Power Mech Projects Limited (POWERMECH) Earnings Call Transcript & Summary

August 22, 2022

National Stock Exchange of India IN Industrials Construction and Engineering earnings 67 min

Earnings Call Speaker Segments

Operator

operator
#1

At this point I'll turn the call over to Mr. Prasheel Gandhi of Nirmal Bang Equities. Sir, the floor is yours.

Prasheel Gandhi

analyst
#2

Thank you, Renju, and good afternoon everyone joining us. Nirmal Bang Equities is glad to welcome all of you to this annual conference call for FY 2023 of Power Mech Projects Limited. Joining us from the management side are S.K. Ramaiah, Director, Business Development, along with Mr. Jami Satish, CFO. So without spending too much time, I'll pass the call to management for their opening remarks, after which we can move to Q&A. Thanks, and over to you, sir.

Jami Satish

executive
#3

Okay, thank you. Good afternoon, everyone. I'm Satish, and joining me is Mr. S.K. Ramaiah, our Director of Business Development. We're glad to have you all on this earnings call for quarter 1 of FY 2022 to 23. Let me begin with the financial highlights for the first quarter of 2023. Our performance in quarter 1 of FY 2023 remained healthy and was consistent with the overall plan the company had set. Reported total income for quarter one of FY 2023 stands at INR 749 crores. EBITDA came in at INR 86 crores, and reported PAT was INR 39 crores. In quarter 1 of the prior financial year, reported total income was INR 628 crores, EBITDA was INR 71 crores, and PAT was INR 31 crores. The revenue mix for quarter 1 of FY 2023 breaks down as follows: the erection business contributed INR 152 crores; the civil business, which includes railway and water projects, is around INR 306 to 376 crores; operation and maintenance brought in INR 196 crores; the electrical business contributed 22, 22 crores; and other income was around INR 2 crores. In quarter 1 of the last financial year, by comparison, the erection business contributed around INR 137 crores, the civil business around INR 184 crores, the O&M business INR 173 crores, the electrical business INR 28 crores, and other income was around INR 6 crores.

Jami Satish

executive
#4

Our domestic operations account for nearly 83%, while the remaining 17% came from business overseas. Power and non-power make up 60% and 40% of the mix respectively. Growth has occurred in every segment apart from electrical business, though the company is mindful about expanding within the electrical business space. For Power Mech, this quarter one ranks as the strongest and highest-ever performance across its whole journey. Total income as reported grew by nearly 19% in quarter one compared with quarter one of the prior year. In similar fashion, EBITDA rose by almost 20%, and PAT increased by almost 26%, thanks to controlled finance cost, depreciation, and a better margin profile. Depreciation cost measured against revenue stayed on the lower side because CapEx spending was kept in check. Typically, finance cost as a percentage has declined owing to reduced overall utilization of limits. The overall execution cycle should improve further, driven by a robust order book, stronger engineering skills, construction management, and strengthened first and second level leadership built in-house. Power Mech is renowned for how it executes. Seven years ago it was purely a power sector play; since then the company has remade itself into a multidimensional infrastructure player while retaining core competence in O&M and mechanical piping, as we anticipated a slowdown in the thermal power sector years back.

Jami Satish

executive
#5

After that, Power Mech has shown it can execute across every segment we operate in so far — railway, road projects, water projects, material handling, cross-country pipeline, international operations, and so on. Another key thing to note is that Power Mech has know-how in running operations in all difficult regions, international territories included. Over this 23-year journey, COVID's tough stretch included, the company has developed the ability to handle any adversity — there were instances where we won a few contracts without a government guarantee, and that reflects our customer's confidence. On the execution side, the company is very confident of delivering on schedule. We're also excited and glad to share that new talent from well-regarded organizations is joining Power Mech across all verticals. The new names include N. Srinivas Rao, MD, who came in as the MD and CEO, International Operations, Africa. Previously, he was with well-regarded companies such as Tata and Shapoorji Pallonji. Mr. Umesh Mehta came in as Chief Techno-Commercial Officer, with more than 30 years of experience. He was previously with some well-regarded companies such as Vedanta, Sterlite, Warman Engineers. Mr. Vijay Bhaskar Rao came in as Vice President, Contract Management and Business Development, with 35 years of experience. Previously, he was with companies such as Tecpro, DGEN, APGENCO.

Jami Satish

executive
#6

Mr. Ashok Kumar Katta came on board as Vice President, bringing close to 30 years of experience, and previously he worked with well-known firms such as Reliance Industries and Nirman L&T. This reflects confidence on the execution side and shows talent being drawn from larger organizations, which gives the team a great deal of confidence regarding execution. Looking ahead, the overall working capital cycle is expected to improve. Average monthly collections are still running between INR 250 crores and INR 300 crores, and this is anticipated to get better going forward. Net current debt, excluding cash and cash equivalents, remains at 140 to 145 days for the period, which again is expected to decline during the year. Gross debt and net debt stayed under control even with growth in the business. Overall debt utilization and finance cost are expected to decrease during the financial year. As all of you would have noticed, Power Mech recently secured a large contract in the FGD space, worth around INR 6,100+ crores, from Adani Group for its projects located at Mundra, Tiroda, Kawai, and Udupi, on a complete EPC basis. These projects will be executed across a period of 30 months.

Jami Satish

executive
#7

Power Mech has set up a distinct entity to manage these projects, led by senior professionals. In addition, Power Mech has partnered with well-established technology providers for both technology backing and equipment supply to install these FGDs, and has taken every required precaution to mitigate contractual and external risks. This major push into the FGD business forms part of our forward integration and significant diversification built on Power Mech's core competence of more than 20 years in power plant installation. Power Mech's extensive experience and in-house core strength to handle any power plant will contribute substantially in terms of value addition when executing these projects. This contract carries a 10% mobilization advance cost, which is interest-free. As a result, we foresee no incremental working capital for executing this project. These projects are self-sustained. And margins are expected to come in at around 11%+ at EBITDA level from the FGD projects. Naturally, there is room to improve further. This is thanks to our inherent strength in a similar field. We will deploy required equipment in-house and new, new with a mix of additional CapEx of INR 25 to 30 crore, which is part of our, part of our CapEx plan for this year.

