Kinross Gold Corporation (K) Earnings Call Transcript & Summary
February 13, 2023
Earnings Call Speaker Segments
Operator
operatorHello, and thank you for standing by. My name is Regina, and I will be your conference operator today. At this time, I would like to welcome everyone to the Great Bear project update. [Operator Instructions] I would now like to turn the conference over to Victoria Barrington, Senior Director of Communications. Please go ahead.
Victoria Barrington
executiveThank you, operator. Good morning, everyone, and thanks for joining us today. Please be advised that this presentation contains forward-looking information about expected future events and outcomes related to the Great Bear project. For a complete discussion of the risks and uncertainties, which may lead to actual results differing from estimates contained in our forward-looking information, please today refer to Page 2 of this presentation, the cautionary statement in our Great Bear news release dated today, February 13, 2023, and the risk factors in our most recently filed AIF, all of which are available on our website, www.kinross.com. Joining us on the call today are Paul Rollinson, President and CEO; Ned Jalil, Chief Technical Officer; Nicos Pfeiffer, VP of Geology; Graham Long, VP of Greenfields Exploration. And with that, I'll now turn the call over to Paul.
J. Rollinson
executiveThanks, Victoria. Before we get started, I'd like to respectfully acknowledge the indigenous lands of Wabauskang and Lac Seul on whose traditional territories, the project is located. Thank you all for joining us today. I'll provide a few opening remarks about today's exciting milestone and then turn it over to our technical team. I would also like to point out that today, along with the press release, we have filed a voluntary technical report focused on geology and metallurgy. We closed the acquisition of Great Bear on February 24 of last year. And at that time, we had high confidence that this property would become a world-class mine. In the 1 year we have owned the property, we have made excellent progress on drilling out this world-class deposit and releasing a substantial initial resource. Today, we are even more excited and confident about the project than we were at the time we closed the acquisition. The drilling results have continued to prove out our thesis that the project could host a multi-decade high-grade open pit and underground mining complex. On our Q3 earnings call, I highlighted one specific hole that I thought was particularly exciting as it demonstrated the mineralization we were encountering at depth. That whole inter-sector mineralization at a vertical depth of 700 meters. We now have a drill intersection at a vertical depth of approximately 1.3 kilometers. With that, I'll now turn the call over to Ned and his team.
Ned Jalil
executiveThanks, Paul. Our focus in 2022 was drilling out the first 500 meters of the LP zone in order to confirm our thesis of a high-grade open pit and underground mine. We drilled over 225 kilometers, which when you combine with drilling completed by Great Bear Resources brings the total drilling on the project to more than 560 kilometers. The results are spectacular. Within 12 months, we have declared a 5 million ounce resource, 2.7 million ounces of indicated and 2.3 million ounces of inferred. This validates our view that the LP zone can host a long-life, high-grade open pit and underground mine. In addition to the diamond drilling, we drilled 35 kilometers of grade control. This is a practice that is common just before production. Nevertheless, we decided to bring this forward because this drilling is at a tighter spacing and provides a larger sample size, which increases our confidence in the resource model. The grade control drilling has confirmed our expectation that the abundant visible gold will potentially generate a positive reconciliation. We also have developed a lithology model and a structural model, which has informed the estimation domains and led to a deeper understanding of the mineral resource. This work has given us the confidence to release a voluntary technical report with a focus on geology and metallurgy. We've done more work than is typical at this stage. Furthermore, to confirm our hypothesis at depth, we drilled 1 kilometer plus deep holes, which intersected mineralization. I would like to share with you that last week, one of our deepest tolls had visible gold at a depth of 1,280 meters below surface. We're very pleased with the robust resource estimate. I would like to point out that this resource includes 140,000 ounces from Hinge and Limb. The resource was run at 1,700 gold price, which is what we are using for resources this year. But it's important to point out that we have selected a $1,400 pit shell. We ran pit shell optimization and underground stope shape optimization. The open pit resource cutoff is 0.5 gram per tonne, while the underground cutoff is 2.3 grams per tonne. This high-grade underground and open pit resource is only based on the top 500 meters of the LP. Furthermore, the mineralization comes to surface, directly below the overburden, making it easy for us to access the high-grade material at the start of the pit. This open pit has the potential to be one of Canada's highest-grade open pits, which again continues to support our view that the LP zone is expected to host a long-life, high-grade open pit and underground mine. As we presented earlier, the resource was developed using a 1,700 