Power Mech Projects Limited (POWERMECH) Earnings Call Transcript & Summary

November 15, 2022

National Stock Exchange of India IN Industrials Construction and Engineering earnings 57 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to Power Mech Projects Ltd's Q2 FY 2023 Earnings Conference Call, brought to you by Nirmal Bang Equities Private Ltd. Please be aware that every participant line is listen-only, and once the presentation wraps up, you'll have a chance to pose questions. If you require help at any point during this call, just press star then zero on your touchtone phone to signal an operator. Kindly note that this conference is being recorded. I'll now turn things over to Mr. Prasheel Gandhi of Nirmal Bang Equities. Thank you, and the floor is yours, sir.

Prasheel Gandhi

analyst
#2

Thank you, Steven, and good afternoon everyone. Nirmal Bang Equities Private Ltd is glad to have all of you join the Q2 FY 2023 earnings conference call for Power Mech Projects Ltd. Joining us from the management side are S.K. Kodandaramaiah, Director Business Development, and Jami Satish, CFO. At this point I'll pass the call to management for their opening remarks, and after that we can move to a Q&A. Thanks, and the floor is yours, sir.

Jami Satish

executive
#3

Alright, thanks. Good afternoon, everyone. This is Satish speaking. Joining me is Mr. S.K. Kodandaramaiah, our Director of Business Development. We're glad to have you all on this call for Q2 and H1 of FY 2022 to 2023. I'll spend a few minutes giving you an update on how we did financially in quarter two and the first half of 2023. Our results for quarter two and H1 FY 2023 match what we set out to achieve and remain solid. The full-year target we've set remains on course, and it looks quite likely and within reach. The FGD ordering process has begun, and project mobilization is already underway. We expect revenue booking from FGD to commence in quarter four. Any revenue coming from FGD would come on top of the overall target we've set for this financial year. Total income as reported for quarter two of FY 2023 stands at INR 774 crores. That marks the highest-ever execution for Power Mech in any quarter two across its history. EBITDA came in at roughly INR 90 crores, with PAT at INR 44 crores, while in quarter two of the prior financial year, reported total income was INR 544 crores, reported EBITDA was INR 63 crores, and PAT was INR 27 crores. Year on year, total income grew by nearly 42%.

Jami Satish

executive
#4

As revenue increased, EBITDA rose 43% and PAT went up 62%. For quarter two of FY 2023, the revenue mix breaks down like this: the erection business brought in INR 161 crores; civil business, which includes railway, water projects, and so on, accounted for nearly INR 367 crores; operation and maintenance came to INR 226 crores; electrical business was INR 17 crores; and other income was roughly INR 3 crores. In quarter two of the previous financial year, by comparison, erection business provided INR 106 crore, civil business about INR 223 crores, operation and maintenance INR 188 crores, electrical business INR 23 crores, and other income approximately INR 5 crores. Domestic operations accounted for almost 87%, with the remaining 13% coming from overseas business. The split between power and non-power is 63% and 37%. Growth occurred in every segment apart from electrical business, where the company is cautious about expansion in the electrical space for a variety of reasons. The O&M business grew 21% and made up nearly 29% of total business. Likewise, total reported income for the first half, H1 FY 2023, stands at INR 1,523 crore. EBITDA is approximately INR 175 crore, and PAT is INR 83 crore.

Jami Satish

executive
#5

In the first half of financial 2022, reported total income came to INR 172 crore, EBITDA stood at INR 134 crore, and PAT was INR 59 crore. Compared year over year, H1 total income has increased by nearly 30%, and alongside that revenue growth, EBITDA rose by 31% while PAT climbed by 42%. For the first half of FY 2023, the revenue mix breaks down this way: the erection business brought in INR 313 crore, the civil business, which includes railway and water, contributed INR 743 crore, O&M accounted for INR 422 crore, the electrical business added INR 39 crore, and other income contributed INR 5 crore. Likewise, in the first half of the prior financial year, erection business did roughly INR 243 crore, civil business delivered INR 507 crore, O&M brought in INR 361 crore, electrical business contributed close to INR 51 crore, and other income was INR 11 crore. In H1 of this current financial year, domestic business made up 85% and 15% came from overseas business. In the power sector, revenue from the power mix is roughly 62%, while non-power is about 38%. Execution bandwidth has been expanding quarter over quarter, helped by more in-house resources, greater manpower strength, additional equipment, and a strong order book. The company also anticipates a healthy volume of order booking and expects the execution cycle to pick up in the international market.

Jami Satish

executive
#6

Mr. Sajja Rohit leads the international business, and alongside him is Mr. N. Srinivasa Rao, who has come aboard as MD and CEO for international operations, arriving from Shapoorji Pallonji. He is a solid addition to reinforce the international operations, and the emphasis is more on the operation and maintenance business to complement both domestic and international operations. The company is now well positioned to execute projects in a range of INR 750 crore-INR 1,250 crore per quarter, and we also expect gradual improvement on a QoQ basis, while retaining core competence in O&M and Mechanical, C&I. Turning to the other line items, depreciation cost as a percentage to revenue stayed on the lower side because of planned CapEx spending. Likewise, finance cost as a percentage and as an absolute number stayed controlled thanks to an improved working capital cycle and cash flow. Overall, the working capital cycle is still improving for the period owing to a change in the customer mix. Net current days, excluding cash and cash equivalent, now range around 138 to 145 days during the period. Further improvement is expected. This stood at around 150 days, 153 days, as of March 31st, 2022, and it was 205 days as of March 31st, 2021.

