Ørsted A/S (ORSTED) Earnings Call Transcript & Summary

February 1, 2023

Nasdaq Copenhagen DK Utilities Independent Power and Renewable Electricity Producers earnings 87 min

Earnings Call Speaker Segments

Operator

operator
#1

Thanks for joining us on this Ørsted Q4 2022 earnings call. During the first portion of today's call, everyone will be in listen-only mode, and after that we'll open things up for a question-and-answer session. With us today are Mads Nipper, our Group President and CEO, and Daniel Lerup, our CFO. Mads, Daniel, over to you.

Mads Nipper

executive
#2

Thanks a lot, and welcome everyone to the call. As you've probably noticed from the earnings we released ahead of time two weeks back, we posted a record high operating profit for 2022, even though market conditions were unusual and extremely volatile. Our financial results are underpinned by a portfolio of assets that run continuously at excellent availability rates and help keep energy supply secure in every market where we operate. That demonstrates what we gain from a strong operating portfolio and from diversifying our asset base. Given these financial results, the Board of Directors will propose to the Annual General Meeting a dividend for 2022 of 13.5 Danish kroner per share. That works out to an 8% increase, consistent with our dividend policy. With that said, let me turn to the strategic progress we made in 2022, beginning with our offshore business. In August, we commissioned the 1.3 GW Hornsea Two project in the U.K., the largest offshore wind farm in the world. That marks a very significant milestone, and I feel very proud of the whole team, who delivered this project under very challenging conditions with COVID-19. We also moved forward with construction of the Greater Changhua One and TwoA project, our first large-scale offshore wind farm in the Asia-Pacific region.

Mads Nipper

executive
#3

We reached first power during the first quarter of 2022, and we anticipate full commissioning of that project in the second half of 2023. In the U.S., our South Fork project received its Final Investment Decision, and we remain well on track for commissioning in 2023. Beyond advancing our construction portfolio, we also achieved meaningful progress across our development and opportunity pipeline. In the UK, we secured a Contract for Difference for Hornsea Three, which at 2.9 GW will stand as the single largest offshore wind project anywhere in the world. We also entered a partnership with Copenhagen Infrastructure Partners aimed at developing as much as 5.2 GW of offshore wind in Denmark through four open-door projects. In Sweden, we filed permit applications for four more large-scale offshore wind farms, lifting our Swedish portfolio to a potential total capacity of 18 GW. We further made tangible moves into floating offshore wind through Salamander, our 100 MW floating project in Scotland, and through our partnership with Repsol to explore joint development of floating offshore in Iberia. In addition, we hold a role in the joint venture behind the Scottish project Stromar, which received a site in 2022 for roughly 1 GW of floating offshore wind along Scotland's northeast coast.

Mads Nipper

executive
#4

Our current project portfolio's value is demonstrated by the fact that our farm-down strategy once more showed how appealing it is, with the farm down of Hornsea 2 and Borkum Riffgrund 3 now completed. Beyond our firm pipeline — which we define as installed, decided, and awarded capacity — there are a number of pipeline opportunities in bottom-fixed and floating offshore wind, along with Power-to-X. In Onshore, we kept up our strong growth trajectory, commissioning 0.8 GWs and moving seven projects totaling 1.4 GWs to Final Investment Decision, among them the 600 megawatt solar and storage project Eleven Mile and the 471 megawatt solar project Mockingbird, both located in the U.S. We also broadened our growth platform in Europe by acquiring the French-German developer Ostwind and through four partnerships in Spain aimed at pursuing early-stage solar PV and Onshore wind projects, giving us a strong presence across key renewable growth markets in Europe. Taken together, these efforts lifted our firm Onshore capacity by more than 30% over the year. We also completed our first ever Onshore farm-down, agreeing to divest 50% of a four-project Onshore portfolio in the U.S.

Mads Nipper

executive
#5

As with our solid history of farm-downs offshore, this deal delivered appealing Net Present Value retention and gave us proceeds to put back into growth that creates value. In our Power-to-X business, we hit a number of important milestones over the last year. We bought the remaining 55% of the FlagshipOne project and made the Final Investment Decision. With an electrolyzer capacity of 70 MW, the facility is set to become Europe's biggest e-methanol plant. We also signed a landmark green fuels agreement with A.P. Moller — Maersk, partnering on a project in the U.S. that will deliver 300,000 tons of e-methanol annually. It's also worth pointing out that our Green Fuels for Denmark project and our Haddock project in the Netherlands both received IPCEI funding in 2022. IPCEI means International Project of Common European Interest. Thanks to this strategic progress, our firm capacity rose by 4.5 GW during 2022, reaching 30.7 GW. Beyond that, our substantiated pipeline across offshore and Onshore projects, along with our opportunity pipeline in offshore, grew by more than 25% to approximately 85 GW. Without question, green energy is the most impactful solution we have in the fight against global warming, and we must accelerate the build-out of renewable energy.

Mads Nipper

executive
#6

It's also becoming clear that achieving success in the green transformation requires us to generate beneficial outcomes for nature and for people — making sure we address essential environmental and societal problems while keeping public backing for the green build-out. Ørsted has established sustainability commitments that lead the industry. As part of getting to our science-based goal of Net-Zero emissions across Scope 1 through 3, we joined as a founding member of the First Movers Coalition's Near Zero Concrete Commitment and formed a partnership with World Wide Fund for Nature aimed at enhancing ocean biodiversity. The world confronts a climate crisis. There can be no dispute that a shift toward a sustainable energy system is required. We keep contributing to this greatly needed expansion of renewable energy. Given the substantial strategic results achieved throughout our business, we stay confident about our long-term financial targets and growth ambitions. Let's move to Slide 4. All through 2022, the renewables sector has faced persistent supply chain bottlenecks, cost inflation, and sluggish permitting of new projects. In spite of every one of these difficulties, renewable energy remains considerably cheaper than any fossil fuel alternative, even when supply chains are strained, and beyond that it is probably the finest conceivable safeguard against future energy price hikes such as those witnessed last year.

Mads Nipper

executive
#7

We have to act so that the investments in renewable energy that are needed get made faster, and regulatory and political barriers need to be pushed to focus on permitting processes that are quick and streamlined, which as of today remain a major bottleneck in our industry. Given this challenging backdrop, it is pleasing to see that political attention and support for the renewable build-out has been a significantly positive development over the past year. In Europe, various political initiatives have come about, such as the adoption of several Fit for 55 files, a REPowerEU, the Esbjerg Declaration, and the Marienborg Declaration. More recently, the European Commission announced that it is planning a Green Deal Industrial Plan, which will be aligned with the 2050 climate targets and offer significant opportunities for the renewable energy sector. The Net-Zero Industry Act is included in the Green Deal Industrial Plan, and it focuses on regulation to scale development of green energy supply chains and raw materials. In addition, the plan focuses on changes to state aid rules to counter relocation of industries' investments in skills and workers, and lastly, international trade with a focus on protection against China. Such initiatives would be incrementally positive for the renewable industry within Europe, which would benefit from the increased EU support as well as easier access to national funding made available through relaxation of EU state aid rules, which of course should be done in a way that preserves fair competition.

