Thanks, Daniel. Hello, everyone, and good morning. It's great to have you with us today. Before we get started, I want to note that we've put together a presentation that goes along with what we'll be talking about, and we'll be pointing to it during this call. You can find those slides on our website, investors.portlandgeneral.com. If you'll turn to Slide 2: a portion of what we say this morning will be forward-looking statements, and we want to caution that these statements carry inherent risks and uncertainties, so actual results could end up differing materially from what we expect. For a description of some factors that might cause our actual results to differ materially, please see our earnings press release along with our most recent periodic reports on Forms 10-K and 10-Q, both of which are available on our website. Leading today's discussion are Maria Pope, our President and CEO, and Joe Trpik, our Senior Vice President of Finance and CFO. After they finish their prepared remarks, we'll open up the line for your questions. At this point, I'm pleased to hand the call over to Maria.

Maria Pope

executive
#2

Thanks, Nick, and good morning to all of you. We're glad to have you joining us today. Beginning on Slide 4, I'll walk through our results for the full year and fourth quarter of 2023, and then I'll discuss our expectations for 2024 and beyond. For the full year, GAAP net income was $228 million, or $2.33 per diluted share, while non-GAAP adjusted net income reached $233 million, or $2.38 per share. That compares with GAAP net income of $233 million, or $2.60 per share, and non-GAAP adjusted net income of $245 million, or $2.74 per share, in 2022. Turning to the fourth quarter, net income was $68 million, or $0.67 per share, up from $50 million, or $0.56 per share, in the fourth quarter of 2022. Even though these results fell short of our expectations, we remain strongly confident in a long-term growth trajectory of 5% to 7%, along with 2024 guidance of $2.98 to $3.18 per diluted share. To start, challenging weather affected the quarter, with mild conditions throughout and the second warmest December ever recorded. That produced extremely low energy usage as well as historically low wind and hydro production. As a result, that mix hurt both our revenue and our purchase power and fuel expense, and performance fell short. The power cost difficulties we faced in 2023 underscore how important the risk reductions secured through the 2024 general rate case are. That includes 500 megawatts of hydro agreements, which strengthens our capacity portfolio, plus the reliability contingency event provision being introduced within the PCAM. These are meaningful steps toward reflecting real power costs and extreme events. More work remains, and we look forward to engaging with the commission, other utilities, and regional stakeholders on a holistic energy framework and solution. Finally, our results also reflect higher costs tied to ongoing capital investment meant to support grid resiliency, customer growth, and decarbonization. Moving to Slide 5. We've said all along that 2023 would be a year of investment. Despite the difficulties we encountered, we hit key milestones that have positioned us for 2024, among them a constructive outcome in our general rate case. 2024 will be a year of growth, and it rests on 3 key drivers: first, continued load growth driven by high-tech and digital customers; second, capital investment to enable that growth, move our clean energy goals forward, and bolster reliability and resilience; and third, continued operational discipline throughout our organization. I'll address each one in turn. First, we anticipate continued strong industrial load growth, backed by state and Federal policies. Microchip recently received $72 million under the Federal CHIPS Act for an $800 million expansion at their facility in <<inaudible>>; that comes on top of multibillion-dollar investments from Analog devices and others; and it builds on the state of Oregon's appropriation of $240 million for semiconductor projects, 85% of which fall within our service territory. Our capital plan now includes extra strategic transmission investments, which will support this high tech customer growth along with other customer growth, plus renewable development. Joe will walk you through the finer details of our plan. Broadly speaking, though, the majority of our transmission work is located within our service territory or immediately adjacent to it. Many of these lower-risk projects involve re-conducting lines that are already in place. On the renewable front, we are currently receiving and evaluating bids for the 2023 RFP, which continues through the first quarter of 2024, and the short list is expected later in the year. Following our prior RFP, the Clearwater Wind project began service in January, achieving a 45% capacity factor, which is impressive; we are also looking forward to our battery storage projects coming online later this year and into 2025. Let's turn to Slide 6. Across the nation, utilities are confronting escalating impacts from extreme weather. This January, a severe storm brought a powerful combination of strong winds, ice and snow, inflicting damage over a broad area and pushing power costs higher; in the face of those extraordinary conditions, we delivered an extraordinary response. That involved more than 1,800 people — crews and support staff — working hard to restore power and repair critical equipment. I want to pause and acknowledge our teams and partners, and thank them for their efforts under very difficult circumstances. The storm came in several waves of severe weather and temperatures in the single digits. Over approximately a week, crews restored power to over 0.5 million customers. That serves as a strong example of our teams coordinating effectively to serve customers at the moments they need us most. Lessons from the severe storms of 2021 informed how we responded, and we continue to improve at what were once events seen only once a decade. That operational focus is apparent elsewhere as well. Our 2023 results demonstrate solid execution on cost management, reflecting our team's extraordinary work to simplify processes, put technology to use and boost productivity. Turning to 2024, we continue building on that momentum. To repeat, 3 main areas hold our attention for growth this year and afterward: first, outstanding customer growth; second, carrying out our capital plan; and third, sustained operational discipline. Given all this, we're positioned well to deliver long-term earnings growth of 5% to 7%, along with 2024 guidance of $2.98-$2.18 per diluted share. With that, I'll hand things to Joe, who will take you through our financial results. Thank you.

