Keel Infrastructure Corp. (KEEL) Earnings Call Transcript & Summary

August 10, 2026

NASDAQ CA Information Technology Software earnings 57 min

Earnings Call Speaker Segments

Laine Yonker

executive
#1

Thanks for joining us, and welcome to Keel Infrastructure's conference call covering the second quarter of 2026. Joining me today are Ben Gagnon, who serves as a Director and our Chief Executive Officer, along with our Chief Financial Officer, Jonathan Mir. Before we get started, please be aware that this call is being webcast and comes with a slide presentation. You can find today's press release and the presentation on our website, in the Investors section. Moving to Slide 2. I want to remind everyone that during this call, we will make certain forward-looking statements, and actual future results might differ from what those statements imply. This forward-looking information rests on certain assumptions and carries risks and uncertainties. I encourage you to review Keel's 10-Q for a full list, which you'll be able to find on our website as well as the SEC website. Keep in mind that we will reference certain non-GAAP financial measures, which means they may not be comparable to similar measures that other companies present. We ask listeners to look at today's press release and our filed 10-Q for the definitions of those non-GAAP measures and how they reconcile to GAAP measures. Also note that unless stated otherwise, all financial references are in U.S. dollars. Now, moving to Slide 3. It's my pleasure to hand the call over to Ben Gagnon, a member of the Keel Board of Directors and our Chief Executive Officer. Ben, the floor is yours.

Benjamin Gagnon

executive
#2

Appreciate that, Laine, and morning everyone. A year and a half ago, we laid out a distinct roadmap for Keel and for the data center industry overall; we explained that the key bottleneck for the most significant technology of our era wasn't semiconductors or funding — it was electricity. We also said that as 2026 comes to a close, electricity would be in even tighter supply and demand would be even greater. Our investment case was straightforward: concentrating on building power in the correct locations on schedules that count would prove extremely valuable to future tenants and would maximize value for shareholders. We laid out the required tasks in advance, and we updated you at each stage on precisely how this company would be turned into a top-tier regional data center developer. We told you we'd pull out of Latin America and Bitcoin and become an American HPC and AI company; that's what happened. We told you we'd restore the balance sheet so we could shift into being an HPC and AI infrastructure business. That's done. We told you we'd be positioned to cash in on our assets once power grew harder to secure and demand grew stronger. That's where we stand. All through this transformation, we've honored our promises, either right on schedule or ahead of it. Whenever schedules shifted, we explained the reasons, spelled out the implications, and clarified which elements were affected and which were not. Luck had nothing to do with it. What you're seeing is a proven history shaped by disciplined strategy and steady performance. Now let's look at Slide 4. Back in May, we communicated that leadership had three priorities for the year: first, pushing forward with permits and leases at all 3 priority sites; second, locking in our expansion capacity; and third, getting energized megawatts to our customers as fast as we possibly can. Here's the status of each, 90 days on. Starting with permitting and leasing. In a moment, I'll go through the permitting and leasing progress for every site one by one. First, though, let me call out the key points: first, during this quarter we pushed permitting even further forward at all 3 priority sites, and we can now see clearly when each site's permits will be finished; second, power is in short supply right now, and our sites already have it. That shortage is working in our favor. It explains why multiple prospective customers are in talks and negotiations at each of the 3 sites, and why those discussions begin from a much stronger position than they would have 2 years ago. That matters a lot, because once your locations address the toughest, highest-value issue prospective tenants face — power, timing and location — the commercial conversation is no longer a sales pitch; it becomes a negotiation. So to steer this next crucial stage, we brought on Ganesh Aiyer last month as President of Keel. Throughout his career, Ganesh has worked where infrastructure meets commercial strategy, and he comes to us following almost 7 years as