Power Mech Projects Limited (POWERMECH) Earnings Call Transcript & Summary
February 18, 2020
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and welcome to the Power Mech Projects Limited Q3 FY' 20 earnings conference call, hosted by Nirmal Bang Equities Private Limited. <<operator_script>> Kindly be aware that this conference is being recorded. I'll now turn the conference over to Mr. Chirag Muchhala of Nirmal Bang Equities Private Limited. Thank you, and the floor is yours, sir.
Chirag Muchhala
analystYes, thanks. On behalf of Nirmal Bang Equities, we're glad to have everyone with us on this conference call covering Power Mech Projects Limited's 3Q FY '20 results. With us from the management side are Mr. S.K. Ramaiah, Director, Business Development, and Mr. J. Satish, CFO. I'll now pass things over to the management for their opening remarks, and after that we'll open it up for questions. Over to you, sir.
Jami Satish
executiveYes. Yes. Thank you, Chirag. Dear friends, good afternoon. Satish speaking. We're glad to update you on recent developments at Power Mech. First, we'll spend a little time on quarter 3 results along with some updates regarding Power Mech Projects Limited. In Q3 — quarter 3 FY '20 — total turnover, other income included, came to INR 547.44 crores. Segment-wise, Erection contributed close to INR 201.47 crores, while Civil business added INR 147.31 crores. O&M came in at close to INR 162.65 crores, and Electrical stood at close to INR 33.99 crores. In the prior year, Q3 turnover including other income was INR 612.84 crores. That's a dip of 11%. On the revenue business — turnover from the Erection business has risen by 5.6%, with traction in line with INR 180 crores to INR 200 crores, moving well. And O&M, as you can see, is also moving from INR 140 crores to INR 160 crores. Growth there is almost 11.73%. For Electrical, we had estimated a slightly larger number. There has been — but still, it has gone up by INR 46.64 crores versus last year, and the dip is largest in the Civil business.
Jami Satish
executiveThe overall 10.67% decline comes from the Civil and Electrical segments. On top of that, we saw some shortfall in a handful of orders we had projected — for instance the electrification work from Sadulpur, which is in Rajasthan, OH Electrical work. We expected roughly INR 128 crores there, but engineering clearance got delayed, so turnover fell short by INR 55 crores. Likewise, on the Ramayampet Canal work — INR 374 crores of work in Telangana — we planned about INR 100 crores, while the actual came in at INR 34 crores due to certain right of way issues. That means a shortfall of INR 100 crores. Beyond that, in Q3 of last year the AMTZ project from Andhra Pradesh — a short-term project — added substantial turnover in Q3 of last year, and we finished it in Q1 of this year. All these things played a part in the somewhat lower projection. Yet looking at 9 months, turnover is more or less flat; despite the Q3 dip, we managed to deliver flat turnover. Revenue from the Erection business stands at about INR 559.83 crores, Civil at INR 428.58 crores, O&M at INR 474.07 crores, and Electrical at INR 104.77 crores.
Jami Satish
executiveOur total turnover stands at INR 1,567 crores, and when you add other income and higher income together, it comes to roughly INR 1,575.98 crores, compared with approximately INR 1,615.85 crores in the prior year. That represents a modest shortfall of 2.47%. On the EBITDA side, margins have held more or less steady. For Q3, EBITDA is around INR 74.21 crores versus INR 80.97 crores a year earlier. So with turnover dipping by 10.67%, EBITDA has declined by 8.35%. PAT for Q3, meanwhile, is INR 36.41 against INR 33.88 crores last year. The increase there is mainly due to the tax benefit, that is, the reduction in tax. Likewise, for the 9 months, EBITDA is approximately INR 211.52 crores compared with INR 216.77 crores last year. So with turnover down 2.47%, EBITDA will decline by 2.42%. PAT, however, is around INR 100 crores, versus INR 86.68 crores a year ago. It has therefore risen by almost 15% — despite a 2.47% dip in turnover, PAT is up nearly 15%. The tax change has helped in this regard, though not in the sense of driving PAT higher.