Joe Trpik

executive
#3

Thanks, Maria, and good morning to all of you. Before I take you through the results and outlook, I'd like to recognize that we didn't submit our 10-K this morning the way we normally do. We're in the final stages of preparing the necessary documentation for the 10-K and wrapping up the related compliance steps. As many of you are aware, we completed a new ERP software implementation during the fourth quarter. Because of Monday's holiday, you'll see our filings with the SEC go up on Tuesday morning. Now let's move to Slide 7. Our 2023 results show ongoing industrial load growth, volatile weather and power cost conditions, progress on our capital plan, and a strengthening growth foundation. Weather played a significant role in our 2023 results, especially during the second half of the year. Compared with 2022, we had 11% fewer cooling degree days and 13% fewer heating degree days. Q4 included historically mild stretches, with our regions experiencing the second warmest December ever recorded. On the whole, we saw 15% fewer heating degree days than the 15-year average. Customer usage was impacted by those conditions, and power costs were under pressure as well, since renewable production was hit hard during those mild periods. PGE's wind farms produced 23% less energy in Q4 2023 than in Q4 2022, which meant generation — PGE's thermal fleet had to cover much of the gap. In the end, these dynamics created a substantial headwind to delivering the level of power cost favorability we had expected for the year. Loads in 2023 rose 0.9%, or 1.4% on a weather-adjusted basis, versus 2022. Residential load for 2023 fell 1.7% year-over-year, or 0.5% weather-adjusted, due to mild weather and energy efficiency, while residential customer count grew 0.8% for the year. Commercial load was slightly lower, down 0.3%, or 0.2% weather-adjusted, against 2022, mostly because of energy efficiency. Solid industrial load growth carried on in 2023, up 5.9%. Over the past 5 years, we've seen a 7.5% compound annual growth rate in industrial load, as high tech investments and AI expansion have fueled growth in semiconductor and data center demand. Although total loads in 2023 came in below what we expected, our service territory fundamentals and our load outlook stay strong. Unemployment in our region is 3.4%, below the national average of 3.7%, and we keep seeing other positive indicators; public and private sector investment suggests broader economic development and continued load growth in 2024 and beyond. I'll now go through our financial performance year-over-year; we saw a $0.14 decrease in revenues, excluding power costs and regulatory program collections, driven by a $0.13 increase from the 0.9 increase in deliveries and a $0.27 decrease from changes in the average prices of deliveries due to higher industrial load and lower residential and commercial loan. Power costs produced a $0.25 increase in EPS, driven by a $0.29 EPS increase from power cost headwinds in 2022 that reversed for this comparison and a $0.04 EPS decrease from higher power costs than anticipated in the annual update tariff. Handling the load when August's heat wave hit, plus how gentle weather affected renewable output in Q4, were the main drivers. Operating expenses — after stripping out deferral-related items — pushed things down by $0.01. Thanks to our work on efficiency and managing costs, especially during Q4, we managed to hold base O&M basically level compared with the prior year. Moving on, several effects came from carrying out our long-term capital plan: depreciation and amortization ran higher, cutting $0.19; interest expenses rose, taking off $0.16; AFUDC came in higher by $0.10 thanks to continuing investment, such as the Clearwater Wind development we