gold price, which translates to a 0.5 gram per tonne cutoff grade for the open pit material and 2.3 gram per tonne cutoff grade for the underground. What is even more exciting for us is that most of the resource is high-grade material. We have this high-grade core. If we raise the cutoff grade for the open pit from 0.5 grams per tonne to 0.9 grams per tonne, we get 3 million ounces at an average grade of 3.5 grams per tonne. Also, if we raise the cutoff grade for the underground from 2.3 gram per tonne to 3.5 grams per tonne, we get 1.1 million ounces at an average grade of 6 grams per ton. This resource, the high-grade resource of 4 million ounces will potentially be the source of mill feed for the first 8 years of the project life at an average grade of 4.2 grams per tonne. We have not completed the studies yet, but assuming a potential 10,000 tonne per day mill with a feed grade of 4.2 grams per tonne and a recovery of 95%, one can see how this will potentially generate between 450,000 ounces to 500,000 ounces per year. Now thinking about the future, as Nicos and Graham will show, the deposit is open at depth. As we go underground with the exploration decline and continue to grow the resource, we see the first 10 years of the open pit and underground complex transitioning to a large, high tonnage underground mine going forward. To visually demonstrate to you what I just covered, please look at these figures. On the left-hand side, you can see the block model with material above 0.9 grams per tonne in red and the low-grade material in blue. On the right-hand side, you see the high-grade material only, the 0.9 gram per tonne and above. See how the high-grade core hangs very well together and how the low-grade material occurs around it. This low-grade material will potentially be able to segregate and stockpile. Now let's talk about the resiliency of the pit to changes in gold price. As I mentioned earlier, this resource was based on a 1,700 gold price. Nevertheless, we have conservatively selected the 1,400 pit shell. If you look at the figure on the right, at a higher cutoff grade of 0.9 gram per tonne, even higher than a potential reserve cutoff grade, most of the resource remain intact and yields 3 million ounces at an average grade of 3.5 grams per tonne. Our intention is to continue expanding the high-grade underground over time, which, combined with the high-grade open pit will provide the blended feed to the mill. Now I pass it over to Nicos.
Nicos Pfeiffer
executiveThank you, Ned. At the LP zone, we see a robust underground resource that complements the open pit. The deposit is characterized by wide mineralization and stacked lenses with exceptionally competent rock. With an average stope width of 6 meters and parallel panels, we envision high productivity, low development intensity mining. We see the initial resource as just the beginning at this project. We have drilled a series of holes below the resource and see mineralization extending to depth in high-grade northwest plunging shoots. Holes like BR-579, which was drilled last quarter and intersected 25 meters of 15.5 grams highlight the tremendous potential of these shoots sitting immediately below the LP resource. These initial drill holes have extended mineralization to depth of more than 1 kilometer vertically and will continue to be followed up throughout 2023 and 2024. You can see here a view of our resource constrained by a pit optimization and [ MSO stope shapes ] as well as the design for an exploration decline we intend to begin developing next year. The decline will facilitate more efficient exploration of the depth extensions of our deposits and enable continued resource growth at LP, Hinge and Limb. While this decline is advancing, we will continue to conduct deep exploration, resource development and regional exploration from surface. I'll now pass the call over to Graham.
Graham Long
executiveThank you, Nicos. Our extensive 2022 drill program has demonstrated that our geological and structural analogy to the Hemlo Gold deposit is reasonably accurate. With the strong deformation corridor hosting mineralization continuing along strike and developing high-grade shoots that extended depth. Mineralization starts its surface for all of the zones. When comparing the 2 deposits, our drilling has shown that the LP zone is more robust from surface down to 500 meters and at the broad and high-grade mineralization we are seeing at depth potentially with coalesce as seen at Hemlo and many other mines of orogenic nature. The land package has potentially significant prospectivity with roughly 20% of the 91 square kilometer property having been explored to date. Our 2023 drill program is intended to grow the inferred resource category to depths up to 1 kilometer while simultaneously carrying out condemnation and exploration programs as we look to place future infrastructure and head for the next ore body. Key exploration target areas will be the strike extent of the LP zone, and then as deep drilling will have us position drill collars further to the Northeast, we will be testing the stratigraphy for potential parallel zones. Unlike the LP zone area, the portion of the property hosting the Hinge and Limb deposits are underlying predominantly by the [indiscernible] and interflow sentiments similar to the units hosting the Red Lake Gold Mines. Detailed airborne magnetic geophysics shows us that there are numerous targets that resemble the Hinge and Limb structures that remain to be tested.