Chief Business Officer of Digital Realty. Our commercial efforts are now under his leadership, and despite joining only about a month ago, he has already hit the ground running. Now, on the topic of room to grow. Earlier in the year, on our last call, we shared the belief that the market was assigning minimal value to the unsecured megawatts sitting in our expansion pipeline. We also said that securing those megawatts ranked among management's top objectives and represented a key source of shareholder value. With that as background, turning first to Pennsylvania: we've been working very closely alongside both of our utility partners to advance the power applications tied to that additional capacity. While we're not in a position to disclose details yet, our confidence continues to grow that we can convert the prospective expansion capacity in our 2-gigawatt Pennsylvania pipeline into further signed ESAs, which would bring energized megawatts for HPC online through 2030. We anticipate being in a position to give investors a thorough update as soon as December or January. In addition, we moved our Sherbrooke data center plans ahead during the quarter, obtaining every required local approval from the city and the local utility, leaving only provincial approval still pending. We're thrilled to broaden our ties with Sherbrooke in a major way, since across the last 7 years we've produced significant revenues, taxes, jobs and community benefits there. If it gets the green light, our three legacy Bitcoin power purchase agreements will be consolidated into a single 96-megawatt HPC and AI power purchase agreement, supporting a new data center development in Sherbrooke — a market where obtaining fresh data center energy capacity is nearly impossible and demand runs high. Sherbrooke will be constructed from the ground up to accommodate the next generation of hardware, and once complete, it could rank among the most technologically advanced data centers anywhere in Quebec. Third, delivering energized infrastructure as fast as possible. Every commercial negotiation really comes down to two identical questions: how soon can I get my first megawatts, and how quickly and how broadly can I keep expanding alongside you after that? Beyond every deal we sign with a customer, there's ongoing work with our partners, the manufacturers we rely on, and our supply chains to keep the timelines our customers build their underwriting around on track. Turning to Slide 5, I'd like to walk through a few illustrations, because the bulk of this work never turns into a press release. Just in this quarter, we received long lead time items along with the initial Vertiv modules at Moses Lake. And as modules come off the assembly line, we'll conduct further factory and predelivery inspections alongside Vertiv. We finished inspections for backup generation equipment in Moses Lake; we accepted delivery of a number of long lead time items in Sharon, among them multiple transformers; we started executing final fiber contracts throughout our 3 sites, making sure multiple path redundancy and connectivity will be in place before the sites go online. We keep revising our data center designs, enhancing power density specs so we're able to satisfy customers' hardware requirements. We finished the first phase of construction at all 3 sites, which involves decommissioning every U.S. Bitcoin mining operation. And what matters most is that we've really expanded our roster of specialists in construction, power, fiber, engineering, controls, and other essential fields, and we keep bringing in more talent for those areas. These are obvious, intentional moves to reduce risk on our project schedules and make sure we can deliver cutting-edge infrastructure inside the timelines and budgets our customers need. Such moves are what separate a pledge from an actual completion date. Take a step back and consider what all of this amounts to. Eighteen months back, we presented our thesis and our strategy. Right now, we are precisely where we told you we aimed to be. The market sits where we expected it to sit. Right now, we're in the middle of the commercial process with the sites we planned to bring to market, and we're doing it when we planned to bring them there. We're operating from a position of financial strength, and permitting is mostly derisked. We kept our promise not to cap our upside by signing leases too early, and that patience is paying off now. This is our goldilocks phase — not too early to matter, not too late to win, precisely the window we built this company to hit. Now let me show you what execution looks like on the ground, beginning at Moses Lake. Turning to Slide 6.

