MARA Holdings, Inc. (MARA) Earnings Call Transcript & Summary

September 14, 2026

NASDAQ US Information Technology Software conference_presentation 67 min

Earnings Call Speaker Segments

Unknown Analyst

analyst
#1

Great overview, Fred. Thank you for that. Russell, Core Scientific was the first bitcoin miner to secure the first large-scale AI colocation deal think over 2 years ago now. If you could walk us through that first contract and how you've seen the market evolve since then, that would be great.

Unknown Attendee

attendee
#2

Yes. So our first deal actually was in February 24. It was a small air cooled site. It was a site that we leased, and then we converted it. So it was to kilowatts or we converted it to 17 to 20-kilowatt structure on 100 200. That was like a 45-day conversion. The next deal we worked out with Corio, we actually signed it in June of '24. And it seems like 1.5 decades ago. So if anything moves as fast as Bitcoin, it's actually the AI-place because -- in that 2 years and 3 months, we've turned on and we're building like 450, 500 megawatts of that right now, which is a good place to be in. But all those other megawatts had to be built from the ground up. And that's basically because direct liquid cool and air cool are just not the same thing. So the legacy data centers that were air cooled just -- it made no sense to try to convert those. We had to build everything from the ground up. Ask about some of the first deals versus right now. I remember very distinctly when we were pricing the first deal, it was like in late '23, we had good hard estimates of around $4.5 million a megawatt to build the direct liquid cool stuff. By the time we got around to ink in the deal in June, that same facility didn't -- is just under $8 million a megawatt. Now the things that we actually turned on this year, the other sites, they were floating around $10 million to $10.5 million a megawatt. And then to give you a little bit of idea, the stuff that we have turning on next year stuff is turning on is between $12 million and $13 million a megawatt. Now most of that increase is in labor and then in a lot of the gears actually coming in the switchgear, the transformers and stuff. But to give you an idea on labor, -- if you have a kid graduating high school right now, they need to become an electrician. So journey electrics right now on 1 of our sites make about $250,000, $350,000 a year in master electricians, are bringing in $750,000 a year. So labor has gone up, and it is literally one of the key points right now for being a roadblock. So it's like, is there a power at the site, is there NIMB at the site? And then do you have your long lead equipment, transformer switch or that kind of stuff? And do you have your labor? And those are kind of the points and every day, that's what we debate now. So the things that were the issues have just gotten bigger. And as Fred just said, Bitcoin miners are in a unique position because we have a lot of those things. We've been doing a lot of those things. So I'm not sure if I answered your question, but I tried to give you a little background on the SP999 History there in this first sites.

Unknown Analyst

analyst
#3

Spot on. Thanks for the history there, Russell. So there are 2 primary business models to monetizing AI infrastructure deployments. We have colocation and AI cloud services. Sam, welcome to the panel. Good to see you.

Samir Tabar

attendee
#4

Thanks for having.

Unknown Analyst

analyst
#5

Great to have you. So this 1 is for you. At White fiber, you're actually pursuing both strategies, right? You're doing colocation, you're doing some cloud services. If you could talk to us about the differences between the 2 models and why a Fiber has elected to pursue both strategies.

Samir Tabar

attendee
#6

Well, WhiteFiber actually started in the cloud business. We're, I think, 1 of the first in the sector in the Bitcoin mining sector to have that cloud contract, and it was essentially a catalyst for us to spin off the business. We felt instead of turning it Bit Digital into an AI infrastructure platform that it would be better, and there are a couple of reasons for it to just spin out the business, which is now today called White Fiber, which IPO-ed last August. And there are a couple of technical reasons for that. One of them is financing. We were dealing with a lot of conservative banks who wanted to finance our AI infrastructure business, but we're uncomfortable with the fact that there was some crypto in the business. And one of the things we were able to do to provide comfort was just start over, just spin out the business and just make it a pure-play AI infrastructure business with absolutely no crypto. So that way, these very conservative credit committees we get comfortable on establishing some credit facilities to develop our AI infrastructure. Another reason why we decided to spin out is just to have a more institutional shareholding capital structure. So when we did the IPO for the -- for WhiteFiber, we were talking to and long-haul like bonds, we're talking to a very institutional blue-chip shareholders. And these are not the type of shareholders that would be interested if we had crypto. They were interested in AI infrastructure, not crypto. And so -- that's -- those are the 2 main reasons why we decided to IPO the business. And we started with this cloud -- this very large cloud deal and we felt to be AI infrastructure, you should really have both the cloud side and the colocation side. And we felt that we did not have the chops , the technical chops to really create an AI campus, creating a bitcoin mining facilities is not the same as creating a data center for AI infrastructure. So what we did was we acquired a company called novum a couple of years ago. That company -- that team has been doing AI campuses for many, many years in a retrofit format. They worked for hyperscalers, such as Amazon and Microsoft. And that team has been doing that for so long, and they just knew how to do that retrofit format. And we felt that the skill set to create a data center for AI customers, just so different from a Bitcoin mining facility that it would make sense to acquire that company. So that company became our colocation business, and then we have our cloud team, and those are 2 separate teams and very, very different skill set. And there are some people here on the panel who may disagree with my position that it's just a very different skill set, creating a big coming from transforming to campuses. But I can tell you that we've done it now. We've -- we've taken over mattress factories. We turned that into data centers. We did that for Cerebrus that recently IPO-ed -- we've taken over a 1 million square foot facility in North Carolina, and we did that for end scale for an $865 million contract. And they are now up and running. They're up and running. And we've done that within 6 months. And that was not because of our abilities as former bitcoin miners, but because we acquired that particular specialized team that does that day and have been doing that for many, many years. So that's sort of a meandering way of answering the question that this cloud business is -- was the catalyst that started this whole company that's called WhiteFiber today, and it's divided into 2. There were technical reasons for it. The first reason was shareholding in the second was financing. And with respect to the colocation business, that's very separate from the cloud business. It's a very different skill set. And we're very proud with what we've built in just basically 1 year.

