Ørsted A/S (ORSTED) Earnings Call Transcript & Summary

April 29, 2021

Nasdaq Copenhagen DK Utilities Independent Power and Renewable Electricity Producers earnings 85 min

Earnings Call Speaker Segments

Operator

operator
#1

Thanks for joining Ørsted's Q1 2021 earnings call. <<operator_script>> Our presenters today are Mads Nipper, our CEO, and Marianne Wiinholt, our CFO. Mads and Marianne, the floor is yours.

Mads Nipper

executive
#2

Thanks. Good afternoon, everyone, and welcome to the Q1 earnings call. In the first quarter of 2021, we made strong strategic progress throughout the whole company. With that momentum, we hit several milestones. We also saw solid operational performance in the quarter. Beginning with Poland, we reached a major milestone when the Polish Energy Regulatory Office granted contracts for difference to the Baltica 2 and 3 projects. Those 2 projects form part of our 50-50 partnership with Polish utility PGE and have a combined potential capacity of up to 2.5 gigawatt. The CfDs carry a maximum subsidy of PLN 319.6 per megawatt hour, and the exact subsidy is expected to be settled in 12 to 15 months, since the CfD award remains subject to final approval from the European Commission. Growing our footprint in Poland, which has set an ambitious renewable build-out target for the years ahead, is an important strategic milestone for our ambitions in Continental Europe. The Polish award lifts the total capacity of our offshore wind portfolio to 17.4 gigawatt. Following a structured divestment process, we signed an agreement to farm down 50% of our Dutch Borssele 1 & 2 offshore wind farm to Norges Bank Investment Management.

Mads Nipper

executive
#3

We expect to close the transaction around this summer, and at that same time we will get the proceeds, which come to roughly DKK 10.2 billion. Ørsted will keep supplying long-term operations and maintenance services out of our O&M base at the port of Vlissingen in the Netherlands, and we will also give NBIM balancing services plus a long-term route to market for the renewable electricity that is generated. We also strengthened our global position and our future opportunities in offshore wind through 2 strategic partnerships. In the Baltics, we signed a memorandum of understanding with Enefit, the leading utility in the Baltics. This MOU provides a green path forward for developing offshore wind energy in the Baltic States and for jointly moving forward toward delivering a large-scale offshore wind farm in the Gulf of Riga before 2030. In Denmark, we entered a partnership with the Danish pension fund ATP, with the intention of participating in the upcoming auction for the Danish energy island in the North Sea. Together with ATP, we would like to build on our strong industrial and financial competencies and contribute to developing the green transformation and renewable energy infrastructure in Denmark. Over the past year, we have seen rapid progress in our renewable hydrogen efforts, and the latest quarter has not been an exception.

Mads Nipper

executive
#4

We unveiled our SeaH2Land vision, in which we — together with Yara, ArcelorMittal, Dow Benelux, Zeeland Refinery, SDR and North Sea port — will work toward decarbonizing ammonia, steel and other product production in the Netherlands and Belgium. That will be achieved by connecting gigawatt-scale electrolysis to large industrial demand via a planned regional cross-border pipeline. The SeaH2Land vision features a renewable hydrogen production facility of 1 gigawatt linked directly to a new 2-gigawatt offshore wind farm in the Dutch North Sea, with both to be developed and owned by Ørsted. This region ranks among Europe's most hydrogen-intensive, and if it comes to fruition, the SeaH2Land project could switch roughly 20% of the region's present hydrogen consumption over to renewable hydrogen. With this opportunity, the total count of hydrogen projects we have announced reaches 9. Our onshore business likewise keeps up strong momentum, with 4 gigawatts of onshore capacity currently in operation and under construction, stretching across Texas, the Midwest and Southeast U.S. in wind, solar and storage. We build at scale, and our recent expansion has placed us among the top 5 U.S. constructors by capacity additions since 2017. Given that very strong U.S. expansion and execution, we signed an agreement to acquire a European onshore wind platform in Ireland and U.K.

Mads Nipper

executive
#5

Thanks to the purchase of Brookfield Renewable Ireland. On the following slide, I'll walk everyone through that acquisition in greater depth. In the middle of February, an extraordinary winter storm hit Texas, and it put pressure not just on our company but on every community that was affected. Along with the freezing temperatures came sharp spikes in power prices, since generating capacity throughout the state broke down under those harsh conditions. Throughout this event, our top concern was keeping our employees, our contractors, and the communities where we operate safe. Our trading team was largely successful in reducing the possible losses tied to our 2 contracts that are known as fixed shape, which obligate us to supply power regardless of how much power is actually generated. In addition, our technical teams put in substantial effort to keep our assets running through the severe weather. The way we handled the business in those challenging circumstances demonstrates the agility of our operating setup. Overall, we emerged from the event without any material effect on our earnings. We'll keep pushing ahead with expanding our renewable onshore capacity in the U.S. And during Q1, we reached final investment decisions regarding the Helena Energy Center in South Texas. That project stands as our biggest onshore one so far, with 268 megawatts of wind and 250 megawatts of solar PV capacity.

Mads Nipper

executive
#6

For the solar PV portion, we qualify for the 30% ITC, and the wind portion qualifies for the 80% PTC. Because this project is hybrid in nature, we can make the most of that outstanding site, an area known for powerful coastal winds and abundant sunshine. The project — anticipated to be operational in the first half of 2022 — has signed contracts with several corporate off-takers, among them Henkel for part of the wind generation and Target Corporation for part of the solar generation. Returning to offshore: we have found a cable issue at a number of offshore wind farms throughout the U.K. and Continental Europe, and we have booked a warranty provision to cover possible costs owed to partners. We promptly began a deeper review of the potential problem at each individual wind farm and have laid out a remediation plan in 2 phases. Our preliminary assessment of the cable protection system issue points to a total financial impact of roughly DKK 3 billion across 2021 to 2023, and Marianne will go through that in more detail. During Q1 2021, the group delivered strong operational performance, with solid availability rates, better-than-expected results from our CHP plants, and extra earnings from completed construction projects. As a result, we can keep our full year guidance in place notwithstanding the negative effect of the warranty provision.

Mads Nipper

executive
#7

As a final point, I want to say how thrilled we are to have made the inaugural TIME100 Most Influential Companies list. By 2030, the world has to achieve the global emissions, and in the much-needed acceleration of climate action, companies have a crucial part to play. Here at Ørsted, we aim to serve as a catalyst for change by deploying renewable energy at scale, helping governments and businesses worldwide make the shift to green energy. So we take real pride in being recognized for what we contribute to speeding up that global shift toward green energy. Moving now to Slide 4 and the Brookfield Renewable Ireland acquisition. Through this deal for Brookfield Renewable Ireland, what we have acquired is a fully functional stand-alone business with an attractive, sizable operating portfolio, a high-quality development pipeline and a strong team of over 70 professionals. The portfolio is made up of 327 megawatts in operation, 62 megawatts under construction, 149 megawatts of advanced development projects, and a development pipeline exceeding 1 gigawatt of mainly onshore wind projects across Ireland and the U.K. This acquisition will grow our business platform in Europe and give us added access to customers, partners and talent, plus a deeper insight into market and regulatory dynamics — all of which will add critical mass to our global presence.