Jami Satish

executive
#8

As of today, the company's order backlog is INR 24,000 crore+, which includes the MDO contract, and INR 15,000 crore+ if you exclude the MDO contract. So far this financial year, the company has brought in new orders worth INR 6,948 crore. For the full year, the company has now set a goal of reaching INR 10,000 crore in new order additions. We expect to add INR 3,100 crore of new orders over the remaining part of this financial year. As things stand today, the company is already overrun on projects by almost INR 1,500 crores. The company has strong visibility for its growth over the next three years. During this financial year, the company is confident of converting its order book into revenue of around INR 3,600 crores, plus revenue conversion from the new FGD contract. In a couple of days, we will come out with a revised revenue target for the year, based on the FGD work schedule. For FY 2023 to 2024, the company expects an opening order backlog of INR 14,000 crores+. That figure excludes the MDO contract. The company plans to convert around 38%+ of its opening order book into revenue during FY 2023 to 2024. The MDO project is progressing according to our original schedule.

Jami Satish

executive
#9

Three years in, the company is well consolidated — it will consolidate its business model to sustain growth, and the emphasis will remain more on improving margins and cash flow. During the first 30 months, the company has an opportunity for an additional O&M contract worth INR 1,000 crore, which will be executed across a period of five years. Annually, that will add almost INR 200 crore+ in revenue terms from these FGD orders and the O&M orders it is set to receive. Beyond that, the MDO contract will begin generating revenue. Furthermore, the company has built credentials and features strong enough in the field of railways, water projects, road projects, international operations, material handling, crop, concrete, pipelines, etc. Power Mech will align its business model, keeping opportunities in line with the NIP. Naturally, operational maintenance, in both the power and non-power sector, including international operations, is expected to play a dominant role in our overall business plan going forward as well. The promoters intend to infuse funds into Power Mech by way of preferential allotments, subject to board and necessary approvals. Power Mech needs non-fund-based limits, mainly performance bank guarantees from various banks. An increase in equity from the promoters will build a lot of confidence among lenders, and will also help a lot, including with the external credit rating.

Jami Satish

executive
#10

That should come to roughly 1.3%-1.4% of the pre-allotment equity base, and it's contingent on the board's consent plus the approvals that are required, which should arrive within a couple of days. At this point, I'd like to ask Mr. Ramaiah to share a few additional developments before we go on to the Q&A. Thank you.

S.K. Ramaiah

executive
#11

Sure. Thank you, Satish, for those opening comments and for laying out the different facts regarding the company's operations. Thanks, everyone. On the marketing and business front, I believe, as you're aware, COVID is behind us, and that has clearly opened up the market in a major way, and it is — that is clearly reflected in the results, the opportunities, and the new orders the company is winning. At the close of last year, we had a backlog of INR 8,855 crores. During the first quarter, roughly INR 1,075 crores of orders were booked on the mechanical side, and then on the civil and civil side, and then on the O&M side, about INR 155 crores. That has come, taking into account the conversion into backlog in the first quarter, and the order backlog now stands at INR 8,883 crores. There is a modest increase based on the first quarter inflow of orders, about 8.6% in the mechanical and EPC business. There is, of course, since the conversion has taken place in O&M, the order backlog stands at INR 1,203 crores. Then civil and infra, the order backlog is now INR 5,789 crores. Then electrical, we are not adding much, it stands at INR 96 crores.

S.K. Ramaiah

executive
#12

In the first quarter of last year, order bookings came to INR 343 crores. This year, that figure has risen to INR 1,075 crores. Among the significant orders we've secured is Khurja Coal Handling — a very good opportunity for us. We're executing it in partnership with Thyssenkrupp, at INR 191 crore. Next, the Godda 800 MW boiler: Adani handed us that job following the existing contractor's failure, worth roughly INR 105 crore, and it's proceeding on a fast-track basis. We also picked up the FGD chain works at North Chennai from BHEL, at INR 119 crore. Then there's shed construction, doubling work stemming from railway opportunities, at INR 113 crore. The O&M opportunity brought us about INR 155 crore. Add bridge construction work of INR 50 crore and other civil works of roughly INR 41 crore. That's how the INR 775 crore breaks up. On the pipeline development side, the major orders are FGD orders covering civil and mechanical installation jobs — about 1,950 MW at Haldia, Chandrapur, and the vertical department, CESC, Goenka Group. We stand lowest at INR 870 crore for approximately 1,950. This isn't an EPC job; rather, it involves balance site execution jobs.

S.K. Ramaiah

executive
#13

On Bangalore Metro, there's one depot construction coming up, roughly INR 450 crore at Yelahanka. Then railway electrification work in Bangalore and Hassan, around INR 88 crore. We also have an O&M opportunity in Nigeria — we're already handling the installation job at Dangote there — worth about INR 94 crore. Those make up the orders in the pipeline. Now turning to the business segment analysis. The domestic business currently carries a balance order backlog of INR 8,361 crore, versus INR 8,012 crore a year ago. On the international side, not much is moving, since our focus right now is entirely on the domestic market given the various opportunities there — INR 523 crore. The power sector business accounts for roughly 43%. Order backlog there is INR 3,799 crore, while non-power keeps contributing, at INR 5,084 crore. Now, two separate developments here are set to give the company a big vision over the coming couple of years. The first is the mine development operation in Jharkhand — INR 9,294 crore spanning 25 years. With that included, backlog as of June will come to INR 18,177 crore. Apart from that major development, there's the new initiative on FGD orders, as Satish was highlighting — 8,460 MW across about 15 units of 330 and 660 MW for Adani at various projects of theirs in Kawai, Mundra, then Udupi, and so on.

S.K. Ramaiah

executive
#14

So the LOI order has come in, and once we factor that in, backlog has risen to INR 15,056 crore. That also strengthens the power sector and the mechanical job presence within the business. Domestic business has swelled to nearly 96%, with a backlog of INR 14,531 crore. And the power sector business has picked up, which had been on a declining trend over the last four, five years. At this point, backlog accounts for 66% of the total order book of INR 15,056 crore, while non-power stands at 5,084 crore. So this gives us a really solid base to take off from and then set a vision for the coming two, three years. Key works we're executing include Udangudi, civil and structural job, INR 345 crore. Then Buxar Boiler for NTPC, INR 176 crore. Bhusawal, civil and structural work, INR 285 crore. Maitree, a major job in Bangladesh, INR 855 crore. Yadadri, for the 5x800 MW, many packages across civil mechanical, fuel handling, INR 813 crore. Ramannapet Canal, roughly INR 373 crore, and then Sambalpur Electrification, INR 350 crore. And the big water projects, which we're doing in UP, around INR 2,775 crore. The present value could rise to +INR 4,000 crore.