Benjamin Gagnon

executive
#3

For Keel, Moses Lake is turning into a landmark project. It stands to be our initial fully permitted location, the earliest one to begin operations, and the first where HPC revenue gets generated — plus, once commissioned, we anticipate it will hand back a substantial amount of equity capital to the balance sheet and turn into our initial wellspring of lasting free cash flow. The permitting regime in Washington differs somewhat from Pennsylvania's, which has let us kick off site work while we complete the go vertical permitting procedure, something we anticipate finishing up in the current quarter. The Bitcoin mine formerly located there has been dismantled, entirely taken away. Right now, the location is getting ready for the Vertiv modules, with all critical long-lead equipment locked in and actively in production; as a matter of fact, the initial Vertiv modules are already on-site, and further deliveries keep coming. Looking at that rendering on the slide, you should recognize that every element within it has been purchased, placed under contract, or is already in production — the building included. We're eager to bring Moses Lake forward as our inaugural completely commissioned and energized data center during 2027. The commercial side of things mirrors that. Interest in Moses Lake comes from precisely the sort of prospective tenants you'd hope for: top-tier AI firms, GPU cloud providers, and enterprises requiring power immediately. Inquiries and deal talks have picked up pace across the quarter, which shows how tight near-term power supply is across the Pacific Northwest. The customer profile Moses Lake targets differs from what our Pennsylvania locations serve — companies that move faster and prioritize speed along with a fully operated facility; given that demand, we might put leases in place here on a modified gross basis instead of triple net, with credit support arranged to fit; such an approach enables these tenants to proceed as quickly as they require, preserves Keel's operational control, and generates greater value for a site as large and broad in scope as Moses Lake. Now onto Slide 7. With Sharon's momentum still growing, we obtained full zoning during April. Land development received approval in the quarter, and our final environmental permits have been submitted and are advancing as planned, with just a handful of environmental permits left before Sharon gets cleared. We additionally refined the designs over the quarter, assessing the optimal way to consolidate compute capacity, which we think would yield a simpler, less complicated build and a stronger overall product. Sharon is currently in active commercial talks with several parties engaging the site at the same time and assessing it for precisely what it represents: uncommon, uncontracted 2027 power within PJM. The structures being discussed here center on triple net and involve matching fast-growing AI companies with investment-grade credit support — precisely the sort of structure that lets a high-growth customer provide a financeable long-term lease. Now onto Slide 8. Then we have Panther Creek. 350 megawatts of secured utility capacity alongside PPL, 2 hours away from New York and Philadelphia, situated amid one of America's most coveted AI corridors. During this quarter, we obtained zoning approval, got conditional sign-off for land development, and further developed the data center blueprint to support denser deployments, since potential growth capacity reaching 500 megawatts or beyond is exactly where buyers are headed — not merely addressing short-term electricity needs, but supplying power capable of continuing to expand for years ahead. Regarding permits, we're at the last phase for our remaining environmental approvals. Every one has been filed and is moving forward. That said, the concluding step involving regulators is stretching a few months beyond what we initially expected. For those investing, let me make clear what this signifies: first, the ultimate DEP permitting won't alter our scheduled power delivery under the ESA; second, it won't alter the projected economics for the project; and above all, third, it hasn't decelerated commercial momentum or interest. As of right now, our soonest RFS date remains 2027. And for the clients we're in discussions with, we don't think this will matter. Commercial appetite at Panther Creek is strong, and we think current wider market shifts also favor this location. Given how large the Panther Creek campus is, talks are being driven by big, sophisticated AI firms, and we anticipate that interest from the biggest names will grow once the site achieves execution-ready permitting status. That's how this market works. The larger the counterparty, the more they prize certainty. And each time a permit comes through, Panther Creek turns into something just a small number of locations across America are able to provide — near-term power, at scale, with space to continue expanding for years. Currently, we have several prospective customers in negotiations spanning multiple sites at once. Demand throughout the portfolio greatly surpasses the capacity available for leasing. And these are exactly the counterparties you'd want involved — hyperscalers, top AI companies, GPU cloud, and major enterprise. Though I can't disclose names or specifics, I want you to grasp that competitive tension exists in this process, and our difficulty isn't locating customer demand, but rather selecting from among it. I'd also like to be candid about our approach to signing. Over the last 18 months, we've been extremely clear regarding our commercial time line. We chose not to hurry toward the finish, instead taking time to derisk our sites, cultivate commercial interest, and make sure we lock in the strongest economics we can for our shareholders. A lease isn't a trophy for a press release — it represents a 15-year commitment of infrastructure, credit and trust. And what separates a good lease from a great one amounts to hundreds of millions of dollars across its lifetime. Controlling the bottleneck everyone requires for growth means we negotiate from a position of strength, and we'll concentrate on optimizing across customers, economics and cost of capital. We won't limit the upside of a generational asset just to produce a headline. Our outlook continues to be very positive, and our confidence keeps growing because of how involved and active the tenants are in our commercial process. That level of intensity makes it obvious that our portfolio is positioned exceptionally well to address a broad range of customer problems. Power that is secured and available in 2027, appealing locations, and delivery partners with a proven track record continue to be the differentiators behind every customer discussion we are having. Moving to Slide 9. With that said, I will hand things over to Jonathan so he can go over our Q2 financial results.

