Power Mech Projects Limited (POWERMECH) Earnings Call Transcript & Summary

February 8, 2023

National Stock Exchange of India IN Industrials Construction and Engineering earnings 62 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to Power Mech Projects' Q3 FY 2023 Earnings Conference Call, hosted by Nirmal Bang Institutional Equities. <<operator_script>> I'll now turn the conference over to Mr. Prasheel Gandhi of Nirmal Bang Institutional Equities. Thank you, and over to you, Sir.

Prasheel Gandhi

analyst
#2

Thank you, Tanvi, and good afternoon to everyone. Nirmal Bang Institutional Equities is glad to have you all join the 3Q FY 2023 earnings conference call for Power Mech Projects. As we begin, I want to express our appreciation to the management team for the chance to host this call. Joining us today from the management side are Mr. S.K. Ramaiah, Director, Business Development, and Mr. Jami Satish, CFO. I will now turn the call over to management for opening remarks, and after that we can take questions from the participants. Thank you, and over to you, sir.

J Satish

executive
#3

Okay, thank you. Good afternoon, everyone. Satish speaking, and joining me is Mr. S.K. Ramaiah, our Director of Business Development. Welcome to the Q3 and nine-month FY '22 and '23 earnings call. Results for Q3 and the nine months of this fiscal year stayed on track with the full-year target. Reported total income for Q3 came in at roughly INR912 crores. That marks an all-time high for Power Mech's execution in any financial year's third quarter. EBITDA stood at about INR106 crores, with PAT of INR51 crores. In Q3 of the prior financial year, reported total income was INR650 crores, EBITDA was INR72 crores, and PAT was INR33 crores. Year on year, total income grew by nearly 40%. Alongside that revenue growth, EBITDA rose about 47%, and PAT climbed almost 54%. For Q3, the revenue mix breaks down as follows: erection contributed roughly INR144 crores, civil — including railway and water projects — about INR492 crores, operation and maintenance across domestic and international combined INR260 crores, electrical around INR12 crores, and other income close to INR3 crores.

J Satish

executive
#4

In Q3 of the prior fiscal year, the figures broke down as follows: erection business added INR127 crores, civil business roughly INR268 crores, operational maintenance INR226 crores, electrical business INR25 crores, and other income came to about INR4 crores. In Q3 of FY ’23, the domestic side accounted for nearly 89%, with the rest generated overseas. In the same way, the power sector made up 55% and the non-power sector about 45%. That's the mix for the FY — Q3 FY ’23. Growth showed up in every segment apart from Electrical business. Within Electrical business, the company takes a highly selective approach and has no intention of expanding its footprint there. The O&M business expanded by nearly 15% and delivered 29% of total revenue this quarter. Likewise, total reported income for the nine months of FY 2023 came to INR2,435 crores. Across those nine months, EBITDA was approximately INR281 crores and PAT INR134 crores. In the comparable nine months of the previous fiscal year, reported total income stood at INR1,822 crores, EBITDA at INR206 crores, and PAT at INR91 crores. Year on year, over the nine months, revenue grew by almost 34%.

J Satish

executive
#5

Revenue has grown, and EBITDA growth is nearly 36% and 47%. For the nine-month period, revenue breaks down as follows. The erection business contributed INR458 crores; civil business, which includes railway and water projects, came in at around INR1,235 crores; operations and maintenance at INR682 crores; the electrical business at INR52 crores; and other income at roughly INR8 crores. In the comparable nine months of the prior financial year, erection brought in INR370 crores, civil business was around INR775 crores, operational maintenance INR587 crores, electrical business roughly INR76 crores, and other income about INR15 crores. On the international versus domestic mix, domestic accounted for 86% in the nine months of FY 2023, with overseas business making up the remaining roughly 14%. Between power and non-power business, the split stood at 59% and 41% during these nine months of the current financial year. Since its inception, the company has always taken a conservative approach, and so when building its business plan it takes all suitable steps to keep that plan under control. Alongside the plan for sustained growth, the company will also keep focusing on cash flow and margin improvement. We are seeing the margin profile improve gradually.

J Satish

executive
#6

By FY 2025, we expect to get back to the margin profile we reported earlier, and after that we'd see some gradual improvement. That's largely because of the various initiatives we've undertaken over the past few years. Also, we're very pleased that our execution cycle keeps getting better each quarter-on-quarter. The company has built a strong position when it comes to resources, equipment, and strong manpower-based leadership skill at the senior level as well as the middle and junior levels, along with engineering skill ATC, to carry out projects in the INR400 crores to INR450 crores per month range, which is encouraging. If you look a few years back, our education range was about INR400 crores to INR450 crores plus in a quarter. Now that same level of education will be delivered in a month. That was the transformation the company has undergone for sustained growth. Every existing project is on track and progressing according to schedule. The execution plan for this year and for the next financial year stays on track, and we don't see or anticipate any changes to our business plan. Likewise, looking at the opportunity side today, the order book target for the current and next financial year appears comfortable.

J Satish

executive
#7

Every month, the business development team's review is carried out based on changes, to confirm that the company's overall target remains intact. The company also anticipates a healthy volume of order booking and execution cycle in the international market. The team has been strengthened in the international market as well, and in particular, we expect a good amount of addition in operational maintenance for the Nigeria market. In addition, the company has put in place a strong risk management policy and team to review the progress of each project and identify associated risks, which is helping us proactively mitigate at an early stage any associated risk, if any. The initiative the company took a few years back is now helping toward sustainable growth across verticals. Moving to the next line item. Depreciation as a percentage stayed on the lower side. As we have said — and even stated on the last call — because of controlled capex, this line item has been kept more or less flat. Cumulative finance cost as an absolute number remains controlled. There has been some increase in non-fund utilization owing to the rise in the order book and improvement in the execution cycle. Now, as a percentage, we expect it to come down further. The overall working capital cycle is improving for the period because of the change in the customer as well as the business mix.

