operatorKindly be aware that this call is being recorded. At this point I'll pass things to Mr. Ashwin Bajaj, Group Head of Investor Relations. Thanks, and the floor is yours, sir.
Ashwin Bajaj
executiveThank you, Sagar, and good evening, everyone. It's a pleasure to have you join us for JSW Steel's earnings call covering Q4 and financial year 2024. Today we're joined by the management team: Mr. Jayant Acharya, Joint MD and CEO; Mr. G.S. Rathore, Chief Operating Officer; Mr. Rajeev Pai, CFO; and Mr. Swayam Saurabh, CFO Designate, who, as we announced today, takes over as CFO from June 1. Mr. Acharya will begin with opening remarks, after which we'll open the floor to questions. So with that, over to you, Mr. Acharya.
Jayant Acharya
executiveThank you. Good evening, everyone. On the macro side, just a brief perspective regarding the global macro picture. 2024 is expected to be somewhat better. The IMF figure was revised up to 3.2 from 3.1, helped by improved PMI and mild expansion, which we saw in quarter one, and that has been positive. Disinflation is being observed across regions, though probably at a slower pace than was previously expected. So rate cuts could be delayed in some of the countries. The U.S. would probably look at it with a gap, but we may expect fewer rate cuts than what we had initially anticipated. Europe would proceed with the rate cuts since their inflation is dropping faster. In China, the property sector continues to be a drag but has been offset by strong growth in manufacturing and investments, which enabled a strong quarter three, 5.3% growth in quarter one. We expect targeted stimulus by the Chinese government to continue during the remainder of the year. In India, the growth momentum continues with positive trends across key sectors and a resilient macroeconomic profile. The IMF has upgraded India's FY 2025 GDP growth to 6.8% and its medium-term growth projections till FY 2030 to 6.5%.
Jayant Acharya
executiveWe anticipate activity levels will rise further once the current general elections conclude. Strong trends persist across major sectors including real estate, manufacturing, automotive, and the energy transition. Taking steel specifically, worldwide crude steel output for January through March increased 0.5% to 469 million tons. China's figure declined 1.9% YoY within that total, whereas the remainder of the world recorded 3.6% growth. Crude steel production in India rose 9.7% YoY to 37.3 million, with consumption up 9% at 35.7 million tons. For the year, steel demand overall expanded 13.6%, and we anticipate that robust growth in steel demand will persist, supported by healthy government CapEx along with solid demand from manufacturing, real estate, automotive, and overall consumption. Private CapEx should likewise improve, as utilization rises on the back of healthy balance sheets. India's steel imports reached 2.61 million, up 30% YoY in quarter four, and totaled 9.65 million tons for the full year, a rise of 37%. Growing steel imports stay a key risk to the domestic steel industry, particularly from China and the ASEAN. Sustainability. At JSW Steel, we are mainstreaming sustainability throughout the businesses, and generating sustainable value has ranked among our strategic priorities.
Jayant Acharya
executiveOur goal is to reach net zero emissions by 2050. For the sixth time in a row, JSW Steel has been named a steel sustainability champion by the World Steel Association, and we are the only steel company globally to have secured the CDP A rating for water security. Under the CDP Climate Change, we have retained leadership rating for the fourth consecutive year. Moving toward renewable energy is a major thrust for us, and we are pleased to announce further 600 MW of renewable capacity, including 200 MW of wind and 200 MW of solar. For the first time, we are also adding battery storage of 320 MWh with this capacity at Vijayanagar. This new capacity, along with the earlier announced renewable capacity, will ensure that 26% of Vijayanagar's power requirement at 18 million capacity will be met through renewables. If you look at the strategy direction, which we have been giving you earlier, towards 50 million ton, and we have updated a slide on slide number 18, I would like to draw your attention to that. JSW has been an industry leader for the last 10 years with respect to growth, and we have grown our capacities, production, EBITDA, and benefited from higher economies of scale.
Jayant Acharya
executiveWe've likewise expanded our capabilities and capacity in value-added products. As the slide shows, across the years our volume has risen, our share of value-added products has risen, and our EBITDA has risen too, all while keeping EBITDA within a sensible band. Scale benefits and margin expansion are now materializing, and that should let us produce larger cash flows and finance growth mostly from internal accruals. Five elements—or pillars, as you might put it—will drive this transformation. Those are growth, product enrichment, cost optimization, raw material security, and the decarbonization pathway, through which we have previously aimed to achieve net zero emission by 2050. We are likewise keeping a strong emphasis on innovation, R&D, and digitalization. The goal is to keep transforming JSW Steel and to make our margins both higher and more resilient. Turning now to operational performance for quarter four and FY 2024. In quarter four, we posted our highest ever consolidated quarterly steel sales of 6.73 million tons, an increase of 3% YoY and 12% quarter-on-quarter. Crude steel production for the quarter rose 3% to 6.79 million YoY. Export sales of 1.3 million were sharply higher quarter-on-quarter, helped by a restocking demand opportunity in global markets, and accounted for 20% of our total sales volume.
Jayant Acharya
executiveDomestic sales came in at 5.16 million tons, down slightly, as a result of high imports and channel destocking ahead of elections. Even so, during the quarter we managed to liquidate inventory by 300,000 tons, helped by extra exports and better-structured execution of domestic sales. In quarter four we posted our highest-ever sales of value-added and special products, at a 62% share, compared with 60% in the prior quarter. We also recorded our highest-ever coated and long product sales, which rose 5% for coated and 11% YoY respectively. Tinplate renewables likewise delivered very good growth in the quarter. For the full year, we reported combined crude steel production of 26.68 million tons and sales of 25 million tons for FY 2024, achieving 101% of our production guidance and 100% of our sales guidance. Please note that these combined volumes include JISPL for the entire year. JISPL merged with JSW, effective first August 2023. At the consolidated level, revenues from operations were INR 46,269 crore, up 10%. EBITDA was INR 6,124 crore, down 15% quarter-on-quarter, with an EBITDA margin of 13.2%. EBITDA per ton on a consolidated basis came to INR 9,101, and profit after tax was INR 1,322 crore.
