Ørsted A/S (ORSTED) Earnings Call Transcript & Summary
February 7, 2024
Earnings Call Speaker Segments
Rasmus Keglberg Hærvig
executiveHi, everyone, and welcome to Ørsted's presentation of our full year 2023 results and our capital markets update. I'm Rasmus Hærvig, and I head up the Ørsted IR team — we've really been looking forward to sharing this update with you. Today, our CEO, Mads Nipper, will give an update on our business plan, and after that our interim CFO, Rasmus Errboe, will walk through our financial plan. That should take about an hour, and then we have an hour set aside for Q&A, where both the people who've joined us here at Gentofte today and those following online can pose questions. So with that, over to you, Mads, for the presentation. Thank you.
Mads Nipper
executiveMany thanks, Rasmus, and a warm welcome to everyone in the room as well as all of you joining us online. We appreciate you dialing in. As Rasmus mentioned, it's a very busy earnings day, so it's great to have you here with us. As Rasmus noted, beyond naturally presenting our 2023 results, we will also—given how challenging 2023 was—present our updated plan. We're very aware that 2023 was a significantly challenged year, not only for us but for all stakeholders, investors included, because of what happened in our U.S. offshore business and, not least, the very difficult yet economically rational choice to stop development of Ocean Wind 1 and, for that matter, 2. That resulted in significant cancellation fees on top of impairments we've had to realize, mostly also tied to that project. With that said, let me begin the business update, including outlining both what we've learned and what will happen going forward. So if we look at the summary of what Rasmus and I will be presenting, there are essentially 4 components.
Mads Nipper
executiveThe first item concerns the 2023 results, where the underlying business performance came in at roughly DKK 1 billion above the upper bound of the range we had guided to, which naturally left us pleased. We also saw a number of meaningful strategic milestones, and we stayed within what we had already communicated at Q3 regarding both impairments and the anticipated cancellation fees for Ocean Wind 1. We fully recognize that none of this ranks as the top priority for our investors, yet it remains an important backdrop worth sharing with you, and I'll do so in a format much shorter than usual. Another thing we have done — and we have worked intensively on this over recent weeks and months — is to make sure we carefully examine which events brought about the situation in our U.S. business, and in particular those that produced the highly dramatic developments on Ocean Wind 1, which resulted in terminating and ceasing development of that project. We have analyzed this, and we have drawn learnings that are either already implemented or currently being implemented. We have additionally carried out a substantial risk review across all of our offshore wind projects, making no assumptions that anything is under control, but instead conducting a systematic and structured review of what has occurred in our portfolio and applying key learnings from it to further de-risk those projects.
Mads Nipper
executiveWe will cover that in more detail today. Then we've carried out a portfolio review that results in a slimmer portfolio—but more importantly, one that is more focused, with higher value creation and a better risk balance. We'll also share the backbone of the updated plan we have, which is a robust business plan that delivers on what we set out to do. The core elements of that robustness—and also of ensuring we protect a solid investment-grade rating with a strong balance sheet—are that we are cutting CapEx and phasing it further. We have an accelerated and expanded partnerships and farm-down program, and we've decided on a 3-year dividend holiday. Then we're also reducing both our development costs and our fixed costs. Let me dwell on that for a second. This has also led us to announce today that during this year we are removing 600 to 800 positions in the company, and to announce today as well that 250 colleagues will leave Ørsted. Obviously we are committed to doing that in a respectful and fair manner, but it is an important part of our program to ensure we further strengthen our competitiveness.