just finished; and dilution from equity forward sale draws in 2023 reduced things by $0.22. Other items added $0.01, which included stronger returns on benefit plan assets and regulatory interest, partly offset by a benefit plan buyout in 2022 that didn't happen again. Finally, the Boardman settlement refund lowered GAAP EPS by $0.05, which brings us to GAAP EPS of $2.33 per diluted share. Once we adjust for that $0.05 effect, our 2023 non-GAAP EPS comes out to $2.38 per diluted share. Now looking at Slide 8, where our newest 5-year capital forecast appears: estimates for 2024 through 2027 have been raised by $1.2 billion, since we aim to maximize customer value through system-wide upgrades and new transmission investments. These transmission efforts will target network enhancements designed to ease congestion, boost adequacy and reliability, support decarbonization and handle customer growth. Transmission projections for 2028 also factor in PGE's anticipated share of the Bethel-Round Butte transmission line upgrade, a project we'll carry out alongside our longtime partner, the Confederated Tribes of the Warm Springs. The previously announced $250 million in U.S. DOE grants given to the tribes will help support this project. Once planning and scoping wrap up for this project and other grant-related ones, we'll revise our estimates and fold them into a later forecast. We've also sharpened what we expect for base capital spending to back grid modernization, system hardening and technology investments. Keep in mind, this chart leaves out CapEx tied to possible ownership arising from the 2023 RFP we recently launched, which reached the market on February 2. The competitive bidding schedule, posted on our RFP website, calls for bid submission, final shortlist selection and shortlist submission to the OPUC by mid-2024. We expect project selection in Q3 or Q4; that timing hinges on how many bids come in and how complex they are, and we'll keep you posted as the competitive process moves along. Although we're still weighing timing, added base CapEx meant to deliver customer benefits, together with the incoming battery projects that improve group flexibility, tip the scales toward a near-term rate case filing. Following our usual approach, we'll let you know about any steps we take on a rate case filing. Moving to Slide 9, our liquidity and financing summary. Total available liquidity as of December 31 stands at $969 million. We still have the same solid balance sheet, investment-grade credit ratings, and stable credit outlook that we reported before. By the end of December 2023, we had signed full sale agreements covering $78 million out of the $300 million accessible through the ATM. So far, no draws have been made under these forward agreements. Looking at the rest of 2024, we expect to issue as much as $730 million in debt over the year, and wherever feasible, we intend to keep issuing through our green financing framework as we've done. On the equity side, the ATM still had enough capacity to cover our base capital financing needs, which includes the battery projects we currently have in progress. The ATM gives us a useful combination of capital access and dilution management that backs our ongoing base capital plan. Managing our capital structure continually and moving over time toward our authorized 50 to 50 ratio stays a top priority. We keep our financing options flexible and stay confident about accessing debt and equity markets competitively whenever needed. As more capital investment opportunities reach maturity, including those from the RFP, we'll keep assessing our strategy and bring you updates on our financing plans. Moving to Slide 10. We are introducing full year 2024 adjusted earnings guidance of $2.98 to $3.18 per diluted share.