Jonathan Mir

executive
#4

Thanks, Ben, and good morning to all of you. Let me begin with one straightforward point that echoes what I said during our Q1 call. Our capitalization right now is stronger than it has ever been in this company's history, and that financial footing provides something extremely valuable in the current market: the capacity to push our sites forward while reducing risk at the speed our customers need, and to make business choices guided by our goal of achieving the strongest long-term risk-adjusted returns for shareholders instead of being forced by a liquidity position under time pressure. I'll go deeper into our capital strategy shortly, but first let me take you through our Q2 results. Please turn to Slide 10. For Q2 2026, we recorded $30 million in revenue, compared with $61 million in Q2 2025. The main drivers behind that decrease were a softer average Bitcoin price and the closure of crypto mining activities at Moses Lake during the quarter. We posted an operating loss of $141 million for the quarter, whereas the prior-year period delivered operating income of $11 million. Within that swing is $63 million in accelerated depreciation related to powering down mining rigs at Panther Creek and Scrubgrass. The combination of Bitcoin's fair value change and realized Bitcoin losses reached $20 million, against a $32 million gain in Q2 2025. Continuing operations gave us a loss of $64 million, which works out to $0.11 per share. That compares to Q2 '25, when continuing operations brought in income of $13 million. For the quarter, adjusted EBITDA came in at negative $24 million, versus $7 million during the same period a year earlier. Operating margins fell because Bitcoin's price was lower, and because we brought on senior subject matter experts, which pushed G&A higher as we grow toward the next phase of our business — stock-based compensation also increased compared with last year. During the first half of 2026, our cash SG&A ran at an average of $23 million each quarter, and right now we expect cash SG&A to reach $100 million for the full year. To repeat, what's fueling the year-over-year increase is mainly the top-tier, carefully chosen senior personnel we brought on to help carry out the commercialization stage of our plan. Between April 1, 2026 and August 7, 2026, this company disposed of 1,085 Bitcoin, generating $75 million in proceeds. Our Bitcoin holdings totaled 1,861 Bitcoin as of August 7, 2026. Our plan, which we've mentioned before, is to sell off our Bitcoin holdings during 2026. Let's move to Slide 11. Next I want to go over a few observations on the capital markets, along with an update on liquidity. During June, we completed a $458 million convertible senior notes offering—larger than the $350 million we initially proposed—thanks to robust investor interest, for which we're very grateful. Because of that interest from investors, we were able to be selective about the parties we invited onto our cap table, and as a result we were glad to bring in a number of strong, long-horizon investors. The response we've gotten from investors has been favorable when it comes to how clearly we've laid out the way this fresh capital will be deployed. This money is not some optional or speculative pool being held in reserve so we can expand power capacity at Panther Creek and Scrubgrass, two of our owned sites that already have their risk taken out. We are not taking on any additional development risk with these proceeds; what we're doing with them is building added power capacity at locations that are already ours. Whenever we need to bring in outside funding, our pledge is to be transparent regarding its purpose and the rationale that the associated risk-adjusted returns over the long run create shareholder value. Taken as a whole, we see the convertible offering as both an endorsement from the market and the very thing that unlocked the following stage of carrying out our strategy, which includes growing the pipeline by adding capacity. Turning to liquidity. As of August 7, total liquidity stood at $819 million, up from the $533 million we reported at the start of May. To say it again, we believe the liquidity we have now can carry site development all the way through lease signing, the opportunity to add expansion capacity, and it completely covers our cash SG&A through 2028. Ahead of taking your questions, I want to share a few thoughts on where capital markets stand, since that directly shapes our approach to financing the buildout of our sites. To start, on the high-yield debt financing at the project level, today's market conditions look workable to us. Yes, spreads have widened, but in our view there's still enough depth to support the sums we'd look to raise, and the returns we'd expect on equity capital are still appealing. Next, securing either a direct investment-grade offtake or a wrap is essential if we're going to land debt financing on efficient terms. When you're lending to a counterparty that isn't investment-grade, the financing costs run considerably steeper and the market doesn't offer as much depth. That said, for the time being at least, the market does have room to provide financing both for investment-grade customers and for certain noninvestment-grade ones. Our view remains that, under those conditions, wrapping a deal around an investment-grade customer with lease terms that hold up over time is the option that serves shareholders best. One more point: because of where our liquidity stood, we were able to assess any capital needs on a post-lease basis, at which point we anticipate our cost of capital coming down. To wrap up, we think today's market backdrop puts us in a strong position to fund construction at every site without friction, and on terms that generate value for our shareholders. Moving on to Slide 12, I'll hand things over to Ben, who has a few final remarks.

Benjamin Gagnon

executive
#5

Thanks, Jonathan. Ahead of taking questions, I'd like to briefly explain the reasoning behind everything Keel is undertaking. Each generation constructs the infrastructure that comes to define it, and that construction always happens prior to the world reaching consensus that it ought to. Railroads, the power grid, highways, the Internet — intelligence belongs to our era. These days, work isn't counted in jewels anymore; tokens are the unit. A token's price may have a limit, yet its worth has none. There's a purpose behind naming this company Keel. What we're building serves as the base layer making the following generation possible. Our aim isn't to rival anybody's AI concepts — we supply the power to those who hold them. Eighteen months back, all of this amounted to nothing more than a thesis for Keel. As of today, we're a business carrying things out in precisely the window we anticipated. Operator, would you please take us to questions?

Gareth Gacetta

analyst
#6

Gareth here, filling in for Brett. I was wondering if you might speak to the sorts of political conditions surrounding data centers throughout the U.S. I realize you said these sorts of projects haven't truly altered the power delivery timeline, nor the commercial momentum with prospective tenants. Still, could you describe how prospective tenants view the regulatory landscape, and what effect that could have on their timing?

Benjamin Gagnon

executive
#7

Sure, glad to, and thank you for asking, Gareth. The regulatory landscape and the political landscape are things we clearly monitor extremely, extremely carefully. Obviously, plenty of headlines are circulating across the U.S. at present involving moratoriums, regulatory measures, and various new frameworks, new policies, or new tariffs being put forward and floated. The way I see it, whenever that occurs in one location, it will boost the worth of other sites that those rules don't touch. And clearly, in a market where growth is occurring so quickly and at such scale, certain markets occasionally require a bit of time to catch up. I'd say one benefit we enjoy in Pennsylvania is that Pennsylvania is somewhat benefiting from the second mover advantage. It certainly wasn't the earliest to step up and begin constructing data centers. Initially, they had far more permits, rules, various steps, and hoops to navigate; therefore, I believe the responses you're witnessing nationwide stem from the enormous surge of data center demand in applications. And I believe Pennsylvania already had a fairly solid framework for large industry, large manufacturers, and very large consumers arriving to build industrial capacity; and I believe it positions us well, and I believe it likely generates some value for Pennsylvania to witness these actions occurring in other locations, since that capacity still has to arrive in the United States. And those are the places where continued opportunity will exist.

Gareth Gacetta

analyst
#8

Great. That's really useful. And perhaps a brief follow-up. Could you discuss the pipeline you have right now? I believe you've locked in roughly 480 megawatts. But might you give us some detail on what portion of that pipeline faces exposure to this application process?

