NBCC (India) Limited (534309) Earnings Call Transcript & Summary
September 15, 2020
Earnings Call Speaker Segments
Operator
operatorGood afternoon, everyone. We welcome you all to the Q1 FY '21 earnings con call of NBCC (India) Limited. We have with us Mr. P. K. Gupta, Chairman and Managing Director; Mr. Rajendra Chaudhari, Director, Commercial; Mr. Neelesh Kumar Shah, Director, Projects; Mrs. B.K. Sokhey, Director, Finance; and Mr. Pradeep Sharma, GM, Engineering. We will start the call with the opening remarks from the management followed by the Q&A session. Thank you, and over to you, sir.
Unknown Executive
executiveGood afternoon, everybody. Our total income during quarter 1 has been much lower than the earlier years because practically, there was a lockdown. The total income has been INR 477 crores. But still, we have been able to maintain marginal profits and pay all our salaries and all other dues. But April and May were practically washed out, very little progress. And June, we had started the work. But after June, the works have picked up, labor has started coming back to the sites. And we hope that next quarter will be much better than the first quarter. Total order book as of now stands to -- close to INR 70,000 crores, about half is PMC projects and half is redevelopment projects. We have started Amrapali project in a big way during this period. We have awarded 19 tenders, and work on 2 projects have already been finished during the last year and work on 17 projects is going on. And this covers total 30,000 houses. The balance tenders of Amrapali are -- is out for -- under tendering, except 2 projects of Heartbeat 1 and Heartbeat 2 for which orders from Supreme Court receiver are yet to be obtained. So that will constitute this -- pending tenders will constitute about 16,000 houses. So the Amrapali has been a big achievement during the last quarter. This is all about opening remarks.
Operator
operator[Operator Instructions] The first question is from the line of Rohit Natarajan from Antique Stockbroking.
Rohit Natarajan
analystSir, if I understand, currently, the PMC project, can you talk something on the labor availability? How much quantum of work is going on? How much we are planning to award in this particular year to contractors?
Unknown Executive
executiveCurrently, we have around 34,000 number of laborers on all our sites. This is about 60% of the total requirement that we have. But labor is increasing day by day, and it's coming back. So by, I think, mid of October, we should have full forum of labor or at least 82% to 80%. As far as tenders are concerned, we plan to award another INR 5,000 crores to INR 6,000 crores worth of tenders during the current financial year. Around INR 4,600 crores worth of tenders we have already awarded during the financial year. So the total figure will be close to INR 10,000 crores at the end of financial year. Majority of this is Amrapali project and certain other projects like IIM Visakhapatnam; CCL, Ranchi; and Election Commission building, these were some -- also to be awarded.
Rohit Natarajan
analystSir, out of this INR 70,000 crores order backlog that we have, what is the proportion in which the work is currently going on? What is the quantum of orders that we are currently working on?
Unknown Executive
executiveTotal value of work which is underway is INR 16,500 crores. That is work of awarded tender minus executed work of INR 6,500 crores.
Rohit Natarajan
analystAnd by the end of this fiscal, what is that number expected to be?
Unknown Executive
executiveIt will increase by INR 7,000 crores, INR 8,000 crores hopefully. So it should be close to INR 25,000 crores.
Rohit Natarajan
analystOkay. Sir, what about the guidance that you gave in the initial part of the year that -- you were talking about 20% kind of guidance. But would that be possible at this current situation?
Unknown Executive
executiveLook, that seems difficult with the pandemic coming, that 20% increase since [indiscernible]. We expected that corona will go away, but it doesn't seem to be going. So works are affected. So that type of increase is not possible.
Rohit Natarajan
analystOkay. Sir, on Amrapali project, if I may have to ask you something on the finances part, I understand the current tie up that we have with SBI and other such things. I mean that number really doesn't gel up to all the way to some INR 82 billion kind of number that you want to execute the complete project. So how are the -- stage-wise, can you explain how much will be awarded in this year? How much would be awarded next year? And what will be the sources of finance?
