Ørsted A/S (ORSTED) Earnings Call Transcript & Summary

January 30, 2020

Nasdaq Copenhagen DK Utilities Independent Power and Renewable Electricity Producers earnings 91 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, and thank you for joining us for the Ørsted Annual and Q4 Report 2019. <<operator_script>> It's my pleasure today to introduce Henrik Poulsen, our CEO, along with Marianne Wiinholt, our CFO. You may now begin the meeting.

Henrik Poulsen

executive
#2

Thanks, and good afternoon, everyone, and welcome to this earnings call. 2019 proved to be a strong year for Ørsted, with strategic progress continuing, global expansion and strong financials. Our group EBITDA, excluding new partnerships, came in at DKK 17.5 billion, which is an increase of 17% on 2018. Earnings from offshore and onshore wind farms in operation rose by 30% to DKK 14.8 billion, driven by ramp-up of new offshore and onshore wind farms. 2019 was also positively impacted by higher earnings from our trading activities and the reversal of a provision related to the Elsam competition case. These positive developments were partly offset by the increase in provisions related to our LNG activities, higher project development costs and a temporarily negative effect from our gas at storage. Our return on capital employed for 2019 was 10.6%, so well in line with our target of an average group ROCE of 10% in the period '19 through '25. On the back of our strong financials, we will propose a dividend of DKK 10.5 per share to the Annual General Meeting, corresponding to an increase in dividends of 7.7%. We still intend to increase the annual dividend by a high single-digit percentage compared to the previous year's dividend up until 2025.

Henrik Poulsen

executive
#3

During 2019, Ørsted shares delivered a total shareholder return of 61%. Now, I'd like to walk you quickly through a few of the main things we achieved that year. Over in offshore, we brought the world's biggest offshore wind farm, Hornsea 1, into operation, and we reached final investment decision on Greater Changhua 1 & 2a — our first large-scale project in Taiwan. On top of that, we secured victories in 2 significant U.S. auctions over the summer, one in New Jersey and one in New York, which was a real breakthrough for our offshore wind business in the U.S. In Japan and Poland, we moved our market entry strategies forward along with potential partnerships involving leading local energy companies. Turning to onshore, we commissioned the Lockett onshore wind farm, and our construction pipeline got a further boost when we took final investment decision on 3 onshore wind farms as well as our first combined solar and storage project. Beyond those investments, we also reinforced the onshore business by acquiring Coronal Energy's development unit. Within Markets & Bioenergy, green heat and power generation hit 100% at the newly bioconverted Asnæs Power Station. We signed an agreement as well to divest our Danish power distribution residential customer and city light businesses to SEAS-NVE, the Danish utility, and lastly, we entered into an agreement to divest our liquefied natural gas activities.

Henrik Poulsen

executive
#4

Looking back at 2019, we feel very good about the strategic progress we made and the results we delivered, especially given the unprecedented level of public backing worldwide for the green transformation. Ørsted continues to hold a leading spot in the fast-growing market for green energy. Our commitment to the vision of a world powered entirely by green energy is as strong as it has ever been. If we move to Slide 4, I want to follow up on our guidance. With EBITDA for 2019 coming in at DKK 17.5 billion, we beat both what we expected at the start of the year and our latest guidance of DKK 16 billion to DKK 17 billion. Even with a net negative impact of DKK 800 million from divesting our LNG activities, we came in ahead of our most recent guidance. That outperformance came from stronger-than-anticipated results driven by robust offshore generation in December, our trading activities, a smaller negative effect than expected from our gas at storage, and lower realized costs throughout the company. Now on Slide 5, let's look at our investments. During 2019, investments in our construction projects rose significantly, and that will support the company's continued growth. Gross investments for the group totaled DKK 23.3 billion, a bit above our guided range.

Henrik Poulsen

executive
#5

Relative to 2018, our construction investments rose by DKK 8.4 billion, which underscores the substantial build-out taking place in offshore and onshore. Our target remains investments estimated at DKK 200 billion across the 2019 to 2025 period, and more than 95% of that is earmarked for growth in offshore and onshore renewables. Looking ahead, green capital will fully fund our investments, whether through operating cash flow generated by our renewable assets or through new debt issued under our green finance framework. Turning to Slide 6, here is an update on key strategic and operational progress in quarter 4. Ørsted carried strong momentum through the final quarter of 2019, with EBITDA of DKK 4.6 billion, which is DKK 500 million higher when adjusted for the Hornsea 1 farm-down in fourth quarter 2018. Higher generation from wind farms drove most of that increase, along with a positive effect from the accounting value of our gas at storage, as mentioned earlier, all stemming from rising gas prices in the fourth quarter. EBITDA from offshore and onshore wind farms in operation climbed 16% to DKK 4.9 billion in Q4 2019. As we keep building out renewable capacity, our green share of heat and power generation reached a record high of 90% in the fourth quarter, up from 83% in fourth quarter 2018.

Henrik Poulsen

executive
#6

Strategically, 2019 was full of activity, and the final quarter proved no different. Allow me to point out just a handful of the key developments. In late December, Hornsea 1 — the biggest offshore wind farm anywhere in the world — was commissioned by us. No other offshore wind farm has ever hit a capacity above 1 gigawatt; this one was the first, and it stands alone globally in being able to supply well over 1 million homes. That record-setting project, and the over 8,000 individuals who have labored offshore at the Hornsea 1 site, make us deeply proud. Also in December, a 100-megawatt corporate PPA was signed with Covestro. Under that agreement, Covestro will offtake green power for a 10-year period from Borkum Riffgrund 3, our planned 900-megawatt offshore wind farm, which is expected to reach full commissioning in 2025, subject to final investment decision. December also saw us sign a nonbinding term sheet on a transaction with PGE, the leading Polish energy company. Long-form documents are now being negotiated for the purchase of a 50% stake in 2 offshore wind projects whose combined capacity could reach up to 2.5 gigawatts. Throughout the past year, Lincoln Clean Energy has been integrated in a systematic way so that an effective operating model is ensured, one that capitalizes on the capabilities of both companies.

Henrik Poulsen

executive
#7

So to really mark how fully LCE has been folded into Ørsted, we chose to give Lincoln Clean Energy a new name — Ørsted Onshore — as of the end of 2019. LCE's founder, Declan Flanagan, is going to lead Ørsted Onshore, and he's been named Executive Vice President as well as a member of Ørsted's Executive Committee. Back in November, we reached final investment decision on Permian Energy Center, which combines solar PV with storage. That Texan project is going to consist of 420-megawatt of solar PV plus 40-megawatt of battery storage. Once Permian Energy Center is online in mid-2021, Ørsted will hold a U.S. portfolio of operating assets covering the entire spectrum of offshore and onshore renewable energy technologies. That lets us provide our competitors with a competitive and diversified portfolio of clean energy solutions. Starting in mid-December, every bit of heat and power coming from Asnæs Power Station has been produced by the new unit, which runs on sustainable biomass. Converting Asnæs Power Station to biomass represents a significant step toward our complete phaseout of coal, since this conversion is our sixth and final one. We've made the decision to shut down our last remaining coal-fired power plant in Esbjerg by the end of first quarter 2023, because we haven't been able to find a joint solution with the heat customers for a bioconversion project.

