Good day, everyone, and welcome to the conference call for Power Mech Projects Limited, hosted by Nirmal Bang Equities Private Limited. Please be aware that all participants will remain in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you require help at any point during this call, just press star followed by zero on your touchscreen phone to signal an operator. Kindly note that this conference is being recorded. At this time, I'll turn the call over to Ms. Natasha Jain of Nirmal Bang Equities. Thank you, and the floor is yours, ma'am.

Natasha Jain

analyst
#2

Thanks, and a good afternoon to everyone joining us. Nirmal Bang Institutional Equities is glad to welcome each of you to the First Quarter FY25 Earnings Conference Call of Power Mech Projects Limited. Joining us from the management side today are Mr. S. K. Ramayya, Director, Business Development; Mr. Rohit Sajja, President, Business Development and Operations; and Mr. N. Aravind, Chief Financial Officer. At this point I'll pass the call to the management for their opening remarks, and after that we will open the floor for Q&A. Thanks, and over to you, sir.

Nani Aravind

executive
#3

Thanks, Natasha Jain. I'm N. Aravind, the CFO at Power Mech Projects Limited. Joining me are Mr. S. K. Ramayya, our Director of Business Development, and Mr. Rohit, President of BD and Operations. Welcome, everyone, to the quarter one FY25 earnings call. Total income reported for quarter one of financial year FY25 came in at INR 1,017 crore, versus INR 871 crore in Q1 FY24 — that's a 16% rise year-on-year. EBITDA stands at roughly INR 123 crore, compared with INR 105 crore, up 17%, while PAT is INR 60 crore, which grew 18% from INR 51 crore in Q1 FY24. So the improvement shows in the overall margin profile. EBITDA margin moved from 12% in Q1 FY24 up to 12.1% in Q1 FY25. The revenue mix for quarter one FY25 breaks down like this: the Mechanical business contributed INR 102 crore, versus INR 139 crore in Q1 FY24, a year-on-year decline of 36%. The Civil business — including railway, mining, and water distribution — contributed INR 557 crore, versus INR 490 crore in Q1 FY24, up 13% year-on-year. Windmill revenue was INR 341 crore, versus INR 224 crore in the corresponding period last year, registering growth of 52%. And the electrical business came in at INR 8 crore, versus INR 9 crore in the prior period.

Nani Aravind

executive
#4

Other income came in at INR 9 crore, compared with INR 6 crore in Q4 of FY23. In the first quarter of FY25, the split between our domestic and international businesses was 94% and 6%, respectively. The power sector's contribution held at 54%. Non-power accounted for 46%. Net current days, excluding cash and cash equivalents, rose from 112 days in FY24 to 142 days in Q1 FY25 — largely because of the elections, along with delays in realizing receivables and delays in certification of works, which pushed up the company's current assets. Debt levels remain under control. As of 30 June 2024, gross debt stood at roughly INR 581 crore, with net debt at INR 40 crore. The debt-equity ratio as of 30 June 2024 was 0.31 times. On order book status, so far this financial year the company has won orders valued at INR 1,746 crore. The order backlog as of 12 August 2024 is approximately INR 57,793 crore. Excluding the two MDOs, the non-MDO order book comes to INR 18,115 crore. For expectations this current year, FY25, the overall business environment appears to have picked up after the elections, and the execution cycle is gaining pace. Even with a somewhat slow Q1, we are confident of delivering revenue growth in the 25%-30% range for FY25.

Nani Aravind

executive
#5

We expect margins to hold steady, and we anticipate additional gains as the MDO business scales up. After MDO revenue reaches its peak in FY26 and FY27, the margin profile will improve noticeably. Regarding the order book, our target stands at INR 11,000 crore for the financial year 2024 to 2025. We will keep concentrating on industrial plant operation and maintenance, railways, and water. Looking ahead, the windmill and MDO businesses will deliver stability in both revenues and margins in a substantial way. At this point, I would like to ask Mr. Ramayya to share the latest developments.

S. K. Ramayya

executive
#6

Yes. Thank you, Aravind, and thank you, Rohit. Good afternoon, everyone. Aravind has covered the key figures as well as the margin improvements and so on. On the business outlook, in the first quarter our order booking came in at INR 1,014 crore, and given the elections and everything, a number of tenders were pushed back and such. Now momentum is building. The base order backlog as of the close of last quarter stood at INR 1,732 crore, with an ordinal improvement to INR 1,408 crore overall. Mechanical orders' backlog rose 2.1%, moving from INR 6,422 crores to INR 6,558 crores, while the civil order backlog increased 2.3%, from INR 7,814 crores to INR 7,995 crores. In windmill, there's a 12% dip, from INR 2,197 crores down to INR 1,933 crores. Electrical is more or less steady, at the same level. The encouraging part, though, is that overall order booking keeps improving. Quarter by quarter, windmill is gaining a lot of momentum. In the second quarter, we managed to lift overall order booking to, let's say, as much as INR 550 crores.