Unknown Executive
executiveWe plan to award all the tenders during the current financial year. And source of funding is that around INR 4,000 crores are from -- come from the homebuyers. And as Supreme Court has issued the details of the installments by which homebuyers are supposed to deposit the money to the court receiver. And another big step taken by Supreme Court is that all the accounts of homebuyers which were NPA loan accounts with various banks. So Supreme Court has ordered that NPA tax would be removed and banks should give the loans to homebuyers. So that process has already started. We hope that this full amount of money will come in the installment. And around INR 2,000 crores is to come from the unsold inventory. Once the construction picks up, then we'll be able to sell the unsold inventory and that money will also come. Temporarily, some loan is being tied up with SBI bank and other banks to bridge over this time gap. So I hope money will not be a problem. To start with, we have got the funds from Supreme Court, and our projects are going through whatever work we have awarded.
Rohit Natarajan
analystSir, lastly, if I may squeeze in one more question. That is more on Jaypee acquisition. What is the progress there?
Unknown Executive
executiveThe case is in Supreme Court. There were a number of appeals against the resolution plan and the decision filed by NCLT. So appeals were filed in NCLAT and now Supreme Court has taken all these appeals to themselves. And that decision is likely to come shortly. 2, 3 hearings have already taken place.
Rohit Natarajan
analystOkay. So you expect in this particular quarter, maybe before September or in the next quarter, you expect?
Unknown Executive
executiveMaybe October, all depends on the Supreme Court. But since all the appeals have been taken together by Supreme Court, at least 1 step of NCLT is now over. So we expect that the results will come out soon.
Operator
operator[Operator Instructions] The next question is from the line of [ Himanshu Shah ] from [ Potentialities Ultimate ].
Unknown Analyst
analystI had a question. Last quarter, you said that if the redevelopment projects are awarded, our tendering will go all the way up to INR 46,000 crores. What is the scene on that sir? Hello?
Unknown Executive
executiveYou see -- we told that, yes, tendering will go up to INR 46,000 crores once all the statutory approvals are given. So we are in the process of getting the approvals. Only a few approvals are pending. I mean they are in process, not pending rather. And maybe another 2 months or 3 months, we may get all these approvals. And we are ready with the tender documents, and it will be immediately tendered during this financial year, subject to as early as we get approval.
Unknown Analyst
analystSo money is not a problem in that case. Is it?
Unknown Executive
executiveThis development is self-sustainable. We will be selling some of the built-up spaces, and from there, we will be generating money. And with that money, we'll construct the rest of the project.
Unknown Analyst
analystBut sir, are you able to sell because you have been postponing auctions for a few times now?
Unknown Executive
executiveYou can very well understand during this COVID...
Unknown Analyst
analystYes, I understand.
Unknown Executive
executiveYes. Yes. So we are aggressively trying because this is the main crux of the redevelopment project. The more we are successful in selling our built-up space, the project will...
Unknown Analyst
analystSir, my question only comes because you said this fiscal, we are only going to do INR 25,000 crores-or-some order, so -- tendering. So the question is in relation to that. Sir, just one more question on the labor front. Last time, your report shows that we have 1,900 people on the payroll for the company. And we have the employee benefit of INR 330 crores. This is about the last entire year. So the average salary comes to about say INR 19 lakh, that comes from everybody from top to bottom. And sir, I fail to understand the quantum of salary because then INR 5,000 crores, INR 6,000 crores of turnover will only go to salaries. So can you enlighten on that?
Baldev Sokhey
executiveYour question is not clear. Myself, Baldev Sokhey, Director, Finance here. Could you repeat your question?
Unknown Analyst
analystYes. Ma'am, my question is, we have, last year, given out INR 330 crores towards employee benefits, okay? And every quarter, the salary is roughly in the region of INR 60 crores.
Baldev Sokhey
executiveYes.
Unknown Analyst
analystSo basically, the difference is that INR 90 crores, maybe with something that I'm missing out on that front? And even if I take that amount, INR 330 crores, if I divide it by the 1,900 people that we have on our payroll, according to last annual report?
Baldev Sokhey
executiveActually, I just would like to clear here. You are talking about the consolidated salary part, right?
