NexGen Energy Ltd. (NXE) Earnings Call Transcript & Summary

March 5, 2025

Toronto Stock Exchange CA Energy Oil, Gas and Consumable Fuels earnings 47 min

Earnings Call Speaker Segments

Operator

operator
#1

Good morning, everyone. I'm Constantine, and I'll be serving as your conference operator today. Right now, I'd like to welcome all of you to the NexGen Energy conference call covering year-end and fourth quarter 2024 financial results. <<operator_script>> Mr. Leigh Curyer, who serves as CEO and Director of NexGen Energy, the floor is yours to begin the conference.

Leigh Curyer

executive
#2

Thanks, Constantine. And thank you, everyone, for being with us today on NexGen's Year-End and Q4 2024 Financial Results Conference Call. I'm Leigh Curyer, Founder and Chief Executive Officer of NexGen Energy, and with me today are Travis McPherson, Chief Commercial Officer, and Benjamin Salter, Chief Financial Officer. During this call, I'll share NexGen's views on the global uranium markets and also walk through the major progress and recent key milestones at NexGen, including completion of the final Federal technical review for Rook I and the CNSC's acceptance of our Federal Environmental Impact Statement as final, along with our first uranium sales contract with leading U.S. utilities and the launch of the largest exploration program in the Athabasca Basin, focused on our new 2024 discovery at Patterson Corridor East, PCE. Once the presentation wraps up, we'll move to the Q&A portion of the call, which gives you the chance to ask any questions. We will be making forward-looking statements throughout today's call, and I invite you to visit our website for all the relevant disclosures. Before we begin, it's worth noting the exceptional scarcity of successful greenfield projects in our industry. Only 1% of exploration projects progress past the permitting stage.

Leigh Curyer

executive
#3

We're getting close to that point. And just 0.01% end up being profitable mines in the end. The steady progress we've made and the various milestones we've hit make it clear that NexGen is solidly on track to enter that select group. Entry barriers are steep. And given how much new supply the uranium market needs to strongly fuel rising nuclear demand, our Patterson Corridor East project matters far more today than it did yesterday — and so does every current uranium developer. The uranium market stays dynamic, formed by rising fresh demand for nuclear energy on top of strong existing global nuclear fleets, along with geopolitical uncertainties and supply chain constraints, all of which underline how critical security of uranium supply is. Legislative actions have heightened supply concerns and stress the need for stable Western-based uranium sources to diversify what has turned into a highly concentrated uranium industry. Short-term market fluctuations driven by market liquidity constraints haven't altered the fundamental market reality. There simply isn't sufficient supply to satisfy demand, and forecasts show that persisting well beyond the 2040s. The sole solution is a substantially higher and sustained price that incentivizes more investment in uranium exploration and mining, which leads to new discoveries and project development.

Leigh Curyer

executive
#4

Absent meaningfully higher and more sustained pricing, those shortfalls are going to keep expanding. To give some context on uranium demand—especially where Western supply is concerned—let's zero in on the U.S. market briefly. America uses close to 50 million pounds of uranium each year, yet domestically it yields under 1 million pounds. Canada supplies 25% of what the country needs at present, and the remainder of primary supply originates from Kazakhstan, Russia, and Uzbekistan. That accessible supply is contracting as well. By 2027, Russia will be barred entirely from the U.S. market through legislation. Furthermore, most of Kazatomprom's output in the years ahead has already been promised to the East. Uranium from Kazakhstan and Uzbekistan is being redirected increasingly toward China and Russia. The West is rolling out extraordinary backing for nuclear, and yet it is lagging in locking down the uranium supply that it urgently requires. Every other piece of the nuclear fuel cycle sits at or close to record highs, but the essential feedstock for that entire cycle—uranium—has not yet behaved the same way. Still, interest in fresh sources of primary mine supply has begun, as shown by our first U.S. utility contracts being signed in December of last year. For NexGen, 2024 was a year of transformation, defined by major milestones. We obtained our inaugural utility contracts, which align completely with our approach of maximizing exposure to upcoming uranium prices and optimizing the return on each pound we produce.