Jami Satish

executive
#7

We've therefore observed a meaningful enhancement in net working capital days, and further improvement is anticipated. In addition, operating cash flow for the period comes in at INR 62 crore+, which is a favorable development. Average monthly collections stayed within the INR 262 crore-INR 300 crore band, and this is anticipated to gradually climb toward INR 350 crore of collections each month. Turning to debt, both gross debt and net debt stayed in check despite business growth and the strong rise in the order book. Gross debt is at INR 481 crore, while net debt is nearly INR 292 crore. It has declined relative to financial close, when gross debt and net debt stood at INR 320 crore. We've recorded a decrease in debt. The company's order backlog, as reported, is INR 24,076 crores. That figure includes MDO. The order backlog excluding MDO comes to INR 14,782 crores. So far in the current financial year, the company has brought in new orders worth INR 7,445 crores. For the full year, the company has set a goal of INR 10,000 crores in new order additions.

Jami Satish

executive
#8

So as it stands, the L1 status order book sits at roughly 964 crores — that's near 1,000 crores. Over the coming four months, we have to plan for fresh orders worth INR 1,600 crores. Our confidence is greater now that we will hit this year's target of INR 10,000 crores in additions. Thanks to the robust order book, the company has established strong visibility for its growth across three years. The quarterly run rate looks quite healthy. In quarter four of last year we booked INR 950 crore, and this year, as things appear, the bandwidth is well positioned to land between INR 750 crore and INR 1,250 crore, so the reserves are built in. With the current order book, visibility for the coming three years is clear-cut. I would now like to ask Mr. S.K. Kodandaramaiah, sir, to add a few more market opportunities before we move into Q&A. Thank you.

Sudha Kodandaramaiah

executive
#9

Right. Thank you, Satish, and thank you, Nirmal, for joining this call. That was for the excellent input you provided on the company's first-half results. Satish, that was very kind of you. Turning to some of the other developments — the business, business growth, then the marketing side, and also the various opportunities and how the company will be taking these opportunities forward — let me give you a brief overview. I think, on a broad basis, the order backlog stood at INR 8,854 crores, 55 crores at the close of last year, and it has risen to INR 40,782 crores, a jump of nearly 67%. I think this is mainly driven by the huge order we received from Adani for the INR 6,163 crore of 8,460 MW of, you know, IPP jobs across four, you know, plants. Now, segment-wise, you know, the changes, you know, in the mechanical and installation business, which was INR 1,650 crore... you know, because of these Adani FGD orders, it has gone up to INR 7,796 crore. The civil, you know, the order backlog of INR 5,842 crore is more or less the same. On the O&M side, you know, it is, you know, from INR 1,244 crore, it is now around nearly INR 1,000 crore.

Sudha Kodandaramaiah

executive
#10

On the electrical side, we moved up a little, from INR 118 crore to INR 148 crore. On the business mix, as Satish mentioned, domestic remains dominant, driven by the many investments coming in, especially from the government sector, plus some private-sector investment as well. That share is nearly 97%, while international accounts for 3% of the backlog balance, out of INR 14,782 crores. Turning to power versus non-power: previously, growth came mostly from non-power because of the power sector's shortfalls over the last five years. The split stood at 45%-50% power to non-power, 41.5%-58.5%. Things have now shifted toward power, thanks to the FGD opportunities emerging. Power sector business is now 63% and non-power 37%, at INR 9,487 crore and INR 5,295 crore. Those are the key figures on order backlog and the rest. Among the major orders booked in the first half: the Adani order, as I mentioned, INR 6,664 crore; a Kudgi coal handling plant at roughly INR 191 crore; Godda balance works, awarded to another contractor on a risk purchase basis, INR 105 crore; FGD civil works at North Chennai, around INR 119 crore; and PEB sheds in the western region, INR 113 crore.

Sudha Kodandaramaiah

executive
#11

And then lately, we've picked up some tracks and towers from Vedanta as well as Central Railway for roughly INR 41 crores, plus a bridge repair job from Adani in Telangana worth about INR 50 crores. And more significantly, over on the O&M side, there are plenty of jobs secured primarily for repair, maintenance, and capital overhauls — around 50 to 60 packages across various plants — and all of these are quick turnaround orders. That comes to approximately INR 166 crores. Looking ahead, what I'd say is that on the O&M side, yes, we are handling major projects, and we saw the first half revenue come in at roughly INR 422 crores. There are opportunities we're chasing in Mundra and Tiroda for the renewable segment, and then opportunities in Odisha — 3 x 660 MW, 2 x 600 MW — then Ghatampur, 3 x 660 MW, then 1 x 800 MW at North Chennai, and also a couple of other projects. And there's focus, as Satish mentioned, with Mr. Srinivasa Rao having come in to support the O&M projects. On the O&M side, we're trying to give a lot of push in the Middle East.

Sudha Kodandaramaiah

executive
#12

We've been observing a bit of an uptrend when it comes to capital overhauls, maintenance jobs, and an O&M job that's in the pipeline. For Dangote, we've already mobilized close to—roughly, nearly—100 crores, and that work's agreement needs to be signed shortly. Then on the opportunities side, we're also examining non-power sector opportunities, O&M, beyond the power sector and various other sectors. And, as an input I've shared before as well, there's an O&M component within the Adani order. Once the jobs are completed, it's an additional 1,000, 200 crores—sorry, 1,021 crore. And the drinking water projects too—what we're handling as of today—those will also carry an O&M component once completed. That comes to roughly 80 to 100 crores. So that's how we're going to further look at consolidating the O&M business. The major works—the status of the major works—are Udangudi, 2 x 600 MW, where we've finished about 15% out of INR 345 crore. The Buxar boiler job, 25%, around INR 176 crore. At Bhusawal, we've completed almost 70% of the work. That's 2 x 660 MW, BTG, this fuel work.

Sudha Kodandaramaiah

executive
#13

Yadadri is progressing quite nicely. It's a big project in Telangana worth INR 813 crore, and 60% is finished. Dangote is nearing completion at $76 million. Maitree in Bangladesh — 2 x 660 MW — is also moving along on a fast-track basis; INR 855 crore, and we've completed 75%. Ramayampet Canal stands at roughly 90%. Drinking water is now receiving a great deal of impetus, and progress has picked up considerably now that mobilization is underway and procurement activity has begun. DPRs for nearly 2,000 villages have been finished. Around 3% of the work is now complete, and we expect revenue of +100 crores each month within the next couple of months. Beyond that, it can grow depending on DPR approval and further orders being regularized. Turning to the road projects, Hassan and Mizoram, INR 780 crores, 35% of the work is done. Now Adani FGD, INR 616 crores — we've gotten the initial orders for the engineering and technological equipment on GA, at the site. That should let us concentrate on engineering and then on ordering the remaining packages for civil, structural, mechanical, as well as many of the other bought-out items.