Jayant Acharya
executiveOn a quarter-on-quarter basis, performance took a hit from lower NSR and increased coking coal costs, though a better blend and higher sales volumes partly made up for that. We managed to liquidate 300,000 tons of inventory, and that contributed additional EBITDA. Overseas operations delivered stable results quarter on quarter, with overseas EBITDA dipping slightly versus the prior quarter. Combined U.S. operations in Ohio and Texas posted EBITDA of $18.5 million in quarter four, up from $12 million plus in quarter three. Italian operations' EBITDA came in at EUR 7.5 million, mainly reflecting lower production volume in rail, where the raw material for rail production was delayed because of geopolitical disturbances in the Middle East, and we anticipate that volume coming through in quarter one. We expect overseas operations to keep performing well in FY 2025. Net debt, to be exact, is at INR 73,916 crore, a reduction of INR 5,300 crore quarter on quarter, largely thanks to working capital relief and calibrated CapEx. We have not, however, calibrated any growth CapEx. Revenue acceptances as of 31st March 2024 stood at $2.05 billion, while capital acceptances were $163 million.
Jayant Acharya
executiveWhat's key is that our balance sheet is still in good shape. Net debt to EBITDA came in at 2.62, compared with 2.64 in December. Net debt to equity stood at 0.93, an improvement from the December 2023 quarter. Funding for growth will come mainly from our cash flows, and we intend to keep our leverage ratio under 3. A final dividend of INR 7.3 per share has been recommended by the board, pending shareholder approval at the AGM. That works out to a payout ratio of 20%, sitting at the upper end of the dividend policy we have stated. We had guided for coking coal cost to rise by $20-$25 in quarter four, and the increase we saw was $22, with the CFR cost of coking coal at $274 CFR. With coking coal prices having fallen recently, we expect them to decline by $22-$27 per ton in quarter one. On iron ore, even with elevated prices, we managed to keep the cost under control in the last quarter, helped by optimized blends and consumption — the specific consumption. One of our strategic objectives has been improving raw material security, and on iron ore we have secured 24 mines through various auctions, with resources of 1.6 billion tons across all these mines.
Jayant Acharya
executiveOf those, 13 mines are currently running, while the rest sit at different points in the commissioning process. Over the near to medium term, we're lifting our iron ore mining capacity in Karnataka from 7 to 15.5 million, through a 4 million ton increase in EC limits at existing mines plus the phased commissioning of 3 new mines, adding a further 4.5 million. Once commissioned, the Goa mines will contribute another 1 to 2 million. At our forthcoming iron ore auctions, particularly in Karnataka, we'll keep taking part and bidding rationally, concentrating on mines located nearer to our plants. Turning to coking coal, three coking coal mines are in the process of being commissioned, and they ought to deliver 2 million tons of clean coking coal for us. We're also pleased to announce the acquisition of the MDR coking coal mine in Mozambique — a coking coal mine — continuing our strategy of strengthening raw material security, coking coal included. That asset holds reserves and resources above 800 million tons, among them over 270 million tons of prime coking coal. The transaction remains subject to regulatory approvals, and we anticipate mining operations carrying on once the required approvals and condition precedents are met and we assume development of the mines.
Jayant Acharya
executiveDemand for steel inside India remains robust. Over the past year, as we discussed, our growth came in at 13.36%. During the most recent quarter, the expansion was 9%. Even assuming an 8%-10% growth rate — which we've described as a conservative trajectory for India across this decade — that implies incremental capacity or demand of 12 million tons annually. We've observed global steel prices climbing by roughly $20 in China, and part of that has shown up in India during April and May too. Prices domestically have hit bottom, so we anticipate a healthier pricing backdrop, which ought to underpin margins. That said, pricing even following the hike is likely around the level of six months ago. The JSW One platform is performing quite strongly, has scaled up considerably since launch and counts over 50,000 registered customers. Annualized gross GMV stood at INR 9,400 crore on the March 2024 exit run rate and keeps expanding quickly. As you'll recall, JSW One platform raised $25 million from Mitsui, Japan, in March 2023. And JSW Steel holds the major shareholding in JSW One. Our CapEx and expansion program continues.
Jayant Acharya
executiveAt JVML, we've commissioned the 5 million ton brownfield expansion of the hot strip mill. Commercial production has begun. Integrated production should be finished within the next two months. Over at BPSL, the Phase II expansions are already done, and we anticipate ramping up both of these capacities as this year unfolds. At BPSL, the Phase II expansion is mostly complete at this point. We might manage the ramp-up sooner, possibly by October 2024. At JSW Steel Coated Products, the color-coated line in Jammu and Kashmir should begin commissioning activities in quarter two. The 30 million-ton slurry pipeline in Odisha is likewise moving along well, with commissioning anticipated in FY 2027. Consolidated CapEx spending for the company in FY 2024, quarter four came to INR 3,500 crore, and across FY 2024 it totaled INR 16,752 crore. For FY 2025, we anticipate consolidated CapEx of roughly INR 20,000 crore. Thanks to the new facilities at Vijayanagar and BPSL, which will be ramped up during FY 2024, we foresee greater volumes in FY 2025. We'll also be undertaking a shutdown of our BF3 furnace at Vijayanagar for capacity enhancement. As a result, our consolidated production and sales for FY 2025 will increase.
