Thanks for joining the Ørsted investor call for Q3 2021. During this portion, everyone will be in listen-only mode, and a question-and-answer session will follow afterward. I'm glad to introduce today Mr. Mads Nipper, our CEO, along with Marianne Wiinholt, our CFO. You may now proceed.

Mads Nipper

executive
#2

Thanks so much, and good afternoon, everyone, and welcome to the Q3 2021 earnings call. This third quarter was unprecedented, given the European energy crunch and global supply chain pressures. But despite these unusual market — conditions, I'm happy to report that we've kept making headway on our construction program and have sustained high availability rates. In addition, our traders have done a great job managing market volatility through an active approach to risk management and have limited the impact on our financial position. What's more, we saw exceptional performance from our CHP plants and higher earnings from our gas business, which means we remain on track toward the full year guidance despite the lower wind speeds. Our performance has shown our company's robust business model, the strength of having a diversified portfolio like ours and the invaluable talent of our dedicated and hardworking teams across all businesses. We've also demonstrated strength in our business development activities this quarter, and most notably, we have moved further toward the final investment decision for our originally fully merchant German Borkum Riffgrund 3 project by executing on two strategic milestones. First, we signed an agreement with Glennmont Partners to farm-down 50% of the 900 megawatt project.

Mads Nipper

executive
#3

For Ørsted, this transaction is a first of its kind and forms part of the broader effort to de-risk the project ahead of the final investment decision — and it marks our first farm-down signed before we take FID. We take a lot of pride in this deal and see it as evidence of two things: continuing appetite for direct investment in our assets, and strong confidence in offshore wind. It also stands as proof of our well-established transaction model, under which we supply full-scope EPC contracts, 20 years of O&M, and a route to market. Second, we have now signed 450 megawatts of long-term fixed-price corporate PPAs for Borkum Riffgrund 3, counting the latest 100 megawatt long-term PPA with REWE Group. We are still working through an advanced pipeline of further PPAs, with the goal of trimming the merchant exposure that remains in the first 10 years as well as in the project's later years. I should also note that earlier this morning, we closed the agreement with CDPQ and Cathay PE to farm down 50% of our 600 megawatt Greater Changhua 1 in Taiwan. As was the case when we announced the deal last year, we are delighted with the transaction partners and with reaching the milestone of applying our farm-down model in Asia Pacific for the very first time.

Mads Nipper

executive
#4

New Jersey recently put out an offshore transmission solicitation, and we view it as an invitation to bring forthcoming offshore wind farms into the state's energy grid in the most efficient and cost-effective way possible. Given how committed we are to backing New Jersey's ambitious clean energy targets, we filed multiple strategic proposals for offshore wind transmission in New Jersey alongside our longtime partner PSEG. Those bids blend our know-how in offshore wind and transmission with PSEG's broad onshore transmission experience. We have also started several further key strategic partnerships spanning our geographies and technologies. In Vietnam, we signed a Memorandum of Understanding with T&T, the leading cross-industry company, to launch a strategic collaboration on offshore wind, which underscores our ambition to build a meaningful position in what we believe will be an attractive market in Vietnam. In the US, we signed an MOU with Williams, one of the largest pipeline operators in the States, to explore large-scale onshore wind energy electrolysis and synthetic gas-via-methanation co-development in Western Wyoming. In Germany, we signed an MOU with Uniper, one of Europe's largest electricity producers and a global gas trader. Together, we aim to install a 70 megawatt electrolyzer install by 2025, with the potential to upgrade the facility to 410 megawatts by 2030 and the potential to source the needed electricity with Ørsted offshore wind farms.

Mads Nipper

executive
#5

Also in Poland, we have signed a Letter of Intent with ZE PAK — the country's biggest privately held energy producer, which has ambitious renewable energy targets — to take part in the upcoming auction for seabed leases in the Polish portion of the Baltic Sea. Momentum also kept building in our onshore business through the third quarter. We brought online our second large-scale solar PV facility, Muscle Shoals in Alabama. We're continuing to advance the execution of corporate PPAs, and construction has begun on the 29 megawatt Lisheen 3 wind farm in Ireland. Taken together, these developments show once more how committed we are to being a leading global green energy major, with a diverse set of complementary assets and offerings in the global renewable market. Finally, in September, we announced that Neil O'Donovan will step into the role of CEO of Onshore and become a Member of the Ørsted Executive Committee. Neil came to Lincoln Clean Energy in 2011, and has served as the CEO — COO of Onshore since LCE was acquired by us in 2018. Given his extensive experience and unique knowledge of Ørsted's onshore acid bait base and development portfolio, along with his demonstrated leadership skill, we strongly believe Neil is the best person to take over as CEO of Ørsted Onshore and execute on our ambitious onshore growth strategy.

Mads Nipper

executive
#6

Before I go any further, let me take a moment to look back on my recent participation in COP 26. It's extremely clear that we urgently need a faster build out of renewable energy and green fuels, plus mechanisms that support the transition and keep stakeholders accountable. We have been very outspoken, and will remain so, about the need to speed up global climate action, and every now and then we get recognition for those efforts. As the most recent example, we're honored that the Science Based Targets initiative just approved our net-zero target for 2040 last week, which makes us the first and only energy company — and one of just seven companies worldwide — to have this net-zero target approval covering the full value chain. We're very proud of this recognition, as SBTI has now established Science Based criteria for long-term net-zero targets that are consistent with a 1.5 degree scenario. Companies must place a cap on 5% to 10% of the amount of residual emissions they offset through carbon removal projects, thus requiring companies to substantiate their net-zero plans with genuine long-term carbon reductions across scope 1 to 3. Turning to Slide 4, where I'll give you an update on our construction projects and pipeline.

Mads Nipper

executive
#7

At Hornsea 2, all foundations are now in place successfully, along with 142 array cables and 116 of the 165 turbines. First power is expected later this year, once the offshore transmission link is connected to the grid, and we aim to commission the wind farm in the first half of 2022. At Greater Changhua 1 and 2a, work on onshore — offshore construction keeps moving forward, and 11 of 111 jacket foundations have been installed. Turbine and array cable installation is slated to begin in Q1 2022, and we still anticipate commissioning the project before the end of 2022. COVID-19 restrictions continue to affect Taiwan, which could still potentially impact the construction timeline. Turning now to the three US onshore renewables projects we have under construction. At Haystack Wind, progress is on schedule, and construction should be finalized around the very end of this year. Meanwhile, we do expect minor delays on our US solar projects. Recent forced labor allegations toward a number of solar panel suppliers in China, as well as other issues related to potential increases in US tariffs on Chinese goods, have slowed solar panel deliveries into the US.

Mads Nipper

executive
#8

This will probably push the commissioning of Old 300 and the solar portion of Helena Energy Center from the first half of 2022, as previously anticipated, to later in 2022. We believe the present sector difficulty involving Chinese panels is temporary in nature, and we treat the matter of forced labor with the utmost seriousness. We have joined the Solar Industry Forced Labor Prevention Pledge, an industry initiative that will create a traceability protocol for the solar supply chain to determine where primary raw materials originate and to track how they are incorporated into solar modules. According to third-party evaluations, we are confident that the panels procured for Old 300 and Helena Energy Center contain no polysilicon from the Schengen region, and for future projects we have resolved to use only polysilicon free panels until the traceability issues are fully resolved. In Europe, construction of the two onshore wind farms — the 62 megawatt Kennoxhead project in Scotland and the 21 to 29 megawatt Lisheen 3 project in Ireland — is proceeding on schedule, and both projects are expected to reach COD in 2022. We are also continuing to move forward with our first renewable hydrogen project at the construction H2RES.