Mads Nipper

executive
#8

In the U.S., a significant move has gotten underway with the passage of the U.S. Inflation Reduction Act, which allocates $385 billion to fund renewable energy generation, green hydrogen production, and climate risks across the coming 10 years. Since the Paris Agreement, few climate efforts have mattered as much as the Inflation Reduction Act, and with historic investments flowing into clean energy, it will make an enormous difference to the green transition in the U.S., particularly given today's conditions, in which offshore projects face challenges. In Asia Pacific, we are likewise seeing solid headway, with firm offshore wind capacity build-out targets in Taiwan and a Green New Deal in Japan. Australia has unveiled regulatory changes aimed at advancing offshore wind power, along with political momentum behind renewable energy solutions. Australia's robust offshore wind potential is something we fully acknowledge. With supportive policies and momentum for green energy behind it, Australia possesses every ingredient needed for a thriving offshore wind market. Across our portfolio, our substantial presence within Onshore, offshore wind, solar PV, hydrogen, and storage means we are well-placed to draw on that political support. Over our 30-plus years in the industry, we have built a strong global presence, with trustworthy stakeholder relations spanning the supply chain, local communities, unions, governments, and policymakers.

Mads Nipper

executive
#9

We possess solid expertise in development, construction, operations, and maintenance. Over 8,000 committed colleagues of mine head to work each day, bringing us a step nearer to a world powered entirely by green energy. Turning to Slide 5 and what lies ahead for offshore wind auctions in 2023. During 2023, we anticipate seeing many auctions and tenders throughout all three regions in which we operate. Over 25 GW is scheduled for auction in 2023, underscoring the robust growth prospects for offshore wind. Beyond this build-out, we keep witnessing a substantial rise in open-door opportunities throughout European nations, which considerably expands the addressable market for offshore wind build-out. We anticipate sustained growth over the long term, with worldwide offshore wind build-out projected at over 20 GW annually toward 2030 and over 30 GW annually from 2030 to 2035. With installed capacity growing at an annual rate of 20% across the coming decade, we see plentiful opportunities to meet our ambition of adding roughly 3 GW of offshore capacity to our portfolio each year. Just as we achieved in 2021, with an additional 4.5 GW capacity, and 2.9 GW in 2022.

Mads Nipper

executive
#10

Let me restate a note of caution: given the supply chain bottlenecks, cost inflation, and the rising cost of capital, it is crucial that the prices we see contracted in auctions and tenders mirror what the current inflationary environment actually looks like. If they don't, the investments in renewable energy that are needed risk slowing down, and that would cause a devastating loss of momentum for the green transformation. On that point, we are encouraged that Massachusetts has removed its price cap, and that better framework conditions for the ORECs have been launched in New York, Rhode Island, and New Jersey, as inflation index mechanisms are being put in place to counter some of the adverse effects of the unprecedented rise in interest rates and cost inflation. In response to New York State's 3rd round of offshore wind solicitations, we submitted a proposal that includes multiple bids with different configurations. We applaud the high number of auctions and tenders, both near term and long term. As a direct result of the unprecedented cost inflation and rapidly increasing interest rates the industry faced in 2022, we had to incur an impairment on our U.S. development project, Sunrise Wind. Since that project is the last one in our execution pipeline towards 2025, it faced specific challenges compared with the rest of the portfolio.

Mads Nipper

executive
#11

Costs on the project went up sharply, and the cause was specifically the pricing of installation vessels along with the related services. At the portfolio level, we've secured roughly 90% of project costs looking toward 2025. In addition, every pre-2025 COD project shows a positive forward-looking Net Present Value when looked at individually, and as things stand we judge this portfolio to carry a positive life cycle Net Present Value, assuming 40% ITC. As we've said before, we keep examining every option for strengthening the business cases, and that includes approaches that give us more robust top lines. Despite the Sunrise Wind impairment, I want to stress that we remain committed to Sunrise Wind and to the remainder of our U.S. offshore wind portfolio. We are building out the biggest portfolio of U.S. offshore projects in the U.S., with seabed leases that were secured many years ago at very low costs, and we'll leverage those for upcoming U.S. offshore wind solicitations, such as the very recent New York 3 auction. Given our unique global presence, we'll evaluate opportunities across technologies in both existing and new markets so that we prioritize capital allocation efficiently. Our strong focus on value creation and financial discipline will continue when we bid into auctions and tenders.

Mads Nipper

executive
#12

So with that, I'll pass things along to you for the financial section, Daniel.

Daniel Lerup

executive
#13

Thanks, Mads, and good afternoon, everyone. I'll begin on Slide six with a look at our full-year EBITDA for 2022. Since we released our operating earnings two weeks ago and have now confirmed those figures today, I won't spend much time on the EBITDA details. At the group level, we delivered total EBITDA of 32.1 billion DKK, including new partnerships. That marks a record-high EBITDA, and this result should be viewed against macroeconomic headwinds, significant volatility in the energy markets, and negative effects from our hedging program. Leaving out new partnerships, EBITDA came to 21.1 billion DKK, ahead of what we initially expected for the year. In fact, that figure carries a negative impact of 1.3 billion DKK stemming from ineffective hedges related to IFRS 9, which will lift EBITDA in later periods. Once you strip out these temporary IFRS 9 adjustments, group EBITDA excluding new partnerships reached DKK 22.4 billion, up more than 40% versus last year. As we emphasized on the conference call a few weeks back, the makeup of our earnings for 2022 differed considerably from what we had initially anticipated. The main drivers were the sharp volatility and rise in power prices, together with unfavorable hedging effects.

Daniel Lerup

executive
#14

That said, what happened during 2022 showed how resilient the earnings from our diversified asset portfolio really are. The fact that we beat our original expectations financially comes from strong results in Onshore and in our Bioenergy & Other segment. Throughout the year, our Onshore division ran at high availability rates, grew its generation capacity, and succeeded in locking in favorable prices during the ramp-up phase of assets under construction in the U.S., while also gaining from upside-sharing mechanisms in some of our PPAs. In Bioenergy & Other, we captured attractive earnings from our gas activities and gained from the high power price levels. Lastly, we stay confident about long-term EBITDA growth toward 2027, when our operating assets combined with projects still to be installed will give us a high degree of earnings visibility. Moving on to Slide 7. Net profit for Q4 2022 came to a negative DKK 0.3 billion. Unlike Q4 2021, no farm downs were completed, and on top of that, the impairment tied to Sunrise Wind pulled down net profit for the quarter. Once these effects are adjusted for, net profit for the period stood significantly above last year, supported by a higher EBITDA.

Daniel Lerup

executive
#15

Return on Capital Employed was 16.8%, up 2 percentage points versus the prior year, supported by higher EBIT across the 12-month period and well above our long-term target. During Q4 2022, equity rose substantially, finishing the year at 95.5 billion DKK. That gain reflects hedges moving into delivery along with lower power prices. The hedge reserve fell by over 50% in the quarter. The negative hedge reserve that remains will be offset by greater future revenue from the underlying assets once the contracts enter delivery. Roughly 30% of that hedge reserve will be realized before the end of 2023, gradually lifting our equity. Moving to Slide 8. At the close of 2022, net debt stood at DKK 30.6 billion, down DKK 15.1 billion from the end of the third quarter. Cash flow from operating activities was heavily affected by a net cash inflow from collateral postings of DKK 17.4 billion, reflecting the decline in forward power prices. As of the end of December, we had posted DKK 14 billion in total collateral payments, most of which will unwind over the next 2 to 3 years.