Henrik Poulsen

executive
#8

Starting in 2020, every bit of our biomass derived from wood waste is going to be certified, versus 96% certified during 2019. Back in December, we reached an agreement to sell off our LNG business to Glencore — a move aimed at cutting our long-term involvement in the gas supply chain, and also because achieving further financial gains would demand extra long-term commitments. Closing of that transaction is anticipated in summer 2020. During November, we raised TWD 12 billion, equivalent to DKK 2.7 billion, by issuing green senior bonds at appealing rates in order to fund the Changhua 1 & 2a project. Those NTD bonds additionally assist in reducing currency risk for our projects. This deal represents the first green entity bond ever issued in Taiwan by a foreign corporate, and it highlights our robust long-term dedication to growing offshore wind there. Also in November, we issued subordinated green hybrid capital securities totaling EUR 600 million, carrying a fixed coupon through December 2027 at 1.75%. At the same time, we redeemed EUR 524 million of the existing EUR 600 million, 3% hybrid capital securities that had been issued back in 2015. Now let's move to Slide 7. The planet confronts a climate emergency, and researchers have shown that global warming must be capped at 1.5 degree so as to restrict the harshest adverse consequences of climate change.

Henrik Poulsen

executive
#9

Crossing that limit is apt to set off grave, possibly permanent harm to ecosystems worldwide. Keeping global warming to 1.5 degrees means cutting worldwide carbon emissions in half by 2030 and bringing emissions down to net 0 by 2050. We had aimed for a 98% emissions reduction by 2025, yet our goal now is net 0 emissions across our own operations by 2025, along with carbon neutrality for our full total carbon footprint by 2040. Ørsted is expected to become the first large energy firm to achieve carbon neutrality under the so-called scope 1 and 2 emissions, which take in our own operations. The main steps we are taking to hit carbon neutrality by 2025 include building out 20 gigawatts of onshore and offshore renewable capacity; doing away with coal entirely in 2023; pushing fossil fuels out of our operations, which includes our pledge of 100% electric vehicles by 2025. On top of that, we have started a program enlisting our suppliers to decarbonize how components and vessel services tied to our offshore wind business are procured. And should it be necessary, we will offset whatever minor residual emissions remain using certified carbon removal projects. Our capacity to expand the business considerably while cutting our carbon emissions by a large margin has earned recognition around the world.

Henrik Poulsen

executive
#10

And in Davos last week, we became the first energy company ever to rank first on Corporate Knights' index of the Global 100 most sustainable corporations worldwide. That recognition makes us proud, and it pushes us to keep up our work deploying green energy at scale and to help drive the deep transformation of the energy system that's needed so the planet stays livable for generations to come. If you turn to Slide 8, I'll update you on our main offshore construction projects. As I said earlier, Hornsea 1 was commissioned in late December, on time and under budget. That 1,218-megawatt offshore wind farm is the 26th one we have in operation, which lifts our installed offshore wind capacity to 6.8 gigawatt. At Borssele 1 & 2 in the Netherlands, offshore construction has begun as planned, and 13 monopiles out of 94 are now in place. Come April, installation of the Siemens Gamesa 8-megawatt wind turbines will get underway. We now expect that 752-megawatt offshore wind farm to be finished by the end of Q4 2020. By that point it will be the biggest offshore wind farm in the Netherlands, capable of supplying renewable power to roughly 1 million households.

Henrik Poulsen

executive
#11

The rest of our offshore wind farms that are still being built — Hornsea 2, Greater Changhua 1 & 2a, and the Virginia EPC demo project — are all progressing nicely and on schedule. Now if you go to Slide 9, we'll look at the onshore projects, plus bioenergy and power distribution construction. On the onshore side, things continue to move along well. Sage Draw, Willow Creek, Plum Creek, and Permian Energy Center are all on track for completion in 2020 and 2021. On bioenergy, the Asnæs Power Station bioconversion — which I mentioned earlier — is finished, and the plant now runs on certified sustainable wood chips, giving consumers green heat and power. Because of recent upgrades at our Renescience facility in the U.K., we couldn't commission the plant in 2019 the way we'd hoped. That said, we've confirmed the core enzymatic sorting process performs as expected. So the mechanical sorting process is still the main challenge. We're still optimistic about getting the plant fully operational this year, but we've booked an impairment charge on the asset, reflecting a prudent view of the project. Let's move to Slides 10, 11, and 12 for a look at the latest market developments across the various offshore wind regions.

Henrik Poulsen

executive
#12

Looking ahead to 2020, we're tracking 3 auctions along the U.S. East Coast. Maryland is expected to hold its second auction during the first half of the year, with a capacity of at least 400 megawatt. Then in the second half of the year, New Jersey and New York are both expected to run their second auctions — 1,200 megawatt in New Jersey and a minimum of 1,000 megawatt in New York. Going back to June, Governor Ned Lamont of Connecticut signed legislation approving the procurement of an additional 2 gigawatt of offshore capacity. Following the recent award of 800 megawatt, Connecticut still has another 1,200 megawatt remaining that's available for future solicitations. In November, New Jersey Governor Phil Murphy signed an executive order targeting 7.5 gigawatt of offshore wind by 2035, which more than doubles the state's prior 2030 target of 3.5 gigawatt. Only a few days ago, Governor Murphy issued an energy master plan outlining how New Jersey can reach 100% clean energy by 2050, and offshore wind sits at the center of that plan. Earlier this year, Rhode Island Governor Gina Raimondo signed an executive order that makes Rhode Island the first U.S. state to be 100% powered by renewable energy by the end of this decade.

Henrik Poulsen

executive
#13

Offshore wind is going to be a key component in decarbonizing Rhode Island's energy system. We commend the ambitious goals that several governors along the U.S. East Coast have put forward. Bold commitment and leadership of this kind are what we need to counter the threat posed by climate change. As part of our push to establish an offshore wind industry supply chain in the U.S., we announced not long ago that our innovation hub in Providence, Rhode Island, is now open. The hub's purpose will be to find faster ways to identify and, where appropriate, finance enterprises tied to offshore wind, with an emphasis on next-generation technology and innovation. As a key part of this process, the innovation hub will draw on Rhode Island's existing innovation ecosystem. On December 20 last year, President Trump signed into law an extension of the federal tax credits. The law extends the investment tax credit by 1 calendar year and raises the value year-over-year from 12% to 18% for qualifying investments made in 2020. In a similar way, the production tax credit was extended by 1 year, with an increase in value from 40% to 60%. We have begun exploring those options, but we'll need a bit more time to determine the potential value of the tax credit extension.

Henrik Poulsen

executive
#14

Offshore wind has clearly been gaining fast support in the U.S., with 7 states along the U.S. East Coast now committed to installing over 25 gigawatts of offshore wind capacity in total by 2035. Right now, the Bureau of Ocean Energy Management is carrying out an analysis of the cumulative impacts of building out U.S. offshore wind projects. The findings from that study will then be incorporated into the permitting template for offshore wind projects in the U.S. We completely back a thorough, holistic approach to how offshore wind affects other stakeholders, including fishing communities and local residents. We've already responded to stakeholder feedback and concerns in our construction and operation plan applications, among other things by proposing a 1 by 1 nautical mile grid to accommodate shipping, coast guard and fishing interests. That said, the analysis was announced after our projects were awarded and was, therefore, unknown when we calculated our project time lines. And it's clear that some delay has occurred in offshore wind permitting since the cumulative analysis was announced as part of the Vineyard Wind permitting process. We won't have a complete picture of the impact until BOEM concludes their analysis.