S. K. Ramayya

executive
#7

There are many new projects coming in on windmill across both international and domestic markets, plus new projects that are being commissioned and some contracts that are being extended as well. Now, looking at the company's overall business outlook for the year, Aravind had given a figure of INR 11,000 crores, and with the current order booking at INR 1,746 crores, we should still be working on gaining traction to hit those goals, since the size of the opportunity has risen substantially. Across various opportunities in the power sector, the non-power sector, and windmill, railways, road construction, and industrial projects, etc., there is continuous tracking of many of these opportunities. We are tracking roughly INR 75,000 crores of opportunities, and there are hardcore opportunities of nearly INR 20,000 to INR 25,000 crores, with the power sector, windmill, and all taking the lead. And as we know, BHEL has been given a lot of orders, and with INR 88,000 crores of order booking over the last more than a year, we have a substantial order booking. And what matters is that in the power sector, there are three developments I would like to update.

S. K. Ramayya

executive
#8

First, there's the order booking BHEL has secured — roughly INR 88,000 crores covering about 13,840 megawatts. That will play a big part in how our order booking shapes up this year and next. Second, Adani is developing three major projects — Raigarh, Raipur, and UP as well, in addition to Mahan. So roughly 4,000 megawatts they're developing on their own, naturally with supply orders placed on BHEL, and a few of those orders we're going to pick up too. The third development: as you know, coal-based power currently has an installed capacity of 218 gigawatts. The government is set on ramping that up to 300 gigawatts by the close of this decade. That's mainly aimed at grid stability, which I believe we've gone over many times before. Now they're determined to make sure the backlog in order booking gets addressed quickly — not just through the many development projects already underway, but they're also planning some pithead stations. So in that direction, NTPC intends to add around 26,000 megawatts of new capacity. Of that, about 5,000 megawatts is already being implemented. The remaining roughly 17,000 megawatts they need to order in two stages.

S. K. Ramayya

executive
#9

For stage one, the work has already been taken up — roughly 8,600 megawatts. Another 8,600 megawatts of tenders still need to be upgraded and all, and those tenders have to be issued and all. And for NTPC, BHEL, Adani, that's what we expect in the power sector to play a role in the coming year. And the total opportunity size can be anywhere between INR 20,000 to 25,000 crore, looking into the various aspects of the civil, structural, mechanical, ETC business and all. And whatever ones are getting commissioned, we have seen the flow of the orders in the windmill segment also. That is going to happen — for example, what has happened in UP for the NLC project, and then there are other projects also which have come. And recently, Nizam Energy has given one more order for the another plant, INR 210 crores. And in fact, so far, we have on the windmill side, about INR 550 crores of orders have been arranged at the current date. And there is an opportunity of INR 1,500 to INR 2,000 crores, which has been tracking hardcore opportunities also. Now, apart from that, the non-core segment is a big business. In particular, railways, we are having INR 2,500 crores of jobs executing in about 15, 14 jobs, including a major job in Bangalore BMRCL, that is railway infrastructure jobs.

S. K. Ramayya

executive
#10

Also, plenty of other railway work is progressing quite well. Adani-related jobs are moving ahead too, and we’re now seeing some momentum on the FGD projects as well — Udupi, and Gondia as well. That ought to bring in some extra revenue during the current year. Now, returning to the other opportunities available out there — for instance, there will be very large investments in steel, in the non-power sector, in minerals and metals, and at NMDC. NMDC is planning INR 60,000 crores of investment, and for many of those projects, tenders should be called shortly. Steel Authority of India, meanwhile, is planning an expansion at the East Coast Burnpur plant for INR 4.5 million tons, with an investment of INR 30,000 crores. M.N. Dastur & Co is a consultant, and many packages should come; we’ll need to look for partners there. JSPL is also coming with a plant of five million tons in Angul, with an investment of INR 27,500 crores. We have ongoing relationships and are doing some of their jobs at JSPL Angul too. Recently, we took a job there worth INR 160 crores. Looking at all of this, and apart from the railways, the road projects, as we said, these opportunities should mature sufficiently.

S. K. Ramayya

executive
#11

So now, once the election period is behind us, I think the major participants will push harder to get orders moving faster—developers such as NTPC, and then the railways as well. And Adani too, they need to speed up their projects, since their plan is to grow their stock base from 15,500 megawatts up to 31,000 megawatts over the coming seven, eight years. They've already begun the first phase. The second phase will also be taken up. And there could be one more development. The organization is making some moves on its own initiative, and its strength has been bolstered when it comes to BOP packaging, and right now we are tracking roughly INR 4,000 megawatts worth of opportunities. Our teams are in talks with lots of the players and so on, because developers and owners alike feel the urgency to figure out how to package things better in a way that brings more participants into the picture for the balance of plant packages, separate from the main plant—so BHEL is the only player in the main plant and they will keep receiving those orders, but an extension is underway at NTPC and with plenty of the private developers too, to work out how the packaging can be done.

