.5 GW. And as Pritesh said, this 6.5 was also calculated for some time, like by 2030.

Prashant Jain

executive
#108

However, there will come a moment when decarbonization advances to the following stage.

Rohit Dokania

analyst
#109

Understood, sir, and thank you. That covers everything on my end. All the best to everyone.

Prashant Jain

executive
#110

We’ve got time for one more question, if there are two of you.

Operator

operator
#111

All right. Our following question comes from Sumit Kishore at Axis Capital. Kindly proceed.

Sumit Kishore

analyst
#112

Appreciate you taking the follow-up. Just quickly, I wanted to verify something on the SIGHT program, where JSW Neo Energy has also been chosen. I believe you cited 10,000 tons per annum. Once the incentive you've factored in is applied, what's your probable cost of producing green hydrogen? And if you could offer any further detail on the green hydrogen bidding, that would help.

Prashant Jain

executive
#113

Right. So a portion of that comes to 3,800, which we're already handling, and we've already walked you through the mechanism we're using under a cost-plus structure. As for the rest, we're still assessing it, but we feel fairly optimistic about the figures we mentioned early on. They'll improve as volume increases. That said, right now we aren't revealing the number, though they will become more competitive as scale grows.

Sumit Kishore

analyst
#114

So 3,800 of that 10,000 would be included?

Prashant Jain

executive
#115

You've got it.

Operator

operator
#116

So out of that 10,000, Sumit, the award notification covers 6,500 tons.

Sumit Kishore

analyst
#117

All right.

Prashant Jain

executive
#118

Yeah.

Sumit Kishore

analyst
#119

All right, understood. Thanks.

Operator

operator
#120

I really appreciate it.

Prashant Jain

executive
#121

Mohit, is there anything further, or not?

Mohit Kumar

analyst
#122

No, that's it. We're finished.

Prashant Jain

executive
#123

Oh, all right. That's great. Thanks a lot.

Operator

operator
#124

Thanks. That wraps up the questions. At this point, I'd like to turn the conference back over to Mr. Mohit Kumar for his closing remarks.

Mohit Kumar

analyst
#125

Yes. Thank you, Ray. On behalf of the investor and analyst community, we want to congratulate Prashant, sir, on a great innings, and wish him all the best in his future endeavors. Sir, would you like to make any closing comments?

Prashant Jain

executive
#126

Alright, thank you. Many thanks to Mohit, and thanks so much to each of you for the cooperation and trust you continue to show. I'd also like to wish all the best to Sharad, Ashok, and Pritesh, and to the rest of the management team for their... Perhaps, on behalf of JSW Energy and Sharad Mahendra, I could say just a few words about Prashant. I think the platform that has been established, and over the last few years we have been watching how JSW Energy has been growing, not just in quantity but with quality. I think, Prashant, the benchmarks that have been set and the team that is geared up to take things to the next level are there, and I assure all of you that whatever direction Prashant has set, the company will keep moving the right way, at the right speed, and with the right governance. And certainly, the results in the quarters ahead will make the outcomes visible. Thank you very much, and all the best to you, Prashant, from the entire JSW Energy team. It has been wonderful with you. Thank you.

Operator

operator
#127

Thanks.

Prashant Jain

executive
#128

Thanks, sir. Many thanks to all of you.

Mohit Kumar

analyst
#129

I appreciate that.

Operator

operator
#130

Thanks a lot. That wraps up the conference on behalf of ICICI Securities Limited. Ladies and gentlemen, we appreciate your participation. You can go ahead and disconnect your lines now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.