Leigh Curyer

executive
#5

That has lined up with wrapping up the Federal technical review and finishing our Federal EIS, pushed project execution forward in a meaningful way, and exceeded procurement and training targets for the region — all while moving ahead the Athabasca Basin's biggest targeted exploration drill program, which produced a brand-new material discovery called PCE, only 3.5 kilometers from our Metis Arrow deposit. An incredibly dedicated team has driven our progress, along with our unwavering mission to make NexGen a world leader in clean energy fuel solutions. As we keep advancing our disciplined development of the Rook I project, which we own 100%, we are now close to finishing the most material phase: permitting. The site, our team and our balance sheet stand ready to begin construction right after the Commission hearing concludes, something we, the Province of Saskatchewan and our indigenous community partners are all eagerly awaiting. With full support through fully-executed and legally-binding benefit agreements and strong advocacy from all 4 indigenous communities in our project area — Clearwater River Dene Nation, Metis Nation-Saskatchewan Northern Region II, Birch Narrows Dene Nation, Buffalo River Dene Nation — the project is optimally positioned to complete the final approval process. NexGen has made significant advancements in construction readiness. Procurement of critical items is well advanced.

Leigh Curyer

executive
#6

For the key critical path activities, we have vendors locked in. And the team—put together deliberately to perform at its best—is ready and set to execute. The disciplined planning and execution we've done so far mean that on day 1 of approval, once final permits are in hand, we can mobilize, with cash on hand covering at least 18 months of post-approval construction activity. At the same time, we keep drawing top-tier talent and growing our local training programs so that industry-leading percentages of on-site labor and commerce come directly from nearby local communities. Sustainable development stays at the heart of how we operate, while we deliver lasting value to shareholders, partners and the communities where we work. In addition, our updated capital estimate reconfirmed Rook I's industry-leading economics, with rapid payback of roughly 12 months based on UXC's long-term price and an exceptionally low operating cost of under USD 10 a pound at USD 9.98. Those low operating costs, together with the ideal geological setting, give NexGen significant production flexibility and strategic leverage on contracting, letting us maximize the value of every pound produced. NexGen's strategic uranium inventory, bought in early 2024, has been key to our contracting position, letting us secure customers who are aligned with us on future market dynamics and ensuring we keep maximum exposure to future uranium prices.

Leigh Curyer

executive
#7

Like we saw in December, taking that proactive stance resulted in our first uranium sales agreements being awarded with several top U.S. utilities, locking in 5 million pounds of deliveries across the first 5 years. With those initial contracts as a foundation, global utilities keep showing growing interest in NexGen delivering a fresh material source of uranium supply into the market, and in helping nuclear operators diversify the supply concentration they currently have. Talks are progressing throughout the U.S., Europe, Asia and the Middle East. With market fundamentals tightening, we expect more contract signings before long, as utilities work to lock in long-term supply and NexGen gets ready for production. NexGen is still well positioned to capitalize on that rising demand, and we're keeping a disciplined approach to our contracting strategy, making sure we optimize value for every pound committed and produced. So, as we move through this evolving landscape, NexGen stays focused on delivering long-term value, drawing on our strategic position in a market with unprecedented and undeniable growth potential, together with our structural supply — with the structural supply constraints. Sustainability is a cornerstone of NexGen's culture and business practices. In 2024, local indigenous communities kept up their vocal support for immediate approval of the Rook I project, given their deep participation in and understanding of the environmental assessment process, as well as the trust that is clearly evident between NexGen and the communities.