S. K. Ramayya

executive
#12

That's where we see the opportunities. That opportunity size can be more than INR 15,000 to 20,000 crores. So looking at all these things, perhaps the flow of orders would improve in the second and third quarter. And one more development is the optical fiber cable, which is a part of the BharatNet connectivity to every village with an investment of INR 3.65 crores. That is taking full shape. And then our business development group, Mr. Rohit, is taking a lot of initiative on that. And then there are we have made up some time with the parties and looking at some of the important opportunities in Madhya Pradesh, Maharashtra, and other places. And then that should take some shape. That will be a substantially big opportunity. And as the development takes place, we will keep you informed on that. Therefore, that is where the thing and the international operations. One of the key developments has been that Nigeria, the two-year windmill job has been further extended for another two years. That is an important add-on to the windmill activity and our work. And this will continue. Our initiative on windmill will continue. The ETC business will continue with more order backlog for BHEL.

S. K. Ramayya

executive
#13

And regarding the NTPC order flow—which, as I mentioned, ought to be sped up—roughly 17,000 megawatts. Then there are Adani's projects already underway. And the railway work. And, naturally, infrastructure projects too. We're keeping an eye on a lot of these efforts. So on that basis, we remain quite optimistic about the targets for this year. Thank you. After that, Rohit, our president of BD, will also share an update on other developments, covering the MDO and everything else.

Rohit Sajja

executive
#14

Thank you, Ramayya sir. Good evening, everyone. So before I hand things over for the question and answer, I'll wrap up with a handful of Q1 of 2025 highlights. And I'd also like to say something about both MDO projects, which I'm watching closely, plus a few updates from the business development side and on overseas business too. So we have some encouraging news on the MDO front. We've received clearance from the Jharkhand government allowing us to take possession of 585 hectares of forest land. That took an extra month, but we managed to secure it before the state elections could be announced, sometime in November or December, which is a good update. So I think we're hoping to break ground sooner. We had expected to break ground in July, the first two weeks of July, but now it's been pushed back by two months. By end of September, beginning of October is when we expect to break ground and start the overburden activity. That's regarding the first mine, KBP. Tasra is the TMPL, and the SAIL mine is proceeding a bit more slowly than expected, owing to SAIL's washery tie-up and their washery capacity being fully utilized. In Q2 of this year, there's going to be, once again, a significant increase in the quantity that they're going to ask from us.

Rohit Sajja

executive
#15

Mining work is continuing in any case, though during Q1 we could allocate only a limited volume to SAIL, and that allowed us to record roughly INR 14 crores in revenue. For Q2, we anticipate strong figures. Dispatching has already begun at nearly 1,000 metric tons each day. That volume is projected to climb to between 4,000 and 5,000 metric tons per day. So that covers the MDO side. On business development, as Ramayya sir mentioned, I want to add a few observations about the BharatNet mid-mile connectivity project, which we recently bid on as part of a consortium alongside a well-regarded optical fiber cable laying firm in the country. We took part successfully in every package — all 16 packages that any company was eligible to bid on. Results should come out at some point before the middle of next month. That is one update. Also, overseas O&M has grown; measured against Q1 of last year, overseas O&M for this year's Q1 rose by nearly 27% in revenue, and this pattern should persist over the coming four to five years.

Rohit Sajja

executive
#16

We're gaining solid momentum. This year we're also looking into new markets. For instance, we've put in bids for a few projects in Jordan. We've brought on new clients in Qatar and Saudi Arabia too. And we expect that pattern to keep going. Plenty of overseas O&M work is set to emerge over the next two to three years. That's what I have to share. Let's move ahead to the Q&A.

Moderator

operator
#17

Thanks a lot. We'll move on to the Q&A portion now. If you'd like to pose a question, just hit star and one on your touchtone phone. Should you want to drop out of the queue, press star and two. We ask that everyone use handsets when asking a question. Ladies and gentlemen, we'll pause briefly while the queue is put together.

Ketan Jain

analyst
#18

Greetings, everyone.

Moderator

operator
#19

Our first question comes from Ketan Jain at Avendus Spark. The line is yours.

Ketan Jain

analyst
#20

Good afternoon, sir. Could you give us some color on EBITDA margins by segment — civil works in power, mining separately, and railway separately? Can you tell us where you see EBITDA margins being relatively higher or lower?