Unknown Analyst
analystYes, consolidated salary part.
Baldev Sokhey
executiveNo, no. As regards with NBCC, it is more or less constant, rather, it is now on the reducing side as the people are now superannuating, and we are not enrolling [Foreign Language] currently the further manpower. So I -- on NBCC side, you have seen that it is approximately INR 60 crores per quarter, right?
Unknown Analyst
analystPer quarter. Yes.
Baldev Sokhey
executive[Foreign Language] It will remain constant during this period, rather slowly will go down.
Unknown Analyst
analystBut madam, even that figure comes to like INR 240 crores for the entire year?
Baldev Sokhey
executiveYes, yes, yes.
Unknown Analyst
analystYes, which is like -- almost like if you do a INR 5,000 crore turnover, and if you have a 7% OPM margin, which you said in the last quarter, you just have those INR 5,000 crores going towards the employees, isn't it?
Baldev Sokhey
executiveYes. You have very correctly noticed this. [Foreign Language] yes, that is a breakeven for us to achieve that to meet out our salary pack.
Unknown Analyst
analystBut madam, if you take the number of employees on the payroll, which is like 1,900 or something. Am I right?
Baldev Sokhey
executiveNo. It is not 1,900. It is now like 1,600 on NBCC's roll.
Unknown Analyst
analystYes. So if you even divide 1,600 by, say, INR 240 crores, your average salary exceeds like INR 17 lakhs, INR 18 lakhs per person, which I fail to understand from -- right from the peon to all the way to the top, which is what I understand is because -- what I understand is that even the CMD of SBI, Mr. Rajnish Kumar, has a salary of INR 30 lakh.
Baldev Sokhey
executiveThe salary structure in the PSU is decided by the Department of Public Enterprises, and it is made applicable on the CPLCs on the same pattern, and there is no deviation from that. So maybe you are taking out the average salary?
Unknown Analyst
analystYes, of course.
Baldev Sokhey
executiveOtherwise, there are scales according to which the salaries of each and every employee and candidate wise is set out.
Unknown Analyst
analystMadam, what do you think -- how much is...
Operator
operatorSir, sorry to interrupt, but for any follow-up, request you to rejoin the queue, please. [Operator Instructions] The next question is from the line of Ankur Deore from Bank of America.
Ankur Deore
analystI have 2 questions. One is on the Nauroji Nagar project. During the last call, you had said that in July, you had sold property of around INR 500 crores, and till then the total property sales for that project was around INR 2,500 crores. So if you could give some update as what has been sold after that? And on ground execution, if that has picked up anything on that particular project? And my second question is on Netaji and Sarojini Nagar. Last time you had updated that all approvals for the revised design were also in place. The only one remaining was forest clearance from the Delhi Government. So if you could tell us what is the status on that? Those were my 2 questions.
Unknown Executive
executiveYes, we have sold till date INR 2,500 crores in Nauroji Nagar. And we are continuously making attempts, and there are a few government agency as well as others who are interested in buying the properties. So we are in the process of continuous auction so as to get to the sale. Now as far as the Sarojini Nagar and Netaji Nagar, yes, forest is still pending. The reason being they were making some separate changes in their Forest Act or something like that. So we are every day, pursuing the matter with Delhi Government, and we hope to get it soon.
Ankur Deore
analystSir, just a follow-up question. Sir, INR 2,500 crores have been sold out of INR 12,000 crores, right, as a total potential there?
Unknown Executive
executiveYes. Nauroji Nagar is INR 12,000 crores, and out of that, we have so far sold INR 2,500 crores.
Ankur Deore
analystAnd sir, in terms of on ground execution, you had said that it had started when we -- on the last call, it had just started at around 180 in workforce, is it ongoing right now? Or...
Unknown Executive
executiveIt is full-fledgedly going on. And right now, we have around 1,500 laborers, 1,200 working in day and 300 working during night.
Operator
operatorThe next question is from the line of Binod Modi from Reliance Securities.