Sudha Kodandaramaiah

executive
#14

The other one that's come in recently is their newest order, the BMRC metro project — a shed construction for the maintenance depot in Bangalore. That's roughly INR 427 crore. We're executing this through a JV partnership with RITES, and that work should also get underway this year, with some revenue coming in. Now, what I can tell you is that the remaining opportunities we're pursuing total close to INR 15,000 crore for the current year, which covers the FGD packages at about 3,000 MW, worth around INR 3,500 crore. Water projects, roughly INR 2,500 crore in UP and other locations. Railway maintenance shops — that's metro shops, metro jobs, maintenance sheds — around INR 500 crore. Railway jobs in Nellore, Surat and Kazipet, close to INR 1,000 crore, and there are road projects of about INR 6,000 crore. So the forecast Satish rightly made regarding future growth ought to be quite strong. Now, given the present backlog of INR 14,781 crore plus the L1 position of roughly INR 960 crore, I believe we're quite well positioned to hit a target of close to INR 10,000 crore. Assuming a projected turnover of INR 3,600 crore, the backlog at year end may perhaps stand at INR 15,000 crore.

Sudha Kodandaramaiah

executive
#15

I believe that ought to provide a solid kickoff for revenue growth in the coming year, as well as for the opportunities that will emerge going forward. Maybe the emphasis will land on FGD jobs, infrastructure box jobs, railway work, and then metro projects, since metro projects are seeing a great deal of growth. And after that, maintenance jobs will also start coming up on the FGD side. As for the investment that is further coming into drinking water schemes, almost 50% has already been provided, and then plenty of opportunities are coming. In drinking water too, we are chasing many projects. Railway, multi-modal terminals, and in material handling packages, there can be quite a number of opportunities. In fact, the National Infrastructure Pipeline has been a tremendous booster for investments. We, organizations such as Power Mech and many other similar organizations, have gained a great deal from these investments coming up, and this will keep flowing over the next couple of years as well. That is what I can say. We ought to be able to keep up sustained growth. Perhaps next year, on a conservative basis, we should be targeting around INR 8,000 crore, and that should be the trend going forward too.

Sudha Kodandaramaiah

executive
#16

Appreciate it, everyone — and we can pick that up with the question.

Operator

operator
#17

Thanks a lot. At this point we'll open it up for questions. If you'd like to ask something, you can press star and one on your touchtone phone. Should you want to drop out of the queue, just press star and two. We ask that participants use their handsets when posing a question. Ladies and gentlemen, we'll hold for a moment while the queue builds up. As a reminder to everyone, if you want to ask a question, you may press star and one right now. Our first question comes from Riya at Aequitas Investments. Please go ahead.

Riya Mehta

analyst
#18

Hi there, and thanks for the chance to ask. For my first question, given that civil work now makes up a growing share of the order book, what margin profile should we expect over the next several quarters?

Jami Satish

executive
#19

Right, so we've actually been seeing some better margin performance, OK? So roughly speaking, for this year, we expect that figure to carry on through quarter three and quarter four, all right? There might be a slight incremental gain, OK. That's the pattern we anticipate ahead of us over the near term.

Riya Mehta

analyst
#20

Okay. Okay. And… hello?

Jami Satish

executive
#21

Sure, go ahead.

Riya Mehta

analyst
#22

On the working capital side — since we're going to be executing at a higher level over the next two quarters, how far can we stretch things?

Jami Satish

executive
#23

Could you say that again?

Riya Mehta

analyst
#24

Given that our execution should be higher, what level of working capital are we expecting for H2?

Jami Satish

executive
#25

Right. Look, on receivable days — right now they're sitting at roughly 75 to 80 days, okay? There's room for some improvement there, alright? If you look at it holistically, taking the whole working capital cycle, it's currently running at about 143 to 145 days, okay? We expect that cycle to carry on, and there may be some gains — perhaps down to 135 to 138 days. That's the net current days figure, and that's our expectation. With the order book we have, most projects are already mobilized. Typically, about two months of working capital is needed to mobilize a project. Most of our projects are already mobilized. For this FGD Adani project that we recently secured, we have an advance provision — interest-free at 10%, drawn as needed. We see this project as a self-sustained cash flow model. So going forward, it should come down — net current days perhaps in the range of 130 or 135 days by the end of this year.

Riya Mehta

analyst
#26

Alright. Alright.

Jami Satish

executive
#27

Right, right.

Riya Mehta

analyst
#28

Given that our order book looks solid at the moment, how much of that execution can we actually get to? Are there any capacity limits — say, on headcount or anything along those lines?

Sudha Kodandaramaiah

executive
#29

No, actually, our staffing levels are sufficient. As of right now, we have close to 30,000 workers — that's the total in-house figure. In O&M as well, we have a sizable team, roughly 12,000 people, eleven thousand people. And when it comes to direct labor and indirect labor — direct, HR, and indirect too — we're adequately staffed. In fact, the... Regarding staffing and redeploying manpower, for the incremental job orders we're picking up, we've observed it. I believe Adani will now be a major order, and then there's this BMRCL job that we need to take up. Other O&M jobs are already ongoing ones, and we're well staffed on those too. This way, we'll be substantially able to fill the resources needed, both on the manpower side, then the supervision side, and the equipment side. Many of these jobs, as we've seen — and I'm giving you the status of the work — many are at later stages, 50%, 60%, 70%, 80% completed, and that's how this project gets redeployed. We don't expect any major problem in deploying all these resources, and we will be able to execute them.

