Good day, everyone, and welcome to the JSW Steel Limited Q3 FY20 Earnings Conference Call, hosted by SBICAP Securities Limited. Please be reminded that all participant lines will remain in listen-only mode, and following the conclusion of the presentation, you'll have a chance to ask questions. If you require any help during the conference, please signal an operator by pressing star, then zero on your touch-tone phone. Kindly note that this conference is being recorded. I'll now turn the conference over to Mr. Dayanand Mittal from SBICAP Securities. Thank you, and over to you, sir.

Dayanand Mittal

analyst
#2

Thanks, Moderator. And thanks to all of you for being with us today on JSW Steel's Q3 FY20 Post-results Conference Call. The full senior management team of JSW Steel is here with us. So, without any further delay, I'll hand things over to Mr. Pritesh Vinay, VP Corporate Finance and Group Investor Relations. Over to you, sir.

Pritesh Vinay

executive
#3

Thank you, Dayanand. Good evening to everyone joining us, and welcome to the earnings call covering JSW Steel's results for the third quarter of fiscal 2020. The senior management team of JSW Steel is with us today: Mr. Seshagiri Rao, Joint Managing Director and Group CFO; Mr. Vinod Nowal, Deputy Managing Director; Mr. Jayant Acharya, Director of Commercial, Marketing and Strategy; and Mr. Rajeev Pai, CFO. Mr. Rao will begin with a few minutes of opening remarks, after which we'll open the floor for Q&A. With that, I'll hand things over to Mr. Rao.

Seshagiri Rao

executive
#4

Good evening, everyone, and thanks for joining us for the quarterly performance briefing covering the third quarter of the 2019 to 2020 financial year. As you've observed, the September 2019 quarter's downturn carried over into October. Prices fell even further. Meanwhile, on a global basis, supply adjustments have produced improvements in pricing. That prompted restocking, which began taking place in India from November 2019. Everyone anticipated that resistance prices would head upward. As a result, the destocking seen in earlier quarters gave way to restocking in India. On top of that, the Government of India's renewed spending and the release of disbursements to various contractors restored demand across the construction and infrastructure segments. Consequently, November and December turned out to be much stronger months than September and October. In India, imports during the third quarter also dropped by 26%, while exports rose by 86%. That likewise aided destocking — not just at the channel level. Even at the producer level, inventories came down significantly during this quarter. Against that backdrop, looking at JSW Steel's performance, I'm very pleased to tell you that we crossed the 4 million mark once again, in both production volume and sales volume.

Seshagiri Rao

executive
#5

For the quarter, crude steel output came in at 4.02 million tons, up 5% from the prior quarter. Consolidated sales reached 4.032 million tons, marking 13% growth quarter on quarter. That volume performance in consolidated sales is mainly the result of a substantial gain in domestic sales, which rose 25% quarter on quarter and 11% year on year. Exports moderated somewhat, to 949,000 tons from 1,092,000 — 1.09 million tons — in the preceding quarter. That moderation in exports is roughly 50,000 to 60,000 tons. What matters in these quarterly results is that domestic sales climbed past 3 million tons during the quarter, a 25% increase. Retail sales powered this domestic improvement, growing 33%, while sales in the OEM segment grew 21%. In the Auto Sales segment as well, we lifted our sales volume by 10%. The share of our value-added products rose to 50% from 46% in the last quarter. We also took advantage of this buoyant demand to bring inventories down by 245,000 tons, to 10.78 million tons from 13.23 million tons.

Seshagiri Rao

executive
#6

Inventory has come down, domestic sales have improved, and retail sales have improved as well. That is the reason we performed quite strongly on volume during the last quarter. On prices, looking at blended NSR on a year-on-year basis, there was a 23% decline, and in the quarter the decline was 7%. The NSR reduction that kept occurring through the first half — the July, September, and August effect that landed in the full quarter — was followed by a further drop in NSR during October. Although November and December showed improvement, the total net decline in NSR on a blended basis came to 7% this quarter on a quarter-on-quarter basis. Cost of production declined 5% this quarter, largely on account of coking coal prices, with the average down $30 quarter on quarter. Captive iron ore supply of 1.22 million tons, along with other efficiencies, contributed to this 5% cost reduction. EBITDA per ton stands at INR 6,622 on a standalone basis, which is 16.9%. Operating EBITDA was INR 2,667, and profit after tax for the standalone company was INR 691.

Seshagiri Rao

executive
#7

On the domestic side, the subsidiaries performed well. JSW Coated, JSW Industrial Gases, and Amba River Coke collectively added INR 265. Overseas continued to weigh on results. Even in Q3, it posted roughly the same negative EBITDA, at INR 335. Taking the domestic and overseas subsidiaries together, consolidated operating EBITDA came to INR 2,451, while consolidated profit after tax stood at INR 187. I'd like to draw your attention to a one-off item: INR 250 of income the company booked this quarter from assigning a long-term industrial gases contract it had signed. When that contract was originally executed, assignment wasn't allowed. Later, owing to certain regulatory issues, they came to us asking that the contract be transferred, or that we accept the assignment, and for that they paid us consideration of INR 250. That's the one-off item. When I cite EBITDA per ton of INR 6,622 on a standalone basis, that figure includes this INR 250 received during the quarter. It works out to INR 621 per ton. Adjusting for that amount, the actual EBITDA for the quarter is INR 6,001.