Binod Modi
analystSorry, I joined a little bit late, if my question is repeated. I just wanted to understand our -- the mobilization of labor. Last time you said you could mobilize around 18,000 laborers till first quarter out of your almost more than 40,000 pre-COVID. So what is the status as of now, sir, if you can broadly guide me?
Unknown Executive
executiveWe have around 34,000 laborers on our site as on date.
Binod Modi
analyst34,000?
Unknown Executive
executiveYes.
Binod Modi
analystOkay. So essentially, we can say we are almost at 80%, 85% of our pre-COVID levels?
Unknown Executive
executiveNo, 60%, 65% of the requirement. We are comparing with the total requirement. So we are around 60%, 65% of labor.
Binod Modi
analystOkay. So by October end, we may be at 85% plus or maybe 90%?
Unknown Executive
executiveI guess.
Binod Modi
analystAnd about the order book profile, sir, I -- we understand that around INR 70,000-odd crore at stand-alone level, you had said in the previous quarter, considering low execution, and I think order inflow during the quarter would have been -- I mean, it's not that much. So can you essentially say the order book more or less remained same as of now? Or if there is any sort of change?
Unknown Executive
executiveLook, specifically, it remains the same. We have got some more orders, but more or less in that range only.
Binod Modi
analystSo it's more or less at a similar range, right? Hello?
Unknown Executive
executiveYes.
Binod Modi
analystAnd sir, just wanted to understand, last time, you said only INR 13,000 crores of order out of the INR 70,000 crores were under execution. What is the status as of now? How much of order is under execution? And how much do you expect is still to award in coming months, if you can?
Unknown Executive
executiveOngoing works are INR 16,500 crores. And we are going to award another...
Unknown Executive
executiveINR 6,000 crores, INR 7,000 crores.
Unknown Executive
executiveINR 6,000 crores, INR 7,000 crores.
Binod Modi
analystOkay. INR 6,000, INR 7,000 crores for the entire fiscal -- for this entire fiscal, INR 6,000, INR 7,000 crores for entire fiscal, sir? Or for the quarter?
Unknown Executive
executiveYes. Yes. Entire fiscal. It can be even more depending -- it's too early to say, but minimum around this value will be awarded.
Binod Modi
analystOkay. And sir, would there be any sort of change in your guidance now. You had last time guided around INR 6,000 crores kind of top line, almost 25% growth? So is there any sort of change after this sort of [indiscernible].
Unknown Executive
executiveI think that kind of growth will be difficult to maintain because the pandemic is still on. So difficult to guess, but that kind of growth will be difficult.
Binod Modi
analystSo would you be able to give any sort of guidance today as per current standard -- status?
Unknown Executive
executiveWe should be able to do more than the last year. In spite of pandemic, we should be able to do more than last year.
Operator
operatorThe next question is from the line of Parvez Akhtar from Edelweiss Securities.
Parvez Qazi
analystSir, 2 questions from my side. What would be our current cash and bank balance at the consolidated level? And from that, how much would be our own money and how much would be customer advances?
Baldev Sokhey
executiveTotal cash and bank balance on consolidated basis is around INR 5,000 crores. And...
Operator
operatorMa'am sorry to interrupt, but request you to speak a little closer to the device, please. Your voice is not audible.
Baldev Sokhey
executiveWe have INR 5,000 crores of cash and bank balance on a consolidated basis in our group. And approximately INR 500 crores pertains to our own funds, including our subsidiaries. And the amount of client balance is around approximately INR 4,500 crores, right? Or anything else you would like to know?
Parvez Qazi
analystThat is it.
Baldev Sokhey
executiveOkay. Thank you.
Operator
operator[Operator Instructions] The next question is from the line of [ Sagar Parekh ] from [indiscernible] Finance.
Unknown Analyst
analystHello? Can you hear me?
Baldev Sokhey
executiveYes, yes. Please, carry on.
Unknown Analyst
analystYes. So my first question is on the status of the redevelopment projects for Railway Station in Gomti Nagar and Charbagh. What is the status of these 2 projects? And are we going to award any more railway station redevelopment projects in the current financial year?