Jami Satish
executiveAnd for both Domestic and International — if you look at 9 months, International business revenue is close to 17%, while last year it was close to 23%. A very small decrease in business from Oman and Saudi, but Bangladesh is picking up. So more or less, it should be in the range of 19% to 20%. And similarly, the mix between power and non-power: for 9 months, revenue from power is close to 67%, and that includes both O&M as well as Other power activities, and non-power is close to 33%, whereas last year, it's 68% and 31% — 68% and 32% — so more or less the mix is the same. In terms of balance sheet, net working capital days remains close to 160 days. We anticipated some relation to happen from the AMTZ Andhra Pradesh project. So we anticipated close to INR 20 crores plus to come during January — that got postponed. The government has assured to give close to INR 20 crores during this month. So we planned January, February and March to realize the complete amount from Andhra Pradesh. But the way it looks like, it may get postponed one more month, April, because this month, they're planning INR 20 crores of allocation.
Jami Satish
executiveSo we might receive INR 20 crores plus some additional amount in March. That means a portion could slip into April. Once that comes in, net working capital days should improve somewhat. As for debt, gross debt is more or less the same as what we had in Q2. And on net debt, today it stands at close to INR 298 crores versus INR 322 crores in the last quarter. So there has been -- despite a delay from Andhra Pradesh and all, we were trying to manage our working capital and receipts and payments within the existing limits. So we made an effort to bring net debt down, that is where the focus is, and probably with the help of AMTZ realization, year-end debt may come down slightly. That is what we are working towards. And on order booking, today we have a backlog of INR 4,928 crores, which is a completely executable order book. And besides that, close to INR 1,300 crores of orders that are at L1 stage, and we are about to disclose those orders perhaps in the next 7 to 10 working days. And by year-end, we plan to add another INR 800 crores to INR 900 crores.
Jami Satish
executiveWith that in mind, our plan was INR 4,000 crores, and if things feel comfortable, we might add INR 3,800 crores plus. Should that come through, the backlog order book that can actually be executed would be near INR 6,300 crores by year-end. That gives us comfortable visibility for the next 2.5 to 3 years of robust growth. I'd ask Mr. Ramaiah sir to add a few more points on development.
Sudha Kodandaramaiah
executiveYes. Thank you, Satish. To carry that forward — on the business development and marketing fronts, we had a factor last year, perhaps jobs, and accordingly our backlog now stands at INR 4,907 crores, comprising INR 3,448 crores from power and INR 1,473 crores from non-power. I think at the year's end, we are confident about the INR 4,000 crores projection; many things are happening. In particular, what has occurred is that certain projects got postponed for tendering and finalization. And still, we are hopeful about quarterly L1 status, as Satish has said; some more jobs we have to focus on, and we should be able to do this. Coming back to certain immediate opportunities and the business outlook: see, we are focusing on 2 major projects presently. One is Khurja 2x660 megawatt, that is the SJVN project — sorry, THDC, Tehri Hydro Development Corporation, owned by. Another is the Buxar project 2x660 megawatt owned by <<inaudible>> Jamuna Hydro Project. Now in these 2 projects, L&T has taken the EPCs job in the case of Buxar, and we are trying to look at the opportunities on the boiler erection.
Sudha Kodandaramaiah
executiveWe've already submitted the offers, and some discussions have taken place. For Khurja specifically, the EPC job was divided between 2 parties: L&T handles the boiler package, while the Turbine Island sits with the BHEL package. Beyond that, we're also examining a number of balance of plant opportunities at that site. In fact, roughly INR 800 crores of opportunities there are what we're targeting, from both the L&T side and the BHEL side. On top of that, there are independent BOP packages such as material handling, which is currently at the tendering stage. We are in the process of tying up with thyssenkrupp, and that will be a substantial package amount of INR 300 crores. Then there's boiler work — 2 boilers, 2 turbines, then the TG Island, civil and structures work, boilers plus civil and structural work. So that is where the overall target lies. These are the 2 important projects we need to focus on over the coming couple of weeks and months. Then, aside from this, there are 2 — 1 project that keeps getting postponed, NMDC. I think we have dwelt on it many times; it has been going on over the last 3 quarters.
Sudha Kodandaramaiah
executiveOur price bid was submitted during the second quarter. We anticipate closing it by the third quarter; regrettably, certain procedural matters have come up. At this point, every prebid — preprice issue concerning terms and conditions has been settled. We're waiting for the final revised configuration of the price bid. The customer has indicated they will request it by the close of this month. As soon as that arrives, we'll have clarity on where we stand. That package matters greatly for our future growth. It also represents a significant diversification move into material handling. Here we've adopted a consortium approach together with thyssenkrupp, and it will be a substantial order. I'll keep you informed as things develop, but their figures we prefer to hold back given the competitiveness involved. Still, it's a substantial thing if it happens. On new development, that can be in JSW — we're already executing roughly INR 330 crores of work in the non-power sector at the steel plant in Dolvi and Vizag — sorry, Vijayanagar. They had a major expansion plan from 13 million to 18 million tonne; because of steel price issues, those expansion plans have been put on hold for another 6 months to 1 year.