Riya Mehta

analyst
#30

All right, so do we have sufficient resources ready?

Sudha Kodandaramaiah

executive
#31

Yeah, yeah.

Jami Satish

executive
#32

So, we're all set for solid figures moving forward. Thank you.

Sudha Kodandaramaiah

executive
#33

Alright.

Operator

operator
#34

Thanks. Our following question comes from Deepak Poddar, who is on the line from Sapphire Capital. Please proceed.

Deepak Poddar

analyst
#35

Hello? Hello.

Jami Satish

executive
#36

Yes, yes, yes, Deepakji, go ahead.

Deepak Poddar

analyst
#37

Yeah. Yeah. Yeah, thanks a lot for giving me the chance, sir, and those are really strong numbers. So my first question is about execution — right now we've been discussing FY 2023, and the order backlog we're aiming for is fifteen thousand crores, correct? And typically, in any given year, we execute 38%-40% of the order book we start with, right? So if I work that out, we'd be looking at roughly INR 5,600 crore-INR 5,700 crore of execution, FY 2024. So is that also something we're considering when it comes to the execution level next year?

Sudha Kodandaramaiah

executive
#38

Right. So what I can tell you is that orders come in a mix—some contracts run short, others run long, and schedules vary from one contract to another, so that 40% norm can apply. What I can say is that from the INR 2,720 crore we have achieved, we are going to reach close to INR 3,600 crore. That's due to growth in certain jobs where we're also including some materials.

Deepak Poddar

analyst
#39

Right.

Sudha Kodandaramaiah

executive
#40

A lot of these jobs we’re going to take on involve a meaningful material component — in particular, the Adani job is in there, and then the BMRCL job will be there as well. Some of the other scheduling jobs are in there too. So what we can say with confidence is that, given the schedules we’ve committed to the customer and the resources we have available, we ought to be able to go past at least INR 5,000 crore next year, with a backlog of INR 15,000 crore.

Deepak Poddar

analyst
#41

Fifteen percent of what, exactly?

Sudha Kodandaramaiah

executive
#42

Fifteen, INR 15,000 crores.

Deepak Poddar

analyst
#43

Uh-huh. Yeah.

Sudha Kodandaramaiah

executive
#44

On the revenue side, it's possible for us to go past INR 5,000 crore in revenue next year.

Deepak Poddar

analyst
#45

Okay, that's fair. I understand. All right, got it. And sir, I mean, if you look at our order book and backlog, we've witnessed a huge increase in that backlog. For instance, our FY 2020 order backlog stood at INR 4,500 crores, correct? And as of today, we're at roughly INR 24,000 crores. Of course, that includes the MDO, which is a 25-year contract. So how should we view that opportunity across the coming three years, if I'm speaking in terms of order book backlog? Do you expect additional MDO contracts of this kind to come into play for us? So some clarity, if you could offer, on how you see—

Sudha Kodandaramaiah

executive
#46

Yeah.

Deepak Poddar

analyst
#47

Over the coming 3 years, looking at the order book — that INR 24,000 crore figure — is there a chance it drops to INR 15,000 crore? So, roughly along those lines.

Sudha Kodandaramaiah

executive
#48

Yeah, that's a really interesting question, I think.

Deepak Poddar

analyst
#49

Yeah.

Sudha Kodandaramaiah

executive
#50

Look, with MDO-type work, there's a great deal of need in this country. Take Coal India, for instance — they're planning to ramp production up to more than 1,500 million tons by 2030, up from the current 7,700 million tons. A lot of their mine site handling plants aren't fully mechanized, and MDOs aren't in place there. As things stand today, they've completed just about 100 million tons — 100 million ton of MDO operations — and Coal India is now in the process of awarding a further 60 million ton. That accounts for only 25%-30% of the total MDO requirement.

Deepak Poddar

analyst
#51

Uh-huh.

Sudha Kodandaramaiah

executive
#52

Also now, in coal mining, privatization is happening. A lot of other players — private players too — have come in, and MDO is going to be a significant operation. What we plan to do with the present MDO is have it take effect from the end of 2024 and the start of 2025. We anticipate that we can target at least another two to three jobs. And that's further reinforced by the fact that we're handling many similar jobs when it comes to EPC and construction contracts at Kurnool, Talcher, and Kudgi, and we're gaining a great deal of expertise in these jobs. And by then, we'll be able to start work on the MDO and the Kotre Basantpur, and the further jobs — you know, we'll be well-placed.

Deepak Poddar

analyst
#53

Right, so we do expect another 2 to 3 MDO-type,

Sudha Kodandaramaiah

executive
#54

My take is that's pretty optimistic, though at minimum one or two will certainly go for it, since that delivers recurring revenue across 20, 30, 35 years. So I'd expect Satish to chip in with a few more points here as well.

Jami Satish

executive
#55

Right. Deepak, look, this year at INR 10,000 crore, that leaves a solid opening order book going into next year. For the cash contracts, the order book target for next year might fall in the range of INR 8,000 crore, since that again leaves a healthy order book for FY 2024. After that, the MDO, KBP, Kotra Basantpur project will begin. So the thinking now is this: for FY 2023 to 2024, we've set a target of INR 8,000 crore, and for 2025, a figure of INR 9,000 crore, okay? By 2025 to 2026, we'll see this MDO becoming more and more materialized, and we'll see ground-level activity begin and revenue booking start. Okay, after that, since this project has taken almost two, three years, we've made efforts to secure a decent-sized project after weighing all the risk factors. So if all goes well, we may consider one project, based on how KBP progresses, but not right away, because the order book is quite full. But if given the chance, and if we get an attractive price, we may add one more project.

Deepak Poddar

analyst
#56

There's another MDO project as well.

Jami Satish

executive
#57

Yeah, yeah.

Deepak Poddar

analyst
#58

All right. But according to what you mentioned, we're anticipating order inflow of roughly INR 8,000 crore for the coming year, FY 2024.

Jami Satish

executive
#59

For fiscal year 2024, our goal is INR 8,000 crore in order bookings.