Henrik Poulsen

executive
#15

We can’t rule out the possibility of delays, but we’ll need to wait for BOEM to set out a road map for when projects can expect to receive construction and operations plan approvals. Naturally, we will examine every option to offset any potential delays by using the flexibility available to us in our PPAs and in our OREC agreements to accommodate changes in time lines. We’re still very enthusiastic about our U.S. project portfolio and the growth potential in U.S. offshore wind, and we look forward to giving a full update on our U.S. build-out at our Capital Markets Day in June. Moving to Slide 11 and recent market developments in the U.K. and Continental Europe. In December, the U.K. government confirmed a target of 40-gigawatt offshore wind by 2030. That new target amends the previous target of 30 gigawatt by 2030 in an effort to reach net 0 emissions by 2050. The application for our Hornsea 3 project is currently being determined, with a consent decision expected during second quarter this year. The Crown Estate launched the fourth leasing round, opening up the potential for at least 7 gigawatt of new seabed rights for offshore wind developments in England, Wales and Northern Ireland.

Henrik Poulsen

executive
#16

The tender process got underway in October of last year and is set to continue through autumn of this year. Those new seabed rights might be granted as early as 2021, after which developers would move on to pursue planning consent for their own projects via the statutory planning process. Turning to the Netherlands, where the deadline for bids in the upcoming tender of up to 760 megawatt for Holland Coast North has been pushed back by 2 weeks, to April 30 of this year. And lastly, Poland's Ministry of State Assets has released draft legislation aimed at promoting offshore wind power, with the goal of awarding 9.6 gigawatt of capacity in the Baltic Sea by 2027 on the basis of 25-year CfDs. Under our CfD system, with a fixed price set by the government, Poland intends to award contracts for the first 4.6 gigawatt from predeveloped projects by the end of 2022. The rest of the capacity is slated to be tendered across at least 2 competitive CfD auctions by 2027. We're really enthusiastic about the long-term build-out of offshore wind in Poland, and about its potential to support local decarbonization and economic activity. Moving to Slide 12 and Asia Pacific. At the inauguration of the second phase of our partly-owned 128-megawatt Formosa 1 offshore wind farm in Taiwan, President Tsai set out Taiwan's ambition to add a further 10 gigawatt of offshore wind capacity between 2026 and 2035.

Henrik Poulsen

executive
#17

The framework for Taiwan's third auction round is expected to be announced during second quarter this year. The capacity and exact timing for the auction is still unknown. In Japan, we continue to progress our partnership discussions with TEPCO. The preliminary selection for the second round of promotional zones has commenced. In the first round, 11 areas with a capacity of approximately 7 gigawatt were designated as potentially suitable for development of offshore wind. 4 of these 11 areas, including the Choshi area have been selected as prospective areas and will work towards qualification during first quarter this year. The Japanese Ministry of Economy, Trade and Industry is targeting a first auction to take place in the second half of this year. Turning to Slide 13. This slide provides an overview of the many expected offshore wind auctions and tenders in 2020 and 2021, highlighting the accelerating global demand for offshore wind. We have, during 2019, seen many governments raise their build-out targets, and we will, during the 2020s, see a significant increase in annual awarded capacity. After more than 10 gigawatt being awarded for the first time ever in 2019, we will likely see a step down in 2020 before 2021 potentially and expectedly, reaching a new all-time high in terms of total global awards.

Henrik Poulsen

executive
#18

Looking ahead through the rest of the 2020s, we'd anticipate staying on course toward a range of 10 to 15 gigawatt, and then, as we get into the latter part of the decade, we'd expect the market to keep going and exceed 15 gigawatt in yearly global awards. That wraps up offshore market development. Let's move to Slide 14 and how our U.S. onshore business is progressing. Over the last year we've achieved a great deal, establishing ourselves as a developer across multiple states with a robust portfolio of projects that are operating, under construction, and under development. In November, we reached final investment decision on Permian Energy Center, our first large-scale solar wind farm, which will combine solar PV and storage. With that FID, our total installed and decided onshore capacity is now 2.1 gigawatt. Our strategic ambition is to establish a leadership position in the North American onshore renewables market. Since we entered the U.S. onshore market, we have doubled our operating portfolio, and by 2021 it will more than double once more. We keep seeing solid risk return investment opportunities in the market. This encouraging development lets us set a target of 5 gigawatt of installed onshore capacity by 2025.

Henrik Poulsen

executive
#19

Even though onshore wind will keep making up most of our portfolio, we'll also aim to expand our solar PV capacity, which lets us widen our growth platform and capture the advantages of diversification along with integrated customer offerings. With that said, I'll now pass the word over to Marianne.

Marianne Wiinholt

executive
#20

Yes. Thanks, Henrik, and good afternoon from me as well. We'll begin on Slide 15, where I'll walk through the group's financials for Q4 '19. During Q4 '19, we achieved an EBITDA of DKK 4.6 billion, adjusted for earnings from new partnerships in Q4 '18 of DKK 15.1 billion. That EBITDA came in DKK 0.5 billion, or 11%, above Q4 '18. In offshore, we delivered stronger earnings from our operating wind farms, which rose by 13% thanks to generation ramping up at Hornsea 1 and Borkum Riffgrund 2. Earnings from existing partnerships came in lower. Onshore earnings were DKK 0.1 billion higher than Q4 '18, lifted by greater generation from new wind farms in operation. And LNG EBITDA was DKK 0.6 billion below Q4 '18 and included a negative impact of DKK 0.8 billion tied to the divestment of these activities. The remaining Markets & Bioenergy was DKK 0.8 billion above Q4 '18. That increase came from a positive effect on the accounting value of our gas at storages, as gas prices rose in Q4 '19 versus falling gas prices in Q4 '18. Implementing IFRS 16 added DKK 171 million in Q4 '19, with roughly half of that in offshore.

Marianne Wiinholt

executive
#21

Net profit came to DKK 0.9 billion, which is a drop of DKK 14.3 billion from Q4 '18. If you adjust for the Hornsea 1 farm-down gain, net profit was DKK 0.4 billion lower, and that's because of impairment losses of DKK 0.6 billion tied to our Renescience plant in the U.K. as well as our 20-megawatt battery storage Carnegie Road in the U.K. Free cash flow from continuing operations was negative DKK 3.6 billion. Cash flow from operating activities in Q4 '19 reached DKK 4.8 billion, largely driven by EBITDA, which was partly offset by funds tied up in working capital, mostly from higher receivables at year-end. Gross investments for the quarter came to DKK 8.8 billion, mainly tied to construction of our offshore wind farms, Hornsea 2, Greater Changhua 1 & 2a and Borssele 1 & 2, as well as onshore projects, Sage Draw, Plum Creek and Permian Energy Center. Divestment cash flow was DKK 0.4 billion. Turning then to Slide 16, and our net interest-bearing debt and financial ratios. At the end of Q4 '19, our net debt stood at DKK 17.2 billion. The DKK 5.1 billion increase in the quarter was primarily tied to the negative cash flow I just described, as well as a negative DKK 1.1 billion impact from exchange rate adjustments, mainly related to the strengthened sterling rate.