Mads Nipper

executive
#8

We've done a thorough review of the European onshore market and looked at several onshore targets throughout Europe. And we do think we've identified the best fit, since BRI provides a platform in a competitively advantaged position, powered by its development pipeline, its operating portfolio and its very strong team. By way of BRI, we gain the capabilities and expertise to back broader growth into other European onshore markets, which present substantial medium- to long-term growth opportunities. Given our strong onshore foothold in the U.S., we view this as a good moment to expand into Europe. This expansion won't dilute our focus on maximizing value creation growth in the U.S., which stayed our dominant onshore growth engine. Our strategic ambition is to further strengthen our position in North America by building a diverse onshore wind and solar PV portfolio. Furthermore, it doesn't dilute our focus on being the leading offshore wind developer. All in all, this acquisition is an important strategic milestone for the Ørsted Group, and it's a natural next step for us in our vision of creating a world that runs entirely on green energy. Now turning to Slide 5 and 6, where I'll give a brief update on our construction projects within offshore and onshore.

Mads Nipper

executive
#9

Construction is proceeding on schedule at both of our offshore wind build-outs, Hornsea 2 and Greater Changhua 1 & 2a. At Hornsea 2, work is under way both onshore and offshore, and 71 of the 165 foundations have now been set in the sea. Over at Greater Changhua 1 and 2, horizontal directional drilling has begun as preparation for laying cables and for scour protection work, getting the seabed ready for foundations to go in. Related onshore construction is moving along nicely, and that includes finishing the civil works on the 2 onshore substation main buildings plus the upgrade of the hinterland at the port of Taichung, which will store key components for offshore installation. A broad range of marine engineering, vessel suppliers and personnel, drawn from home and abroad, will back the offshore construction. Peak periods are expected to see over 25 vessels mobilized — crew transfer vessels, installation and support vessels, service operation vessels and guard vessels among them — along with 500 to 800 people working at sea. Moving to Slide 6, let's look at where our onshore construction portfolio stands. I'm glad to report that good progress continues across the construction projects in our onshore business.

Mads Nipper

executive
#10

Looking ahead over the coming 2 quarters, we anticipate bringing online our initial 2 utility-scale solar PV developments, Permian Energy Center and Muscle Shoals. For Q2, our expectation is to energize Western Trail and begin turbine deliveries at Haystack. With Old 300 and Helena Energy Center also progressing as planned, we're well on track to reach 4 gigawatt commissioned in the U.S. alone by Q2 of 2022 — close to our entire 2025 target of 5 gigawatt. Turning now to Slide 7 for a status update on forthcoming auctions and market trends. Momentum is strong following President Biden's March 29 offshore wind announcements, in which the Biden administration set a fresh U.S. offshore wind goal of 30 gigawatt by 2030, along with a comprehensive financial support program. We're enthusiastic about the Notice of Intent announced for our Ocean Wind project and the memorandum of agreement we signed with the National Oceanic and Atmospheric Administration covering the sharing of physical and biological data in Ørsted-leased waters. We further anticipate the Biden administration will act quickly to issue the remaining NOIs, and we expect our Revolution Wind project's NOI to arrive imminently.

Mads Nipper

executive
#11

We’re keeping a close watch on the mechanisms and incentives being proposed in order to hit President Biden’s goal of 100% emissions-free electricity sector by 2035, since they could support and provide an additional boost to Ørsted’s U.S. growth. Among them are the expansive green energy tax package that Congress is considering, a clean energy standard, and a possible infrastructure package. How things turn out at the legislative and executive level is still to be seen, but it’s clear the administration is pushing offshore wind forward at a very accelerated pace. For our 1.1 gigawatt Ocean Wind project, we have closed the agreement with PSEG to sell a 25% ownership interest, and we’re delighted to officially confirm our partnership with PSEG on Ocean Wind. We recently submitted our best and final offer as part of New Jersey’s second offshore wind solicitation, and we have submitted a bid that reemphasizes our commitment to manufacturing in New Jersey while making sure that all New Jersey communities benefit from the opportunities in this new industry percents. We look forward to hearing the New Jersey Board of Public Utilities’ announcement in the coming months. The busy U.S. auction calendar continues into 2021, and we expect additional auctions in Rhode Island, Massachusetts, Maryland and potentially, Connecticut.

Mads Nipper

executive
#12

Turning now to Asia Pacific. Japan held its inaugural auction in November 2020 covering the Choshi, Noshiro, Yurihonjo North and Yurihonjo South promotion areas. Bids must be submitted by May 27, with awards anticipated during the second half of 2021. That auction totals 1.5 gigawatts distributed across the 4 zones, and it marks a significant first step toward Japan's goal of 10 gigawatt of offshore wind by 2030. In Vietnam, our first office has opened in Hanoi, where we intend to assemble a local team and collaborate closely with government authorities and local partners. Vietnam offers strong potential and ideal conditions for offshore wind development, and we're eager to take our first steps in this market. Turning to recent developments in Europe. In the U.K., we anticipate the fourth CfD round opening near the end of 2021, where our Hornsea 3 project can take part; that project has a capacity of at least 2.4 gigawatt and received consent in December of 2020. Following the results of the recent U.K. lease auction, Crown Estate Scotland finalized revised criteria for its first ScotWind seabed leasing round.

Mads Nipper

executive
#13

Submissions for the 10 gigawatt round close in mid-July of this year, and we intend to take part in the seabed lease auction. Beyond that, we anticipate that France, Denmark, Netherlands and Germany will launch competitive tenders at some point during 2021. So 2021 clearly brings a great many chances when it comes to offshore wind auctions and tenders, and we keep working tirelessly so that we are positioned as a strong competitor and so that we capture our fair share of capacity while not compromising the value creation. We have already seen success at the beginning of 2021, having secured capacity in Poland, formed a number of partnership for future growth within offshore wind, found an attractive and meaningful way to enter the European onshore market, and we added our largest U.S. onshore project to date to our portfolio. With that, I will now pass the word to Marianne.

Marianne Wiinholt

executive
#14

Thanks, Mads, and good afternoon from my side as well. First, I'll walk through the warranty provision tied to the cable protection problem, and after that I'll move on to the group financials. While carrying out a cable inspection campaign at Race Bank offshore wind farm, we found an array cable failure brought about by a problem with the cable protection system. This problem arises when the cable protection systems shift over the scour protection — the rocks that are put in place to stop seabed erosion around the foundations. That can wear down the cable protection system and, in the worst case, lead to cable failures. Since the cable protection system design served as the common solution for several years, we presently estimate that as many as 10 of our offshore wind farms in the U.K. and Continental Europe could be affected. It should be noted that at some of those wind farms, the risk may involve only a handful of cable protection systems. So although we said up to 10 wind farms are at risk, the degree of risk differs from one wind farm to another, and additional engineering work is under way to sharpen our understanding. The cable protection system design has been updated.