Jayant Acharya
executiveFor FY 2025, our guidance remains 28.4 million tons of production and 27 million tons of sales, respectively. The full benefit from the Vijayanagar and BPSL expansions will come in FY 2026. We anticipate EBITDA per ton to improve as we move into FY 2025 compared with quarter four. With the low raw material costs we are currently seeing, we expect coking coal costs in quarter one to decline by $22-$27, as we discussed. Improved efficiencies along with some of the cost-saving projects we have implemented will help bring costs down. We are seeing more stable prices, and that should support margins in quarter one and through the remainder of the year. I would also like to add that for the nine months of FY 2024, our normative EBITDA numbers have ranged between 12 and 12.5. Through various improvement measures, falling coking coal prices, and the stable steel prices we are seeing, we expect to return to our normative EBITDA numbers during FY 2025. In conclusion, India continues to be a bright spot among major global economies. That said, we are watchful about rising geopolitical tensions. We stay positive on the overall India growth story, and we expect strong steel demand to be sustained, supported by continued thrust on infrastructure development, a pickup in public as well as private CapEx, and continued momentum across sectors.
Jayant Acharya
executiveOn top of that, the rural economy has improved, and with stronger monsoons, we'll see an even better rebound in rural areas too. Thank you, and we're looking forward to your questions.
Operator
operatorThanks a lot. We're going to start the Q&A portion now. If you'd like to ask something, you can press star and one on your touchtone phone. Should you want to drop out of the queue, just press star and two. We ask that participants use their handsets when posing a question. Ladies and gentlemen, we'll hold for a moment while the queue is put together. Our first question comes from Sumangal Nevatia at Kotak Securities. Please go ahead.
Sumangal Nevatia
analystGood evening, sir, and thanks for the chance to ask. I'd like to start with the Mozambique acquisition. Could you share what volumes, cost structure, and investment we should expect, and also the timeline for when the mine can begin commercial production?
Jayant Acharya
executiveMDR is a mine in the pre-development stage. Among prime hard coking coal assets worldwide, it ranks as one of the biggest. We managed to secure it. Its JORC reserve exceeds 800 million tonnes. We were able to lock in 92.19% of that for an outflow of $74 million. Enterprise value stood at $80 million, plus closing adjustments. Assuming standard approvals and conditions precedent come through, we anticipate closing this mine during the latter half of this year — so it may land in H2, we hope — and we ought to be in a position to begin developing the mine in FY 25. This is prime hard coking coal. As you know, we have been hunting for assets of this kind, both internationally and at home, in the past. Not only will it give us some cushioning against the highly volatile PLV index, it is also logistically nearer to India, and so it will deliver an optimized cost.
Sumangal Nevatia
analystSir, could you give us some kind of quantification—perhaps volumes or a cost structure—for what we can commercially produce from these mines?
Jayant Acharya
executiveLike we mentioned, this contains more than 270 million tons of prime hard coking coal. So because of that, output shouldn't face any constraint. To begin with, we'll examine evacuation out of Beira port, and we'll keep increasing that evacuation capacity as we proceed and while our own operations keep expanding. Still, it's a bit too soon to say precisely how many years this will take. As I noted, this is a pre-development mine. Exploration work has been completed, and resources have been identified. We'll wrap this up, and once we've gone a bit deeper, we can share more detail on cost and timing.
Sumangal Nevatia
analystGot it, that's quite clear. My follow-up concerns slide 18, where you describe the way our share of value-added has grown over time. Could you share, for the total India consolidated entity, what capacity we hold in value-added? And what contribution do we believe can be attributed incrementally if we undertake more value-added work, in terms of margin? Then, at September 2027, with the 42 million tonne capacity, what are we looking at regarding the value-added mix?
Jayant Acharya
executiveSlide 18 here, you know, essentially lays out for you a broad picture of where we stand today in terms of growth and of the value-added special products on the journey we've traveled so far. Our present capacities in downstream operations — and when I say downstream, I mean everything from hot rolled through cold rolling, galvanizing, Galvalume, color coated, et cetera — come to almost 12.5 million tons. Should you add the downstream operation attached to our plate mill plus the LRPC operations of wire, we'd land close to 13.5 to 14 million tons of downstream capacity. What we're focused on is making sure that this downstream capacity gets maximized where volumes are concerned. In this segment we observe less, lesser volatility. It's more sticky by nature and typically delivers incremental EBITDA in the range of INR 4,000 per tonne. That does vary depending on how the market sits. Sometimes it can improve, sometimes it can be marginally lower. But since we're growing our capacities, doing more branding in the downstream segment, and are able to approach wind through our plate mill, these are all areas of operation that are far more non-volatile, and so we see more sticky EBITDA coming through VASP operations as we go along.
Sumangal Nevatia
analystRegarding fiscal year 2027 and that 42 million tonnes figure, sir, what is our vision there when it comes to expansion, the pipeline, and so on, for downstream?
Jayant Acharya
executiveSo as our hot rolled coil capacities increase—you already have our hot rolled coil figures—we've held to a guiding principle of wanting at minimum a 50% thumb rule for downstream operations on hot rolled coils. We remain at that level or better. And as we expand capacity in our hot strip area, the hot strip mill area, we'll keep adding facilities at both our downstream sites at Vijayanagar, coated or near Dolvi. That said, I'd also like to highlight one thing you'd have noticed in the press release: we've received approval for the Phase III expansion at Dolvi to 15 million tons for integrated operations. This line is again part of our VASP process, since it's a 5 million ton wide mill, with 2,600 mm width, up to 32 mm product, which offers you a combination of sheet and plate. In this mill we'll be able to produce plate at a much lower cost than a normal conventional plate mill, and so this will additionally be able to contribute to our accretive value story. So this too will form part of our special product strategy going forward.