Marianne Wiinholt

executive
#22

Our key credit metric, FFO to adjusted net debt, was 31%, which is in line with where we want it to be. Return on capital employed reached 10.6%, and the decline versus '18 was primarily driven by the farm-down gain from Hornsea 1. That return was roughly at our goal of an average return on capital employed of about 10% for the group across the '19 to '25 period. Now let's turn to Slide '17 and go through the results of the business units. Back in June, we made the decision to combine the business units Customer Solutions and Bioenergy into one new unit called Markets & Bioenergy. Since we operate the business with end-to-end value chain thinking, we also determined that every activity and all earnings tied to offshore and onshore would be reported within these segments, even when the day-to-day work is carried out for the group inside Markets & Bioenergy. So earnings from trading linked to hedging our power exposures, along with power portfolio optimization activities connected to offshore and onshore, now show up in these business units. For the full year '19, EBITDA of DKK 725 million was moved to offshore, and EBITDA of minus DKK 18 million was moved to onshore.

Marianne Wiinholt

executive
#23

During 2018, DKK 237 million went to offshore operations. Offshore, generation reached 3.9 terawatt hours — up 20% versus Q4 '18 — mainly because Hornsea 1 and Borkum Riffgrund 2 ramped up, adding 0.6 terawatt hours combined in the quarter. Average wind speeds in Q4 came to 10 meter per second, a bit under Q4 '18 and below the normal level for the quarter. Across full year '19, wind speeds averaged 9.2 meter per second, matching the normal speeds for the portfolio we hold now. Quarterly availability was 93%, matching Q4 of last year. Full-year availability, also 93%, took a hit from unusually heavy grid curtailments and outages. Once those effects are adjusted for, availability reached 96% in 2019. Quarterly EBITDA came in at DKK 4 billion, DKK 14.8 billion below Q4 '18, including new partnerships, and DKK 0.3 billion higher when excluded. Earnings from sites O&M and PPA rose 13%, driven by ramp-up — again, Hornsea 1 and Borkum Riffgrund 2 — plus solid results from trading activities tied to hedging of our U.K.

Marianne Wiinholt

executive
#24

Energy-related exposures likewise played a part in the increase in earnings. The cause of their stronger growth in power generation relative to site EBITDA is that at present just 1/3 of Hornsea 1 output is covered by the CfD, with the remainder sold at market prices. As we have said before, the other 2/3 will be covered by CfD as of 31st of March 2020 and 31st of March 2021, respectively. Lastly, project development costs came to DKK 0.6 billion, consistent with Q4 '18, and were mostly tied to our development work in the U.S. Cash flow was negative DKK 1.7 billion in Q4 '19. EBITDA was partly offset by funds locked up in work in progress from building the transmission asset at Hornsea 2. And during Q4 '19 we invested DKK 5.4 billion in constructing Hornsea 2, Greater Changhua 1 & 2a and Borssele 1 & 2. Moving on to Slide 18 and onshore. In onshore, power generation reached 1 terawatt hours in Q4 '19, which is 0.4 terawatt hours more than Q4 '18. That gain was driven by ramped-up generation from Tahoka and Lockett plus better availability.

Marianne Wiinholt

executive
#25

Availability was extremely strong, at 98%. For the quarter, EBITDA reached DKK 0.2 billion, which is DKK 0.1 billion higher. Site earnings rose thanks to greater generation, and production tax credits contributed another DKK 0.2 billion. Project development costs partly offset that. Free cash flow for the quarter was negative DKK 2.8 billion. Gross investments of DKK 0.9 billion (sic) DKK 2.9 billion tied to Sage Draw, Plum Creek and Permian Energy Center offset the EBITDA. Moving to Slide 19, I'll walk through the results in Markets & Bioenergy. EBITDA was DKK 0.5 billion, DKK 0.2 billion above Q4 '18. Gas Markets & Infrastructure earnings went up because of a positive accounting value effect on our gas storages, driven by rising gas prices versus the opposite trend in Q4 '18. On top of that, solid optimization performance on our gas assets gave results a positive lift. EBITDA from CHP plants and distribution, B2C and city lights matched Q4 '18. Our LNG divestment weighed negatively by DKK 0.8 billion in 2019, since the agreement calls for a bigger payment than we had provisioned for.

Marianne Wiinholt

executive
#26

That was partially counterbalanced by solid results tied to optimizing LNG deliveries and by reversing unfavorable timing impacts carried over from earlier periods. Overall, LNG contributed DKK 552 million, a more negative figure in Q4 '19 than in Q4 '18. Free cash flow for Q4 '19 came in at negative DKK 0.7 billion. EBITDA was offset by increased receivables alongside reduced payables, plus investments of DKK 0.5 billion, mainly tied to Asnæs bioconversion and the power distribution network. Moving to Slide 20. Through 2019, results from our trading activities linked to hedging U.K. energy exposures have beaten expectations. I'd like to take a deep dive into how this unfolded. As I noted earlier, offshore saw an exceptionally large favorable effect from power trading tied to power hedging and optimization, amounting to DKK 725 million in 2019. Back in 2018, power trading added DKK 237 million. Our market trading function actively handles market risk across our entire energy portfolio via commodity trading and other risk management efforts. More precisely, market trading hedges expand power exposures into traded markets so cash flow becomes more stable. Since certain market exposures of ours lack much liquidity, market trading can perform what's known as proxy hedging, which under tight mandates lets our traders lower market risk by taking advantage of correlations linking our underlying less liquid exposures with instruments that trade more liquidly.

Marianne Wiinholt

executive
#27

When it comes to how we hedge power in the U.K., one piece is a time spread strategy: a portion of our longer-dated power exposure gets hedged through rolling shorter-dated hedge instruments. Then there's the spark spread strategy, where we similarly hedge part of that longer-dated U.K. power exposure by selling gas, taking advantage of the fact that U.K. power prices are to a large extent driven by gas prices. Because liquidity is higher and costs are lower, both trading strategies are commonly used to hedge our exposures. As I mentioned, results from our market trading activity were extraordinarily high in '19, and the main reason is that both of those hedging strategies for U.K. power exposure proved very favorable for us. Over the course of '19, U.K. power forward prices fell at the front and rose at the far end of the forward curve, which produced gains on the time spread hedges for U.K. wind farms. Simultaneously, U.K. power forward prices rose relative to the corresponding gas prices, which produced a gain on our spark spread strategy. I want to stress that 2019 was special: we saw an unusually long stretch in which price development at the short end and the long end of the power curve, along with development between the gas and power curves, both moved in our favor, which produced higher-than-expected profits.

Marianne Wiinholt

executive
#28

Risk management keeps a constant watch over our market trading operations, and the risk governance framework there covers limits on value at risk along with stress scenarios at net open positions. That brings the group's financials for Q4 '19 to a close. Let's move on to Slide 21, then, and the outlook for 2020. For 2020, we expect EBITDA — leaving out earnings from new partnership agreements — to land between DKK 15 billion and 17 -- DKK 16 billion, versus DKK 17.5 billion in 2019. On this slide, before I get into more detail on the business units guidance on the next slide, I'll point out the main developments relative to '19. Just as in earlier years, existing offshore partnership agreements are the only ones our guidance covers. No new partnership agreements were signed in 2019, yet EBITDA from existing partnerships came to DKK 3.8 billion in '19. Looking at 2020, EBITDA from existing partnerships should be very limited. During 2019, we signed the agreement to divest our Danish power distribution, residential customer and city light businesses. That transaction is expected to close in the first half of 2020, and earnings for the first half of 2020 are included in our EBITDA guidance. Furthermore, our '19 results included a positive effect from the provision reversal tied to the Elsam competition case, while altogether we incurred a loss of DKK 1 billion in our LNG business in 2019.