Unknown Executive
executiveThe Charbagh project is no more with us. There was some change in planning. So we are not doing Charbagh. Gomti Nagar is on, but we don't plan to do any more railway station projects in the current financial year.
Unknown Analyst
analystOkay. So Gomti Nagar, I believe that the construction work is going on very slowly. So what is basically stopping us from ramping up the project?
Unknown Executive
executiveThe problems are the sales during pandemic, the sales have been very low. We have not been able to sell the property. That is one of the major reasons.
Unknown Analyst
analystSo when do we expect this project to ramp up significantly for us?
Unknown Executive
executiveWe are going cautiously in Gomti Nagar because entire real sector -- real estate sector is having a severe downtrend this thing. So we are doing construction, but at the same time, we are trying to sale so that we get the money generated through sale and construction.
Unknown Analyst
analystOkay. And my last question would be on the guidance that you just mentioned of -- you would be able to do better than last year in terms of top line. So as your -- consolidated top line for last FY '20 was about INR 8,000-odd crores. So when we say more than that, so we are talking about consol level, right? So if I just reduce the INR 677 crores of top line for Q1, we are talking about at least INR 7,300 crores of top line for the remaining 9 months. So do you think that is achievable considering the pandemic is still on? So I mean, just a broad suggestion that ideally shareholders would be happy if you under-promise and over-deliver rather than constantly giving guidances and then not working or, I mean, not achieving the set guidance?
Unknown Executive
executiveWe will be able to achieve the levels of last year in spite of pandemic. So INR 8,000 crores, INR 8,500 crores.
Unknown Analyst
analystSo INR 8,000 crores, right? INR 8,000 crores would be the number we...
Unknown Executive
executiveINR 8,000 crores, INR 8,500 crores in that range.
Unknown Analyst
analystAnd in terms of margins, sir, any guidance on the margins because I believe now the new orders are coming at lower margins in -- as far as PMC is concerned. So what kind of margin should we expect now for the -- I mean for the consol level for us?
Baldev Sokhey
executiveEBITDA will remain in the range of 1% to 1.5%.
Operator
operatorThe next question is from the line of Sunil Bansal, an individual investor.
Unknown Attendee
attendeeSir, I'm an individual investor for a long time for NBCC and has seen my wealth growing. I just want to know what is the outlook for the company in long term? In terms -- and second question is, see, earlier we used to have a monthly presentation from the NBCC management. From 2018, that has been stopped for the shareholders. I think we need to get some idea of what is happening?
Unknown Executive
executiveCan you please repeat the -- your voice is not clear.
Operator
operatorMr. Bansal, can you take the phone off speaker, please?
Unknown Attendee
attendeeYes. Sure. Sir, I'm a individual investor for a long time, and I have seen my wealth risen. My question is I want to know what is the outlook for the company in long term? And second question is earlier, we used to have a monthly presentation from the NBCC, what is happening in the company. I think from 2018, it has been stopped. So we request you that these presentations are useful to the shareholders.
Unknown Executive
executiveOutlook is very strong. Unfortunately, from the pandemic, we would have started many more work. One of the major projects that are likely to come is Jaypee and other redevelopment projects. AIIMS redevelopment projects, also, we have started, West Ansari Nagar. And Ayurvigyan Nagar is also likely to start. And if the redevelopment projects also start, we are waiting for the effect of pandemic to be over. So the future is quite strong. But our major focus would be on redevelopment projects. We are in a...
Unknown Attendee
attendeeThank you, sir, for your comment. I will continue to be an investor.
Unknown Executive
executiveThank you.
Unknown Attendee
attendeeThe second question is regarding presentations that we used to have up to 2018, but it has been stopped, quarterly presentations on the company's outlook, et cetera?
Unknown Executive
executiveWe are thinking of starting that again. There were some changes in the top management, that could have been the reason. But we are going to start it again. Maybe from the next quarter.
Operator
operatorThe next question is from the line of Rohit Natarajan from Antique Stockbroking. Mr. Natarajan, can you speak closer to the handset, please?
Rohit Natarajan
analystIs it now audible?
Unknown Executive
executiveYes.