Marianne Wiinholt

executive
#15

So we don't anticipate seeing any impact on the projects we're currently building or developing. We're taking proactive steps to safeguard the long-term integrity of our assets through a 2-phased approach. Phase 1, which will be carried out in 2021, aims to stabilize the cable protection system and stop further degradation, while Phase 2 involves repairing or replacing damaged cables and will likely be carried out in 2022 to 2023. The stabilization will provide the best value risk management over the short term to prevent additional damage and can likely remove the need to repair or replace most of the less damaged cables in Phase 2. In addition, we anticipate limited production downtime from the stabilization work. Our early assessment points to a total financial impact of around DKK 3 billion across 2021 to 2023, with the biggest portion of the cash outflows in 2022 and 2023. And we've made a warranty provision of DKK 0.8 billion to cover potential costs toward our partners. We expect the biggest cash outflows will fall in 2022 and 2023 as part of the Phase 2 campaign. Of the DKK 3 billion, we expect roughly 1/3 can be capitalized and 2/3 will hit EBITDA.

Marianne Wiinholt

executive
#16

We're going to keep digging into the cable protection system problem and the redemption steps that are required, including how suppliers, partners and insurance are affected. We anticipate a clearer picture of both the problem and its consequences closer to the end of the year. Moving on to how the group performed financially in Q1 2021, we posted an EBITDA of DKK 4.9 billion, a drop of DKK 1.9 billion. Most of that decrease comes from the warranty provision plus the changes to assumptions regarding the divestment of Hornsea 1 offshore transmission assets in Q1 2020, worth DKK 1 billion. On top of that, 2020 contained earnings from our distribution, B2C and City Light businesses, all of which we have now divested. Those negative quarter-on-quarter effects were partly offset by a positive DKK 500 million effect in Q1 2021 stemming from no longer reporting under the business performance principle. Once you adjust for these items, Q1 2021 matched last year. In Q1 2020, earnings at offshore wind sites got a positive boost from very strong wind speeds of 12.1 meter per second, whereas Q1 2021 reached 10.5 meter per second, below the normal wind level of 10.9 meter per second.

Marianne Wiinholt

executive
#17

That gap in wind speeds leads to an EBITDA hit of roughly DKK 900 million versus a year earlier. On top of that, Q1 2021 took a negative hit from increased transmission tariffs that followed the sale of the offshore transmission assets at Walney Extension in mid-2020; from reduced earnings at Horns Rev 2 as the subsidy period finished in October 2020; and finally, from weaker rock recycled prices. Partly balancing these negatives were the ramp-up of output from Borssele 1 & 2 during Q1 2021 and the addition of a further 400 megawatts at Hornsea 1 receiving CfDs. Underlying earnings from partnerships in Q1 2021 mainly related to adjustments tied to finalizing construction projects. Our onshore segment got a boost from the ramp-up of generation at the 3 new wind farms, Sage Draw, Plum Creek and Willow Creek, along with early output from our premium energy center. That substantial increase in power generation was partly offset by a small loss caused by the winter storm in Texas in February. Underlying EBITDA in Bioenergy and Other matched Q1 2020, which came in above what we had expected, helped by stronger results at our CHP plants. Let's now move to Slide 9 and look at our financial performance and net interest-bearing debt.

Marianne Wiinholt

executive
#18

Net profit for the period came to DKK 1.6 billion, which is down from last year, primarily because of lower EBITDA and increased depreciation stemming from a greater number of wind farms in operation. Free cash flow for the quarter amounted to DKK 1.4 billion, while cash flow from operating activities reached DKK 8.1 billion, supported by EBITDA and the March 2021 divestment of the Hornsea 1 offshore transmission assets. Gross investments came in at DKK 6.9 billion, reflecting our ongoing investments in offshore and onshore wind as well as solar PV farms. Net debt at the close of the quarter was DKK 13.2 billion. The rise in net debt over the quarter was mainly attributable to the distribution of DKK 4.8 billion in dividends to our shareholders, along with a negative impact from exchange rate adjustments tied to the appreciating sterling. That was partly offset by the positive free cash flow I just mentioned and by the issuance of new hybrid capital in Q1 2021. Let's now move to Slide 10, which presents our financial and non-financial ratios. Our credit metric, FFO to adjusted net debt, was 45% for the 12-month period ending in March 2021, which puts us well ahead of our credit metric target.

Marianne Wiinholt

executive
#19

Return on capital employed for us was 7.5%, and the drop versus a year ago stems from lower EBIT across that 12-month stretch. The quarter's ROCE sits under 10%, yet we remain on course to deliver the 10% average ROCE we guided for between '19 and 2025. Greenhouse gas emission intensity rose temporarily because our coal-fueled units generated more power — and there we carry a regulatory duty to put our capacity into the market in the most cost efficient manner. Even with that rise in emission intensity, we are still on track for our scope 1 and 2 targets of under 10 grams of CO2 equivalents per kilowatt hour in 2025. On safety, we recorded a 17% reduction in the number of injuries, and as a result the total recordable injury rate fell from 3.6 in Q1 '21 — sorry, in 2020 — to 3 in Q1 2021, which keeps us on track for our 2025 target of 2.9 or lower. That wraps up the group's financials for Q1 2021, so let's move to Slide 11 and the outlook. As Mads said at the start of the call, we reiterate our full year guidance for 2021 EBITDA, excluding new partnerships, of DKK 15 billion to DKK 16 billion.

Marianne Wiinholt

executive
#20

The DKK 0.8 billion warranty provision tied to the cable protection system problems is partially offset by stronger-than-anticipated results at our CHP plants, along with extra earnings from construction projects completed in Q1 2021. Beyond that, we anticipate a modest contribution from Brookfield Renewable Ireland after the deal closes. Gross investments are set to rise compared with the guidance given in our annual report. And assuming the Brookfield Renewable Ireland acquisition closes as expected by Q2 2021, the purchase price will be added to our present gross investment expectation of DKK 32 billion to DKK 34 billion. With that, I'll hand the word back to Mads.

Mads Nipper

executive
#21

Much appreciated, Marianne. Before we begin the Q&A, I want to point out that registration has now opened for our Capital Markets Day on June 2. I also want to repeat how eager we are to see all of you virtually and to bring you up to date on our strategy and long-term targets. So with that, let's open it up for questions. Operator, please?

Operator

operator
#22

That wraps up our presentation, and now we're glad to take your questions. We do have to finish this call by no later than 15:30. <<operator_script>> Our first question comes from Rob Pulleyn at Morgan Stanley.