Marianne Wiinholt

executive
#29

When it comes to LNG, we'll reach breakeven during 2020. Taking these effects into account, comparable group EBITDA for 2019 lands at roughly DKK 13.7 billion, which means our guidance for 2020 implies underlying growth of somewhere between DKK 1.3 billion and DKK 2.3 billion relative to 2019 EBITDA — that's 9% to 17%. In Offshore, earnings should rise thanks to wind farms that are now in operation, with the driver being the ramp-up of generation during 2020 from Hornsea 1 and Borssele 1 & 2. On top of that, as I noted earlier, another 400 megawatt of capacity at Hornsea 1 starts receiving the CfD price as of 31st of March. And finally, we anticipate reduced costs on project development. Turning to onshore, we look for a positive effect versus '19 stemming from ramp-up generation at our wind farms. And in Markets & Bioenergy, once you adjust for the effects I just went through, earnings are set to decline because of the temporary shutdown of the Tyra gas field, and that will pull down earnings from the gas portfolio as well as from our offshore gas pipelines. Gross investments for 2020 should come in at DKK 30 billion to DKK 32 billion. This outlook mirrors a high activity level in offshore, with ongoing investments in Borssele 1 & 2, Hornsea 2, Greater Changhua 1 & 2a and our U.S.

Marianne Wiinholt

executive
#30

We also have activities and onshore investments in building Plum Creek, Willow Creek, Sage Draw, and Permian Energy Center. Let's move to Page 22, which gives a more detailed outlook for our business units. For our offshore division, EBITDA in 2020 is expected to come in below '19. Earnings from offshore wind farms in operation should rise thanks to ramp-up of generation at Hornsea 1, commissioned in December '19, and Borssele 1 & 2, which we expect to commission at the end of Q4 2020. We'll also see a positive effect from the additional 400 megawatt of Hornsea 1 capacity covered by CfD starting at the end of March. By contrast, we expect lower trading earnings, since we don't expect to repeat the very positive results from '19. As mentioned on the previous slide, earnings from the existing partnership are expected to go from DKK 3.8 billion in '19 to very limited in 2020. Expensed project development costs are expected to be lower in 2020 than in 2019. Turning to onshore, where EBITDA for 2020 is expected to increase, the earnings increase comes from a full year of production from Lockett, commissioned in July '19, as well as ramp-up of generation from new wind farms coming online in 2020, including Sage Draw expected in Q1 2020 and Plum Creek and Willow Creek, both expected in Q4 2020.

Marianne Wiinholt

executive
#31

And wrapping up with Markets & Bioenergy, we expect EBITDA to go down in 2020. Underlying earnings from our CHP plants should come in around the same level as '19, once you exclude the Elsam provision reversal. For Gas Markets & Infrastructure, earnings are projected to fall because of the temporary shutdown of Tyra, which runs from late '19 through 2022, and that reduces our earnings in the gas business. That said, we don't anticipate a repeat in 2020 of the negative effects from revaluation of our gas at storages. As I mentioned, earnings from LNG activities should breakeven in 2020. At the close of '19, provisions have been made for the expected loss on the divestments and the expected operating loss through to closing. So the loss from our LNG activities will therefore move from DKK 1 billion in 2019 to DKK 0 in 2020. For power distribution, residential customers, and city light businesses, earnings should be roughly half of the DKK 1.3 billion posted in '19, since we've only included earnings for the first half year. Slide 23 recaps the 2020 guidance I just walked through, along with our long-term financial estimates and policies, which match the update we gave in October 2019.

Marianne Wiinholt

executive
#32

That being the case, we'll move into the question-and-answer portion now. Operator, if you would, go ahead.

Operator

operator
#33

<<operator_script>> Kristian Johansen from Danske Bank has our first question.

Kristian Johansen

analyst
#34

I have two questions. First, Henrik, you mentioned the environmental impact assessment that BOEM is carrying out. Could you expand a little more on what effect that might have on the expected return for your U.S. projects? And then, at this stage, how much visibility do you have on that?

Henrik Poulsen

executive
#35

Honestly, Kristian, there's just no way for me to say anything about that today. We're still waiting on BOEM to make an announcement, and that will shed more light on what this does to our timelines. Like I mentioned before, we do have some room to maneuver within our PPAs and our OREC agreements, so we can essentially absorb timeline changes without incurring financial penalties of any sort. That said, there are clearly several other things in flux in our U.S. development portfolio right now, one of them being that we're working to clarify the potential tied to the extended tax credits. So with all these elements in motion, I wouldn't be in a position to provide an update today on the U.S. portfolio, beyond telling you that we continue to feel quite good about the development portfolio, and we also stay quite confident in our ability to extract the value from it that we're hoping for. Still, it will probably take a few more months to work through the whole portfolio along with the implications of the cumulative impact assessment and the tax credit extension. That's also the reason I mentioned that we're looking forward to providing a full update at the Capital Markets Day in June.

Henrik Poulsen

executive
#36

To be honest, that's likely the right time line, since it gives us the time we need to further mature the portfolio and then come back to you at that point with more visibility. But let me be clear: we have absolutely no reason to believe that we are looking into any significant value deterioration of any kind.

Kristian Johansen

analyst
#37

Alright, that's fine, thank you. My next question concerns your onshore operation and the 5-gigawatt goal for 2025. That extra 3 gigawatts would be added during the first half of the 2020s. How do you think returns on that portfolio will stack up against the 2-gigawatt you plan to build through 2021? And obviously, I'm particularly focused on what the declining production tax credit means for those considerations.

Henrik Poulsen

executive
#38

Obviously, we’ll need to offset that PTC reduction by lowering electricity costs and, over time, by realigning PPA pricing as well. We have some confidence that both of those mitigants can contribute. As a result, we still see meaningful value spreads in the projects we’re currently reviewing within our development pipeline. So overall, I’d say the Onshore division’s performance in 2019 has, if anything, positively surprised us. We continue to see very significant potential in the years ahead. So I’d say we’re looking at what, in our view, is a very meaningful and healthy growth opportunity toward 2025. I’m not going to start saying we had this kind of spread on the first 2-gigawatt and we expect that kind of spread on the next 3-gigawatt. Frankly speaking, we wouldn’t have the exact visibility to even start running those numbers, but I can only say that what we see today looks quite attractive.

Operator

operator
#39

And moving on, our next question is from Casper Blom, who is with ABG.

Casper Blom

analyst
#40

Let me begin with the area Marianne nearly closed on when discussing trading — which today sits within, among other things, the offshore business and a portion of sites. I get the sense that you believe you performed well there in '19. Could you offer any sort of guidance on what a normalized assumption would look like for a trading business of this kind going forward? Essentially, that way we can back out what was formerly the predictable piece of that division — namely, the earnings production coming from sites.

Marianne Wiinholt

executive
#41

I can't provide a specific figure, but I'd say that across the past 5 years we've witnessed large fluctuations, yet results in that area have never come in below roughly DKK 200 million annually. It will vary, though—some years will be very strong, and we'll likely have others that are less strong. What we'll do is give you visibility into the numbers, so you can distinguish the site earnings from the earnings generated by trading.