Seshagiri Rao

executive
#8

Also, to properly understand the results, it's important to note that as of 30th of September 2019, we had 13.23 lakh tons of inventory. That's high-cost inventory which gets sold during the quarter. On a standalone basis, these inventory losses, if I look at it, come to INR 221. Including coated and overseas, on a consolidated basis, it's INR 300. That INR 221 standalone translates to INR 550 per ton. The INR 550 gets added, and INR 620 gets deducted. The net impact is just INR 70 against the INR 6,622 to be adjusted. Net debt for the company came in lower by INR 88 — it was INR 49,552, and stands at INR 49,642 as of 30th September. We were also able to bring down our weighted cost of interest by 30 basis points during the quarter. It stood at 6.52%. Acceptances on revenue account were INR 1,274 million, while acceptances on capital account were INR 543 million. Debt to EBITDA 3.71, debt to equity 1.35. The tinplate line we commissioned last year at our Tarapur unit has stabilized. Tinplate production volume grew 14%.

Seshagiri Rao

executive
#9

That's going to increase even more going forward. We also commissioned the PLTCM at Vasind within the downstream unit. A number of projects on the downstream side are in the process of being commissioned. Due to the monsoon — which we talked about on the previous call — that got stretched into October and also part of November, and that hit overall construction activity at Dolvi and partly at Vijayanagar as well. We did our best to make up for some of those delays. Given how the work is progressing on the ground, some delays are possible. Those delays will be in the range of three to six months. Rather than the Dolvi project being fully commissioned on 31 March, it will be fully commissioned by June — or perhaps one or two months either side of that. We're giving guidance of three to six months at the maximum, and before that the entire Dolvi project will be commissioned. We also finished the acquisition of Vardhan Industries Limited. We paid a total consideration of INR 63.5 crore. There are two things we achieved through this acquisition. First, our holding in JSW Vallabh Tinplate rose from 50% of the erstwhile holding to 73.5%. That's one thing we could achieve. The second is that they have a color coating line, with a capacity of around 40,000 to 50,000 tons per annum.

Seshagiri Rao

executive
#10

We can now provide our CR or hot rolled coils to this unit, convert them into color coating, sell in those markets, and capture the additional EBITDA on color coating. We've also started the fifth mine in Karnataka, Rama Mine. Plus the last Category C mine we've obtained will also be commissioned within the next few days. With that, all six Category C mines we got in Karnataka will be commissioned. The guidance of 4.5 million tons from captive sources, we will be able to accomplish this year. The guidance for the year that we've given — 16.5 million tons of production and 15.5 million tons of sales — we will be able to achieve, considering the progress and the outlook for Q4. The supply side adjustments and also the restocking we're seeing in the marketplace changed the sentiment of the National Infrastructure Pipeline, where they said they will spend INR 19.5 on infrastructure in 2021, as against INR 13.5 in 2019 to 2020. There's a significant increase in the outlays in the infrastructure segment. That is quite sizable.

Seshagiri Rao

executive
#11

There's INR 600,000,000,000 of additional spending the government would be putting into the infrastructure pipeline, and that works out to 43% growth. That's also a positive for the industry, and especially for steel. Steel demand across India rose roughly 3.5% during the first nine months. When we look at how Q4 is shaping up, our expectation is that demand for the full financial year will come in at 4%. Come next year, that 4% should climb further thanks to the factors I just listed, and we're expecting something around 5% for next year. On the overseas side, for Q4 we expect our European operations to turn EBITDA positive. As for the U.S. operations, we'll be able to cut our EBITDA losses substantially in Q4. At Monnet Ispat, the blast furnace is being restarted. Heating has already begun. That company will bring the blast furnace back up by the end of this month or in early February. With that, the stage one turnaround we had planned for Monnet will be finished during this quarter. That's where I'll stop, and if there are any questions or clarifications, we're happy to address them. Thank you.

Operator

operator
#12

Thanks a lot. We’ll move on now to the Q&A portion. If you’d like to ask a question, you can press star and one on your touchtone phone. Should you want to drop out of the question queue, press star and two. We ask participants to use handsets when asking questions. Ladies and gentlemen, we’ll pause briefly while the question queue is put together. Our first question comes from Amit Dixit at Edelweiss. Please go ahead.

Amit Dixit

analyst
#13

Thank you for the question, sir. There are two things I'd like to ask. First, regarding the decline in NSR: what we actually observed is that exports also fell, which should have worked in our favor. Even so, NSR declined rather significantly. Could you break it down by segment — how large a drop occurred in autos, and how large a drop occurred in retail specifically — so we can understand this decrease better?

Seshagiri Rao

executive
#14

See, the decline in NSR across July, August, and September—that was completely reflected in this quarter. In October, prices fell further in India, specifically steel prices. On top of that, Auto Sales contracts were repriced as of October 1st. As you're aware, pricing generally runs on a six-month cycle. From April through September, since steel prices were declining, auto steel pricing was cut for that six-month period. That effect comes to roughly INR 6,000 per ton. Together, these two factors brought NSR down by 7% on a blended basis. What matters here is that after global prices rose from $430 to nearly $500 at present, in November and December the company implemented price increases that the market absorbed. We've made one additional increase in January. So those increases from November and December were only partially captured last quarter. The full effect will show up this quarter.