Rob Pulleyn

analyst
#23

Sure. I’ll let others handle the questions about the cables, and I’d just like to ask about the U.S. First, could you give a bit of an update on the latest timing and next steps for your U.S. projects, especially given the policy tailwind that’s now evident—that would be great. And as a part B, a second question: can I ask—there seems to be a very large U.S. seabed acreage leasing round coming up for the New York pike in the next 12 months. I’d be very interested to hear how Ørsted viewed that seabed auction in light of its existing acreage in the U.S., its opportunities in other markets, but also the scale benefits and multiyear visibility this auction would likely convey on the winners, which, of course, might make it very competitive.

Mads Nipper

executive
#24

Thank you very much for that question — I really appreciate it. And as you said, I think the cable-related questions will probably be left for others. But I'm genuinely glad to share in your excitement about how things are moving with U.S. legislation, and in particular, yes, the strong progress on the BOEM approval processes. The NOI for our Ocean Wind has come in, and one for our Revolution Wind is imminent as well — that's something we're quite pleased about. We can't say precisely what that means just yet, since we do need to secure those NOIs for the portfolio, but we're working hard to update the schedule. We'll be able to share that in the relatively near term. Hopefully, once we've also received the NOI for Revolution Wind, we'll be in a position to give a more specific update shortly. As for the New York Bight, we see it as fundamentally positive that the U.S. is making more seabed available. We need that to reach the 30 by 30 ambition. It's absolutely necessary. We still have good seabed availability in our current pipeline as things stand, and — but of course, we will look at the opportunities in the New York Bight seabed auction.

Mads Nipper

executive
#25

We haven't reached a conclusion on that yet. And it isn't the case that we'd have nothing on hand if we decided against taking part. Still, that is definitely one item we're examining quite closely as a possible participation.

Operator

operator
#26

The next person to ask a question is Alberto Gandolfi from Goldman Sachs.

Alberto Gandolfi

analyst
#27

Let me step back and take a somewhat broader view here. This comes out of an interview you did recently, Mads, in which you mentioned the possibility of being under pressure should you fail to win a prominent capacity auction. So I was hoping to understand the thinking behind that a bit better. As I see it, right now you appear to have an official gross seabed pipeline of something like 14, 15 gigawatts, which ought to be enough to cover growth for several years. But what I was trying to get at is why not take a somewhat more front-footed approach on seabed, because to me it looks as though, absent a proper backlog of seabed, it's hard to persuade the market that you can keep growing at a very high pace beyond capacity auctions of the 2027, 2028, 2030 type, let's say. So we'll probably see 27 gigawatts of seabed auctioned this year. So I suppose I was trying to get your general observations on what I've just said. And would you mind perhaps telling us where you feel a little bit stronger? How much seabed do you think you need to procure this year and over the next 3 years to keep your growth story going and to be perceived as a secular grower?

Alberto Gandolfi

analyst
#28

Since I believe that, beyond the competitive angle, if prices rise across the board, then presumably the expense of seabed will simply be passed through. And the reason I'm putting this to you is that investors sometimes tell you: why is the company putting EUR 600 million into offshore in Ireland? Is that because they're concerned about structural growth in offshore? I apologize if that came out somewhat convoluted, but I wanted to lay out all the background for the question.

Mads Nipper

executive
#29

Thanks a lot, Alberto. Those are all pertinent aspects, and I'm glad to address them. Once more, I'll begin with the remark I made regarding possibly being under pressure. What wasn't particularly clear from the bid that got picked up by international media was that it arrived against a backdrop of extremely strong growth anticipated toward 2030. And clearly, I mean, I think we're all aware that competition is rising at the same time, but honestly, with the market set to grow sixfold from where it stands today, we have no doubt that chances for us to keep expanding are certainly present. Still, we're humble, yet also quite resolute about delivering that growth amid tougher competition. When I — when we discussed problems, I suppose there was also a bit of a misunderstanding around whether failing to win one of the more contested auctions over the next 12 months would count as specific trouble or challenges. And obviously, not — the context I'd like to provide there is that we hold a very stated and very clear ambition that, in 2030 as well, we intend to be a leader in offshore.

Mads Nipper

executive
#30

So in a hypothetical scenario where we don't secure any competitive auctions over the next 12 to 18 months, that would clearly create some pressure. However, I want to emphasize again that competitive auctions aren't the whole story behind our offshore expansion. You'll hear — you'll see that the 2.5 gigawatt project in Poland is definitely something we're quite enthusiastic about. We've already mentioned the MOU with Enefit in the Baltic state, which might bring as much as 2 gigawatt through a noncompetitive auction. We also shared that we're launching new market initiatives in Vietnam. So we remain quite active across multiple areas, including a specific focus on seabed, and we've stated we'll take part in the upcoming ScotWind auction. That's something where we're openly declaring we'll commit to it. We're actively evaluating New York Bight. And we're actually ramping up our market development work in Japan, Korea, Vietnam, the Baltic states, and elsewhere. So while we hold competition in high regard, I'd add that we also feel free to stay quite assured that our pipeline and capabilities are very strong enough to remain the leader.

Mads Nipper

executive
#31

I don't believe we're able to specify the amount of seabed we must add this year or over the next 3 years to remain a leader. Our seabed availability is by far the strongest of anyone, so this isn't something that worries us imminently. Still, we recognize there's a world beyond 2030 as well, so naturally we'll continue developing for the long term too.

Operator

operator
#32

Jenny Ping from Citi has the next question on the line.

Jenny Ping

analyst
#33

I have questions from 2 areas, and I'll address the cable cover matter. From what I understand, the DKK 3 billion you first flagged today is really meant to substitute for part of the cable cover problem rather than necessarily replacing any damaged array cables, which is clearly the more expensive portion. So I suppose what I'm really asking here is how much assessment have you carried out regarding the array cable damages? And is that DKK 3 billion effectively the worst case scenario? And then how -- and then one for Marianne. How should we think about that DKK 3 billion in terms of the EBITDA phasing across the quarters for '22 and '23?

Marianne Wiinholt

executive
#34

Yes. We've done evaluations, and naturally these are preliminary evaluations, but part of the question is how much is damaged to some degree and how much further deterioration we can prevent by placing rock on top of the cables. We've produced this estimate of DKK 3 billion, and in Phase 1 we'll commit only modest sums to the rock dumping, and that work will happen during 2021. During 2022 and 2023, we'll continue with the possible replacements and repairs. And that's where the bulk of the expense falls in this phase. And as we've stated, roughly 1/3 of the costs should be capitalizable, with the remainder impacting EBITDA. You could say we've already booked the DKK 800 million this quarter. So then, in a sense, what's left arrives across 2022 and 2023. And as I mentioned, during 2021 we face only limited extra costs, since this rock dumping isn't particularly pricey. Just how the split falls between 2022 and 2023 is somewhat hard to gauge at this point. But for the time being, in a way, our best estimate is an even cost across those 2 years.