J Satish

executive
#8

Net current debt, leaving out cash and cash equivalents, is running at about 145 to 146 days for the period. And as I said before, we expect that to improve further. As all of you know, this figure used to be 153 days as of 31st March, 2022, and 205 days as of 31st March, 2021. So the working capital cycle has improved meaningfully. In addition, operating cash flow has been positive — roughly INR45 crores plus during the period. And even more importantly, we're seeing average monthly collections get better every month; they used to be INR250 crores to INR300 crores, and now they've moved to almost INR300 crores to INR350 crores plus. We expect that to rise again to INR400 crores to INR450 crores per month as the business grows. Turning to the debt line item, gross debt stands at about INR535 crores, and net debt is almost INR336 crores, whereas in FY ’22 it was INR527 crores, with net debt of INR320 crores. So despite growth in the business execution cycle and all of that, we have kept this number flat.

J Satish

executive
#9

We're also making efforts to reduce that. So this reflects the gain in working capital as well as cash flow. Turning to the order book: the backlog at 31st December 2022 is approximately INR24,200 crores. And for this year we've set a plan of nearly INR10,000 crores. We're endeavoring to move toward that line item. To date we've achieved INR8,500 crores. Beyond that, we have projects at L1 worth about INR970 crores. So we're confident about reaching the nearer figure — the target we've set for this year. At this point I'd like to invite Mr. S.K. Ramaiah to share a few more developments before we move into the question-and-answer session. Thank you.

S.K. Ramaiah

executive
#10

Ramaiah here. Good afternoon, everyone. Satish, thanks for walking us through the various figures. We remain bullish, I'd say, on how we're approaching the new opportunities, along with the development work and marketing across our diverse customer base, plus the investments happening throughout all sectors of the economy. Essentially, the order backlog has grown substantially versus March 2022, when it stood at INR8,854 crores. As Satish mentioned, it has now touched almost INR50,000 crores. That works out to almost 90% — over 90% — growth in the backlog, driven by considerable opportunities in the FGD business across various infrastructure projects, as well as other key opportunities. For quarter three, total order booking came in at INR1,531 crores, versus INR1,628 crores in the prior quarter. And naturally, the second quarter saw bulk orders, particularly on FGD. Our expectation is that, in the balance of things, with over INR8,500 crores there, somewhere between INR9,500 crores and INR10,000 crores ought to be a reasonable possibility by year-end. That should help us build a backlog of nearly INR10,000 crores by the end of the year, and as of today we already stand near that figure.

S.K. Ramaiah

executive
#11

As I mentioned earlier, on the mechanical side, the backlog increased from INR1,650 crores to INR8,260 crores. Civil went from INR5,842 crores to INR5,663 crores. That covers March ’22 through December ’22. O&M moved from INR1,240 crores to INR850 crores, and electrical went from INR118 crores to INR130 crores. Then on the domestic side, there’s significant growth thanks to more opportunities. And we are — clearly, our focus is on the domestic market given all the market that’s available. Also, the power sector keeps boosting the backlog through the FGD opportunities and a handful of other installation opportunities that are emerging. That amounts to INR9,638 crores versus INR5,268 crores for non-power. Aside from the MDO, this is backlog. Now, turning to the key orders backlog, beyond what we had in the first two quarters: BMRC, Challaghatta, Bangalore workshop depot at roughly INR427 crores. Then wagon repair for the railways at INR250 crores, along with other FGD jobs. And the L1 status stands at more than INR70 crores. So with these opportunities, clearly what we’re aiming at is somewhere around INR9,500 crores to INR10,000 crores, which would be achievable.

S.K. Ramaiah

executive
#12

Moving on to the following year — 2013, 2014 — we're already charting a number of those opportunities. As we've observed, the infrastructure and capital investment in the present budget stands at INR10 lakh crores, with the bulk of that money flowing into railways at roughly INR2.4 crores, roads at INR2.7 crores, and then the energy sector along with other miscellaneous and various other areas as well. So we're aligned with these opportunities generated by government investments, especially in drinking water schemes, the energy sector, oil and gas, mining and minerals, aside from roads. As a result, we'll keep pursuing these opportunities aggressively, and our estimate is that opportunity-wise we can target close to INR30,000 crores to INR35,000 crores. On the international side too — given how bullish our domestic market has been, we weren't concentrating much there over the last one or two years. But the Middle East will be opening up in the Middle East market, plus 300 gigawatts of opportunities, and then there's West Africa; Nigeria, where we're already at work. We're also taking on an O&M job for the job that has just now been completed. And then other countries in the Western Africa.

S.K. Ramaiah

executive
#13

On the domestic side, clearly, there will be ongoing scope potential for the FGD, roughly 80,000 megawatts. Also, several of the new plants are expected to enter Neyveli Lignite operations in Orissa — around 2,400 megawatts. NTPC will additionally add capacity at Singrauli, Lara, and other projects too. So additional opportunities are going to arise, and these are anticipated in the thermal sector as well. Then infrastructure — especially mining, minerals, and coal mining, plus material handling and railways. Railways will represent a substantial opportunity. As a matter of fact, we are already handling around six or seven projects. And there are plenty of opportunities in maintenance of repair shops, and then these Metro projects — this one we executed in Bangalore for the Challaghatta project; comparable projects we can take on for the new Metro projects, since wherever metro projects are coming up, maintenance shops are needed, and that is where we are focusing for new opportunities. So all of this, taken together, targeting opportunities of INR30,000 crores to INR40,000 crores is not a challenge. And with a hit rate of 20% to 30% — 25% to 30% — I think our next year targets of about INR7,500 crores to INR8,500 crores should become a reality.

S.K. Ramaiah

executive
#14

I think this growth trajectory ought to keep going over the next 2 to 3 years, in addition to the fresh opportunities that are going to emerge. And one more thing I can mention is that a substantial amount of investment is set to arrive in the private sector, especially in minerals and metals, steel, and so on. On the total investment side, ArcelorMittal will undertake a major expansion, then JSPL is arriving with expansion. JSW is arriving with expansion. Beyond all that, in minerals and coal mining, plenty of expansions are anticipated. And these opportunities will increase for EPC jobs as well as erection testing, commissioning jobs, and many other civil works, etc. For that too, we have — if we factor it in, these opportunities will rise even further. That is what I wanted to say, and now we can wait for your questions. Thanks.