Nani Aravind

executive
#21

Yes, sir. Sir, regarding the erection businesses you mentioned, we're achieving an EBITDA of roughly 6%. In industrial construction, for the erection businesses in question, turnover volume is quite low. So we're getting approximately 1% EBITDA there. As for civil power, we're seeing an average EBITDA margin of about 12%. On the infrastructure side, which includes your sand mining and water division combined, we're getting a margin of around 17%. In transmission and distribution, we're at roughly 0.5% EBITDA. For international operations, since it's Q1, we're getting margins of around 20%. And in the water division, we're generating approximately 19%. Taking a weighted average across all two years, we're getting roughly 10% to 11% in the infrastructure businesses in question. On mining, as of now only Tasra is operating. So we earned an EBITDA margin of 13% during Q1, sir. So the weighted average EBITDA we get is around 12.2%.

Ketan Jain

analyst
#22

That's useful. So when I look at these figures, your water division and your civil work in power are comparatively higher, whereas erection and industrial construction are comparatively lower. And power T&D is also on the lower side. Is that correct?

S. K. Ramayya

executive
#23

Right, right. The reason is that certain projects — O&M domestic and overseas, water, civil, covering both power and non-power — sit on the higher side. And as you correctly noted, the remaining businesses, industrial construction along with non-power construction, are somewhat on the lower side.

Ketan Jain

analyst
#24

Got it. On your second question about the opportunity on the power side — you brought up roughly 17 gigawatts from NTPC, plus a lot of projects from Adani as well. What NTPC is saying is that their total construction cost comes to about INR 10 crore per megawatt. So out of that INR 10 crore, what share would the civil opportunity represent?

S. K. Ramayya

executive
#25

Sure — NTPC pricing comes in at INR 10 crore including IDC. We might need to factor in roughly INR 2 crore, or perhaps INR 1.5 crore, out of that total. That portion won't count as an opportunity — it represents interest during construction. So we can treat INR 8 to 8.5 crore as the base price, along with whatever the current price happens to be. Typically, when you account for full material content plus engineering and supply, and then the structural portion together with the material content, the civil and structural piece works out to about 20%. Roughly speaking, we can put it at around INR 2 crores.

Ketan Jain

analyst
#26

All right, 20% of INR 8 crores. All right.

S. K. Ramayya

executive
#27

Sure, 20 to 25% is something we can accept. Because, naturally, when they award the contract to BHEL, we'll need to look at the scope carefully — whether it includes material or not. Those details will be handled separately.

Ketan Jain

analyst
#28

All right. Because you brought up BHEL, my last question is this: we're hearing that at present, on the thermal side, BHEL is the sole vendor. So do you think that all of this 17 GW by NTPC, plus another 10 to 15 by Adani Power — will all those capacities get equipment delivered on time from just one vendor? What's your view on that? Is the government taking any steps to broaden the vendor base?

S. K. Ramayya

executive
#29

That's a really crucial question, and we need to reflect on it ourselves. Look, BHEL—I'm a former BHEL person myself. BHEL's base shop capacity stands at 15,000 megawatts. That much is certain. And when you examine the current balance of order bookings, they are slated to add 80,000 megawatts over the coming seven to eight years. On paper, that is achievable. Yet BHEL has other matters to deal with—whatever their working capital situation is, so many issues—and those can persist, because their margins have slipped somewhat. Or "somewhat" really means there are other problems at BHEL. Still, they are delivering. But what I can tell you is that the government is also lending encouragement. For instance, we recently got some inquiries from Thermax as well for the DVC Raghunathpur project, two into 650 MW. Naturally, they are involved in the boiler package. In fact, DVC has floated a tender for the boiler. That is, they have a boiler and turbine island. Which means it spans the whole plant. So, these ideas could surface for NTPC too. They might alter their strategy. As a matter of fact, NTPC has been in discussions with players such as us, another BoP player, about how we might also enter the BoP business.

S. K. Ramayya

executive
#30

Yet, as I mentioned, BHEL can pull this off provided they arrange their financing and other matters somewhat more effectively. Beyond that, they possess the shop capacity, I can assure you. And L&T likewise had built-up capacity, and they were performing quite well, with ongoing work proceeding in Buxar and other locations. What has occurred, though, is that the new CEO, Subrahmanyan, has stepped up. He has taken the initiative, along with a bit of BoP, whatever exists there. But at this point the government will certainly back them. The Ministry of Power will be advocating for them, similar to what they did for Thermax as well. Maybe L&T will likewise join in. And GE represents another possibility, though GE possesses a turbine island, which is GE, and a boiler too they have. That, however, is a separate matter. I would rather not say much about it at this point, since there is an EDF takeover of the GE turbine portion. And should that come into play, they too could contribute to it, in one aspect of the power plant.