Unknown Analyst

analyst
#7

A mattress factory to an AI data center in 6 months, pretty impressive. fabs. Good stuff. Thank you for that, Sam. Michael, you're also scaling both business models over at bit tier. Anything to add?

Unknown Attendee

attendee
#8

I just think that it is a very different process to do both of them. Because of the size and scale that we are in approaching the business, we decided for Tieto Norway, it would be better to do a colocation deal. So we signed a deal with Volta, which is providing GPUs for their end customer. It's about 121 critical IT megawatts. And we're building out the data center itself and then the GPU is being handled by our tenant. That way we can learn how to scale and build large data centers to the current technical specs that are required while somebody else is taking care of the GPU and the GPU financing. So we're pleased that, that deal went through and working hard to get the buildings and everything finished for the end of this year and the end of Q1 of next year. At the same time, we feel that, one, we have some smaller sites that don't make as much sense to do colocation alone. It's just not the scale that the big players at 1 would like. and two, to take the land and power that we've worked so hard to build up and lock it all up -- all of it for 20 years. It's almost like becoming a read, and it sort of takes the optionality of what we could do with this land and power ourselves. So we're also starting a neo-cloud or a GPU as a service business, mostly starting in Malaysia right now, our headquarters in Singapore puts us in the Asia market and lets us contact some leading Asian customers. So starting off with about 10-megawatt deal cloud site in Malaysia, which we have 2 customers for and then we're going to be rapidly -- we have another 20 megawatts in Malaysia, and we just announced this morning another 65 megawatts. We have good customer pipelines there to fill them up. In the U.S., we have a 10-megawatt facility in Washington, about 50 megawatt facility in Tennessee and about another 40, 50 megawatts left in Tito, Norway that we could do something with as well. So I think we're well positioned to do neo-cloud at smaller sites where we can scale and learn the skills and get the software all perfected. And we have 2 large sites in the U.S. with Rockdale being the easiest, we just did a large land purchase for that, the size that we could build an AI data center may be too big for us to do everything to build the data center and to do the financing. So we'd look at doing colocation as a possibility. But again, maybe we don't want to lock up all of the available power in the sites that we have so that we're not locked up our best asset for the next 20 years. So that's the business we're working through right now.

Unknown Analyst

analyst
#9

And for those on the panel who are doing only co-location today, would you consider procuring your own GPUs on the future deployments? Why or why not? And I'll leave that one open for the group.

Frederick Thiel

executive
#10

Yes. One of the reasons we took majority control of the French company, Axion, which was a subsidiary of EDF was specifically because that's their specialty. We did that deal closed in March of this year, and they have already started taking contracts. Interestingly enough, hosting U.S. inference and training loads in Europe, because the delays in getting stuff online in the U.S., there are now people seem very happy to take European capacity, and then we'll bring ion's expertise in running these mission-critical data centers and building them onshore in the U.S. as we continue to develop the smaller sites we have, which, to your point, a lot of times, they don't make sense for hyperscaler or another neo-cloud to take them. They're better off just using these inference sites.

Michael Colonnese

analyst
#11

All right. So we talked about the history, how the market has evolved, the broader market opportunity and ways to monetize these deployments. I'd now like to focus on recent deals that each of you have secured some of the specifics around those contracts. In addition to a question we get a lot from investors sites within your portfolio that you believe are closest to lease execution and why? And we'll go through the whole panel for this one, Matt, why don't we start with you? I think Clean Spark entered the game coming out became strong with $6.6 billion deal a couple of months ago. .