Leigh Curyer

executive
#8

Our benefit agreements keep producing real community programs, workforce training, and economic partnerships, which strengthens our long-term dedication to responsible resource development. Initiatives like Pathways to Your Future, which prepares people for mining careers at the Rook I project, along with our distinctive sports partnerships that provide meaningful mentorship to youth via leadership development, are generating enduring growth opportunities for the next generation of leaders throughout our region. We're also pleased to report that, consistent with NexGen's pledge to support and advance local indigenous communities and businesses, 96% of procurement for the Rook I site came through our community partners in 2024. That's industry leading — the #1 position in the industry — and it shows how genuine our commitment to local communities is, and that commitment will grow exponentially once the project gets through the commission hearing process. Outside of Rook I, our 2024 exploration program was NexGen's most successful since the discovery of Arrow in 2024, a major uranium discovery at Patterson Corridor East, only 3.5 kilometers from Arrow. It shares all of Arrow's characteristics. And when it comes to size and the presence of ultra-high-grade mineralization, it surpasses Arrow at the same stage of drilling.

Leigh Curyer

executive
#9

What we've found at PCE is a transformational development. It unlocks new resource potential and sharpens just how truly district-scale NexGen's land position is. We've just started our 2025 exploration program — sorry, our 2025 exploration program — one of the biggest and boldest drill programs in the Athabasca Basin, at 43,000 meters of drilling, centered on 2 key objectives: defining the scale of mineralization at PCE and unlocking the full potential of this high-grade system. On the financial side, NexGen holds a strong position, with roughly CAD 477 million in cash at year-end, which covers the construction spend for the first 18 months of post-approval activities. In addition, expressions of interest from lenders have grown to approximately USD 1.7 billion — more capacity than is required — which highlights just how incredibly financeable this world-class project is. We're continuing to move discussions forward across multiple financing streams, rigorously evaluating options amid strong interest from around the world and from various industries. We'll keep advancing all financing alternatives through the rest of this year, leaning on our ability to optimize the capital stack with patience, given our strong balance sheet. As we look ahead to 2025, we do so with tremendous confidence, momentum and focus on our strategic objectives.

Leigh Curyer

executive
#10

Securing all federal approvals—including the Commission hearing coming up—is where our attention is, and as we do that, we're pushing engineering, procurement and training forward to strengthen the execution phase further. NexGen takes enormous pride in standing at the leading edge of one of the most consequential moments in global energy markets, where a convergence of forces—energy security, the energy transition and geopolitics—keeps working in our favor. With demand for clean, reliable and secure energy growing stronger, we're prepared to confront this challenge directly. Our strategy is the right one, and we have a highly skilled and committed team behind it, grounded in values and a dedication to all stakeholders. Thank you—I look forward to bringing you updates on our progress across what promises to be a transformative year. At this point I'd like to open the floor for questions.

Operator

operator
#11

<<operator_script>> Our first question is from Katie Lachapelle of Canaccord Genuity.

Katie Lachapelle

analyst
#12

Congratulations on the final EIS being accepted recently. A competitor of yours just gave notice of when its Commission hearing will take place. How does that news shape the way you're thinking about the schedule for your own hearing date? And, as something of a follow-up, do you still anticipate that it will be a 1-part hearing, or could a 2-part hearing be a possibility? And, in the end, does that call rest with you, or does it sit with the CNSC?

Leigh Curyer

executive
#13

Okay, thanks Katie. Yes, this is really good news. Denison has gotten its Commission hearing date. I think that's something everybody should take note of, and clearly it's a positive sign for when we might expect to hear about ours — the scheduling of it. The CNSC has told us it will be just 1 part, and we're waiting eagerly for that date to be announced. So obviously, the CNSC has only so many resources. And so we're cooperating with them to get that commission hearing date set as early as we can. And the push from all 4 local communities to the CNSC to make sure that happens as immediately as possible is extremely strong. So that's what we know, Katie, at this moment. And we have everything filed and ready, prepared to hold that Commission hearing even if it were scheduled for tomorrow. And then, once that Commission hearing process concludes and approval comes, we'll literally begin construction the week after. So yes, we're very much looking forward to the Commission responding and setting a date.

Katie Lachapelle

analyst
#14

Great, and now perhaps something on a different topic. You put a lot of emphasis on the Patterson Corridor East discovery during your opening remarks, and I believe the market still isn't giving that enough credit. When do you expect to put out additional results from the PCE program? And then, maybe some thoughts on when a maiden resource there might potentially come?