Sudha Kodandaramaiah
executiveHowever, there's a particular package where they're placing their expansion plans on the Coke Oven, along with a portion of the structural work, and we've already secured that at roughly INR 126 crores. Then, an opportunity exists for the Coke Oven equipment piping worth close to INR 150 crores. Finalization on that should happen by the close of this month. So we're feeling positive, though it hinges on how we price things on a competitive basis. And given our performance with JSW at Dolvi, which has been quite commendable, even when compared to L&T, they might extend some preference to us—but in the end, it comes down to competitive pricing. For this year, I think we'll concentrate on it. Then there's the FGD story—a lot has happened over the last 1 year, and I believe I updated you on this last time as well. Of 164 gigawatts, nearly 65 gigawatts have been awarded. And right now, we're in ongoing discussions with GE. GE has approximately 22 units totaling 13,940 megawatts, but they haven't been able to find the right partners for site execution across all those units, and earlier they tried with smaller parties and didn't succeed. Now they've come back to us.
Sudha Kodandaramaiah
executiveWe held 2 rounds of talks with them. And at this point we're trying to see what opportunities come out of this 13,940, 50% — we've attempted to speak with them. And we've also tried to set up a back-to-back arrangement covering 1 or 2 projects, including all of the site works. That means the overall opportunity is roughly 17 sets in GE, 7000 megawatts. We're aiming at 50% of that. So something ought to move within the next couple of months. That's on the FGD side. Then, on the non-power side, I covered it with respect to the — mainly JSW and then the NMDC material handling. And on the O&M side, a new development has come about. Vedanta — we're already at work on 4x600 megawatts. And they're now moving to a revised bidding process for a comprehensive offering across the whole O&M for the next 5 years to a very strong party. As of today we work under Vedanta, not on a comprehensive basis, but at field-level operation. Now they want total responsibility, at least 1 agency. We're in dialogue with JSW and then <<inaudible>> — whoever wins the job, perhaps we'll be there alongside them to work it. And beyond that, since we've built a track record of working with them over the last couple of years, we'll be the preferred subagency for whoever takes that job.
Sudha Kodandaramaiah
executiveBeyond that, at the 9x135 megawatt Jharsuguda site as well, they're looking to move toward comprehensive O&M. So both of these opportunities — there are three plants: 9x135 megawatts, 4x600 megawatt, which is up for renewal, and then 3x30 megawatt across Jharsuguda and Lanjigarh combined — put our total opportunity at roughly INR 1,000 crores. At least a portion of this should materialize within the coming couple of weeks or months. That covers the O&M side. Moving to infrastructure, we have numerous projects underway. At Khurja, we're in discussions with BHEL and L&T. Also, some of the civil work within FGD, since FGD work and the site involve both civil and mechanical work — that too we're discussing with GE. As for new developments in the power sector, there isn't much to expect. Just 2 plants are anticipated to reach the bidding stage: Singrauli 2x800 megawatt, which is NTPC, and Lara 2x800 megawatts. Other than those, we don't see anything, and since FGD is going to be there, another 1 lakh megawatts have to be tendered. Now, a lot of — we're also trying to see whether we can bid directly as a qualification.
Sudha Kodandaramaiah
executiveWe’ve had some discussions with Jaypee Associates regarding the Nigrie plant. And then we’re also looking at Tata’s — they’re moving forward with their — they’ve acquired Prayagraj 2x660 megawatt and then Mundra 4x — 5x800 megawatt, to see whether we can have some involvement in that — in the FGD retrofit packages. Those are the — some of the items. Otherwise, as Satish mentioned, our — as of today, the hard opportunities we’re tracking amount to INR 6,500 crores in the last quarter. At least, we hope roughly 20%, 25% of that should materialize within the next 40, 45 days. And going into next year, we will lay out the opportunities to ensure that, that 4,500 megawatts, this — opportunity — this order booking stays on track, and we will come out with the full opportunity list in another 15 days. Thank you.
Jami Satish
executiveYeah. Yeah. Chirag, at this point you’re able to shift us into the question-and-answer session.