Joe Trpik

executive
#4

As Maria noted earlier, January's storm system hit our service area hard, and we're continuing to assess the implications of that multi-day occurrence. At this point, our estimate for storm restoration operating expenses falls in the range of $35 million to $45 million, along with about $15 million in capital spending to repair the damaged assets. We filed earlier this month for a deferral of those costs through an existing emergency restoration deferral. Because the region saw market price spikes, balancing authority alerts and resource adequacy constraints on PGE system, the criteria were satisfied to activate the first reliability contingency event treatment under the revised power cost recovery framework for MACT. Through the RCE mechanism, PGE can seek recovery of 80% of the cost for the RCE above what was forecasted in the AUT, while the remaining 20% goes through the existing PCAM. Our current estimate for the RCE cost falls between $85 million and $100 million. We're still finalizing these impacts, but we'll share more detail when we report Q1 2024 results. Due to how unprecedented and unusual last month's storm was, we are leaving its impacts out of our 2024 guidance, and they will likewise be removed from our adjusted non-GAAP results for 2024. Doing so supports better comparability of earnings and gives a clearer picture of our continuing financial performance. We anticipate this will mean removing the 20% share of RCE cost that cannot be recovered, along with any operating costs deemed unrecoverable under the mechanisms already in place. Now I'll discuss the other factors shaping our 2024 guidance. As I noted before, we still have strong confidence in our service territory, as shown by ongoing load growth among industrial customers and slight gains in the residential and commercial classes. Taken together, we are assuming weather-adjusted retail load growth of 2% to 3% for 2024. Those patterns of demand, along with the money we keep putting into the region for a backlog of projects still to come, keep reinforcing our belief in the load figures we've projected for the long haul. Because of that, our guidance for load growth over the long term — 2% all the way through 2027 — stays where it was. On O&M, we're looking at somewhere between $815 million and $840 million. That figure takes in $165 million tied to regulatory deferral amortizations that don't affect earnings, plus costs for wildfire mitigation and vegetation management, and various other items that offset each other. Once you strip those out, the middle of our O&M range works out to a 3% compound annual growth rate measured against the 2022 base O&M with comparable offsets removed. We're still focused on bringing in the right tools to get the most out of our productivity and deliver top-tier service to customers, all while keeping operating costs in check. That approach, together with the risk-reduction progress we achieved and the key investments we made during 2023, keeps our confidence in the growth strategy strong. Because of that, we're restating our guidance for long-term earnings growth and dividend growth at 5% to 7%. With our sights now set on the coming year, our central priority stays the same: delivering clean, reliable and affordable energy safely, while creating value for our communities, our customers and our shareholders. Operator, at this point we're ready to take questions.

Nick Campanella

analyst
#5

So I'd say this is a fairly significant step up in the base CapEx plan. Could you help us get our heads around whether there are any further equity needs on top of the $300 million ATM you flagged in the slides? And maybe I'll stop there for now. Then, given this new CapEx plan, where would you say you sit within that 5% to 7% EPS CAGR?

Maria Pope

executive
#6

Sure. Thank you so much. To start, one of the additions you're seeing — we broke it out and listed it separately from what we'd previously presented — is our transmission investment plan, and that's likely to keep growing going forward as well. Then, on your questions about our equity offerings or where we're looking at the ATM: the ATM will handle what's required for the foreseeable future, batteries included. We're waiting to find out where we land with the RFP projects that may come in, and those could call for extra capital. Our confidence in the 5% to 7% growth rate hasn't changed. And you'll see that carry forward with confidence as we look toward 2024, which is a really strong year for us thanks to how our rate case turned out, customer growth, and the capital plan we just went over.

Nick Campanella

analyst
#7

All right. So regarding the base plan as it stands right now, it's simply the equity funding that's required at present to carry out that base plan. Clearly, that could shift once this RFP arrives, and we'll find out what portion you're able to hold versus what you aren't. Is that the correct way to put it?

Maria Pope

executive
#8

Yes. You've got it right, Nick.

Nick Campanella

analyst
#9

All right. And then, I suppose, regarding those storm-related costs — I get that a piece of that is being pushed out. You mentioned a range of $35 million to $40 million, and then $85 million to $100 million tied to the RCE costs. Put simply, how much of that is genuinely being deferred, as opposed to being left out of the non-GAAP figure for '24?

Maria Pope

executive
#10

Absolutely. I'll have Joe handle that one. And something I'd like to point out is that this really was an event unlike anything we'd normally see — not just when it comes to the restoration work involving customer outages, but across the whole region, the energy markets were in a state of serious turmoil. Joe?