Sumangal Nevatia
analystGot it. Just one final quick question, if I may?
Operator
operatorApologies, Mr. Nevatia, but I'm giving this one back.
Sumangal Nevatia
analystAll right, certainly — thanks a lot.
Operator
operatorLadies and gentlemen, so that management can take questions from everyone joining the conference, we ask that you limit yourself to 2 questions per participant. Should you have a follow-up, you're welcome to get back in the queue. Our next question comes from Ritesh Shah at Investec. Please go ahead.
Ritesh Shah
analystYes. Hello, sir. Appreciate the chance. I’ll begin right where Sumangal’s question left off. First, regarding the coal mine: is this the identical coal mine that Anglo American bought in 2012 for a 59% stake at $550 million, and the consideration, from what I heard, came to roughly $74 million? Is it that same mine?
Jayant Acharya
executiveNo, this isn't the same mine. This one sits in that area where Vale and Rio Tinto had their operations, which is now held by Vulcan and ICVL, International Coal Ventures — sorry, ICVL.
Ritesh Shah
analystAlright.
Jayant Acharya
executiveThey're active in that region. This mine, though, is not the same. Given the geography of that area, it holds very rich hard coking coal, which we've observed. As I mentioned, resources and reserves of 800 million tons and above, plus hard coking coal of very good quality. So because of that, we, we were able to get this transaction closed at an enterprise value of $80 million, plus closing adjustments, for a 100% stake. However, we've now acquired 92.19% with an outflow of $74 million.
Ritesh Shah
analystThat's useful. So I just looked at the geography—there are 2 mines. One is Zambeze and the other, as you pointed out, was Benga. Given their track record, they haven't really performed well when it comes to production. So what makes us confident about this particular asset? And could you provide some timelines regarding the offtake, plus any guidance on the numbers—whether cost or whatever else would be helpful?
Jayant Acharya
executiveIf I consider the operations currently underway in that adjoining-mines area, then taken together, I'd say they likely amount to somewhere between 11 and 12 million tons of mining each year. Evacuation is happening via two ports — Beira and Nacala. Our position will be nearer to Beira port. Initially, we'll attempt evacuation through Beira first, and after that we'll examine expanding port operations further so capacities can be raised, or failing that, do midstream loading. Operationally speaking, given what others are already doing today, we don't perceive any constraint on ramping this up capacity-wise to the level we'd like it to reach, from the standpoint of integration with our Indian operations and perhaps potentially for the market as well.
Ritesh Shah
analystRegarding that EC figure of 5 million tons, sir — would it be fair to assume a number like that, say, 2 years out or 3 years out?
Jayant Acharya
executiveCould you say that again, Ritesh?
Ritesh Shah
analystFrom the last plan I reviewed, the EC limit for that asset we examined was 5 million tons. Is that a fair outer limit for one to consider, or could it go beyond that?
Jayant Acharya
executiveNo, I don’t believe we have an annual figure that can be raised. We aren’t seeing any limits on that, though we can look into it further and get back to you. Just give me a second, I’ll… No, a 15-year mine life is already in place. It could be extended by another 25 years. That’s the approach, no issue. Resources are in fact greater. Reserves are what I mentioned to you. Right, so we ought to be able to increase this. We don’t see any constraint on EC.
Ritesh Shah
analystThanks, that helps. On the second question, you focused on value-added products. I believe slide number 18 also shows a figure of 61%. Could you provide a general breakdown of EBITDA for upstream and, in particular, for the value-added portion?
Jayant Acharya
executiveRight now, doing that might be somewhat challenging. Still, as I mentioned, the value-added VSP segment has been delivering incremental EBITDA of roughly INR 4,000 per ton. We keep adding downstream capacity, and we are also adding capacity through the Phase III expansions at Dolvi, which we are now undertaking. That will be a plate mill type of product, with a mill cost — a plate mill cost, rather — and it will allow us to market wider plates of greater thickness from this capacity in the western market. So in that sense, I think our focus will remain. As to whether we can eventually give you more detail on how we are structuring our downstream business and overall profitability, we will take a look at that and perhaps get back to you as we move through the year.
Ritesh Shah
analystThanks, sir. I really appreciate the responses at the close of things. Thank you.
Operator
operatorThanks. Our following question comes from Ashish Jain at Macquarie. You have the floor.
Ashish Jain
analystHello, sir, and good evening. My first question is—
Jayant Acharya
executiveMr. Jain, your audio isn’t coming through on our end. Your voice is quite faint. Could you turn up your volume a little? Yes. I wasn’t aware that you couldn’t hear me. Is the sound acceptable at this point?
Operator
operatorThat's a big improvement, sir.
Jayant Acharya
executiveYeah. Yeah, I think perhaps you're fine there.
Ashish Jain
analystLet me start with my first point.
Jayant Acharya
executiveYes.
Ashish Jain
analystYou know, when it comes to EBITDA per ton of output, well, that's—
Jayant Acharya
executiveI’m not able to hear you.
Operator
operatorMr. Jain, would you mind picking up a handset if you happen to be on speakerphone or something like that? We can't hear you at all.
Ashish Jain
analystHi there, can you hear me at this point?
Operator
operatorSir, your voice is coming through very softly.
Ashish Jain
analystAlright, I’ll rejoin the queue.
Operator
operatorAppreciate it very much, sir.