Deepak Poddar

analyst
#60

Yeah.

Jami Satish

executive
#61

And 25 — possibly somewhere around INR 9,000 crore, all right.

Deepak Poddar

analyst
#62

This year, we're aiming for order inflow, right? That's similar to what we're doing. Ideally, yes.

Jami Satish

executive
#63

This year it's a bit higher on account of Adani, though perhaps in the next year, INR 10,000 crore might not be required, okay?

Deepak Poddar

analyst
#64

Yeah, that's right.

Jami Satish

executive
#65

So even assuming a conversion rate of 36%-38%, which is on the slightly higher side, by the time O&M comes into play, okay, that pie could reach, could touch, INR 1,400 crore-INR 1,500 crore, okay? Looking at the next three years, okay, the blended figure — we have very clear-cut visibility, and the backlog order book stood at INR 8,000 crore, and after that, INR 9,000 crore.

Deepak Poddar

analyst
#66

Right.

Jami Satish

executive
#67

That’s going to leave us with a really solid order book to execute against. So I think,

Deepak Poddar

analyst
#68

Right.

Jami Satish

executive
#69

For FY 2026, we have to make a decision about how we consolidate, plus which areas to grow in and which ones to leave alone. Yeah.

Sudha Kodandaramaiah

executive
#70

Satish, allow me to add a couple of points here. Look, this NIP that's underway — INR 11,100,000 crore of investments — we're already seeing the company benefit from it, and that will continue for at least another three to four years.

Deepak Poddar

analyst
#71

Right.

Sudha Kodandaramaiah

executive
#72

A significant amount of private-sector investment is on the way, particularly in steel, close to $158 billion, and that will bring associated jobs — good jobs. We'll also see residual investment in power to close the gaps for base load operation — another 10,000 MW that CEA is planning, on top of the 24,000 MW of implementation already underway. On the infrastructure side and rail, railway investments come to roughly INR 1,000,000 lakh-INR 1,300,000 lakh in total, and each year INR 1.5 lakh-INR 2 lakh, which will also keep going over the coming seven, eight years.

Deepak Poddar

analyst
#73

Mm-hmm.

Sudha Kodandaramaiah

executive
#74

Actually, FGD — what's happened is the commissioning of that FGD investment has now been pushed back to 2026. So that work will ramp up further as well, and the new projects that include FGD will bring those jobs too. Now, when it comes to drinking water, infrastructure, roads, railways, and the other segments, the diversification we carried out over the last couple of years — we'll keep that going, with improved margins, thanks to the expertise we've built up. On top of that, the international market: for a range of reasons, investment there had slowed, especially in the Middle East. That spending is set to recover, and there will be substantial investment in that region. In West Africa, we've identified a solid opportunity — we've begun working in Nigeria, and then there's Sierra Leone, and Ghana, many locations, and Mozambique. West Africa is set to become an attractive investment destination, given the considerable growth requirements, in fact. So the export market, the domestic O&M market, the domestic infrastructure business, and then the residual FGD work that remains — a balance order book of 80,000 MW. And in drinking water, new schemes will also emerge in surface drinking water as well.

Sudha Kodandaramaiah

executive
#75

We're going to take part in that as well. So at minimum, for 3 to 4 years, opportunities won't be lacking. And, like I mentioned, private investment will arrive on a large scale afterward. It has to trail the government's investment across steel, infrastructure, minerals, metals, and petrochemicals — a range of areas. In all those areas we've built our presence, and that will hand us considerable room to maneuver.

Jami Satish

executive
#76

With this FGD extension, alright, that once again, okay, creates chances over the coming 2 years, alright. We're able to go after a few, a few additional projects, and beyond that, the, okay, the power thermal side, we figured, like, there might be a slowdown, yet the way it appears, there's at minimum solid visibility across the next 5 years, so that too will bring in some solid opportunity for us.

Deepak Poddar

analyst
#77

Right, right, right. That's pretty interesting. But yes, and my last quick question — I believe we've said before that because of our legacy orders, it's tough for us to push our EBITDA margin higher. So if we assume that by the fourth quarter all those legacy orders will have been executed, have you given any thought to what kind of margin improvement one might see in FY 2024, at a higher execution level, once we're also done with that legacy order book?

Jami Satish

executive
#78

Yeah, look, there's a strong likelihood that the margin profile ought to get better, right, and we're actually seeing that even in quarter two, okay? Improvement should come gradually, okay. That said, though, the FGD — which is a big contract, okay — we're expecting 10%-11% on that.

Deepak Poddar

analyst
#79

That's right.

Jami Satish

executive
#80

If we leave FGD out of the picture, there's a bit of improvement showing up in the margin profile. One factor is the jump — the quantum jump. The second thing is that for certain projects, we used to give away the royalty on the PQs and so on, but now we're quoting on our own. That should also contribute somewhat toward strengthening the margin profile. All right.

Deepak Poddar

analyst
#81

Right.

Jami Satish

executive
#82

Perhaps during 2024, 2025, and the first half of 2024, we'll observe how the FGD conversion is progressing. So that will—the execution, we'll need to see the degree to which we're converting and all, okay?

Deepak Poddar

analyst
#83

Right.

Jami Satish

executive
#84

That's what's going to determine the blended margin.

Deepak Poddar

analyst
#85

That's right.

Jami Satish

executive
#86

We're confident there will be some enhancement to the margin profile, though how much and all of that remains to be seen — perhaps in six to eight months, we'll know how the FGD is converting.

Deepak Poddar

analyst
#87

Right, and that's going to take place during the first half of FY 2024, correct?

Jami Satish

executive
#88

No, we're anticipating that will occur in quarter four, all right? And if that—

Deepak Poddar

analyst
#89

For the fourth quarter of fiscal year 2024.

Jami Satish

executive
#90

No, no. As for the FGD, the billing bill — the billing should come in quarter four of this year.

Deepak Poddar

analyst
#91

Yeah.