Casper Blom

analyst
#42

Much appreciated if that’s possible from here on as well. And second, on a possible farm down in Taiwan, you said before that it might take place either in 2020 or in 2021. Is there any update on when we could expect that to occur?

Henrik Poulsen

executive
#43

Things are moving forward precisely according to schedule. So all of it looks completely fine. Predicting the precise timing is hard. We'd stay hopeful that we might reach a signing at some point later in this year. Yet forecasting the period from signing to closing is tough, and that's clearly the point where it affects our books, purely because regulatory approvals come with a fairly unpredictable schedule. So, Casper, what I'm getting at in brief is that it might occur in late 2020, though there's also a reasonable chance it lands in 2021.

Casper Blom

analyst
#44

Alright. That one sounds like a coin flip, honestly. Then just lastly, from where I sit, you've divested quite a few things over the past 2 years, and what remains now is a very, very green business. Would you say there are any obvious candidates that could go within the next 2 years? Could it be the power plant, for instance — would you look to divest that and concentrate more on the genuinely green energy production side?

Henrik Poulsen

executive
#45

At the moment, I’d say our attention is simply on completing the sale of Radius B2C and city lights, plus now the LNG business as well, which is keeping us pretty occupied right now. We’re likewise working through selling a portion of our B2B sales business. So I’d say our plate is full. We currently have no intention of divesting the power plant division. It is delivering strong results. It has been entirely converted to sustainable biomass. So we don’t perceive any pressing need there. That therefore isn’t part of our plans.

Operator

operator
#46

And the next person to ask something is Deepa Venkateswaran from Bernstein.

Deepa Venkateswaran

analyst
#47

I’ve got a few questions. Let me begin with the financial ones for Marianne. Marianne, could you speak a bit about tax? I saw that the effective rate this year was 31%. What does that suggest for future years? Is it still around 20%, 22%? And the cash outflow on taxes was DKK 4.8 billion versus the charge of DKK 2.8 billion. So again, if you could clarify how much was one-off, or should we be modeling anything similar for the next few years? Then I have a few questions on the other market and growth. So for Poland, will the first auction just be administratively determined? And would there be competing projects, or is this more or less almost a done deal that PGE would get a project and hopefully, you would share? So any kind of insights on how the pricing might work or at least the mechanics? And I guess I also had a follow-up question on Virginia, which has now signed — which now has a target, and it seems like Dominion has been talking about building this 2.6 gigawatt project. I’m just wondering what the arrangement there might be, given it appears that Dominion is probably going to put this in their own rate base.

Deepa Venkateswaran

analyst
#48

So I guess I was just curious about what role you could play in this opportunity? That's everything I wanted to ask.

Henrik Poulsen

executive
#49

Virginia, would you like to kick us off?

Marianne Wiinholt

executive
#50

Yes. Let's start with the tax questions. Regarding the tax rate, yes, you're correct that it's above the roughly 22% we previously guided to. This impairment is one factor affecting the tax rate, since we aren't taking a tax deduction for it. There are also some other items that push the tax rate up this year. We don't expect that to continue going forward. In a way, it's more of a timing matter for '19. So going forward, we expect it to be around 22%. As for the higher current tax relative to the P&L tax, that's driven by Hornsea 1 — specifically the gain from Hornsea 1. The CA portion of the gain becomes taxable when we commission the plant. So the gain we realized in '18 flows into '19 taxable income. So that was — that's the difference.

Henrik Poulsen

executive
#51

Regarding Poland, Deepa, our understanding is that the first 4.6 gigawatt will be handed out through a process run by the government to certain projects that have already been developed quite far, so that offshore wind build-out ramps up fairly quickly. And naturally, the Baltica portfolio that we're talking about with PGE would be a candidate for that kind of initial allocation, though other projects currently being developed in Poland would also qualify for it. So saying there's any done deal would be going too far — that's definitely not the situation. Still, we'd view the Baltica portfolio as among the stronger contenders in a government-controlled allocation of that sort. On pricing, we have no visibility at this point. Our impression is that the Polish government will set a strike price. We've seen some early drafts of what the wider regulatory framework will look like, and it appears fairly standard and consistent with what we'd have seen in other developed markets. In Virginia, Dominion has decided to advance the 2.5 gigawatt project.

Henrik Poulsen

executive
#52

And as you correctly pointed out, once that gets moved into the rate base, it naturally places certain constraints on what kinds of collaboration they're able to set up with third parties. Our strategic dialogue with Dominion is still strong. On the pilot currently under construction this year, we continue to be solid partners. And we keep talking with Dominion about other partnership opportunities as well. But when it comes to the specific 2.5 gigawatt, it's simply too early for me to say whether there's a role for us or not — we'll just have to wait and see.

Operator

operator
#53

Peter Bisztyga from Bank of America has our next question.

Peter Bisztyga

analyst
#54

Thus, 2 questions from me. First, carrying on with the new-markets theme and Japan: could you tell us what you anticipate the auction terms will be? Will it be an auction based purely on price? Will it resemble what we saw in New Jersey, for instance, where the quality of a bid and the bidder forms part of that decision? And do you currently have any visibility on how many competitors you'll have? Then on guidance, your IR team very kindly sent around a consensus ahead of results, and your EBITDA guidance, I think, on a like-for-like basis for 2020 is DKK 15 billion, DKK 16 billion versus the consensus DKK 16.4 billion. That looks a little bit light, and presumably you know where the differences are. I was just wondering, is that in offshore, onshore or in new markets? And also on CapEx, similarly, you're guiding to DKK 30 billion to DKK 32 billion of gross investments next year, streaks in a DKK 26 billion, I think. I'm just wondering what the delta is there? Is that some of those cost pressures, for example, that you flagged on new U.S.

Peter Bisztyga

analyst
#55

On those projects? Or are you simply speeding those up, for instance with onshore wind? That's what I'd like to ask.

Henrik Poulsen

executive
#56

Apologies — could you say that last question again? I’m not certain I caught precisely what it was.

Peter Bisztyga

analyst
#57

The final question concerns your guidance for CapEx or growth investments in 2020. The range you're giving is DKK 30 billion to DKK 32 billion, while consensus sits near DKK 26 billion. That DKK 30 billion to DKK 32 billion marks a substantial step up from 2019, and I'm wondering how much of that gap relative to where the Street stands stems from cost pressures — in the U.S. business you flagged a few months back, for instance? Or how much simply reflects the fact that you're building more things at a faster pace?

Henrik Poulsen

executive
#58

Okay, okay, thanks. I'll begin with Japan and the CapEx question, and then Marianne will address EBITDA and the point where we diverged from consensus in the guidance. On Japan, the final framework for the auction hasn't been seen by us yet, and the auction's volume is still unknown to us. That said, some preliminary allocation frameworks were issued earlier by the Japanese government, in which price is going to be a key parameter, though a number of other qualitative criteria will also be applied — your experience and your track record in offshore wind, for instance. So a broader set of criteria, both quantitative and qualitative, will be applied in Japan. Exactly how competition will shape up there is something we have no full visibility on. It remains a market in development, with a lot of activity at the moment, but one where visibility is relatively limited regarding precisely who will be ready for an auction expected during the second half and who will have projects ready that allow them to bid. At present, our focus is on working with TEPCO to ensure the Choshi project gets qualified and stands ready for a potential auction later this year.