Chirag Muchhala
analystYes. Certainly, sir.
Operator
operator<<operator_script>> Our first question comes from Rishit Shah with Dhanki Securities.
Analyst
analystSo essentially, with the latest budget, there was a directive issued by the government—basically aimed at those thermal plants that are polluting, to shut them down. So, because of that, should we be expecting any extra FGD orders to come through?
Sudha Kodandaramaiah
executiveYes. So, look, CEA has issued very clear guidelines for how FGD plants should be laid out across 164 gigawatts. Every plant has been identified — in the public as well as private and state domains. Of that, as I mentioned, 65,000 megawatts of EPC ordering has already been done, and that is now coming up for tendering — subcontracting tenders from the various EPC contractors, okay. Now the balance 1 lakh megawatt as well, perhaps within the next 1 year, they have to award it, since the deadline is to commission all these plants by 2022. There is already a delay of 2 to 3 years. And the government has issued a lot of stiff guidelines to all the developers as well as the plant owners. Now, coming to the question of — because of pollution issues, shutting down of plants, 15,000 megawatts have been identified as plants that will be shut down. And NTPC has certain plants to augment capacity — not augment capacity, but wherever some plants are getting retired, they would like to put up new-age supercritical units. And that is how — whatever plants are shut down, maybe equivalent capacity, NTPC's plan is to have 11,000 megawatts of subsidiary plants as a substitute, once the shutdown comes up in all these cases.
Sudha Kodandaramaiah
executiveAnd it also hinges on the other private — sorry, the other state utilities. But some of those plants are really old — 50-year-old, 40-year-old, 30 megawatt, 60 megawatt, and then 110 megawatt — and maybe they won't pursue any replacement for those plants. Any replacement would involve supercritical technology together with the FGD package. So there could be some opportunities to replace this 15,000 megawatts that are going to be shut down. And FGD, as I said, 164,000 megawatts. And then all the new units, whatever comes, will come with the FGD as part of the main part of it.
Kaushal Shah
analystSir, Kaushal here. Just following up on that — what's the timeline, likely for the FGD as well as the ones you mentioned regarding NTPC?
Sudha Kodandaramaiah
executiveNo. NTPC already has — their plan, their overall plant capacity plan of 61,000 megawatts counting the JVs, what they have, plus 40,000 megawatts that they awarded. And the lot 5 orders are being finalized right now. That will be wrapped up over the coming couple of — over the coming 1 to 2 months, perhaps they need to close it out. NTPC will more or less be — be finished with all the ordering for the FGD requirements at their plants. Now, what's lagging is the IPP sector. Even though the IPP sector faces a lot of pressure to retrofit, like Tata's is in there, Jaypee Group is in there, KVK is in there, JSK is in there — sorry, KSK. And these players, at this point they are putting together this funding arrangement and also — since they've got a tariff issue as well, they are settling all of those things. And one by one, these plants are now coming up for tendering. And that is — and then the state governments too, like Maharashtra State Electricity Board, then Karnataka, then all the State Electricity Boards also have a mandate to finish their tendering within the next 1 year.
Kaushal Shah
analystAnd sir, could there be any chance of multilateral funding in this case?
Sudha Kodandaramaiah
executiveThey claim the tariff will be a pass-through. What CERC, CEA and the government have worked out as the mechanism is that, since this is an investment costing roughly — the current rate is around INR 60 lakhs per megawatt for the FGD. And if it's a 1,320 megawatt moving to 660 megawatt, roughly INR 780 crores to INR 800 crores plus IDC, it may come to INR 1,000 crores with all the things that they are funding through, again, through banks only. And then the tariff is getting guaranteed increase, maybe up to INR 0.18 per unit there is a guarantee that we have pass-through, that is why the banks also will lend them.
Operator
operatorFollowing the operator's instructions, our next question comes from Sanjay Dam at Old Bridge Capital.
Sanjay Dam
analystYes. So to this point, everything that NTPC has tendered out in FGD — by NTPC. So whoever has won all of those — we aren't in the running, as far as what's already been tendered, we're focused on future opportunities, right?