Ashish Jain
analystCorrect.
Operator
operatorSatyadeep Jain from Ambit Capital has the next question. Your line is open.
Satyadeep Jain
analystHello, and thanks. I have one follow-up tied to all the Mozambique questions. I realize the other plays are running, but speaking broadly about infrastructure and mine development, where we stand today, what level of CapEx might you envision here over the coming few years? The reason I ask is that every overseas venture by Indian companies, whether mining or otherwise, has largely failed to meet expectations, since many firms ultimately record impairments and losses. Given that, what makes you confident when you examine the deposit, and what CapEx do you foresee for mine development and infrastructure to bring this into operation? That is my first question.
Jayant Acharya
executiveYou know, mining is naturally an area that demands more effort and diligence. But the reason we're looking at this particular mine, and the reason we've taken it, is that it's prime hard coking coal — a PLV coal — and that's the grade that has been most volatile and has affected our costs. You'll remember it climbed to $600 and for most of the last year it's been hovering in the $300-$350 range. That has caused a lot of volatility in our operations and profitability. The other indexes haven't been nearly as volatile, so we wanted access to PLV coal that would integrate with our operations and in that way give us a cushion to arrest this volatility. That's the main reason. The second advantage of this mine is that it's a large mine and logistically close to India — Mozambique — so we'll be able to get it to India with faster turnaround and lower logistics cost versus the U.S., Canada and, maybe, even Australia. So that's the second positive. On the cost side, it's too early to say. It's a new mine, a pre-development mine.
Jayant Acharya
executiveWe’ll move forward with developing this once the approvals are completely secured. So there’s a bit more waiting ahead. Once we have a clearer sense of things, we’ll be in a position to share how much we can accomplish each year, what the cost structure will look like, and so on. But based on what we’re seeing right now from our initial due diligence—since the operating mines nearby are performing reasonably well—we don’t foresee any issue in reaching the volume targets from this mine.
Satyadeep Jain
analystAlright. And then second, regarding the growth trajectory you described, Dolvi is included there. Past Dolvi, there's 8 million tons between 2027 and 2031. That looks fairly conservative — picking up just 8 million tons from 2027 through 2031. Might there be upside potential? And for that 8 million tons, what type of capital expenditure should we expect? Would it just be comparable to Dolvi, or does that include a greenfield piece?
Jayant Acharya
executiveNo — between 43.5 and 51.5, nothing comes from greenfield. What we'll have is a choice involving Vijayanagar. It'll be a choice involving our Salav greenfield — sorry, our Salav green steel conversation, the one we've been carrying on about, low-carbon emitting steel, which we intend to build in two phases as a 4 million facility — and the BPSL brownfield. So all of these are brownfield, and that gets us to 8 million and past it. As you correctly put it, the scope is larger. We could do 5 million at Vijayanagar, 5 million at BPSL, 4 million. So technically it's permitted, meaning technically we can go further with the brownfield expansions. But our focus will be on giving priority to two of them, and that's how we arrive at 8 million. That said, there will be CapEx for a third facility on top of this, which will get underway before FY 2031 and which will likely begin delivering volumes a year or a year and a half after FY 2031. So what we're weighing is whether we'd be looking at BPSL in Odisha or the new site in Odisha, which is the Jagatsinghpur site.
Satyadeep Jain
analystAlright, moving to the second stage — and I have one quick question about the power capacity you're adding: 600 MW and a 320 MWh battery. What does it cost to procure that power, and how does that compare with the PPA you hold with JSW Energy for coal and your other sources?
Jayant Acharya
executiveAs you can see, regarding our renewable power strategy, we've been emphasizing that our aim is to move along a decarbonization path that we've taken on ourselves. Thermal coal is what we want to replace with renewable energy. We had already announced 1,000 MW of renewable energy projects, which are already being executed in Vijayanagar and mainly in Vijayanagar, some in Dolvi, a little bit in Salem. Now we're adding 600 MW to this, so our total renewable capacity will be 1,600 MW across three locations, but mostly in Vijayanagar. With this, Vijayanagar will be 26% on renewable energy from at 18 million ton level, which is a good kind of direction to achieve. From a cost perspective, it will be difficult for me to share exactly what cost, but I would only like to say that it is more cost effective than our current power. Also providing greener power with a fixed price, kind of a price contract, over the years.
Satyadeep Jain
analystAlright, thanks a lot.
Operator
operatorThanks. Just a quick reminder for everyone on the line: if you'd like to ask a question, hit star and one at this point. Our next question comes from Noel Vaz at Union Asset Management. Go right ahead.
Noel Vaz
analystHi there, am I coming through okay?
Jayant Acharya
executiveYes, that’s possible.
Noel Vaz
analystYeah, I just had a single question. Now that we’re increasing capacities, how does that ramp look quarter over quarter, say from 1Q onward? Like, how will growth essentially be in, say, the first half of this two, the second half, first quarter versus second quarter? Yeah.
Jayant Acharya
executiveAs our capacities are ramping up, you'll see in the press release that we've said the integrated steel capacity at Vijayanagar should be finished in roughly the next two months. After that, the ramp-up begins. The hot strip mill has already been commissioned. BPSL is already done, so production there will rise gradually. It's hard to give a quarter-by-quarter picture, but I'd say H2 will bring ramp-up at both locations. BPSL comes a bit earlier, and JVML, which is starting later, therefore comes a bit after. At Vijayanagar, BF3 — where we're looking at debottlenecking and raising capacity — that shutdown we'd take in H2 of this year, and it would add further capacity to our overall capacity. I think we'll add roughly 1.5 million tons through that debottlenecking, on top of JVML and BPSL. So in total, about 8 to 8.5 million tons will be the overall addition during this financial year by the year end. Some of that capacity will show up in production this year, and the full impact you'll see next year.