Joe Trpik

executive
#11

So Nick, let me kind of take that from the back end. On the cost side, what we'd anticipate wouldn't get deferred — that's the operating piece — the exclusion there would land somewhere from $0.10 to $0.15. And everything else we discussed, I think, would fall under deferral through one of those 2 mechanisms we brought up earlier.

Jim Kennedy

analyst
#12

James speaking, covering for Shar. To kick things off on the demand side — some background here is that a great many semiconductor makers and AI-oriented data centers have been attracted into your service area. Can you help us understand the way AI is fueling expansion among the various customer categories, from your vantage point? And beyond that, any details you can share about the kinds of additional generation or transition possibilities taking shape further out, especially coming from those customers?

Maria Pope

executive
#13

Absolutely. What a great question. Looking at the long run, we have without question served as a center for semiconductor production going back many decades. About 15% of semiconductors are produced inside the area we serve, and we're expecting substantial growth over the longer term. Putting up those plants requires a lot of effort. AI-driven data centers are easier to construct and deliver growth sooner, covering both the giant facilities and certain grid edge computing projects. So demand is coming in heavily from virtually every hyperscaler and cloud computing firm around, which represents an enormous opportunity on our end. Nearly all of these businesses want 100% clean energy. Frequently they supply their own backup reliability and want extra transmission substation infrastructure, among other things. This means there's room for considerable expansion down the road. When it comes to the neighborhoods we support along with our other clientele, putting money into upgraded infrastructure makes our service dependability and ability to bounce back stronger across the board, while also delivering crucial employment opportunities locally, revenue from property taxes, and various other notable advantages.

Jim Kennedy

analyst
#14

Understood. Then, turning to the regulatory angle, Joe, you gave a hint about this near the close of your prepared remarks. My assumption is that the schedule for new rates, January 1, '25, would involve the new GRC filing within the coming week or 2. Could you perhaps provide a bit more detail regarding your perspective on the timing?

Joe Trpik

executive
#15

Certainly. So, our thinking on the schedule hasn't been finalized, though what you said is accurate. According to Oregon's regulatory framework, there is a 10-month window; therefore, should we desire rates to take effect immediately on January 1, a filing would have to be made by the close of this month. We are still in the process of finalizing our thinking and approach, and we will of course share that once we have it. As I said earlier, certain items are adding weight to the scale, including the batteries coming online and some other items that we would anticipate, requiring additional time to recover.

Julien Dumoulin-Smith

analyst
#16

So, picking up on what just came out of the Oregon PC — specifically the clean energy plan getting turned down. I'd like to grasp this a bit better, okay? Since clearly, this is partly a near-term matter versus a longer-horizon one. Regarding that 100% target, what signal are they attempting to deliver, particularly when weighed against affordability? And I'd really value hearing it in your own words — some sense of how the various pieces currently in play break out? Then I have a quick follow-up.

Maria Pope

executive
#17

Certainly. No, that's a terrific question. To begin with, this marks our inaugural clean energy plan; and I do want to give credit and note that our integrated resource plan received acknowledgment, and we're proceeding on the basis of that IRP. The questions really centered on modeling that gets more granular when it comes to admissions. Our modeling of admissions has been done on a day-by-day basis, and their preference is to see emissions modeling done hour by hour. Broadly speaking, as you'll recall too, back in July our initial IRP was upsized fairly substantially — for added energy requirements along with added capacity requirements. And I believe there's further conversation happening among stakeholders and key constituents concerning how we'll satisfy those added requirements through more renewable energy plus other infrastructure. So it's a fine moment for a constructive conversation about what is genuinely a dynamic, fast-expanding environment here.

Julien Dumoulin-Smith

analyst
#18

Yeah, absolutely. And I just want to confirm I've got the main point right. I mean, it feels like there's a bigger issue around how you reach that 100%, in the sense that maybe more is required, again, since I'm aware there have been moments when affordability has drawn intense attention, and maybe there's a way to open up and guarantee an avenue toward affordability. I simply want to be certain I'm correctly hearing where this long-term rejection originated.