Mads Nipper

executive
#35

And just to add something very quickly there, Marianne. If I got this right — and apologies if I didn't — if I heard the first part of your question properly, you were also asking whether that DKK 3 billion covers only stabilization, a possible repair of the cable protection system, and then, as an indirect part of the question, whether potential cable repairs or replacements would come on top of that? No, that's not the case. That DKK 3 billion represents our current best estimate of the total cost for everything that has to be remedied, covering both stabilization and potential repair and potential replacement.

Marianne Wiinholt

executive
#36

And the dumping of rock.

Mads Nipper

executive
#37

That's right.

Marianne Wiinholt

executive
#38

So, that covers all of it.

Mads Nipper

executive
#39

Yes.

Operator

operator
#40

The next person to ask a question is Deepa Venkateswaran from Bernstein.

Deepa Venkateswaran

analyst
#41

My question relates to that recent Danish development where you've partnered with ATP. Could you perhaps help us grasp how that arrangement differs from, say, the store — the store tender that's ongoing? And would you also see additional financial partnerships of this kind arising for other projects? And more broadly, how will the Danish government go about choosing which party develops this energy island? Any thoughts on that would be helpful.

Mads Nipper

executive
#42

Yes. Thanks a lot, Deepa. I can start us off. That ATP partnership applies solely to the North Sea energy island. It's a project with no connection to the Thor auction. Thor, then, is a separate auction that comes earlier, while the energy island serves roughly as the hub for as much as 10 gigawatts of offshore wind that will later be constructed around that island and fed into it, and what we've now teamed up with ATP to do is to place a bid for that island, which will be the first energy island anywhere in the world, and so something we consider highly interesting, strategically as well, for building new capability. It's still premature, since there's still, so to speak, political discussion and talks under way with the government regarding which specific criteria will be most important for the energy island tender. We do know it's going to be competitive, yet we also think that, unlike, say, Thor, which will mainly be price-based, this one is going to be an auction with multiple sorts of criteria, though that isn't finalized as of yet.

Mads Nipper

executive
#43

As for whether the ATP partnership would fundamentally change how we go about developing wind farms as well — no, that isn't what we intend. When it comes to developing wind farms, our intention is to maintain the operating model we have now, where sometimes we build in partnerships with others and sometimes on our own, with a subsequent opportunity to farm down, as you know.

Deepa Venkateswaran

analyst
#44

And would the Danish consortium get any kind of edge here, considering that this is such a big investment for the Danish government? So would you gain any advantage from having partnered with ATP, or from your range?

Mads Nipper

executive
#45

My view is that regulation will come into play—some EU rule, I mean—that would make this accessible to everyone. We anticipate that at least one of the rival consortia might likewise be Danish. One consortium has already stated publicly that it too has an interest. But in an artificial sense, there won't be any assured Danish edge regarding which party wins the consortium or the competition.

Operator

operator
#46

Peter Bisztyga from Bank of America has our next question.

Peter Bisztyga

analyst
#47

Okay, returning to the subject of those cables — and I believe you mentioned this a bit earlier — but it would be helpful if you could give us some additional specifics. So could you make clear whether this cable problem is particular to how those 10 wind farms were designed? Or does the fault lie with the equipment itself? And I suppose the relevant questions flowing from that are whether you're able to make a claim under an assurance here, or whether you might recover damages from your equipment supplier. And then as well, could this problem potentially impact other offshore wind farms that other companies own? In other words, is this a generic offshore wind farm issue?

Marianne Wiinholt

executive
#48

Yeah. To rewind a little on the history, since I think that helps. For the first batch of wind farms we constructed, we used a different approach. It was what we call a double layer of rock. So initially, rock went around the monopile, then the cable comes out, and after that we place rocks on top once more. Later, working with the industry, we concluded a better option existed, so we skipped adding that second rock layer on top. At the time, that was considered the optimal approach, and we applied it at 10 of our wind farms. We have since learned that it isn't a good approach. So at the sites under construction right now, Hornsea 2 and Changhua, we are stabilizing the cables once more. So in a sense, it's those 10 particular wind farms where competitors face the same problem. In a sense, it isn't for us to speculate, but this approach was, in a sense, the industry norm during that period.

Peter Bisztyga

analyst
#49

Okay, so this isn't tied to the cable protection permit at all — meaning you can't really turn around to the suppliers and say their systems are defective?

Marianne Wiinholt

executive
#50

Yeah, that's a fair question. In a sense, we've come out with this bad news quite early, so it isn't the case that all our investigative work is finished. And we're looking into whether there might be potential claims toward insurance, suppliers, and so on and so forth. But we don't expect that to significantly alter this DKK 3 billion figure. Of course, though, we're at a stage right now where we're exploring every kind of thing that could help bring the cost down for us.

Operator

operator
#51

Sam Arie from UBS has our next question.

Sam Arie

analyst
#52

There's something I wanted to ask — well, really, my question was about the Danish energy island, since I think that's a really interesting item on your horizon, but I believe that's already been covered. So may I shift to what might be a slightly less upbeat subject, namely U.K. taxes. I'm aware there's already somewhat of a tax issue in play between the U.K. and Denmark, but since we last spoke with you, we've also had the budget and the rise in the U.K. corporate tax rate, together with some capital allowances and so forth that will apply over the next 2 years. So I don't believe — apologies if I missed it — but I don't believe you commented at all on how those U.K. tax changes might affect you. Could you take a minute to sort of walk through the sensitivity, I suppose on both sides, the rate increase and the allowance increase in the near term.

Marianne Wiinholt

executive
#53

Right. So the jump from 19% to 25% by itself isn't good news, obviously, but those allowances do help, of course. We don't have the complete picture yet, though we don't anticipate a major impact from this change — we do expect to see one, and it leans negative, but not significant. That said, I don't have the full overview.

Sam Arie

analyst
#54

So I guess what I'm asking is this: you have that wind site guidance out there, the 20% CAGR through 2023. So I assume that in that year, you'll be paying the higher U.K. tax rate. I realize you may have some carryover from the cable issue, and you have one more farm down there. When you add all of these things together, are you still comfortable with that 2023 guidance?

Marianne Wiinholt

executive
#55

Yeah, we feel good about it. And keep in mind the tax increase won't affect EBITDA — that sits below the line.

Sam Arie

analyst
#56

Yeah, I suppose you're right about that.

Marianne Wiinholt

executive
#57

Right, right. Even with that additional expense tied to the cable problem, we still feel confident about hitting the target, yes.

Operator

operator
#58

Casper Blom from ABG Sundal Collier has our next question.

Casper Blom

analyst
#59

I'd also like to say a few words about the energy island project and your big hydrogen ambitions down in the Netherlands. And thinking more conceptually, it looks to me as though you're moving into somewhat new territory. We've been accustomed to hearing mostly about constructing wind parks, and now you seem to be expanding into other parts of the overall energy system, so to speak. How are you thinking about bringing in the right competencies for this? And how do you see this from a risk standpoint? I mean, should we regard this as somewhat higher risk, given that you're now moving into territory that's a bit uncharted?