S.K. Ramaiah

executive
#15

On the roadworks front, in Karnataka and Mizoram we're doing roughly INR 780 crore. The most recent job we've picked up from Adani is the Khammam Khodad road project in Telangana, at INR 645 crore. Adding up the FGD across the four projects gives INR 663 crore. So that's where the company's attention is going to be over the coming two to three years. O&M keeps contributing to our bottom-line growth and also helps with revenue generation. We have a major presence in Singareni at INR 343 crore; Tuticorin, 2 x 600 MW, INR 391 crore. We've also taken non-power jobs at JSPL, INR 66 crore. Then Jharkhand, Jharsuguda, 4 x 600 MW, INR 387 crore. On the international side too, the focus now is on O&M, since we've completed plenty of installation jobs there and we're expecting around INR 100 crore. That's the picture on the O&M side. As for manpower, the company keeps bringing people on board, as was rightly mentioned, at both the senior level and the working level, to reinforce execution and oversight of project execution. The figure stands at about 32,000, with contract labor of nearly 15,000. There may be further additions needed to handle the new orders, okay?

S.K. Ramaiah

executive
#16

On the opportunities side, I— I mean, without FGD, our target was INR 4,000 crore. With INR 1,500 crore sitting in the L1 position plus INR 775 crore, maybe, you know, we can still hit those numbers even without FGD. Once FGD is included, order booking for this year could reach as much as INR 10,000 crore. So that ought to help us see, at the close of 2023, assuming conversion of the INR 3,600 crore Adani order—the Adani FGD order—can rise somewhat higher, to +INR 4,000 crore. By the end of next year, the backlog should land somewhere between INR 14,000 and 15,000 crore. That gives a very clear working model, you know, for the coming couple of years. The main work areas are drinking water projects at INR 2,075 crore. Road projects at INR 1,650 crore, and FGD comes to roughly INR 6,163 crore. O&M jobs are around INR 1,200 crore. These, I think, are the business—as Satish rightly put it, we have aligned ourselves with the National Infrastructure Pipeline, which shows up in our order flow over the last two, three years.

S.K. Ramaiah

executive
#17

When you examine how orders have come in over the past 2 years, 2021 saw INR 4,638 crore, and 2021 to 2022 came in at INR 4,231 crore. Based on the projects, including that Adani order, there's certainly a possibility we could reach roughly INR 10,000 crore this year. Going forward, clearly, NIP investments are going to stay bullish, with all sorts of spending on infrastructure, railways, then minerals and mining, then mine development. That represents a big opportunity, because we've already moved into that space. In fact, Coal India is planning mine development work of roughly 1 to 2 million tons. And drinking water projects keep getting funded well. Of 91, 19.1 lakh crore of households, 50% have been provided over the last, the impact of the last couple of years. We're active in roughly 3,000 villages in UP. One more area for, maybe, the long-term vision could be that operation maintenance of thermal power plants will see fundamental changes as capacity grows in renewable power... and, by 2024 to 25, it's expected to rise to 450 GW of installed base. And at the end of the decade, the PLF, the current PLF, it sits at 58%.

S.K. Ramaiah

executive
#18

It has dropped, and it's going to drop further to 30%-40%. But in a sense, thermal plants will face a great deal of stress in operation given the fuel generation mix. And that clearly demands different O&M practices. The company is gaining a further — it has a huge presence across roughly 67,000 MW of operating base and works in about 30 plants. In fact, working under these adverse conditions in operating those plants is not an opportunity for us, because in many of these cases, down the line, the power plants must run on a day-and-night basis. That can also add to the O&M costs. In a sense, it can be an opportunity, and railways are coming with big investments, and we are already there. Perhaps with the INR 500 crore of working orders that we are executing, another INR 450 crore is expected shortly. Railways is going for 500 numbers of multimodal terminals, cargo terminals, and then station pre-developments. The new opportunities we are looking at are the metro project. Today, metro is going to be there in most of the A&D grade towns, and the total length has gone up to 702 km, and is planned to go up to 700 km.

S.K. Ramaiah

executive
#19

The chance here is INR 280 crore to INR 320 crore for each km. As I told you before about roads, investment during this year comes to almost INR 200,000 crore, with compounding growth in investment of 20%, and we are executing roughly 151 km of roads worth INR 1,646 crore. On the electrical P&D transfer and distribution side, yes, we are considering how to move forward there, given the competition. Four projects have been completed successfully, and another four are underway in Northeast Bihar and Bombay. We are keeping an eye on the opportunities. Substantial investment is coming in P&D as well, to reinforce the grid and reduce transmission distribution losses, at nearly INR 300,000 crore. Railway electrification will be a massive opportunity, and we have finished 640 km of railway lane in the southern port section, out of 527, and we are bidding for a further 80 km and hope to secure it. So that is what I can share regarding the opportunities, then auto, the auto portion and the marketing side. Yeah, we can move to the next phase of the question-and-answer. Thanks a lot.

Operator

operator
#20

Thanks. We’re moving into the Q&A portion now. To ask a question, press star and one on your touchtone phone. If you’d like to take yourself out of the queue, press star and two. When asking a question, participants are asked to use their handsets. Ladies and gentlemen, we’ll pause for a moment while the question queue is put together. Our first question is from Abhishek at HDFC AMC. Please go ahead.

Abhishek Poddar

analyst
#21

Good afternoon, and congratulations on such a strong set of orders. My first question is about the FGD order we've received. Could you give us some understanding of how the revenues will be booked across 2024 and 2025? And also, if you could share some understanding of the payment terms — how much is the retention money?

S.K. Ramaiah

executive
#22

Right. So I think that 6,160 crore is going to be spread across the coming 30 months, and in the first year we can expect roughly 10% of revenue — that's the ceiling. So maybe in 2023 and 2024, the revenue from this should — at least 50% should get converted, 30% to 50%. That can lift revenue, along with the other product backlog for 2023 to 2024, because by the end of the year, as I mentioned, there will be 14,000 to 15,000 crore of backlog. That ought to give a vision of 4,000 to 4,500 crore up to 5,000 crore of revenue beyond 2023.