Rohit Natarajan
analystYes. So my question is more to do -- more systemic in nature. That is -- this redevelopment projects were part of the Master Plan of Delhi 2021 and now government is already thinking about unavailing Master Plan of Delhi 2041. Is there a possibility that some of these projects could probably be considered in MPD 2041 or is there any changes -- any ideas that have been talked about by government to you?
Unknown Executive
executiveThey have initiated the process of making MPD 2041. And it is a very lengthy process. Our project most probably will get sanctioned in MPD 2021.
Rohit Natarajan
analystSir, but MPD 2021, the deadline, what is exactly -- is there any such deadlines that they have to strictly adhere to? Or is it like something long term in nature?
Unknown Executive
executiveSo far as 20 -- as far as MPD 2021 is concerned till the 2041 doesn't come, this will remain because we submit all our plans to various statutory bodies. And whatever is applicable, accordingly, they sanction it.
Rohit Natarajan
analystOkay. Okay. Sir, just one question on the Jaypee part. One is that the bank -- the monetization, the bankers part, how do you plan to extinguish the debt? Is that -- does that include the selling of the road asset? And -- or if not, would you be taking a bet in that particular SPV? Is there some financial thoughts that you have given at this point in time?
Unknown Executive
executiveSee, if you go through the resolution plan, our resolution plan consists everything in detail.
Operator
operatorThe next question is from the line of Rachit Kamath from Anand Rathi Share & Stock Brokers.
Rachit Kamath
analystFirst of all, I want to know the stand-alone cash balance that we have on our books now?
Baldev Sokhey
executiveCan you repeat your question, please?
Rachit Kamath
analystMa'am, I wanted to understand the stand-alone cash that we have, that is NBCC's money and then the subsidies' one?
Baldev Sokhey
executiveOn stand-alone basis, we are having a cash and bank balance of INR 1,600 crores, and then consolidated, it is INR 5,000 crores. And INR 500 crores is approximately of our own for a group as a whole.
Rachit Kamath
analystOkay. Sure. No, I got it. I got it. Ma'am, my next question is previously, I was kind of confused. So you were saying in the beginning of the call that you are targeting to end up around INR 25,000 crores kind of a project -- projects under execution by end of this year. But then we are planning to only award additional projects of only around INR 6,000 crores to INR 7,000-odd crores. Now given the fact that, I think, we are at around INR 16,000-odd crores, we will -- like what's the exact number like, there's some mismatch of around INR 2,000-odd crores -- INR 1,000 crores, INR 2,000-odd crores?
Baldev Sokhey
executiveYour voice is not very clear. It's breaking somewhere. You please ask this question from Krishna.
Balkishan Singla;Investor Relations Officer
executiveRachit, you can call me or you can contact me on my investor mail ID.
Rachit Kamath
analystSure. I have one last question. Regarding this Nauroji Nagar project. What kind of revenues are you expecting to be booked over there in this year?
Unknown Executive
executiveWhat kind of...
Rachit Kamath
analystWhat kind of contribution are you looking at -- from the Nauroji Nagar project in this year? Given the fact that, that is the only Delhi redevelopment project that is underway for us? And that also happens to be the largest project?
Unknown Executive
executiveAre you asking turnover from Nauroji Nagar?
Rachit Kamath
analystYes. Like what sort of contribution are you expecting over there?
Unknown Executive
executiveNauroji Nagar is -- Nauroji Nagar, we may touch INR 700 crores -- INR 600 crores, INR 700 crores.
Rachit Kamath
analystOkay. Okay. Sure. My last question is regarding on the stand-alone entity, what kind of revenues are we expecting? Will it be around INR 5,000 crores?
Unknown Executive
executiveMore than INR 5,000 crores.
Rachit Kamath
analystSure. Sir, but then given the fact that you only had around INR 430-odd crores in this quarter. It kind of works to almost INR 1,600 crores kind of a run rate for the balance 3 quarters?
Balkishan Singla;Investor Relations Officer
executiveRachit, your voice is not audible. Either you can call -- you can call later or maybe you can call me. I'm sorry, your voice is not audible properly.
