PLS Group Limited (PLS) Earnings Call Transcript & Summary
January 31, 2022
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone joining us and are glad to have you on the Pilbara Minerals December 2021 Quarterly Investor Conference Call and Webcast. Everyone attending is currently muted and can only listen. After a presentation, we will hold a question and answer session. Should you want to pose a question over the phone, press the star key and then the number one on your telephone keypad. At this point I will turn the conference over to Mr. Ken Brinsden, Managing Director and CEO. Please proceed.
Ken Brinsden
executiveThank you, Rachel, and I'd like to welcome everyone who has joined this call, along with those listening through the webcast — particularly the shareholders who took the time to be with us. We really appreciate it. Here at the Perth head office of Pilbara Minerals, I'm accompanied by Dale Henderson, our Chief Operating Officer, and Brian Lynn, our Chief Financial Officer, and you'll be hearing from both of them during this call. Also here in the office are Alex Eastwood, our Chief Commercial Officer and General Counsel, and David Hann, our Investor Relations Specialist. Thanks to all of you for joining. Now, the context for this quarterly call is strong demand, prices that are accelerating and, in part, Pilbara Minerals responding — though some production challenges were evident, particularly through the December quarter. We've kept working on accelerating output at Pilgangoora throughout a very, very busy quarter, as we began production at the Ngungaju Plant. That plant, as a reminder, is the former Altura facilities. We delivered the Pilgan Plant improvements project, which is complete and now fully tied in, and we're continuing to ramp up production at the Pilgan Plant. Supporting all of this has been a great deal more site activity, including fairly significant growth in mining volumes, which you'll find in the production tables in the quarterly.
Ken Brinsden
executiveEven though we still need to push higher to underpin output expansion, in both the near term and the medium term. Customers clearly are after additional tonnage. That's evident when you look at pricing. The pricing is pretty extraordinary, and I'll return to discuss that in greater depth later in our commentary. Yes, extraordinary outcomes on our BMX platform when it comes to spot sales. Really robust pricing, particularly in China, which, just as a reminder to everybody, ranks as the biggest lithium raw materials market globally. That is now extending into international markets, with prices reaching record highs almost every week. That is flowing through very well into spodumene, which forms part of what, once again, I will lay out in more detail. The reference prices against a headline lithium chemicals price and how that feeds into the value in the spodumene. I will unpack a bit more detail there so you grasp some of the dynamics at play in the market. The production ramp-up keeps going, albeit more slowly than we'd prefer. Just as a reminder to everyone, we're lifting Pilgangoora output from roughly 330,000 tons of spodumene concentrate per annum to 580,000 spodumene concentrate production. Substantial output growth, and alongside that have come certain challenges. Yet as ever, the Pilbara Minerals team is working tremendously hard and possesses some excellent skills that we've picked up over the years regarding how to bring that production online.
Ken Brinsden
executiveWe're still aiming for a run rate of 580,000 tons of spodumene concentrate by the middle of this year. But both plants remain in their ramp-up phase, and that factor, together with the impacts of, you know, labor market challenges and, more recently, community transmission of the COVID virus here in Western Australia, means there's some risk to how hard and how fast we can produce relative to what we'd like. Even so, you know, a great deal of work is underway, as I mentioned, and the Pilbara Minerals team has all the right skills to make it happen, and obviously we're doing the best we can. The POSCO downstream joint venture was executed during the quarter. We're now working through the completion criteria for the joint venture's final formation. In parallel, POSCO themselves have begun early works at the Gwangyang site, and they've confirmed that significant construction works will start during the current quarter. We look forward to their progress over roughly the next two years, as we move toward Pilbara Minerals' first hydroxide production in joint venture with POSCO. Coming up, Dale will explain a bit more about what we're doing in both production and as we ramp up the plant and also production growth to the medium term.
Ken Brinsden
executiveBrian is going to add some remarks regarding how we generate cash flow, plus a bit more on the cost narrative. With that, Dale, I'll hand things to you.
Dale Henderson
executiveThanks, Ken, and good morning, everyone. I'll give my remarks in three sections. First, a bit about operations. A brief mention of the reserve update we completed in the quarter. Then, to wrap up, I'll share some perspective on the projects area and the expansion plans we have ahead. Beginning with operations, as Ken said, it was a quarter of growth, with two operations brought on and both beginning to ramp up at the same time. A growth quarter, but we've certainly experienced some growing pains, and Ken referenced the labor shortages, which are occurring throughout the state. Pilbara hasn't been immune to that, and we've felt some of those pains from end to end across our operations. That said, the quarter still delivered fairly solid production of 84,000 tons, at the low end of our guidance. Recovery averaged 62% across both operations. Once again, a touch below where we'd hoped it would be. Now walking through the parts of the operation. On the mining side, it was a quarter of moving additional waste, which was in line with the plan, though not quite the volumes we were aiming for. Again, a result of some of the labor shortages our mining contractor is experiencing.