Abhishek Poddar

analyst
#23

And so, regarding the retention money, what figure did we agree on?

S.K. Ramaiah

executive
#24

It's roughly 10%.

Abhishek Poddar

analyst
#25

All right. Once we hit the one-year mark after completion, we’ll be—

S.K. Ramaiah

executive
#26

No, no — that comes at the completion's end, so at that point we can get it, the payment time.

Abhishek Poddar

analyst
#27

All right. So regarding the commodity escalation clause and the margins — in what way are those addressed within this contract?

S.K. Ramaiah

executive
#28

My sense is that they align with what the market anticipates and with what competitors are doing, roughly 11%-12%. What works in our favor is that we add more value on our end, since our operations rest on solid foundations — in-house equipment, supervision, and our own construction know-how. The area we need to concentrate on is procurement. As for funding, working capital ought not to pose an issue, given that we receive advances, and we will arrange payment terms with suppliers on a matching basis as well. That is the approach we intend to take in carrying this out.

Abhishek Poddar

analyst
#29

Got it. I believe an earlier remark was that, for next year, you're contemplating 38% execution against an opening order book of INR 14,000 crore, which is going to be in place. That would translate to roughly INR 5,300 to INR 5,500 crore of revenue in 2024. Is that interpretation right? Could you also speak to how execution capability is being ramped up, and how the planning has been carried out within the company?

S.K. Ramaiah

executive
#30

That's a really good question, I think. How the execution ends up being depends on expertise, and as Satish explained, that's been built up over more than 23 years. In fact, during the last couple of years, and even through COVID, we've handled projects better than our competitors did. That's why — one example I gave you — the Godda project, the customer took the job away from the other agencies and handed it to us... just on the strength of the resource management we have, and a strong supervision base of close to 6,000 to 7,000 engineers and supervisors working online, on-site at any given time. And then we have an SBU-based project management approach with focused project implementation, plus delivery management and customer relationship. For us, taking on this many projects isn't a challenge at all, because we're quite used to running about 40 to 50 projects. What we might need here is another modest bump in manpower, roughly 5%-10%. As for resources, we have plenty when it comes to execution — what we built up for the coal-based power plants. In fact, we have excess capacity in resources, in construction equipment, that can be gainfully deployed across all these jobs.

S.K. Ramaiah

executive
#31

Our in-house abilities when it comes to field works, and beyond that structural fabrication and erection work, are also a strong point for us. Erection station jobs are already a core strength of ours. In O&M we keep playing a leading role, which is exactly why customers prefer us. So I think, going from INR 3,600 crore this year up to INR 5,000 crore with the resources we already have plus some modest additions is not a challenge. Because, as you know, we were earlier in the INR 2,000 crore range. Now we expect to reach INR 4,000 crore within three, four years. That is how the company is scaling up its capability and resource management, and then getting optimal utilization of the resources.

Abhishek Poddar

analyst
#32

Got it, sir. On operating margins, we said on the last call that we expected an improvement driven by O&M, and that royalty costs would also come down. When will we begin to see operating margins improve, sir?

S.K. Ramaiah

executive
#33

A lot of the projects we're handling through joint ventures and consortia should wrap up within another six months to one year. As you know, that will put us in a stronger position to bid on a PQR basis, standing alone. When we go after railway work in passenger jobs and the many specialist jobs we currently do alongside others, that ought to lift our operating margins considerably. At this point we can't put an exact figure on it, but there will be some improvement there.

Abhishek Poddar

analyst
#34

Alright. Thanks very much, sir — and best of luck to you.

S.K. Ramaiah

executive
#35

I appreciate that.

Operator

operator
#36

Thanks. Our next question is from Pritesh Chedda at Lucky Investment Managers Private Limited. The line is yours — go ahead.

Pritesh Chheda

analyst
#37

Sir, just a couple of things to clarify. You said revenue for 2023 would be INR 3,600 crores and revenue for 2024 would be INR 5,000 crores, and that most of the FGD execution — meaning it will slow down into 2024. Is that right on the assessment?

S.K. Ramaiah

executive
#38

My understanding is that the INR 3,600 crore figure came from the INR 8,855 crore order backlog that we had accumulated at the start of the year.

Pritesh Chheda

analyst
#39

Uh-huh.

S.K. Ramaiah

executive
#40

When you factor in all the orders we're going to build up during the current year as well, leaving out the FGD orders — and once the FGD orders are included, that figure should climb to roughly INR 4,000 crore+. Then next year, clearly, the backlog rises by the end of the year, driven by the remaining pipeline of orders worth INR 1,500 crore, plus the FGD orders that have been backed, plus the additional orders we're expecting. That's the basis on which that projection was provided for beyond 2023 to 2024.

Pritesh Chheda

analyst
#41

My second question is this: you said that on FGD you received 10% advance, and the assessment is that there won't be any incremental working capital. So that means—

S.K. Ramaiah

executive
#42

Right.

Pritesh Chheda

analyst
#43

If you go from INR 3,000 to INR 5,000 in revenue, is there barely any change in your working capital—in the absolute working capital requirement?

S.K. Ramaiah

executive
#44

It's not a large amount, honestly. What I can tell you is that in this kind of business, you also arrange back-to-back terms with your suppliers, and the remaining resources come from our own side—things like construction and infrastructure inputs. So that is already in place. That doesn't call for investment. What you need to do is place orders for the supply packages, and we'll tie those on a back-to-back basis with matching advances and so on. That's how we can manage it without much of an increase in working capital.

Pritesh Chheda

analyst
#45

So, is that assessment right? Whatever the absolute working capital is today, when you shift revenue from INR 3,000 to INR 5,000, the absolute working capital requirement won't increase in sync with revenue?

S.K. Ramaiah

executive
#46

That won’t—

Abhishek Poddar

analyst
#47

Regarding what Molik requested, Satish, that is interest-free, so we need work in order to utilize it. So look, this project is going to be self-sustained. So all of it can be cash neutral.

S.K. Ramaiah

executive
#48

This won’t affect our cash position either way.

Abhishek Poddar

analyst
#49

We don’t expect any further money to be put into this project.

Pritesh Chheda

analyst
#50

Alright. Sir, my final question: are these FGD orders one-off in nature, the ones that bring you to these levels of backlog and revenue? And after 2024, do you foresee a tapering off, or do you foresee this higher base holding — or what levers would sustain that higher base?