Henrik Poulsen

executive
#59

Regarding this year's CapEx guidance and how it differs from consensus, that comes entirely from higher activity levels. Cost pressure has nothing to do with it. I'd frame it as just a variance reflecting the fact that we're seeing greater progress across a wider set of construction projects, and keep in mind that we're now building offshore wind in 3 separate regions, while at the same time we have 3 onshore wind farms under construction plus a solar project. So this is a very large construction program. And if you return to the broader target of DKK 200 billion for the period from '19 through '25, the DKK 30 billion is roughly the run rate we ought to anticipate moving forward.

Marianne Wiinholt

executive
#60

Yes. Now, regarding your guidance and how we view the variance versus consensus — it sits in offshore. There's also a variance in onshore as well as Markets and Bioenergy, though those essentially offset each other. So the variance is in offshore.

Peter Bisztyga

analyst
#61

Okay, and if I could just ask a quick follow-up on that: is there anything specifically in offshore that’s maybe not quite as strong as we’d hoped?

Marianne Wiinholt

executive
#62

No, no. That's not how we see it, no. So really, it's difficult for us to determine what that deviation is tied to. But...

Henrik Poulsen

executive
#63

You have to keep in mind that, I mean, clearly we enjoyed a really robust '19 when it came to growth from the sites. And with the construction portfolio, everything is progressing as planned, and site EBITDA growth in 2020 is going to come from the ramp-up or full-year production at Hornsea 1 along with some late ramp-up at Borssele 1 & 2 and, naturally, from the Onshore division as well. And if you look at that 20% average growth target we set for 2017 through 2023, inevitably some years will see us a bit above 20%, and some years will see us a bit below 20%. It all traces back to the construction and ramp-up profile within our build-out portfolio, and that portfolio is moving forward entirely according to plan. So I think this is really just about getting the timelines of the various construction efforts aligned and turning that into a growth target for 2020.

Peter Bisztyga

analyst
#64

So it's more about phasing effects than something we should be worried about?

Henrik Poulsen

executive
#65

Getting them exactly right on a year-over-year basis could prove difficult. You'll see swings around that 20% growth rate—that much is clear. Still, when it comes to that 20% average growth rate over the long term, we remain very comfortable with it.

Operator

operator
#66

We’ll now take our following question from Elchin Mammadov, who is with Bloomberg Intelligence.

Elchin Mammadov

analyst
#67

First off, on transmission: over here in Britain, we're noticing a few problems with the Western link. Output from some wind generation has been curtailed. In your view, will transmission pose a problem for the wider wind industry generally, or does this come down to that one specific project? My second question concerns the trading business. You've enjoyed a strong year, though so did plenty of other utilities, oil majors, and commodity trading houses. In the news, they usually attribute it mainly to volatility. It's early days, I know, but we've already witnessed a fair amount of volatility at the beginning of this year. So if that continues, ought we to anticipate another robust year for your trading profits, or not? And my last question is about the -- your bond: are you noticing any meaningful spread between green finance and nongreen bonds? Yes, that's everything from me.

Henrik Poulsen

executive
#68

When it comes to transmission, the curtailment we saw in the U.K. was a very specific situation that followed an outage, and that outage was a very rare event. So that is not something that would extrapolate in any way. That being said, transmission is clearly a key matter in every market right now. There are many markets where investment is needed in transmission and interconnection, and it's one of the key things to develop across all of our projects. So in the U.K., in other European markets, and at the moment in the U.S. as well, securing the right interconnection and the right transmission capacity will always stay a critical component of any project. But the issue in the U.K., in particular, was what we regard as an anomaly.

Marianne Wiinholt

executive
#69

Yes. Then, regarding your trading question: I believe it's worth stressing that, in a sense, we don't run an administration house. Our trading exists to lower risk, and we carry it out inside very narrow wire mandates. So compared with some of those other players, naturally, volatility works in our favor, but what helped us in 2019 wasn't so much volatility — it was the hedging strategies that ended up delivering positive results. So I just wanted to make that point. Then, the next question about the bond: yes — previously, we truly saw no gap between green and non-green bonds. At this point, a marginal difference is beginning to appear, though it isn't big.

Operator

operator
#70

And moving on, our next question is from Alberto Gandolfi with Goldman Sachs.

Alberto Gandolfi

analyst
#71

I’ve got 3 questions on my end. The first 2 are somewhat broader in scope, and the third relates more directly to results. So, for the first one: could you please — I’ve seen some of the interviews you sent out regarding achieving net 0 carbon emissions, and the European Commission has been discussing a green deal, a green new deal. The EU Energy strategy, published last year, already referred to an upper end for offshore wind in Europe of 450 gigawatts by 2050, and that wasn’t a net 0 paper. So my question for you is: with a specific module due to come out this year in Europe, how much do you think the European market alone could represent by then? And perhaps you can shed some light on the basically 100% clean target you mentioned earlier today that we are likely to see, for instance, in — I don’t know — your Rhode Island or New Jersey. From a percentage perspective, how much of the total power generation mix could be offshore? The second question is, can you maybe elaborate a little more on your ability to keep pace with a rising number of auctions in the global market.

Alberto Gandolfi

analyst
#72

If we're shifting to 20, 25 gig, could we see you taking part in all of those, perhaps outside China? So what's your capacity to scale up your business? And what sort of ideal market share are you contemplating over the medium run? I mean, I don't know, is it 10%, is it 5%, is it 20%? Do you believe you can lose 9 megawatts to win one, or do you need to lose 3 or 4 to win one? I don't know whether you had any thoughts on that? And the final question is a bit about your offshore deviation, shall we say, for your guidance. Do you have a sense of going a little bit maybe deeper, do you have a sense of how much of that could be the normalization of trading vis-à-vis some estimates not including an escalator for the CfD and Hornsea 1. That's quite relevant. And I think what I'm trying to understand is how much of this deviation, let's say, is a timing issue for 2020 and '21? And when Hornsea and CfD is fully in place, suddenly, actually, you don't see really much of an offshore deviation in consensus?

Henrik Poulsen

executive
#73

Thank you, Alberto. Regarding the European green deal — the new green deal — forecasting is clearly quite hard. The ambition is the correct one. It is a bold ambition. And it represents a significant opportunity for Europe to take the global lead in this field. This is among the industrial sectors where Europe actually already stands as a worldwide technology leader. And I genuinely think the commission has got it right in setting such a bold goal of achieving net 0 by 2050. In the end, that EUR 1 trillion deal has to translate into action all the way down through the individual countries, and every country must chart a route toward net 0 and toward compliance with the Paris agreement. And a lot of countries across Europe are still not on a trajectory where expanding green capacity and phasing out coal would put them on the path to hitting the Paris targets. So in the end, you will need to see all of that pushing national build-out targets higher. We observe this occurring incrementally. But I do think additional progress is coming across the next 2 years. Whether that ends up reaching a 450-gigawatt potential by 2050, or perhaps beyond that.