Daniel Lerup

executive
#16

For the quarter, gross investments came to DKK 9.8 billion, mostly due to what we put into building offshore and onshore projects. A partner paid us an amount tied to project development, and finally, we saw a favorable impact from issuing hybrid capital plus an exchange rate adjustment stemming from a weaker pound sterling. Our key credit metric — FFO to adjusted net debt — was 43% for the full year of 2022. That level came in higher than last year, mainly because of stronger EBITDA. Moving to the next slide. For the full year 2022, the taxonomy-aligned and eligible portion of revenue was 73%. OpEx accounted for 80%, and EBITDA was 85%. Gross investments made up 99%. The non-eligible portion of revenue is mainly tied to our long-term gas legacy activities and power sales that are non-eligible. The green share of energy reached 91%, versus 90% a year earlier. That movement stemmed chiefly from additional wind and solar farms being in operation, along with stronger wind speeds. Since the Danish authorities have instructed us to extend the Esbjerg Power Station's operation past Q1 2023 and to restart the coal-fired unit at Studstrup along with the oil-fired Kyndby peak load plant, this will presumably hurt our green share of energy and our taxonomy-aligned KPIs in 2023 and 2024.

Daniel Lerup

executive
#17

Under that order, we must run the units through June 2024, and so we keep our pledge to reach carbon neutrality by 2025. On safety, unfortunately we are not seeing a performance that is up, that is up to the standards we expect, since our Total Recordable Injury Rate stands at 3.1 for 2022. We have recorded more injuries among our contractors, partly offset by a slight decrease in recordable injuries among our own employees. We work continuously to strengthen and promote a safety culture. Particularly given the latest trend, we have put in place several initiatives, including greater leadership involvement, safety stand-downs, and targeted safety campaigns on specific issues. Let's move to Slide 10. Across 2022, we have seen material unintended and adverse effects on our financials stemming from our previous hedging framework. Those effects have been tied to over-hedging, temporary IFRS 9 adjustments, and inflation-indexed power purchase agreements. We have learned the hard way that our previous risk management framework was built for very different market conditions and had ended up being too complex. Our updated hedging framework will greatly lower the risk of adverse hedging effects in the volatile market conditions we are seeing, and instead support the high predictability of earnings that our portfolio of renewable energy assets is capable of delivering.

Daniel Lerup

executive
#18

In the past, our hedging framework worked well for us, since it gave us stability and earnings visibility. But it was built for risk management and earnings optimization in market conditions that were fundamentally different from those we have seen recently—conditions illustrated by the extreme rise and volatility of power prices over the last few years. To adjust to these unprecedented market conditions, with high volatility and a substantial increase in power prices, and to better reflect how our business is composed today, we chose to stop all new hedging activities at the end of 2021 and carried out an extensive revision of our hedging framework. The design criteria drew on some of the key lessons we learned over the past year. First, lowering our hedge level has been crucial, so we significantly cut the risk of having to buy back hedged volumes. Second, we have seen a substantial rise in the collateral we have had to post in connection with our hedge portfolio. We have felt a significant drag on our liquidity. Throughout the year, we took several proactive steps to ensure a sufficient level of liquidity to meet the collateral requirements while also supporting our ongoing build-out and operations.

Daniel Lerup

executive
#19

A crucial requirement for our new framework has been that we substantially lower the danger of needing to put up collateral to a comparable degree going forward. Also, our earlier framework was extremely systematic and methodical, meaning we would adhere strictly to our hedging staircase, hitting set hedge levels at specified time horizons. What we have learned, though, is that we need to build greater flexibility into the framework so that we can maximize value and back commercial initiatives — for example, by securing power prices above the levels assumed in the business case. If we move to the next Slide, I will walk through the updated framework built on these design criteria. Despite the considerable rise in power prices, we still get a very large portion of EBITDA from long-term regulated and contracted activities. From here on, we will hedge no more than 70% of the remaining limited merchant exposure from our offshore and Onshore assets in the current and the next calendar year. Under this approach, we will greatly cut the danger of unintended adverse hedging effects down the road, including a lower risk of over-hedging, fewer collateral postings, and also a smaller impact from temporary IFRS 9 effects.

Daniel Lerup

executive
#20

Looking at historical wind and production data, it's clear that our old, very high hedging requirements led to over-hedged volumes in 1 of 3 months, whereas a hedge level of 70% would result in over-hedged volumes in 1 out of 20 months. That's a far more comfortable probability, particularly considering today's market volatility, elevated power prices, and greater renewable penetration. Our renewable portfolio carries a natural risk-reducing mechanism, thanks to the negative relation between production and price. When wind is high, the merchant price will be relatively lower, but higher generation from the subsidized assets will offset that. Conversely, when wind is low, merchant prices will be relatively higher, and the high price level on merchant generation will counterbalance lower generation from the subsidized assets. So our renewable assets provide a natural offsetting portfolio effect. The negative relationship between production and price is expected to become even stronger going forward, as renewables will account for an increasingly larger share of energy supply. In designing our new framework, we have taken this offsetting effect between power generation and price volatility into account. Accordingly, how much we hedge our merchant generation depends on the portfolio composition of subsidized and merchant exposure, as well as prevailing market prices.

Daniel Lerup

executive
#21

On the right-hand side, that graph shows two portfolio compositions that have differing shares of merchant exposure. When a portfolio has a 100% merchant exposure share, that tells you that raising the hedge level for it will make revenue uncertainty greater, because the natural portfolio effects get removed, and it also raises the over-hedging risk. Conversely, with a portfolio whose merchant exposure share sits at around 40%, raising the hedge level will bring revenue uncertainty down, though only up to a point. If you hedge the merchant generation at an excessively high level, the natural portfolio effects will be removed and over-hedging risk introduced. What this means is that when a portfolio has a low merchant exposure share, keeping a high hedge level raises the over-hedging risk, and that is the adverse impact we have observed in our portfolio across the past years. By deciding to bring the hedge level and duration down, we will end up with lower risk in our portfolio going forward, since the mix of a high share of regulated and contracted earnings together with the portfolio effect I just described will support revenue certainty going forward. Under our new framework, we will set our year-to-year hedge level according to the overall portfolio composition, and in that way steer clear of situations in which hedging increases risk instead of reducing it.

Daniel Lerup

executive
#22

We're shifting from the systematic, methodical hedging approach we've used toward a more flexible, dynamic framework—one that gives us the flexibility we need to strike the right balance between regulated and merchant earnings. It's worth pointing out that we're still putting this framework into practice, since our prior hedging framework also locked in a fairly high hedge level within offshore for 2023. That said, we've taken proactive steps to lessen the degree to which our hedge level could affect us negatively. For instance, we've opportunistically repurchased forward sold volumes at attractive prices to lower the risk of over-hedging, and because of that, we're entering 2023 with an offshore hedge level of around 85%, which is meaningfully lower than the close to fully hedged level in 2022. At the group level, we hold a hedge level of around 70% for 2023. Lastly, let's move to Slide 12 and our outlook for 2023. As we highlighted on our conference call a few weeks ago, we guide our full year 2023 EBITDA in the range of DKK 20 billion–DKK 23 billion. I won't walk through the underlying assumptions behind our guidance now, since we covered them back then.