Noel Vaz
analystThanks. And one more thing — I just want to make sure. I believe you said that the path up to roughly 50 million tons is largely brownfield, with perhaps some greenfield in the mix. I'd just like to clarify that.
Jayant Acharya
executiveAs much as 51 million tons comes from brownfield, which is what we've shown you at this point. The 51.5 million figure includes 1.5 million from the U.S., so that leaves 50 million in India. All of that rests on brownfield. What I said was that during the interim period from 2027 to 2031, the question came up about whether we'd undertake anything further. We might consider launching one more CapEx program, assuming everything goes well, between one brownfield site that will stay and our new greenfield site in Odisha. That call we'll make as things move forward. It would bring capacity on top of 51.5.
Noel Vaz
analystThanks. Thank you. And just one final point to clarify. That 1 GW of RE that's presently with JSW Steel, plus the 600 MW that I believe is under execution — how does that work? Are these captive units?
Jayant Acharya
executiveThese fall under Group Captive. So, in line with India's Group Captive regulations, we would hold a 26% stake in that asset.
Noel Vaz
analystAll right, thanks. I’ve got nothing further. Thanks.
Operator
operatorThanks. Our next question comes from Amit Dixit at ICICI Securities. The line is yours — please go ahead.
Amit Dixit
analystHello there, good evening, and thank you for the opportunity to ask a question, sir. There are two things I'd like to cover. First, regarding your expansion roadmap: previously, you had guided that capacity would hit 50 million tons by FY 2030. It now appears that timeline has slipped by one year. I'd just like to grasp what caused that slippage. Also, when I look at most of your capacity, I had thought you might also move into longs, yet even Dolvi 3 is mainly geared toward flat. Aside from the BPSL expansion you're pursuing, flat remains our core focus. So I wanted to check, within that 50 million tons you're referring to, roughly how it splits between flat, and when any long capacity might come onstream, if at all?
Jayant Acharya
executiveYes. So on your timing question, we had said 2031 — that's the financial year 2031 we expect, right? So it runs up to March of 2031. We mention it only for the sake of the financial year. Nine months of that still fall in calendar year 2030. So timing-wise, nothing has changed at all. On flats versus long, we're looking at a possible enhancement to our long product mix, which we're studying right now. That would also be added at one of our brownfield locations. There's an opportunity to do that, and it's on the drawing board right now, and we'll come back to you with more detail once we finalize it. BPSL — we've anyway indicated that we could do longs, but that's, that's already something you know. That's one option at BPSL, which we already have.
Amit Dixit
analystThe second question concerns realization. You mentioned coking coal costs declining by $22-$27 in Q1. We've observed some price increases implemented by various players in May. So I just wanted to understand how much of a price hike we've implemented in May, how much is expected in June, and what it might be on a blended basis — you know, the overall prices, the price difference between Q4 and Q1?
Jayant Acharya
executiveLongs and flats each moved up, but at differing rates. Long products rose more quickly, since the secondary sector within longs pushed prices higher, driven by increased iron ore costs and also by a higher thermal coal price, which climbed for them. Prices for long products, particularly bars, were already depressed, so the increase there was larger. On the flats side, globally, Chinese prices gained roughly $20 per ton, as we observed over this period. In India, I believe we reported a comparable figure for April and May taken together. So that's the position we're in. For long products, it's somewhat higher in both GMP and wire rod.
Amit Dixit
analystSo if I compare on average, you know, would Q1 still be a bit lower than Q4, or will it be at par?
Jayant Acharya
executiveYeah, I get that — it's a question you're probably thinking about. So my feeling is it'll likely be... at par or slightly better, since coking coal prices are coming down, as we said, $22-$27. We're seeing a softer coking coal environment. As we speak today, it's around $235, FOB Australia, FOB Australia. And that, you know, would give a benefit in quarter one, and if this price holds for another month or two, you'll see the benefit carry into quarter two as well. So in H1, I'd say that, overall, you'll see a cost benefit. You're already seeing stable prices. Keep in mind that domestic prices corrected in quarter four, and even after that correction, we're probably now where we were six months back. So, from a domestic price standpoint, I, I see it as totally bottomed out, and therefore prices would stay stable, maybe range-bound, as we go forward. So then, on a, a quarter-to-quarter basis, I'd say we're likely to be similar or a little better.
Amit Dixit
analystExcellent, sir. Thank you very much, and best wishes.
Operator
operatorThanks. We’ll take the next question from Raashi Chopra at Citigroup. The line is yours — please proceed.
Raashi Chopra
analystThanks. Just to pick up where the last question left off: so if pricing is probably going to stay range-bound, and you've got a $22-$27 benefit on the coking coal price, basically from an EBITDA per ton standpoint, we're sort of factoring in the coking coal improvement along with any efficiency gains that you might be seeing, correct?
Jayant Acharya
executiveYeah, Raashi, that is correct. Some efficiencies on coking coal, which we do see, will be built into cost reduction in quarter one, and a portion of that will carry over into quarter two. Like I mentioned, should coking coal stay where it is, quarter two benefits too.
Raashi Chopra
analystOkay, thanks. Regarding iron ore, let me just lay it out: you've got roughly 15 million tons of captive ore in Karnataka, around 25 in Odisha, and approximately 1 to 2 in Goa. Is that accurate?
Jayant Acharya
executiveRight, so that comes to 15.5 million from the mines we already have, counting the three new ones that will be brought into operation in Karnataka. That's right. And for the Goa mines, it's 1 to 2 million tons. Correct.