Maria Pope

executive
#19

What drove it, Julien, was above all a requirement for further emissions modeling. The fuller picture, though, is that we're witnessing quite substantial upward shifts in energy consumption, and we want to genuinely grasp where the economics behind each of those procurements come from. When we add renewable resources — Clearwater makes a solid illustration — what we find is that customer prices don't respond the way we'd expect while we're pushing out costlier purchased power from the market. So the extra renewable procurement really isn't moving customer prices to the degree someone might assume when we project it out. What's actually moving customer prices going forward is the broad investment need, an aging infrastructure, and backing major customer growth — that matters more than building out clean energy.

Julien Dumoulin-Smith

analyst
#20

Of course. Julien Dumoulin-Smith here; on that subject, there's a significant rise in transmission spending, which isn't too shocking considering the signals you've been sending lately regarding transmission requirements. Could you lay out how you view potential upside in generation, given the increased spending level, particularly for transmission? Should we keep viewing this as additive? Has your approach to directing capital toward generation changed? I'm aware you're restating the 5% to 7% range, yet occasionally there seems to be a limit on how far you're willing to grow your core rate base, given all the different demands. Might some investments be delayed? Or should we really see this as purely additional on top of other incremental chances?

Maria Pope

executive
#21

Absolutely. Customer pricing must always come first for us. Clearly, we've observed strains on customer prices, and we're highly sensitive to what our customers need, ensuring affordability remains the top priority. A key reason we hold competitive RFPs for renewable generation capacity and energy is to secure the best possible prices for customers through competitive bidding. We've succeeded in those before, and we aim to keep providing the lowest cost, least risk clean energy resources to customers that is notably available. As for transmission, there's some adaptability. A portion of this transmission spending was part of our historical run rate. Some is fresh and additional; we view it like concentric circles. The innermost circle is inside our service area, directly affected by customer growth. The next one is to deliver clean energy from our region or right next to it to our customers. Then the third involves wider investments throughout the Northwest. A major jump as you look farther out on the chart in 2028 is the Confederated Tribes of the Warm Springs project on our current <<inaudible>> line, where we got a $250 million Department of Energy grant to greatly expand that existing line, with most of it continuing over existing rights of way. So when it comes to transmission, we're concentrating on relatively straightforward to implement—and my colleagues might argue transmission is never straightforward to implement—but comparatively lower risk projects inside our service area, aimed at repowering and expanding current rights of lines.

Julien Dumoulin-Smith

analyst
#22

Great, thanks. That's excellent. If you don't mind, I just have a quick housekeeping question about the ITC. For the battery, will that show up in one year, or is it spread across 5 years? How should we think about the accounting for these ITCs, quickly, since this is kind of a new topic in storage and regulated land?

Joe Trpik

executive
#23

Julien, when it comes to recognition, those ITCs will be recognized as the battery starts operating, and given that we have 2 batteries coming online during '24 and '25, our expectation is that we'll recognize those ITCs — what I'd describe as onto the balance sheet — and the customer gets the benefits of those ITCs, which we'll set out in our next regulatory filing, and those will be amortized to them. Julien, I believe the real question here is that after we get them onto the balance sheet, the expectation is that we'll monetize them fairly soon after that. So once we recognize them and there's certainty around the ability to transfer, we'll be seeking to monetize it.

Julien Dumoulin-Smith

analyst
#24

Understood. That's happening pretty much simultaneously. Understood. Great. So — and that's going to appear on the income statement?

Joe Trpik

executive
#25

The monetization is going to come through as cash flow, correct, from buying and selling the ITCs, and for us, income will be neutral on the income statement.

Gregg Orrill

analyst
#26

About the rate case that's on the way, do you have any initial views regarding how big a rate increase might be, or any views about affordability as we head into it?

Joe Trpik

executive
#27

Clearly, affordability for the customer is always where we begin when we open a case, and we're also mindful that a prior case has taken place. In this instance, my expectation is that the real emphasis will fall on the batteries — the assets placed into service to keep driving reliability forward, add capacity to the system, and also small amounts of cost. What I mean is, I think this will mostly amount to simply an infrastructure update to the plan, and affordability stays our focus.