Amit Dixit

analyst
#15

All right, great. The second question concerns iron ore costs. During January, we saw a sharp uptick in iron ore prices, both in Odisha and from NMDC. Now, given that iron ore bidding is real — I mean, and the — do you expect iron ore costs to rise further in the country? And if so, what cost increment might we see purely from iron ore and coking coal in Q4 versus Q3?

Seshagiri Rao

executive
#16

When it comes to coking coal, we anticipate that the benefit from present prices, on a blended basis in Q4, will be roughly $10 per ton. On the iron ore side, you're correct that prices rose during January. If anyone was watching, the prices of the private mining company in Odisha have been revised twice. Following this amendment for seamless transfer of statutory clearances, they rolled back a portion of those increases. Now, the auctions have been announced. They begin on 31st of January and conclude on 28th February. Once successful bidders are declared on 28th February, and then seamless transfer of mines plus a large amount of iron ore stocks that would be sitting in various mines, including sale, we don't expect prices to rise. We have already seen that type of trend, at least from private mining companies. That is what we expect will happen.

Amit Dixit

analyst
#17

So you're figuring the iron ore price will rise by the amount it's already risen—right now that's roughly INR 500 a ton, more or less. Is that the highest rate you could get?

Seshagiri Rao

executive
#18

It won't rise any further. It could be revised lower.

Amit Dixit

analyst
#19

Alright, thank you very much, sir. Best wishes to you.

Operator

operator
#20

Thanks. Our following question comes from Anuj Singla at Bank of America. Go right ahead.

Anuj Singla

analyst
#21

Thank you very much for the chance to ask. Mr. Rao, my first question concerns the international operations. These operations have been losing money heavily for roughly the last five quarters. Looking just at Acero Junction, the cumulative EBITDA loss at this operation alone has been INR 130 million over the last five quarters. That is a major drag on the company's cash flows as well, while we are embarking on our growth plans in India. On this count, what kind of comfort can we draw for FY 2021 or 2022? Where do we see this number going? What is the game plan there in terms of turning those operations around?

Seshagiri Rao

executive
#22

Yes. No, look, you're referring to the three operations we have: Ohio, Plate and Pipe Mill, and also in Europe. On Europe, I already provided guidance that during this quarter, we turn EBITDA positive there. The European operations will turn around next year. If I look at Plate and Pipe Mill, phase one there is done. Their losses of roughly $13 million, which are declared this quarter, will drop drastically as far as Plate and Pipe Mill goes. It may not be positive this quarter, but it will drop drastically in the US Plate and Pipe Mill. Next year, it will be positive. As far as Ohio goes, we have plans to ramp up production because prices in the US have fallen quite significantly. That had an impact on the Ohio operation and on our turnaround plan. What we intend to do is ramp up quickly and then make this unit EBITDA positive. That will be achieved next year, next financial year. This quarter as well, it remains EBITDA negative, but at a lower level than the $25 million EBITDA loss we reported in Q3.

Anuj Singla

analyst
#23

All right, all right. So basically, you aren't building in any sort of pricing recovery. In the U.S., the turnaround rests mainly on operations ramping up over the next year. Would that be a fair way to put it, sir?

Seshagiri Rao

executive
#24

Prices are coming back up, and that should also support the move to positive EBITDA. That's the first point. Second, on the plate mill side, phase one is finished. We'll start seeing the upside from that now. Phase two should also be done by the close of the next financial year. Those two phases combined are going to be what really transforms the Plate and Pipe Mill in the U.S. As for Ohio, our plan there includes putting some capital into modernizing the Electric Arc Furnace. That EAF modernization is going to take 10 to 11 months. By doing that work alongside the equipment already in place, we're working to stabilize operations, ramp up capacity, and capture the benefit of a better U.S. market and better pricing, which is how we'll cut the losses and get to positive EBITDA next year. I believe the year after that, we'll be able to generate a profit in Ohio.

Anuj Singla

analyst
#25

Alright, got it. Sir, could you share the CAPEX figures for the nine months we've completed, and how much CAPEX is left for the fourth quarter? Is there any update on next year's CAPEX number?

Seshagiri Rao

executive
#26

On a cash flow basis, capital expenditure for the quarter came to INR 2,812 crore. Cumulatively, across the nine-month period, that figure stands at INR 7,767 crore. Our revised guidance is INR 11,000 crore. We'll spend the remaining amount and finish this INR 11,000 crore CAPEX program for the year. As for overall CAPEX next year, we'll return to you with that in the month of May.

Anuj Singla

analyst
#27

All right. Sir, finally, you mentioned that steel prices are rising quarter over quarter. Could you provide any sort of figures on that? On an average basis, what sort of recovery ought we to anticipate?