S.K. Ramaiah

executive
#51

I mean, look, the company has diversified considerably compared with what it was 5 years ago or 10 years ago, and we feel pretty confident, you know. Of course, all of these are one-time retrofit jobs. So 50% has already been ordered, the remaining 50% is in the pipeline, and there our target is under 2,000 to 3,000 MW, and that as well—

Pritesh Chheda

analyst
#52

You said 3,000 MW, correct?

S.K. Ramaiah

executive
#53

Roughly 169,000 MW of that total is made up of identified retrofits. Of that portion, half has already been ordered in the market, and the remaining 50% is still going through the ordering process.

Pritesh Chheda

analyst
#54

Alright.

S.K. Ramaiah

executive
#55

This ordering should wrap up within the next six months to a year, possibly. That's to meet the deadline. It may not be entirely feasible to hit the 2024 deadline. It could extend by another one, or 12 to 18 months, to handle the remaining order, booking, and execution and so on. But what I — specifically your question, I agree, what happens without the FGD going forward? I think, as of today the company operates in the infrastructure space, the O&M side, we're growing in the non-power segment, and in international markets as well. And then, in railways, we've established a major presence, and railway investments will keep continuing, and we are putting in more than INR 100,000 crore annually. There are plenty of jobs that fit our product or service profile — depots, maintenance depots, maintenance workshops, and then railway train works. So, I agree, certainly, the opportunity exists. And then more significantly, the private sector is going to arrive with large investments in state infrastructure, and then mining and metals. And what I can say is that mining will present a great many opportunities. As of now, we've secured a mining development project of 5 million tons.

S.K. Ramaiah

executive
#56

We intend to raise that figure to between 15 and 20 million tons over the coming 1 or 2 years. That ought to deliver substantial growth at the top line, and at the bottom line too where the O&M business is concerned. If this MDO gets implemented starting in 2024, it should bring in as much as INR 400 to 600 crores of extra revenue on the O&M side. We're also examining another 1 or 2 projects — a further 10 million tons — which ought to push revenue up further to, let's say, INR 1,500 to 2,000 crores. So we do have plans in place for closing those gaps, though we recognize these make up all the opportunities available. As for the infrastructure segment, I don't believe any slowdown will occur there. There will only ever be upside where investment is concerned, and the company has rightly kept pace with all of these investments, and that explains how the order booking is coming in.

Jami Satish

executive
#57

Right. So this FGD carries a follow-up O&M contract worth nearly INR 1,000 crore, spread across five years. That works out to roughly INR 200 crore each year. Beyond that, the MDO project is going to stabilize. Just these two together will contribute INR 1,000 crore in top line after three years. So once the FGD wraps up, for those three years we'll consolidate, and this INR 1,000 crore will come on top as a supplement. Beyond that, the BoPs we've now developed in-house will be a big help when it comes to bidding for larger projects. So we'll watch how it goes in terms of project count, because as things stand we're running 112 projects, O&M included, O&M included. So we'll see the size come down. Naturally, O&M will keep going, so the number will always stay on the higher side. Based on our PQs, we'll go after larger projects. So this will be a big help in terms of our, in terms of sustaining growth going forward as well. So after three years we'll consolidate on where to, move ahead. And naturally, the, the focus will remain on margins and cash flow, because that matters. Yes, sir.

Pritesh Chheda

analyst
#58

And finally, sir, out of 69,000 or out of 80,000 MW that have been ordered, what is the MW we've secured? And our line of business here is mostly mechanical, civil, and erection — does that include the equipment or not?

S.K. Ramaiah

executive
#59

So this project is a full EPC scope — 8,460 MW, roughly 15 units ranging from 330 MW to 660 MW. Engineering, procurement, and construction are all in there, along with the civil, structural, and mechanical work. As for the technology partner, we'll be opening up there, and the critical process equipment — the absorption equipment and the technology portion of the FGD — is going to be supplied and sourced from them. The remaining installation work and sourcing, we'll handle ourselves.

Pritesh Chheda

analyst
#60

All right.

S.K. Ramaiah

executive
#61

We handle civil and structural installation entirely, ourselves. That’s the way the plan is set up.

Pritesh Chheda

analyst
#62

That sounds good.

S.K. Ramaiah

executive
#63

So because of that, it's really baked into how our business model works.

Pritesh Chheda

analyst
#64

All right, thanks a lot.

Operator

operator
#65

Thanks. Our following question is from Rohit Natarajan of Antique Stock Broking. Your line is open — please proceed.

Rohit Natarajan

analyst
#66

Thanks a lot for giving me the chance to ask. Congrats on that really impressive orders in hand. My first question has to do with the L1 you've flagged — it's roughly INR 1,500 crore. Could you shed some light on just what those orders consist of, where they stand, and exactly when they're expected to show up in the backlog?

S.K. Ramaiah

executive
#67

Could you repeat that, please?

Rohit Natarajan

analyst
#68

the L1 order worth INR 1,500 crore.

S.K. Ramaiah

executive
#69

Yeah, as I mentioned, right. So in this, we've got roughly seven FGD orders — these aren't EPC orders, they're construction orders — around 1,950 MW for approximately INR 870 crore. That comes from the Goenka Group of CESC, at Haldia, Chandrapur, and Birzebbuga station, units of 250 to 350 MW, seven units. And then there's the Bangalore Metro project, where we're L1 for roughly INR 450 crore. And then a railway electrification job in Bangalore, around INR 88 crore. And then one O&M job in Nigeria, where we're already handling the installation work for the Dangote, about INR 94 crore.

Rohit Natarajan

analyst
#70

Alright. And sir, you also mentioned that beyond what we’ve already won, you’re seeing an opportunity of about INR 3,100 crore.

Jami Satish

executive
#71

No, my point was that we had a plan of roughly INR 4,000 crore. Out of that, INR 700 crore has already been secured during the first quarter. I'm referring to this excluding FGD, and beyond that we are chasing opportunities valued at close to INR 17,000 to 18,000 crore across power, civil, non-power, electrical, OEM, water, and then roads, et cetera. So we are fairly confident that perhaps another INR 1,500 to 2,000 crore ought to come through in addition to the orders already in the pipeline, on top of the FGD orders that we are winning.