Paul Fremont

analyst
#28

So my initial question — considering those January storm deferrals — is whether you plan to recoup that money through the rate case you've got on file right now. Or does it sit outside what that case can address, since it happened so recently?

Joe Trpik

executive
#29

Paul, the way storm recovery works, it actually moves through 2 distinct tracks rather than the general rate case; both of those tracks are mechanisms that already exist; so — when it comes to the operating costs, roughly, plus the reconstruction costs, those go through a deferral rider that gets filed and has a proceeding of its own, which is — and then — when it comes to the cost of the energy and the RCE event, that moves through the PCAM process. Each one follows a somewhat different timeline; take the PCAM process, for instance — it wouldn't be filed until 2025, and the recovery from it, that would find its way into 2026.

Analyst

analyst
#30

What about the schedule for getting OpEx back — is that something you'd typically see happen inside 12 months, or could it be quicker?

Joe Trpik

executive
#31

That recoupment is going to be left to the commission's judgment. Typically, because of how big these storms are and how material they are, they get paid back across a longer stretch. The most recent instance of this kind of storm cost recovery took 7 years to complete. And there's another thing we'll examine — I'd put it this way, we'll also check whether either one qualifies for securitization, and that, clearly, can alter the recovery timeline too.

Analyst

analyst
#32

All right. Then when we consider the increased base CapEx, what's the right way to view that alongside how you bid into the renewable RFP? Given the size of that CapEx increase, would you aim to win fewer RFPs, or would your business strategy essentially stay unchanged?

Maria Pope

executive
#33

Our approach to bidding now, our approach to bidding moving forward, and our approach to bidding previously has never differed, and that means delivering the most competitive projects at the lowest cost and with the least risk for customers; and those projects come out ahead, they benefit customers, and they support financing.

Analyst

analyst
#34

All right, and after that, it appears that CapEx is going up by $200 million to $300 million on a yearly basis. When we consider that additional spending, should we assume it's financed about 50% through equity? Is that a reasonable way to view how the financing works?

Joe Trpik

executive
#35

When we consider our long-term financings, I believe we keep looking at using flexibility, managing our capital structure, and continuing to shift toward 50 to 50. So if you assume that over time, that balance level would be the focus, that would be a sensible way to view it.

Analyst

analyst
#36

Great. Then for my final question, I think there's a significant increase in transmission and spending in '28. I was just curious about what explains that.

Maria Pope

executive
#37

Sure. That connects to what Julien asked earlier — it's the Pelton Round Butte to 230 line, which is slated to be upgraded to 500 kV alongside the Confederated Tribes of the Warm Springs. We said before that a $250 million grant from the Department of Energy was awarded for this effort. Clearly, the price tag on that project would exceed $250 million. It stretches beyond 100 miles, and it would take multiple years, with the first year we're expecting being 2028.

Analyst

analyst
#38

So would the amount we're putting into transmission sort of remain at that elevated level for a number of years?

Maria Pope

executive
#39

Likely for 2 years following that, in 2029 and 2030. That transmission line, along with the addition, also unlocks a substantial chunk of Oregon's central region for more renewable build-out alongside the tribes; right now we share ownership of multiple hydro facilities with them. So this is going to permit a major increase, especially in solar, but truly turning the central portion of Oregon and the Confederated Tribes of the Warm Springs Reservation into a chance for additional development all the way through 2028 and past that.

Analyst

analyst
#40

Then for my final question, considering the increase in CapEx, what percentage rate base growth does that provide through '28?

Joe Trpik

executive
#41

Paul, in the companion document we filed this morning as well, for the base capital—covering transmission and the line Maria referenced—that places us at approximately 8% rate base growth. Also, within that update, we've created certain scenarios about an RFP result, and that revision would give you—assuming a 25% result—a 9.2% rate base through '28.

Travis Miller

analyst
#42

A quick thing about the battery side of things — that bump in the 2024 figure, does it come from new projects, or is some of it money carried over from 2023?

Joe Trpik

executive
#43

To be specific, on the battery, what you're seeing is the 2021 RFP shifting later. In fact, all of the battery spending you see in '24 and '25 came from that RFP, and it goes like this — the first batch of spend is the console project, or the smaller battery, and then the spending that lands in 2025 is the seaside battery, which is the bigger one.