Ned Jalil
executiveThanks, Graham. The network also shows favorable results. The initial test work indicates a recovery of approximately 95% with no indications of deleterious elements. Furthermore, with abundant visible gold found in the LP zone as well as the Hinge and Limb, our expectations are for high recoveries. Within that, another positive is that we expect 40% to 50% of the recovery be by gravity. Our overall schedule for Great Bear is driven and subject to the permitting process. Our estimated time lines are in line with comparable Canadian projects. Environmental baseline activities are progressing well, and we plan to begin preparing the impact statement later this year. We are continuing to target start-up production in 2029 with the potential for 2028 in the event the permits are received quickly. With that, I will hand it back to Paul.
J. Rollinson
executiveThanks, Doug. We are extremely pleased with the initial resource estimate and believe the best is still to come. We are targeting releasing the first details regarding mine plans and economics with the upcoming study results in 2024. In closing, let me say we are committed to developing this project through a genuine partnership with the Wabauskang and Lac Seul First Nations and with full respect for their values and traditions. Thank you all for joining us today. Operator, we would now like to open up the line for questions.
Operator
operator[Operator Instructions] Our first question will come from the line of Anita Soni with CIBC World Markets.
Anita Soni
analystCan you hear me.
J. Rollinson
executiveYes, we can hear you, Anita.
Anita Soni
analystOkay. I just have a few questions, and I'll pass it off. So firstly, in terms of a little confused on the presentation between the elevated cutoff grade and the baseline. So the baseline is done at $1,700 gold, right? And then the elevated cutoff grade that was done at -- I think Chris was telling you around $900 per ounce. Can you just explain to me the material that falls off because that used a very high gold -- sorry, very low gold price there. Why is it included in the resource estimate. Why wouldn't you just not bother going after that material? Because it seems like it's 0.6 gram per tonne material in the open pit, and it's only 300,000 ounces. It doesn't seem like it's worth bothering [indiscernible].
Ned Jalil
executiveThanks, Anita. As you know, we -- as I mentioned on the call, for this year, we are using $1,700 for declaration of the resource. And as the standard practice in the industry is that you report everything above the cutoff grade that the $1,700 gold translates to. As such, the material that's in the low grade bin has to be reported. That being said, I wouldn't discount completely the material. The material is part of the open pit. We're going to go through it anyways. We're going to mine it, whether we mind it as waste, low grade. It doesn't really matter. We're going to mine that material. So the proposal or the vision for this would be to stockpile that material as low grade and whether it's 0.6 or 0.7, that material could supplement mill feed in the future of the deposits, say, in the next 10 years of the project as a supplement to the, for example, high-grade underground feed that would come from an underground-only mine at that point.
Anita Soni
analystOkay. Second question, as I look at the resources that have been delivered in the open pit, and there's a gray area in some of the -- sorry, the brown area on the sum -- in the slide. Is that what you indicated resource shell is going to look like and the mineralization that's at the bottom. That's what's going to be mined out eventually? And if so, could you just kind of give us an indication if the strip ratios are still coming in at 6 to 8:1 as you had previously indicated, I think, in June.
Ned Jalil
executiveDo you want to take that, Nicos?
Nicos Pfeiffer
executiveSure. it. Yes. So what you see the brown area there, that's our LG shell. So that's our actual resource pit shell. And then the material sitting directly below that, those are resource stope shapes. So those are actually MSO stope shapes that we run to constrain the underground resource. With respect to the strip ratio, I can pass that over to Ned.
Ned Jalil
executiveYes. Did we answer your first question, Anita, I guess just to confirm.