Leigh Curyer

executive
#15

Yeah. So the way we handle it is to put out results in batches as we go, so there’s always some context around them. The one thing that would shift that approach is if we drill a hole that alters PCE’s whole direction. That’s what happened at Arrow. We defined mineralization. We hit some high-grade veinlets. And then hole 30 came along and fully opened up Arrow’s size, potential and scope. We’re drilling those holes both to define how far the mineralization extends and to try to unlock PCE. That could be the very next hole. It could take 100 holes. We don’t know. So our focus on that, plus the materiality assessment, means we’ll release those results in drilling batches so context is always provided. But unless — yes, like I said, if a barn burner shows up, we’d put that out as soon as we can.

Operator

operator
#16

The upcoming question is from Regan Burrows of Bell Potter.

Regan Burrows

analyst
#17

To follow up on what Katie asked earlier regarding the PCE assay results: has there been some kind of hold-up in receiving those results? Or, to expand a bit on your earlier comment, should we read this as the strategy having changed because of something found in those results?

Leigh Curyer

executive
#18

No. Look, the scintillometer results from the 2024 program have already been released. And at this point, the assays matter less. What matters is figuring out how far the mineralization extends and hunting for the high-grade hearts inside that mineralized zone. Once we move into project delineation, where we're working toward establishing a resource, that's when the assays become very, very material. But really it's just a matter of batching the results, sending them to the lab, and getting them back. Those assays from 2024 will come out in the near future, and most likely alongside the first phase of 2025 scintillometer results from PCE. So, no one -- yes, there's no need to read anything into the length of that. Yes, the lab does get backed up. But the priorities and that core were just in the normal course. And those assays will be coming. But as I said, at this stage, the focus is on the scintillometer results and the extent of mineralization, looking for those high-grade hearts.

Regan Burrows

analyst
#19

To expand on that a little more regarding the '25 program — are the majority of these holes simply offsets from the original holes? Is that roughly how you're going about it? And what sort of spacing are you aiming for on each individual hole?

Leigh Curyer

executive
#20

Absolutely, that's a great question. And similar to what we did at Arrow, when we're defining the mineralized area we essentially work off a grid with 50-meter spacing, and that's exactly our approach here. So these aren't drill holes placed 20 meters apart, side by side; in effect, we're operating on a 50-meter grid. Then, should we encounter a high-grade core, that would call for tighter drilling at that point. But given that you can miss these deposits by a meter or even less, and we're working on a 50-meter grid while hitting mineralization at the rate we are in those holes at PCE, it tells you we're onto something extremely significant. And I've said this consistently: Arrow was found on the very first hole drilled within a 4.5-kilometer radius of the initial hole that discovered mineralization. That's an unprecedented exploration success, especially when you consider how confined these deposits are. For us to be running a wide grid and hitting mineralization the way we are, this PCE justifies the largest drilling program in the Athabasca this year. So the geology team and all of us are extremely excited.

Leigh Curyer

executive
#21

The idea that we could be looking at a mineralized system of the same caliber as Arrow is a total game changer for us. We're moving through the last permitting phases and getting ready to begin building at Arrow, and to have a second one developing in parallel like this is unprecedented in terms of what it will mean for the company.

Operator

operator
#22

Craig Hutchison from TD Cowen has the next question on the line.

Craig Hutchison

analyst
#23

Among your goals for this year is handling the optic negotiations. I'm just wondering, ahead of a possible approval next year, what kind of volumes are you aiming to get under contract?

Travis McPherson

executive
#24

Yeah. Thank you, Craig. This is Travis speaking. Honestly, I wouldn't describe us as having a fixed volume goal for any particular year. What we're doing right now is cultivating relationships, staying patient with the approach we've chosen, and making certain that, when all is said and done, we get the most value possible out of each pound we generate. That's where we stand today. Demand for what we sell is considerable, which the premium pricing we talked about in December makes clear. Given how scarce and premium our product is, that stands to reason. So those conversations are happening and will keep going all year long. I'd certainly anticipate additional contracts being announced during this year. But we absolutely are not setting a target of X pounds for 2025 and X pounds for 2026. We'll watch how the market evolves and how the negotiations proceed, and we'll stay patient while we keep building relationships as we go.