Sudha Kodandaramaiah
executiveNo, no. As for where the orders stand — take BHEL, for instance: they have 58 units totaling 28,530 megawatts; GE has 22 units amounting to 13,940 megawatts; Doosan and L&T together hold 26 units, right. Now, in BHEL's case anyway, when it comes to tendering, we've rotated <<inaudible>>. You see, the problem with FGD is that the packages aren't large enough for our sustainability, overhead costs can run high, and beyond that we have to deploy certain assets. So we're picking the plants where we're able to work. That's the area where we feel more at ease working alongside GE, since we've demonstrated one plant that has been commissioned at Vizag. It's the first FGD plant commissioned in the country, and we're part of that initiative. So our interest lies in working with GE. That's where we — they're also reaching out to us, because they aren't finding good agencies. When it comes to BHEL and L&T, yes, depending on competitiveness and our wish to participate, we'll examine that.
Sanjay Dam
analystYou mentioned that you're looking at 50% of that opportunity. So let's say, on average, for the main contractors such as GE, it comes to somewhere between INR 40 lakhs and INR 60 lakhs per megawatt. Out of that, what's the relevant pie for us?
Sudha Kodandaramaiah
executiveRight. No. If that's the case — look, building a site breaks down into 2 parts — actually 3 parts. First comes the civil work, then the mechanical work, and third is the electrical work. Within civil, there's also a materials component, namely steel and cement. If you take all of that plus the remaining items, which are service jobs, manpower, and so on — so we can figure roughly 20%, INR 10 lakhs to INR 12 lakhs per megawatt.
Sanjay Dam
analystAll right. And by what point, sir, do you think you’ll have a reasonably clear view of how large the pie is for us? When will you have a solid sense of some final rating?
Sudha Kodandaramaiah
executiveNo. Here's the thing. Earlier, we weren't very enthusiastic about taking on every FGD job, since those jobs were valued below INR 50 crores and so on. But since GE has expressed interest, we said we'd handle the whole job — we won't take on piecemeal work. So we had some discussions with them not long ago. Take Singaji, for instance — it's up for bidding now. They've said they'll bid back-to-back with our offer. In other words, we'll submit the offer upfront for all the site works, 4x660 megawatt. They'll place the bid. If they win, they'll hand the job directly to us. Then, for example with Simhadri, we're working on submitting an offer. And we're also — at some of the plants we're L1, such as Unchahar 5x210, we're L1 there. We've already submitted the offer. So Rihand, we're L1 there too, 2x500 megawatt. So all of this, as I showed, means we're keen to support GE.
Sanjay Dam
analystSo of the roughly 20% value of orders you mentioned those guys are implementing, the margins we expect to earn there will be in line with or better than our overall organizational margin?
Sudha Kodandaramaiah
executiveLook, when we say we're going to negotiate with GE, they're also in — not a very comfortable position when it comes to execution. What's happened is that this FGD has an 18-month timeline, and the execution methodology has not been very good so far, and the government isn't happy either. That's why GE has come back to bigger parties, even though the values aren't much, and maybe we'll get some premium. At least we'll be able to get better than the normal margins we get in the traditional BTG business.
Sanjay Dam
analystRight. Right. And also, when you were describing the opportunities you're seeing, some power players are — some players are going in for — sorry, material players are going in for a comprehensive O&M, where you'd be looking to work as part of a team of larger O&M players? Is that what...
Sudha Kodandaramaiah
executiveYes. I believe we've made some progress, and I think we've talked about that. Take Nagarnar, for instance, with NMDC — that's a mineral processing plant, and there's also a steel plant being built there, which is Nitin's, and we've secured a material handling O&M contract there, their INR 52 crores job. And we've also picked up small, small jobs with Tata Steel. And we are certainly — like, with JSW we're in discussions. For example, right now we've gained a foothold in Bellary. We're talking about whether any opportunities exist in O&M and all. So ultimately this is a process we have to drive from power as well and diversify further into non-power O&M. That's our aim. Because growth will come with more diversification beyond power too.
Sanjay Dam
analystYeah, yeah. And sir, I missed — my line dropped in the middle there, so did you mention anything about Railway and any opportunities we're looking at further?
Sudha Kodandaramaiah
executiveWhich one?
Jami Satish
executiveRailway?