Raashi Chopra
analystTwenty-five Odisha?
Jayant Acharya
executiveYeah, Odisha ought to come in around 25. If it turns out that’s needed, we can push it up a bit. So where CC is concerned, there’s no issue for us. But yeah, you can figure roughly 25 million.
Raashi Chopra
analystUnderstood. Alright, thanks so much.
Operator
operatorThanks. Our following question comes from Pallav Agarwal at Antique Stock Broking. You have the floor.
Pallav Agarwal
analystGood evening, sir. I just had a question about the iron ore price increase that NMDC implemented in Q4. It doesn't appear to be showing up in either the raw material cost or the mining premium and royalty. So, was this because of a change in the mix of iron ore sourcing in Q4?
Jayant Acharya
executiveYeah, that's right. On iron ore prices, we managed to keep them in check by improving our mix — geographically, by grade, and by lowering specific consumption as well. So because of that, we were able to hold down what iron ore costs us.
Pallav Agarwal
analystSo that's how it'll continue going forward?
Jayant Acharya
executiveYeah, that should be fine. We don’t see any challenge there.
Pallav Agarwal
analystYes, sir. On the second question — this quarter, the subsidiaries appear to have performed quite strongly. So if I look at how consolidated EBITDA differs from stand-alone EBITDA, that gap is a fairly large figure, and EPC-BPSL plus the overseas subsidiaries you mentioned account for roughly half of it. So what are the remaining subsidiaries — perhaps Amba River, or which among these subsidiaries contributed to EBITDA in this quarter?
Jayant Acharya
executiveThe key Indian subsidiaries that pitched in are, as you correctly pointed out, BPSL, Coated, and Amba River, plus two smaller ones, JIGPL and Mivan. Those are the Indian subsidiaries that added to the total EBITDA. On the overseas side, as you saw and as we said, performance has also been strong. Looking at it annually, just so you get a sense of how much improvement took place, the U.S. operations as a whole — Ohio and Texas together — produced $75 million of EBITDA in FY 2024, compared with $27 million in FY 2023. Italy, meanwhile, brought in EUR 52 million against EUR 26 million in FY 2023. Looking ahead, we expect steady operations at Ohio on the steel production front, and Baytown is performing better thanks to plate and wind demand, et cetera. And now, with the investments at Ohio for special grades, together with vacuum degassing and soft reduction of the casters, we'll be in a position to supply those grades, and spreads will incrementally improve. So we believe the U.S. operation will do better. And Italy has bilateral orders, you know, from the Italian rail as well as from some markets in export.
Jayant Acharya
executiveWe also anticipate that the Italian operations will perform strongly too. So internationally, I believe, yes, you've witnessed a considerable uptick, and I think this type of range is what you'll see in FY 25 as well.
Pallav Agarwal
analystAbsolutely, sir. Yes. Yes, I appreciate it, sir.
Operator
operatorThanks. Our next question comes from Siddharth Gadekar at Equirus. Your line is open — go ahead.
Siddharth Gadekar
analystHi, sir. I just wanted to ask what our captive iron ore production was in FY 2024, and how should we view that taking shape in FY 2025 and 2026?
Jayant Acharya
executiveYour question is about the iron ore we produce captively?
Siddharth Gadekar
analystRight.
Jayant Acharya
executiveI believe we simply don’t have that figure available right now. Still, to give you a sense of it, Investor Relations will follow up with you. In FY 25, though, we’ll likely be sourcing nearly 50% from our captive mines. Is that right?
Siddharth Gadekar
analystAll right, sir, understood. Thank you.
Jayant Acharya
executiveHold on, just a moment. It's roughly… yeah, roughly 35%. We'll be mining, likely somewhat more, though a portion of that could also head to the outside external market. So 35% will go into the captive.
Siddharth Gadekar
analystAll right, understood. Thanks.
Operator
operatorThanks. Our next question comes from Amit Murarka at Axis Capital. Please go ahead.
Amit Murarka
analystYeah, hello, and thanks for the chance to ask. So regarding expansion, Vijayanagar and BPSL — I just wanted to get a clearer picture. It looks like the ramp-up guidance has now been pushed to Q3, but our earlier understanding was that it would come in by March and then probably ramp up in Q1 and Q2. So is that because mechanical completion has slipped a little, or is it due to market conditions that the ramp-up guidance is now going to Q3?
Jayant Acharya
executiveNo — okay, let's take the two assets one at a time. For BPSL Phase II, the expansion has been commissioned and is complete. Only one oxygen plant remains outstanding, and it will be finished in June. Once that's in place, BPSL is entirely finished. That will support volume as well as some cost savings, since the oxygen gives us better PCI throughput, lower cost, and so on. So the BPSL ramp-up will come faster. That said, BPSL has some shutdowns — annual shutdowns — planned for certain installations that were already pre-ordered. So that may slow part of it, but the new capacities will begin running, in my view, from October onwards. So in H2, meaning from October onwards — when I say it will start running anyway, it's operational regardless, but from October onwards you'll see something close to full ramp-up of the BPSL facilities. So the blast furnace, which is the major area, as you know, will reach its full capacity by October. On the JVML side, we've completed the HSM part, as you must have read. We're running integrated operations now over the next two months, so that will essentially need a bit more time to ramp up.
Jayant Acharya
executiveAnd, you know, the furnace is significantly larger, which is exactly why we're taking a somewhat more careful stance on it, and we're indicating that it might, you know, possibly get up to speed by the end of quarter three, and by quarter four you'll be seeing that asset running at full capacity utilization. That's the broad—
Amit Murarka
analystAh, understood. And then, regarding Dolvi III, will the land already be in hand? Since my understanding was that land would pose a problem for going past 10 million tons — how do you figure you've resolved that?