Mads Nipper
executiveTaken together, this should deliver a savings of roughly DKK 1 billion in 2026 versus 2023 on a like-for-like basis. And as you'll hear us repeat, all of this means the updated guidance holds at an unchanged spread of 150 to 300 basis points to WACC. As I'm sure you know, that's industry-leading, and it's fully loaded — fully cost-loaded with our fixed costs included as well. An unchanged average return on capital employed of 14%. Estimated installed capacity of 35 to 38 GW by 2030. That figure is a reduction, but it's also one that comes with an investment program that, on a like-for-like basis, is approximately a third. So when you compare the DKK 475 billion announced at the Capital Markets Day with our roughly DKK 270 billion now, on a like-for-like basis, adjusting for what we spent last year, that's a reduction of a third. And that produces EBITDA of DKK 39 billion to DKK 43 billion by 2030, excluding new partnerships. That's average growth of around 8%. And I'll note that this number would have been around 10% if we had landed in the middle of our guided range for 2023. So the CAGR toward 2030 is naturally, mathematically lower because the underlying business performed better than expected in 2023.
Mads Nipper
executiveThat's essentially the skeleton and the main points we're bringing to you today, though naturally we'll go deeper into each of those areas. Let me quickly recap 2023 once more through the underlying business results. DKK 24 billion in earnings before partnership and cancellation fees. Return on capital employed came in at 12.9%, net of cancellation fees and impairments. We finished the year with DKK 26.8 billion of impairments, a touch below what we had estimated, and that was because interest rates were lower. We closed out with a reduction of almost 50% across our Scope 1 to 3 emissions, plus a really substantial cut in Scope 1 and 2, which came from burning far less fuel at our combined heat and power plants. On the strategic side, the milestones included 4.5 GW of final investment decision, among them Hornsea 3, the largest offshore wind farm in the world. We'll return to that, since it's such a major project for the company. But we also saw strong — there was good momentum in a number of our chosen high-priority markets, illustrated here by securing the electricity business license for the Greater Incheon project of 1.6 GW, located close to a heavy load center around Seoul.
Mads Nipper
executiveWe kept up our successful farm-down track record, with 2 transactions closed. Construction moved along well, and we're approaching COD at both South Fork Wind and Greater Changhua 1 and 2a. We also broke ground on Flagship One, Europe's largest e-methanol facility, as well as on our Danish carbon capture and storage opportunity here. That's all I'll say about 2023. Rasmus will return with a bit more of the details, including the 2024 guidance, but apart from that, let's turn to some of the events we've learned about, that we've implemented, and that will shape the backbone of our plan going forward. So which negative events have hit us since the Capital Markets Day, and particularly hit our investment capacity? Most notably, unsurprisingly, is the cancellation costs of the ceasing development of Ocean Wind 1. Since this is FFO, this is something that has a material impact on our investment capacity. But we've also seen that the forward prices, and hence also the expected revenues, have come down, and in select markets, just over the last months, we have seen the markets come down, the forward prices come down as much as 40%.
Mads Nipper
executiveWhen it comes to supply chain effects, 2 impacts are noted at the bottom. The first is broad inflation, which has persisted, though not at those same steep rates; the more significant one, however, is that through our risk review we have raised both our contingencies and the pre-commitments we have made to secure backup capacity for the critical path, or for certain project components in the execution that could otherwise carry a risk of larger material consequences. That carries a cost, but it should be viewed as an insurance policy protecting against far bigger potential effects. So we see being better prepared for that as a positive. And that also sets up the structure for what I'm going to cover over the next 15 minutes: we have finished the review of the events at Ocean Wind 1 and put the learnings into practice. We have run a risk review across every one of our projects. We have completed a portfolio review that produced a smaller — and again, more importantly — focused portfolio. And then we are putting measures in place to make sure we have a strong and robust plan. And so, without any further ado or delay, let's turn to what happened at Ocean Wind 1, since that is the most significant impact that hit us in 2023.