Jayant Acharya

executive
#28

Looking at the bottom side, if you've seen October, prices had dropped to levels of $430. That is now at a level of $500. From the bottom, $70 international quote. We have shifted part of this between December and January. We are watching the market, and we are hopeful that some increases would take place in the coming months. We should be able to do better going forward with this last quarter.

Anuj Singla

analyst
#29

Got it, and thanks a lot, sir. Many thanks.

Operator

operator
#30

Thanks. Before we move to the next question, we want to let participants know that so management can take questions from everyone in the conference, please keep your questions to 2 per participant. If you have follow-up questions, we ask that you rejoin the queue. The next question comes from Ritesh Shah of Investec Capital. Please go ahead.

Ritesh Shah

analyst
#31

Hello, sir. Thank you for the chance to speak. Sir, my first question is this: are there any particular details you'd be willing to share regarding Bhushan Power, and how should we view that asset going forward?

Seshagiri Rao

executive
#32

Regarding Bhushan Power and Steel, as we mentioned during the previous call, we are seeking immunity before moving forward. An amendment has been made. As for how that amendment applies to the resolution applicant—namely JSW Steel—the NCLAT requested information, or confirmation, from the investigating agencies. Affidavits have been filed by them, and once again those are not particularly clear. On that basis, there were some arguments in court yesterday. It has now been settled that the hearing will take place next on 30th January. Hopefully, it will be resolved quite soon—if not on 30th, then during February.

Ritesh Shah

analyst
#33

All right, sir, I just want to ask about this. There was an amendment that had already been made, right? What exactly is the court examining here? Is it whether that amendment can apply retrospectively or not? And sir, if that's what it comes down to, where do we stand on that?

Seshagiri Rao

executive
#34

When you look at the ordinance that's been passed, it introduces Section 32 into the IBC, and what that section says is that immunity will be available to the resolution — to the corporate debtor — provided the resolution applicant isn't a promoter, isn't promoter-related, and isn't a related party. Control has to change hands away from the promoter. That's essentially the gist of it. So, previously, JSW Steel asked the investigating agencies to confirm whether Section 32 applies to JSW. There's no dispute on that point. They submitted an affidavit stating that there was a joint venture between JSW Steel and Bhushan Power and Steel — namely Rohne Coal Company Private Limited. In that company, Bhushan Power is an associate of JSW Steel. So Section 32 provides that control must not shift to an associate. JSW Steel is an associate company of Bhushan Power and Steel. As a result, Section 32 doesn't apply. That's argument one. Their second argument concerned the retrospective versus prospective effect of the ordinance. This ordinance applies to resolution plans approved or passed by the NCLT. The resolution plan submitted by JSW Steel was passed on 6th of September.

Seshagiri Rao

executive
#35

The ordinance came afterward. It doesn't apply to the resolution plan that NCLT has already approved. Essentially, two arguments were put forward. In our understanding, it covers every resolution plan, since there's no carve-out saying it doesn't apply to plans approved earlier. That's the first one. Second, when we submitted our resolution plan, we disclosed our relationship through a joint venture with Bhushan Power and Steel in our declarations so we could qualify under Section 29A. Under Section 29A, if we're a related party to the promoter, we'd be disqualified. The resolution professional, working with independent consultants, examined this and then qualified JSW Steel as an eligible bidder under Section 29A. If you look at 29A and 32, which the ordinance now introduces, the two are similar in nature. From our standpoint, JSW Steel, under the definition, is not an associate of Bhushan Power and Steel. And Bhushan Power and Steel is not an associate of JSW Steel either — not under accounting standards, not under the Companies Act, nor in any other way it could be interpreted.

Seshagiri Rao

executive
#36

So the courts will have to weigh in on this regardless. Given that, I expect there will be arguments presented in court. Ultimately, the courts will make the decision.

Ritesh Shah

analyst
#37

That's interesting, thanks a lot, sir. Sir, for my second question, regarding the balance sheet, how should we view the effect of that Duferco trade finance deal we did at the beginning of the year? Both alongside the net debt figure and alongside the acceptances figure that we report?

Seshagiri Rao

executive
#38

The net debt figure takes into account the advance we received from Duferco. That advance is already counted within the debt we're presenting. On the balance sheet, when we present it, it might not appear under borrowings — it will show up as an advance from customers. To make things clear, it's a long-term advance, and we've included it as part of net debt when we give those numbers to all of you. The ratios, as well, were worked out treating the Duferco advance as debt.

Ritesh Shah

analyst
#39

What would that figure come to?

Seshagiri Rao

executive
#40

When we took it on, Quantum stood at $700 million. That figure gets revised monthly, since we've been exporting ever since April 2019. From that point on, it has been adjusted. It will be paid in full across five years.

Ritesh Shah

analyst
#41

Alright. Thanks. I’ve got additional questions. I’ll reconnect with you later. Thanks a lot.

Operator

operator
#42

Thanks. Our following question comes from Sumangal Nevatia of Kotak Securities. The line is yours — please proceed.

Sumangal Nevatia

analyst
#43

Hi, yes. Good evening, sir. Sir, regarding steel spreads, if you could give some guidance — taking into account the price increases, the reduction in coking coal costs, and the rise in iron ore costs — I mean, how do you expect spreads to move in 4Q compared with 3Q?