Rohit Natarajan

analyst
#72

Understood. One further item concerns the capital injection you mentioned, the professional development fund. In what precise way might that help, if it helps at all, with any credit enhancement you have in mind — including the possibility of bankers extending improved non-fund-based limits and fund-based limits? What does the situation actually look like there, sir, if you could shed some light on it?

Jami Satish

executive
#73

Typically, funds aren't something we require. As a matter of fact, we're working to reduce the fund base. So the key need is non-fund facilities, meaning bank guarantees and similar instruments. We've therefore secured limits totaling close to INR 1,650 crore. Out of that, roughly INR 900 crore is utilized. We've maintained these limits to back our growth. Whenever a solid project comes along, I should be positioned to support the non-fund-based limit. This will assist with promoters' inclusion as a backstop for long-term equity, which gives bankers considerable confidence when they carry out the assessment for the non-fund limit. Beyond that, it helps enhance the internal trade rating with the bank, allowing us to negotiate better pricing. And it will also be helpful for the external-

Rohit Natarajan

analyst
#74

All right, so just to make sure I've got this right — suppose the order is INR 100 crore, then normally you'd need a non-fund-based limit of roughly INR 20 crore. Is that how the non-fund-based limit should be viewed?

Jami Satish

executive
#75

At present, the range is 3%-10%.

Rohit Natarajan

analyst
#76

Alright.

Jami Satish

executive
#77

Depending on the project, we’re able to take 5%-7% on average — that’s for the PBG.

Rohit Natarajan

analyst
#78

So would that 5%-7% cover everything, like your EMD, or perhaps the performance guarantees?

Jami Satish

executive
#79

Look, when we quote for a project, the EMD typically comes in at around 1%, but as soon as the contract gets awarded, that EMD is released. What stays in place after that is the PBG — the performance bank guarantee — at somewhere around 6%-7%, or perhaps 5%-7%.

Rohit Natarajan

analyst
#80

How about that mobilization advance? When the client hands it over, you’ve got to provide some kind of guarantee for it too, correct?

Jami Satish

executive
#81

That really hinges on the customer, sir, since whether we'd draw a mobilization advance varies from one customer to the next. It either arrives as an upfront mobilization advance or as an advance tied to milestones. So because,

Rohit Natarajan

analyst
#82

So when you mention that not much in the way of incremental working capital is needed, I figured perhaps you're looking to push much more aggressively on this mobilization advance. Which would mean your requirement for additional non-fund-based limit is going to be considerably higher.

Jami Satish

executive
#83

Yeah, if we pull it, then yeah, we have to. For which—

Rohit Natarajan

analyst
#84

So looking at it, the current annualized limit sits at roughly INR 700 crore, and if I apply that 20% metric for the non-fund-based limit, then your limits are probably, you know, mostly used up, correct? I mean...

Jami Satish

executive
#85

Well, now, look — we don't take the advance on every contract. Take BHEL, for instance: each contract includes a clause allowing a 10% mobilization advance, and we don't draw on it, since it now carries 14% interest — we don't take it. So it-

Rohit Natarajan

analyst
#86

Right, right.

Jami Satish

executive
#87

It's somewhere in the neighborhood of 20% to 30%, maybe 35%, of all the projects. We don't offer that on every project, and not every project is going to include that clause.

Rohit Natarajan

analyst
#88

Understood, sir. Noted, noted. Many thanks. That's all from me. Wishing you the best.

Jami Satish

executive
#89

Yeah, thanks for that.

Operator

operator
#90

Thanks. Our next question is from Vivek Hinduja at Thrive Capital Partners. Please go ahead.

Vivek Hinduja

analyst
#91

Hi, everyone. Thanks for giving me the chance to speak. Sir, I had a question: during the first quarter, we saw reports about an income tax raid on the company — so to speak — and that included top management and the promoters. If you could shed some light on that for us as we go, and also, has the IT department made any monetary claim against the company as a result of those raids?

Jami Satish

executive
#92

Okay, so from 13 July through 17 July, they conducted a search under Section. It was a search, in fact, across different premises. Right now, the matter is still ongoing. Whatever information the Income Tax Department has requested, we have kept supplying it. They came regarding certain subcontractors, connected to some projects where they had some concern, alright. They have even visited multiple companies, Power Mech included. So we are furnishing all the information from the search. The matter is still in progress at this point. It could take additional time. Naturally, this will have no impact as far as our operations go, and we don't foresee any impact measured on our financials.

Vivek Hinduja

analyst
#93

All right. Sir, based on what the media has reported, we heard about it, and I understand some incriminating evidence was discovered on the premises. Could you shed some light on that, or perhaps offer some clarification?

Jami Satish

executive
#94

Yeah. Look, even the media — we’ve run into this because I don’t know where they’re getting their information and all, but honestly, that’s not really the situation, okay? It is, yeah, it’s entirely speculative, because the sharing of information and all is still underway. It’s an ongoing process. It could take another 3 to 4 months. So we’re providing all the information that’s required regarding contractors, projects, wherever it’s needed, and the matter is continuing. And no claim is being made, okay, as of now? Because it takes time. It’s the information flow and all, it will take time. We have to supply everything required to the department’s satisfaction. So based on how the information flows, the case will be settled. So it will take some time, sir. Okay. Thank you very much.

Operator

operator
#95

Thanks. The next question is from Dixit Doshi at Whitestone Financial Advisors Private Limited. Please go ahead.

Dixit Doshi

analyst
#96

Yeah, thanks for the chance to ask. First, just one clarification about that FGD order worth INR 6,100 crore — does that figure take in the INR 1,000 crore of O&M?

Jami Satish

executive
#97

No, it doesn’t include it—it’s excluded. So that INR 1,000 crore comes on top of INR 6,100 crore; that order has not yet been received.

Dixit Doshi

analyst
#98

Alright.

Jami Satish

executive
#99

That's going to give us another chance down the road with FGD.

Dixit Doshi

analyst
#100

Following the commissioning. Following the commissioning.

Jami Satish

executive
#101

That order hasn't come to us yet. It will be tendered—it has been tendered; we're L1—but the awarding side is split into two parts. They've even given the FGD, the EPC portion, of INR 6,100 crore. The remaining INR 1,000 crore they'll award afterward.

Dixit Doshi

analyst
#102

Alright. Alright.