Daniel Lerup

executive
#23

I should point out, though, that the 2023 financial outlook shows a substantial improvement in earnings from our operating renewable energy assets, especially in the offshore business. Under the guidance we've issued for 2023, we anticipate earnings growth of more than 80% for our generating offshore assets, which represent a central, value-creating growth area of our business. On gross investments, our expectation is a figure between DKK 50 billion and DKK 54 billion. The drivers here are timing effects from investments pushed from 2022 into 2023, along with a general lift in investment level reflecting the build-out of our pipeline in offshore and Onshore. At the most recent Capital Markets Day, we laid out four key financial estimates that underpin our growth plan of roughly 50 GW of installed renewable capacity by 2030. Owing to supply chain disruptions following the COVID-19 pandemic, cost inflation, and drawn-out permitting processes, particularly in the US, our gross investments across 2020 to 2027 that will enable the 50 GW build-out are at present trending above the roughly DKK 350 billion we had planned. That said, should inflation and energy price levels stay elevated, those factors would have a positive effect on our EBITDA CAGR and ROCE across the period and would raise the relative share of EBITDA that is merchant.

Daniel Lerup

executive
#24

Even with the upward trend in CapEx, our commitment to the current CMD plan is unchanged. On that point, I'm also genuinely excited to share that a Capital Markets Day will be held on June 8th, and there we'll give a progress update on our long-term strategy. Please mark that date down. With that said, we'll now take questions. Operator, please.

Operator

operator
#25

Thanks. That brings the presentation to a close, and at this point we'll take questions from the floor. The call must wrap up by 3:30 P.M. at the latest. We ask that each participant limit themselves to one question, after which you're welcome to rejoin the queue for a second one. If you'd like to ask something, press 5 star on your phone's keypad. Should you wish to pull your question, press 5 star once more. We'll pause for a short moment while the questions come in. Our first question comes from Kristian Johansen at SEB. Your line is open — please go ahead; you're unmuted now.

Kristian Johansen

analyst
#26

Yeah, thanks. I wanted to ask about that 50 GW goal of yours. When I look at the pipeline numbers you've provided, adding together your firm capacity and your substantiated pipeline, the total now stands at 59 GWs. If I go back to your CMD in 2021, that figure was 48. And as you point out yourself, this number is climbing quite considerably. For me, it kind of suggests the odds of surpassing your 50 GW target are rising as well. Could you share a few thoughts on just how likely that is, and then also what it would take for you to actually go out and revise this target?

Mads Nipper

executive
#27

Yes, thank you so much, Kristian. I'm glad to speak to that. It's true that both the substantiated pipeline and firm capacity have risen considerably, and that's something we're very pleased about. Still, you shouldn't read that as an automatic sign that this will naturally keep climbing, because at the moment, given the industry conditions we've been describing, it's crucial for us to make sure we concentrate on the investment opportunities that create the most value, which is exactly why having a fairly broad substantiated pipeline to choose from is such a great privilege. Keep in mind that as our work moves forward, the opportunity pipeline will keep feeding down into the substantiated pipeline too. I'd say absolutely, yes, this makes reaching the roughly 50 GWs we've set even more likely, but it's also necessary to have a wide pipeline of substantiated projects or project opportunities that make value creation even more likely.

Kristian Johansen

analyst
#28

Got it, thanks.

Operator

operator
#29

We’ll take the next question from Deepa Venkateswaran at Bernstein. Please proceed. Your line is unmuted now.

Deepa Venkateswaran

analyst
#30

Thank you. This is Deepa Venkateswaran from Bernstein. My question concerns the U.S. impairments. I believe many investors are finding it hard to handicap possible additional downside, or just how many more issues could arise. I was wondering whether you could provide some disclosures — even at the total project level for all of your near-term U.S. projects — covering what total capex is and how much you have spent. And what % inflation there has been, so that we can likewise do the math on what the risk might be if inflation were to rise further. Thank you.

Daniel Lerup

executive
#31

Yeah. Thanks. Thanks, Deepa. We won’t be providing an updated figure for our full U.S. portfolio. I think the headline numbers you have are the DKK 350 million for our build-out towards 2027. But perhaps I can offer a bit more clarity on what we have spent so far in the U.S. We say that roughly a spend of roughly DKK 13 billion, mainly on the near-term development pipeline being the NEP project and Ocean Wind One. It’s... it corresponds to roughly a low double-digit percentage of the totality of the near-term development pipeline in the U.S.

Deepa Venkateswaran

analyst
#32

Alright, thanks.

Operator

operator
#33

Thanks, Deepa. We'll take the next question from Alberto Gandolfi at Goldman Sachs. Alberto, your line is now unmuted — please go ahead.

Alberto Gandolfi

analyst
#34

Good afternoon, and thanks for the question. I'd like to ask about debt leverage, plus a bit more. When I look at Bloomberg consensus for 2023, net debt expectations sit at DKK 66 billion, and you've just reported DKK 30. If you look at operating cash flow, gross CapEx, and your usual approach of rotating assets — I know you normally don't give guidance — could you help us understand this figure? I mean, are we grossly overestimating net debt for 2023? How much of that DKK 11 billion working capital influence in Q4 is going to reverse? If consensus is incorrect, doesn't that mean FFO to net debt is much better than we were thinking, given the margin calls, the absorption, these working capital inflows — so how much of that reverses again remains to be seen? Does it also mean we're a little bit too worried about the timing of an equity raise? You know, you kept saying the equity raise would potentially be for funding a deal, or perhaps if your win rate is much better, if your substantiated pipeline gets converted faster. Should we think about it in those terms — based on the current plan of what you have won so far, you don't really need equity?

Alberto Gandolfi

analyst
#35

If there's anything you can add on that relationship, a debt equity of insert exact figure if present — none in source would be fantastic. Thanks very much.

Daniel Lerup

executive
#36

Yes, I'll do my best on that, Alberto. If we look at the projections for our capital structure — our own internal figures as well as those used by the rating agencies — we obviously feel confident that we can meet the thresholds laid out in those capital structure metrics. That's essentially what we've solved for so that we can deliver the roughly 50 GW in 2030. That is where we start from. You'll naturally see fluctuations in net debt and in FFO to net debt from one year to the next. Still, we do believe we can meet those thresholds. On collateral, we currently have roughly DKK 14 billion tied up in it. We do expect a fair share of that to come back in 2023. I'm not sure whether that could close some of the gap. I don't know the details of the average Bloomberg number well enough, but it could potentially account for some of it. Regarding the ABB, as we've said previously, we don't plan to use it to close a gap in our capital structure. It gives us financial flexibility that we will draw on in a situation where we judge that the combined probability of all the options we have for growing above 50 GW becomes large enough for us to say, "Okay, now it makes sense to issue more equity to fund further growth beyond the 50 GW."

Alberto Gandolfi

analyst
#37

Thanks.

Operator

operator
#38

Thanks, Alberto. We’ll take the next question from Rob Pulleyn at Morgan Stanley. Go ahead — your line is unmuted now.

Rob Pulleyn

analyst
#39

Good afternoon, and thanks so much for taking my question. I just have one, and I hope you can give us some color on it. Yeah, there's been quite a bit of talk about those U.S. projects, and as I think we should all keep in mind, the previous management team signed them. So I was wondering if you'd be open to sharing your perspective on the main lessons that have been learned over the past two years, and how that experience might shape what comes next and, shall we say, the risk-taking, the value creation, and the outlook for Ørsted. Thank you very much.