Sanjay Dam
analystOn the railway side, we’re looking…
Sudha Kodandaramaiah
executiveOn the railway side, there's a job we're handling in Sadulpur worth INR 350 crores. Through that work, we're trying to build up our experience. What happened is that after we took on the job through the joint venture, the tender conditions were altered somewhat over the last year, since they didn't want new entrants coming in and flooding things with a lot of agencies. That job is moving along quickly now, and by the end of the year — in another couple of months — we'll have the qualification from completing it. So for now, we're holding off on that. At least in the future, we'll bid, perhaps after a couple of months, once we've got the qualification from doing the Sadulpur job; after that, we can bid on our own, and that's what we're waiting for. Then in Madhya Pradesh, we completed a substation project worth INR 78 crores successfully, and it's been in operation for the last 1.5 years. That one too, we'll make use of. And in fact, on the electrical — the transmission and distribution side, we've identified roughly INR 2,000 crores of opportunities across Maharashtra, Gujarat, Bihar, and also Bangladesh.
Sanjay Dam
analystOkay, okay. And in the parts where I skipped something, so Satish, could you just give us a sense of how much is still pending from AP right now? And how much do we expect to receive by the end of 4Q? And what would gross debt outstanding be at present?
Jami Satish
executiveYes. Regarding the AP piece, it comes to roughly INR 55 crores, all right, and that amount is owed to us from the AMTZ project; it was meant to arrive in 3 tranches — January, February, and March, okay. In January, it didn't come through. They've set aside INR 20 crores for this month. So in all likelihood, before this month ends we ought to receive approximately INR 20 crores, perhaps a portion in March, and the remainder should reach us in April. So it keeps slipping by one more month beyond the current one. The encouraging thing is that this project stands completed, and they were keen to showcase it. So even now they continue to seek our assistance although our work is finished. A great deal of coordination is therefore underway. We've also been providing them post-completion support. They're quite pleased. So the likelihood of collecting this money looks very strong. And on the debt side, sir, the gross figure — taking working capital together with certain equipment loans and term loans — comes to about INR 448 crores, and that was in Q2. Q3 sits at nearly the same level, roughly INR 460 crores.
Sanjay Dam
analystGreat. And beyond that, are there any other receivables from AP?
Jami Satish
executiveAP, that isn’t there, sir. At this point everything has been completed. At this point it is closed.
Operator
operator<<operator_script>> Our following question comes from Chirag Muchhala with Nirmal Bang Equities Private Limited.
Chirag Muchhala
analystYes, sir. Regarding O&M, during the previous call we noted a GMDC Gujarat project valued at approximately INR 750 crores on which we held L1 status. So is there any update on that project?
Sudha Kodandaramaiah
executiveYeah. For now, it's been paused — that's the Akrimota one.
Chirag Muchhala
analyst<<inaudible>>.
Jami Satish
executiveGMDC.
Sudha Kodandaramaiah
executiveGMDC — that one's on hold. Even so, we achieved substantial success in O&M this year. And if Vedanta also comes through, we expect our O&M backlog to improve, since there are roughly INR 1,000 crores of opportunities with Vedanta.
Chirag Muchhala
analystOkay, but is there a particular reason, sir, that this was put on hold?
Sudha Kodandaramaiah
executiveMy sense is that a PPA problem is what they ran into. The key reason is that the PPA was nearing its end, and unless they renegotiate that PPA, they are now committing to a long-term O&M contract without a proper PA in place, which may not be a proper procedure. That is the reason they have kept it under hold. Once that takes place, maybe we — it can be revived.
Chirag Muchhala
analystAlright. And sir, regarding the overseas side of things, what share of the total order book does international business represent at this point? And looking ahead to next year, where do we expect the scaling up from international inflows and the order book to come from?
Sudha Kodandaramaiah
executive1,100 — I believe that came to roughly INR 1,100 crores.
Jami Satish
executiveIt's -- together with -- International is nearly at --
Chirag Muchhala
analystYes, I understand.
Jami Satish
executiveIt might be assembled, Maitree and everything. So INR 1,320 crores...
Sudha Kodandaramaiah
executiveWe recorded INR 1,375 crores.
Jami Satish
executiveYeah, Chirag, as you can see, it's mostly with this International piece, okay. That's roughly INR 1,375 crores out of the INR 4,927 crores backlog, okay. A substantial chunk is now coming from Bangladesh, which is quite active at the moment, okay. We need to close that over the next 1.5 year. And then there's Dangote. And MPA and Oman, not much...
Sudha Kodandaramaiah
executiveEvery one of the projects is closing.
Jami Satish
executiveSo the work is still underway, which is why it has come down. So of that INR 1,375 crores, a substantial amount is coming from Bangladesh.