Dale Henderson
executiveOne result of this was ore that was a bit compromised as plant feed, and that carried through into recovery coming in somewhat below plan. So there's an impact there related to mining movement. In response to the mining situation during the quarter, Pilbara put in place its own mine fleet and brought in a small owner-operated fleet of our own to back up the south pit operation, which mainly supplies the Pilgan Plant. We got that going during the quarter, and we're happy to say it started off well. Leaving mining and going to each of the processing plants. At Pilgan processing for the quarter, recovery averaged 65% against a plan of 35. As I said earlier, a bit off from where we wanted it. The improvement project package — the debottlenecking project for that plant — reached construction completion and was commissioned, and we're really just working through an optimization phase now as we aim to ramp up and raise throughput at that operation. On costs, we're higher than we'd like to be. That comes from increased mine movements, some mining contract performance challenges I mentioned. On the plant side, ore feed being a bit off from where we wanted it, plus some delays around commissioning at both plants, including some extended shutdowns.
Dale Henderson
executiveSo to sum up, there are a number of factors contributing to the cost impact. Brian will go into that in a bit more detail later in his section. Moving on from the Pilgan processing plant and turning now to Ngungaju. The December quarter was when we essentially hit the ignition switch, if you will. Our first concentrate from the core circuit came through in early October. With that operation, we're taking it through a staged ramp-up, core circuit first, with floats to follow. As for the float circuit, we remain on track to effectively flip that ignition switch for the circuit during this quarter. The ramp-up has been slower than we wanted and slower than where we wanted it to be. Some maintenance issues have contributed there. All things considered, it's good to have the wheels turning and production beginning to flow from that operation. The last item on the ops update is production guidance. You'll see from our update that, given the labor challenges and some of the ramp-up challenges we've faced, we're starting a review, and we'll look to revise our guidance as part of our half-yearly results when those come out in due course. That wraps up the ops update. Moving to part two on the reserve. Just a note there that during the quarter, we completed a significant reserve upgrade.
Dale Henderson
executiveThe driver here was combining the Altura reserve and resource with what Pilbara Minerals already had. That's a substantial lift — a 47% upgrade versus the previous year, taking it to 162 million tons. It's a very large reserve increase, and naturally it underpins both the ramp-up underway and the progressive expansion plan. Then there's the expansion plans themselves. Where do things stand? In the past we described expansion using stage two and incremental stages within stage two. That naming convention has been dropped, and we decided to go back to simpler labels so it's clearer for everyone. What's now known as the P680 project is the next incremental expansion past the ramp-up we're right in the middle of today. It adds 100,000 tons to our overall production capacity, taking us to 680,000 tons per annum. So where does that project stand? Study work is in its final stages, and we're aiming for an FID in the June quarter, assuming all goes well. After that comes the P1000 expansion project, which, just as the name implies, lifts aggregate production from the operations to 1,000 kilotons per annum. For that expansion, we're targeting an FID in the December quarter of this year. And finally, in the project space, there's the midstream project — which, as a reminder for everyone, is the production of value-added, high purity lithium chemical salts.
Dale Henderson
executiveRight now, the scoping study is nearing completion. Alongside that, we're finishing up the economic assessment and plan to share it publicly. Once we've made that scoping study announcement, we're favorably inclined to advance that project together with our partners at Calix, with the end goal of commercializing both the project and the approach and launching what we believe is a better product onto the market. Keep an eye out, and we're eager to bring you the relevant update. That covers operations, reserves, and projects. With that, I'll pass things over to Brian.
Brian Lynn
executiveOkay, thank you. Many thanks, Dale, and good morning or afternoon to all of you. When I consider the financial effects of the quarter we've just completed, I tend to break it into three aspects. The first is clearly a highly favorable pricing backdrop. We generated very strong operating margins. Given some of the operational difficulties Dale just described, we've clearly seen some effect in the form of elevated unit operating costs. On the physical side, we turned out a little more than 83,000 tons of spodumene concentrate, and we sold roughly 75,000 tons of concentrate produced at the Pilgan plant plus around 3,600 tons of concentrate produced at the Ngungaju plant. That leads to an inventory build of roughly 5,000 tons, and we ended the quarter with closing stocks of approximately 16,000 tons, equal to about half a month of production. Regarding price and operating margin, I believe everyone knows pricing has improved quite extraordinarily over the past quarter. We averaged a price of between $1,175 and $1,800 a ton on an SC6 basis. As a reminder, that is against the $850-$900 a ton we realized for September.
Brian Lynn
executiveThat is a pretty remarkable price increase. Given that kind of pricing backdrop, it's clear we achieved a substantially better operating margin. For the tons sold out of Pilgan — the 75,000 tons from Pilgan — our margin came to roughly $1,150 per dry metric ton. Thanks to that robust operating margin, the company's cash position has risen considerably. Our September cash position stood at around $137 million, and of course we cite cash, but also the LCs for shipments made during the quarter. In September we had $137 million, and by the end of December we now sit at $245 million. That works out to a gain of slightly less than $108 million. What's driving that gain? The cash operating margin the Pilgan plant managed to deliver accounts for slightly under AUD 116 million for the quarter. Also, through the tons we sold at Ngungaju — even though, as you know, Ngungaju remains in its ramp-up and commissioning stage — we still actually produced positive cash flow of roughly AUD 2 million after selling the 3,600 tons from that operation. Capital spending across the business came to slightly under AUD 27 million, and that money went, as you'd expect, toward the Pilgan plant improvements, the restart and commissioning of Ngungaju, and the visual waste mining now under way.