Mads Nipper

executive
#40

Absolutely, Rob — glad to do that, and I’ll ask Daniel to add anything he can as well. Without question, one of the main takeaways is this: we’re pleased to see that inflation indexing on the revenue line is apparently being put in place across a number of states too, and that matters a great deal. We’ve engaged quite closely with regulators to make sure that happens, since when the cost of capital is rising and CapEx inflation is rising as well, a revenue line that stays fixed, with a set annual escalator, is plainly a difficult situation. The work with regulators to make sure we take that risk out from the developer’s perspective — so the risk rests with those best able to manage it, instead of pushing developers to price in a risk premium — is one important lesson. Another important lesson, which isn’t too far from our long-term strategy, is making sure we get as much CapEx certainty as we can as early as we can. Because the variability we’ve seen even in scopes that previously weren’t all that unpredictable is something we’ve learned can shift as industry bottlenecks shift.

Mads Nipper

executive
#41

And that means having the foresight about... plus structural and systematic foresight regarding where bottlenecks are most likely to occur, where they could arise, and making sure we really secure both the capacity and the fixed price agreements, as we're doing right now as we speak, so we're not simply sitting on those learnings. We're putting them into practice by making certain that we establish frame agreements that don't just assure and ensure capacity, but also some that lock in significant portions of the volatility we'd otherwise confront. Those are 2 examples of learnings that we're both absorbing and are already in the process of implementing.

Rob Pulleyn

analyst
#42

Much appreciated, and I'll hand things over now.

Operator

operator
#43

Thanks, Rob. We’ll take the next question from Casper Blom at Danske Bank. Go ahead — your line will be fully unmuted.

Casper Blom

analyst
#44

Thank you very much. I also have a question about the U.S. projects. Mads, you said that one of the cost items where you've seen a lot of inflation was vessels for doing the installation, particularly in the Sunrise Wind projects. My assumption is that this isn't a market with hundreds of vessels and that relatively few vessels could quickly change things. So what are you seeing here in terms of the pipeline on vessels going forward? Do you see any upside from potentially other projects being delayed, postponed, maybe not even built, that could actually make things easier even in the near term for you? Thank you.

Mads Nipper

executive
#45

Yes, thank you. Thanks so much, Casper. We have hardly any question in our minds that capacity will expand structurally and in an overall positive way. In a market this tight, vessel owners clearly are spotting sizable opportunities — and that applies worldwide, not only in the US. FIDs on heavy lift vessels are taking place right now as we speak. That is a positive development, and it will plainly contribute additional capacity. We keep pressing on this, because one of the Slides we presented today shows the capacity expansion that still needs to be built out, and we must make sure that through both our market predictions and the commitments we make, we can lock in more — even more — capacity. Because building these vessels takes time, the honest answer, Casper, is that the projects closest at hand — for instance, the portfolio of U.S. projects we have towards 2025 — are unlikely to be affected, either positively or negatively, by any of the capacity expansions now under way. Looking towards 2030, there is no doubt that we see this as an area we hope, and believe, could be debottlenecked.

Casper Blom

analyst
#46

All right, thanks a lot.

Operator

operator
#47

Thanks, Casper. We'll take the next question from Harry Wyburd at Exane, on the line. Go ahead — your line is unmuted now.

Analyst

analyst
#48

Hi, everyone. Thanks so much for taking my question. I apologize for belaboring the write-downs. May I ask something a bit technical? If we consider projects that reach COD after Sunrise, I suppose their book value isn't very large at present. What risk is there that, as time passes and you put money into them, you eventually reach a stage where they do carry book value, and then you must assess whether a write-down is needed? Put differently, what's the risk that the CapEx you invest over the coming couple of years — CapEx and DevEx — ends up being value destructive, and then, 2 years from now, you have to write that down, though you don't need to do so at this moment because book value on this project is essentially zero. Perhaps I could slip in the vessel costs. Clearly, you've seen much higher vessel costs on Sunrise. Did you apply the same assumptions to the other projects as well, or are you implicitly assuming vessel costs decline, as you mentioned, by 2030?

Analyst

analyst
#49

Appreciate it.

Mads Nipper

executive
#50

I'll address the last item first, Harry, and then pass the first question over to Daniel. As we also noted in our text regarding the Sunrise Wind impairment, the reason that's the project we're impairing — while the others enjoy comfortable headroom under current assumptions — is that we had locked in a larger share of those scopes, vessels included. So it isn't because we've done anything terribly wrong or because there are any significant outstandings on the remaining projects. It's simply that Sunrise was the last to lock in a market where rates and prices were climbing sharply. That accounts for it. As we mentioned, we do have roughly a 90% capex price lock-in for those 2023 to 2025 COD projects, which gives us a very high degree of certainty, whereas Sunrise was the last one, and it was hit specifically by those steep increases.

Daniel Lerup

executive
#51

Yes. Regarding your first question about the later-dated development portfolio in the U.S., the amount we've booked on those projects is fairly insignificant. I don't see a big impairment risk there. It's more back-end-dated spend. These are projects where we have some more flexibility because they are to be delivered later in the decade. Of course, we will make sure that when we take FID on those projects and also spend more on them, we do it with the consideration to make sure that we have meaningful value creation on those projects.

Analyst

analyst
#52

That's very clear. Thank you.

Operator

operator
#53

Thank you, Harry. Our next question comes in writing, from Sam Arie at UBS. Listening to your presentation, I pick up these main points. The sector has to draw in far more capital. Greater government backing is anticipated across the globe. Some projects may carry more risk than people realized before, as last year's events made clear. Developers need to submit higher bids. Putting all of that together, would it be reasonable to conclude that over the next few years, returns in this sector have in fact risen considerably, both in the headline IRR you can reach and in the spread over WACC that this mirrors? Thank you.

Daniel Lerup

executive
#54

Yes, absolutely — we do expect that absolute returns are going to need to rise as inflation picks up, costs climb, and interest rates move higher. As for the spread we're aiming to earn from a project win, that will naturally depend heavily on the individual project — on timing, on whether there's inflation indexation, and on whether we're able to secure cost certainty at the point of bid. A great many factors feed into that, of course, but we are certainly factoring in the greater uncertainty we're currently seeing, and that ought to show up either through a wider spread to WACC or possibly through a larger contingency where we have doubts about whether we can deliver the CapEx we've assumed in a bid case.

Operator

operator
#55

Thanks, Sam.

Daniel Lerup

executive
#56

Correct.

Operator

operator
#57

Please proceed. Speakers, the floor is yours.

Daniel Lerup

executive
#58

No, let's move on to the next one. My apologies.

Operator

operator
#59

Alright, that's noted. Our following question comes from Mark Freshney at Credit Suisse. Your line is now unmuted — go right ahead.

Mark Freshney

analyst
#60

Hey, thanks. Thanks for the question. On vessels, the way I understand it, there's a bit of a chicken and egg situation, you know. Some builders or asset owners don't want to build these vessels until they have firm commitments. And you don't want to give them until you have firm clarity on when you need the vessels. In the past cycle — I mean, you yourselves were a joint vessel owner with Siemens. I'm just wondering why, and so were RWE and partially Centrica. I'm just wondering why, you know, given the clarity you have in your business plan, you're not going ahead and building your own vessel because you know you need it. If I may be cheeky and ask a one-liner as well, can I ask what the WACC is that you're using for the impairment testing of the North American projects? Thank you.