Mads Nipper

executive
#9

For the 2 megawatt electrolyzer project, the plan is to draw power from our two Avedøre Holme offshore wind turbines, and commissioning is anticipated during the first half of 2022. Taken as a whole, these projects amount to 16.5 gigawatts of renewable capacity that is either installed or under construction. Speaking of renewable hydrogen, I'd also like to note that we keep witnessing robust momentum across the globe, along with advances on our early stage projects. A major milestone was reached by our green fuels for Denmark project when it was designated an important project of Common European Interest — IPCEI, for short — under the EU program, which unlocks two additional funding pools for the project. On top of that, Lingen Green Hydrogen and HySCALE100, two of our other projects, have also been shortlisted for IPCEI status. Our awarded projects keep moving forward in development according to plan. In the US, we are carrying out our bid commitments aimed at creating local jobs and developing the supply chain. In New York, for instance, we joined Governor Hochul and our partner Eversource in recently announcing a $86 million investment — the largest single New York State offshore wind supply chain investment — that brings construction and steel manufacturing business to the Capital Region and Western New York.

Mads Nipper

executive
#10

We're still seeing the expected movement on permitting as well — for example, in August, when the Bureau of Ocean Energy Management, or BOEM, issued Sunrise Wind's Notice of Intent, which was consistent with what we anticipated. On top of that, it's encouraging that the US Interior Department began last month the work of pinpointing possible additional seabed lease offerings covering 2022 through 2024 across seven areas. For offshore wind developers around the world, having seabed available and permitting that is robust matters greatly, and we welcome the emphasis on clearing those hurdles in the US. As I said earlier, we've hit a number of milestones in developing our German portfolio, and we anticipate a final investment decision near the end of this year. Lastly, our later-dated awarded pipeline of projects in Taiwan, Poland and New Jersey is entirely on track. Moving to Slide 5, here's an update on offshore wind auctions and tenders coming up. Over the next 15 months, we keep seeing plenty of opportunities. Given our recent awards in Poland and New Jersey, the upcoming results we look for are Maryland and Japan, roughly at the end of this year or in the very early part of next year.

Mads Nipper

executive
#11

In Maryland, we placed a bid covering 760 megawatts via the Skipjack 2 wind project. That came after the Public Service Commission asked for as much as 1.2 gigawatts of offshore wind. Over in Japan, we put in three bids alongside our joint venture partners: one with TEPCO and Choshi, and two with JWD and EURUS, in Noshiro and Yurihonjo. That auction covers a total capacity of 1.5 gigawatts, divided across four zones. As you might have seen, we chose to sit out the recent auctions in Germany, France and Massachusetts. That shows we are willing to prioritize where we put our effort and to remain financially disciplined, concentrating on opportunities that match our strengths. And our substantiated opportunity pipeline of more than 50 gigawatts — oversized as it is — gives us room to be selective about which auctions and tenders we join, so we can optimize the development, sizing and timing of our build out in each region. On top of that, we are highly pleased with our 2021 auction success rate, having secured 3.6 gigawatts so far this year. All in all, I continue to be satisfied with how we have progressed in 2021, where — despite the difficulties tied to extremely extreme energy market volatility, COVID-19 and pressures on global supply chains — we managed to work around those challenges and protect the Group from severely negative effects.

Mads Nipper

executive
#12

We owe all of this to our gifted, driven teams, whose active risk management, preventive and forward-looking steps, and unrelenting emphasis on execution made it happen. With that, I'll pass the word to Marianne now.

Marianne Wiinholt

executive
#13

Thanks, Mads, and good afternoon, everyone. Let's begin on Slide 6, where I'll walk through EBITDA for Q3 2021. Group EBITDA came in at DKK 3 billion, which is down versus last year, driven by weaker earnings from our operating wind sites, while our CHP plants and gas business made a positive contribution to the results. In Q3 2021, we saw a positive effect of DKK 168 million from ceasing to report according to the business performance principle, whereas Q3 2020 included earnings of the same magnitude from a distribution, B2C and city light businesses that we have divested. Earnings from offshore sites took a negative hit from wind speeds below the norm. In Q3 2021, wind speed was 7.6 meter per second against a normal wind of 8.3 meter per second. The gap in wind speed versus the normal wind quarter translates into an EBITDA impact of roughly negative DKK 600 million. I'll note briefly here that, looking at our historical production levels, we see no sign of structurally lower wind speeds. And even though Q3 finished 8% below the norm, we have seen wind speeds above the norm in October. As we have known since the start of the year, and as we also reported in the earlier quarters of 2021, we have had a negative impact from higher transmission tariffs, following the divestment of the offshore transmission assets at Hornsea 1 in Q1 2021, as well as lower earnings from Hornsea 2 because the subsidy period ended in October 2020.

Marianne Wiinholt

executive
#14

Beyond that, earnings from our power portfolio came in lower, reflecting increased balancing costs alongside reduced volumes. Partially counterbalancing those adverse impacts was the contribution from the final 400 megawatts of Hornsea 1, which began receiving CFD in April 2021. During Q3 2021, our offshore partnerships generated no meaningful EBITDA. By contrast, partnership earnings in the prior year stemmed from construction of Virginia coastal wind and a construction gain on Hornsea 1 tied to reduced CapEx. Our onshore segment posted a 34% earnings rise, powered by growing output from the wind farms Willow Creek, Plum Creek and Western Trail, together with the solar PV farms Permian Energy Center and Muscle Shoals. That substantial increase in generating capacity was partially counterbalanced by weaker wind speeds, since portfolio wind speed averaged 6.2 meters per second against a normal 6.8 meters per second. We also recorded elevated fixed costs, M&A costs and project development expenses stemming from ongoing expansion of our onshore business. Within Bioenergy and others, earnings rose substantially, propelled by outstanding results at our CHP plants thanks to elevated power prices and spreads that drove greater generation, along with increased sales of ancillary services.

Marianne Wiinholt

executive
#15

Gas markets and infrastructure also drove the strong outperformance in Q3 '21, thanks to renegotiated gas purchase contracts and solid underlying results in a highly volatile, bullish gas market, where we could optimize purchases under our long-term contracts. In earlier quarters, gas business earnings benefited from rising gas prices, which led to greater revaluation of gas storages. Even with the substantial gas price increase in the quarter, we did not see a comparable positive effect, since the forward curve rose more than the spot price. Mark-to-market hedges hurt us, offsetting the positive revaluation effect. Moving on to Slide 7, which covers net profit, net debt and credit metric: net profit for the period came to DKK 0.5 billion, well below last year, because Q3 2020 included the gain from divesting our power distribution, residential customer and city light businesses. Net debt at the close of Q3 was DKK 21.2 billion, up DKK 9.1 billion in the quarter. Cash flow from operating activities reflects EBITDA as well as tax — equity contributions from our partners at Western Trail and Muscle Shoals in the US, offset by hedge margin payments of DKK 2.4 billion, and higher spending to fill gas storages given the substantial gas price increase during the quarter.