Benjamin Gagnon

executive
#9

We have 2 separate categories of energy. There's our secured capacity, and there's our expansion capacity. At present, every bit of our secured capacity, in our view, remains unaffected so far, and we will keep watching that extremely carefully. Future shifts or future policy consequences could affect the expansion capacity. Yet at this moment, things are going remarkably well when it comes to locking in our expansion capacity. I brought this up briefly during the call. We're engaging with our utilities every single day. Our filings to lock in our expansion capacity, which totals nearly 2 gigawatts throughout the state, are moving along very, very nicely. And we grow more and more confident that we can obtain extra power, and we look forward to providing investors an update as soon as December or January.

Greg Lewis

analyst
#10

I wanted to spend a moment discussing the permitting side of things. You mentioned certain environmental approvals — the i's we need dotted and the t's we need crossed — while you're dealing with your data center clients, so I'm wondering whether there's a parallel track for tackling some of these permitting hurdles. What prompted my question is that we've been told backup power generation, whether diesel or natural gas, often sets off environmental permitting complications, or at least items requiring attention, whereas backup batteries might serve as the answer. I'm just wondering whether that's under consideration in case environmental permitting runs longer, or simply moves more slowly than anticipated?

Benjamin Gagnon

executive
#11

Yes. Thanks, Greg. To respond to that, you're definitely correct that securing environmental permits, particularly for backup generators, can prove difficult. And you can handle that in a number of ways. There are varying levels of generator efficiency and varying levels of emission control quality; as a result, some generators face an easier permitting path, while others face a harder one. It really hinges on the amount you anticipate running those generators and the related emissions across the year. So the same backup generator could be part of a data center project, yet depending on its expected uptime, end up with 2 completely different permits. So the situation is somewhat complex and nuanced. Still, we're constantly trying to identify methods to accelerate and shorten those schedules, particularly when it comes to something such as permitting; therefore we look at every solution available concerning BESS or alternative generator options, aiming to keep that process as fast and as efficient as we can.

Greg Lewis

analyst
#12

All right, that's excellent. Next, Ben, I was hoping you might share some thoughts on Sherbrooke. Now that electricity has, I believe, been brought over to the whole site, or whatever arrangement potential customers make use of it, I suppose that's 9,600 megawatts plus 1 site. From a marketing standpoint for Keel, what does that truly signify?

Benjamin Gagnon

executive
#13

Yes, terrific question, Greg, and I'm glad to discuss the Sherbrooke project. We hold a reasonably sized portfolio in Quebec, and that province is a very captive market. Plenty of legislation exists, both at the Canadian federal level and the Quebec provincial level, that provides really strong incentives for data sovereignty nationally and provincially; yet sadly, obtaining fresh electrical capacity for data centers has proven extremely, extremely difficult. In Quebec, we possess an enormous energy portfolio, though it's specifically approved for Bitcoin mining. The approval we got at Sherbrooke was meant to merge 3 separate Bitcoin mining power purchase agreements we hold into one new single power purchase agreement, expressly for HPC and AI. That single element, the shift in industrial use case, is the major transformation here that lets us genuinely proceed with building an HPC and AI data center, once the provincial minister gives the final sign off. The truth is that since the legislation exists and demand is captive, we believe Canada and Quebec can broadly command a bit of a premium for the very same compute, simply because they are that much more captive and capacity is that much more scarce.

Logan Hennen

analyst
#14

Logan here, filling in for Mike. Ben, to start with, could you give us a formal update on whether Keel is still aiming for 3 leases to be announced in 2026, now that Panther Creek has a longer time line? And perhaps also an update on how demand has shifted over the past 90 days since that target was made public?

Benjamin Gagnon

executive
#15

Yes, glad to address that, Logan; at all 3 of our sites, we remain in active due diligence and negotiations. In my view, the commercial process is going extremely well. At each of our 3 priority sites, we have plenty of very interesting and sticky potential tenants who are working their way through the negotiation process. And I think right now, as we work through the negotiations, we're simply going to keep focusing on working through those negotiations and the multiple parties rather than trying to give a clue or an indication as to where any particular negotiation for any particular site or tenant stands. But we stay incredibly optimistic and confident, given the commercial process so far, given the continued process we have with permitting across all 3 sites, as well as the other background works with the engineers, the supply chains, the fiber contracts — everything continues to move forward. And I think the closer you get to energization date, the more valuable your energy becomes by the day; and so it becomes an easier and easier commercial process when you're working through a 2027 delivery date as opposed to a '28 or 2029. And so that continues to keep us incredibly confident, optimistic, and it also helps to keep our potential tenants very engaged.

Logan Hennen

analyst
#16

Great. Yes, I appreciate that perspective. Then one more question from our side. Could you give us a formal update on the Scrubgrass site — where things stand right now, how it's advancing, and what kind of demand you're seeing for that power in 2028 and beyond?