Operator

operator
#15

Thanks a lot. <<operator_script>> Our first question comes from Mohit Kumar, who is on the line from DAM Capital. Go ahead, please.

Mohit Kumar

analyst
#16

Good afternoon, sir, and congratulations on a very good set of numbers. My first question concerns the revenue guidance for FY 2023 — I believe you've provided guidance of INR36 billion; are you keeping that figure? And on this base, how do you view FY 2024?

J Satish

executive
#17

Look, FY 2023 — we're on track. Usually, if you look at nine months, the first half versus the second half — and the second half is considerably higher than the first half, right — so the targets and the execution cycle are more or less under control. So we're confident that number will keep going. For 2024 as well — we've maintained — water is going to play a big part, and naturally, O&M will stay in the range of INR150 crores to INR200 crores. As for the water business — the order backlog we've picked up is roughly INR2,800 crores to INR3,000 crores. The math works out per village at about INR1 crore. Well, after the detailed project report, the DPR, that value rises by nearly 20% to 25%. So right now, on the order book, we've booked the original contract value. Once — a few villages get split out, close to 20%, 25% is still left to be revised, right? So perhaps by 31st of FY 2023, in quarter four, we'll split out the full number. That should give us a very large backlog, including for execution. Water by itself now, on average, is running at nearly — after December, in January, it's roughly INR120 crores to INR150 crores.

J Satish

executive
#18

We expect this cycle to get better, reaching INR150 crores to INR160 crores. So next year we can perhaps look at INR1,400 crores, INR1,500 crores in terms of our execution cycle. And the single order backlog right now, okay, at an average of 42% to 43%, is fairly comfortable to carry into next year.

Mohit Kumar

analyst
#19

Sir, you're referring to a figure of 43 billion — is that the number — is that number —?

J Satish

executive
#20

No, conversion is 40% plus — actually above 42% when it comes to converting the opening order book, okay? That's fairly comfortable. Beyond that, the temporary shutdowns plus any fresh orders carry over into the following year, and those will contribute to the total as well. So, provided everything goes smoothly, the discussion suggests that in FY 2024, we ought to exceed roughly INR5,500 crores plus.

Mohit Kumar

analyst
#21

Got it. And sir, have you begun carrying out the Adani FGD project? Is it already contributing, or do you think it will need some time to take off?

S.K. Ramaiah

executive
#22

So I believe we've gone through a detailed review of every one of these Adani projects — 15 plots ranging from 6,000 to 8,460 megawatts. And sensibly, the — first thing is that the ordering position stands at roughly 1,100 crores that has already been ordered. By the close of March, another INR100 crores should come through. Then in the following year, by the second quarter, and perhaps early in the third quarter, the bulk of the orders ought to be finished, with the exception of the lost segment, electrical T&D. Naturally, that should provide a solid track record when it comes to execution here, since there are commitments attached to this. Every one of these projects is a committed project. And with the local regulator available to sanction and subsequently approve this project for the PP and other matters. So we remain on track across all of these projects as done to-date.

Mohit Kumar

analyst
#23

Finally, sir, regarding Talabira, Singrauli, and Lara, what sorts of opportunities are we able to serve? And are you seeing tenders from these — the companies for which we will qualify?

S.K. Ramaiah

executive
#24

Yeah, you're referring to the power plants?

Mohit Kumar

analyst
#25

Yes.

S.K. Ramaiah

executive
#26

Yes. Look, with Talabira, that 300 to 800 megawatt — NRK <<inaudible>> has put in bids already, and BHEL and L&T are in there too. They're prepared to make a decision, possibly by the close of this year — by the close of this year, maybe a decision will come. That chance is going to be there. And naturally, NTPC, as I mentioned, they have to — they're calling for bids on the Lara project as well, 200 to 800 megawatts. Then Singrauli too, which is one more opportunity. So next — all of these projects will likely come up over the coming year as far as the power sector business goes. And there I mentioned the FGD business to you. And then, on FGD, what we're largely doing at present is that, now <<inaudible>> we've submitted an offer already. And then JSPL is coming with FTD conversion across all their plants around Tamnar, then in Odisha, which is in Chhattisgarh, Odisha. That's going to be a sizeable set of opportunities, roughly around 4,000 megawatts. And we enjoy a solid relationship with JSPL, <<inaudible>>, Tamnar and various other projects of that kind. And that ought to bring opportunities worth at least INR2,500 crores to INR3,000 crores, aside from the other government tenders and utility tenders that are expected to be completed.

Mohit Kumar

analyst
#27

Got it, sir. Wishing you the best, sir. Thanks, and good luck to you, sir.

Operator

operator
#28

Thanks. <<operator_script>> Our following question comes from Dixit Doshi, who is with Whitestone Financial Advisors. You may proceed.

Dixit Doshi

analyst
#29

Yes. Appreciate the chance to ask. I'd like to begin with where things stand on the MDO project. Is it online? Is it onstream? Previously, your guidance indicated revenue generation should begin by Q4 FY 2024?

S.K. Ramaiah

executive
#30

Yes, yes, yes. I'd like to give an update — one positive update, one favorable development. Look, for — beginning with the MDO project, Stage-one forest clearance is the critical milestone, and we've secured it, sir. So it's — regarding approvals, they're now in place; over the next two months, environmental clearance will come through, since Stage-one FC matters for environmental clearance. So come June, we'll begin ground activity. So this project is fully under control and is going according to plan. So we had planned roughly INR50 crores plus for FY 2024, and that remains on track. It's possible. Perhaps a slight improvement owing to escalation. We've taken the price as we quoted. So probably maybe in the second half or quarter three of next year, we'll review the numbers and will come out with the revised figure. So the number will be INR50 crores plus.