Unknown Attendee

attendee
#12

Yes. Thanks, Mike. So Clean Spark has amassed a portfolio of 35 different sites around the country. We're in a number of different states. And we made the decision about a year ago to start to evaluate the highest and best use for the electrons that we currently have energized. And what is a massive differentiator is having substations built and live power today because as we've seen, the barriers to entry and really the bottleneck for development of data centers really is land and power. So our first site that we leased is in Sandersville, Georgia. We've been operating there for almost 4 years with 11x Ashton Mining, but we built a substation. It's fully energized it's 250 megawatts of power. So we met with our tenant and came to understand their basis of design and the reference architecture that they wanted to incorporate into the data center. And then we went to the community. -- we said, "Guys, we need more land. So they assisted us in procuring 122 acres of land, driver 9-iron from where our existing site was. They also assisted us in the power pathway to pull the power over with the right of ways in the easements. And that enabled us to go to this 20-year triple net $6.6 billion lease with a high investment-grade tenant. So what was important to us and a lot of really valid points talking about owning GPUs and doing GPU as a service or cloud spinning up your own cloud for us at Clean Spark it was about stability. So getting our first lease, $6.6 billion, which equates to $330 million in annual revenue and being triple net, which means that million annually is almost 100% to the bottom line gives us the stability and flexibility to move into other opportunities that we see fit. Importantly, as we represented the relationship with the community to our tenant, they were impressed with the flexibility that the community showed and their willingness to assist us. So that same tenant asked to get exclusivity on certain other components of our portfolio. So they've also entered into a short duration exclusivity on up to 885 additional megawatts in Texas. Important to note that of that 885 megawatts, 585 megawatts was recently announced to be batch 0 base load. So the time lines for energization and the ability to deploy a data center there meets the expectations of our tenant. From a standpoint of construction, I've listened to a lot of my peers talk about the risk, and that's a very real thing. So for us, our tenant actually came with a specific request for an EPCM and that EPCM has built for them before, and they also manufacture a lot of the mechanical, electrical and plumbing components internally. So it enabled us to get certainty on supply chain. It enabled us to push some of the potential risks and liquidated damages over to the construction site. So we entered into a lump sum turnkey contract that contemplates the first data hall will be delivered in December 2027. So with that, I think one of the things that it's important to note, and this was brought up as we've investigated the financing of this lease long term. And that is in the beginning the analysis for high yield or investment grade was who's the guarantor? What's the credit wrap, Who's going to give certainty that the rent payments are being made. That evolved to who's the guarantor and what's the certainty on construction. And it's now gone beyond that to who's the guarantor, what's the certainty on construction? And what do the political headwinds look like? So we've really done everything in our power to mitigate that risk. We've got a guarantee from the parent, high investment grade, of which there are a handful in the world. Obviously, that will become public as the financing is completed. The ability to build that quickly has been derisked largely because of the fact that one -- that lump sum turnkey contract at the request of our investor. And the last point about political headwinds as we've begun to grow the portfolio, we reached out to some of the communities that we operate in, and we've asked them for letters of reference. And to give you a specific example, Jimmy Andrew is the mayor of Sandersville, wrote a letter of recommendation for CleanSpark for other cities that we may operate in, talking about the community partnership and the win-win spirit that we've operated within those jurisdictions. So -- it really has knocked down a number of the hurdles or the barriers to entry, and we feel very confident that the next -- the exclusivity period and the option for that will ultimately be executed, and we're seeing price go up in parallel with demand.

Michael Colonnese

analyst
#13

Thanks for that, Matt. Fred will go on to you. MARA has guided to 2 leases by year-end, and I would love to get your thoughts on that.

Frederick Thiel

executive
#14

So we don't announce LOIs or exclusivities around leases, but we feel very confident about signing the 2 leases by year-end. I think if you look across our portfolio, the other part of your question was where do we expect to see stuff happening first. I think you're going to see it both in the small and the large sites because there's a wide appetite for sites today. Hyperscalers, frontier model providers, neo-clouds. There are different size requirements. In some cases, it's 400 to 500 megawatts in other cases. It's 50 to 150 megawatts. And so you can optimize your pricing model to the credit profile of the prospective tenant to the duration of the lease to the use case for the site, really to optimize the portfolio value. And you look at a large site like the Medicare side or the Long Ridge site, where you have the opportunity to scale significantly north of 500 megawatts, you have the ability to have multiple tenants and optimize the value of the portfolio. So if you have a hyperscaler in a triple-net lease where you're talking about a yield on cost of you may have a neo-cloud at 15% yield on cost, and you may have enterprise clients at an even higher level. So building a portfolio that maximizes the profitability of the electrons is kind of very much our focus.

Michael Colonnese

analyst
#15

And John Salon is taking an interesting angle with renewable energy assets. If you could share where you guys are on your , I believe, LOI most recently.