Seshagiri Rao

executive
#44

We’ll provide guidance on spreads. As I told you, a $10 reduction will apply, given where coking coal’s index stands now. That is a $10 cut across overall prices in this quarter. On the iron ore side, a reduction occurred during December. Then January brought an increase. We don’t anticipate additional rises in iron ore prices. At the same time, our new captive iron ore mine has begun operating. Additional output will come from captive sources. We don’t expect iron ore prices to climb further beyond what has already occurred. Even the January increase won’t affect the entire quarter. We’ll keep purchasing through auctions. We hold roughly one and a half months of iron ore coverage. So even if that impact lands within the quarter, it won’t span the full quarter. Regarding the prices I just referenced, November and December saw an increase. That effect will apply across the whole quarter. In January, we raised prices again. Now, when I compare the landed cost of imports against these domestic prices, domestic prices sit at a discount.

Seshagiri Rao

executive
#45

In my view, it's close to 5 to 6%. So, considering the buoyancy in overall demand, there's room for a price revision in the domestic market in February and March.

Sumangal Nevatia

analyst
#46

For Q3, the average price compared with spot prices is going to come in no less than INR 3,000-INR 3,500 above. Would you say that's a fair way to frame it?

Seshagiri Rao

executive
#47

Prices are certainly going to be higher, though we don't want to specify the exact quantum. Those prices come in above the average.

Sumangal Nevatia

analyst
#48

Got it. Sir, my second question is about the iron ore mines. Starting from 4.5 next year, what might captive iron ore production be? What's the peak? Is it roughly 8 to 9 million tons?

Seshagiri Rao

executive
#49

That figure stands at 4.5 million. There are another three mines located in Bellary, and those will also be brought into operation during the next financial year. Should all nine mines run at full capacity, the iron ore available would be close to 7 million tons. We're also examining the possibility of expanding capacity at the six mines that were made operational this year. We'll be in a position to provide an accurate figure, but at a minimum it will exceed 4.5 — somewhere between 4.5 and 7 million tons. That's the range we expect next year.

Sumangal Nevatia

analyst
#50

Alright, just one final point of clarification regarding Bhushan Power. We're still holding to the position that we'll take it over with 50% ownership and bring in a JV partner. That's unchanged, correct?

Seshagiri Rao

executive
#51

At no point did we mention 50% or 40%. Our actual statement was that consolidation is not going to take place within JSW Steel's books. Should it happen at all, the transaction must be finished on the basis of a favorable judgment, with our resolution plan approved — then we will finish the transaction. Let us repeat once more: there will not be consolidation of BPSL into JSW Steel's books until the turnaround occurs.

Sumangal Nevatia

analyst
#52

Got it. Sounds good. Thanks very much, and best of luck to you.

Seshagiri Rao

executive
#53

Thanks.

Operator

operator
#54

Thanks. Our following question comes from Indrajit Agarwal at Goldman Sachs. You have the floor.

Indrajit Agarwal

analyst
#55

Good evening, sir, and thanks for taking the question. I have two things to ask. First, regarding the supply-demand balance in India next year, you mentioned demand growth of roughly 5% on an annual demand base of 100 million tons. That works out to about 5 million tons of extra demand. Given that, you have 5 million tons of capacity coming on stream. There is also additional sales volume from Steel Authority. Essar has changed hands now, so utilization there will likely rise. And JSPL too. So how do you expect overall industry utilization to trend next year? Will that affect how attractive the domestic market is?

Jayant Acharya

executive
#56

Looking ahead to next year, considering the overall demand picture, our expectation is that conditions will improve relative to this year. We should finish this year at 4%. For next year, the range ought to land between 5 to 6%. Taking even a midpoint figure, incremental demand in India works out to between 5 and 6 million tons. Turning to flat steel capacity additions, some of those may come online during this year, and that includes our Dolvi project. Let me give a bit of detail on Dolvi: of the 4.5 to 5 million tons involved in this project, measured as hot rolled coil, roughly 50% is tied backward into our downstream operations. That portion gets absorbed in-house. The remaining volume becomes incrementally available to the market. As you know, we are likewise holding talks regarding purchases of certain downstream assets, such as Asian Colour, which would further assist in consuming a portion of this within downstream operations. On the incremental effect, since demand growth is arriving, this capacity should not prove difficult across the year, because in any case it will be starting — as we have said — with a delay of three to six months for part of the year.

Jayant Acharya

executive
#57

So that's the situation with Dolvi. The other rival mill that could show up in the market might be Steel Authority of India Limited or NMDC, though that supply will probably only be partly available again during the next year. Taken together, I believe the capacity ought to be sufficient to satisfy domestic demand, given that monthly imports of roughly 200,000 have by now dropped considerably. For next year, I don't really foresee an issue when it comes to consumption at this unit.

Indrajit Agarwal

analyst
#58

Thanks. Regarding that earlier question about the drop in auto sheet prices, has the full effect of that shown up this quarter? Or might some of it carry over into the March quarter and the June quarter too?

Jayant Acharya

executive
#59

No. Auto pricing works this way: whatever decline happened in the prior half is essentially baked into the pricing for the following half. The drops from the first half are already reflected in H2 pricing for this year. As we mentioned, in the second half of this year, from October onward, things have bottomed out. Prices are getting better. So the effect of higher prices in H2 will show up in auto contracts next year, beginning in April.