Mads Nipper

executive
#60

Sure, and thanks a lot, Casper. I can offer a few thoughts on that. Yes, there's no question that doing something for the first time is, almost by definition, going to carry more risk than putting your, say, wind turbine number 1,600 into the ocean. But I also believe it's quite clear that future energy systems will obviously include a large-scale build-out of renewable energy as a backbone, yet there will also be new solutions that are absolutely needed to decarbonize the — and not least the hard-to-abate sectors. That's why green hydrogen and green fuels are a vital part of this, which I'm sure you also know is a potential application on the back of the energy island supplying large-scale power-to-X projects as well. So I'd say that while we will absolutely remain very, very focused on being a leader in offshore wind development, and while expanding over proportionally also our onshore, both wind and solar PV and storage, we see it as both something that would be absolutely needed — that some of the pioneers in the business lean into these new opportunities of green hydrogen and, in this case, also the energy island.

Mads Nipper

executive
#61

Yet we believe that Ørsted's early entry into offshore wind has generated genuinely appealing commercial possibilities. In our view, occupying a pioneering position—and being among the most ambitious players in this area—carries meaningful potential for value creation over the long term. So yes, the risk profile is higher. And we are moving into territory where we, like everyone else, possess limited or very limited—or essentially no—experience. We are substantially expanding green hydrogen and green fuels, including within our own team. We also collaborate closely with partners on both the offtake and technology fronts, and a considerable number of partners are involved in many of our 9 hydrogen projects. Thus our ambitions to drive this forward are high. But we recognize as well that although we are developing capability internally, partnerships remain necessary to advance this at the level of ambition we hold.

Casper Blom

analyst
#62

Okay, if I could just ask a quick follow-up there, Mads. Would it be fair at all to link the concern about reduced returns in offshore wind — because of increased competition — with your move into new areas? Is that partly being driven by a need on your part to identify new areas so you can lock in future project profitability?

Mads Nipper

executive
#63

No, I wouldn’t draw that connection. Even with competition having ramped up, we continue to see plenty of offshore build-out opportunities that make commercial sense, because—I mean, we haven’t reached the end of the road yet when it comes to bringing costs down and raising efficiency, and also to finding other routes to strong differentiation around local workspaces, biodiversity protection and so on. There’s ample room still to create differentiation. So no—even with more competition, offshore remains highly interesting and is also an area where we think we can generate a profit. But we do think that we are—I mean, many people speak, ourselves included, about the transformation Ørsted has carried out successfully from fossil fuel based to green energy, especially in offshore. Yet we view ourselves as being in a constant transformation, and part of that next transformation lies in green hydrogen and, in this case, also energy island. And we think it’s—for the market leader, we think it’s right to be forward leaning into areas where we are also building a capability, otherwise we are diving into these project opportunities.

Operator

operator
#64

The next person to ask something is John Musk from RBC.

John Musk

analyst
#65

Sure. Perhaps I could slip in a quick point on the first one, just by way of clarification. I wanted to confirm that you said there are no further revenue effects we should factor in stemming from outages tied to the cable problem. The real question, though, is this kind of event, which is, I suppose, an unanticipated risk we carry with offshore wind, and it brings back a bit the wait and blockage problem we faced 2 years ago. At that time, though, I guess returns were better. Now, with the world more competitive and returns being squeezed, a small issue such as this clearly has a bigger effect on the overall spread a project can earn. And do you believe we are at a point where competition is beginning to ignore some of those risks? Or do you think bidders are still behaving sensibly?

Mads Nipper

executive
#66

Sure, I can start us off, John, and then ask Marianne to add anything. So I think — what I'd say is that there will always be, in my view, the possibility of something like this happening; that risk of course exists, just as I'm sure it does with any kind of technology. And we don't see this as something that has been ignored, because many new entrants will also have to take this on, and even though we already have a lot of experience as an offshore developer, this is further evidence that this technology does not have a very wide base of highly experienced participants and that not everything is very mature. What we believe is — the way we see it, we talk about it early, and we also believe we have every capability required to resolve it fast. So yes, of course it's irritating. But looking at the bigger picture, we still regard this as clearly manageable and not something devastating, even given returns that are obviously lower than they were a few years back. But Marianne, anything you'd like to add?

Marianne Wiinholt

executive
#67

Yes. Just to address your first small question, no, we don't anticipate any meaningful revenue impact, because you take one array cable at a time. So the downtime is very, very limited. I would also add that, going forward, we will, of course, not use the same solution for this cable protection system. But the new solution that we will use with stabilizing the cables, it isn't very much more costly. So this issue in itself will not impact the returns on our future projects. It's small money. So -- and had we known that, of course, we should have spent those money. Yes.

Mads Nipper

executive
#68

Sure thing.

Operator

operator
#69

The next person to ask a question is Mark Freshney with Crédit Suisse.

Mark Freshney

analyst
#70

I won't be asking about Danish energy islands or cable repair campaigns. What I want to focus on instead is Slide 7, where you highlighted 25 gigawatts of offshore auctions and tenders for this year. We're in a world with EUR 50 carbon, where power prices across most markets now sit above the level, or the LCOE, needed for offshore wind. I think ahead of your onshore wind business, even noted that PPA prices are rising now. So, Mads, do you believe this year might be the last one in which tenders are actually awarded, and that we'll instead begin seeing projects built on the merchant price of power or through corporate PPAs? And as a 1b to that question, when will you be ready to move forward with a project based on corporate PPAs offshore, entirely outside any kind of government contract?

Mads Nipper

executive
#71

Yes. Thanks a lot, Mark. On your first question, no, we don't believe this is the final year in which there would be backed or supported projects. We think this will go on for — in fact, for many years. But we also think that the likelihood, and maybe even the need, for build-out of significant merchant projects is — will also happen. Keep in mind that our Borkum Riffgrund 3 project is actually fully merchant. And we have also — we have already now signed on a significant share of that through corporate PPAs. So I would not rule out that this is something that can — that would be a real option short term, and also for some of the green hydrogen projects. And if you look at some of the major corporations that are in need to decarbonize their business not just in terms of what can be electrified, but also for potential high-volume green hydrogen and green fuels. This is something that could substantially increase the need for short-term build-out of high-capacity offshore wind. So answer to your question, no, this — we definitely don't think this is one of the last years with government-backed offshore projects.

Mads Nipper

executive
#72

But yes, we could be prepared to take on additional fully merchant projects, possibly even on a shorter-term basis.

Mark Freshney

analyst
#73

So does that mean — you've got the 15 gigawatts, I believe, in the back, there's a slide back there, in the appendices I think, that shows your offshore gigawatts. But does that mean that in 2025, you could have a project in there that isn't part of a government tender, for example, and isn't Borkum Riffgrund?

Mads Nipper

executive
#74

No, that wouldn’t happen by 2025. That probably wouldn’t be the PPP.

Operator

operator
#75

The next person to ask a question is Ahmed Farman from Jefferies.