Unknown Attendee

attendee
#16

Yes. Just for the benefit of the room, if folks don't know about Salon, we do something unique in that we go to existing renewable energy power plants, both wind and solar that already have substations that are connected to the grid, but they have a problem that they need to solve. And that is about half of their power never makes it to the grid. So they have power that needs to be monetized. They don't have a way to monetize that energy. We bring the monetization or the load to that wind and solar plant, and then we build a data center campus in that location and go vertical there. For the last 5 years, we've been doing this in the U.S. We have over 200 megawatts of that spinning. And on the Bitcoin side, we've built data centers that are then leased by very large mining companies. In the last year, we've been transforming the company during -- taking the same model where we interconnect to the power plant, get access to its power, power from the grid, and we can also build on-site generation to build these unique campuses and essentially have been building out a new series of facilities that will be AI focused. This model has allowed us to amass over 6.3 gigawatts of power assets over 30 projects. We have about 1.6 gigawatt of that, that we're actively developing. And there are 2 projects that we've announced most recently, one is called Cai. It's in the southeast part of Texas. It will be a 350-megawatt campus. -- we are actively designing and preparing to start construction on the first 100 megawatts of that. And we did sign an LOI this year and negotiating a lease for that. So that will be our first announced lease for that campus. And then the second 1 is Dorothy 3, the northwest part of Texas, and that sits across the street from an existing bitcoin farm. It also sits across the street from a wind farm that we acquired this year. So we took 1 step further in our thesis that power assets and compute assets will become over time, 1 in the same thing. So Soluna is building a power compute integrated platform. to support the future of AI. So Dorothy 3 will be our second campus. We're building that to be about 300 megawatts. Part of the power will come from moving the power from the Bitcoin side, and then the rest of the power for both D3, Dorothy 3 and Cody will come from something we call clustering because our pipeline is so big over 6 gigawatts now in each site, we have multiple wind farms or solar projects that can source -- we can source power from that -- that are within 5 to 8 miles of each other. And so we can pull power into a campus and build a very large footprint. Cody 2, for example, will benefit from clustering to get it over that 350-megawatt structure, and Dorothy 3 as well, we'll use clustering to bring in over 200 megawatts of CIT. So we are in the midst of our transformation. We're very excited about what we've done thus far. There's been some discussion about the risks in building out these new technologies. We focus on infrastructure and power because that's our core expertise, and we're doubling down on that capability. And we're adding to our existing strength execution capability. So we've hired an incredible leader from Microsoft, who will lead up our construction and operations and Well, I'd see not only the very large campuses, but I also see small difference sites being in high demand right now, especially from your labs that just need some of that inference load. And that's what we're at right now.

Michael Colonnese

analyst
#17

Thank you, Russell. Now Sam, white fiber has had a very busy summer. It feels like the last few months, you've announced an accelerated number of cloud services deals. Would you like to talk about those?

Samir Tabar

attendee
#18

Yes, we just announced about $500 million of cloud service deals, which is actually even surprising for me, our cloud services team is been really at it. So we're really proud of that. And we see a lot of stuff in the pipeline as well on the cloud side. So that's been surprising for management and how hard working our cloud team has been producing results. But just going back on the colocation side, I think it's always very tricky to like to build and spend all this CapEx on a facility without a contract. That's something we try not to do. We have now 6 facilities that we could speak of. The first 3 facilities in Quebec, Montreal 1, Montreal 2, Montreal 3. Let me just give some color on that on when we have 20 customers in that smaller facility. The second facility was a pharmaceutical capsule production factory, which we took over. The third facility, as I mentioned, was a mattress factory, which we turned into an AI campus for Cerebras. That's fully dedicated to cerebri and we got that up and running on time and within budget, Cerebrus has been a great client of ours, and we look forward to potentially working with them again in the future since we have served them well. And now in the United States, we've been focusing on North Carolina and the utility company there is Duke. We have great relationship with them. the NC1 campus, the 1 million square foot, that's just online is just basically -- we're only halfway there with 50 megawatts, and I'm rounding some numbers up right now. And Duke has -- there is a path towards 99 megawatts associated with that facility. And over the next few years, potentially another 100 megawatts in NC1. We finished -- we're now on -- we first -- we have the first 50 megawatts online for NCI for. So we started billing, which is great news for us. And there's tranche 2 for NCI, which is another -- so that is something in which we have a very pregnant pipeline of customer interest, particularly investment grade, looking to get that second tranche. They've seen what we've done with britey've seen what we've done. So they like the execution story, and they are looking at the second tranche C1 in order to execute for them and get that up and running. We -- as you mentioned, you didn't mention this, but we just acquired we just put deposits on NC2 and NC3, which is about 60 megawatts. And again, because of the reputation we've acquired on executing on time. We have investment-grade clients who are looking to -- basically, they want us to build it out for them, on NC2 and NC3. So it's -- these are good problems to have, but I do sympathize with the heavy CapEx and trying to match that in time with your contract revenues. That's always a very stressful period.