Jami Satish

executive
#92

If there's any slippage at all — look, we've set a target of INR 3,600 crore for this year, along with some conversion coming from the FGD. Should that not materialize, it will roll over into quarter one of next year.

Deepak Poddar

analyst
#93

Right. That's right, that's right.

Jami Satish

executive
#94

So over the coming 2 quarters — possibly Q4, possibly Q1 of next year — we should get a clearer picture regarding the conversion from FGD.

Deepak Poddar

analyst
#95

That INR 400 crore figure is the one we're referring to.

Jami Satish

executive
#96

Right, right.

Deepak Poddar

analyst
#97

All right, that's fair. Yeah, yeah, got it. Yeah, that's really helpful, sir, and I appreciate you taking the time, and all the best to you. Yeah. Thanks.

Jami Satish

executive
#98

Thanks, Vipin. I appreciate it.

Sudha Kodandaramaiah

executive
#99

Thank you.

Operator

operator
#100

Thanks. Just a quick reminder for everyone: if you'd like to ask a question, press star and one at this time. Our next question comes from Dixit Doshi at Whitestone Financial Advisors. Please go ahead.

Dixit Doshi

analyst
#101

Yeah, thanks for the chance to ask. Actually, most of what I had has already been covered. I just have one question: when will the MDO project begin recognizing revenue?

Jami Satish

executive
#102

Sir, for quarter four of 2024 — that's FY 2024, right, quarter four — we expect to book somewhere between INR 40 crores and INR 60 crores in revenue, okay, at a rate of INR 886 per ton, but the rate has now risen significantly on account of the escalation, okay. So that figure could climb to INR 70 crores or INR 80 crores.

Dixit Doshi

analyst
#103

On a quarterly basis?

Jami Satish

executive
#104

Right, right. And from 2024 to 2025, that figure could rise to INR 250 crores, and for 2026, we're looking at roughly INR 400 crores to INR 450 crores.

Dixit Doshi

analyst
#105

Alright.

Jami Satish

executive
#106

Yeah.

Dixit Doshi

analyst
#107

Will the margins in this segment come in higher, correct?

Jami Satish

executive
#108

Yeah, sir, there is a bit of investment involved, and there is some CapEx as well. So we quoted a price that worked out to almost 20%+ at the EBITDA level, since there is also some depreciation element in there. But with the revised price, the margin profile is going to improve again. The price we quoted was INR 886, and today it stands at almost INR 1,300 to INR 1,400+. So there is a high probability that the margin profile could improve further, sir. We will see how it turns up.

Dixit Doshi

analyst
#109

What's the amount we plan to put into this CapEx?

Jami Satish

executive
#110

That's 360 crores across 2.5 years, and it'll come as a mix of term loan and equity at the SPV level.

Dixit Doshi

analyst
#111

Alright.

Jami Satish

executive
#112

Yeah.

Dixit Doshi

analyst
#113

All right, I appreciate it — that's all I had to cover. Thank you.

Operator

operator
#114

Thanks. We’ll take the next question from Abhishek Poddar at HDFC Mutual Fund. Your line is open—please go ahead.

Abhishek Poddar

analyst
#115

Thanks for taking my question, and congratulations on a good quarter. About the order outlook of INR 8,000 crore for 2024 and 2025, and INR 9,000 crore for 2025 — if you look at this year, we had a very large order of INR 7,000 crore coming from Adani.

Jami Satish

executive
#116

Yeah.

Abhishek Poddar

analyst
#117

So, if we remove that from the INR 10,000 crore figure, what remains of the order comes to roughly INR 3,000 crore. So I'm just trying to get my head around that — you know, the gap between INR 8,000 crore and INR 3,000 crore, that extra INR 5,000 crore amount for next year.

Jami Satish

executive
#118

Yeah.

Abhishek Poddar

analyst
#119

Are you seeing any sizable orders out there, sir, or is it more broad-based?

Sudha Kodandaramaiah

executive
#120

Right, no, no — I'd say Adani was more of an exception. What I can tell you, though, is this: if you look at the opportunities, what we pursue annually, we pursue somewhere in the range of INR 25,000 to INR 40,000 crore. That's the kind of BD development that various groups carry out across all the segments. And as for the eight thousand crores, the confidence there comes from the sustained balance ordering that's to be done in the FGD — nearly 81,000 MW is out there. We'll try to focus on a couple of those megawatts, maybe 3,000 MW to 4,000 MW. Then there are water projects as well — that means drinking water projects and surface drinking water projects — plus road and road and metro projects. Take metro, for example: we entered in a big way. That's a major breakthrough on our part. It's happening everywhere; metro expansion is going up — I think the number of stations and the mileage involved will double — and there's also the need for maintenance shops and all of that. We're already bidding there for a couple of projects in Bangalore and other places too. So there's a mix of what I'd call traditional business in the new units, whatever is going to come up, maybe on the thermal side, and then O&M continues to be.

Sudha Kodandaramaiah

executive
#121

Our aim is to strengthen our presence in operations and maintenance within the non-power segment as well, and in the international business too. Then, on the infrastructure front, we have a mix of road projects, railway projects, drinking water projects, and metro projects. The basket has now grown, and on the electrical side we are watching cautiously where we can participate, but we are not — we have not left anything aside, and recently we took a job of perhaps INR 80 crore as well. So there is room, and we have set a benchmark of INR 10,000 crore. We are going to establish it. And with additional opportunities, maybe, you know, we will be looking at opportunities of nearly INR 40,000 crore to INR 50,000 crore in the coming year. To that extent we will concentrate on it, and a 20%-25% hit rate should not be a challenge across all these opportunities.

Jami Satish

executive
#122

Yeah, just to sum up, sir,

Abhishek Poddar

analyst
#123

Yeah.