Jami Satish

executive
#103

That's going to represent an INR 200 crore per annum opportunity on the O&M side.

Dixit Doshi

analyst
#104

All right, all right. My next question concerns this MDO project at Coal India — the MDO project. So when will revenue begin to come in?

Jami Satish

executive
#105

Starting with Q4 of 2024, sir.

Dixit Doshi

analyst
#106

For Q4 of FY 2024 — and as of today, what are the current figures for gross debt and net debt?

Jami Satish

executive
#107

Right. As of today, we've reached roughly INR 490, and then net, our deposits stand at INR 150, so the net figure works out to about INR 340 crores, and we expect that to decline.

Dixit Doshi

analyst
#108

Okay. And as a final question, what would the retention money on our balance sheet amount to as of today?

Jami Satish

executive
#109

That comes to roughly INR 315 crore.

Dixit Doshi

analyst
#110

Alright, that's all I have to share. Thanks.

Jami Satish

executive
#111

Yes, thank you, sir.

Operator

operator
#112

Thanks. Our next question is from Ankur, an individual investor. Go ahead, please. Mr. Ankur, please proceed with your question. Mr. Ankur, if your phone line is muted, kindly unmute it and ask your question. As we haven't received a response from Mr. Ankur's line, we'll move to the following question, which is from Faisal Hawa of H.G. Hawa and Company. Please go ahead.

Faisal Hawa

analyst
#113

My question is this: for the orders you've booked so far — specifically those taken over the last 1.5 years — what ROC and ROE are you aiming for? And given the commodity price rise of the past 3 to 4 months, will you see a benefit from that?

Jami Satish

executive
#114

Right. Look, these aren’t pure cash contracts, all right? So margin-wise, it’ll be 11%+. So for sure, we don’t have to put in much beyond the CapEx of INR 25 crore–INR 30 crore. So that’s going to help quite a bit when it comes to lifting both ROE and ROC, since we have no plans to take on any debt, so that will also help push ROE.

Faisal Hawa

analyst
#115

So what's the ROE that will ultimately come out, say, for a year and a half, and then somewhere along the way?

Jami Satish

executive
#116

Sir, my assumption is that it will definitely go past 18% to 19% or more, sir. On a blended basis.

Faisal Hawa

analyst
#117

Sir, I’m unable to hear you.

Jami Satish

executive
#118

18% to 19% or higher, blended, sir.

Faisal Hawa

analyst
#119

Sir, it seems like we're expanding into a lot of sectors, you know. So what risk management are you now putting in place? Because if two or three projects go bad, or there's some government intervention in those projects, does that affect the company? Could you just list out the risk management steps, you know, say, I think, the steps you've taken to really, you know, protect the company from, you know, going backwards?

Jami Satish

executive
#120

Could you say that again, please? I’m sorry, but the audio isn’t coming through clearly.

Faisal Hawa

analyst
#121

We're moving into a lot of sectors now, and a lot of those sectors aren't related to each other. So what kinds of risk management steps are you taking to, you know, keep the company from going backwards?

Jami Satish

executive
#122

Okay. So in our industry, there are three elements: first, execution; second, service; and third, the material component. We come in as a contractor, so typically everything is already in place when we step in, which means most of the risk is automatically mitigated. Now, on the service component, manpower of course plays a key role. We find that the price variation clause offers solid protection, so that for any changes in labor and so on, we are well protected. The second part is the material component. Again, over the last two years we have seen very abnormal price movements. So whatever minor cost impact we had, we have observed that. Now, going forward, for the projects we are quoting, we have made a decision: unless it is well protected in terms of a price variation clause, escalation, we will not bid for those types of projects. And more importantly, once we execute and it comes to the payment part, okay, the experience has been that, at one time, the receivable cycle used to be 45 to 60 days, that rose to 90 to 100 days. Now, it is coming down to 70 to 80 days. And we are very particular about the customer in terms of the funding, the healthiness of the financials, so that we are executing and we are getting paid on time.

Jami Satish

executive
#123

That point matters a great deal. So when we pick projects, the payment cycle needs to stay at 60 days at most. Naturally, it can stretch to 70 or 75 days. On the recent project, the terms have consistently been, you know, everything sits at 30 or 40 days at most. So the goal is to shorten the working capital cycle as far as we can. That's one of the things we're taking more seriously.

Faisal Hawa

analyst
#124

Sir, what's the order book ratio on the government side? And how intense is competition in government orders right now? You know, is it extremely competitive, and, you know, articles, you know, even citing below the base price? And, you know, how many orders have you lost over the last three to four months to very, very aggressive bidding?

S.K. Ramaiah

executive
#125

Let me break that down for you. I think this breaks into a few different segments. The mechanical business is the main one — we're a leading player there, and when we bid, we do it around the margins we're able to protect. And as I mentioned, in certain jobs the customer has ended the contract that was already in place and handed that work to us. That's what's happening right now. Then we hold a leadership position in this infra business, the mechanical business. And on the civil side too, there are a handful of players out there. But even so, on one of the jobs in Udupi, a job was terminated, and we also found INR 275 crore. So competition exists. We're able to handle that competition, and we quote what we expect our cost to be, and then our margins are there. And also, especially on the private side and the oil and gas side, we have an advantage thanks to our execution capability and our commercial capability. That's why we get preferred on the oil and gas side as well, and with some of the private players too. But yes, competition will be there on the government projects.

S.K. Ramaiah

executive
#126

There's no way around that. Still, plenty of opportunities exist. Even a success rate of 15%-20% works fine for us, and we're ready for that kind of hit rate. That's what the market expects when 78 players are in the segment.

Jami Satish

executive
#127

Look, Power Mech has been pretty conservative from the very beginning, so it doesn't take on just any project, all right, since that kind of thing can carry risk. We're very selective, okay? And that conservative approach is what we'll always stick with. We're comfortable, we'll take the order. If we spot certain risk factors where we aren't at ease regarding execution — whether that's the customer or the location — we stay out of that project. So that conservative way of doing things is going to carry on.

Faisal Hawa

analyst
#128

What's the split, roughly, between private orders and government orders for us?

S.K. Ramaiah

executive
#129

Yeah, it can be roughly 50/50. Of course, FDG order may shift with this. We have to redo work on that. That's just how it is. The majority of infrastructure projects get the go-ahead in government.