Michael Colonnese

analyst
#19

So multibillion-dollar deals secured, and it sounds like several billion on the way with this group here. So you did touch on this, Sam, I want to kind of go a little deeper on to this. So CapEx intensity of AI data center builds certainly quite after. There's no secret there. John, maybe you can discuss the sources of funds, cost of funds and the cost per megawatt to build out these data centers.

Unknown Attendee

attendee
#20

Yes, sure. We -- our model is probably no different than others on the panel. We look at a project level financing that will be primarily debt, 80% of the cost being debt, high yield, attached to the asset and the remaining 20% through equity, most likely through the TopCo pushed down into the project. To give you a sense, just on a theoretical project, call it, 100 megawatts, call it $1.2 billion to $1.4 billion to build. So it's somewhere about $10 million to $12 million per megawatt. This depends on where you're building it. We tend to be in remote locations. So cost is higher. Russell's point about labor cost and access to certain critical folks raises the cost to some extent. And so when you do that 80-20 split, you're talking about a few hundred million dollars of equity that has to be invested in our first, let's say, 100 megawatts. But when you look at the returns on that, you're talking about upwards of $10 million to $15 million net NOI. I think we have a slide in one of our investor presentations that teases this out. The yield on cost is going to be in the high teens. And at some point, the cap rate is in the single digits. And so you get somewhere on 100 megawatts, $2.4 billion of asset value added to the company. So you compare that to our current valuation and asset base, the 6.3 gigawatts that we have is a very valuable asset if we can convert those assets to spinning data centers. Our average construction time is going to be much like anyone else here so you can map that out to what that looks like from a revenue and growth perspective for the company. What I'd like to do sometimes for fun is take that framework and then apply it to the 1.6 that we've got spinning and then apply it to the 6.3 to see what the potential value is. And then the rest is really about execution, making sure you put together a bankable lease can take it to market. So the high-yield folks like what they're going to get and feel secure in the asset -- and then, of course, you need to execute and actually deliver the data center.

Michael Colonnese

analyst
#21

Thank you, John. Anyone else have anything to add on CapEx or funding for these projects?

Unknown Attendee

attendee
#22

So I agree with everything that everybody has talked about. And 1 of the constraints, obviously, is labor. And a lot of these data center builds, the GCs use travelers. So guys that live in North Dakota that are spending 10, 12 months in West Texas to build the data center. We took a bit of a differentiated approach with our EPCM and the fact that they build the vast majority of the data center in a factory. So it becomes an assembly line process rather than a bespoke one-off deal where you've got a number of different trades trying to work together. And that has simplified the delivery for us, but it's also with a fixed price lump sum contract given us certainty. So the way we talked about it is our expectation is that $10 million, $11 million a megawatt complete RFS on the data center, and we expect similar to what John is talking about, to finance that at the project level through the debt markets. We're targeting right now high-yield investment type -- excuse me, high-yield investment bond opportunity. But CleanSpark has -- we've used our bitcoin as the means to prevent any equity dilution on the company for that build. So we went into the project, signed the lease on the very first day we did our equity contribution. So it is fully funded from our side of the table, and having that certainty of the space in the assembly line and the certainty on the supply chain really derisks that. So in our conversations with lenders that's really what they're focusing on is what are the potential risks that get in the way. So as you think about CapEx and you think about the finance on these, what you also have to consider is the liquidated damages if you fail to deliver on time. and that becomes an existential risk for some folks in this business because if you make promises and there are GPU purchases that can be many times the price of the data center build. Now you've got some real exposure for liability. So getting the certainty there and being able to laser focus in on what that build cost and the time frame looks like is a differentiator when it comes to financing these projects.

Michael Colonnese

analyst
#23

Great insight, Matt, Anyone else have anything to add here?

Unknown Attendee

attendee
#24

Just I'll pile on a little bit. I think similar to Matt's concerns regarding risk of delivery. It was 1 of the reasons why we chose to partner with Starwood we have such a big portfolio to do this ourselves, especially not being an expert in building data centers for hyperscaler demands. We want to increase certainty and reduce risk Starwood has built over 70 gigawatts of data center capacity for hyperscalers. They have a captive EPCM within the worldwide digital who's built a lot of these sites. And what we're finding is because of the structure of our model, our cash-on-cash returns are significantly greater than the traditional model because we leverage our site as a contribution on the equity stack. And if you use an 80-20 model the amount of additional capital we have to include over and above the value of our site in these joint ventures is fairly de minimis, which means that the cash-on-cash return is much greater. It also means we can do more sites in parallel simultaneously. -- and greater capacity without it having to all be credit provided by us. So we feel very optimistic about that. It's going to allow us to move very quickly as we really get started here, and we're super excited about it.