Craig Hutchison

analyst
#25

Have U.S. tariffs affected at all the conversations you're having with utilities?

Travis McPherson

executive
#26

Yeah, that question comes up often, and the quick, straight answer is no — honestly, it isn't even something we discuss, really. Uranium is very much a long-term, global business. So these kinds of matters, or these kinds of considerations anyway, are fairly standard in those discussions across different jurisdictions. And our contracts also specify that tariffs are borne and worn by the uranium purchaser.

Leigh Curyer

executive
#27

I'd just like to add to that — apologies, Craig — since many people are trying to figure out where the uranium price stands and where it's headed. Behind the scenes, there's a lot happening with offtake agreements. And look, I've worked in this sector since 2002. We've had stretches when the spot market lacks liquidity, which is the situation right now, but also stretches when it becomes very liquid once utilities fail to lock in enough pounds via offtaking. That has occurred throughout this uranium market's history. Personally, I have never witnessed demand this strong for a new source of mine supply. And it will come to pass. But a moment will arrive when utilities must attempt to pull pounds from wherever possible. We witnessed that earlier in the 2000s, when uranium's price climbed from $7 a pound to $136 extremely fast. That illiquid spot market turned highly liquid in an instant once that threshold broke. And in my view, today's situation is wound even tighter than it was back in those early 2000s.

Travis McPherson

executive
#28

Alright, great. Perhaps just one final question from my side. Regarding budgets, could you give us some idea of what you intend to spend on exploration during this year? And then what you intend to spend on Arrow, obviously leaving out a possible final investment decision this year as well?

Leigh Curyer

executive
#29

So, regarding the exploration program, that's 43,000 meters at CAD 15 million. As for the situation, if we received final approval from the Commission hearing, the initial 12 months would come to $209 million in capital spending on the project. As we're aware, the cost — we understand the cost right down to the screwdrivers and shovels that are going to be used.

Operator

operator
#30

The next question is from Ben Finegold.

Analyst

analyst
#31

Congratulations once more on the <<inaudible>> development that came up recently. I have 2 questions for you. To start, you brought up the domestic deficit over in the U.S. specifically, along with the reality that these first contracts were signed with U.S. utilities. So I was curious whether anything has shifted with those contracts since the new administration came in? And do U.S. utilities give you the impression that, tariffs notwithstanding, Canadian uranium lands in essentially the same category as domestic pounds? My second question concerns pricing. The recent <<inaudible>> mentioned floors at $70 a pound. Is that, I suppose, the same thing you folks are hearing in your conversations right now?

Travis McPherson

executive
#32

Yes. Thanks for that question, Ben. As for whether U.S. demand is shifting or anything like that, no. Honestly, I'd say the most significant shifts happened in earlier years, when it became clear that the supply risk they faced—not from Canada, but from Eastern countries—was turning into a serious issue. The fact is, U.S. utilities don't have many options. And especially when you consider the point at which we'll be producing, or could be producing, in the latter half of this decade and on into the 2030s and past that, the need is severe. So that shortfall Leigh referred to simply can't be addressed within the U.S. to any meaningful degree. As a result, there's a recognition that they must depend on Canada, honestly. And again, I'd say there's been no effect at all on the talks. We'll see how tariffs and other matters play out, but the underlying situation doesn't change: we're the neighbor to the north and have delivered uranium material into that market reliably over a very long stretch. And with Arrow coming online, honestly, that's an enormous aid in cutting dependence on other jurisdictions.