Operator
operator[Operator Instructions] The next question is from the line of [ Himanshu Shah from Potentialities Ultimate ].
Unknown Analyst
analystAnd I just wanted to know how overstaffed we are. That was my question we left at. Like what kind of staff reduction that is possible within the setup because of the high labor cost that we have?
Unknown Executive
executiveWe have a order book of INR 70,000 crores. Right now, we have -- we are not looking into staff reduction.
Unknown Analyst
analystOkay. We are not. Okay, fine. Sir, one more question about the labor ministry. We have some -- we have some [ INR 400 crores plus INR 100 crores ] with the labor ministry that we are -- we were supposed to receive. For the last 3 years, I've been asking this question, and it was always in the process. Where have we reached -- is there some arbitration there or something going on with that?
Unknown Executive
executiveYou are talking about [ USLP ] project with the labor ministry?
Unknown Analyst
analystYes, yes.
Unknown Executive
executiveSo we have around 8, 9 hospitals all over India. And the hospital projects are, I mean, for last 8, 10 years are in progress actually. Because of various reasons, there are problems in -- it's not greenfield sites for the hospital or any hospital. So now except 2 hospitals, we have completed all major 7 hospitals all over India. So now it is under process, in fact, finalization is in the process because the hospitals were not completed. So client was first willing to complete the work. And then -- now they have taken up our claims like lot of deviation is there. The projects are different type of projects where NBCC is only a contactor, like -- and not -- PMC is having clients, is having its own PMC and consultancy. So hopefully -- we had a high level meeting also, representing at the level of, I mean, secretary labor and the labor minister. And now gradually, it has -- I mean it is in progress -- in process, and we hope to realize soon.
Unknown Analyst
analystOkay. About the hospitals, because of the pandemic, do you think is there any thrust by the government that they could like award a lot of hospitals or something like that to companies like ours?
Unknown Executive
executiveYes, definitely. Definitely a lot of -- because we have now -- some new hospitals are in pipeline in Rajasthan. So we hope to get some new projects of hospitals in Rajasthan. Recently, we had got 1 project in Himachal Pradesh also, in Chamba, which we have already started. Now we have awarded this work. Plus another advantage, these old hospitals, which have been not taken over by the clients. So some 2, 3 big hospitals they have taken over, and they have converted into COVID hospitals. So a lot of thrust is there from the government side.
Unknown Analyst
analystSir, one question about Jaypee. As a company, like NBCC, at the end of the road, what will be left with NBCC out of acquiring Jaypee? A rough figure, a rough ballpark figure?
Unknown Executive
executiveYes. If you -- it will be -- once we acquire Jaypee, it will give a business for another 10 years with the land available. And...
Unknown Analyst
analystOkay. Sir, but you must have done some analysis of numbers, like if you're putting x amount over a period of 10 years, you will be left with some amount. So have they...
Unknown Executive
executiveThat has been -- we will answer this question after acquisition.
Unknown Analyst
analystAfter acquisition. Okay. Sir, and how much money we are putting out of...
Unknown Executive
executiveIt is sub-judice, lots of detail to be given.
Unknown Analyst
analystCorrect, sir. Sir, out of our own money, we will be investing into Jaypee some money, right? Acquiring their equity capital? What is that initial sum?
Unknown Executive
executiveUp to INR 125 crores.
Unknown Analyst
analystINR 125 crores.
Unknown Executive
executiveThese all things are available in resolutions one.
Unknown Analyst
analystBut sir, INR 125 crores will give us what percentage of shares?
Unknown Executive
executiveWhat percentage of shares, 100%.
Unknown Analyst
analyst100% in INR 125 crores? Okay.
Unknown Executive
executive100% of our company beyond subsidiary of NBCC.
Operator
operatorThank you. Ladies and gentlemen, due to time constraint, that was the last question. I now hand the conference over to the management for closing comments.
Balkishan Singla;Investor Relations Officer
executiveThank you so much for joining. If you guys have any issue or any queries, you can call Investor Relations. Thank you.
Operator
operatorThank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete NBCC (India) Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to NBCC (India) Limited earnings transcripts and 251,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.