Mads Nipper

executive
#61

Yes, I can respond to that. Thank you very much. I’m able to address the first question. You’re correct that we entered this as vessel owners. In principle, we would far prefer to allocate our capital toward expanding renewable energy. We believe there are ways we can genuinely pass this on—as you said, we have a considerably larger pipeline and therefore greater build-out certainty than anyone else in this sector, which puts us in a distinctive position to make those commitments. That’s the reason we are doing so. We would much rather engage in discussions with companies whose core business is operating vessels, providing them with the commitments and the stable outlook that would allow them to make safer investment choices, instead of using our capital to become vessel owners ourselves. We are definitely drawing on the strength of our portfolio’s predictability. Again, we would rather not be vessel owners.

Daniel Lerup

executive
#62

Regarding the WACC point, a specific figure isn’t something I can provide, but our approach to applying WACCs in impairments is, you know, fairly market-conform. The same WACCs are what we use when making investment decisions. It reflects up-to-date, current rates. A classical capex approach underlies it, with leverage assumption and market betas. I’d describe it as a fairly standard approach, and naturally it is also being pushed higher by the high interest rate environment we are seeing right now.

Mads Nipper

executive
#63

Mark, if I could just—

Mark Freshney

analyst
#64

Thanks.

Mads Nipper

executive
#65

Maybe I can tack a bit of a second part onto your first question regarding vessels. I think this isn't about ownership either way, but for any vessel owner, one of the main things to weigh is, naturally, how future-proof is my investment? With turbines and foundations continuing to get larger, this is obviously something everyone is attempting to forecast: how large does my vessel have to be? So if the equipment ends up growing too big, is there a danger that my vessel becomes outdated within too few years relative to my depreciation period? That's another reason, or another area where we can add value as a customer: we're actually able to determine what turbine and foundation size we wish to use, and so provide that added certainty as well if we choose to enter those discussions.

Mark Freshney

analyst
#66

Great. Thanks so much, Mads and Daniel. Appreciate it.

Operator

operator
#67

Thanks, Mark. We'll take our next question from Dan Togo Jensen at Carnegie. Go ahead — your line is unmuted now.

Dan Togo Jensen

analyst
#68

Yes, hi, and thanks. I just have a question about how much flexibility you have in capex and financial planning. You've got a 50 GW target, with 30 GW of that for offshore. You expect to add 3 GW per annum, roughly in that region each year. From what I understand, you're a bit ahead at this point. How much flexibility is there? Suppose you're sitting here in 2023 and perhaps even in 2024 adding 5 GWs in the offshore zone auctions and tenders. Does that automatically mean you'd have to do a capital raise? I'm just trying to get a sense of what these step stones, so to speak, actually are, and how much flexibility your financial planning has right now. Thanks.

Mads Nipper

executive
#69

I'll start us off, Dan. Thanks. Suppose we get to a point within a year or two where we're adding firm capacity at a clip of 2 times 5 GWs — that would very likely set off a capital need, since it would represent an acceleration beyond that. Basically, it would put us near the full 2030 opportunity, and so it would be a strong signal that growth past the 30 GWs offshore is achievable. That said, I'd caution that this probably isn't the likeliest scenario, and as we've stated on many occasions, we aren't so hungry for GWs that we'd fail to keep a special eye on making sure we truly pursue the opportunities that create the most value. That matters a great deal. What we've observed is that we focus on project opportunities — whether centralized tenders or open-door — where we feel most comfortable with the potential for value creation. We would prefer to go a little low so that we stay on the safer side when it comes to value creation, rather than go really high simply because the opportunities exist. Naturally, that's a balance we have to strike.

Mads Nipper

executive
#70

In a scenario like that, we would probably go out and raise capital. I think it's less likely that we'd have 2 times 4 or 5 over the next 2 years.

Dan Togo Jensen

analyst
#71

Alright. Thanks.

Operator

operator
#72

Thanks, Dan. We’ll take the next question from Jenny Ping at Citi. Go ahead — your line is unmuted now.

Jenny Ping

analyst
#73

Hi. Thanks. Mads, I want to build on a point you made earlier about the U.S. projects as a portfolio showing a positive NPV, assuming a 40% ITC. Could you just factually tell us which of your U.S. projects includes the customer rebate clause as part of the agreement that was originally signed? Thank you.

Mads Nipper

executive
#74

Yes, we can. If I’ve understood your question right, that relates to our Ocean Wind One project. That one is New Jersey. In addition, for the later projects, it is New Jersey and Maryland that include these passback clauses, while the Northeast programs — South Fork, Revolution, and Sunrise — all lack a passback clause.

Jenny Ping

analyst
#75

Sorry—may I just double-check something? The clause refers to 4, 12%, right?

Mads Nipper

executive
#76

That relates to, I mean, the initial case had a 12% ITC, so it would go past that, correct? Danny, I'm turning to you.

Daniel Lerup

executive
#77

I’m not entirely certain I follow what you’re asking. Jenny, could you say the question again?

Jenny Ping

analyst
#78

I get that a few of those provisions mention a rebate above a 12% ITC. Clearly, you're working from a 40% ITC assumption.

Daniel Lerup

executive
#79

My recollection is that the initial figure was 18%.

Jenny Ping

analyst
#80

Alright.

Daniel Lerup

executive
#81

There is.

Jenny Ping

analyst
#82

I appreciate that.

Daniel Lerup

executive
#83

Above the 18%, there’s a passback mechanism that was already present when we submitted the initial bid in New Jersey.

Jenny Ping

analyst
#84

All right, that's great. Thanks so much.

Mads Nipper

executive
#85

So, Jenny, to point out what’s clear, for Ocean Wind One, where the ITC assumptions were lower, the possible upside from securing the full 40% is clearly very substantial and larger than it is for Ocean Wind Two.

Jenny Ping

analyst
#86

Much appreciated.

Operator

operator
#87

Thanks, Jenny. We’ll take the next question from Ahmed Farman at Jefferies. Go ahead — your line is unmuted now.

Ahmed Farman

analyst
#88

Yes, hello, and thanks for taking my question. I believe your remarks included a point that the present CapEx trend is running higher than what you had in the business plan at the time you guided to the 350 billion DKK. So I was just wondering whether you could share a bit more specific color on that. How significant is the current trend relative to the business plan assumptions, as you see it? And if possible, could you offer some granularity on how CapEx trends in the U.S. stack up against some of your key European markets? Thank you.

Daniel Lerup

executive
#89

You're right that we expect the average 20, or the 2027 figures we provided at CMD on the CapEx side, to rise because of the cost inflation and bottlenecks we're seeing. We also expect EBITDA and ROCE to increase, essentially offsetting that. We won't be updating all those numbers right now. We can simply say we see them trending higher. Naturally, at a CMD later this year, I think those are of course some of the key metrics we'll give you more detail on. On the differences in cost development across regions, I think it's fair to say that in the U.S., being a more immature market, we're seeing costs trend up somewhat faster than in Europe. You also have constraints such as the Jones Act, where it becomes a bit more difficult to secure the full suite of vessels for your construction projects. Bigger increases in the more immature markets.

Ahmed Farman

analyst
#90

Thanks. Could I just get some clarity, or follow up specifically regarding the ROCE point? Is it merely offsetting that, or is there actually some positive optionality on ROCE too? I ask because clearly you're posting above 16% this year, while your target sits at, you know, 11% to 12% across the period.