Jayant Acharya
executiveSo we managed to resolve that. A few of the lines are connecting. We've succeeded in acquiring, and are still in the process of acquiring. So we have sufficient land to finish this Phase III. It's been carried out under that plan and that plan alone.
Amit Murarka
analystAlright.
Jayant Acharya
executiveRegarding additional land — is that what you're asking about, additional land? Yes. We did need more land, and some of it has already been acquired while the rest is in the process of being acquired, so we'll be able to handle that.
Amit Murarka
analystOh, thank you very much.
Operator
operatorThanks. We’ll take our next question from Ashish Jain at Macquarie. Please go ahead.
Ashish Jain
analystHello, sir. Good evening. I trust you can hear me at this point.
Jayant Acharya
executiveYes, that's right. Much improved.
Ashish Jain
analystOkay, my first question relates to pricing and what you said earlier about normative EBITDA being nearer to INR 12,000. Over roughly the last 12 months, Indian steel prices have generally stood at a premium to parity, whereas during the prior decade or so they were at a discount. So what is behind that? How should we think about that figure? And second, on your remark about normative EBITDA, if I consider it alongside the volumes, in theory we could generate INR 25,000 crore to INR 30,000 crore of EBITDA. From a leverage standpoint, should we take it that we have peaked if we hold to the current CapEx guidance given for the next three years?
Jayant Acharya
executiveFor the second part of that question, I’d like Rajeev to answer. I’ll get back to you regarding the pricing piece.
Rajeev Pai
executiveSure. On capex, we said roughly INR 20,000 crore, and that's what we'll spend in FY 2025. We can fund that from internal accruals plus refinancing of the repayments coming due, so debt should stay about flat. So to answer your question, yes, I'd say where debt is concerned, we've peaked. There might be some working capital investment in a quarter or two, but that should unwind in the quarters after.
Jayant Acharya
executiveAnd regarding CapEx, the way to think about it is this: even as we expand, we're watching our ratios very carefully, and those ratios have gotten better. As we exit the year, we sit at 2.62, versus 3.2 at the close of FY 2023. So despite committing so much CapEx, both our net debt to EBITDA and our net debt to equity have improved, and we'd like to hold them within this band, and perhaps do even better going forward. Should cash flows strengthen, there's room to bring debt down, and we'll pursue that without giving up growth. That said, I don't believe we'll compromise on the ratios. On price, it's hard to offer guidance on where it will head. What I will say is that in India, price results from supply and demand. Given how Indian steel demand has expanded across the past two years — 13, 13.5, 14% demand growth — that rise in consumption within the country is essentially what's pulling this steel.
Jayant Acharya
executiveSo price is one factor, sure, but goods are actually moving, and that's really, really encouraging to see. And we're noticing that folks are now putting a bit more effort into optimizing their costs when it comes to long lead time procurement. So maybe some people who want to play the market will try importing too, but apart from that, long lead imports don't really pay off for an OEM or a manufacturer. So those benefits should come our way over time. That said, China imports are a concern, and we'll have to keep watching that this year as well.
Ashish Jain
analystSir, if I could just ask one quick follow-up. So of that roughly 9 million tons that India brought in this year, can you put a figure on how much of that import volume is, you know, sticky by nature — meaning it doesn't hinge on pricing? Because my guess is part of this comes from global contracts held by OE— by, you know, global MNCs, and also CRGO-type steel, which is, which will keep coming into India no matter what, at least right now. So is there a number that's sticky and, it doesn't depend on prices and all?
Jayant Acharya
executiveLet me frame it this way. In my view, over 95% of imported steel—perhaps 96%–97%—is made in India, and all the domestic mills, or most of them, are fully capable of producing it. So availability within India isn't a constraint for those items. Second, on the subject of contracts: I don't believe any OEM in this area holds long-term contracts with anyone. As for your question, there are a limited number of certain grades that may be imported because they aren't MOQ—meaning the minimum order quantity isn't available for some special items that may be too small for us to handle. Beyond that, I don't see any need for import, or for anyone to depend on imports. I don't see that either. Most imports, I think, stem mainly from a price arbitrage opportunity that arises. Some units buy from their parent units overseas. Those are the only two reasons.
Ashish Jain
analystAlright, sir. Thanks a lot, and good luck.
Jayant Acharya
executiveAppreciate it.
Operator
operatorThank you. Ladies and gentlemen, we'll treat that as the final question. At this point, I'd like to pass the conference back to management for their closing remarks.
Jayant Acharya
executiveTo recap what we discussed before, I'd say this year delivered a really solid operational performance. We managed to achieve growth in crude steel, in sales, and in EBITDA as well. Looking ahead to next year and the years after, we've now kicked off our new capacity expansion. In terms of direction, we're heading toward 50 million tons. Phase III of Dolvi is going to get underway now. Our emphasis on value added remains in place. Even as we expand, we haven't dropped our attention on securing raw materials, for both iron ore and coking coal. So we're working to ensure that everything we're doing on the growth side is sustainable in every respect, and not just when it comes to decarbonization.
Ashwin Bajaj
executiveThanks.
Jayant Acharya
executiveThanks.
Ashwin Bajaj
executiveThanks a lot, everyone, for being with us today, and if anything else comes up that you'd like to ask about, please don't hesitate to reach out.
Operator
operatorThank you. That brings us to the end of this call on behalf of JSW Steel. We appreciate your participation. You can go ahead and disconnect your lines now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete JSW Steel Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to JSW Steel Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in JSW Steel Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.