Henrik Poulsen

executive
#74

Once more, forecasting today is simply not possible, so I won't even try to do so. Still, nobody can question that Europe holds enormous potential where offshore wind is concerned. And in my view, people now understand that a technology which was regarded as niche renewable just 2 or 3 years back has become a key element of the coming European energy mix, something the IEA also referenced only a couple of months ago. We therefore anticipate that Europe's offshore wind construction will speed up over the 2020s. As I mentioned before, throughout the 2020s we'll be operating at a global level of 10 to 15 gigawatt annually, yet we will soon begin shifting into a 15 to 20 gigawatt per year range. Should things speed up further, we might even need to raise those targets as we progress deeper into the 2020s. So the potential there is significant. Regarding what proportion offshore wind could take in tomorrow's energy mix? Once again, that is extremely hard to forecast. In nations such as Denmark and the U.K., however, offshore wind is already on course to turn into a highly substantial part of the future electricity mix by 2030.

Henrik Poulsen

executive
#75

Over time, this will naturally lead to additional auctions and tenders as well, and that is already happening. In the deck we presented today, you saw the slide showing that we exceeded 11 gigawatts awarded during 2019. We also expect the count of auctions and tenders to keep rising globally in the coming years. Being able to capture that opportunity is clearly something we work on continuously. At present, we are establishing regional capacity across Asia, North America, the U.K., and Continental Europe, and we are reinforcing each of those regions further so that we can pursue the growth opportunity over the long term. For now, we remain committed to our goal of 30-plus gigawatts of total renewable capacity by 2030, and we will of course keep monitoring whether the market should push us toward a larger ambition. As things stand, we still believe that ambition is the correct one. If you convert that into how much offshore wind we would have to construct in the years ahead, you can begin calculating how much we would need to capture from a market that is currently nearing 15 gigawatts per year. It also goes without saying that we will no longer have to hold the 30% market share observed across the past 6, 7 years; that will not be necessary in a market once it begins advancing to 10, 15, 20 gigawatts per year.

Henrik Poulsen

executive
#76

Naturally, as time goes on, that win rate of ours may decline, and even so, it will continue to back a highly ambitious long-term growth strategy for the company.

Marianne Wiinholt

executive
#77

Yes. Now, regarding the gap between our guidance and consensus — you're right that either of those 2 factors could explain the difference. My own view, though, is that timing plays the bigger role. The reason is that throughout the last year, we've repeatedly flagged this point concerning the CfD for Hornsea 1. Sure, somebody may have missed it, but we've stated it time and again. Beyond that, I also sense that most of you baked the trading results into Markets and Bioenergy, since visibility was quite limited before we actually released this annual report. That said, you're right — it could be part of the reason.

Operator

operator
#78

And the next person to ask a question is Alex Lang from UBS.

Analyst

analyst
#79

Thanks as always for the presentation. We had a question about market development. There's obviously a risk that the offshore wind market will experience a stretch of fierce competition and pressure on returns, and maybe even more so if the oil majors keep expanding their presence, as you pointed out on the slide today. So the question is, how would you deal with that scenario, if it arose? Would you lower returns and compromise on value if needed to make sure you still win projects? Or would you be content, say, to go a number of years without winning any new projects if auction returns drop below your current hurdle levels?

Henrik Poulsen

executive
#80

Naturally, that's a complicated one. Still, when you review the last 3 years, competition in offshore wind has been extremely fierce, with quite a few participants involved — infrastructure players, energy companies, and oil majors alike. Yet across that 3-year stretch, we kept securing projects annually and preserved solid value creation within our project portfolio. To this point, nothing suggests we can't keep landing projects, expanding the business, and generating value. Competitive intensity certainly exists, there's no denying that. That said, as we discussed moments ago when answering Alberto's questions, we're likewise observing a market that continues to grow. So right now you have a dynamic in which demand for offshore wind is rising worldwide, while simultaneously more competitors are entering and more capital is accessible in the market. Within that dynamic, our task is essentially to continue driving down the cost of electricity, continue driving down the cost at which we're able to generate offshore wind electricity, and thereby preserve our cost competitiveness. Beyond that, financial discipline is required. Nobody benefits if we abandon our financial discipline, and that requires us to keep demanding value creation from our projects.

Henrik Poulsen

executive
#81

If we aren't able to generate real value, then we shouldn't accept those projects. That path leads nowhere for this company. We have to keep it healthy both strategically and financially, and we stay committed to doing that. Are we capable of that? I'm still convinced the company is in such a strong position that it can keep growing and create value at the same time.

Operator

operator
#82

Since time is nearly up, the final question will come from John Musk at RBC.

John Musk

analyst
#83

I have a couple of questions — one that's more near term and one that's longer term. Regarding the markup you absorbed on gas storage and infrastructure, I believe it's roughly DKK 500 million, which I think you said was tied to elevated gas prices in Q4. And we've clearly witnessed a notable softening in gas prices over the last few weeks — perhaps even a month or so — so is there a danger we could see part of that reverse, given how gas prices have shifted? Then second, partly connected but longer term, my question concerns the cannibalization impact that renewables could have over the longer horizon: quite a few market consultants are publishing long-term power price forecasts, and those can include some very low power prices tied to a greater build-out of renewables. I mean, do you believe there's a self-correcting mechanism within some of these growth ambitions — such that if we do begin to see far, far lower power prices down the road, growth would moderate? And how do you weigh that dynamic?

Marianne Wiinholt

executive
#84

Yes. I'll begin with what you asked about gas. When you consider how gas prices affected us across the whole year, we experienced very low prices all through 2019, and for the full year, as we've mentioned, the effect was negative. Looking just at Q4 on its own, we saw a very, very large positive effect because prices rose during the winter quarter, Q4. But when you examine where the forward curves stand, in a sense we don't anticipate — at least if the forward curve plays out — that gas storages will produce a negative effect in 2020. Still, it's crucial to stress that every bit of this is fully hedged. We hedge the gas margin. So these effects amount only to a timing impact. So keep that in mind.

Henrik Poulsen

executive
#85

Regarding how power prices will develop over the long term — John, that's obviously a complicated matter, as you're aware. Without question, as renewables get built out, and possibly even at a faster pace, that is going to affect pricing over the long term. Conversely, you're going to witness a very substantial wave of coal capacity being retired, and in certain nations nuclear capacity as well, and to a large degree that will counterbalance part of that effect by evening out capacity and supply within the market. Simultaneously, according to our projections, you'll see fairly considerable expansion in electricity across OECD markets during the coming 10, 20 years, which is unusual, since for many, many years there has been essentially flat growth in electricity demand — yet the sole route to decarbonizing modern societies involves, in essence, a huge green electrification of society, in which you electrify heat supplies, electrify industry, and electrify transportation. That is going to produce substantial demand growth for green electricity, for example, arising from electrification of vehicles, for private transportation as well as for heavy transportation. Once you weigh all those differing effects together, the question of what the future price will be turns complicated.

Henrik Poulsen

executive
#86

We keep an eye on this and model it continuously. We believe our view here is fairly prudent. For a great many years ahead, gas will remain, in your view, the ultimate transition fuel and, because of that, the price setter during numerous hours of the day across most markets worldwide. That will keep supporting power pricing over the longer term. So we don't worry that we are heading toward some massive self-correction mechanism. Quite the opposite: we are actually fairly convinced this will prove a reasonably healthy long-term development when we look a couple of decades ahead.

Operator

operator
#87

And at this point I’ll turn it back over to our speakers for their closing remarks.

Henrik Poulsen

executive
#88

I really appreciate everyone taking the time to be here. Thanks for all those excellent questions. As usual, if anything else comes to mind, feel free to reach out — our IR team will be available to help. And I hope to see plenty of you over the next few days on the roadshow. Thanks again for being with us. Have a wonderful day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.