Ketan Jain

analyst
#31

Right, sir, so what I’m picking up is that BHEL looks capable on paper, yet it still needs to resolve certain execution and financial issues. At the same time, the government will certainly need to press other companies such as GE and L&T, among others, so deliveries happen on schedule and this target can be met. If not, delays are certain.

S. K. Ramayya

executive
#32

Right, right. Thermax could definitely be part of this, because honestly speaking, they put a lot of money into their Pune facility, and a couple of years ago we were in talks with them as well. Of course, once the slowdown hit, they didn't make that commitment either. But at this point they have — maybe this whole push has come down from the Ministry of Power. I believe the same approach will be taken with L&T too. These new entrants will be brought in. Thermax is capable of delivering as well. We've already done a bit of work with Thermax too. They have the capacity for it.

Ketan Jain

analyst
#33

Thank you very much, sir. I'll rejoin the queue.

S. K. Ramayya

executive
#34

Yeah.

Moderator

operator
#35

Thanks. Just a quick reminder for everyone: to ask a question, press star and one. Our next question comes from Riya Mehta at Aequitas Investment Consultancy. Please go ahead.

Riya Mehta

analyst
#36

Thanks a lot for the chance to ask. My question is really about the broader macro picture. Recently, a Supreme Court ruling came out saying that states are allowed to impose a mine tax with retrospective effect starting from 2005. So would that have any effect on our existing MDO business, or on future business?

Nani Aravind

executive
#37

Riya, could you say that question again?

Riya Mehta

analyst
#38

Absolutely. So not long ago, a Supreme Court ruling came down stating that state governments held the authority to impose tax on miners retroactively starting from 2005. So does that create any shift in the current commitments for the two MDO projects?

S. K. Ramayya

executive
#39

Ma'am, MDO — we've held the MDO ownership. We only do the mining excavators. So whatever GST taxes apply, they fall on my revenue. So the MDO ownership has been with us.

Riya Mehta

analyst
#40

Right, right, got it. But are they going to lower the offtake volume on account of their payment cycle, or is it that they're required to pay for roughly the last 17 years? So have you observed anything like that?

Rohit Sajja

executive
#41

This won’t affect the offtake in any way. Should there be any effect on the offtake, the offtake is protected by clauses—possibly under the contract rule in this case. Yeah. So no impact on the offtake will occur.

Riya Mehta

analyst
#42

All right, that's encouraging to hear. And then, regarding what you mentioned about the Adani Mundra project — that the FGD work there is going to begin — could you share some additional specifics on that?

S. K. Ramayya

executive
#43

Yes, I believe the trend review is underway. We’re working on it, and it may be finalized in 2 months, and we’re fairly optimistic about that.

Riya Mehta

analyst
#44

And if that plays out for this year, would we be looking at an extra INR 100 to 150 crores?

S. K. Ramayya

executive
#45

Sure, we’re watching that closely. That’s another possibility as well. But as things stand today, we’re budgeting roughly — since offers are moving forward on a business for the UDP project, and also for the other two into 650 MW in Mundra — around INR 600 crores of offers on the supply chain side are being locked in. So we’re confident that INR 300–INR 350 crores of revenue should be achievable this year. Work has already begun in UDP.

Riya Mehta

analyst
#46

So for all the Adani projects together, we're talking INR 300 crore to INR 350 crore, correct?

S. K. Ramayya

executive
#47

Right, right, right. At this point.

Riya Mehta

analyst
#48

Understood. Understood. I believe I appreciate both the questions and the responses.

S. K. Ramayya

executive
#49

Thanks.

Moderator

operator
#50

Thanks. Everyone, if you'd like to ask something, just hit star and one. Our next caller is Sanjaya Satapathy with Ampersand Capital. Go right ahead.

Sanjaya Satapathy

analyst
#51

Yeah, thanks a lot for the chance, and I just wanted to confirm a couple of things. We've noticed your sales growth has finally started getting a little better, with some 16% kind of growth this year, and your guidance is almost like 30% growth for the rest of the year, which looks pretty high compared to what has been happening in the same period, so can you just tell us what could be the factors that will drive this kind of better growth?

S. K. Ramayya

executive
#52

Right, okay. So on the power sector and the opportunity side, I mentioned that INR 15,000 to 20,000 crores will come through over the next two years. As for whatever ordering BHEL needs to do for the supply chain, they have to wrap that up. Adani has to finish their piece. Now NTPC, like I said, 17,000 megawatts — they're expected to place orders this year. Something could come from that. So in the power sector, on the O&M side, as I mentioned, close to INR 600 crores has already been booked. There are plenty of opportunities out there. We're also engaged with some new players. GMDC, INR 240 crores — that's also anticipated. Then there's another order with the Vedanta Group that we're in discussions on for 91 megawatts. After that, Panki — a 1 into 650 megawatt O&M order that we're discussing. And then another 250 MW lignite boiler with GMDC, which we're also discussing. So we're fairly bullish on O&M this year as well, in this range, within the power sector. Some of the non-power side is possible too. Railways is another sector — roughly 5,000 crores of opportunities that we're tracking.