Anita Soni
analystYes, I was waiting for the strip after.
Nicos Pfeiffer
executiveOkay. Okay. Yes. So the strip ratio for the overall resource is approximately 7% as the number within the range you mentioned. But as you know, as we start doing mine planning work in the next phase of studies, we will optimize this in the sense that the starter pit and the first couple of pushbacks will have a significantly lower strip ratio. But the overall strip ratio for the resource, for that pit shape that you see is the you've asked about.
Anita Soni
analystOkay. Second to last question, the dilution that I should be considering when I move these resources to reserves in my model in the open pit is like a 5% to 10% level fare and in the underground a 20% level fare? Is that?
Nicos Pfeiffer
executiveSo with the -- this is Nicos again. With the open pit, we reblock the model, so we actually have a 10x 5x10 block model informing that resource. So there is some amount of dilution already considered in those underlying numbers. And then with the underground, there's a minimum stope with of 2.5 meters. So we forced our stopes to be at least 2.5 meters wide, which is incorporating some dilution. So I would guide you to go lower on your dilution figures.
Anita Soni
analystOkay. So I think you mentioned stope with a 6 -- you said 2.5% minimum, but it was 6 by something that I noted that you guys.
Nicos Pfeiffer
executiveYes. The average stope width is 6 meters, and we have stopes above 20 meters. So we're thinking about a pretty high productivity underground set up here. We've got multiple panels running parallel to each other. So imagine what that will do from development intensity and just tonnes generated from the underground.
Anita Soni
analystAnd the last question... I think you threw out the 4.2 gram per tonne material at 10 [indiscernible] tonne per day, that's how you get to the 450 to 500 . Can you sort of give us an idea of how many years of pit at what grade do you envision? And then how many years have underground at what grade do you envision?
J. Rollinson
executiveAnita, at this point, this -- we haven't completed our studies. We're actually just kicking off the study work. So we don't have the details between an open pit and an underground split that one would put in an economic model. That being said, back of the envelope calculation, you look at the 3 million ounces in the pit, right? And you look at the 1 million ounces in the underground as high grade. We have access to both materials at the potential start of a mine because we're driving this advanced exploration decline early in the project. As such, we have access to high-grade material from underground and a high-grade material from the pit. Now to bring to your attention, this average grade for the 3 million ounces that you see in the presentation, we have the potential, as we start the detailed my planning work as part of the next coming phases of studies to elevate even that average grade higher in the early years. But as a back of the envelope calculation, we provided you with a chart so you can model the first 8, 10 years of the mine life.
Anita Soni
analystOkay. And I lied, one last question. And this is more of a corporate question. You're using 17 for your resources. Is it fair to say that the rest of the assets will be done at 17 this year?
J. Rollinson
executiveYes.
Anita Soni
analystOkay. And similarly, the reserves were, I would guess 14 then?
Ned Jalil
executiveYes, we're jumping the gun a little bit. We'll talk a little bit more about that later in the.
Anita Soni
analystI know I'm getting questions why are you seeing 17 for you versus the 16 last year.
Operator
operatorYour next question will come from the line of Greg Barnes with TD Securities.
Greg Barnes
analystJust on the -- your evolution of your thinking around how you developed this. I know last year, we were talking to 15,000 tonnes a day, biasing towards the higher end of that blending grade, stockpiling. It seems like you've moved away from that lower tonnage, higher grades. Is that where you're thinking has gone, yes?
J. Rollinson
executiveYes. I think as one go through the drilling, which is the first phase of a project and starts with the initial resource, which we're doing right here, you go through multiple phases of back-of-envelope calculations. What we see today with this high-grade resource, we don't see the need to go for a larger mill. Again, we have not completed our studies yet. As such, we will go through that in the next phases of defining what is the optimum pit size, what is the underground? Where does it start? And what is -- and we zoom in and lock in the mill size. But with what we know today, a 10,000 tonne per day mill with the grades we're feeding is very attractive for this deposit.
Graham Long
executiveI think the other thing, Ned, though, which is we have the advantage here of really the time to really design this in a way that we have the flexibility. Our sort of cardinal rule here is never to build a mill that we'll be struggling to fill because ultimately, this will be a longer life underground. And so we're trying to optimize the economics in the early years with the open pit, which makes you want to have a bigger mill, but we're mindful of the longer-term underground and not having an oversized mill. We've seen that many times where people struggle to keep the mill full, and it really hurts you on the economics. So we're balancing the 2.