Charlie Schumacher

executive
#25

Yes. If I may add, we do something similar. We have access to power, infrastructure. And in some cases, we'll have power plants. But that land once it gets fully developed and you're ready to go vertical becomes much more valuable than what you pay for it, and that can be used as a contribution on the equity side. On the execution side, being a smaller Bitcoin infrastructure company, we were thinking about the risks with execution around these very complex data center projects and -- we approached it in 2 ways. One is on our initial project, we partnered with a development company that is a group of AWS folks who have experience developing, constructing and operating these facilities. That's allowed us to design and develop and market these sites in a way that customers would expect. And then this past quarter, we started building our own in-house capability, hiring the first major role to the company, a gentleman that is run and built over $10 billion worth of data center projects for Microsoft. I think you built their largest AI facility. -- and hiring is tea here over the last couple of months. So building out our own execution capability to deliver these sites to the end user customers at the level of quality and timing that they expect.

Michael Colonnese

analyst
#26

All right. Let's move on to a controversial topic to spice things up a little bit. Some headlines out there would suggest that we are in an AI infrastructure bubble. I'd be curious to get the group's thoughts on this, and I'll leave it open for whoever would like to start here.

Frederick Thiel

executive
#27

I mean I think if you talk to the people who have a need for the compute, they would tell you there's no bubble. They just need a lot of compute and they don't have the ability to deliver on it. I think there are 2 things going on. One is, is there a bubble in the hyperscalers and this $1 trillion spend? Or is there a bubble in the AI compute world, 2 very different things you're looking at. AT&T recently announced that over 40% of their workloads are being done on open weight, open source models. They are not using frontier model providers for that. They expect that number to grow to 70% over the next 2 years. One of the biggest challenges today is cost per token. And about 60% of workloads done by AI today are fairly mundane. They can be done by open source model or an open weight model on de minimis amounts of infrastructure. So there is a huge need for inference the question is how much of it will happen in the hyperscaler cloud and with the Frontier model provider versus how much of it will happen in the enterprise and with the let's call them neo-clouds for now, but for the neo-clouds providing a full stack of software services that allow people to run and load whatever models they want to run in fully air gapped environments. One of the reasons we when after the Axion opportunity was, we wanted to have the capability to run fully airgap, fully sovereign increase at scale for enterprises because if you look at what it costs to run in AWS today with dedicated hardware, dedicated resources versus running in private cloud, it is a 10x higher cost. And companies are looking at AI as a cost item, right? It has become part of their OpEx budget. And if they are going to pay huge fees to the frontier model providers versus training their own models and paying once for a model and then running it proprietarily. You're going to see a lot more inference move towards either behind the firewall or near prem, on-prem inference providers who can allow people to run sovereign models. And I think that is going to be by far the biggest thing moving forward in this industry. And you'll still see a lot of revenue going into the frontier model providers, a lot of revenues still going to the cloud providers. But the first in cleaning of this, I think, is how Google reorganized their AI business. Who is it that runs Google's AI business today. It is the guy that operates their cloud business? It is not their AI team.

Matt Schultz

attendee
#28

Yes, to echo Fred's comments, I certainly -- from CleanSpark's perspective, we certainly don't see it as a bubble. Russ and I had breakfast this morning, we were talking about the increase in rates for these long-term leases. And the -- how rapidly they're appreciating and what we really see is that there are 3 constraints. Capital. So money is flowing where there's the least amount of risk and the highest credit certainty energy availability and those energized megawatts to have conversations with hyperscalers that they're actually contemplating behind-the-meter investments and building their own power plants in order to support the data center, the need for compute that they have. gives you a pretty strong indication that this is certainly not a bubble. And then the last thing is delivery certainty. As we've entered the conversations for credit assessment of the project and working with the high-yield market. they talk about the fact that certainty of execution is now the predominant factor in determining not only the availability and the willingness for the high-yield market to provide that credit, but also drives the rates in a very strong way. So I see that if you have energized megawatts of power, and you have those -- those exist in areas that don't have strong NIMBYism. I mean, let's be honest, if we sat here a year ago, I don't think anybody on this panel would have assumed that the Governor of Texas would come out and put a moratorium on data centers for certainty of execution. This has become a political hot mess. And both sides of the aisle are mutually opposed to it. But now we find ourselves with the labor unions in agreement with President Trump that it's an absolute necessity to build these sites here for 2 reasons that number one, just like with Bitcoin mining. If you drive Bitcoin mining offshore, it will continue. It will just continue somewhere else, and that doesn't give certainty on block space for U.S. investors. But number two, these models that are being trained are being trained outside of the U.S. And so that presents an additional level of risk. So we really feel strongly that bringing the right package and the right assets in the right communities and doing an educational process in that is going to be a differentiator to solve for the bubble. In Texas, we worked with our EPCM provider for our Georgia site, and we did a roadshow. We set it up like a trade show with boots addressing everything from dark sky issues and water usage to ambient noise and impacts on utility rates. And if you can lead with education and facts rather than just hype in theory, it's a huge differentiator that we believe solves for a lot of that issue, but as to whether or not there's a bubble, hard note from my perspective.