S. K. Ramayya

executive
#53

As you're aware, we're handling 12 to 14 jobs, which includes the metros plus railway doubling, traction doubling, and all of that. And by now we're well versed with the system, and the payment mechanism is good. Our execution system is also fully established across our organization and everything. So we can be more aggressive on the railway jobs as well. Then of course, new opportunities will come up on the industrial side and the steel plant side mining. And then mine side facilities — for example, Coal India is planning INR 62,000 crores of investment for mechanization of the mine side. All those things will also come up. So the overall opportunity we're tracking, as I said, is INR 75,000 crores, and that is being continuously followed. And the good thing is that by the end of the second quarter, the end of the third quarter, and the end of the fourth quarter, many of these things should happen the way we have planned.

Sanjaya Satapathy

analyst
#54

Thanks for all that detail. What I'm getting at is this: you'd already built up a sizable backlog over the past few quarters, yet the pace of execution was slowing somewhat. Now, though, you sound far more confident. Has something shifted? After all, what we're discussing at this point is execution, not order intake.

S. K. Ramayya

executive
#55

Looking at the execution side, the figure was INR 3,600 to 4,200 crores and it now stands at INR 5,200 crores. That is achievable. In the first quarter, revenue came to roughly INR 1,000 crores, which is what has been delivered so far, and then you look at the second quarter — and we can factor in the monsoon and other things for that one — but the third and fourth quarters are typically the strong growth periods. So that should still be within reach, and then the orders that are landing in the first quarter, in the first two quarters, those 17,000 to 1,746 crores, some of that will move toward conversion, and then the Adani order worth INR 300 crores will also move toward conversion, and any orders that come in during the third quarter as well carry some further possibility of conversion. But when it comes to what the organization is capable of, its strength, and the various other inputs needed, we already have those inputs in place — manpower, resources, construction equipment — and the people are there for that. That is not a challenge.

Sanjaya Satapathy

analyst
#56

Got it. Sir, if I may just ask about that, I mean, is your tax rate going to fall to 25%-26% this year?

Nani Aravind

executive
#57

Yes. It’ll decrease this year, sir. Last year, because of income tax, extra income was offered to income tax owing to the sales channel, which meant additional cost was incurred. So this year it should return to normal — perhaps roughly 26%-27% will be the goal for this year. Yeah.

Sanjaya Satapathy

analyst
#58

All right, so when it comes to MDO's contribution — you said that's going to speed up, but you also said the margin-expansion benefit from it probably won't show up this year. It's more likely starting next year. Is that right?

Nani Aravind

executive
#59

Right. We’re in the development phase here. So the first ramp-up in production has to take place. Getting that ramp-up could require at least another 2 years. After that, our washery will begin contributing as well—washery revenue. So at that stage, you’ll see the incremental gain. There will be incremental improvement 2 years from then. From 2026 and 2027 onward, we may look for margin improvement in MDO. Up to then, we’ll be at roughly 15%–16%.

Sanjaya Satapathy

analyst
#60

Understood. Understood. Thanks, sir.

Nani Aravind

executive
#61

Thanks. Thanks a lot.

Moderator

operator
#62

Thanks. We’ll take the next question from Anupam Gupta at IIFL Securities Limited. Go ahead, please.

Anupam Gupta

analyst
#63

Yeah. Good afternoon, sir. So my first question concerns MDO. You mentioned that the CCL project is experiencing a 2-month delay. So aside from that land possession, are there any other clearances still outstanding at this point before the project can begin at the end of September, or is that now realistically certain?

Rohit Sajja

executive
#64

Good afternoon, Anupam. This was the final step before we could begin mining activity. Now we just have to file an online application, which we're doing either tomorrow or the day after tomorrow. Once we receive clearance on it, that will take about a week. After that, we can officially start the pre-filling activity. Pre-filling happens before we begin removing overburden.

Anupam Gupta

analyst
#65

So it's fair to assume that certain revenues from the CCL project will land in the third quarter, correct? Or is that the right way to think about it?

Rohit Sajja

executive
#66

Right, so at the close of Q3 and into the start of Q4 — the reason being that we first need to reach 45 to 50 meters of strike along where the seam runs. Up to that point, overburden excavation has to continue. Tree felling will require two months. Once those two months are up, it's all OB until we hit 45 to 50 meters. It's only after the overburden comes off that we'll actually reach the seam.