Dixit Doshi

analyst
#31

All right, thank you. My second question is really just to get a clearer picture. So any time we finish a given piece of work, at the close of each month we must be issuing an invoice to the client. Suppose certain clients fail to pay — how far do we keep going, or do we halt the work?

J Satish

executive
#32

Typically, with our cash contract — the recalled cash contract — the payment cycle runs 30 to 60 days. In practice, though, it's stretching to nearly 70, 75 days. So for existing customers, where we have that understanding, we'll go as far as 60, 65, 70 days too. For new customers, however, we don't go past 40, 45 days. That way, we see the payment is well protected otherwise. So we'll end up bearing extra costs.

Dixit Doshi

analyst
#33

All right. All right. But — there are — so previously, has there been a case, say, where a payment hasn't arrived even past 70 days. Do we usually halt the work then?

J Satish

executive
#34

Sir, this case has gone through several instances. We need to create that pressure, okay. Because our logic of around 50%, 55%, even 65%, is manpower, okay? So we need to build that payment — my payments are tied to our collection. So we've done it across multiple cases.

Dixit Doshi

analyst
#35

Alright. Alright. My final question concerns that Adani FGD order. So you said before that an advance is coming to us and that we won't need to put in our own funds for this project — is that correct?

J Satish

executive
#36

Yes. As of today, sir, our position hasn’t changed at all. It’s a complete—the aim is for this project to be cash-neutral. So apart from the equipment costing between INR25 crores and INR30 crores, which is already done, we won’t be putting anything in as working capital. We’ve therefore collected close to INR100 crores in advances for this project. We were already aware of this, and over the last two days we received some amount, and in maybe another week we’ll get a further INR25 crores to INR30 crores. So on a net basis we’re drawing funds because there’s no interest cost. And our progress is again in line with the receipts. So it’s on track, sir, yes, you are right. This project is going to be cash-neutral.

Dixit Doshi

analyst
#37

Alright. That wraps it up. One final question, then. Regarding margins by segment, are they broadly alike, or do they differ depending on things like erection, civil work, and O&M?

J Satish

executive
#38

Regarding the margin profile, sir, on O&M, we actually comment more on that, okay, we comment more on that, sir. And versus domestic and international, it's a bit on the higher side.

Dixit Doshi

analyst
#39

All right?

J Satish

executive
#40

And on the mechanical side, it operates at roughly 11.5% to 12.5%. For Civil, right now it's running at 9% to 10.5%. The reason is that we've been spending on royalties to build up the credit for four to five years now, and that fruit is coming to us at this point. So here's what will happen: the projects we've ported that are paying royalty now, those will be wrapping up maybe over the next few quarters, and we'll see that margin profile improve. So we're targeting that in FY '25, at a minimum we should get to our normal reported higher margins, which used to be 13%, a flat 13%. So that's what we're working toward.

Dixit Doshi

analyst
#41

All right. All right, that works. I’m done on my end.

Operator

operator
#42

Thanks. <<operator_script>> Our following question comes from Satish Heyda <<inaudible>> at Lucky Investment Managers. The line is yours.

Satish Heyda

analyst
#43

Yes. Hello, sir, I hopped on the call somewhat late. This may be a repeat question, and I apologize for that. I simply wanted to ask what update you would provide on the INR6,000 crores order that has come from Adani Power on the FGD side — regarding execution and regarding the timeline — and will it, by any chance, alter the initial expectation of revenue that we had for the ’24 and ’25, which I think in the last quarter, we mentioned that we’ll do about INR3,800 crores to INR4,000 crores revenue this year and about 5.5 next year. So, does it change anything? Does it change in terms of the order inflow advances? If you could comment on that, Sir? And I’m sorry if this question was answered earlier.

J Satish

executive
#44

Yes. As Satish I think mentioned not long ago, the advances remain on schedule — INR100 crores, plus a further INR50 crores, are likewise in the pipeline. Regarding conversion, these projects should reach completion by ’25. So what matters most for executing all of them is the ordering cycle. That ordering cycle will wrap up over the coming six to nine months. As a result, conversion ought to stay on track. In this year, we might book roughly INR50 crores to INR100 crores in turnover. For the following year, we expect a minimum of about INR1,500 crores, and the remainder will be finished within the next 12 to 18 months. So these projects carry full commitment, and we are tracking every aspect of that execution closely. The bulk of the work will then involve civil, mechanical, supply, structural and equipment supply. And as I mentioned, INR1,100 crores of ordering is already placed, while the remaining offering will be wrapped up between the second and third quarter. That ought to clear the path toward timely — reasonably timely — execution, allowing for local issues, whatever they may be: access availability, customer acceptance of certain items, all of those, plus the usual project issues.

J Satish

executive
#45

Beyond that, we feel quite confident about keeping this project on track at a reasonable pace.

S.K. Ramaiah

executive
#46

And sir, that INR3,500 crores to INR3,600 crores is pretty much the total, since we're talking about a quarter of nine months, so execution cycle improvements have been visible, and things are proceeding according to plan. Therefore, this year, the guided figures stay under control. And next year, even INR5,500 crores plus, okay? And should there be any enhancement in next year's additions, that could push it higher, but we'll bring you that figure, perhaps in the first quarter of next year. Right now, the number you've provided stays exactly as it is.

Satish Heyda

analyst
#47

So out of that INR6,000 crores backlog you have from Adani, INR1,100 crores of orders have already been issued — that's what you're referring to now, correct? Orders worth INR1,100 crores have been issued.

J Satish

executive
#48

Yes.

Satish Heyda

analyst
#49

And how much revenue are you assuming that order will bring in next year — that's '24 — within your total INR5,500 crores that you had in mind?

J Satish

executive
#50

We figure it comes to roughly INR1,500 crores.