Brian Lynn
executiveHowever, that benefit was mostly cancelled out by the reduction in our debt. In the quarter, we seized the chance to raise our bank debt facility by $20 million. We did this on purpose to support funding for bringing the Ngungaju operation back online. The $20 million agreement was executed within the quarter, and those funds were drawn in December. That comes to roughly AUD 27 million. We additionally made interest payments of approximately AUD 2 million on that debt, and we paid about $2 million through a cash sweep required under the debt facility. When the quarter closed, we had roughly $245 million in cash, which gives us a net cash position—meaning after debt—of approximately AUD 68 million. It's clear this quarter mattered a great deal for the company and leaves us financially much stronger than when the quarter began. The one evident negative, so to speak, on the financial side for the quarter is the unit operating cost. That unit operating cost was plainly affected by the tough operating conditions we encountered in the quarter and came in at $587 a ton, roughly $142 a ton above the September quarter's unit operating cost.
Brian Lynn
executiveThat $142 increase includes roughly $56 tied to royalties. Clearly, when the selling price environment rises, the royalty we pay becomes considerably higher. That AUD 56 portion of the increase stemmed purely from having to pay greater royalties because we're receiving a better selling price. The other AUD 86 really comes down to our spodumene concentrate output running at lower levels. As Dale mentioned, this was really the result of the plant shutdown that allowed us to tie in the plant improvement project at Pilgan. We experienced some unplanned downtime events to fix maintenance and equipment issues that required attention. We also wound up with reduced recovery, as Dale noted. That really stems from the ore feed going into the plant not being as optimal as it ought to be. On top of that, we were affected by the simple fact that mining production and maintenance personnel are scarce in the market, which has an impact on how the operation is run. Now, when I consider those cost increases, they are, in my view, specific to the challenges we face at present.
Brian Lynn
executiveMy view is that these aren't necessarily going to represent a lasting step-up. Apart from the increased ore feed costs, which track the selling price, I expect that once we reach steady-state output at the operations, those costs will return to the levels we previously guided to. That said, as Dale said earlier, we're in the middle of reviewing our production and whether our production guidance needs to be revised. Should that production guidance have any effect on unit costs, then obviously we'll disclose it at the same time in late February, when we release our half-year accounts. I believe that covers everything I wanted to address. Ken, I might hand it back to you.
Ken Brinsden
executiveYes. Thank you, Brian. Thanks, Dale. I'll offer a little more commentary on the market — and apologies up front for going into some detail on the pricing environment — but I think it's especially important to walk through how that works so you come away with a better understanding of the opportunity this market presents right now. Clearly, with where prices have reached, there's a widening gap between the supply that's available and demand that's surging. That surging demand comes from, you know, all the things that spell opportunity when it comes to electrifying the global economy. Lithium-ion batteries are now central to that, hence demand growth. On the supply side — and I don't want to put words in other producers' mouths — I don't believe their experience is necessarily any different from Pilbara Minerals'. Bringing on extra capacity is tough in an environment where previously you were being punished. A very low pricing environment has meant every producer slowed down. It's highly likely, I think, that challenges will arise on the supply side, and it's probably true that the supplier response is already being overstated. It's against that challenging backdrop that the price is surging. It's somewhat perverse, but for the very same reason Pilbara Minerals had a challenging production quarter, you're likely to see pricing rise, because the supply response is insufficient.
Ken Brinsden
executiveHopefully, that's clear. Regarding pricing specifically, and going into some of the finer detail, Platts reported that China's domestic price for battery-grade lithium carbonate came in at CNY 386,000 per metric ton, on a lithium carbonate equivalent basis. That works out to more than $60,000 a ton in China. Now, there's a tendency for people to want to brush that price aside, since I think it gets described, somewhat unfairly, as a spot price. But what that price survey is actually uncovering is the genuine price being paid within the same relationship—that is, a long-term seller and a long-term buyer who are continually renegotiating both price and volume. So that's what it is. Well, what I think it represents is the actual price that the chemical conversion industry in China receives. You know, keeping in mind that China is the largest lithium raw materials market in the world. In my view, all the evidence indicates that this price is a real one, because it is also driving international pricing, which usually involves longer-dated contracts. International pricing is already getting close to $50,000 a ton. For anyone who wants to label it a spot price, I think that is somewhat of a misrepresentation. It is the price that the chemical conversion industry receives. Why does that matter?
Ken Brinsden
executiveThis is the point where the spodumene supply base finally gets its moment in the spotlight, and in my view Pilbara Minerals is especially well positioned to take part in that kind of pricing backdrop. The implication is that when a chemical converter is getting 60,000 — more than 60,000 $ a ton — for their battery-grade carbonate, then after you take off the VAT and take off what chemical conversion costs, they're left with roughly $50,000 to put toward raw materials. $50,000 remaining for raw materials, and spodumene is clearly a major piece of that. So what it comes down to is that the chemical conversion sector is able to pay considerably more for spodumene, and the way I see it, they probably will, since there's no other option. They already possess chemical conversion capacity — and there's plenty of it in China — yet there isn't enough spodumene to fill in behind that chemical conversion capacity. The upshot of all of this is that they'll push their margin upstream, meaning spodumene pricing is already quite strong but, as I see it, is likely to strengthen further. I realize that to everyone this sounds like a fairly remarkable scenario. Just consider this for a moment. It isn't iron ore. Spodumene is not iron ore. Spodumene, along with the chemicals derived from it, forms part of an industrial mineral supply chain that is becoming a specialty chemical supply chain, and most participants in it will by then already be tied down by contract.