Marianne Wiinholt

executive
#16

Gross investments came to DKK 8.8 billion, powered by what we keep putting into offshore and onshore and solar PV farms. Our key credit metric, FFO to adjusted net debt, was 42% for the 12-month period ending in September 2021 — well ahead of where we want that metric to be. Before I go on, I want to pause and acknowledge how inventive our finance and sustainability teams continue to be; working together, they built and just recently signed our very first sustainability-linked revolving credit facility. Under that revolver, the interest margin is tied directly to how well we do at cutting carbon emissions and at delivering on our ambitious green investment program. Turning to Slide 8, on our financial and non-financial ratios: return on capital employed came in at 12.9%, and the rise versus last year is attributable to higher EBIT over the 12-month period. During the first nine months of 2021, the taxonomy-eligible share of our revenue was above 65%, our share of EBITDA was above 90%, and the share of gross investments was above 99%. We expect the taxonomy-eligible revenue share to grow in the years ahead, since we plan to phase out coal completely in 2023. Greenhouse gas emission intensity went down, even though the share of renewable generation was unchanged.

Marianne Wiinholt

executive
#17

The reason for this was a greater relative proportion of heat and power produced from biomass because of colder weather, and because biomass stood out as the fuel offering the best cost efficiency for power generation across much of the quarter. Moving on to safety, we've recorded a 30% drop in the count of injuries. Consequently, the total recordable injury rate has fallen to 3.0 across the first nine months of 2021. And lastly, let's move to Slide 9 and the 2021 outlook. Once more we restate our initial full year 2021 EBITDA guidance of DKK 15 billion to DKK 16 billion, covering — sorry, not covering, excluding the impact from new partnerships. And just like in Q2, we continue to anticipate a result at the low end of that range. This guidance rests on an assumption that wind speeds will be normal for the rest of the year. For bioenergy and other, we have revised the directional guidance to significantly higher from higher, reflecting the ongoing strong performance and improved earnings from the CHP plants and the gas business. Gross investments for 2021 are expected to reach DKK 39 billion to DKK 41 billion, which remains unchanged compared with the guidance given in the first half year report.

Marianne Wiinholt

executive
#18

So that brings us to the Q&A portion. Operator, if you'd go ahead and open the lines.

Operator

operator
#19

That wraps up our presentation, and now we're glad to take your questions. Operator, please go ahead. Our first question comes from Robert Pulleyn at Morgan Stanley. Sir, the floor is yours.

Rob Pulleyn

analyst
#20

Hello, good afternoon, and thanks. Yes, I have just the one question. Would you mind walking us through the year-over-year change in EBITDA for the offshore wind sites? The bridge items, among them the weaker wind speed, appear to account for only roughly 50% of that year-over-year movement. So should we take it that the rest — the DKK 700 million — comes from hedging losses or from balancing costs tied to purchasing volume back in the market? Thank you very much.

Marianne Wiinholt

executive
#21

Appreciate the question — I'll go into more detail on that. Looking at the wind effect, like I mentioned, it came to DKK 600 million in the quarter versus what a normal year would bring. However, since Q3 of last year had strong wind, the year-over-year effect works out to DKK 800 million. After that, the ramp-up effect from Hornsea 1 and Borssele is fairly limited, since Borssele was essentially producing at full capacity last year and we've since farmed down half of Borssele. We've also seen a negative impact from over-hedging of roughly DKK 100 million. And as we've stated before, we have these higher to newest costs — well, nothing new on that front. What is new, though, is roughly DKK 200 million in additional balancing costs, stemming from the high balancing cost caused by markets that have been very volatile. And then you also have to factor in Hornsea 2 costs, and Changhua cost as well, which are operating costs we guided to at the start of the year. Then there's Hornsea 2 going off subsidy. So when I put all of that together in my brief rundown, nothing is left unexplained, and I'm unable to arrive at the DKK 700 million unexplained figure that you referred to.

Rob Pulleyn

analyst
#22

All right, that's quite clear. The way you laid out Hornsea, Borssele, plus those 2 points about hedging and balancing, closes the loop. So, thanks. I'll hand it back to you.

Marianne Wiinholt

executive
#23

Appreciate it.

Mads Nipper

executive
#24

Thanks.

Operator

operator
#25

Appreciate that, sir. Our following question comes from Mr. Kristian Johansen at ACP sic — Danske Bank. Go right ahead, sir.

Kristian Johansen

analyst
#26

Yeah, thanks. My question is about your farm-down. I'll be honest — the farm-down of Borkum Riffgrund 3 caught me a little by surprise at this point in time. So with that in mind, could you bring us up to date on the farm-down process for the wind farms — whether anything is currently underway, and when you plan to start the next ones?

Mads Nipper

executive
#27

Yes, Kristian, I can definitely speak to that. As you're aware, Borssele 1 and 2 have been farmed down, that's now complete, and we've also announced the same for Borkum Riffgrund 3, and as we announced just this morning, the Changhua 1 farm-down has closed as well. Beyond that, Hornsea 2 is in a farm-down process, and those are the active farm-down efforts we're involved in. But we were very happy to carry out the Borkum Riffgrund 3 farm-down, partly since it marks the first occasion where we've done a pre-FID farm-down on a project that was previously fully merchant, and partly since it comes during an uncertain period — sort of a time with plenty of uncertainty and volatility. It was simply a really good confirmation that investor interest in our assets remains as strong as it has been.

Kristian Johansen

analyst
#28

Alright, so regarding a few of your US projects where your ownership stake exceeds 50% — when do you anticipate kicking off a farm-down process on those?

Marianne Wiinholt

executive
#29

At this point, we aren't planning to farm down the remaining 25% of Ocean Wind 1. That said, it could happen at some point—maybe we do it one day—but nothing is in progress on that front right now.

Kristian Johansen

analyst
#30

Great <<inaudible>>, thank you.

Operator

operator
#31

Much appreciated, sir. Our next question comes from Mr. Sam Arie of UBS. Sir, the floor is yours.

Sam Arie

analyst
#32

Good afternoon, everyone, and thanks as always for today's presentation. Look, I think there's just one question I want to raise, and it goes back to the subject of wind speeds. Obviously we've had an abnormal quarter, I know that. But with everything going on with the weather, the temptation is to ask whether we still know what normal even is. I know you speak with your experts about this constantly. And I'm sure at some level nobody has the answer regarding what future wind speeds will be. But my question is this: at this stage, are you making any changes to your assumptions about long-term wind speeds? Or do you see any risk to your assumptions on wind load factors for the existing wind farms, the kind you have now? I was really interested in whether you could share any insight with us about whether this recent very low wind in the North Sea is truly just a random anomaly, or whether we should be worried that it becomes a more regular occurrence.