S.K. Ramaiah

executive
#51

That's going to fall somewhere in the range of…

Satish Heyda

analyst
#52

About INR2,000 crores? All right. And sir, since these orders are of a more regulatory nature, putting up these FGDs was mandatory. Is there any timeline issue set by regulatory authorities for implementing it, or anything like that?

J Satish

executive
#53

What I can say is that the whole FGD retrofit program follows the <<inaudible>> covering ’24 through ’26, and plants fall into three classes: Class A, Class B, and Class C — with the majority of them in Class C, which is why ’25 and ’26 matter. So there’s a reasonable window to get this project done and satisfy the regulatory debt balance set by the government. Ordering is proceeding on that basis, and that’s also how the EPC has been placed by Adani.

Satish Heyda

analyst
#54

All right, all right. So under any circumstances, is there a way to call this off or push it back? Or are we required to go through with it?

S.K. Ramaiah

executive
#55

No, no. One aspect falls under the national commitment. And secondly, the FGD implementation totaling 1,69,000 megawatts represents the entire plant capacity identified from roughly 2,10,000 megawatts. This forms part of the mandatory incorporation pledged to COP2026, whatever international commitments exist there. Moreover, meeting the sulfurized emission control is extremely important for this country, and there is no reversing course on this. In fact, orders are anticipated. Indeed, numerous inquiries are already arriving — over 55% of ordering has been completed, and another 40%, 45% must be done perhaps within the next one year; all this ordering should be finished.

Satish Heyda

analyst
#56

And sir, how are things coming along on the balance — the 80,000 megawatt of projects where the FGD order hasn't been placed yet, and where you were hoping to pick up some order wins?

S.K. Ramaiah

executive
#57

Right, yes — we're aiming for roughly 7,000 to 8,000 megawatts there. As I mentioned, JSPL is involved, and Vedanta Group too; both of them rank among our favorite customers. Beyond that, there are private as well as public sector utilities. In Tamil Nadu we're going after business — we've already put in the offer — and in other chosen locations where we have a presence, we're able to do the same. Our intention is to look at opportunities totaling at least somewhere between 7,000 and 8,000 megawatts on this.

Satish Heyda

analyst
#58

All right, and one final question from me: MDO order execution is going to begin in ’25, is that correct? Is that how it works? Or does it happen in FY’24?

Sajja Kishore Babu

executive
#59

Look, MDO, right before your question came up, we had that update. So MDO, we've hit the first milestone, and that matters for getting the project underway. It's the Stage one forest clearance. Once that Stage one clearance is in hand, then Stage two and the environmental piece will follow within two months. So that approval has come through, sir. At this point the approval side is under control. As a result, work on the ground gets going from June onward. So the INR40 crores to INR50 crores, or perhaps that figure might rise a bit owing to escalation and what we've projected according to the timeline.

Satish Heyda

analyst
#60

So some of that business will be executed in ’25, right — ’24, sorry, ’24?

Sajja Kishore Babu

executive
#61

For 2024, we're looking at close to INR50 crores, and it may dip a bit due to the escalation figure <<inaudible>> ramping up.

Satish Heyda

analyst
#62

And regarding margins, should we anticipate any margin expansion in the coming year?

Sajja Kishore Babu

executive
#63

Sir, there's been a gradual improvement, because look at the last four, five years — we've been losing on royalty even though our core business has been delivering a good amount of execution margins. There's a high probability that it will go up. But we're confident that now, thanks to all these new initiatives, at least in ’25 we'll try to get to a normal margin — that's in the plan.

Satish Heyda

analyst
#64

This is that 2.5% of the order that you have to pay for…

Sajja Kishore Babu

executive
#65

That percentage is decreasing, alright? And gradually, the margin profile is getting better. So we’re observing that by ’25, we ought to return to our usual reported margins of 13% at minimum.

Satish Heyda

analyst
#66

Thanks. Thanks a lot, sir. I appreciate it.

Operator

operator
#67

Moving on, our following question comes from Jay Sinha <<inaudible>> with Jay Tours and Travels. You have the floor.

Jay Sinha

analyst
#68

Good afternoon, everyone.

Sajja Kishore Babu

executive
#69

Yes, sir.

Jay Sinha

analyst
#70

I think this is a question we keep hearing. It concerns only the Adani order — because of the news around Adani, our stock took a hit, I believe. So on the payment side for those Adani orders worth INR6,000crores, how protected are we now when it comes to both the payments and the execution?

Sajja Kishore Babu

executive
#71

As we mentioned, sir, okay, even we had similar portions, okay. Like we said, this project is cash-neutral. We have <<inaudible>> we will draw and utilize heat-based. So we've drawn INR100 crores plus. We'll be trying some more amount and almost INR1,100 crores to INR1,200 crores order being done. Now it's a global mandate and for them also there's a time pressure. So in terms of execution, it's on track. We are planning maybe INR50 crores to INR100 crores of turn over this year and maybe next year, we have planned INR1,200 crores to INR1,500 crores. And this number may further go up, because of time pressure, but that will come in maybe quarter one or quarter two of next year.

Jay Sinha

analyst
#72

That falls under the project.

J Satish

executive
#73

It's pretty much completely under control, sir. We're not seeing any slowdown.

S.K. Ramaiah

executive
#74

And building on what Satish mentioned, every project we're handling is performing really well up to now. We haven't actually reviewed that yet. The road project, the infra projects, and even the mining projects — plus what we're doing on the FGD jobs — none of our bills are outstanding beyond a month. 30 days, or what else?

J Satish

executive
#75

Over 16 years, we've been on a journey of getting to know the customer. So my actual payment cycle runs 30 days, all right. So if you look at today — as of today, nothing is actually pending as due. And since this is a large contract mitigation, we've made sure it has to be a cash-neutral project, with extra capex of INR42.40 Crores actually improving things. Those are in-house equipment. Beyond that, there won't be any working capital investment from our side.

S.K. Ramaiah

executive
#76

Actually, we did hold a review with the organic names, and we're providing the unpredicted support when it comes to these investments. Since they're highly specific to satisfying the regulatory requirements, and they're already committed to these projects.