Unknown Attendee

attendee
#29

I have ever contrarian perspective, and I think this is a better way to look at the question. I would say that whether it's a bubble or not is kind of a moot point because if you look at technology, development and infrastructure build-out for the last 50 years, every single major improvement in our capabilities as a humanity businesses, technology services on a global basis has been preceded by major investments like this. The last 1 was 30 years ago, where people were sort of scratching our head. What is this Internet thing? And let me tell you what happened. We built out the most advanced telecom infrastructure capability around the globe. We're all super connected. We then added to that mobile and content platforms and social connectivity software, which eventually delivered to us. What everybody is itching and looking at in their hand, where you essentially have a compute content bundle that gets delivered to you effectively for free. And that took billions of dollars of build-out to deliver that type of capability. AI is another one of those. It is the greatest general purpose technology we've developed in the last 30 years. And I can tell you, I've been a technologist for that time. And I've was trained to see these types of waves. This is another big tech wave. You can tell it's a major tech wave when you have infrastructure investments that hit the core elements of the base infrastructure in any given epoch, if you will. And this is the first time we're touching the energy infrastructure to power this technology. So like most of my colleagues are talking about hyperscalers are looking to build out energy. They're looking to solve the pain, which is speed to power, if you will. That's because the ultimate new bundle is going to be intelligence. We will now have the ability to have intelligence walk around in our pockets at the greatest level we've ever seen, and that's going to be made possible by multiple hundreds of billions of dollars per country. So that's trillions of dollars on a global basis that will be built out to deliver this technology. We cannot stop. As a country, if we stop doing this, we will fall behind because it's so powerful to technology that is now almost at a military level. So I think we were too where we built out roads to sort of protect the country in that sense. That's the power of this technology. And the reason the companies on stage here are so valuable is because we are part of helping to create that new technology infrastructure. So bubble or no bubble, you can only see it in hindsight, connect the dots, but I'm telling you the dots point to a new form of infrastructure that integrates energy, compute connectivity and telecom into one bundle to deliver tokens or otherwise known as intelligence framework or intelligence infrastructure.

Michael Colonnese

analyst
#30

You already have it. We are not in an AI infrastructure bubble, at least according to those -- Sam, did you have something to add here?

Samir Tabar

attendee
#31

Yes. Just very briefly, obviously agree with that. I would say that there are 3 catalysts for the Industrial Revolution. The first 1 was electricity was changed industry than the Internet, it's change industry and now AI, which is going to change the industry. So that -- there's clearly no bubble. But just with respect to the over -- there's a lot of pushback on data center development. And I think there are many communities these days who are upset that some of us are perhaps taking farmland or building these on-site data centers in their communities where it just used to be greenfield. And that's one of the main reasons why white fiber is retrofitting. These are -- we're taking over basically facilities that are left for dead. And we have community days. So for example, in North Carolina, we had a community day where we explained that we're using 95% less water than the facility that was being used before we took it over, that we're creating a lot less noise than the facility that we're taking it over from. So this retrofit format really solves a lot of the tension that's happening for -- against -- which I think is probably not a great idea, doing greenfields are kind of -- you're going to get community pushback, especially if you're taking up farmland. So this retrofit format is a way to sale from that community pushback that we've been that we've been able to solve with our Community Day with the local communities where we're building these retrofitted data centers.