Ken Brinsden
executiveThey have a contractual obligation to sell chemicals to either a cathode material company or a cell manufacturer, possibly in China, though Japan and Korea are just as likely. That contractual obligation exists, yet they lack the raw material. So the implication is they'll pay essentially any price to get that raw material. The situation I'm describing here is quite unlike what most folks would be accustomed to in natural resources markets. Take iron ore, for instance — that's a huge, liquid pool of product available for purchase. An industrial mineral supply chain doesn't look like that at all, since participants have constructed purpose-built chemical plants designed to match a blend of feedstock inputs, at a defined quality, for a customer who is likely a longer-dated buyer further downstream. When there's such a severe mismatch between the supply that's available and demand that's surging, all of those forces produce something highly unusual in the pricing world. That is exactly what's happening in spodumene markets. Pretty extraordinary. In my view, Pilbara Minerals is positioned really well. We likely outperformed when it comes to the price we received in the December quarter. And the March quarter already looks extremely, extremely strong.
Ken Brinsden
executiveOur guidance is $2,600 to $3,000 per ton CIF China, on a 6% spodumene basis, since we observe very strong pricing in lithium chemicals, and that serves as a key peg for our spodumene price. Yeah, these are incredible times, but even so, Pilbara Minerals will get its day in the sun. That's the detail in the spodumene market. Another way we seek to take advantage of that is via the BMX platform. Typically, the BMX platform will handle excess product from our Pilgangoora production, most of which comes through the growth in Ngungaju production that is coming. So far, we've only been producing through the HMS circuit. We keep chipping away at that and the flotation circuit, with the expectation that the flotation circuit starts during the latter part of the current quarter. In that case, we should have more product available for the BMX platform, and we look forward to the price discovery that fleshes out. To close, in summary, bringing on the two plants and the expanded capacity they represent is a challenge, especially given the tight labor market that WA currently suffers from. We're all looking forward to the border's opening, because ultimately it should provide some relief to those tight labor market conditions.
Ken Brinsden
executiveTo start, that quarter was difficult, and it isn’t only Pilbara Minerals facing this. We believe nearly every resources company is dealing with comparable problems, and that includes the other suppliers of lithium raw materials. What does that indicate? It indicates, at least partly, that supply is constrained, which probably indicates a higher price. We believe we are positioned very well to benefit from that over the next few quarters. I have confidence in the team and in their capacity to deliver the remaining capacity, and if that happens, we will have an extremely strong year. Rachel, I’ll hand it back to you. I’m certain there will be many interesting questions on the phone call, but also some that come from our webcast. Yes, I look forward to people’s questions. Thank you, Rachel.
Operator
operatorAlistair Harvey from JPMorgan has our first question. The line is yours.
Alistair Harvey
analystHello, Ken and everyone. I have a couple of questions. Maybe I’ll begin with the recovery situation at Pilgangoora. I’m curious about Ngungaju: once you bring the floats online, what do you expect the maximum recovery there to be, and what timing do you think we might see for that across the operation?
Ken Brinsden
executiveLooking at the specifics, Pilgan was affected by the new equipment being introduced as part of the improvements project, along with the impact of a blend that wasn't optimal. We saw recovery at Pilgan of roughly 65% compared with 75%. At Ngungaju, recovery is significantly lower while we're running only the HMS circuit, with the transition—or nominally 30% recovery—until the float station circuit is brought on. As for target recovery, the average view over time with a fully optimized circuit is probably around the high 60 to 70% range, versus Pilgan at 75%, for argument's sake.
Alistair Harvey
analystThat's genuinely useful, thank you, Ken. On a second point, regarding the FID for P680 and P1000: if those reach a successful conclusion, I'd like to know how soon construction could get underway following FID, particularly given the constrained labor market you're describing, and also any thoughts you might offer on the percentage rises in CapEx that you've observed versus earlier studies.
Ken Brinsden
executiveYes, I’ll hand that over to Dale.
Dale Henderson
executiveYes, certainly. I'll address the schedule for when those projects would begin execution after FID. The encouraging part is that P680 may move quite fast, since that project is essentially an expansion of the HMS circuit. Considering engineering work, scheduling, and long-lead items, we believe construction might begin in as little as six months following FID. A ramp-up would probably not be expected until roughly nine to 12 months after FID. That timing largely reflects our assumptions regarding long leads. On the subject of capital and cost increases, we have certainly seen escalation broadly across the board in the W.A. environment, steel prices and similar factors. We have not yet factored that into the CapEx forecast for these specific projects. Naturally, we will do so when making the FID decision. I hope that responds to your question, <<inaudible>>.
Alistair Harvey
analystYeah, thanks, Dale. Just regarding the P1000, do you figure that one will take longer to build once FID happens, simply because it's somewhat larger?