Indrajit Agarwal

analyst
#60

Sure, thanks — that helps. If I can squeeze in one final thing, did you say something about a timeline for Bhushan Power? I just missed it. I mean, do you expect it to get resolved, one way or another, by February? Is that what you said?

Seshagiri Rao

executive
#61

No. It hinges on when the clearance comes through. Given how NCLAT responded yesterday, they seemed to want the hearings wrapped up as soon as they could. If the ruling comes down the way we filed the resolution plan — approving it — then we'll finish inside 30 days from that date. That might land in this quarter. It could also push into the next quarter. We'll have to wait and see when the approval happens.

Indrajit Agarwal

analyst
#62

Alright. Thank you. I have nothing further to add. Thanks, Anuj Singla.

Operator

operator
#63

Thanks. Our following question comes from Pinakin Parekh at JPMorgan. You have the floor.

Pinakin Parekh

analyst
#64

Thanks a lot, sir. First question from my side: when I look at export volumes for the company over the past two quarters, they came in at roughly 1 million tons per quarter on average. Going back to Q3 of FY2019, that figure stood at 0.3 million tons. Now, at this point, at the end of January, as you're putting together business plans for the March and June quarters, do you expect that 1 million tons per quarter export volume to be sustained by the company? Or is your view that it should fall off across this quarter and the next one?

Jayant Acharya

executive
#65

Export is, as you know, a figure that balances things out by nature. We keep our exports at a particular level so that we remain present in the market. In quarter four, with the market situation as it currently stands, we do expect exports to moderate somewhat. That said, since international prices have risen, we will form a view against the price available this quarter in the domestic market and in the international market, and then adjust our tonnages for exports in this quarter accordingly. As for next year, I think we are in the process of putting our business plans together. Closer to the time, I think we will be able to give you a clearer picture on that.

Pinakin Parekh

analyst
#66

Sure. Thank you, sir. My next question concerns Dolvi. We're discussing a delay of three to six months, and if it is commissioned somewhere between June and September, then from that point I assume there would be a stretch of ramping up the blast furnace and stabilizing the plants. On that basis, would a material amount of commercial steel sales volumes be available from Dolvi in FY21?

Seshagiri Rao

executive
#67

Absolutely. Relative to what we already run, that will be substantial. All told it comes to 5 million tons, even if you assume only six months of availability. During those first six months, we’ll be using it for commissioning as well as for ramping up. In our view, there is a six-month period that will certainly be available.

Pinakin Parekh

analyst
#68

So from where you sit, during that window, availability ought to sit at a high level of utilization relative to nameplate capacity?

Seshagiri Rao

executive
#69

Correct.

Pinakin Parekh

analyst
#70

Got it, and thanks a lot, sir.

Operator

operator
#71

Thanks. Our next question comes from Bhavin Chheda at Enam Holdings. Go ahead, please.

Bhavin Chheda

analyst
#72

Good evening, sir. Could you give us the rough EBITDA figures for Amba River Coke and BPSL — both for the quarter and for the nine months?

Seshagiri Rao

executive
#73

For the quarter, it came in at INR 134 crore. From industrial gases, INR 13.7 crore. And INR 115 crore.

Bhavin Chheda

analyst
#74

Airfield, 115. And Salav?

Seshagiri Rao

executive
#75

Salav wasn't running during the previous quarter. On top of that, the merger was applied retroactively.

Bhavin Chheda

analyst
#76

My apologies — it got combined into what, exactly, in each case?

Seshagiri Rao

executive
#77

Retroactively, it was folded into JSW Steel.

Bhavin Chheda

analyst
#78

Alright, so Salav numbers aren't going to be presented as a standalone subsidiary or anything like that. What we need to do is simply consider this industrial gases piece and the Amba River, on top of the other overseas subsidiary and the coated and plate mill — what is it?

Seshagiri Rao

executive
#79

That's right.

Bhavin Chheda

analyst
#80

Okay, so what was JSW Steel's inventory, measured in tonnage, as of December 31?

Seshagiri Rao

executive
#81

The figure is 10.78.

Bhavin Chheda

analyst
#82

Lakhs?

Seshagiri Rao

executive
#83

Yes, 10.78 lakhs.

Bhavin Chheda

analyst
#84

About 1 million tons, is that right?

Seshagiri Rao

executive
#85

Yes.

Bhavin Chheda

analyst
#86

Alright, on the overseas figure — you mentioned Europe wouldn’t have losses, but the losses are in the U.S. Even for plate and pipe mill, since U.S. is again split into plate and pipe mill operations separately, and Ohio operations are separate. Will both still keep posting losses, or will plate and pipe mill still break even in Q4?

Seshagiri Rao

executive
#87

Losses at the plate and pipe mill are going to decline quite substantially from the $12.6 million figure that was reported in Q3. That drop will be quite substantial. The plate mill won't be a bit positive in this quarter, Q4. In the same way, in Ohio, it will be lower than in Q3.