Travis Miller

analyst
#44

Alright. I was considering the comparison with the earlier capital update, which I believe went from $100-and-something million to $235 million.

Joe Trpik

executive
#45

These are the identical batteries. No projects have been introduced by us. This represents the revised pricing for those very same batteries.

Maria Pope

executive
#46

So there were some payments that went from 2023 to 2024.

Travis Miller

analyst
#47

Understood. All right. All right. Yeah. That matches my thinking. Then, on a connected point: regarding the battery portion in particular, how much of that CapEx within those payments do you expect can be included in the rate case, considering — and tell me if I have this wrong — considering they likely won't be finished, correct, up and running within the next couple of...

Joe Trpik

executive
#48

When we refresh the — so at the time we make the filing, the filing will appear — we'll rely on a projected rate base figure. So we'll rely on a rate base as of the close of 2024; and once we — at the moment we choose to file, we'll put a mechanism in place there that would anticipate cost recovery for the batteries as of their in-service date. The first one, the console battery, whose in-service date falls somewhere right around the close of 2024, and after that the seaside battery, which enters service during 2025. As you might remember from our earlier case and whenever we submit whatever we submit in our subsequent case, we'll take up the RAC, or the renewable adjustment clause, which permits renewables to enter service. Earlier we had asked for batteries to be added in that provision. That way they simply enter service automatically. Once more we'll examine, as part of our filing, how to handle that policy, and possibly weigh additional policies, to make sure the batteries enter service promptly, just like other renewable assets.

Travis Miller

analyst
#49

Alright, that's quite useful. Now for another question. With capital spending going up and what you've said about returning to a particular capital structure, how does that affect the dividend growth you're expecting?

Joe Trpik

executive
#50

What we expect is that as growth continues, we remain committed to holding to that 5% to 7% earnings growth and dividend growth in a similar range; therefore we don't anticipate any shift to our dividend growth rate relative to the plan we laid out before.

Travis Miller

analyst
#51

Okay. In line with earnings?

Joe Trpik

executive
#52

That's right.

Analyst

analyst
#53

Quick question, circling back to the equity side of things. Looking at the balance sheet, debt to cap — you closed out 2023 at roughly 56%. At what point do you expect to be nearer to that permitted 50% you received in the most recent rate case?

Joe Trpik

executive
#54

Okay. As we put together the 5-year plan, we've factored in a trajectory that moves us toward that 50% across that stretch, with some latitude around the timing in between, depending on peers, depending on the RFP, depending on how a with and without RFP scenario plays out. So we've got, in effect, a set of adaptable approaches that will carry us to that point across what I'd describe as these longer planning horizons.

Analyst

analyst
#55

Got it. And turning to battery storage for a moment — with load growing, should we expect to see more of that? Or is your generation spending leaning more toward conventional renewables?

Maria Pope

executive
#56

Honestly, I believe we'll be seeing both. Capacity really matters, obviously, especially given how unpredictable the weather has been lately. So additional batteries will come in, I'd expect, by way of RFPs. And beyond that, you'll likely see more wind and solar, the more conventional renewables. On top of that, independent power producers have been developing some pumped storage projects, plus other efforts that sit further out on the timeline. So as we go forward, this really amounts to what I'd describe as a whole set of solutions. And we're collaborating very closely with our customers too — on how they use energy, on flexibility, and on standby generation — so that every resource gets brought to bear throughout this transition.

Maria Pope

executive
#57

Wonderful. Many thanks. We're grateful that you've taken an interest in Portland General Electric; 2024 has us enthusiastic, with the ongoing expansion of our high-tech digital customer base. Our capital plan is there to back that expansion in renewable development, plus our ongoing emphasis on operating costs and operational excellence. We're eager to reconnect with all of you shortly, and we truly appreciate your presence with us today.

Operator

operator
#58

This concludes today's conference call. Thank you for participating. You may now disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Portland General Electric Company transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Portland General Electric Company earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Portland General Electric Company or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.