Dale Henderson
executiveThere's still an unresolved question about how we stage that specific piece of the expansion. We could potentially decide to place forward orders for long-lead items. For those two expansions, the long leads are really what sets the critical path — in our view it isn't so much a labor constraint. It's more about long leads, and regarding the P1000, the good news is that we already have the HPGR for that circuit. So for us it would really be about examining ball mill timing and the float cells principally. Everything else is largely in hand, so potentially we'd be well positioned to move fairly quickly on that one.
Alistair Harvey
analystThanks, Dale. I’d like to fit in one final question if possible. I’m just curious whether you have an approximate breakdown of Pilbara’s product going to hydroxide converters compared with carbonate converters, and whether that mix has shifted materially now that carbonate pricing has risen more sharply than the hydroxide price.
Ken Brinsden
executiveRight. The customers we have under contract do a combination of the two, so pinpointing precisely what share goes to the carbonate chemical suite as opposed to hydroxide is really tough. Honestly, though, in the current market you can afford to be somewhat indifferent, since any primary hydroxide producer — meaning straight from run-of-bank to hydroxide — is likely moving hydroxide over to carbonate, an extremely low-cost carbonation process, to capture the benefit of the carbonate price. So in the grand scheme, they're accomplishing that at about the same expense as chemical conversion to carbonate would carry in any case, given that the primary hydroxide route would normally come in somewhat cheaper. From where we sit, we aren't especially bothered either way about where it ends up being consumed. With the price gap that exists between carbonate and hydroxide, converting hydroxide into carbonate is a highly probable market reaction.
Alistair Harvey
analystPerfect. Thank you, Ken. Many thanks, everyone. I appreciate it.
Operator
operatorThanks. We'll take the next question from Mitch Ryan at Jefferies. Go right ahead.
Mitch Ryan
analystMorning, everyone. Only a quick aside here, but I'm just hoping to get some clarity. One of your recent talks mentioned that they intend to scale up their lithium hydroxide refinery across the next few years, and off-spec products are now being looked at for use again as a platform. Beyond that, I'm simply curious whether that would amount to material earnings — whether it would be material for your earnings?
Ken Brinsden
executiveThat's a solid question, Mitch, and honestly it's tough to argue with the reasoning that as you build up greater volume along with additional price points on a platform like that, you get a stronger mix of price transparency and market development, which in turn lets more advanced market tools take shape. In general terms, we back the goal of generating additional product pricing on venues such as the BMX platform. We're quite willing to have those conversations, and it probably comes as no shock that they're already happening. That strikes us as a highly sensible model to put in place. This industry clearly has a real need for better price transparency.
Mitch Ryan
analystGiven that, I suppose you wouldn't really be seeking a substantial commercial gain. It would be more that greater market transparency would help every participant, I guess.
Ken Brinsden
executiveExactly. A rising tide lifts every boat. Yeah, that's basically the reasoning, and in the end, having a more sophisticated pricing methodology available will be beneficial for the market overall. We aren't especially focused on the commercial potential in that model—just broad participation across all products. And as a matter of fact, Pilbara Minerals itself is eager to add more price points on the platform by, you know, varying spodumene grades and, over time, midstream products, and who knows? Perhaps our own lithium chemicals down the road.
Mitch Ryan
analystThat's all from me. Appreciate you taking my question.
Operator
operatorThanks. Our next question is from Jack Gabb at Bank of America. Go ahead, please.
Jack Gabb
analystThanks, and hi, Ken and the team. I've just got a couple of questions. First, I suppose, on the labor challenges and especially regarding some of the stripping — I guess this year was going to be somewhat of a catch-up year for stripping rates. I'm just curious whether this is going to pose a challenge at some point. Will it create a bottleneck for you as you look to expand, or do you? Do you have quite a lot of headway on that? I'll just follow up with one more question. Thanks.
Ken Brinsden
executiveYeah, Jack. I’ve got a couple of opening remarks on that topic, and then I’ll pass it over to Dale. Yeah, you’re right. This year is entirely about catching up, and we had roughly 15 to 18 months of higher-than-life-of-mine stripping that we needed to make up. That has required us to mobilize additional fleets and bigger fleets. Labor has been a limiting factor, and that’s part of the difficulty. Dale, is there anything else you’d like to add?
Dale Henderson
executiveThe one additional point I’d make is that buying Altura opens up further opportunities when it comes to access for all. There is no doubt that a great deal of material must be moved as part of waste movements, but we have several areas we can draw on. That leaves us in a reasonably strong position as we consider different mine plans and so on. That is everything I would add.
Jack Gabb
analystGreat, thank you. Now just a single question about pricing. Could you help us understand the range of prices you actually get across your contracts — setting BMX aside for a moment — within your guidance? And second, as part of that guidance, are you at this stage factoring in any meaningful volumes from the BMX platform? That's for Q1. Thanks.
Ken Brinsden
executiveJack, let me take the second question first. Actually, the quarterly figure of $2,600 to $3,000 per ton that we laid out is an estimate of contracted pricing, and it's based on what we're seeing today. That is contract pricing only — it leaves out anything that could still happen on the BMX platform. I'd just add that there's probably a risk of further upside, depending on how quickly chemicals have accelerated. Oh, yeah, sorry. On the first question, actually pricing is relatively tight across the customer group. There's really no material difference showing up when it comes to the various pricing models. They've pretty much come out close to each other, within a couple of hundred dollars, you know, for each individual contract. They do vary over time, since they use slightly different sorts of pricing modeling, but that's in the detail. They all reference lithium, or typically all reference lithium chemicals, potentially in a slightly different way, but the net outcome of the pricing is pretty tight.