Bhavin Chheda

analyst
#88

Alright, my final question is this: our other operating income has been declining year over year, both in the quarter and across the first nine months, and that's mostly VAT credit and Dolvi and so on. Have there been some rate adjustments? My understanding was that under the new GST regime, the rate came in higher than the earlier regime. So why is it, when volumes are similar or even higher, that our other operating number is going down?

Seshagiri Rao

executive
#89

The incentive that applied at Dolvi, which covered as much as 3.3 million tons, came to an end in August 2019. So that is no longer available.

Bhavin Chheda

analyst
#90

Across the whole 3.3 million?

Seshagiri Rao

executive
#91

Right. That’s expired — that period is over. Any incentive we receive now will apply only to incremental production above 3.3 million.

Bhavin Chheda

analyst
#92

All right, regarding Dolvi — what we're stating is that at Dolvi, which runs at a rate of 4.5 to 5 million, on 3.3, we aren't receiving incentives at this point?

Seshagiri Rao

executive
#93

Got it.

Bhavin Chheda

analyst
#94

That figure of INR 318 crore — that relates to Karnataka, right, at 2 million tons, and then 1 to 1.5 million tons from Dolvi?

Seshagiri Rao

executive
#95

That's right.

Bhavin Chheda

analyst
#96

Alright. Alright, thank you very much, sir.

Operator

operator
#97

Thank you. Our next question comes from Kumar Prashant with CGS-CIMB. Please go ahead.

Kumar Prashant

unknown
#98

Sir, congratulations on a strong result in one of the toughest quarters since 2016. Sir, my question is about the trade side. India and the U.S. recently agreed to settle amicably a trade dispute in which the WTO ruled against the U.S. I'd like to hear your view on that. Could this be viewed as a precursor to some mini trade deal we might expect in February, when Mr. Trump visits India to meet the Honorable Prime Minister?

Seshagiri Rao

executive
#99

Could you clarify which one you mean by trade deal? Do you mean the China-US trade deal, or is it something different?

Kumar Prashant

unknown
#100

No, sir. Regarding India and the U.S., a trade dispute arose over hot rolled coil products. In that dispute, the WTO issued a ruling against the U.S., and India has been pursuing enforcement of it since 2016. I believe word has recently reached us that India and the U.S. have reached an amicable settlement. Have you heard about this? What's your view, sir?

Seshagiri Rao

executive
#101

India brought this anti-dumping matter to the WTO some time ago — not recently. That was, yeah, that happened a few years back. The ruling went our way, in India's favor. It was never put into effect in the U.S. as far as any correction to the anti-dumping duties goes. We haven't heard about any recent change that accepts it or grants relief on that duty. We don't anticipate anything major coming out of Mr. Trump's trip to India, especially regarding this issue.

Kumar Prashant

unknown
#102

Yes, sir. Okay. On the demand side, one more point about India-level demand. Sir, if that INR 6.5 lakh crore of incremental infrastructure really does happen next year, and if we assume a steel intensity of, say, 8% or 10%, then one could figure there is probably INR 50,000 crore of additional steel to be consumed. That alone works out to roughly 8 million ton. Assuming other sectors grow as well, other segments. Are we in for a huge demand surprise next year, sir? What is your view?

Jayant Acharya

executive
#103

When you take a hard look at the different projects as they emerge or get announced, the steel consumption in this country is going to be very substantial. That's assuming all these projects get funded on schedule and actually begin on the ground within the next few months. From that angle, we do see an upside. A big share of that will be rebars. In the last year — or rather, the year that's passing — we expect roughly 27 to 28 million tons of rebar to be consumed. I think there will be an upside as new projects come in — the micro projects, the bullet train now getting underway, I mean, the tender is due on 31st, smart cities, hospitals, various new projects are on the ground. We do see an upside to that figure. Whether it's a huge surprise or not, I think funding and timing will tell us. On the flat side as well, we see some investment in oil and gas. They're trying to build the gas grid and the water grid. We see effective demand of probably close to 3 to 3.5 million tons over the coming two years.

Jayant Acharya

executive
#104

That will also take effect. Yes, we're seeing substantially higher demand coming from the infrastructure side, assuming implementation on the ground occurs on schedule.

Kumar Prashant

unknown
#105

Yes, sir. Sorry — if I could, just one final question. Sir, regarding the Acero junction asset, Mr. Rao has already mentioned that next year we might not see particularly strong numbers here. Sir, but when it comes to a long-term normalized EBITDA per ton, would $100 per ton be a reasonable figure to build in on a long-term basis, assuming the steel market sits at normalized profitability and conditions in the U.S.?

Seshagiri Rao

executive
#106

You know, we don’t really like to give EBITDA guidance, since it hinges on two or three factors. Especially in steel, it’s very hard to picture what the steel price will be one year ahead or one and a half years ahead, and the same goes for costs. Because all we can really look at is volumes. What we’re trying to do in Ohio is turn things around and get volumes up, and then it automatically becomes profitable.

Kumar Prashant

unknown
#107

Excellent, sir. I really appreciate it.

Operator

operator
#108

Thanks. We’ll take the next question from Rajesh Lachhani at HSBC. Your line is open — please go ahead.