Greg Barnes
analystYes. Okay. That makes sense. And I think, again, when we talked about this last summer, there was a fairly significant percentage of stockpiling going on of this lower grade material for later in the mine life and then you blend it through. It sounds like that's still part of the plan, but perhaps less so.
Graham Long
executiveWell, I think, I mean, Ned, I would say, that Nicos, based on what we're talking about today, preliminary, you've probably got a minimum of 10 years of stockpile that we'd be able to work with as we transition underground, minimum. So we've got lots of comfort as we think about the future and the transition from the open pit to the underground, both with the stockpile and just how we build that mill and our flexibility on if we wanted to even potentially derating it at some point in the future if we wanted to go from 10 to 8 or something like that. So I think we've got 2 levers to pull there.
Operator
operatorYour next question comes from the line of Jackie Przybylowski with BMO Capital Markets.
Jackie Przybylowski
analystI think most of my questions have been answered, but maybe I'll just ask if you could just take a step back and maybe from a high level, talk about how you see this property over time. I know you've sort of alluded to it. You've got the starter pit, you've got an open pit and then a longer life underground. But can you maybe walk through how the different deposits maybe fit into that overall plan, at least as far as you're thinking right now, [ Nicos ]?
Nicos Pfeiffer
executiveYes, I think you got it there. If I guess, if you go to the cross section, you can see that.
Ned Jalil
executiveThe decline.
Nicos Pfeiffer
executiveSlide 10. To Slide 10. You can see there are multiple zones in the mineralization. So the pit focuses on these zones. And then you can see on the slide after Slide 11, you can see the exploration decline, which we are planning on driving next year or starting to drive next year. That goes underground to enable us to access both the LP zone and the Hinge and Limb zone. So you have the pit covering the LP zone. You have the underground decline covering both the LP Zone and the Hinge and Limb. And all of this material will potentially be sources of ore in the future of this project. Again, we would like typical for these deposits, you start with a pit. The pit starts with a starter pit, you phase it out several pushbacks to optimize strip ratio over the life of the mine. And you go from that into blending it with underground material. And then at one point in the future, say, with what we know today, 10 years -- after 10 years of the initial life, you transition to an underground-only complex. And given what we see of LP, we see it as a potentially high tonnage underground mine similar to the analogy we did with Hemlo, for example.
Jackie Przybylowski
analystAnd in terms of the underground, is it LP is going to be like the initial source of underground? Like how does Hinge and Limb fit into the plan? Are they going to be starting concurrently with LP for underground or later or earlier?
Graham Long
executiveYes. Like, again, one answers these questions when you have a detailed mine plan, which we don't. We're going to start this work -- we're going to commence this work this year. And like what Paul mentioned, we'll release next year, the early view of economics, mine filing and as such. But I can tell you just knowing the mineralization. Hinge and Limb is a Red Lake style [ inertization ]. It's high grade. While LP is orogenic similar to Hemlo, it's high tonnage. So we have access to both at the beginning of the mine life. We don't have a mine plan. I don't have a mine plan, but just from experience, what I would say is that potentially, one would go after the high-grade open pit in the starter pit, blended with high-grade stopes from the underground, whether it's Hinge and Limb or LP, feeding the mill with the highest grade in the first couple of years to pay back capital and have a great IRR.
Jackie Przybylowski
analystOkay. No, I appreciate that. I know this is all very early stage. I appreciate any color you can give. I'm just trying to get my head around the sequence of events.
Operator
operatorYour next question comes from the line of Carey MacRury with Canaccord Genuity.
Carey MacRury
analystJust a question on the 2024 PEA. And I guess my question is really how many meters are you planning to drill this year? And is that PEA going to be based on this resource? Or should we expect a resource update sort of in the interim prior to the PEA.
J. Rollinson
executiveYes. So we're forecasting about 180,000 meters of drilling this year, and that will inform our PEA in '24.