Jack Gabb
analystThat is genuinely useful. Many thanks. I'll stop at that point.
Operator
operatorThanks. We'll take the next question from Peter Kerr of the Australian Financial Review. Go ahead, please.
Peter Kerr
unknownDale and Ken, I appreciate you both making time. On the border question, my assumption is that you won't be part of the wave of other WA-based CEOs relocating east. Second, regarding the 5 February delay, did that disrupt anything you had planned — for instance, were there specific East Coast markets you were targeting as of Feb six? So how are you dealing now with that kind of open-ended uncertainty?
Ken Brinsden
executiveSure, Peter, that’s a fair question. I can tell you there were plenty of tears in the Brinsden household once the border closed after February 5, because the kids are in their own locations and we wanted to see them. On the work side, no, I don’t intend to relocate to Melbourne or Sydney, certainly not in the near term. Did it throw plans off? Well, the border’s indirect effect is that it limits short-term labor supply. That really gets to the core of many of the problems we’ve been facing, particularly as we ramp up the two plants. When a shutdown comes around, you usually can’t secure the labor, at least not in the manner we previously used to build the peak load needed to finish the jobs fast. So a shutdown that ought to have taken 36 hours ends up taking, you know, 72. A broken ball mill coupling takes around 56 hours to repair when it should have taken 24, you know, that kind of thing. That’s really one of the main issues. Our contractors, the mine contractors, feel it too. They usually carry a somewhat larger transitory workforce, and they’re highly mobile.
Ken Brinsden
executiveRight now, in that contractor segment, everybody is drawing from one shared pool, and that’s producing plenty of, you know, difficulties when it comes to getting labor and keeping labor for our contractors. So yes, if the border keeps being closed, that creates problems around peak staffing and around how far our contractors are able to hold on to their people. So yeah, this is a major issue. The faster the borders open and we regain the, you know, the movement of workers, that really is what matters most.
Peter Kerr
unknownSo I take it you figure the hit from those labor issues will be bigger than what COVID will do once it begins moving through your workforce — you know, the way it already is over here?
Ken Brinsden
executiveThere's definitely some exposure for WA mining companies when it comes to the production environment — no question about that — but it ought to be fairly short-lived. I think of it in months, a couple of months, rather than six to 12 months.
Peter Kerr
unknownThanks, Ken.
Operator
operatorThanks. Our following question is from Adam Baker at Global Mining Research. You have the floor.
Adam Baker
analystAfternoon, Ken Brinsden and the team. I just want to ask about the grades at the mine. For quite a while now, they have stayed above the 1.18% reserve grade. I was just wondering what your mine plan indicates about returning to match those reserve grades — how far away are we from that?
Ken Brinsden
executiveThanks, Adam — that's a fair question to start with. We've said pretty consistently over time that Pilgan, or the original Pilgangoora operation, mined at a somewhat higher grade across roughly its first 4 years of production. That simply reflects how the ore shows up at Pilgangoora, so there's nothing especially difficult about it. The lower reserve grade is also a consequence of bringing in the south pit — that is, the former Altura operations — which, again, always carried a lower reserve grade than the original Pilgangoora reserve grade. That accounts for part of the gap as well. We've now been producing for 2 or 3 years, so we have another year or 2 of somewhat elevated grades left, and after that they'll begin reverting more toward the reserve norm.
Adam Baker
analystThanks. On the second point — yes, you brought up that there may be a review of guidance when the half-year results come out in February. I would assume there will be some effect on the second half of financial year 2022 guidance, but I'm just curious how probable an impact is to that target of 540 to 580 thousand tons of spodumene by mid-year.
Ken Brinsden
executiveWe’ll have more to discuss, since roughly another four weeks remain before the half-year results. A number of factors are on our minds, and the coming three or four weeks will likely be formative. First is the impact of the ongoing plant ramp-up. There’s a substantial difference between the historical output of 360,000 spodumene concentrate tons per annum and the 580,000 spodumene concentrate tons per annum we’re moving toward. Our guidance is sensitive to how quickly we can bring that capacity online. We genuinely need another three or four weeks to observe how the plants perform, along with the work already completed and the integration of the combination of new equipment, particularly Nugget 2, where we’re bringing on the flotation circuit. That’s part one. As for absolute production capacity, i.e., 580,000 tons, well, you know, we remain confident about reaching that run rate in the middle of the year, as a function of both plants and their performance. The part we’re sensitive to is the remaining ramp-up. Lastly, it’s worth mentioning the borders and COVID. You know, there’s obvious community transmission occurring here now. Mining companies are going to start feeling that.
Ken Brinsden
executiveWe’re somewhat attuned to what that effect could cause. Right now, indirectly, it has already done us harm, since we’ve had difficulty obtaining peak people, as I described. Yet there could also be production effects stemming from community transmission and how that ties into the workforce we have available. Give us another 3 or 4 weeks, mate, and we’ll have that mostly resolved and offer more definitive guidance.
Adam Baker
analystThat's great. Thanks a lot.
Operator
operatorThanks. At this point we have no more inquiries coming in by phone. I’ll pass things along to Nicholas Read now for any questions submitted through the webcast.