Benjamin Gagnon

executive
#17

Yes, absolutely. Glad to share an update on Scrubgrass, though there isn't a whole lot of substantive news to report. Scrubgrass is what we refer to as a pipeline site. It's a very exciting campus of more than 1 gigawatt in Western Pennsylvania. That said, at present the Scrubgrass process remains in the energy application stage. We've been coordinating with the local utility on a detailed load study covering 750 megawatts. And as a lot of investors are aware, we've also been working on the pipeline and engineering for a pipeline that would support 550 megawatts of on-site generation using CCGTs, along with an IPP who would step in to deploy the turbines, provide financing, handle operations, and sell the power to the end customer. At this point, we're still working toward securing the power. Until that power is secured and we have a firm, final understanding of how large the site will be and by when, we aren't doing the engineering work to build out the data centers or planning them out. We haven't filed any permits or submitted any proposals so far. Our focus is really on securing the power and working through what we call a mass grading plan and a kind of site campus layout plan, so that once the power gets approved, we'll know where we want to put buildings, how we want to construct them, the size of the buildings, how many there will be, the cadence, and that sort of thing. But at this point, it's still really in the energy application phase, and we ought to be in a position to give investors an update as soon as December or January.

Michael Donovan

analyst
#18

Regarding Sharon, I was hoping we might go over the timing for RFS. Do you still anticipate 30 megawatts for that initial data center, followed by an expansion of 80 megawatts?

Benjamin Gagnon

executive
#19

Well, Mike, that's something we've been focused on, and we've also been focused on the question of how to shorten our schedules to the greatest extent we can; plus, how to boost our power density. At this moment, we haven't made an update, though we're exploring options to squeeze it down to a single 110-megawatt phase.

Michael Donovan

analyst
#20

All right, that's useful. So regarding Moses Lake, can we still add another 10 megawatts there?

Benjamin Gagnon

executive
#21

No, that possibility has been dropped. Right now our attention is solely on the 18 megawatts at Moses Lake, and we have let that option go.

Bill Papanastasiou

analyst
#22

Could we take a closer look at the environmental permitting process? With the recent political headwinds around building data center capacity, are you noticing a higher bar being set? And to be more specific, how would you rate the odds of getting environmental permitting approvals now compared with earlier quarters?

Benjamin Gagnon

executive
#23

Thanks, Bill. Sure, glad to go into that a bit. Really, when you look at our permits for Sharon and Panther Creek, the permits are basically identical at the two facilities. They're all environmental. Most of it relates to sewage, and that's a fairly standard permit to apply for and receive. It isn't one that usually attracts controversy, and the same goes for the ground-related items. So erosion, water, storm water — that's essentially what the remaining permits cover. So these are engineering-driven. As I said, they typically aren't politically sensitive or subject to much opinion. It's really just the engineering work. One thing we've brought up on earlier calls — I think people have asked about how we work with the OTO, Pennsylvania's Fast Track Office, so Governor Shapiro has a fast track office for permitting. That's actually operated out of the DEP, since the DEP is well known for taking the longest line item in the permitting process. And that's actually divided into 2 departments. There's a Eastern DEP and there's a Western DEP, and the Eastern DEP is the one that tends to be a bit more overworked and takes a bit longer to go through the permitting process than the Western one. So it's really just a matter of working through the backlogs. But this is a well-known — these are pretty standard permits. This is a well-known process, and we remain incredibly confident, most confident we've ever been on completing our permits for both Panther Creek and Sharon today.

Bill Papanastasiou

analyst
#24

I appreciate that. Ben, my apologies if somebody already brought this up, but regarding the conditional approval for Panther Creek, which conditions come with it?

Benjamin Gagnon

executive
#25

Naming every single condition would be impossible, but to offer a few illustrations, a conditional approval might involve something such as adjusting your setbacks, or perhaps lowering the height to 60 from 62, or something along those lines. These tend to be fairly standard suggestions. They're extremely specific. Typically they're highly numeric in nature, and the form is either make these recommendations, or put these systems in place, or meet these conditions. Complying with them isn't difficult. What really helps about receiving that conditional approval is that it functions as a really clear checklist covering all the items you must complete, allowing that conditional status to be removed and leaving you completely permitted. So it amounts to a really clear prescription, or recipe, or whatever framing you prefer, for reaching that point. If they had no interest in getting you approved, they would never hand you such a clear road map toward success.

Bill Papanastasiou

analyst
#26

Got it. Then earlier, someone had asked about Quebec. Could you discuss that possibility? How mature is the sovereign AI sector in that province? And in what ways do you expect Keel to take advantage of it?