Unknown Attendee

attendee
#32

Mike, could I add a quick note I wanted to add on to something that Fred touched on earlier about the enterprise client and with the question being, are we in a bubble. The answer for Big Digital is now as well. I have -- I spent 20 years in health care. Just 1 small sector of this great economy we have in the U.S. And in the last 2 months, I've had the opportunity to sit down with 2 founding CEOs of health care-focused and drill down to long-term care focused software companies, building AI models to serve that sector. And I heard the same thing from both of them. we have the product, we have the client. Our biggest fear as we scale up and out is that we can't secure the level of compute that we'll need going forward. And if I could leave anything with the investors in this room is we're always thinking about the big 5, right? We're not thinking about the tens of thousands of enterprise-level companies out there that need the same level of compute and they need it secured and available so that they can grow their businesses. And so that's something that we are at Big Digital and very focused on is the enterprise level clients more specifically with my background in health care, I'm very focused on how can I serve the health care client. But I would say the current narrative whomever was made up by, I'm sure they had their agenda, but it's completely false. -- let me tell you, there is a bubble. Let me tell you where it's at. So there's about 5 gigawatts of rack space being delivered every year, and there's about 15 gigawatts of chip demand every year. But in Texas, what the governor did was reasonable because there was 474 gigawatts of request in for data centers. We don't have enough foundry silicon foundries on the planet to use that much space. And that's what's scaring everybody. It's because there's 5x the request in Texas that the whole grid commits to. So the issue is not the guys that were rack space or the guys living the chips -- it's every farmer in rancher in Texas or Oklahoma or any state that has a transmission line or a gas line running through their site that says, "I'm going to put a data center there. we get people telling us, "I've got a 3 gigawatt site, the next cobest says, I got 3 gigawatts stand the goose says, "I have 3 gigawatt site. Well, they're all counting the same gas line and they're all count the same gas. And that's the issue that the Governor's office in ERCOT had in Texas. It was how many of these data center requests are actually real. So there really is 15 gigawatts a year of demand, and we really are -- we're not able to fulfill it. And it's going to go on for as long as we can. What there's not is nearly 500 gigawatts of demand in Texas alone. And that's where I think -- I actually don't think it was a bad thing the governor said, "Hey, wait a minute, how much of this is real. Who has a substation, who has a PPA, who has power, who has your behind the meter plan together." And I think it's reason for any state to ask that question because all of these are not real. We saw the same thing in Bitcoin mining, some -- I know some of you guys were there. Texas ERCOT told us -- and by the way, Core Scientific is 1 of the largest users of power. We talked to ERCOT multiple times a day, all the time. ERCOT told us there was 20 gigawatts of Bitcoin mining demand in Texas. There wasn't. And there's like a bit of that. What it was, was the same guys chasing the same -- everyone wanted to sell me some stuff, they want to sell freshest, -- they want to sell mats.sthe same as people just brokering these deals or putting deals together. So that actually is a bubble. There's not tens of thousands of gigawatts of demand in every single state in the country. So I think what needs to happen is some regulations on, hey, what's real and what's not real. I think that's an unbelievably reasonable request for anybody to make. I agree with that. Just to level set, it takes 5 to 6 years to build a new gas-fired facility. And while solar and wind or grade, it's intermittent. And until we manage the orchestration issue. So if the U.S. Sun Duke did the study last year, the U.S. has 72 gigawatts of power available to it based on current generation today. you want to add anything to that? -- it all takes a couple to 6, 7 years and billions and billions of dollars to do it.

Michael Colonnese

analyst
#33

Yes, there's a dislocation. All right. Last question. We do have 3 of the largest publicly traded bitcoin mics on the stage here. So I'd be remiss to not ask a question about Bitcoin and Mining. So specifically for MARA, CleanSpark in bid tier if either of you had something and, specifically, how do you plan to leverage your mining assets in Bitcoin Holdings to really fit into your longer-term strategy as you continue to execute on the AI data center side?

Unknown Attendee

attendee
#34

Well, Bitcoin was obviously higher a year ago, and it was obviously lower a month ago. And so we've developed an institutional-grade trading desk to manage our Bitcoin. We have -- if you go to Bitcoin Treasuries, I think we're 8 or 9 on that list. Fred, I think it's but we have over $1 billion in Bitcoin, and we have $400 million in largely untapped going back lines of credit and we have an institutional grade trading desk to help generate yield on that $1 billion plus a bitcoin that we hold. So we see it really as a capital tool. Additionally, we've prevailed on land and power sites because of Bitcoin. In Cheyenne, Wyoming, as an example, 110 megawatts from Black Hills Energy, they put out an RFP to acquire that, and there were 2 bidders, One was a $1 trillion hyperscaler and the other was CleanSpark. And we prevailed not because we have a better balance sheet or were more handsome but because of the fact that we were able to deploy immersion cooled.

Matthew Plummer

attendee
#35

From our perspective at Saluna in this topic, Bitcoin is a core part of our business, we're not 1 of the largest big coin miners, we're not a bitcoin miner at all. We're 1 of the largest bitcoin hosting companies that host some of the largest miners -- and that business approach allows us massive amounts of flexibility, especially as it relates to partnering with these large power plant owners. They have a problem, they have wasted energy that they need to monetize very quickly to return these projects to profitability. So we can deploy Bitcoin mining to some of these sites, especially the smaller ones, we can continue to grow our hosting business, build a relationship with these power asset companies, which allows us to then monetize that asset while we're developing the AI project, which tends to take longer and also show them a quick win for monetizing that power asset, which unlocks for us a lot more projects that are even bigger. That's how our pipeline has grown so significantly over the last few quarters because we've developed this very strategic approach to monetizing their power fast and then opening up the door to a longer relationship where we can build much larger scaled operations on the AI side. So Bitcoin has become a very strategic platform for us as we transition into.

Michael Colonnese

analyst
#36

All right. With that, that will conclude our panel discussion for today. Thank you all for attending.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete MARA Holdings, Inc. transcript — plus 254,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to MARA Holdings, Inc. earnings transcripts and 254,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.