Mads Nipper

executive
#33

Sure, thank you very much. The brief response is that none of us, in our view, ought to be concerned. As you mentioned, we're naturally, at all times, both collaborating with specialists in this field and bringing in our own specialists, and we're carrying out every sort of analysis. And beyond that, the extremely useful Bernstein report, which not only confirms this correlation between temperature and wind speed, but likewise pulled out the various scientific studies that have been conducted. And in fact, a team at Princeton University has in reality shown that across a 40-year span, wind speeds have in fact risen somewhat. And we've run simulations as well on what the 1-year, 5-year or 10-year rolling averages would in fact have been if all of our built assets were back from 1999, and that would in fact have been a curve rising somewhat. So the brief response is that unless something entirely out of the ordinary began this year, and we have no reason whatsoever to think that would be so on the basis of any other indicators. Our belief is that it's an anomaly, and we were glad as well to see that, as Marianne said briefly, October, which is in fact a fairly large wind month, came in somewhat above average.

Mads Nipper

executive
#34

And so, as we finish the longer version of that answer, we remain quite convinced that over time this will fully normalize to the trend we have witnessed across the past 20-plus years.

Sam Arie

analyst
#35

All right, that's really helpful, and it's a very useful answer regarding today's context. So, thank you.

Operator

operator
#36

Appreciate it. Our next question comes from Alberto Gandolfi at Goldman Sachs. Alberto, the floor is yours.

Alberto Gandolfi

analyst
#37

Thank you, and good afternoon. I appreciate you taking my question. My question concerns returns, specifically on the backlog of awarded projects. I just want to verify this on the basis of two aspects. So, your target is a project IRR of 150 to 300 basis points over WACC. Given the supply chain disruptions you're seeing at the moment, and taking into account the current level of raw material prices, I was wondering whether you can give us an update on that 150 to 300 if we were to take a snapshot of the situation as we see it today. Or perhaps you could tell us that what we're seeing today is temporarily transitory and that we should disregard it entirely. Maybe you can help us navigate a bit of a roadmap, or returns on your awarded projects, particularly those due to come in 23, 24, 25 in the earlier portion of the backlog. Thank you so much.

Mads Nipper

executive
#38

Yes, thanks a lot, Alberto. I can start us off, and Marianne can add to that. The short answer is that we haven't — we have not observed any shift in the picture we saw following Q2. That remains what we describe as a moderate effect on the mid-term pipelines. Just to repeat the whole context, the two projects under construction — Hornsea 2 and Greater Changhua 1 and 2a — are fully locked, with very, very limited, if any, impact from the recent price searches on commodities. And for those that are longer-term, we don't need to take a FID anytime soon, so we have the flexibility to lock when it is right to do so. But on the — as you asked more specifically, the mid-term here, we are well developed in, for example, the German development program and also on under north east programming in the US and on an Ocean Wind; we are pretty progressed and have locked in, made contracts on relatively big shares already. And as we believe, we mentioned before, we have already locked in 70% of the steel exposure and now US practice already. That said, the total exposure to CapEx on those mid-term projects we estimate to sort of be mid single-digit, which we don't expect to change anything on the guidance to stay within the range of spreads to WACC that we have that we have announced.

Alberto Gandolfi

analyst
#39

Thanks a lot.

Operator

operator
#40

Appreciate that. Our next question comes from Mark Freshney at Credit Suisse. Mark, the floor is yours.

Mark Freshney

analyst
#41

Hi, thanks so much for taking my question. On the gas in storage and the contract renegotiations, could you clarify that for me? Because it seems like in some quarters you record a positive or negative mark-to-market on the gas in storage. In other quarters, like this one, we've seen the effect of forward hedging move against spot market valuations. And you also mentioned a renegotiation of a gas contract. My understanding was that the legacy gas contracts were renegotiated, I believe, three, four years ago, and you had the positive gains. So could you talk around that piece and give us some clarity? And if I may be cheeky and ask a follow-on, or a question 1b, what's the long-term outlook for that business? Because evidently housing fossil fuels is not — should not be consistent with net-zero. So if you could talk through those bits, that would be fabulous. Thank you.

Marianne Wiinholt

executive
#42

Yes. So, Mark, as you've seen, we've experienced fairly considerable volatility in our gas business because of these storage impacts. And that's even though it's actually a margin business, where, you know, we lock in margins right away whenever we have the exposures. We're now working on changing some of the accounting principles around the storages, and probably by next quarter, I think we'll have gone through with that. And then you'll see less volatility. In this quarter, in particular, we've had some good optimization gains from the gas business. Because we've been able to lock in solid profits, in a way. And then we have these renegotiation gains, which, according to the contracts, we're not allowed to elaborate on. I don't think you can expect any more renegotiation gains going forward, because in a way we — these are, in a way, legacy contracts that, in a way, will disappear over time. So therefore, I think this is the last time you see this kind of one-off gain from renegotiation. And on your question, on Scope 3, and you know we're having fossil fuels in our mix. Yes, you're right now, and Mads talked about this net-zero scope 1 to 3 confirmation that we got from Science Based Target, in a way that, of course, means that we need to go out of gas, and we will go out of gas, and these contracts are, in a way, declining and expiring over time.

Marianne Wiinholt

executive
#43

So that’s going to happen on its own.

Mark Freshney

analyst
#44

Alright, thanks a lot.

Operator

operator
#45

Appreciate that, sir. Our next question comes from Mr. Peter Bisztyga with BA Securities — correction, Bank of America. The line is yours.

Peter Bisztyga

analyst
#46

Good afternoon. Peter Bisztyga here, from Bank of America. So this morning we saw a significant profit warning from Vestas regarding supply chain bottlenecks and cost inflation. And, you know, at the same time, we're hearing from you folks that kind of everything is fine, and that you're handling everything very well. So I'm rather curious, you know, why is it that Vestas seems to be operating on different planets, in different universes? You know, can we expect that at some point there will be some blowback on you from the problems Vestas are having, you know, or indeed from any of your other suppliers — you know, could somebody at some point trigger force majeure, because somebody is trying to renegotiate a framework agreement or a contract? So, you know, if you could just help us sort of reconcile those two different worlds, that would be very interesting.

Mads Nipper

executive
#47

I think what I mean is that we hold back from discussing matters that are more specific to Vestas or to the other supply chain partners we work with. But obviously, I think the character of our business is that we will usually be committed for a longer stretch of time. And then only if there are sort of significantly longer stretches of sustained high inflation would it begin to affect us to anywhere close to the same degree. I think it's — it's just the character of the business, short-term versus somewhat long or mid-to-longer term. I think that's what accounts for the difference between the two companies. But fundamentally, we as a developer and someone who is a manufacturer, the whole business model is one that we don't think can be directly explained as such. And only in the case of long-term, truly long-term sustained inflation levels would this be something that has an overall impact. But in that case, it will affect all developers and — and that will mean that — that will also mean that the bid prices that all of us will come with will change. So we remain confident that apart from sort of the mid-term projects I already mentioned that we have a moderate impact on, we think that our exposure going forward also on upcoming bids that we'll submit is limited.

Peter Bisztyga

analyst
#48

And so nobody has come in and tried to reopen contracts or framework agreements? As far as you're concerned, that side of things is holding up solidly?

Mads Nipper

executive
#49

Yes.

Marianne Wiinholt

executive
#50

No, we haven't had —

Mads Nipper

executive
#51

Nope, we haven't had any. No — we — they're solid. All of them are — sorry. Yeah, yeah, no, nobody has called us, no, we — those are secured.

Peter Bisztyga

analyst
#52

Understood — thanks.