Daniel Lerup

executive
#91

Sure. One could make the case that ROCE wouldn’t rise unless it made up for the increased CapEx. What we expect is that ROCE will be moving upward as CapEx and EBITDA also move upward.

Ahmed Farman

analyst
#92

Much appreciated.

Operator

operator
#93

Thanks, Ahmed. Our following question comes from Stig Frederiksen at ABG. Go right ahead — your line is now unmuted.

Stig Frederiksen

analyst
#94

Thanks a lot for taking my question. It's a somewhat more technical one, about your decommissioning provisions. Those are rising by over DKK 5 billion, or close to 60%. Naturally, your portfolio has grown, and so on, but you're also mentioning the shift in methodologies and scope and the way you handle decommissioning provisions, and so forth. Could you expand a little on what to expect and what lies behind that rather substantial increase? Thank you.

Daniel Lerup

executive
#95

Right. That's naturally an area where we've picked up additional insight and have been pushing somewhat up against certain older assumptions as well. We're likewise observing that the vessel market is getting pricier. Part of that comes from increased vessel rates. To ensure we don't disturb the habitats of the offshore wind farms, we will, and this is probably quite far off, be cutting the monopiles rather than exploding them, which was among the earlier assumptions. We've also discovered that the decommissioning would have to be carried out in two trains instead of only one. There are several reasons for that, since we've done a pretty substantial deep dive to confirm that the assumptions we rely on also hold true for future worlds, so to speak.

Stig Frederiksen

analyst
#96

That’s great. Thanks so much.

Operator

operator
#97

Thanks, Stig. We’ll take the next question from Peter Bisztyga at Bank of America. Go ahead — your line is now unmuted.

Peter Bisztyga

analyst
#98

Yeah. Hi, thanks for taking my question. I figured it would be helpful if you could lay out the main milestones that have to be cleared before you can actually reach FID and begin construction on the U.S. projects. It's February 2023 now, and those projects are meant to be operational in 2025. It seems to me there isn't a huge amount of time left if they're going to be contributing EBITDA at some point over the next couple of years. Can I also get some clarification on something? You mentioned that you expect to be overall NPV positive, assuming a 40% ITC. Following up on Jenny's question, I guess, is that statement only true if you're able to renegotiate the customer rebate in New Jersey and Maryland? Thank you.

Mads Nipper

executive
#99

Yes, I can definitely speak to those. Thank you very much, Peter. So, regarding the milestones, what it really comes down to is getting all scopes ready and having enough locked-in debt — we're quite close on that. It's also about making sure we have sufficiently strong value creation that we feel it's financially right and prudent to take those FIDs. It's a combination of — let me frame it somewhat vaguely — stakeholder dialogues reaching a satisfactory conclusion, so that our EPC, and particularly our contracts, but also our EPC plan, is mature. Those are basically the two things required. You're absolutely correct that we're looking at hopefully near-term FIDs, but we won't rush them until that full construction plan is ready and until we reach a satisfactory conclusion on securing the top lines we need for the projects. Specifically on the passback, I'd say we can't comment on the specific dialogues, and unfortunately we'll continue to be boring on that front. We are — we do see a pathway to getting that portfolio. 2023 to 2025, we do firmly believe that this is one where we can get the life cycle NPV to be positive as well, and not just a forward-looking one.

Mads Nipper

executive
#100

That's about as near as I can get.

Peter Bisztyga

analyst
#101

I want to be clear about this. Where we are right now, the situation isn't positive.

Mads Nipper

executive
#102

No. That is.

Daniel Lerup

executive
#103

This all hinges on the belief that these projects will be able to qualify for the 40% ITC. Naturally, that is what we expect.

Peter Bisztyga

analyst
#104

Alright. Sounds good. Thanks a lot.

Operator

operator
#105

Thanks, Peter. We’ll take the next question from Lars Heindorff at Nordea. Go ahead — your line will be unmuted.

Lars Heindorff

analyst
#106

Thanks. Yeah, I have a question about the vessels—the installation vessels. I’m not sure whether you could give a status on what’s happening in Taiwan right now? We’re still waiting for a new installation vessel, and how much will that affect—or have any material impact on—your CapEx assumption compared with what it originally was when you started the project? Thanks.

Mads Nipper

executive
#107

Sure, we can definitely speak to that. For the Taiwanese projects we have coming up, we're quite far along in getting vessels under contract. The short answer, Lars, is that this isn't an outstanding concern.

Lars Heindorff

analyst
#108

Okay, thanks.

Operator

operator
#109

Thanks, Lars. Our next question comes from Alex Wheeler at RBC. Go ahead. Your line is now unmuted.

Alex Wheeler

analyst
#110

Hello, and thank you for the presentation and for taking my question. You mentioned the substantial volume of capacity that will be auctioned in 2023, and that it's crucial to see contract prices reflect the current environment. With that in mind, are there particular geographies that you see as more attractive right now as you consider the 2023 auctions, based on current visibility and the prospective auction structure? Thank you.

Mads Nipper

executive
#111

Yes. Thanks a lot, Alex. The straightforward response is clearly what's already out there publicly — specifically, the New York 3, which we've decided to bid into. At this moment, honestly, it isn't feasible to state with certainty where the most appealing chances lie, because take Japan, for instance, which proved quite difficult in round one, as I believe every observer of the industry is aware; we're still trying to figure out whether the revised framework for the upcoming auction is something that leads us to think it could be appealing — and we do think it can be. That's one example. Beyond that, we're putting substantial effort into really understanding the recently announced German auction framework so we can assess whether we think that framework will create opportunities for the strongest value creation. Naturally, we aren't huge supporters of auction frameworks in which negative bidding turns into a possibility, which appears to be the case here. That said, the abundant capacity suggests there might still be chances inside it. We are... I'd put it this way: we're tracking everything closely. What we know for certain is that although we sadly weren't successful, the upcoming Dutch IJmuiden 4 GW auction is one that in all likelihood will also appeal to us.

Mads Nipper

executive
#112

Beyond that, we're keeping an eye on all markets and not ruling anything out on this Slide apart from Ireland, since the seabed isn't available to us there.

Alex Wheeler

analyst
#113

All right, that makes sense. Thanks.

Operator

operator
#114

Thanks, Alex. Our next question comes from Vincent Ayral at JPMorgan. Go ahead — your line is being unmuted.

Vincent Ayral

analyst
#115

Yes. Thanks for taking my question. I want to return to the hedging topic. You've put up a few slides on it. Obviously, all the hedging in 2022 hit you. Just 10 — like 10 days ago, you were mentioning hedging levels of about 95%. In the pre-release, we heard roughly 9%. Today, for the hedging level on offshore wind in 2023, you cite 85 as the final figure. You've likely repurchased some volumes. My question here is that this probably cost money. Is it locked into the 2022 numbers, yes or no? Second, on the same subject, you discuss your new hedging strategy — cutting the other hedging and not exceeding 70% at group level, which is fine. You also mention IFRS 9, but IFRS 9 is a non-cash matter. It's an issue of presentation. You've been presenting on a non-adjusted basis. Why not shift to an adjusted basis? If you don't, basically, how much do you expect to unwind exactly in 2023 should the power price stay where it is? Doing nothing with current commodity prices would quite clearly produce a lower IFRS 9 impact in 2023.