Leigh Curyer

executive
#33

And as for the pricing we get in our contracts — well, it leads the industry, and it's substantially ahead of the industry when it comes to leverage to uranium's future price. So what we're doing is purely reflecting the flexibility of the mine and the very, very low cost of having maximum exposure to the return on every pound produced. And the utilities recognize that. And on that front the outlook for NexGen is absolutely terrific, and we'll keep that industry-leading exposure to the future price of uranium.

Operator

operator
#34

The following question is from Graham Tanaka, representing Tanaka Capital Management.

Graham Tanaka

analyst
#35

Is my voice coming through?

Leigh Curyer

executive
#36

Got it, Graham — coming through loud and clear.

Graham Tanaka

analyst
#37

Alright, I was just curious about how much the announcements regarding Denison and their approval process could slow things down for the NexGen process. Or is it possible for your approval and review processes to get underway at the same time? I'm just asking about timing.

Leigh Curyer

executive
#38

Yes. <<inaudible>> Graham, and it's good to talk with you. So that everyone is aware, Graham has held shares since just after the 2013 listing. Graham, my view is that the news about Denison's Commission hearing is a bigger positive for NexGen. And once more, congratulations to David and his team at Denison for reaching that milestone. Look, all I can do is pass along what the CNSC has told us — that our file ranks as a top priority. And I'm also aware that word has gone to the local communities that the date will be set imminently. Now, I know the local communities have all asked for the Commission hearing to take place very early in 2025. Obviously, the CNSC has its own resourcing considerations, and we respect that. So to sum up, I would treat the announcement of Denison's Commission hearing as a clear positive that ours will be imminent too. As for the actual date it gets scheduled for, I don't know. We're waiting on the CNSC, since their resourcing is not something I control.

Graham Tanaka

analyst
#39

Right, okay. So just going back over it again — I know you've been speeding up how you handle procurement. Suppose you heard, for instance, that your hearing date lands in, say, I don't know, whichever month you'd care to name, and that could be the soonest — then how many months and years would it take before key milestones in the construction process could be staged?

Leigh Curyer

executive
#40

Absolutely, and that's a great question as well. Look, I want to say — even if the Commission hearing ends up happening later in this year, and if you use Denison as a comparison, it actually won't have a material effect on the timeline at the outset. A great deal of what we're doing on project execution can happen in parallel with that Commission hearing. So we'd like this Commission hearing to take place as early as possible, but plenty of work can still proceed in parallel without materially impacting the overall timeline through to production. In simple terms, though, once approved, it will be 42 months through to construction. And as we've done with everything, we'll be extremely transparent about those construction milestones and about tracking progress against them — milestones covering both the construction of various items and the cost and time required to execute. But overall, 42 months from the moment shovels hit the ground, which, as I mentioned earlier, would be literally the week after we receive the conclusion of the Commission hearing process.

Graham Tanaka

analyst
#41

All right, thanks. Now regarding how we'd stage Patterson Corridor East — if that indeed proves to be a major discovery, and if we consider the macro picture and suppose, on one hand, that a very, very robust demand climate emerges over the next few years, how fast could Patterson Corridor East be brought online? And would you layer any of that output onto the later production years at Arrow, or would you proceed sequentially?

Leigh Curyer

executive
#42

So — I think there's a possibility, once things are up and running at Arrow and so forth, and look, I'll state right now that all the evidence points to this being the same mineralizing event, as if something has burst in the region and mineralization is falling out in multiple areas. I think there's enough evidence today to be very, very clear on that fact. Same mineralizing event, same mineralization, same metallurgy in a similar setting. It wouldn't be like you're permitting something from brand-new. There would obviously be a lot of aspects that could be applied from the permitting of Arrow to this new discovery, but obviously subject to the regulatory process. And from an economic operational sense, yes, there are opportunities to double production. Arrow's 30 million pounds per annum won't even meet the number of pounds that are coming offline from mine supply between now and 2030. So — and then, that's on the back of a demand and supply gap of approximately 80 million pounds already occurring every year. The world needs more than 1 Arrow. It needs 2 to 3 Arrows and preferably up and running by 2030. That is not going to happen. But with PCE, in the event that it was to be Arrow-like or perhaps even better, it's good to know that we'll have that optionality in that event.