Benjamin Gagnon

executive
#27

Sure. We have had conversations with quite a few industry experts, particularly within the province; our view is that rates across Canada tend to be above those seen in the United States, though pinning down a specific number is difficult. Still, broadly, they are higher; and we observe that our company stands to gain some appealing diversification advantages; there is that U.S./Canada mix; in Canada, for instance, there is no need to be concerned about regulatory shifts around tariffs and similar matters, all of which can affect what a data center costs. So our sense is that building in Canada may be less expensive than building in the United States, and we also believe the market there might be valued above what it is in the United States. What makes Canada difficult is the very same difficulty we have always faced there. Growing organically in that market is simply very tough. Consequently, if your goal is to reach 1 gigawatt of growth within Canada, that is likely an extremely, extremely, extremely tall order and a far taller order than reaching 1 gigawatt at a campus such as Scrubgrass in Pennsylvania. Yet with the power capacity available to us, we are confident that by pushing through to secure that approval, by moving ahead to ensure we hold a clear path, every permit, and all the backing required and locked in for us to build a data center, we can produce fairly appealing yields within Canada.

Stephen Glagola

analyst
#28

Ben, when it comes to the August 20 Department of Environmental Protection meeting for Panther Creek, how should investors weigh what that gathering means, and which major rulings or benchmarks ought to result from it?

Benjamin Gagnon

executive
#29

That meeting is quite ordinary. You shouldn't view it as something exceptional or one of a kind. It's simply one more standard meeting.

Stephen Glagola

analyst
#30

Okay. All right. Good to know. I suppose a broader question for you would be this: as you assess potential tenants, how much does your read on the long-term model or the landscape shape whether you're willing to partner with a given AI lab?

Benjamin Gagnon

executive
#31

That's a really interesting question, and honestly it's something we spend a lot of time on, since the market is shifting so fast. In fact, just last week, we were discussing how the whole company, Keel, has adopted Claude for our enterprise AI solution, yet 12 months ago, not one of us was using Anthropic — we were all on ChatGPT — and now everything has flipped. So I think that model — or rather, I think the market will keep changing and adjusting. In this market, the incentive is extremely high. Plenty of people are aiming to push for the top, and we do expect it will keep changing. Our view is that Anthropic has carved out a nice niche in the enterprise market, which is the one we've consistently identified as the one that will truly drive this industry forward, as opposed to retail — it's going to be enterprise consumers — and maybe they build a bit of a moat here. But we're going to try to remain as agnostic as we can when it comes to the models, because as we've said previously, a lease isn't really a trophy for a press release, it's a 15-year commitment. And the gap between a good one and a bad one comes to hundreds of millions of dollars. We're not in this for the company that can only pay their rents for 1 year, right? We're in this to find the companies that will be able to give us long-term contracted, predictable revenue for 1 to 2 decades.

Nick Giles

analyst
#32

There have already been quite a few solid questions. So I just wanted to step back and ask you, Ben, what would you say are really among the largest risks right now? It sounds like you've made headway when it comes to the supply chain, but I'm wondering whether there's any additional mitigation work you could still do there?

Benjamin Gagnon

executive
#33

Thanks, Nick. Probably the single largest risk right now is simply the wider macro picture. The truth is that power for 2027 remains in very short supply on the market. And our position is quite strong, since we still hold a very sensible quantity of leasable capacity for 2027. So on the whole, I'd say that keeps a great many of our — well, in fact it keeps every one of our prospective tenants deeply engaged; it makes them extremely sticky. Every one of them is trying to solve the very same deployment challenges. And that gives us a genuinely powerful edge, thanks to holding that 2027 power that everybody is so intent on delivering. I'd say the wider market is likely the thing we monitor most closely: how our capital markets are evolving and shifting, how financing options for the market are shifting, what's going on with interest rates and the broader risk-on, risk-off mood, how the market is digesting the growing volume of intercompany financing we're seeing throughout the industry? Those, I'd say, are the items that truly represent the larger risk factors for the business; and luckily, they're items that the whole industry confronts in equal measure. But since we hold that 2027 power that's in such high demand, we feel extremely confident about our portfolio and about pushing ahead with the commercial processes for each of our sites.

Nick Giles

analyst
#34

Nice, that's encouraging to hear. Then, regarding CapEx, I was wondering whether you might have a rough idea of how that could ultimately turn out. Also, is there some kind of development cost figure or a specific yield-to-cost threshold you aim to hit whenever you sign something?

Jonathan Mir

executive
#35

Jonathan here. I appreciate the question, and it's good to speak with you this morning. Our guidance remains that, for your own modeling, you should apply the industry-average rule of thumb that you'd likely come across in equity research when it comes to construction costs and yield on costs, and that ought to serve you well.

Nick Giles

analyst
#36

That's reasonable. I appreciate it, Jonathan. Then, if I may, just one additional question. I believe every one of the BTC sites has now been decommissioned, so should we truly be taking revenues down to zero for the rest of the year?

Jonathan Mir

executive
#37

At the start of the year, we stated clearly through our liquidity forecast that we were not counting on any cash coming in from BTC in any of our forecasting. As a practical matter, we still have rigs operating up in Canada. They might deliver 2 or 3 Bitcoin each day. But once again, everything we've said regarding liquidity and projected liquidity takes as a given that no cash will come from the Bitcoin business across the year.