Faisal Hawa

analyst
#130

India as well?

S.K. Ramaiah

executive
#131

Coal India too, yeah. That nation — because right now they're, you know, performing quite well.

Operator

operator
#132

Thanks. Mr. Hawa's connection dropped. Rishikesh from Robo Capital is up next — go ahead, please.

Rishikesh Oza

analyst
#133

Hi, can you hear me?

S.K. Ramaiah

executive
#134

Yeah.

Rishikesh Oza

analyst
#135

Hello, sir. I have a question of my own. Would you be able to share the EBITDA margin guidance for FY 2023 and FY 2024, please?

Jami Satish

executive
#136

Right now we're running at roughly 11%-12%, and they're watching that margin profile get better as we go. And like we talked about, the projects we're quoting directly can help us save on things like the cost of borrowing credits and so on. That should also contribute to EBITDA margin. So we expect the profile — the margin profile — to improve steadily.

Rishikesh Oza

analyst
#137

Alright, thanks a lot.

Operator

operator
#138

Thanks. Our next question is from Deepak Poddar at Sapphire Capital. Go right ahead.

Deepak Poddar

analyst
#139

Thank you very much, sir, for the chance, and many congratulations on the strong result. So, we just wanted to ask: what is our present execution capability each month, expressed in rupees crores?

Jami Satish

executive
#140

At this point it's properly established, sitting somewhere between INR 750 crore and INR 1,000 crore. That figure can be scaled up, and in fact it could gradually be raised as far as INR 1,200 crore.

Deepak Poddar

analyst
#141

Is it INR 750 crore to INR 1,000 crore, and as much as INR 1,200 crore annually?

S.K. Ramaiah

executive
#142

On a quarterly basis.

Deepak Poddar

analyst
#143

On a quarterly basis.

Jami Satish

executive
#144

On a quarterly basis, that comes to INR 1,000 crore.

Deepak Poddar

analyst
#145

Mm-hmm.

Jami Satish

executive
#146

That covers it. Now, regarding the FGD, we've set up a standalone unit led by senior professionals. The team is fully in place at this point.

Deepak Poddar

analyst
#147

Mm-hmm.

Jami Satish

executive
#148

Alright, so this should climb steadily over time.

Deepak Poddar

analyst
#149

Right. The reason I asked that is, given the revenue output we have for this year, ideally — since the second quarter is generally lean — our second half execution per quarter should be close to about INR 1,000 crore-INR 1,200 crore, right? I mean, unless we have that, we won't kind of execute our annual target, right?

Jami Satish

executive
#150

During any financial year, the fourth quarter — and quarter three, too — those are the periods when our turnovers come through.

Deepak Poddar

analyst
#151

Alright.

Jami Satish

executive
#152

When you compare it, it has shifted from quarter one to quarter two. Previously, the figure was around INR 450 to 500 crores. It has now risen to INR 600 crores, and at this point it has climbed to nearly INR 750 crores, which is an all-time—

Deepak Poddar

analyst
#153

Mm-hmm.

Jami Satish

executive
#154

So within the Power Mech journey — in Q4 of last year, we closed at close to INR 900 crore, right? So that INR 900 crore to INR 1,000 crore level is well tested by now. What we need to focus on is improving further. Right now, we're working on building up the resources and infrastructure needed to sustain execution.

Deepak Poddar

analyst
#155

All right, all right, all right. So, given that we've already completed INR 900,000 crore, on top of that, perhaps INR 200 to 300 crore more could be needed by the fourth quarter — I mean, by the third and fourth quarters — to boost your execution capability, considering the level of output we have, correct?

Jami Satish

executive
#156

Okay, so at this point it stands at INR 900 crore, and that figure was already put to the test in quarter four of last year, right? Then for this year, the target we've set is more or less — it's fairly comfortable — since on an incremental basis you'll find that quarter three and quarter four will contribute, right, additional volume when measured in absolute terms, okay? Bit by bit, you'll see that figure climb even higher.

Deepak Poddar

analyst
#157

That's fair enough. Yeah, I get it. Yep, that's all I have on my end. Best of luck to you, sir.

Jami Satish

executive
#158

Yeah, thanks a lot.

Operator

operator
#159

Thanks. Just a reminder for everyone that you can hit star and one if you'd like to ask something. Once more, everyone, you can press star and one to ask a question. Our next question is from Ankur, an individual investor. Go right ahead.

Analyst

analyst
#160

Hi, thanks. My question concerns the notice sent to the stock exchange today about a board meeting regarding a possible issue to the promoters. Now, we know the company is at an inflection point. Profitability, revenue, everything is going to be very, very good over the next two, three years. So at this point, for the company to go ahead and make a preferential issue to promoters really isn't minority shareholder-friendly. What would be nice is a rights issue, which is offered to all the stockholders of the company. If somebody subscribes, fine. If not, then promoter shareholding will go up. So that's my humble submission to the promoters.

Jami Satish

executive
#161

Yes, sir, we have observed that, and thank you.

Analyst

analyst
#162

Alright, I’m finished.

Jami Satish

executive
#163

Thanks very much, sir. Appreciate it.

Operator

operator
#164

Thank you. Since no more questions remain, we've come to the conclusion of the question-and-answer session. At this point, I'd like to pass the conference back to management for closing remarks.

Jami Satish

executive
#165

Raghuram, did you want to chime in on that?

S.K. Ramaiah

executive
#166

Yeah, I think quite a few points have already been addressed. I'd say we have a very clear vision for those three years, and as for the issues that might arise in year three, perhaps we're prepared for those as well — on the marketing side, on the business development side, and then most importantly, on the operations side. So the company is well positioned for INR 4,000 to 5,000 crore of turnover over the coming years. And what matters is sustaining that growth, and then there will be new opportunities in infrastructure, wind and mining, and then railway, and we'll also focus now on international operations, as I told you, with the India piece behind us. So I think this growth story will carry on for the next couple of years. On the operations side, we're fairly comfortable with the present setup that we have, and adding headcount — critical headcount — and also the capability that's needed in different areas. That should take care of our conversion and then the overall thing of the project. Thank you.

Operator

operator
#167

Thanks. This is Nirmal Bang Equities signing off — that brings the conference to a close. We appreciate your participation. Lines can be disconnected now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Power Mech Projects Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Power Mech Projects Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Power Mech Projects Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.