Marianne Wiinholt

executive
#53

And keep in mind too that the OEMs don’t bear commodity risk — steel, for instance — that risk sits with us. So in a sense, we now actively go out and have hedged part of that exposure. So in that respect, the OEMs are, in a way, not fully exposed.

Peter Bisztyga

analyst
#54

All right, thank you so much.

Operator

operator
#55

Thank you, sir. Our next question comes from Madam Deepa Venkateswaran at Bernstein. Madam, the floor is yours.

Deepa Venkateswaran

analyst
#56

Thank you. This is Deepa Venkateswaran from Bernstein. I appreciate the earlier mention of our report. My question concerns your farm-down to Glennmont Partners. Obviously, Mads, you said you completed it before because it reduces risk. I also notice you have assured them of a specific price. So I just want to understand the reasoning there, and whether you generally — you will have back-to-back PPAs, and so once the full 900 megawatts of PPA is in place, effectively it is back-to-back, either the PPA you give Glennmont versus the one you have from the corporate. If you could just point out what residual risk on this project will remain with you after FID, that would be helpful.

Marianne Wiinholt

executive
#57

Yeah. Great question, Deepa. Only a portion of that is secured with fixed prices toward Glennmont. And you're right, the plan is for us to do back-to-back PPAs. I think we're actually succeeding at that in a way. So once we're finished, the remaining risk will essentially be none.

Mads Nipper

executive
#58

I can even add that a number of those negotiations are quite far along. So we’re quite confident that what Marianne describes is going to happen.

Deepa Venkateswaran

analyst
#59

Alright, thanks.

Operator

operator
#60

Thank you, Madam. Our next question comes from Mr. Dominic Nash at Barclays. Sir, the floor is yours.

Dominic Nash

analyst
#61

Thanks for taking my question. I'd like to ask about your bioenergy and other division. Clearly, you're pointing us toward a notably higher figure for 2021 than what was expected before. Could you break down the big change we're seeing right now — how much of it still comes from trading? What portion reflects underlying performance that might carry on in later years? In other words, how much of this improvement do we think bioenergy can genuinely hold onto going forward? Thank you.

Marianne Wiinholt

executive
#62

Yeah. Yes, to be honest, not much of that is sustainable, because there are two effects here: these renegotiations, which are one-off, and then the solid performance in the underlying gas business, which will vary from year to year in a way — we could have some good years, but it's not a big deal. Where we see a significant overperformance is at the CHP, the biomass-fired CHPs. And you could say that we actually view it as a very efficient hedge against low wind, because in a way, low wind has contributed to high energy prices. And with high electricity prices, in a way you'll have significant earnings and high production at our CHPs. So if we keep seeing elevated energy prices, we'll keep earning a lot of money from the CHP, but if we — as we expect after winter 2022 — see prices decline again, then in a way you'll see normalized earnings from our CHPs.

Dominic Nash

analyst
#63

I appreciate that.

Operator

operator
#64

Thanks very much, sir. The following question comes from Mr. David Paz of Wolfe Research. Mr. Paz, the floor is yours — go right ahead.

David Paz

analyst
#65

Hi there, and thanks for taking my question. Am I coming through okay?

Mads Nipper

executive
#66

Yes, we hear you.

David Paz

analyst
#67

Alright, thanks a lot. So, regarding the clean energy tax credit provisions that were put forward in the US Congress last month, if that legislation were to pass in the form it's written, how would that affect your business in the US?

Mads Nipper

executive
#68

My apologies — I wasn't able to catch what you asked. Would you mind saying it again?

David Paz

analyst
#69

My apologies for that. Are you able to hear me now?

Mads Nipper

executive
#70

Yes, that sounds great.

David Paz

analyst
#71

Thanks. With regard to the clean energy tax credit provisions that came up in the US Congress last month, if that bill were passed in its current form, what effect would it have on your US business?

Marianne Wiinholt

executive
#72

Would you like me to respond? Yes. So essentially, you're referring to a direct award, should that be approved. And additionally, the PTC and ITC extensions—just to make that clear.

David Paz

analyst
#73

That’s right.

Marianne Wiinholt

executive
#74

Yes, okay. So let me begin with offshore and then move to onshore afterward. On the offshore side, having a direct award will help us, since we avoid, in a sense, the discount that comes from having to sell the tax credits. And for our business cases, in a sense, that is really what we hope for. With certain contracts, such as the one in New Jersey, some of that will have to be passed along to the ratepayers, but on some of the other projects, we can retain it for ourselves. Then, turning to our onshore business, the extension of the tax credits is, of course, an advantage for us. And definitely something, in a sense, that benefits our business. So overall, in a sense, the entire package is, in a sense, something we support 100% and hope makes it through the hallway.

David Paz

analyst
#75

All right, excellent. Thanks. I'll rejoin the line.

Operator

operator
#76

Thanks, and now we’ll take a question from Klaus Kehl at Nykredit. Klaus, the floor is yours.

Klaus Kehl

analyst
#77

Yes, hi there. My question concerns the extremely elevated power prices we're seeing in Europe at the moment. So what I'd like to know is how that impacts PPA prices. And more broadly, how does it influence the appetite for entering into new PPA contracts? Any thoughts you have on that would be helpful.

Mads Nipper

executive
#78

Yes, thank you very much. I mean, clearly, it — I'm certain this reminds someone that we can't simply assume power price development. But honestly, we still clearly see and hear that what fundamentally drives these large-scale corporate PPAs is the need for corporates to decarbonize their businesses. So this might serve as a reminder, and it might be something that gets them to speed up. But we don't see this as something that significantly drives prices up, because on a PPA of 10-plus years, I think nobody expects this to be anywhere close to a normal situation. So we stay convinced that the underlying decarbonization drive is the main reason for it. And that there's no structural price change to the level we can — the price level we can obtain based on current prices.

Klaus Kehl

analyst
#79

Okay, great. Thanks a lot.

Operator

operator
#80

Thank you, sir. The next question comes from Mr. George Musk — sorry, John Musk of Bank of Canada. Sir, go ahead, please.

John Musk

analyst
#81

Yes. Good afternoon. This is John Musk. On — may I just ask about the other line, project development in your offshore business, which appears to be trending below last year? I believe the guidance was for it to come in above last year? What is causing that to perhaps be a little better than expectations? And where do you expect that to turn for the year? And then, linked to that. It's sort of the reverse in the onshore business, where overhead costs are somewhat higher. So what is pushing those numbers up?

Marianne Wiinholt

executive
#82

Yes, absolutely. So if you look at offshore first, you’re correct that our spending is lower, and that’s largely because during the previous year we had significant expenditure in the US on both Ocean Wind and for Northeast this year. And it’s particularly in the US where those costs run very high. So this year, we aren’t spending the same amounts, and we don’t anticipate doing so. As a result, we expect to see, in a sense, an overperformance or lower costs on that front. On onshore, as you mentioned, it’s the exact reverse. That’s heavily driven by the raised ambitions we presented at the CMD. So we’re spending more — for instance, we’ve put money into M&A activity, Brookfield. And we’re also, in a way, stepping up project development to match those higher ambitions.

John Musk

analyst
#83

Alright, thanks.