Ahmed Farman

analyst
#76

I just have a question — a clarification one, actually, about the 2021 Q1 results. Earlier in the year, when the guidance was given to us, you called out 3 particular negatives affecting offshore EBITDA, and those included greater O&M costs and higher tenuous charges? You also flagged that DEVEX would go up. It would be very helpful to understand better how much of those items has been recognized in the first quarter.

Marianne Wiinholt

executive
#77

I can handle that one. The tenuous item we flagged—which is already showing up in Q1, since we're now paying tenuous for Walney Extension. The higher DEVEX, we aren't seeing that. We expect it to show up later in the year. And then we also flagged those O&M costs for Changhua and Hornsea 2, and we haven't progressed far enough yet that we've begun spending money on O&M for these projects, but that too will come later in the year.

Ahmed Farman

analyst
#78

Right, so I just want to confirm that your expectations on these costs are unchanged — it's simply the timing.

Marianne Wiinholt

executive
#79

No, it's the same.

Operator

operator
#80

Our following question is from Marcus Bellander, who is with Nordea.

Marcus Bellander

analyst
#81

I'd like to ask a follow-up about the energy island. Mads, you said you want to be the first mover in this area. And there's no question that the energy island is a new concept and will be a large project. But I'm just wondering how much innovation will really be required here that could potentially enable higher returns. I mean, constructing an island has been done previously, and I would imagine you'll be installing transmission infrastructure on it similar to what you've installed before. So I'm just wondering where the innovation actually sits in this.

Mads Nipper

executive
#82

Yes. Many thanks. And once more, this is another matter where discussion with the Danish government continues, since what is certain is that this <<foreign_lang>> based island will exist in the North Sea. A Baltic Sea energy island will exist as well — an island named Bornholm is already there, and it will likely remain, though the principle behind the concept is identical. As for what sits on the island, what will take place there, whether Power-to-X green fuels production will be located there, and what sort of international distribution network might potentially be possible — all of that remains to be determined. But the reason we chose to lean in at this early stage and also build the island is not that we harbor some dream of becoming systematic island builders. It is simply that the experience we believe we will obtain from being involved from the first go is something that could deliver invaluable learning to us regarding the entire energy island concept, which could result in systematic innovation, both concerning the — yes, some of those transmissions will also be international. We will have to cooperate with TSOs across borders and so forth.

Mads Nipper

executive
#83

A lot of firsts still have to take place here — some on the technical side, some when it comes to international collaboration, and definitely something related to scale, since 10 gigawatts on a single island is at a magnitude the world has never seen. So while we can't be overly precise about which innovations we think will prove the most unique, we're confident those opportunities exist, and we're confident it makes sense for us to lean in and secure a potential ticket to play.

Operator

operator
#84

Klaus Kehl from Nykredit has our next question.

Klaus Kehl

analyst
#85

Yeah, Klaus from Nykredit here. One boring question regarding this cable issue. Marianne, you said it was an interesting norm, the way you constructed them a couple of years ago. So would it be fair to assume that the fault lies in your design process rather than coming from your sub suppliers? That's my question.

Marianne Wiinholt

executive
#86

Honestly, we haven't yet pinned down what's actually causing this, and that work is ongoing. What we do know is that a problem exists, though more investigation is needed before we can be sure of the true underlying cause. That's the reason I'd prefer not to go beyond that for now.

Operator

operator
#87

The next person to ask a question is Kristian Johansen from Danske Bank.

Kristian Johansen

analyst
#88

My question is about the upcoming tender in France, where from what I could tell, you haven't been prequalified to take part in the tender. So I'm just wondering whether that's a deliberate choice on your part not to pursue this tender, or whether you're assuming you weren't selected by French authorities to continue in the tender?

Mads Nipper

executive
#89

Yes. Thanks, Kristian. The very short answer is that this was a deliberate choice. We always evaluate the upcoming auctions very diligently, looking at which ones best match the strengths we have. And given what you can also see on Slide 7, there are lots of opportunities. And even though we have a very high capacity to be able to bid in, this — the French auction is one where we have actually chosen not to prioritize and not try to qualify.

Operator

operator
#90

The next one to ask something is Jørgen Torstensen from Fearnley Securities.

Jørgen Torstensen

analyst
#91

I'd like to pick up as well, if that's alright, on what you said regarding leading positions in the market. So my impression is that you haven't been especially active when it comes to floating wind. I'm aware you've discussed this previously and that you're examining ScotWind, which is at least in part floating, although clearly you could simply concentrate on the fixed-bottom portions of the auction. But could you help us close the gap, please, between taking leading market positions—or moving first, so to speak—and how you're approaching floating wind?

Mads Nipper

executive
#92

Happy to do that. And when we announced the annual results, we probably already began what we call sending signals that we're leaning further into floating wind. But first let me say — and it's crucial to repeat this — we still believe there's substantial potential for continued build-out of bottom-fixed offshore wind. That said, we also believe that as the world moves toward net zero in 2050, several additional technologies will be needed, floating offshore among them. And we genuinely believe this is an industry gaining momentum right now, even though at present it really must mature technologically and gain scale before anything can be proven. But we believe that toward the end of this decade, commercial-scale projects could exist out there. That's also why we're now both working with partners and strengthening our own floating capability. We are gearing up. And in the upcoming ScotWind, we'll also have floating as part of that. So I guess the short answer is this is something where we'll play a role. It's something where the technology will take quite a while to mature enough to be competitive.

Mads Nipper

executive
#93

It really has to come down the cost curve in a significant way. Still, we're deliberately embracing that so we can be part of the journey, and we'll also, among other regions, in Scotland as well, make that part of what we -- what would be vetted.

Operator

operator
#94

The following question is from Pujarini Ghosh, who is with Bernstein.

Pujarini Ghosh

analyst
#95

Turning back to how things are moving on the U.S. legislative side, could you give us any sense of how you see the PTC schemes being extended? For instance, do you figure it stays at 60% for another few years and then steps down gradually? I know you mentioned that you'll get 80% for your Helena Energy Center, but any specifics you might be picking up from regulators would be really helpful.

Marianne Wiinholt

executive
#96

Right. We don’t have any clarity on that. You could say we do have clarity regarding offshore and the extension that we received just before year-end. But when it comes to onshore, any possible extension of PTC — at least we don’t have any further insight, probably, than what you have. So we’ll just have to wait and see.

Operator

operator
#97

Vincy Bu from UBS has our next question.

Vincy Bu

analyst
#98

I’ve got some questions about your hydrogen project pipeline. Your presentation lists 9 hydrogen projects in the pipeline, and that’s quite a lot considering where the market stands today. So I just wanted to ask how much CapEx that would represent if all these projects move forward. And do you expect them to deliver a commercial return, or would they be more like R&D-type projects?