Chirag Muchhala
analystAll right. And sir, what's the outlook for next year? Are there any big inquiries we're pursuing from international markets besides Maitree and Dangote?
Sudha Kodandaramaiah
executiveUntil recently, Qatar was a market we avoided due to visa complications stemming from tensions between Qatar and the Gulf — the GCC nations. At this point, though, they've announced a sizable desalination and power plant package. Samsung serves as the EPC contractor, and they came to us. We still need to evaluate that one. So that's something we're currently examining. Beyond that, opportunities are emerging in Nigeria as well as North Africa. Those too are under our review. Still, we must watch how the Middle East dynamics play out, since we enjoyed considerable success across all those markets. Lately, however, activity in the Middle East has been fairly quiet. Right now Qatar is one item, and Africa — whatever is available there — we're looking into it.
Jami Satish
executiveAnd beyond that, Bangladesh, where a lot of traction is actually taking place.
Sudha Kodandaramaiah
executiveIn Bangladesh, we're also seeking a transmission system. These are the items we should perhaps concentrate on.
Chirag Muchhala
analystAlright. Sir, regarding the order book for our civil works: so, sir, those 2 projects in Andhra Pradesh — I mean the water project worth INR 1,240 crores and the INR 870 crores <<inaudible>> projects — I believe neither is in the order book anymore now, correct, sir?
Sudha Kodandaramaiah
executiveYes.
Jami Satish
executiveCorrect.
Chirag Muchhala
analystYes. So, sir, regarding both of those projects, is there any amount of work we completed that still has receivables outstanding?
Jami Satish
executiveRight, so on that INR 1,200 crores plus — an LOI was issued, but no contract got signed. That means no execution has taken place. For the INR 872 crores piece, though, we've spent close to INR 12 crores, and of that, roughly INR 500 crores — sorry, INR 5 crores — sits in inventory and receivables. That leaves a net figure of close to INR 6 crores, which we need to see whether the government will compensate. We're engaging with the government on it. Let's see how things progress. So the net impact, if you look at it, is INR 6 crores, while the gross impact comes to INR 12 crores.
Chirag Muchhala
analystAll right, and there aren't any additional projects out of Andhra Pradesh that haven't begun yet and might end up being canceled, correct?
Jami Satish
executiveNo, no. No — there's nothing in place at this point.
Chirag Muchhala
analystAlright, sir, and finally, turning to the working capital cycle. You said it currently stands at roughly 160 days. So given the present order book, how do you expect that to shape up in the next fiscal year? I mean, is it likely to, say, come down significantly, or stay broadly at the same level?
Jami Satish
executiveNo, that figure should actually decline. Once AMTZ is realized — okay — it definitely ought to come down. So for next year, our expectation is roughly 130 to 135 days, or perhaps a bit under that. Because look, O&M filed is more or less under control, okay. The delay we're encountering stems from a rather bad experience we had with Andhra Pradesh. There was also a minor holdup involving the Irrigation Kaleshwaram project, but that's now back on track. Beyond that, a few BHEL projects — mainly the domestic ones — have slipped slightly, though where Bangladesh is concerned, they've been paying within 40, 45 days, okay? Now as soon as the AMTZ realization arrives, the BHEL portion is shrinking too. Taking the new mix overall, it should land in the 130, 135 day range. That's what we're aiming for, or perhaps a touch below it.
Chirag Muchhala
analystAlright, and sir, this is our final question. Sir, how much retention money is there in total at present? And of that amount, how much would currently be coming from BHEL?
Jami Satish
executiveSo overall retention now stands at just above roughly INR 300 crores. Within that, BHEL's share could be a bit over 40%.
Chirag Muchhala
analyst40%?
Jami Satish
executiveYeah, yeah. Because, you see, mostly with international and O&M and all, there hasn't been much progress, since most of the projects we took on 4 years back were largely BHEL, okay, and that share is now coming down. So if I put it this way, as of 31st March, we had close to INR 320 crores despite the growth and everything, and that figure is still unchanged, which means the realizations are indeed happening.
Operator
operator<<operator_script>> Our following question comes from M. S. Arun, who is calling in from Capital Market.
Arun M Sethuraman
analystCould you give me the order book split across Civil, Erection, and O&M?
Jami Satish
executiveRight, so at present the backlog stands at INR 4,927 crores. That figure relates to the completed executable order book. As for the projects currently on hold — well, first 100 have now been eliminated. Broadly speaking, the split is roughly INR 2,214 crores for the mechanical side and INR 1,273 crores for Civil, plus O&M operational maintenance...