Nicholas Read
executiveThanks, Rachel. There are quite a few questions that people have submitted online for the team here. To start with, we have some from John Bosworth. He asks, "Could you say more about the company's Strategy and about the initiatives that have been introduced to address the skills and labor challenges and risks that currently exist in WA.
Ken Brinsden
executiveAbsolutely, John — that's a fair question. And yes, there's actually been a substantial response already. The first step was taking part of that challenge on ourselves: Pilbara Minerals has started running its own mining fleet. There are several reasons behind that decision, but a major one is that Pilbara Minerals is seen as relatively more acceptable for longer-term employment than our contractors are. It comes down to how the workforce operates here in Western Australia. Most employees — not every one, but the majority — would tell you that longer-term work with an established company is the safer option. I think we also benefit from our association with the new economy in mining — battery raw materials — which people view as the future, and because of that, the brand has stronger appeal and retention. That's the main thing we've taken on ourselves, and so far it's going well. We haven't encountered many problems recruiting people directly, though our contractors certainly have. Work has also been done around retention — for instance, how we pay our staff, the bonuses, the net benefits. We've put effort into our camp as well. There are plenty of measures that have been implemented which ought to achieve the intended result of drawing in and keeping people over time.
Ken Brinsden
executiveOn the contractor side, we've actually applied somewhat more creative approaches with them. So again, rosters, you know, the camp, and in some situations, how they receive incentives, all aimed at helping us draw in and keep hold of people. The single major difficulty we still have not truly gotten on top of is that peak labor situation I mentioned. When you require, you know, big numbers of personnel for shutdowns and/or breakdowns. That remains an area of concern. Again, it's not something we're tackling alone. It's a very wide-ranging problem for the mining companies here in WA in general. I hope that makes sense, John.
Nicholas Read
executiveThanks, Ken. John has a couple more questions. First, regarding the drop in the share price over roughly the past week, what portion would you put down to the wider global market correction, and what portion to investors' worries about the risks and challenges we've talked about today? Second, with the strong financial performance recently, could you update us on how the company is viewing its dividend policy?
Ken Brinsden
executiveSo regarding Pilbara's share price, I'd say it has mostly moved in step with comparable companies. Nothing especially distinctive has happened there tied specifically to Pilbara Minerals, in my view. A pullback wouldn't be surprising given how strongly lithium stocks had been running, and you also have to factor in wider sentiment problems across global markets. The threat of inflation, you know, obviously produced a somewhat risk-off mood. Most of that share price movement, I'd put down to that effect. Second question-
Nicholas Read
executiveOn the dividends side.
Ken Brinsden
executiveOn dividends — yeah, so as Dale laid out, there's substantial growth in front of us, and in our view that amounts to a sensible reinvestment back into the business. That matters, and in the end it comes down to how the price behaves. How price stacks up against cost is going to be among the things we weigh when deciding whether dividends eventually form part of the picture over the medium term. There's more to learn on that front, John, before we can say anything definitive about a dividend stream.
Nicholas Read
executiveThanks, Ken. We have a question coming in from Rob Clark. He’s asking: regarding the impressive strengthening of your balance sheet, does your midstream project justify additional resources, and can you explore ways to speed up this product’s path to market? He also asks whether you can clarify if this product is aimed directly at Chinese LFP cathode manufacturers.
Ken Brinsden
executiveOh, okay. Yeah, those are both solid questions. Well, we really do like the midstream product, and Dale — I believe your phrasing was along the lines of a very competitive product, or a compelling product for the market, something along those lines. Right?
Dale Henderson
executiveMy memory fails me on that one.
Ken Brinsden
executiveRight, I completely agree with that. For this market it’s a strong offering, and reworking how the spodumene supply chain operates will play a major role in where our sector goes next, since better-performing options exist. On that project we’re pushing as hard and quickly as we possibly can. It’s genuinely great to be collaborating with Calix and their capable team. There’s still engineering work that has to be done, and that’s very hard to bypass. Additional effort lies ahead, and there will likely be more to share on this when we aim to release the initial round of engineering within the next few weeks. I believe that covers it.
Nicholas Read
executiveYeah, great. Our next question comes from Hayden Bairstow at Macquarie. He asks whether the long-term production target after the expansion remains roughly 1 million tonnes per annum, or whether we've revised our long-term recovery assumptions. Second, what share of sales in 2022 is expected to go through the BMX platform?
Ken Brinsden
executiveOver the long term, Hayden, our goal remains above 1 million tons annually of spodumene concentrate. Generally speaking, that ought to occur from the later portion of 2023 into the early portion of 2024 and onward. There's additional engineering and delivery work still ahead. We're certain that Pilgangoora, as a production hub, holds that capability, and it will play a highly important role in worldwide supply. It very much remains in the picture. As for recovery, nothing has actually shifted regarding how we see recovery. In line with what we've said before, Ngungaju runs at somewhat lower recoveries, simply because of how that plant operates relative to Pilgan. A somewhat lower head grade overall is likely to be fed to Ngungaju as time goes on. Recovery remains unchanged, and flotation continues to be a very important element of the future at Pilgangoora, whether at Pilgan or at Ngungaju.
Nicholas Read
executiveAll right, turning to sales.