Mads Nipper
executiveTo begin on the left-hand side, what actually took place? For background, these projects — every one of our early-stage U.S. projects — were materially affected over an extended period by the broadly adverse conditions in the industry. That has hit the whole industry, but since these projects carried no form of inflation indexing, with interest rates climbing and capital inflation rising substantially — 3 to 4 times as high as consumer price inflation, and even greater in an immature market such as the U.S. — the project was already one whose returns were under pressure and which had also lost most of its float in the schedule. We had chosen — and it seemed like the right call at the time — to keep maturing the project, to keep developing it, and simultaneously to commit capital into it with the aim of preserving the plant and the committed COD date. With what we know today, that was not the right call, because it meant that in a pre-FID project we were committing very significant capital, and given the events that struck, it was the wrong decision in light of the knowledge we now have. Beyond that, we made — we had also made ourselves, with the aim of qualifying for the tax credits, dependent on an immature supply chain in the U.S.
Mads Nipper
executiveWe were quite sure this was going to be constructed, so we were heavily involved in creating new facilities. We actually took part in making sure final investment decisions could happen on newly built vessels. We felt confident this was progressing well, yet it moved ahead more slowly for a whole host of reasons, including a shortage of skilled workers, problems with ramping up, and additional issues that did arise. As a result, overall, and particularly during the summer and early fall, we encountered quite a few delays along with suppliers who did not meet their commitments. That meant that, taken together, it was very severely impacted. At that point, we found ourselves unable to secure backup capacity for installation in 2025. If we had known earlier, that could perhaps have been arranged, but by the time we learned of this, it was too late, which, as I'm sure many of you have heard us mention previously, meant the project would encounter a delay so large that we would ultimately need to recontract most of the CapEx at even higher rates. That is what in the end drove the extremely tough, though as I said, economically rational choice to stop development.
Mads Nipper
executiveBeyond that, we discovered — and this is another lesson we're putting into practice — that although they didn't appear critical at the time, a couple of local construction permits ended up being harder to obtain and a larger risk to the project than we had assumed. We also encountered an additional delay with the project's air permit, which once again created extra uncertainty. And when the decision was made, it still wasn't clear which additional tax credit we would be eligible for. Even more important is what we've learned and what we're implementing after this chain of events with Ocean Wind 1. On the supply chain side, we've placed considerably more emphasis on contingency planning — essentially scenario planning around what could go wrong, particularly if several of the material risks we're tracking occur simultaneously. It won't surprise you that for a very long time we've already done thorough work on risks individually. In fact, our project has always maintained a risk register with more than 100 risks identified and quantified, along with the steps needed to mitigate them.
Mads Nipper
executiveBut it's really more about asking: what if these things happen at the same time, if some of the ones with critical dependencies occur? We've increased our capability to handle that, and that also means we've increased our capability to secure things more proactively, particularly installation capacity, well in advance, so that we can soften the most significant impacts of this. That's an absolutely key lesson. We've also learned that especially in newer markets, but also when we have new capacity under construction, such as new build vessels, being even closer to the yards and the manufacturing facilities to check whether the projects are following the construction timelines — and if not, can we help, or can we, in those cases, now also do more proactive contingency planning? Then, especially following a stretch with extremely volatile environments, we've also clearly made it a priority that we will take only inflation-indexed contracts, particularly in markets such as the U.S., where a long time passes from award to actual FID. In a market such as the U.K., where, incidentally, inflation protection exists, the timeline between award and FID is far, far shorter, so risks are lower there. When it comes to the CapEx and break-even profiles, what we've learned in that part of our business is significantly higher scrutiny of pre-FID commitments.
Mads Nipper
executiveWe won’t return to the same level of pre-FID commitments that we had in our early-stage U.S. projects, and particularly not in Ocean Wind 1. Pre-FID capital commitments are going to look completely different from what we saw at those projects, and we’ve already put that in place, as shown for instance by Ocean Wind 2, which was a newer project. We had far, far, far, far less committed there. So that was a lesson already in motion, but we will scrutinize further and further constrain the risks from those pre-FID commitments. Likewise, we want every critical local permit secured before we take FID or make capital commitments. And lastly, we will clearly prioritize projects that have flexibility in the COD timeline. Because if we have that flexibility to delay a project by one, 2 years, that gives us significantly more flexibility in how we commit our CapEx as well. That is even better for the offtaker of this power, because it is a lot better than a project being built a year later than it not being built at all. Then on governance and review of the risks, there are also a few learnings already implemented here.