Mads Nipper

executive
#99

I’ll start us off. Many thanks. To put it briefly, for these projects we do not have a CapEx figure yet. Most of them are at an early stage. As you can probably tell, some of them — several sizes are referenced. For instance, with greenfield in Denmark, it begins at 10 megawatts, rises to 250, then rises to 1.3. So many of these are quite scalable, and multiple partners are involved. Also, for a number of these, reliance on things such as EU support is quite significant as well. So the answer is no — no specific, determined CapEx budget exists for these. Let me just add one comment, because you might ask, well, why do you have that many, and can you actually move all of that forward? Well, we genuinely do believe that since this is, for everyone, an immature business, this is something where everyone agrees the world needs green hydrogen at scale, but very few people have any experience, and even fewer have experience at scale. So we believe the wisest thing we can do right now is to build capability and build experience across a large — sort of a wide range of application areas with different offtake partners in different parts with different approaches.

Mads Nipper

executive
#100

We really think that although it might look like a lot, and most of them are early phase, this is in fact a smart approach for the coming decade to build something capable of commercial impact toward the end of the decade we just started.

Vincy Bu

analyst
#101

And if it's alright, may I ask a quick follow-up question?

Mads Nipper

executive
#102

Of course. Please continue.

Vincy Bu

analyst
#103

Right. As you mentioned, those 9 projects vary quite a bit in size. So I was curious — of all these promising projects, how many are actually in the U.S. and have begun construction?

Mads Nipper

executive
#104

Construction has only just begun for us. We've reached FID on just the smallest of these projects, which essentially serves as a technological proof of concept. That's where we'll gain our first hands-on experience actually working with it. It's located right in our own backyard in Copenhagen, where we have a couple of wind turbines and are collaborating with local partners to apply this to heavy transport. The real purpose here is achieving technological proof of concept, and among these projects, it's the sole one on which we've taken FID.

Marianne Wiinholt

executive
#105

Yes. To add to that, as with everything else, the current task is getting backing for these projects, since they're at an early stage. Those projects require either CapEx backing or a subsidy. And that's where all the attention is at the moment — on bringing the projects to maturity so you can apply for that support.

Operator

operator
#106

Rob Pulleyn from Morgan Stanley has our next question.

Rob Pulleyn

analyst
#107

I’m back just to ask one more follow-up. With what you said about some of these newer markets — and I believe Vietnam has now been added to that list — given how much scale matters for project economics and returns, could you discuss how you’re entering 6 new markets, as I think it now is, and what we should expect regarding whether you’ll concentrate your efforts within those 6 new markets? Or will you keep expanding into additional new offshore markets as they become available?

Mads Nipper

executive
#108

It's tough to give you a firm answer on that, Rob. But as you're aware, we operate with a regional structure overall — Continental Europe, the U.K., Asia Pacific, and so forth. That means, clearly, for certain functions of ours, there's a natural clustering of both resources and capabilities. And for some of our regions that are more mature, we also have clustering around operations and maintenance, plus in-service and setup work, which delivers a considerable advantage. Take a market such as the U.K., for instance, where the critical mass simply provides some efficiency and economy of scale. Whether there's any additional meaningful consolidation beyond the regional structure we already have is too early to say. But clearly, when we go into markets such as Korea or Vietnam — the latest emerging one now — that sits very much on the backbone of our Asia Pacific setup, where we have our Taiwan-based team and also the experience of expanding into Japan and so forth. So we're leveraging our global setup. Any further clustering, though, is too early to say. It would also depend on how we're able to build scale in the individual markets.

Mads Nipper

executive
#109

Regarding additional market expansion, you can never be certain whether the opportunity exists. We might decide to pursue it, but we're also careful about stretching ourselves too thin, so that we aren't fully committed in the places we decide to compete.

Operator

operator
#110

Mark Freshney with Crédit Suisse has our next question.

Mark Freshney

analyst
#111

Sure, I have a follow-up question about what the DKK 800 million in provisions indicates regarding the farm-down contracts. It seems that if you were responsible for replacing components at wind farms you farm down, or the partners element, does that mean you have issued multiyear guarantees and warranties to them that might expose you to additional costs later on? So I suppose what I'm asking is: how far does the liability extend on future projects -- or on existing projects going forward?

Marianne Wiinholt

executive
#112

That's a fair question, Mark. So when we sign these construction contracts, we normally provide a 5-year warranty. On certain projects of ours, that warranty has already run out. On others, a warranty provision is still in place. Every one of these warranties is in fact distinct. So we don't have one standard construction agreement. So in a sense, it's a bit early to say how this is going to play out. We also have projects with shared risk — in the Race Bank farm-down, for instance, the risk was shared. So there, it's clearly not on us. But yes, that's the picture. What we usually do when we sign a farm-down agreement is provide a warranty agreement, a certain amount. I won't give you the exact figure, but we have a standard approach for that. And what we've typically seen is that we've managed to release part of that warranty, since we haven't had many claims under it. This is in fact the first time we've had a situation where we needed to raise the warranty provision. And bear in mind that we have over DKK 50 billion of farm-down gains across recent years.

Marianne Wiinholt

executive
#113

So this isn't a very, very significant — of course it's significant, but in a way, in the bigger scheme of things.

Mark Freshney

analyst
#114

It's modest compared with the gains you saw in Q1, such as the DKK 200 million uplift from closing out earlier projects. I suppose you can't win them all.

Marianne Wiinholt

executive
#115

Nope. You've got it right.

Operator

operator
#116

The last question we have is from Jenny Ping at Citi.

Jenny Ping

analyst
#117

Allow me to pose a follow-up question. Going back to Slides 5 and 6, there's clearly a really sizable gap in the figures — the count of projects being built offshore versus onshore. And I suppose since only 2 offshore projects are under construction, that explains why you're pursuing the European onshore path. I know we discussed this back when you made the Brookfield acquisition, but I'm curious if you could expand a bit more on the kinds of assets you're seeking. Which asset types would fit well alongside the existing Brookfield acquisition, and on regions, could you provide a little additional detail there.

Mads Nipper

executive
#118

Yes. Certainly. Many thanks, Jenny. It — that is definitely not — in fact, there is no link at all between how many offshore projects we have and the — sort of expansion we're carrying out onshore. The Brookfield acquisition, along with the count of onshore projects, is a choice we're making since we see it as an appealing opportunity in its own right. And keep in mind that these 2 projects in Hornsea or in the U.K. and Taiwan will hopefully be followed very soon by a number of construction projects that are set to begin, particularly in the U.S. market. So we do believe — I mean at times we'll have more in construction and at other — at other times, less like now. But this has nothing to do with that. We know as a fact that we are going to be very busy over the coming 3, 5, 7, 10 years building offshore construction. So this has nothing to do with our onshore expansion.

Operator

operator
#119

Thanks. At this point, we don’t have any more questions. I’ll turn it back to the speakers in case they have any additional comments.

Mads Nipper

executive
#120

Yes. Thanks so much for being here and for those excellent questions. We really appreciate it. And as usual, if anything else comes to mind, please reach out — our IR team will be around, and we'll gladly help with any of them. So thanks a lot. Take care, have a wonderful day, and stay safe.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.