Jay Sinha

analyst
#77

Alright.

S.K. Ramaiah

executive
#78

And then PPAs are also already in place. The orders from all the PPAs, including the projects, come to INR67 Crores.

Jay Sinha

analyst
#79

From what I understand, once this project is finished, the longest payment cycle will be 30 to 45 days.

S.K. Ramaiah

executive
#80

No, no. This project — yeah. 30, 40 days are the most beyond that, we can't afford to wait.

J Satish

executive
#81

When it comes to Adani and the FGD job, the investment commitment we've made is working capital, and it's based on what we get from them.

Jay Sinha

analyst
#82

Alright.

S.K. Ramaiah

executive
#83

So, we’ve got that in place.

J Satish

executive
#84

So the whole contract has been structured. Our vendors won't pay until we receive from them.

S.K. Ramaiah

executive
#85

Yeah.

Jay Sinha

analyst
#86

Right, so the order only gets executed after they’ve paid you the advance — that’s the sequence.

J Satish

executive
#87

But as things stand today, if I have a surplus, sir, it's almost more than INR100 crores plus. Okay. What I actually have is INR60 crores, INR65 crores as surplus cash.

Jay Sinha

analyst
#88

Alright. Alright.

J Satish

executive
#89

Alright, could we move on to the next question, sir?

Jay Sinha

analyst
#90

Yes. Thanks. Many thanks.

Operator

operator
#91

Thanks. <<operator_script>> Our following question comes from Anupam Gupta at IIFL Securities. Your line is open.

Anupam Gupta

analyst
#92

Sir, just one question on that. For FY 2024, is the mining MDO revenue at INR50 crore or INR250 crores?

J Satish

executive
#93

INR50 crore. 50.

Anupam Gupta

analyst
#94

INR50 crore. All right. And by FY 2025, to what level ought this figure ramp up?

J Satish

executive
#95

On MDO, for this 25, if we take that base figure and leave escalation out of it, the range will be 155 to 175.

Anupam Gupta

analyst
#96

All right, and escalation comes to roughly 40%.

J Satish

executive
#97

Could you say that once more, please?

Anupam Gupta

analyst
#98

So, relative to the base price, the escalation comes to roughly 40% based on what costs are right now?

J Satish

executive
#99

Yeah, so today the quoted price stands at 886. As for the escalation today, it's functioning at nearly INR1,450. And yes, as you correctly pointed out, that's a bit on the higher side, since diesel carries greater weight in the price escalation index, which is why this price has risen significantly. So the cost isn't proposed at that level. Therefore, the margin profile ought to improve as well.

Anupam Gupta

analyst
#100

All right. And regarding the point at which you consolidate it onto your balance sheet, what kind of capex ought we to factor in for FY ’24 — apologies, FY ’23 and ’24?

J Satish

executive
#101

For FY ’23, at this point the cap is INR15 crores, since not a great deal of investment is going to take place. For FY ’24 — look, we have an equity infusion planned of roughly INR100 crores, and on top of that 75% will come through outgo. So perhaps INR150 crores, INR160 crores, taking both equipment together — equity and maybe everything. So the range could be INR150 crores up to INR180 crores, and that is <<inaudible>> 45…

Anupam Gupta

analyst
#102

The INR150 basically consists of INR75 crores in equity, with the remainder being capex.

J Satish

executive
#103

Correct — INR75 would go up by INR24 crores, perhaps INR30 crores to INR40 crores, and INR25 accounts for the remainder.

Anupam Gupta

analyst
#104

All right, got it. Nothing further from this end. Thanks.

J Satish

executive
#105

Yes. Thanks, sir.

Operator

operator
#106

Thanks. Our next question comes from Nikhil Abhyankar at DAM Capital. Please go ahead.

Nikhil Abhyankar

analyst
#107

I’ve just got a question about bookkeeping. So may I just…

Operator

operator
#108

Nikhil's line has dropped. We'll go on to the following question, which comes from Riken Gopani of Capri Global. Go right ahead.

Riken Gopani

analyst
#109

Hello, sir. Can you hear me okay?

S.K. Ramaiah

executive
#110

Yes, go ahead and begin.

Riken Gopani

analyst
#111

Yes. Appreciate the chance to ask, sir. There are three questions from me. The first concerns the order book. You said earlier that for next year you may bid for roughly INR30,000 crore to INR35,000 crores worth of orders domestically. At 30%, that would translate to somewhere around INR8,000 crores to INR9,000 crores of orders for you here. Yet you also indicate that next year you would step up your emphasis on international markets too. So taken together, what level of order inflow do you anticipate internationally, and in aggregate what sort of addition do you foresee to the order book for…

J Satish

executive
#112

The plan we've maintained is INR7,500 crores, INR8,500 crores, okay. That figure includes roughly INR700 crores from the international order book. That's a target. So it'll be a mix of perhaps 50% O&M and 50% in the mechanical space.

S.K. Ramaiah

executive
#113

The chance we have within the domestic market is a big one. Whenever we find stronger opportunities there, we'll aim for them internationally as well, since India offers plenty of domestic opportunities—the same situation came up last year too.

Riken Gopani

analyst
#114

Understood. So you're anticipating roughly INR7,500 crores of domestic inflow. And within that figure, are you also booking any FGD orders? Or does that sit outside it?

J Satish

executive
#115

No, for FGD total opportunities, we might be bidding on roughly INR5,000 crores. Perhaps we'd expect around 30% of that.

Riken Gopani

analyst
#116

Understood. Alright. Understood. Understood. The following question concerns cash flow—specifically, the fact that you've managed to enhance the whole working capital cycle, as you noted, relative to last year. What is behind that gain? And looking ahead to next year, which direction would you want to guide us toward?