Carey MacRury
analystOkay. Great. And then maybe just on the underground, now that you're obviously getting good results there. Can you just remind us what you're thinking of there in terms of like tonnes per day from the underground potentially?
Ned Jalil
executiveAgain, Carey, we haven't done the studies, but knowing the -- seeing the mineralization that we see today and seeing the width and the shape of the deposit at the LP especially, it's high tonnage. If I would say a number very early today, I would see something in the range of 6,000 to 8,000 tonne per day underground.
Operator
operatorYour next question will come from the line of Mike Parkin with National Bank Financial.
Michael Parkin
analystI know again it's kind of preliminary, but is the thought process of balancing the mill, do you be better kind of situated with the future of the underground. Is that a bit of an insight that you -- and you've kind of alluded to, I think, a bit that you see potentially more ounces in the underground than you do at the pits.
Nicos Pfeiffer
executiveWell, let me jump in. Yes, it's a good question, Mike. I mean we think we've defined pretty clearly the first 500 meters, and we see our mind right there. We've modeled it out in terms of the pit shells. Our thesis, the Hemlo thesis is that this is orogenic. And as you may recall, Hemlo went down over 2 kilometers. And we've been piercing now the mineralization where we expect it to be down to 1.3 kilometers. So I don't think we can just keep doubling sort of the ounces contained as we go from 500 meters to a kilometer to 1.5 kilometers. There will be some -- as you know, we're ounces can kind of be what you want depending upon the cutoff grade. But as we move to pure underground, the cutoff grades will come up, we'll be focused on a higher grade mine scenario. So it's not a linear kind of doubling of open pit as you go down another 500 meters. But yes, I do think based on that expectation, we probably have a longer life underground than we will open pit. So we're thinking about all of that and retaining flexibility.
Michael Parkin
analystOkay. Now it's kind of a big ask to answer that question at this point. But -- and then that's a pretty impressive drill program budgeted for this year. Is that going to be a bit more focused on that 500 to 1,000 meter level or is it balance of that plus a long strike extensions as well. As you've kind of noted you've already pretty well defined that first 500 meters.
Nicos Pfeiffer
executiveI'll just start and hand off of Graham, who's I must say, has done an excellent job of running the drill program this year. It's really been like run like a Swiss clock. I mean we had excellent execution to get the drilling done and to achieve what we did within the year. So that was a huge accomplishment. The only thing I would point out, and I'll turn it over to Graham is just to remind, these 1-kilometer pierce points, those are pretty -- to get to 1 kilometer, you got to drill about 1.5 kilometers. These are deep long holes that take over a month to drill. So the rate of access as we go deeper just becomes slower. So our strategy, which I'll turn over to Graham, is to contemplate some of that, but also along the property.
Graham Long
executiveYes. So exactly, Mike, it's broken up into different bins, if you will. So right now, we have 8 drills on the property. We'll probably ramp up to 12, and we're going to be hitting different areas at the same time. So we still have about 15,000 meters of pit infill to bring that all into indicated. And then we'll have roughly 20 kilometers of work planned to do condemnation because the engineers are waiting for us to condemn areas so that they can start planning infrastructure. But that's also exploration as well. We're placing those condemnation holes in areas where we want to see more about the lithology. And then in terms of pure exploration, we have about 20 kilometers planned and that's strike extents on the LP parallel zones and the Hinge and Limb area, the Red Lake style mineralization, where we see a lot of geophysics signatures that have to be drill tested. So they look exactly like the Hinge and the Limb. And then the majority of the drill program is going to be that 500 meter to 1 kilometer depth, inferred drilling. It's about 125 kilometers that we have planned right at the moment. But it's going to be based on whole intercepts. We hit, we might wedge holes off or go deeper or start new holes to go up and infill these areas because it's tough to precisely hit a target when you're drilling 1.5 kilometer deep holes at 75-meter spacing.
Michael Parkin
analystI definitely appreciate that. And then if you're moving into this getting approval with this exploration decline. What's just the time frame of -- like are you going to take that down to kind of the 500-meter level to be able to do much closer infill work on that, call it, medium zone of 500 to 1,000 meters.