Leigh Curyer

executive
#43

So all options are on the table, Graham. The really good news is that in a scenario where it's warranted, we have those levers available to pull.

Graham Tanaka

analyst
#44

Just to make sure I understand: if demand really does outpace net new output substantially in 2030 and after, you'd have the option to speed up production at Patterson Corridor East — that is, to lift the total pounds NexGen produces past what Arrow alone would reach at its peak?

Leigh Curyer

executive
#45

Sure, that can definitely be done, provided the regulatory process allows for it.

Graham Tanaka

analyst
#46

Right, okay. So, based on what you've observed up to now from folks such as Denison and others working to bring partly developed mines into production, plus other regions of the world where exploration is underway in Australia and so forth, do you have a very rough estimate of how many millions of pounds might come online at which price levels in, let's say, the 2030 and beyond window — at what price levels?

Leigh Curyer

executive
#47

Yeah, at NexGen we've got a really firm grasp of that — of every project worldwide, what production capacity each one claims, what it costs them to produce, and what the economics look like. Take the early part of the 2000s: plenty of these projects already existed back when uranium was fetching USD 136 a pound. Even so, many of them never reached production — they didn't even break ground to start construction. That USD 136 a pound, in today's money, works out to roughly USD 210 a pound. The way I see it, this investment thesis is remarkable. And I believe we're already watching some of the projects that are attempting to get up and running fall short of the output they'd hoped for. There are 1 or 2 exceptions, naturally, down in Australia, but they aren't producing what they'd like and their costs are much higher. So I'd say the outlook for the uranium price is extremely bullish from here on. Even under the best case scenario, as I mentioned, the world requires 2 to 3 Arrows operating by 2030 to close that gap.

Leigh Curyer

executive
#48

That isn't going to occur. The obstacles standing in the way are simply too big for any material production to begin operating. And credit is due to the uranium developers out there. I'll give our own team a bit of praise too. But NexGen, incorporated back in 2011, putting in the effort across the past 1.5 decades, together with the Denisons and the Bosses and the Energy Fuels and the UECs, to bring these projects online. Iso is doing a magnificent job acquiring projects in the U.S., but is probably at the front of the queue when it comes to getting them into production as well, subject to price. Plenty of people are doing plenty of work behind the scenes and -- but the challenges are significant.

Graham Tanaka

analyst
#49

Alright, and there aren’t many additional pounds involved. So I don’t mean to press you too hard, but if the world can’t supply another 2 or 3 Arrows—which would imply a shortfall of what, 60 million to 90 million pounds annually—then why would anyone sign uranium contracts at today’s prices right now?

Leigh Curyer

executive
#50

Correct, Graham — at today’s prices we are not contracting. What we do is contract at the prices that will apply when those pounds are delivered. So you’ve hit on a crucial point, absolutely right there. Today’s prices are not what we sign contracts against. The contracts we sign reflect future pricing at delivery time. And that, I’d argue, is a genuine point of difference for NexGen — and, I would add, for the other emerging producers as well when set against the producers operating today.

Graham Tanaka

analyst
#51

Excellent. Well, congratulations on all you've achieved up to now, and best of luck with your timing.

Operator

operator
#52

<<operator_script>> At this point, we have no more questions. Leigh Curyer, I'd like to hand things over to you for some closing remarks. Sir, the floor is yours.

Leigh Curyer

executive
#53

Thanks, Constantine, and thanks to all of you for joining us today. And we — yes, NexGen is prepared. And this market has never looked better than it does now, and we're ready to carry out this project and look forward to doing so, while running our exploration program, PCE, at the same time. It's an incredibly exciting time at NexGen. And I thank all of you for your support and for buying into this incredible company. Thank you.

Operator

operator
#54

That brings us to the end of this conference call. We appreciate everyone for joining us. You can go ahead and disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete NexGen Energy Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to NexGen Energy Ltd. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in NexGen Energy Ltd. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.