J Satish

executive
#117

It's really straightforward. For instance, as you can see, we've been working with BHEL for 23 years now, okay. Five years ago, the experience with BHEL was a bit different. But for the past five years, we've been seeing the receivable cycle stretch to 80 to 95 days, okay. And — so that was one of the reasons. And on some projects, BHEL — when a project is nearing completion and it's time for final bid certifications, they take a somewhat longer time. Now for four, five years, we've been working on various fronts, various initiatives such as railway, water, international and all. So now we're picking projects where we see the project is well-funded, the working capital cycle is good, and we're comfortable in terms of execution. So that is helping us — and bringing down the BHEL Pipe. If you — if we look back seven years, BHEL Pipe was almost 65% to 70%. And if we look back two years, BHEL Pipe used to be almost 35% to 40%, but now it has come down to 14% to 15%. So that is helping us — helping us a lot to rotate the working capital and the retention money, which we had INR250 crore to INR280 plus, okay.

J Satish

executive
#118

Even with growth, we're holding that steady, since for some of the projects—or shifts and the like—with private customers, the retention money comes in to back the BG. So that's going to help us out when it comes to working capital.

Riken Gopani

analyst
#119

Understood. So you anticipate that this 138 days will continue to decrease further over the next year?

J Satish

executive
#120

The plan is to get it down to at least 135 days first, over at least the next 12 months, okay, that's the plan. And with the new initiatives and all the new projects, there's a high probability that it should come down further. So we've seen that gradual improvement.

Riken Gopani

analyst
#121

Understood. Understood. And just to get one thing clear on the FGD piece, you said there’s a regulatory timeline that has to be adhered to. But to understand this better, are there any requests that could be made to delay this? Or is there no situation under which that’s possible? Could the timelines currently being set out for FGD be postponed in any way?

S.K. Ramaiah

executive
#122

Yes. I believe these — the data is being watched constantly by the central government as well as the central authority. They had set 24 there, and at this point they have raised it to 26. And considering — because it isn’t just the primary ordering that matters, but also how it gets executed, with plant availability for shutdowns, plus some access availability in those locations, since all of them are going to be retrofitted. Those considerations will be factored in, along with equipment availability and where it was sourced from, how sourcing is done, and all of that for every one of these aspects. And then, naturally, the entire FGD investment forms part of the tariff pass-through. And every one of these items must also be finalized together with tariff commitments from the DISCOMS <<inaudible>> and LC Boards. So it is a mix of all these elements, yet the commitment to carry out FGD is quite clear, and that is exactly what we have observed in the ordering as well. Plenty of ordering keeps taking place continuously.

Riken Gopani

analyst
#123

So it's at least fair to assume that for the projects you currently have on hand, there may be reasonable visibility that they aren't being pushed any further, and it will be done by FY ’25.

S.K. Ramaiah

executive
#124

Yeah, that's exactly where our optimism comes from.

J Satish

executive
#125

Our view is that this happens at the ground level.

S.K. Ramaiah

executive
#126

We're also keeping an eye on how the ordering process is being handled, since for all of these projects ordering is the single most critical element. Beyond that, we're carrying out 2 additional projects for BHEL as well. Those are on the civil side, and they too remain on track. So we don't expect major delays, or any delays at all on this, given that the government itself is pressing for completion. The developers have also made a commitment.

Riken Gopani

analyst
#127

Understood, understood. That’s really useful. Thank you very much, sir, and best of luck going forward. Yes. Thank you.

Operator

operator
#128

Thanks. We'll take the next question from Sheen George at Geojit Financial Services. The line is yours.

Sheen George

analyst
#129

Hello.

S.K. Ramaiah

executive
#130

Yes.

Sheen George

analyst
#131

Hello?

S.K. Ramaiah

executive
#132

Yes, we can hear you, sir.

Operator

operator
#133

Yes, go right ahead.

Sheen George

analyst
#134

Good evening, sir. Sir, could you share the revenue forecast — what's the estimate for 2024 and 2025, by 2024 and 2025?

J Satish

executive
#135

Yes. Look, as we talked about for ’24, and as we’ve also mentioned, if you look at the conversion, 40% to 42% is quite likely. So that’s INR5,500 crores plus whatever upside comes from the FGD, which will help us — that’s the plan. And then for 2025, since the MDO is going to begin, and we’ve even closed the water projects and everything, right? So there might even be some upside in FY ’25 as well. So that should come in, maybe, at around — taking the MDO together — it should come in close to INR6,000 crores plus, because we also have to finish the water projects.

Sheen George

analyst
#136

Got it. And could you share…

J Satish

executive
#137

We’ve maintained a goal of INR7,000 crores to INR7,500 crores, okay. And for ’25, we’ve set an order book target of INR8,000 crores, okay? So for the FY ’25 order book, we aren’t applying any conversion percentage. I’m simply taking the backlog.

Sheen George

analyst
#138

Sir, could you go over the order book one more time? Your voice came through very faintly.

J Satish

executive
#139

No. What I'm getting at, sir, is that for FY '24 we've set an order booking target of INR7,500 crores plus. And for FY '25, the target we've set is INR8,000 crores plus in order booking. So if you take a 40% conversion against the opening order book — and I'm not counting that year's additions — then we should manage to go past INR6,000 crores plus in '25.

Sheen George

analyst
#140

All right, and what can you tell us regarding your estimates for order intake — are those available?

S.K. Ramaiah

executive
#141

Actually, for this year we held INR10,000 crores, so we'll land near that figure. FY ’24, INR7,500 crores plus, and FY ’25, INR8,000 crores plus.

Sheen George

analyst
#142

Alright, thank you, sir.

Operator

operator
#143

Thanks. Our next question comes from Anish Jobalia at Girik Capital <<inaudible>>. Please go ahead.

Anish Jobalia

analyst
#144

Good evening, sir. Sir, you did provide certain figures regarding cash flow from operations during your opening remarks. So if you could just — I lost your audio at that point. But if you can share your — the figure covering the nine months? And what targets do you have in mind for the full year, and for next year too? I mean, considering the situation of better growth in revenues and margins, along with the working capital that we anticipate. So, if you could share some figures, that would be great, sir.