Anupam Gupta

analyst
#67

And second, regarding the SAIL project — the washery problem was also present in Q4. And I think in Q1, it actually wasn't there as far as the revenue delivery you had. So where does the washery tie-up stand right now? And is it structured so that until your washery comes online, volumes stay guaranteed at least once it starts?

Rohit Sajja

executive
#68

So Q4 of 2024 was fine, really. They managed to take a fair amount of capacity from us, but Q1 of 2025 has gotten worse. The main reason is that SAIL's washery capacity is maxed out. One of the lines isn't running, and the other one is at full capacity, and it depends on when they need it, so we talked with them, we signed minutes of meeting, and beginning the first of August, we've started taking 1,000 metric tons per day. They've already hit 1,500 this week. This week, we're already beginning to supply 2,000 metric tons per day, so again, this ramp-up will happen gradually. We're in discussions with SAIL, so at the moment, this is how it looks. They'll begin taking 80,000 to 1,000,000 per month, moving up gradually from 60,000 to 1,000,000. Beyond 1,000,000, once again, we're talking with them about raising it to 1,500,000 and 2,000,000 per month.

Anupam Gupta

analyst
#69

Got it. So the 25%-30% growth figure you mentioned for this year — how much of the mining revenues for this year did that include?

Nani Aravind

executive
#70

Actually, we took in INR 250 crores from Tasra and INR 50 crores from KBP. So perhaps 250 — tax maybe roughly 100, 150, 100 crores, perhaps tax. Since the offtake isn't there. Beyond that, we are, in line with our guidelines, able to achieve.

Rohit Sajja

executive
#71

So Anupam, from the two mines combined we're projecting roughly INR 300 crore — 250 and 50. And we expect to get there because with KBP, even if we aim for Q4, we can hit that INR 35-INR 40 crore once production begins from the end of Q3 and the start of Q4 onward. And KTMPL, it depends on this ramp-up, since our washery — by the way, I just wanted to mention that construction on our washery has begun. Soil testing is underway. So I think right now it's only a temporary, momentary issue. But I think SAIL has given us their word that they'll free up some washing capacity for us. But mainly because of Q1, we couldn't do anything. We could only manage INR 14 crore. We expect a revenue dip in Tasra, the SAIL mine, to the tune of INR 100 crore, so against a projection of INR 250 crore, we'll do about INR 150 to 170 crore based on this ramp-up schedule that we're discussing with SAIL.

Anupam Gupta

analyst
#72

Got it. Okay. And a final question regarding your order inflows. So obviously the overall picture is quite clear. But take BHEL, for instance—when do you expect the tendering to actually begin, and when will you be in a position to book some orders from BHEL, considering they already carry such a large order book?

S. K. Ramayya

executive
#73

So they've begun the tendering process for Lara in Gadarwara. And with Talcher, they've already picked up some jobs there. Then they need to get going on the work, since all of this follows roughly a 42-month schedule. The ordering has to be wrapped up within the first year — only 5 to 15 months. After that, Yamunanagar is also going to come up. And Kodarma has only come up recently. That one will take another five to six months. So now is when BHEL needs to speed up order booking, because in these mechanical orders, perhaps what happens is they first have to concentrate on civil engineering. They might be working on the engineering side. Once the engineering is finalized, civil comes up, and after that the mechanical comes up. That's the sequence. But we expect things to move quite a bit faster in the second, third, and fourth quarters. And of course, most of this order booking has to be completed over the next 12 to 15 months.

Anupam Gupta

analyst
#74

Alright, understood. One final question, circling back to mining going forward. Let's assume this year, clearly, there's a mess because SAIL isn't taking the offtake. But does that affect what you can deliver next year in terms of run rate, or what they're able to take?

Rohit Sajja

executive
#75

No, Anupam, I really don’t see any effect from this in the coming year. There won’t be much of a knock-on effect, since we’ll keep pressing them to take additional capacity — at a minimum the contracted capacity — until we get to the PRC, peak rated capacity. So I don’t expect any cascading problems from this into next year.

Anupam Gupta

analyst
#76

Sure. Okay, and one final ask. The order book you disclose in the presentation — it would be helpful if you reported it at quarter-end and mid-quarter, since otherwise comparing becomes really difficult. So give us a figure as of the end of June, the end of September, the end of December, instead of a 12th August number, because that makes comparison impossible.

Nani Aravind

executive
#77

Yes. Since we’re providing the break-up for both versions, we’ll include it regardless and stick with the same approach.

Rohit Sajja

executive
#78

I believe Q1, Q2, and Q3 will be included in that. For June, a 12th August date has already been provided as well.

Anupam Gupta

analyst
#79

Alright, that’s fine. Thanks.

Rohit Sajja

executive
#80

Appreciate it.

Moderator

operator
#81

Thanks. We’ll take the next question from Ketan Jain at Avendus Spark. Go right ahead.