Operator

operator
#84

Much appreciated, sir. Moving on, we have a question from Brian Finkelstein of Key Group. Brian, the floor is yours.

Brian Finkelstein

analyst
#85

Appreciate you taking the question. I’ve got a quick one: you talked about wind speeds affecting offshore, but the load factor of 27% compared with 35% in the prior year seems to have a bigger effect on power generation. Do you know the reason the load factor is lower? And, I suppose, on a TTM basis, it’s still well under the guidance of around 48% to 50% for load factor?

Mads Nipper

executive
#86

Yeah. The brief response there is that no direct link really exists between when production ends or the load factor and wind speeds. So when wind speeds drop, when they come in lower, we end up taking a hit on production that's more than proportional, and particularly, say, in Q2, a month with relatively low wind, production actually comes in proportionately below how much the wind itself falls short of normal speeds. On the other hand, when we're already at a higher production level or higher wind levels, it doesn't strike quite as hard. So the explanation comes down to this: when wind is low, and above all when it's low during some of the seasonally lower wind months, the load factor takes an over proportional hit. That's about as untechnical as I can put it.

Marianne Wiinholt

executive
#87

Right, but the shape of the power curve is what drives that. If it’s — I’m getting a bit more technical here.

Mads Nipper

executive
#88

Correct.

Marianne Wiinholt

executive
#89

Yeah.

Brian Finkelstein

analyst
#90

Right, understood. So over time, you guys have aimed for that 48% to 50%?

Marianne Wiinholt

executive
#91

Yeah —

Brian Finkelstein

analyst
#92

My understanding is that this was a one-time item.

Mads Nipper

executive
#93

Correct.

Brian Finkelstein

analyst
#94

But I suppose the way to view that over time — because that's a major factor in just —

Marianne Wiinholt

executive
#95

Right. In a sense, that was a target we established at the last CMD — not the CMD this year, but the previous one. As our portfolio expands, we're going to see load factors that differ quite a bit across regions. Broadly speaking, apart from Taiwan, where load factors run very high, you find low wind speeds in places such as Korea and Japan. That, of course, brings the load factor down. And in certain other countries we're moving into, we're likewise seeing lower wind speeds. So we haven't revised the guidance, because honestly — it's somewhat hard for us to predict where the next project will be won. And take the US alone as an illustration: wind speeds are considerably higher up in the north, and the further south you go, the lower the wind speed becomes. So that's simply to explain why we haven't updated it.

Brian Finkelstein

analyst
#96

That's fine, of course. And looking at it over the long term, offshore wind is going to see a big build out. How do you go about balancing the volatility on something like a year-over-year basis, simply because it just can't be that large?

Marianne Wiinholt

executive
#97

In a sense, there's an advantage to holding a bigger and more varied portfolio. Take this year: had Changhua been operational, we would have seen that wind speeds across Asia have actually been considerably above what a typical year brings. And through a great deal of analysis, we've shown that, in a way, the more diversified the portfolio becomes, the smaller the wind-speed deviation turns out to be when viewed at the portfolio level. So that's something we look forward to.

Brian Finkelstein

analyst
#98

The — no, I get it from a portfolio standpoint, but when you look at it regionally, it really feels like the impact could be huge if a lot of wind farms get hit simultaneously, whether that's on the positive or the negative side.

Marianne Wiinholt

executive
#99

Yet that is essentially the pattern showing up this year — most of our wind farms sit in the North Sea. So in a sense, low wind speeds there are hurting us. And this is, in a way, a matter of timing, since we fundamentally think long-term wind speeds stay quite steady. It's a volatility that, in a way, this industry simply has to accept.

Brian Finkelstein

analyst
#100

Alright.

Marianne Wiinholt

executive
#101

Even so, this year has been extreme in a certain sense.

Brian Finkelstein

analyst
#102

All right, thank you very much.

Operator

operator
#103

Much appreciated, sir. Our following question comes from Mark Freshney of Credit Suisse. Sir, the floor is yours.

Mark Freshney

analyst
#104

Hi there. I’ve got a question specifically about floating. I understand that historically a great deal of your internal R&D has centered on fixed bottom. And we’re aware that you’ve partnered with some companies to examine the Scottish leasing, which appears as though it will be very much floating. But could you bring us up to date on the work you’ve been carrying out internally on floating? And do you think — at what point do you think floating will have to become mainstream, given things like seabed whites, et cetera, and shortages of seabed? What’s your thinking in this area? Thank you.

Mads Nipper

executive
#105

Yes, thanks very much, Mark. Yeah, I can provide a fairly quick update on that. You're correct that we partnered with BlueFloat and Falck Renewables on the floating bids in ScotWind. And in a similar vein, we announced our interest in the Utsira area — the northern section of the Norwegian seabed that was made available. And we're actually seeing that this year was kind of the first year in which floating seabed began to be made available at scale. So probably 2021, looking back, is the year when our floating activity really started to kick in, which is also among the reasons this year was when we changed our CMD. We actually changed ourselves, and now we will engage. We're in discussions with various partners — so not only partnering on projects the way we do with BlueFloat, but also potential partners on different technologies. We're engaging with the people who hold the most experience, we're technically investigating various floating platforms. We're mobilizing our own internal teams, asking what would make sense for us in order to accelerate a proprietary capability, and where it makes the most sense to work with partners.

Mads Nipper

executive
#106

And all of that has been sort of sped up during this year — it's all been accelerated over the course of this year. And we feel confident that we will be — sort of, once hopefully — that opportunities would materialize more specifically from either Scotland, Norway, could be California, or some of the Asian markets, and we're confident we will be ready. As for when it will be mainstream? Well, by the end of the decade, it will still be a relatively small part. And we expect that floating being cost competitive is unlikely before earliest 2035. But there will probably, or very likely, also be special subsidy programs that could still make those projects interesting, which is why we're also bidding in for seabed as we speak.

Mark Freshney

analyst
#107

Thanks — I appreciate that, thanks a lot. That’s quite interesting, thank you.

Operator

operator
#108

Much appreciated, sir. The next question comes from Madam Jenny Ping at Citi. Madam, the floor is yours.

Jenny Ping

analyst
#109

Good afternoon, and thanks so much. Let me return to Borkum 3, since that project has historically done a very good job of giving visibility and transparency on contracts. Now that we're looking at PPAs and back-to-back hedging, how will Ørsted deliver that same level of transparency for some of these corporate PPA-type assets going forward, so we get a better sense of the risk Ørsted is taking on? And since we're already on the second round, I'll squeeze in my second question too. Going back to what you said earlier, Marianne, about the risks of taking on steel risk and the fact that the OEMs don't bear the risk that Ørsted does — could you elaborate a bit on that? Because at the Capital Markets Day, I recall, there were some discussions about using derivatives, but my understanding is that derivatives aren't really — they're not liquid enough to handle the risks around steel, and I was under the impression that the OEM took some of these risks. So any further clarity on that would be great. Thank you.