Ned Jalil
executiveYes. You can see in the slide, I think it's Slide 11 there. We put an exploration drive across the strike length of kind of the central area of the ore body. I think that's coming in at about 5.75 right now in our current plan. So that will facilitate infill to get underground ounces up to indicated as well as deep exploration and inferred growth. And then the same on the Hinge and Limb side, we're really excited to get underground and do some work there. We did add a small Hinge and Limb resource this year, but it's those are challenging targets to drill from surface. So we're pretty cautious in what we included there. Underground will help us get that across the line.
Michael Parkin
analystOkay. You might not have this handy, but if you want to follow up that's totally fine. Can you give us a sense of what percentage of the holes making up the resource were impacted by capping rate?
Graham Long
executiveYes. We can -- let me get back to you on that one. We do have a sensitivity -- in the technical report, there's a sensitivity to capping table, which I think would get you most of the way to your answer. [indiscernible] Hinges by domain, but yes.
Michael Parkin
analystThat's it for me.
Operator
operatorYour next question will come from the line of Tanya Jakusconek with Scotiabank.
Tanya Jakusconek
analystA lot of them have been answered already, but maybe just from a bigger picture, can we still think about the development of this property in that $1 billion to $1.2 billion of capital that you initially talked about last year and costs all-in sustaining in that $600 to $800 per ounce range. Have those changed at all in mind?
Graham Long
executiveTanya. When it comes to this question, again, as you know, we're -- we focused our efforts last year and early this year on defining this resource and releasing this resource, so drilling, drilling, drilling. And obviously, we're excited on the results that we have to date. But I would say, looking at CapEx, right, let's look at the projects that are being built in Northern Canada now, similar projects. So I think the $1 billion that you mentioned is in line with those projects, and we don't see any significant material difference for Great Bear versus those other projects. So that's regarding CapEx. When it comes to ASIC and costs and cash costs, you can see the costs in the technical report. It won't have the ASIC in it, but you can see the cost that supports the resource, right? You can use that to guide your calculation on cost. But knowing the mineralization and knowing our cost from mining globally, I'm sure, I'm confident and we anticipate that the ASIC will be well below $1,000 per ounce.
Operator
operatorYour next question will come from the line of John Tumazos with John Tumazos Very Independent Research.
John Tumazos
analystI'm enjoying the geostat tables and the technical report like a math puzzle. How much of the gold content was erased by the top cut factors first. You alluded to a table. I have it. I'm on Page 164, I haven't seen it yet.
J. Rollinson
executiveLet me take a look here... sorry, did you have another question? I'll just take a lot to the technical.
John Tumazos
analystSure. I'm looking at Pages 163 and 4 where the top cut factors were described the 32 domains where I think 8 of the top cut factors, 8 of the domains were between 60 and 205 grams. There were 11 of the 32 domains where after a top cut, the coefficient variation was still greater than 4. Wouldn't that suggest that maybe those top cut factors could have been a little deeper? And then thirdly, final question. Do you have coefficient variation for the global deposit without slicing it into 32 domains. If you have 500 domains, then there's no variability. I'm sure that the men have a justification and qualitative geology, but sometimes I like to just look at the raw math.
J. Rollinson
executiveSure. So I would guide you to the statistics on that page that show the uncapped versus cap CVs. As you can see, most of our domains, call it, 1 through 10. These are the high-grade domains. So that's controlling most of the grade in the block model, most of the ounces. You see those CVs are falling in well in the 2 lines. So we're not expecting -- we think we did a reasonable approach with our capping there. And then when you move into the 1,000 domains, those are more of our bulk domains. So those are controlling more disseminated mineralization. So we're not as worried about the CVs being a little above 2 there. I think the other important thing that I would point you to is our comparison against the RC. So we did about a 1 quarter production volume of RC drilling. We were sampling 10 kilogram samples. So wide hole diameter and 810 grid. This was all done dry. And we use that to reconcile our block model against and get comfort in our capping levels, something we normally wouldn't do until closer to production, but we wanted to make sure we got it right on this one.
Operator
operatorOur next question will come from the line of Anita Soni with CIBC World Markets.