J Satish

executive
#145

Yes. Look, sir, for the nine-month period, that figure stands at roughly INR45 crores to INR50 crores plus, since that's the actual number. And we expect this number to rise, because whatever spending was needed to mobilize the projects, we've already incurred that for all the new orders, including the recent Kazipet and Bangalore Metro. So all the mobilization that's needed, the initial mobilization, we've completed it. So at FY ’24 year-end, it may land in the range of perhaps close to INR100 crores — that's our expectation. And in ’24, the number ought to increase, perhaps to around INR180 crores to INR190 crores.

Anish Jobalia

analyst
#146

All right, so let's look at the half year — during that period, I believe we had already brought in around INR62crores. So if you've recorded INR45 crores, that would suggest operations generated negative cash flow this quarter. Is that right?

J Satish

executive
#147

Perhaps INR10 crores to INR15 crores, accounting for the difference. Yes, that's correct.

Anish Jobalia

analyst
#148

All right, so even so, we still anticipate hitting the INR100 crores CFO for FY ’23, right? That is the goal. Is that right, sir?

J Satish

executive
#149

That's the target, sir. The reason is that for the new projects at Kazipet and Bangalore Metro, whatever mobilization was needed, okay, we've completed that in-house. So construction gets underway, perhaps 30 or 45 days after that. Typically, it takes 30 to 60 days. So as for the projects we currently have on hand, the funds have all been spent by now. And quarter four is usually a strong quarter for collections, and when it comes to execution, there is pressure from — there always used to be pressure from the customer during quarter four. And if you look at it in terms of quantum as well, quarter four will be almost — will be the high one compared with quarter one, quarter two and quarter three. So we are expecting a good amount of collections.

Anish Jobalia

analyst
#150

Understood, sir. Wishing you the best of luck with the next question and for the year ahead. Thank you.

J Satish

executive
#151

Yeah, absolutely. Thanks a lot.

Operator

operator
#152

Thanks. Our following question comes from Riken Gopani of Capri Global, whose line is now open. Please proceed.

Riken Gopani

analyst
#153

Sir, just a quick follow-up on FGD. So the order win we currently have is for roughly 6,000 megawatts. And the total order book comes to about INR6,000 crores. Does that work out to something like INR1 crore per megawatt — is that the way to look at it? And in that light, when you mentioned that you're aiming for about 8,000 megawatts of additional ordering, could you just help me understand why you're building in INR1,500 crores of new order win expectations for next year?

S.K. Ramaiah

executive
#154

So, what exactly is — well, packaging comes in two varieties here. First, when you have a full EPC package, the figure we received from Adani was roughly INR73 lakhs for each megawatt. Then there are contracts given out on a package basis, such as heavy mechanical supply plus a service job. That range can run anywhere from INR20 lakhs up to INR30 lakhs per megawatt. It all depends on what the customer chooses. So, the orders currently in the pipeline from CESC, Goenka Group follow that same philosophy rather than EPC. So it ends up being a mix of EPC, package-wise arrangements, and so on. But as I mentioned in ballpark terms, if we look at the 7,000 to 8,000 megawatts of opportunity, what we intend to target comes to about INR5,000 cores, INR6,000 crores. And then, drawing on our past experience along with how competitive the market is, that gives the figure I mentioned of INR1,500 crores.

Riken Gopani

analyst
#155

All right. But as for the rest of the power capacity that still requires FGD retrofitting, that figure is roughly 80,000 megawatts — is that right?

S.K. Ramaiah

executive
#156

Yeah, it's approximately 80,000 megawatts. Then you've got the other private players — Adani, for instance, has already moved ahead on this. JSPL is in the mix now, JSW too. Vedanta Group is also there. Beyond them, a range of other private developers still need to act, and on top of that, the state utilities are involved as well. Tamil Nadu, for example, is bringing in plenty of inquiries, followed by Maharashtra, then Gujarat, and the remaining states — most of them will have some leftover orders to place. The bulk of the ordering so far has come from NTPC alone, plus a few private players. So all of this has to be wrapped up within the coming year, since the deadline is 2026. On that basis, these figures will be INR1 crore.

Riken Gopani

analyst
#157

Right, so you'll still be part of that 80,000 too. This is only according to what you can currently see?

S.K. Ramaiah

executive
#158

Right. What I'd like to say is that these are all industrial packages, with individual plants in place. So roughly 10% of the available opportunity will participate. That's on a conservative basis. Maybe we'll go beyond that as well. But we're taking this one, our present this one, we can do that much easily.

Riken Gopani

analyst
#159

Got it, sir. Got it. That really helps, and many thanks for the responses.

S.K. Ramaiah

executive
#160

Yes. Thanks, sir.

Operator

operator
#161

Thank you. Since no one else has a question, I'd like to turn the conference back to management now for their closing remarks.

S.K. Ramaiah

executive
#162

Alright, Ramaiah here once more. Many thanks for joining us, everyone. I believe Satish has already covered the figures, along with the marketing side and the opportunities that exist within the INR10 crores budget. Capital investment overall has risen 30% on the government's part, and private capital is now set to arrive on a large scale in infrastructure, followed by capital equipment, steel plants, infrastructure projects, mining, minerals, and so on. So an opportunity worth INR30,000 to INR40,000 crores, I'd say, is not a challenge — which means the targets set at INR7,500 crores for next year, and holding to them going forward, are reasonably achievable. On our ordering side, the execution cycle is also getting better. There's a clearer grasp of the business across the various projects we've taken on, including wherever we moved into new areas in non-power. Execution cycles are improving, projects are coming under control, and execution as well as cash collection are better. So we stay optimistic, and the numbers reflect that in terms of ordering, execution, and the other PAT and EBITDA margins. That's what I wanted to share.

Prasheel Gandhi

analyst
#163

Thanks, everyone. Many thanks.

Operator

operator
#164

<<operator_signoff>>

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Power Mech Projects Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Power Mech Projects Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Power Mech Projects Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.