Vincent Ayral

analyst
#116

I appreciate you taking these questions.

Daniel Lerup

executive
#117

During our conference call two weeks ago, I mentioned roughly 90%. The more accurate figure is 85%. That call wasn't focused on the hedge percentage, so it was more of a rough estimate. We've been repurchasing hedges in late 2022, so there's some cost embedded there. Also, some here at the start of 2023, and naturally that is reflected in the guidance we've provided. On the IFRS 9 point, you're correct. We want to ensure we adhere to the IFRS 9 method of reporting our figures, so that's what we're doing in our annual report. We're also providing supplementary information so you can see how significant the drag has been on our numbers. In 2022, it was DKK 1.3 billion. Since it's a timing effect and we expect it to return, we've factored in a profile that aligns with the underlying hedges. Of that 1.3, you have DKK 200 million coming back in 2023, which is also included in our guidance.

Vincent Ayral

analyst
#118

Okay, thanks a lot.

Operator

operator
#119

Thanks, Vincent. We’ll take the next question from Louis Boujard at Oddo. Go right ahead. Your line is now unmuted.

Louis Boujard

analyst
#120

Yes. Good afternoon, and thanks so much. Perhaps one question about how flexible you can be with your pipeline. Of that 11.2 GW of awarded and contracted renewable capacity — the portion not yet FID on the offshore wind project — is there eventually some room, if the discussion and the negotiation on some of them don't reach a conclusion, for you to decide not to proceed, not to take the FID, and eventually to withdraw them? If so, what would the financial consequence be for 1 or 2 of these projects if that had to happen?

Mads Nipper

executive
#121

Yes. Thanks a lot. I’d say our ambition is clear: to turn every one of these projects into reality. As you put it. In principle, I mean, you — there’s always an exit route, but naturally that has to be taken into account. What would that cost, both regarding commitments we may already have taken on and so forth. Broadly, that scenario is far more probable — not probable, but more probable than abandoning the projects. We’re saying we could gain ourselves time to collaborate with our partners so those projects improve, since some flexibility exists around when things happen. That’s much more the direction we’re considering. Where that scheduling flexibility — which we have in certain projects, obviously — where does it actually come into play in possibly reaching a window when bottlenecks are fewer, when pressure on commodity costs is lower and so forth, and when it aligns better with our construction sequence across different projects. We do have flexibility, and walking away from anything isn’t impossible, but we stay committed, and we’re working, first of all within the current timelines, but if truly necessary, also with a potential extension, to make the projects investable.

Louis Boujard

analyst
#122

All right. Just to follow up, if I may: should I take it that eventually there could be a CapEx that gets spread out over a longer timeframe, then?

Mads Nipper

executive
#123

Yes. Of course, other opportunities exist as well. As we mentioned earlier in response to a prior question, we see very substantial possibilities, spanning Onshore, offshore, centralized auctions, and open-door as well. A few of those could arrive in a comparatively nearer timeframe. For instance, we noted that among the up to 5.2 GW Danish open-door opportunities, some might actually reach COD as early as potentially 2027. And if we proceed and potentially extend things to improve the projects from the list already awarded, options could arise. I'm not claiming that will happen, but there could be options for directing that CapEx toward other projects. Please don't take this as us saying we're currently planning an extension or that we're planning to walk away, but I'd also say that if it does happen, it won't automatically imply a wholesale extension of the CapEx spend. Where value-creating opportunities exist, we would likely pursue them instead.

Louis Boujard

analyst
#124

Thanks. I really appreciate it.

Operator

operator
#125

Thanks, Louis. We’ll go next to Tancrede Fulop at Morningstar. Your line is now open—please go ahead.

Tancrède Fulop

analyst
#126

Hi there, and thanks for the question. I've got two. First, on CapEx and the 2023 growth investment guidance of DKK 50 billion-54 billion — that's well above what people were expecting, roughly DKK 32 billion. Could you walk us through where the upside comes from, how much reflects phasing, perhaps the Greater Changhua delay, and how much is inflation? That's my first one. My second question is on the U.S. project. You mentioned that most of them will be NPV positive if they qualify for an ITC of 40%. Should we read that as, fine, NPV positive, but the spread between IRR and WACC will sit below your target range of 150, 300 basis points — meaning you'll go ahead with projects that meet your returns result? Thank you.

Mads Nipper

executive
#127

Sure, I can offer some perspective on that. For the 2023 CapEx budget — the DKK 50 billion to DKK 54 billion range — roughly DKK 5 billion of that represents a carryover from 2022 into 2023. Beyond that, as we mentioned in response to an earlier question, we anticipate — and certainly hope for — a relatively substantial number of FIDs being taken, which would clearly speed up our CapEx spending. It's also worth keeping in mind that if you take the total CapEx we laid out at the most recent Capital Markets Day and divide it across the years, you'd get an average of roughly DKK 44 billion to DKK 45 billion. Across the past three years, the figure would land right about there. That isn't an unusually elevated level, but given the phasing across the two years and, hopefully, faster CapEx deployment on projects we've identified, that we haven't — we see this plainly in our plan. As for the U.S. projects, the straightforward answer to your question is yes: given the new realities around the cost of capital and CapEx inflation as well, those projects will fall outside our guided range of 150 to 300.

Mads Nipper

executive
#128

We obviously know that when we placed our bid, they sat comfortably inside that range at that point, but because of those circumstances, that is no longer the case today. As for the 23 to 25 portfolio, it reflects the assumptions we talked about earlier. At the portfolio level, those deals are NPV positive, yet they fall outside the range.

Tancrède Fulop

analyst
#129

Got it — thanks, that's very clear.

Operator

operator
#130

Thanks, Tancrede. We'll now take the next question from Dominic Nash at Barclays. Dominic, your line is open, and you're unmuted.

Dominic Nash

analyst
#131

Good afternoon, everyone. I’ve just got one question, and it’s about your partner—or partners, I should say—at Eversource and PSEG. Could you update us on the situation with the Eversource stake, specifically whether they’re still seeking to sell, and what kind of timeframe should we expect for news flow on that? Would you potentially look at buying it back, or acquiring Eversource’s 50% sale and repurchasing in a way similar to PSEG? Thank you.

Mads Nipper

executive
#132

Yeah, I can address that, though I won’t be able to give you a very detailed answer. Yes, the sales process with Eversource is still underway. It’s highly unlikely that we would buy the remaining 50% stake, even though we did that at cost in Ocean Wind 1 with the 25%, which, as we explained on an earlier call as well, was not because Eversource is running away, but because it’s now ITC rather than PTC, and Eversource or sorry, PSEG, had trouble monetizing that. That was the reason for it. With Eversource, things are moving forward. I don’t think we’re in a position to put a timeline on it. Eversource needs to be the one who answers that. As was said before, if anything, it would be a conversation between us and Eversource about potentially buying the seabed, but not the 50% stake on the Northeast program.

Dominic Nash

analyst
#133

All right, thanks.

Operator

operator
#134

Thanks, Dominic. Since time is nearly up, I'll pass it back to Mads now for any closing remarks.

Mads Nipper

executive
#135

Yes. I just want to say thank you so much for being with us, and I appreciate all those excellent questions, as always. If anything else comes up, you know our IR team would be glad to help with it. Thanks so much. Stay safe and have a wonderful day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.