Anita Soni
analystSo well one was asking his question, I'm going to ask square a little bit further. And I noticed the cost numbers that you're using are -- can you just give us a little bit of color on like how you came up with those costs? I think it's on Page 172 of the technical report. And normally, I guess, for resources, you generally tend to go a little bit, I guess, not as conservative, but you can capture everything in the cost numbers. So like could you just give us an idea where -- like how you got to the process cost number? Was that kind of benchmarked to things and sort of envision the 10-K 10 per day similarly for the mining cost numbers?
Ned Jalil
executiveYes. Thank you very much. I think one thing to point out is that when we run our resources and our reserves, we're very rigorous, right? So as an operator, right? We have mines around the world, open pit and underground. We have our internal cost data. We also benchmarked across Canada, the project team did that. And that's how we arrived on the numbers that you see. And I would say it's reasonable and comparable to open pits and underground mines that are similar tonnage in Canada.
Anita Soni
analystOkay. No, I was only asking for the -- I just want to know what kind of background like work has been done so that I can say, should I be using this as one estimate? Or is it just sort of like broad strokes at this point, but it sounds like you've done some work on that. And then secondly, just trying to understand how you say you used $1,400 for volume with then $1,700 for the grade. So when you're using a lower gold price to estimate your resources, right, you're basically deciding whether or not you should be moving that material in the first place. And then the reserve calculation later is going to be whether or not you should actually send that to the Miller stock pilot. So how are they using 2 different like resource prices impact that sort of trade-off decision? I'm just trying to understand that.
Graham Long
executiveYes. Like this is -- I recognize your question, and this is common when you have this deposit that has both open pit and underground. And sorry, I'll give you a little bit more technical detail here just so we can wrap our heads around it. So when you have this great deposit that can be accessed by both open pit or underground. When you run the resource, we run the pit optimization like the LGs, you run it freely. And that runs a series of pit shells starting from a low gold price going up to 1,000, 1,400 and then you get to the 1,700 pit shell. And all of these are incremental, and that's how we end up with the -- what we call technically the ultimate pit. You do the same in the underground. You run MSO, which is Mine Shape Optimization process, and you run that through surface, right, like you run all of the deposit, then you come in a selection point. You could decide to go with a large pit, a smaller underground or go with a medium pit, larger underground or a smaller pit and more underground. So whatever doesn't get mind by the open pit gets transferred to the underground. Now why the 1,400 shell, which comes to your question. So the cutoff grade for the resource table is based on 1,700, but we selected the 1,400 shell because that line in terms of volumetrics well with the reserve price that we will be running for the rest of the portfolio starting this year. And then inside that 1,400 shell, the cutoff grade is 0.5 grams per tonne, which relates to the 1,700 gold price. If you elevate that cutoff grade in the 1,400 shell to the $1,400 price, you're looking at something in the range of 0.65 grams per tonne, which would lower a little bit of that low-grade material. When -- I know there's a lot of technical detail, but when to action. Okay, good. So that's what we did mechanically, right, for the definition of the resource. Now when you go into mine planning and economics, then it's another layer above that because then you want to feed in what maximizes your cash flow year-over-year, and you can raise the cutoff grade over the 1,400 to what we demonstrated to you to something like 0.9 grams per tonne that gives a higher average grade coming out of the pit.
Anita Soni
analystOkay. And then the last question, which relates to what you just said. So that -- I guess, if you raise it again, then you're making a decision whether or not you sort of stockpile that low-grade material that's maybe below 0.65 grams for later in the mine life. If you do -- when you're talking about the 6 to 8 strip ratio, is that with the -- like is that the overall strip of the whole ore body? Or is that including like once you do things like elevating the cutoff grade in that scenario? I mean, I guess you get a higher operating strip ratio in that sense in the early years and then lower later. Is that correct?
Graham Long
executiveNo, no. Like the reverse. They're actually the reverse because what we'll do is we'll start with a starter pit, a smaller pushback and a bigger push back. Those initial pushbacks early in the mine life will look at, say, something around 3.5, 4 strip ratio and slowly extend until you get the full resource at a 7 strip ratio.
Operator
operator[Operator Instructions] We have no further questions at this time. Ladies and gentlemen, that will conclude today's meeting. Thank you all for joining, and you may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Kinross Gold Corporation transcript — plus 252,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Kinross Gold Corporation earnings transcripts and 252,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.