Martin Toner

analyst
#38

Nice work on the advancement. I'd like to ask about scheduling. Given that Panther Creek — your flagship, or crown jewel, property, to avoid putting words in your mouth — has slipped, probably in comparison with the rest. In your view, how does that affect when deals get announced? In other words, could a tenant be after all 3, meaning signing would take somewhat more time? Or which do you expect to move first?

Benjamin Gagnon

executive
#39

Thank you, Martin. There's — internally we even run a betting pool on which location moves first, yet nailing down precisely where things will end up is truly, truly difficult. You can't fully see what's happening behind the scenes with any given customer. Broadly, their level of aggression will match how strong their own forward demand pipeline is; thus they'll push hard based on whatever is particular to them. On the question of when Moses, Sharon, and Panther Creek move, and whether 1 prospective tenant might want all 3, well, I can say for certain that multiple tenants are interested in all 3 sites. That said, it doesn't follow that this is the way we'd like to handle the process, or the way we'd necessarily like to construct our portfolio. Our preference is to try to have tenants concentrate on separate sites, have them zero in on a single site they can take down, and afterward explore how they might create a potential growth pipeline alongside us past that initial asset. So a great deal of what — a great many of the tenants we've spoken with lately aren't merely seeking an asset; they're seeking a development partner they can keep scaling with in a predictable way over time. That's why so many of these discussions revolve around how we move ahead with Moses Lake first, yet then also how we commit to a second site or ongoing expansion in '28 and '29 alongside you. The same holds for Sharon, and the same holds for Panther Creek. Whether that has any bearing on Panther Creek's schedule isn't clear at present, since the commercial process remains extremely active and no one appears fazed. So long as our RFS date stays at 2027, I don't expect any effect on our commercial process.

Martin Toner

analyst
#40

That's quite useful. Has the RFS date in 2027 shifted at all for any site?

Benjamin Gagnon

executive
#41

With Panther Creek, it's always been the close of '27, and Sharon is the same, close of '27. So I don't think we would delay anything in Pennsylvania. Moses Lake, I believe, has slipped by perhaps a couple of months versus the guidance we originally gave, though it remains the first location we anticipate being online next year.

Brian Dobson

analyst
#42

When you look at what you own, where do you want to put more money or grow the things you already have? And are there particular regions you prefer over others right now?

Benjamin Gagnon

executive
#43

Thanks, Brian. That's a really good question, since we're thinking about how to keep growing what we have in development past '27, through '28, '29 and 2030. We still take a worldwide perspective, but I'd say we lean strongly toward the East Coast — particularly the U.S. Northeast and the Midwest. In our view, those regions offer enormous energy resources and enormous inference potential over the coming couple of years, and they'll probably be where the biggest chances for HPC and AI infrastructure build-out show up. That said, it's early days. There will always be fantastic opportunities in other places, and we definitely won't shut ourselves off from those fantastic opportunities. Still, I'd say that's broadly where our attention will be.

Brian Dobson

analyst
#44

All right. So over the last few weeks, I suppose you've had governors out of New York and Texas, I guess, casting — placing a higher degree of scrutiny on data centers. Do you figure this could be something that starts showing up in other key energy areas? And when all is said and done, do you figure it works in favor of proven operators such as your company?

Benjamin Gagnon

executive
#45

Appreciate it, Brian. What's happening at present, or the currents at present, suggest we're likely to get a handful of additional headlines along these lines over the next several months. In our opinion, Pennsylvania is a genuinely, genuinely distinctive centrist state. This state is extremely, extremely concentrated on energy and heavy industry; within the big cities it's extremely, extremely blue, and outside of those it's extremely red. So if you consider Governor Shapiro and, in a sense, the way politics work in Pennsylvania, they truly embody a quite distinctive sort of centrist stance for the United States nowadays; in my opinion it's among the least polarizing states when it comes to politics, since they understand they have to strike a balance between the trades, the industry, the energy, all those kinds of job opportunities, which is what propels Pennsylvania, and the other worries coming from the opposite side. So we believe Pennsylvania is a fantastic location to be in; we believe that should states choose to shut themselves off from the finest economic chance for development seen in decades, and possibly for the next 2 decades, then in our view that's quite shortsighted, since if you examine what a single one of these data center investments delivers for communities, for revenues, for job opportunities, for tax budgets, for the schools and for the roads and so forth, these things are transformative for the communities we're putting money into; and we believe they're extremely, extremely enthusiastic about the projects as a result of those investments, because someone is genuinely trying to do that. So we consider it quite shortsighted, but we'll likely keep seeing a handful more; and broadly speaking, we believe Pennsylvania sits in a sweet spot.

Benjamin Gagnon

executive
#46

I appreciate everyone being here today, and I want to thank the whole Keel team — what they accomplished this quarter says more than any words I've offered on this call. We'll be back in November with additional things to share. Thanks.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Keel Infrastructure Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Keel Infrastructure Corp. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Keel Infrastructure Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.