Marianne Wiinholt

executive
#110

Yes. I'll take the first one first, on the corporate PPAs. Of course, we're very transparent about everything except the price for these PPAs. So in a way the credit — the potential credit risk, in a way, you know exactly who the counterparty is, you know the term of the PPAs, but in a way, revealing the price is not something we'll be able to do, because that is so commercially sensitive. But I think, for example, through — we have shared the slide on the Borkum 3 farm-down with estimating the gain from the transaction and et cetera. So, I think we're as transparent as we can be, but unfortunately, we cannot be more transparent than that. Then on your next question, on steel. I'm talking now about offshore. So just to make that clear. At the CMD, we said that we had locked in quite a significant part of the steel exposure for our next projects. And we said in the northeast cluster we had locked in around 70%, we also locked in a significant part of Borkum Riffgrund 3. And we did that before steel prices increased and to be honest, in a way, we didn't even foresee at that time that prices would increase.

Marianne Wiinholt

executive
#111

Still, in a sense, we were fortunate that we had gone ahead with it. Regarding hedging, yes, your point is correct. What we've done to lock things in hasn't come via hedging — it's come via direct agreements made with the supplier. That said, looking ahead, we're in a sense working toward being able to hedge the steel, and that will be done by way of proxy hedging — in other words, locking in the iron ore, the cooking coal, et cetera, so that we obtain what we regard as a very efficient hedge. In a sense, we are very, very close to already being ready to execute on that.

Jenny Ping

analyst
#112

Thanks. Sorry, so does that mean you’re holding steel in warehouses?

Marianne Wiinholt

executive
#113

No, that's held by the supplier. We did sign a purchase agreement with fixed prices, though we aren't maintaining the warehouse.

Jenny Ping

analyst
#114

That's great. Thanks so much.

Operator

operator
#115

Much appreciated, Madam. The following question comes from Deepa at Bernstein. Madam, the floor is yours.

Deepa Venkateswaran

analyst
#116

Thanks. My question concerned the overall 2040 net-zero goal. And I wanted to probe a little further on how you intend to cut scope 3 — most of your scope 3 at present either originates in the gas supply division or consists of emissions within the supply chain for wind turbines and so forth. So could you address that, and more broadly, the notion that when your gas contracts run out, you simply close that business? And it wouldn't be around in 2040? Or instead, will you shift into hydrogen contracts or something different?

Mads Nipper

executive
#117

Right, thank you very much, Deepa. The response to that is: to meet the SBTI requirements, we have to do both things. So it's both — at that point we won't have our gas business. Sure, a renewable hydrogen business will exist, but it will be renewable. And so it will be net-zero. But we will — we expect that once these heritage contracts expire, that's the moment when we will, over time, also phase out, and by 2040 we won't have any gas business at all. We have a really ambitious plan, quite a bold one, for decarbonizing the supply chain, and that is absolutely necessary. We're already taking short-term steps right now and working with our top partners, requiring them to use green power in the next fairly limited number of years. But even more importantly, we're engaging structurally — for instance, in first-movers coalition initiatives like steel zero, where we're a founding member and where we're involved in the steel industry. That way we can structurally help not only in general, helping the individual supplier or partner that we have, but also structurally help decarbonize the hard-to-abate sectors that we buy a great deal from.

Mads Nipper

executive
#118

So those are the plans we're summing up, with some phasing out of gas, but very importantly, we're also engaging deeply both with individual suppliers and at an industry level for those areas that would be hardest to engage with.

Deepa Venkateswaran

analyst
#119

Alright, thanks.

Operator

operator
#120

Thanks, Madam. Our next question comes from Mr. Ingo Becker at Kepler Cheuvreux. Sir, the floor is yours.

Ingo Becker

analyst
#121

Yes, good afternoon, and thanks. There are 2 questions I have. The first concerns Slide 14, your offshore build out plan. People have raised this before, so if you'll permit me, I'll try a different angle. I mean this build out plan, especially the portion following Hornsea 2 and Greater Changhua — you've presented it for a good while now, and it seems the market, and we as well, are somewhat concerned about what will happen with all of those FIDs still pending. You continue to stress confidence regarding supply chain matters, and that you're able to handle them over time, and that there's no hurry on your side, which we understand. Even so, it appears that varies just with the share price, which keeps returning. At the same time, in a similar vein, demand for PPAs is climbing and you keep successfully — closing those deals. And you state that decarbonization is the underlying trend, which is probably why people want a PPA, and that's understandable, yet PPA pricing has to have a counterbalancing effect on the entire process. So with supply chain pricing uncertainties mounting, there appears to be an offset on the sales price side. And I'm wondering whether you could help us grasp this if we look at the pending FIDs on the right-hand portion of the slide.

Ingo Becker

analyst
#122

So subjectively, taking every one of those factors into account over the last 12 months, how has that changed things for you? Speaking for yourself, is the likelihood that you proceed to FID the same, or has it moved in one direction or the other — higher or lower? And I suppose in general the market would have expected those projects to reach FID. Second, on bioenergy and your other segments, where I think getting the forecast right has been a struggle for us this year given all the many changes — you now have the stop change, and we have gains in the power market that we might not want to extrapolate if your gas procurement contracts get renegotiated. As I understand it, some of those gains could be recurring while others are not. I was wondering whether you could help us a bit beyond this year with where we should expect EBITDA to progress for the segment. Thanks very much.

Marianne Wiinholt

executive
#123

Sure. Maybe I’ll begin with your first question. On Slide 14, the US projects are, in a sense, coming up for FID. The US differs greatly from every other market because we take FID quite late there, owing to the permitting process, which in a way takes a long time. While we wait for the permits — and now that the NOIs are in place — we in a way have far more predictability regarding the timeline. So a great deal of work to mature these projects has been under way over the last year. And we have a fairly firm CapEx budget for those. So there’s no doubt, in a way, that we will take FID, but it is the permit process that holds us back. On the German project, I think that is actually a good example of exactly what you’re referring to. We have seen only marginal impacts from cost inflation. But we have also seen at the same time that we were able to close these PPAs at higher levels than what we thought just a year ago. So actually, when we look at our business case — now, when we very soon expect to take FID, and a year back — in a way it is neutral to the NPV, because these two effects, in a way, are a wash.

Marianne Wiinholt

executive
#124

For us, then, there aren't really any issues with this awarded pipeline — it's largely a question of timing. The FIDs will arrive as each project matures, secures permits, and moves forward. Then, on your other question about bioenergy: as I mentioned, you should view 2021 as an unusual year because of the elevated power prices. If power prices return to lower levels, you'll be back to an earnings picture similar to what you saw in 2020. So most of this is essentially one-offs, or it's driven by those very, very high power prices.

Ingo Becker

analyst
#125

Thanks. Could I just ask a quick question — you're likely talking about the underlying DKK 1.2 billion for 2020, and not the declared figure for that year, correct? That was a different topic.

Marianne Wiinholt

executive
#126

Correct — that figure is for 2020, yes.

Ingo Becker

analyst
#127

That came to DKK 1.2 billion.

Marianne Wiinholt

executive
#128

Bioenergy and other—hold on, let me locate that. Yes, right. It's actually DKK 1.5 billion.

Ingo Becker

analyst
#129

DKK 1.5 billion — that's excellent. Thanks so much.

Marianne Wiinholt

executive
#130

But after that, you have to subtract the divested business — the distribution.

Ingo Becker

analyst
#131

Okay.

Marianne Wiinholt

executive
#132

Yeah, so.