Rajesh Lachhani

analyst
#109

Yeah, thanks for the chance to ask. Sir, my question relates to net debt. We've brought our net debt down a bit. But when I do the math, we had INR 2,400 crore of EBITDA, yet CapEx came in at INR 2,800 crore and interest was close to INR 1,000 crore. I just want to understand, what was the working capital release this quarter?

Seshagiri Rao

executive
#110

Right, and actually you're already aware of that figure. From what I gather, the inventory we held at 13.23 lakh tons has dropped to 10.78. So working capital that was tied up in inventory is now flowing back into the system.

Rajesh Lachhani

analyst
#111

Got it. So all of the decrease in net debt comes from the shift in working capital, for the most part?

Seshagiri Rao

executive
#112

This isn't about paying down debt. What you're seeing is the total funding need, compared with no growth in borrowings, or only a very slight cut in the increase, and that comes from inventory unwinding.

Rajesh Lachhani

analyst
#113

Alright. Alright, I also wanted to get a handle on this. India's crude steel output has fallen in fiscal year 2020—the nine months of fiscal year 2020. During this year we likewise turned into a net exporter of steel. I just want to grasp how consumption is still arriving at 3.5% above the prior year? Could you shed some light on that?

Seshagiri Rao

executive
#114

For the nine months, crude steel consumption used in production is 0.1%. That matches last year's figure. Regarding the import situation across the nine-month stretch, the drop isn't all that large, even though we are the net exporter. We are the net exporter. If you factor in the inventory reduction — because a huge amount of inventory was sitting there as of 1st of April 2019 — there is a decrease in inventory. There is a decrease in imports. There are more exports. Production is staying more or less at the same level. The consumption number is a derivative.

Rajesh Lachhani

analyst
#115

Got it, thank you very much, sir. That's all from me.

Operator

operator
#116

Thanks a lot. We’ve got time for one final question. Our last question comes from Sagar Gandhi at Future Generali Life Insurance. Go ahead, please.

Sagar Gandhi

analyst
#117

Sir, you mentioned that Monnet Ispat, the company you recently acquired, will likely begin operating a plant around late January or early February. What capacity will that facility have, and how do you expect that to develop over the coming 12 months?

Seshagiri Rao

executive
#118

Capacity sits at roughly 1 million tons. Within that, a pellet plant with 2.4 million tons of capacity runs at nearly its full rate. In the same way, our DRI plant is running at its maximum of 50,000 tons per month. What we're bringing online now is a blast furnace plus one melt shop — actually two melt shops. One of those is being commissioned. A TMT mill of 500,000 tons is also being commissioned. Once this first phase — what we call phase one — is commissioned, capacity will land somewhere between 700,000 and 800,000 tons. When phase two is commissioned — that's a plate mill and the second part of SMS, the second SMS — if we commission it, then 1 million to 1.2 million tons will be reached. What we're having completed right now is that first phase.

Sagar Gandhi

analyst
#119

All right, so how soon do you think phase two will get underway? And will that call for extra financial commitments or CapEx?

Seshagiri Rao

executive
#120

The capital expenditure involved isn't especially large. To get phase two commissioned, somewhere around INR 110 crore or INR 120 crore has to be spent. Our plan is this: with phase one, we'd like to get started, then ramp up the capacity, and after that take up phase two.

Sagar Gandhi

analyst
#121

Is it fair to expect all of this to be done in the next 1 to 1.5 years?

Seshagiri Rao

executive
#122

Yes.

Sagar Gandhi

analyst
#123

Thanks a lot, sir.

Operator

operator
#124

Thanks. There’s time for one more question, and the final one comes from Vivek Ramakrishnan at DSP Mutual Fund. Go ahead, please.

Vivek Ramakrishnan

analyst
#125

Thank you, sir, for that final question. It does look like an excellent quarter, with strong cash flow from operations. Sir, I simply wanted to ask: what are the main debt repayments coming up in the remaining two months of this year, and in FY2021, sir?

Seshagiri Rao

executive
#126

Altogether that comes to 3,000 crores in Q4, January included. For the following year, the figure will be INR 7,000 crores.

Vivek Ramakrishnan

analyst
#127

All right, thank you very much.

Operator

operator
#128

Thanks a lot. We’ll treat that as the final question. At this point, I’d like to return the conference to the management team so they can offer closing remarks.

Seshagiri Rao

executive
#129

Thanks a lot. We anticipate that Q4 will be significantly stronger than Q3 when it comes to volumes and NSR, along with reduced cost pressures in Q4. We're also putting effort into cutting down the delays that have occurred in commissioning projects. Our aim is to begin commissioning in March over a six-month period, both commissioning and ramping up. That should do it. As a result, I believe next year we'll have incremental capacity of 5 million ton available to us fully for nearly six months. We're also commissioning our downstream. That too will be finished within the next few months. With that, I think in FY21, we'll be in a position to provide a clear picture regarding total production and sales volumes when we meet in May. Thank you. Thanks very much.

Indrajit Agarwal

analyst
#130

Much appreciated. This brings our conference to a close on behalf of SBICap Securities Limited. Ladies and gentlemen, we thank you for being with us. Your lines can be disconnected at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete JSW Steel Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to JSW Steel Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Steel Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.