Jami Satish

executive
#124

When you look at operation and maintenance—O&M—across both domestic and international, together with the orders that are set to be renewed and all of that, the total comes to roughly INR 1,000 crore to INR 1,100 crore. In addition, there are some follow-up FGD orders we're still negotiating, and those could slip into quarter one of next year, since multiple inquiries keep coming in and talks are ongoing. That piece by itself is expected to involve close to two or three projects, perhaps INR 1,500 crore to INR 1,700 crore. Beyond that, over the last two years we've been somewhat slow in the international mechanical space owing to COVID. The team is now fairly active. Mr. Rohit and Srinivas—look, they are traveling extensively to review where we can revise the opportunities. There are many opportunities out there. Within the mechanical space internationally alone, we have already identified close to INR 500 crores to INR 600 crores of opportunities. And on top of that, metro and railway—okay, we are already talking with multiple players, right? We're hoping that, the way we did this year for Bangalore Metro, we'll add one more project next year, and that should come to around INR 600 crores, okay. Beyond that, water and STP—we had a solid amount of additions there.

Jami Satish

executive
#125

So perhaps in the coming year we could bring in another INR 750 crores to INR 800 crores, all right, possibly a couple of projects. And for our usual mechanical power side, that figure should land somewhere near INR 800 crores to INR 900 crores. So the opportunities out there are pretty big. All right, INR 8,000 crores looks like something we can reach 100%.

Abhishek Poddar

analyst
#126

All right, sir. So, sir, when you look ahead to next year, you're guiding toward INR 5,000 crore of revenue, or more than that. So if we, you know, look a bit further out to 2025, and considering the order backlog will grow again in 2024 as well, might we see INR 6,500 crore to INR 7,000 crore in revenue in 2025, and are we prepared for that, sir?

Jami Satish

executive
#127

That is very possible, sir. The explanation is that for FGD itself, we need to add roughly INR 2,000 crore plus, okay? But at this point we are well positioned, okay. The amount is big, yet it is distributed across five projects. So owing to the supply component in every case, okay, it appears to be a bigger amount, okay. For that single contract alone, we must carry out the supply, the direction, and the civil work combined, and that will add INR 2,000 crore. Yes, that is very possible, sir. It's, it's we, we have to do that.

Abhishek Poddar

analyst
#128

Got it. Sir, regarding margins, if you could help us a little there: you said O&M is going to double from here. In what way does that help the margin — and that 11% EBITDA margin you reported in 1H, how should we view it in 2024 and 2025?

Jami Satish

executive
#129

Yes. Sir, I'll do that — let's break down how the margin works for Power Mech, all right? As we all know, O&M tends to carry a higher margin than the mechanical, civil, and electrical pile, correct? In erection, our experience was that we used to operate at 13%, 13.5%, but over the last two to three years that has dropped to 11%, 11.5%, since the size has decreased, all right. In civil, naturally, we were losing 2%–3% in order to buy the PQs. Across the past three to four years, we spent roughly up to 3%, and that had a direct impact on our EBITDA margin. Now, however, we are able to bid directly, all right, so Power Mech is well placed to bid for projects, so that can remain the same, all right? That said, railway, water, all right, and a few of the civil projects — the intensity of competition there is somewhat high, all right? Operating at 11% or 11.5% is, I would say, somewhat of a challenge. Then, beyond that, on FGD, we expect something in the 10%–11% range. That is achievable for Power Mech, as it has been for certain other players — perhaps marginally lower, since we have our own in-house equipment, manpower, resources, and so on, all right.

Jami Satish

executive
#130

Now, as business and the top line improve, there's a strong likelihood that the margin profile should gradually move toward 11.5% to maybe 12%, 12.5%. But what we're trying to say, sir, is that FGD will now play a significant role in our revenue profile, okay? If it works at 10% or 10.5% or 11%, then the blended will again look to be 12% or, okay, 11.8%-12%. So what we are trying to say is, maybe over the next six months, this trend of existing margins may edge up slightly, okay? And once the FGD starts, we need to see how much of margin we are able to convert, okay? So maybe in the next six to eight months, we'll have more clarity on what extent margin profile can be ramped up, sir. But we are sure that the existing profile should improve gradually.

Abhishek Poddar

analyst
#131

Regarding the FGD issue you're raising, sir — commodity prices have eased somewhat over the last two to three quarters since those orders were booked. So at least on the FGD side, shouldn't there be a tailwind coming purely from commodities?

Sudha Kodandaramaiah

executive
#132

Right. So on the pricing front, we've also secured certain protections from Adani Group for this job. First, the cost per megawatt comes to almost INR 23 lakhs. As a matter of fact, looking at pre-COVID levels and all of that, it used to be INR 40 lakhs to INR 50 lakhs per MW. So there's a quantum jump in the per-megawatt cost. I think that's already been cushioned where the material is concerned. And the second point is that most of the contracts on the supply side are done on a back-to-back basis. Whatever we bill is based on the billing, the order specs, and the terms negotiated back-to-back with the suppliers — that's on the supply chain. So, in that way, we are, we are definitely covering up many of the risks there, through the suppliers as well. And the other thing is, as Satish rightly said, we have in-house capability to execute 25% of the work — 25%, 25% of the work on site execution. That should help us too. That's how we're structuring the SPV, and we don't anticipate any major implications on cost.

Sudha Kodandaramaiah

executive
#133

Steel prices have already come down below the peak levels we had substantially. And maybe, you know, with the tie-ups we've made with the vendors, that protection should help us in executing this.

Abhishek Poddar

analyst
#134

Got it, sir. So just one more question, and that’ll be the last one. About the Andhra project, INR 60 crore was stuck there. Is there any update on its status, and when do you expect that money to be recovered?

Jami Satish

executive
#135

The positive side is that everything has now been finalized. They've included it in the budget, right? The difficulty lies in their cash flow limitation, okay. For the past few months, we've been wrestling with how to get it approved by the cabinet and have them put it into the budget. That portion is done. Now they have to release the payments, and we don't anticipate this happening as a single lump sum. Perhaps each month they'll show some amount, okay? If everything goes well, we're expecting that by December, we should see at least INR 8 crores to INR 10 crores, and realizing the full amount would take at least six months, sir.