Ketan Jain

analyst
#82

Thanks. Hello sir, apologies if this repeats an earlier question. Could you tell us what order inflow guidance you're giving for FY25, expressed in rupees crores?

Nani Aravind

executive
#83

The figure we're projecting is INR 11,000 crores.

Ketan Jain

analyst
#84

Could you break that number down by segment at all, sir?

S. K. Ramayya

executive
#85

Yes. If we look at it segment by segment, maybe the sizable orders will arrive — in oil and gas, we'll execute another INR 1,500 crores of opportunities around Panki today. After that, the ETC business and the fuel business will form the next lineup for this one, and naturally, larger orders ought to be anticipated depending on how things unfold, as Rohit has described regarding the power plant activity, since plenty of opportunity exists there, and with so many territories and areas available that can be tendered in a manner that should let us secure something there. That is something we should reasonably achieve, and then the usual non-power sector and whatever we are placing on the mining side, the mineral side, and then how the water system projects should also be.

Ketan Jain

analyst
#86

Got it, sir. You also said the bidding pipeline sits at roughly INR 75,000 crores, largely in the power sector and O&M. So if you could split that bidding pipeline across power, O&M and mining, what does the exact pipeline come to?

S. K. Ramayya

executive
#87

I believe those figures are reflected there. I believe roughly INR 40,000 to 45,000 crores goes to infrastructure and railways. Then the remaining segments will appear under the ETC business at around INR 12,000 to 15,000 crores. After that comes the non-power sector along with the O&M side and water. And water is included there as well.

Ketan Jain

analyst
#88

And for power, sir — for power, what would that figure be?

S. K. Ramayya

executive
#89

Power, we see opportunities in the range of INR 12 to 15,000 crores.

Ketan Jain

analyst
#90

And that covers O&M too, correct?

S. K. Ramayya

executive
#91

Power ONM. Okay, so O&M stands apart. What I'm trying to get at is the civil and ETC business.

Ketan Jain

analyst
#92

Yes, sir. Got it. Sir, what’s the O&M for power?

S. K. Ramayya

executive
#93

Sorry, could you repeat that?

Ketan Jain

analyst
#94

Opportunity.

Nani Aravind

executive
#95

Could you talk about what you're seeing in terms of opportunity in power O&M?

Rohit Sajja

executive
#96

Operations and maintenance comes to roughly INR 1,500 crores. That INR 1,500 crores is domestic, and once you include overseas, the figure lands at about INR 2,000 crores, sir. Somewhere between INR 2,000 and 2,200 crores.

Ketan Jain

analyst
#97

Got it, thank you, sir. That’s all.

Rohit Sajja

executive
#98

Thanks.

Moderator

operator
#99

Thank you. A quick reminder for everyone on the line: you can hit star and one to pose a question. Ladies and gentlemen, you can hit star and one to pose a question. Since nothing further has come in, I'd like at this point to pass the conference to Ms. Natasha Jain of Nirmal Bang Equities for her closing remarks.

Natasha Jain

analyst
#100

Thanks. If management has any closing remarks, I’d ask that they share them now.

S. K. Ramayya

executive
#101

Yes. There's one development we may need to bring up to date. I believe we've covered all the background and everything. Just the green hydrogen initiative—we're also showing interest there. There's a national green hydrogen policy targeting five million tons by the end of this decade. It envisions an investment of nearly INR eight lakh crores, covering both the hardware side and the development side of these projects and so on. Tenders are already coming in thick and fast for boosting green hydrogen capacity—each plant going from 10,000 tons per annum to, say, I think, 40,000 to 50,000 tons. On that front, Rohit and I traveled to Portugal and Spain to look at the technology available in Europe. We're talking with a number of technology players, and we've also reviewed some working plans. That's one area the organization will perhaps focus on going forward as well. And yes, this will tie in nicely with our mechanical construction business and the related civil works too, since the contract structure and the way the work gets done are similar as far as execution goes. Naturally, the other side is pursuing development projects and, wherever it fits in commonly—for instance, this one, urban transport and rural transport, where we can power up the buses and all of the road transport corporations.

S. K. Ramayya

executive
#102

Also, with cement plants, there may be room to inject green hydrogen. Of course, we're looking into all of these things. It's at an early stage. But the plants that are coming up on an investment basis, and all of them for petrochemicals and fertilizers — many plants are coming up. So we're working on that. And this is more about the other developments, what we explained regarding power, non-power, and then MDO, etc.

Moderator

operator
#103

Appreciate it. Speaking for Nirmal Bang Equities, that brings this conference to a close. Thanks for being with us — you can go ahead and disconnect your lines at this point.

S. K. Ramayya

executive
#104

Thanks.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Power Mech Projects Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Power Mech Projects Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Power Mech Projects Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.