Operator

operator
#133

Much appreciated, sir. Our following question comes from Mr. Rob Pulleyn at Morgan Stanley. Sir, the floor is yours.

Rob Pulleyn

analyst
#134

So, as we work to get a handle on how exposed you are to these power prices — for the portion of the portfolio that you hedge financially, would you be open to sharing how much of the book is filled for 2022 and 2023? And how much that has possibly shifted since the half year? In this kind of extraordinary power market, how much have you managed to get into the hedge book, where you've financially hedged some of your production? Thank you.

Marianne Wiinholt

executive
#135

Right. The usual way to think about it is that we're pretty much fully hedged across the first two years. So in a sense, for 2021 we've been fully hedged, and 2022 is fully hedged as well. After that, we roll quarters as we go forward. For 2023, I believe the hedge is roughly 7 to 47%. So about 50%. And through the latter portion of that, in a way, we pick up some benefit from the higher prices. But — sorry, 80%, sorry, sorry, 81%. Apologies for that. So more or less fully hedged for two years, then 80% in 2023. So we don't gain a lot from these high power prices in our offshore and onshore business.

Rob Pulleyn

analyst
#136

All right, thanks. I'll hand it over.

Operator

operator
#137

Thanks, sir. The next question comes from Mr. Alberto Gandolfi at Goldman Sachs. Sir, the floor is yours.

Alberto Gandolfi

analyst
#138

Thanks. I’ll keep this really short. So the question is whether you could expand a bit on why you chose not to take part in the Germany, France, and Massachusetts auctions. And I get the thinking behind steering away from what might be competitive tenders. But I’m wondering why the strategy isn’t, as you know, that some of your competitors in other segments are essentially attempting to bid in every market while staying disciplined. And if somebody isn’t disciplined, then they end up losing the auction. So that’s what I was expecting from you. Is it because you need to build the organization up further before you’re able to bid everywhere? And so you don’t want to spread too thin. So — or why would you say, before seeing the auction result, that those tenders are going to be especially competitive? And if I may ask, you know, obviously I’m overstepping here. So please feel free to say no. But regarding your hedges on iron ore or steel, you know we’re talking about hedging billions of exposure for years ahead. What would the cost be, expressed in basis points, of hedging? And have you always done it? Or is this something new in reaction to the recent backdrop?

Alberto Gandolfi

analyst
#139

I really appreciate it.

Mads Nipper

executive
#140

Yes, thank you, Alberto. I'll take that first question. Well, several answers apply here. First, given the sheer volume of solicitations being issued, we do need to prioritize, since preparing a qualified bid takes hard work. And we want to make sure that whenever we do it, we do it where we can be very well prepared. So we know we have firm ground under our feet when we do it. And we want to make sure it's something that plays to our strengths, so we have a very good chance of actually being awarded. If you take the two specific examples you mentioned, Germany and Massachusetts, there are actually two very distinctly different reasons why we chose not to. One is that in Germany, there are these, I think, well-known step-in rights, where it was highly unlikely that those who held the step-in rights would actually not exercise them. And therefore we thought — and I believe rightly so — that it would simply risk being a waste of time to bid, and it turned out that these defaults are exercised. And for Massachusetts, it was because of the cap — the price cap, which meant that even though we have the lease area, or have the lease area of 500, we simply did not evaluate this as a sufficiently financially attractive opportunity for us compared to the alternatives we have at hand.

Mads Nipper

executive
#141

It comes down to keeping our attention on the areas where our odds are strongest, making sure at all times that we stay disciplined on the financial side and are able to put together projects worth investing in, and focusing on the places that suit what we do best and where the likelihood of success is greatest — that's the somewhat longer version.

Marianne Wiinholt

executive
#142

Yeah. And regarding that last question about what hedging costs us — honestly, we don’t really view hedging as a cost. Our business model aims for 90% coverage of merchant exposure over the long term. We also hedge a very significant portion in the first years, which helps us keep earnings very stable and is an advantage for rating purposes as well. You can always argue that there’s a bid-ask spread when you hedge further out. As I said, most of our hedging sits within the next three years, and we also use proxy hedges to eliminate or reduce those bid-ask spreads. So for us, this really isn’t something we see as a cost. You can always go back and ask whether you should have hedged at that time; from time to time we’ve done those kinds of analysis, and we’ve actually shown that over time, following this hedging policy has been a good thing for us.

Mads Nipper

executive
#143

And Alberto, if I could just briefly return to that first question. I actually believe there’s a site-level upside to staying out as well — in Massachusetts, for instance. Honestly, I’m not sure whether it has now been definitively confirmed, but it appears very likely that the price cap will in fact be eliminated, since our decision not to bid came as a surprise. So we also see some value in the fact that, as a clear global market leader, when we decide against participating, that itself sends a signal — in this instance to regulators — that financial discipline isn’t merely something benefiting an individual company. It is an absolute prerequisite for this — for developers to be able to build out sustainably over time. So we were in fact very pleased. We didn’t bid, and we hope it will drive some structural change that will mean —

Marianne Wiinholt

executive
#144

That it has force -

Mads Nipper

executive
#145

That's been verified, which was kind of a site advantage of staying out that we were quite pleased about.

Alberto Gandolfi

analyst
#146

Mads, that's really clear. Thank you. Marianne, my apologies — actually what I was referring to was hedges on raw materials, not on our power for —

Marianne Wiinholt

executive
#147

You were asking about raw materials. Honestly, I'd look at it similarly in a sense—for me, whether locking in a price is wise or unwise hinges on where prices go. And it isn't really a cost as such; it's more, in a sense, about the timing of your hedging.

Alberto Gandolfi

analyst
#148

Thanks. And I appreciate you waiting. Thanks.

Operator

operator
#149

Thanks very much, sir. The next question comes from Mr. Dominic Nash at Barclays. Sir, the floor is yours.

Dominic Nash

analyst
#150

Thanks for letting me ask a second question — I hope this one's quick. On the Borkum Riffgrund 3 sell-down before FID, what kind of delta are you seeing? Or do you believe there's a difference in risk and the related cost of capital for partners depending on whether you sell down earlier versus settling now at FID or indeed at commissioning? Is there any delta at all, and what does the spread look like? Thank you.

Marianne Wiinholt

executive
#151

In fact, what we've observed is that any delta—if one exists at all—is at minimum extremely, extremely small. The reason is that when we provide this EPC wrap, there's arguably so much trust placed in us as the EPC provider. So what we genuinely observe is that, in a sense, customers pay the same amount even when it's pre-construction.

Dominic Nash

analyst
#152

So I'd imagine, then, following on from that, that selling down sooner in the lifecycle of your offshore wind farm is probably going to become more of a trend if that gap between commissioning and the early period moves toward zero — is that right?

Marianne Wiinholt

executive
#153

Yes, that's right. There are situations where tax factors might lead us to handle it differently. But broadly speaking, you've got it.

Dominic Nash

analyst
#154

I appreciate it.

Operator

operator
#155

Thanks very much, sir. That's all the questions we have, so I'll hand it back to you for the closing remarks.

Mads Nipper

executive
#156

Yes, and let me just say thank you so much for the really good questions during what was an unusual quarter — but one that, as I'll say again, we're quite pleased to have navigated successfully. I appreciate your engagement. And thank you for your confidence.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.