Ken Brinsden
executiveApologies — regarding sales into the BMX platform. Yes, some uncertainty remains there. It comes down to how fast we can add the rest of the capacity at Pilgangoora. On the production side, we're still at a fairly early stage, since we're only using HMS on the transitional ore. Construction of the flotation circuit has moved along well. We're working in the cells now, and we still expect those cells to be fired up. On the construction side, we're wrapping up the final work in the cells so it lines up with our flotation techniques, and our expectation is that commissioning will begin later in the March quarter. The open question is how quickly we can bring that online and add the extra capacity. That capacity, plus whatever we can stretch Pilgan to, is what becomes surplus capacity for the BMX platform. Honestly, Hayden, it's hard to say with certainty what will ultimately be sold on spot this half. Once the plant reaches full capacity — that's 580,000 tons — roughly 200,000 tons of that becomes available for us to sell however we choose. Right now, we would choose to sell the large majority of it to the BMX platform, because pricing is going to be very strong.
Ken Brinsden
executivePlayers in the chemical conversion business will hand over their margins just to lock in spodumene supply — and if that happens, then spodumene pricing, you know, could surprise everyone by moving higher.
Nicholas Read
executiveThanks, Ken. A few other BMX questions came up, so I’ll bundle them together, and I apologize if we’re repeating anything here, but one of them was: can you confirm whether you expect a BMX option this quarter?
Ken Brinsden
executiveYeah, that one belongs to us. Correct.
Nicholas Read
executiveMoving on to the second question — assuming everything proceeds smoothly at the Ngungaju plant, could you provide some kind of estimate for total BMX sales and tonnages we should expect for this calendar year?
Ken Brinsden
executiveSure, I’d say it’s along the lines of what I mentioned before regarding how quickly the Ngungaju plant ramps up. Once the capacity has been fully built out, I could be more definitive, since at that point you’d have roughly an auction every three weeks, as reflected by the overall excess capacity that reaches the spot market.
Nicholas Read
executiveGreat. Thanks, Ken. We have a question here from Mr. Mills. He says that as the company moves relatively quickly to P680 and P1000, what concerns should there be or are there with shipping movements to markets given global shipping challenges and increased costs?
Ken Brinsden
executiveOh, yeah. Well, from what we've seen, getting access to vessels isn't a problem for us. In our sector there's sufficient trade and enough vessels around that we specifically don't struggle to secure the vessels themselves. The problem is simply what it costs to draw the vessels in. This quarter brought a bit of relief on shipping costs. Shipping costs reached a peak of roughly $70-$80 a ton. Average shipping costs, Brian, if I remember correctly, came in around 55 or something along those lines.
Nicholas Read
executiveYeah. Yeah.
Ken Brinsden
executiveIt's dropped a bit, and that points to more ships being on the market. I'll say again: the issue isn't really whether a vessel can be secured — it's the price of the vessel itself.
Nicholas Read
executiveThanks, Ken. We've got just a couple of market-related questions to finish up with. The first comes from Mr. Zinghini. He's asking whether you could give some commentary on how recent developments have affected the lithium market — for example, the Rio Tinto project in Serbia, as well as some of the political shifts in Chile, and what ramifications those developments might potentially have for lithium supply.
Ken Brinsden
executiveSure. First off, with all due respect to the analysts out there, supply figures are simple to drop into a spreadsheet. Actually delivering those volumes in the field is far harder. Once you get to that stage, many more complications arise. You've heard Pilbara describe the hurdles involved in adding more capacity. We aren't traveling this road by ourselves. Ramping up spodumene supply and lithium units across the globe is difficult, particularly given the need to combine rising volumes with quality. In our opinion, both of those will be overstated, and as a result markets are likely to stay tight for a good while yet. Over the years, plenty of analysts have claimed lithium markets would swing into oversupply and that the world holds abundant lithium — yet what the world lacks is abundant lithium matching the proper mix of location, supply quality, infrastructure access, and jurisdictions free of geopolitical difficulties. Yes. I mean, this is a complicated world for an industrial mineral supply chain that would prefer not to be complicated, yet inherently is.
Nicholas Read
executiveThanks, Ken. Here's one last one, and it's related, but a good note to finish on. This gentleman asks, "The big carmakers are citing large figures for EV output out to 2030. Will there be sufficient lithium to meet those production projections?"
Ken Brinsden
executiveIt may sound like a cliché, but automakers were not paying attention. Over the past five years, they gave too little thought to the base that supplies raw materials for batteries. That is now causing them problems, since not enough incentives were put into the market at the moment they were truly needed—particularly in that window of three to five years ago—to reach the position we must be in today. Too little capital has been moving upstream, there are too few firm offtake agreements that lock in the supply chain, and too few interconnected agreements that give the supply chain a reason to interconnect. Every one of those items is a significant challenge for the industry that ought to have been resolved several years back, yet now it has to be resolved and will require several years to put right.
Nicholas Read
executiveGreat, thank you, Ken. I have nothing further to add.
Ken Brinsden
executiveAll right, thanks. Nick, Rachel, seems we've reached the end here.
Operator
operatorAppreciate it. That brings today's conference to a close. Thanks for joining us. You're welcome to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete PLS Group Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to PLS Group Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in PLS Group Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.