Arun M Sethuraman
analystSir, how much is that, Civil?
Jami Satish
executive1-2-7-3.
Arun M Sethuraman
analystOne-two-seven-three. All right.
Jami Satish
executiveAnd operations and maintenance comes to INR 1,100 crores. And the electrical pie — that last leg — is INR 339 crores. That's roughly INR 340 crores.
Arun M Sethuraman
analystOn the civil side, how's execution coming along — is it getting better?
Sudha Kodandaramaiah
executiveYes. For instance, the Bhusawal project has kicked off and is proceeding on schedule. That one is INR 284 crores. And then, as you know, that Rampal job in Bangladesh is a total of INR 860 crores, a mix of — mostly Civil, 60%, 70%. So those 2 are also moving ahead on schedule.
Jami Satish
executiveAnd about Ramayampet, sir — the canal work has now begun, right? The billing there was running at INR 4 crores to INR 5 crores a month, and starting last month it has risen to INR 12 crores to INR 13 crores. In March, we might reach close to INR 20 crores. There's pressure coming from the government side as well. So that should also help us push the Q4 turnover.
Arun M Sethuraman
analystSir, is it possible that we end up seeing flat growth for the full year on the <<inaudible>> side?
Jami Satish
executiveRegarding Q4, sir, we expect meaningful contributions from three projects — Sadulpur, Bangladesh, and Ramayampet. So Q4 will clearly be stronger than Q3, though it could end up flat or only marginally better. We are making an effort to accelerate Sadulpur since a large supply component sits there. The encouraging part is that Q1 of next year may come in roughly equal to Q4 of this year. In Power Mech's history, this would be a first — if you look at the pattern, Q1 and Q2 have been lower while Q3 and Q4 have been higher. Given the order book we hold today and the projects currently in hand, momentum could begin at INR 650 crores plus starting from Q1. So we now have strong visibility. And if any additions come through — we are planning close to another INR 800 crores by March, before March — then Q3 and Q4 would probably be somewhat higher than that.
Arun M Sethuraman
analystAnd sir, about the Electrical's things, what went wrong for us there in Q3?
Jami Satish
executiveCould you say that again?
Arun M Sethuraman
analystTurning to Electricals, sir — how did execution go in Q3, and in what ways are things getting better?
Jami Satish
executiveWhen it comes to Electrical, the largest project is OH Electrical, Sadulpur, all right. And if you look at it quarter by quarter, it's currently running at roughly INR 30 crores to INR 35 crores each quarter. Now, in Q4, we're expecting about INR 60 crores, and from Q4 onward that should hold at INR 60 crores to INR 65 crores per quarter from the models we already have, sir, until — unless we bring in some new orders, in which case it could rise.
Operator
operator<<operator_script>> Since no more questions remain, I'd like at this point to pass the conference back to Mr. Chirag Muchhala for his closing remarks.
Chirag Muchhala
analystYes, thank you. I’d like to express appreciation to management for the chance to host the call, and to everyone joining us for being here. Sir, would you care to offer any closing remarks?
Sudha Kodandaramaiah
executiveYes. I think when it comes to sales and turnover, we're confident, since the site lift remains in place. During the past year, we saw growth a bit above 40% — we might have achieved 10% growth, if not for the issues at Sadulpur, along with certain Electrical jobs and also Ramayampet. Now we're working to get past that. So, on a positive note, we're focusing on the non-power segment and O&M; maybe we want to grow the business further on the non-power side beyond the traditional areas. And then the Civil side, whatever exists there, and FGD is a key focus area. We want to refocus on it. Previously, we weren't taking much of this on. Now we believe it's better to concentrate on that as well. So in the coming year, we ought to see reasonable growth. And we'll maintain this fourth quarter sales momentum through the quarters ahead too. And the aim is to build a backlog of at least INR 8,000 crores plus by the end of next year. So that ought to bring growth back into the — this one the side.
Sudha Kodandaramaiah
executiveThanks.
Jami Satish
executiveYes. Anyone who would like to clarify a few more points can reach out to us directly. Thank you for being on the call. Many thanks.
Operator
operatorAppreciate it. That brings this conference to a close on behalf of Nirmal Bang Equities Private Limited. Thanks for being with us — you're welcome to disconnect your lines at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Power Mech Projects Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Power Mech Projects Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Power Mech Projects Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.