Abhishek Poddar

analyst
#136

Sir, that should also help bring down those working capital days you mentioned—down to 130 to 135 days. Is that being factored in as well?

Jami Satish

executive
#137

No, sir, I haven’t taken that portion, because this is a single line item where, despite all our efforts, the timelines are something we don’t have much control over, okay?

Abhishek Poddar

analyst
#138

Alright.

Jami Satish

executive
#139

Should that come through, it would contribute somewhat toward further improvement—though what I'm referring to is leaving out the Andhra portion.

Abhishek Poddar

analyst
#140

Got it, sir. All right, best of luck, sir. Thanks. Thanks.

Jami Satish

executive
#141

Thank you, sir. Thank you.

Operator

operator
#142

Thanks. Just a quick reminder for everyone: if you’d like to ask a question, you can press star and one now. Our next question comes from Sheena George at Geojit Financial Services. Please go ahead.

Sheena George

analyst
#143

Hello?

Operator

operator
#144

Sir, please go ahead with your question.

Sheena George

analyst
#145

Can everyone hear me?

Operator

operator
#146

Yes, sir. Yeah.

Sheena George

analyst
#147

Good evening, sir. The first question is this: could you tell us the exact — how much would that exact amount be, roughly?

Operator

operator
#148

Mr. George?

Sheena George

analyst
#149

Hello there.

Operator

operator
#150

We lost your audio partway through.

Sudha Kodandaramaiah

executive
#151

Audible. No, yeah, yeah.

Sheena George

analyst
#152

Hello?

Sudha Kodandaramaiah

executive
#153

Could you say that again, please? My apologies.

Sheena George

analyst
#154

Yeah, so my question is about the FGD order we got from Adani — how should we think about the revenue forecast for the quarters ahead?

Sudha Kodandaramaiah

executive
#155

So the whole contract is set up to run somewhere between 18 and 30 months, counting from when we begin the kickoff dates separately for each project. And at this point, we've gotten underway with 1 or 2 projects.

Sheena George

analyst
#156

Mm-hmm.

Sudha Kodandaramaiah

executive
#157

After that, additional projects need to come along, in line with the progress we've already mapped out and are about to map out.

Sheena George

analyst
#158

Mm-hmm.

Sudha Kodandaramaiah

executive
#159

So at this point we understand that revenue in the first quarter or two will actually be low, since the engineering work still has to be completed and orders still need to be placed. That is what Satish was referring to — maybe revenue will begin coming in around the close of this quarter, at the end of this year. However, in the next year we ought to be able to achieve a substantial conversion of that INR 600 crores. And over the following two years, that is probably how we will manage to finish this major work.

Sheena George

analyst
#160

So for Q4, that's INR 400 crore, if I've got that right?

Sudha Kodandaramaiah

executive
#161

No, what I can tell you is that, like, the two plants we've now taken onboard, other plants we have to take up because we haven't drawn the advance. And then, the engineering kickoff hasn't started, zero dates haven't started, and that's expected to begin shortly. But once we start it, you know, these two projects will be the focus. Therefore, this year, at the end of the quarter, you know, it can... We don't want to give any firm figures on that, because there are many various aspects we have to project in engineering and ordering. And then, the documents have to be prepared for the site execution work as well. Therefore, that's how in the normal first 4 to 6 months, you know, revenue can be low, and some revenue we expect in the last quarter.

Sheena George

analyst
#162

All right, so roughly, what would that amount come to? Do you have any idea about that?

Sudha Kodandaramaiah

executive
#163

Sure, the figure could land somewhere in the range of INR 200 crores to INR 300 crores. There’s a chance it edges up a bit, though that really hinges on timing, sir, since we’re anticipating that conversion will take place in quarter four. If a slippage does occur, however, it would push into quarter one of next year.

Sheena George

analyst
#164

All right, I've got it.

Sudha Kodandaramaiah

executive
#165

Right.

Sheena George

analyst
#166

Got it. What about that Bangalore Metro order — the one you secured recently?

Sudha Kodandaramaiah

executive
#167

Regarding the Bangalore Metro order, we've already secured it. Now an agreement needs to be signed by 25th November. For the INR 427 crore contract, the initial kickoff meeting has already happened. Once that kickoff meeting begins—though we haven't factored revenue generation from it just yet—some conversion ought to take place in the fourth quarter.

Jami Satish

executive
#168

Right, the contract is INR 490 crore in size, and our portion comes to INR 422 crore. Also, mobilization has already begun, sir. Billing and revenue booking will get underway from December, January onward, sir. During January, February, March, we could see somewhere between INR 35 crore and INR 45 crore.

Sheena George

analyst
#169

All right. All right, that works. Thanks.

Sudha Kodandaramaiah

executive
#170

Yeah. Yeah.

Sheena George

analyst
#171

That’s all, sir. Thank you.

Operator

operator
#172

Thank you. Ladies and gentlemen, since no additional questions remain, I’ll now turn the conference back to management for their closing remarks.

Sudha Kodandaramaiah

executive
#173

Yes, Rama garu? Yes, and I believe we should thank everyone. These are quite intriguing times, with plenty of expectations surrounding us, and there is much work ahead when it comes to the challenge of execution. Still, opportunities abound, and our company is properly prepared for the execution model. We possess the necessary means, and we have shown on numerous occasions that our peak enhanced estimates need to be delivered — something we accomplished in earlier years as well. Given the resources at hand and the opportunities before us, I am confident that the coming 2 to 3 years will prove rather bullish for our organization, both in growth when it comes to order booking and in the conversion of those orders, along with an improvement in margin. I hope these things will move forward. Thank you very much.

Jami Satish

executive
#174

Yes. Thanks to everyone.

Operator

operator
#175

Thanks. So, everyone, that wraps up this call on behalf of Nirmal Bang Equities. We appreciate all of you being with us, and at this point you're free to hang up your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Power Mech Projects Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Power Mech Projects Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research