Mads Nipper
executiveSo we're doing — we've always had stage gate reviews, but now we're doing them in an upward way, internal reviews, so that teams, expert teams from outside the project team, are scrutinizing ahead of the stage gates to make sure that before we commit any additional resources, we've been through a challenge session. On select projects, as we've done for several of our existing projects, we've also brought in external reviews that really challenge and come in and say, "Is there something here that we might not be seeing?" We won't do that for every project, because we do strongly believe we have the deepest capability in the company, but we have chosen, and we will continue to choose, that on select projects we'll do those risk deep dives. Finally, we've also increased the frequency and the scrutiny with which we in top management, and also the board of directors, take a view of these top risks. And we've already institutionalized, since a couple of months, that we do a systematic project-by-project top risk review, including pushing for mitigating actions if needed. So with all of these things, we feel a lot more comfortable — not only that we won't run into an Ocean Wind 1-like situation again, but also that our general organizational capability to better and more proactively manage risks is better.
Mads Nipper
executiveNow let me move on to the portfolio of projects we have under construction. It's a bit out of the ordinary for a CEO to do this. However, with the conditions and the situation we're facing, we believe it makes sense for me to walk you through each project, one by one, and give you the status of where things stand, including what exactly we're doing and preparing on every one of them. So, starting with Greater Changhua 1 and 2a and South Fork — those are 2 projects that are finishing right now. As we speak, we're installing the final 4 turbines at Greater Changhua 1 and 2a, Taiwan's first genuinely large, significant-scale offshore wind farm. It will be commissioned before the end of Q1. The same applies to South Fork, the first utility-scale offshore wind farm in the U.S., and in particular also in the state of New York. We've installed 10 turbines. The 11th is loaded, and once the weather allows, it will head out and complete that construction too. Both are expected to reach COD with no or limited risks before the end of Q1. Moving to the German program, which, as you probably know, is made up of 2 projects — Gode Wind 3 and Borkum Riffgrund 3.
Mads Nipper
executiveGode Wind 3 remains on schedule. All monopiles have now been installed, and Borkum Riffgrund 3 is moving forward nicely too, though its timeline is tighter. The main reason for that is the monopile supplier, which is still working through some ramp-up difficulties, even if the present plan shows no project delay. In any case, we're in advanced talks to lock in an extension of the installation vessel so that any additional possible delays won't actually affect us. So this is a project that illustrates that with this risk — even though the current plan and the supplier's current messaging don't point that way — we're saying we need to exercise prudence, particularly given that we're also present at the fabrication site, because there is a chance the completion of those monopiles slips, and we're ready to pay that premium. On Greater Changhua 2b and 4, a very significant milestone was also achieved in the last few days. Manufacturing of the offshore substation has been completed ahead of schedule at a yard in Singapore. And here as well, we have — we do have a compressed schedule, but one that is on plan.
Mads Nipper
executiveWe are likewise engaged in active conversations to proactively reserve installation capacity for the start of 2026, should the 2025 schedule end up too compressed. And for those of you who have — who knows how dramatic entering a new installation window can be, the economic impacts of doing so are much lower if, in due time, we actually book and plan that additional capacity. So that is another example where a tighter schedule has us in advanced discussions to book it. On Revolution Wind, our first very big project to reach FID at a difficult date for the company, namely on November first, we have signed all major contracts. As I believe I also mentioned at our Q3 call, we have secured full and 100% backup capacity for the delayed Jones Act-compliant vessel. We have the Scylla, which is a barge solution to install. By the way, that is the same solution we have on South Fork, and we have ramped up installation speed to the necessary level, so we are seeing that installation scope perform. We also have a very strong focus here on monopile delivery, because 20% of the monopiles for Revolution Wind are delivered by the same European supplier, who has the ramp-up challenges I mentioned for the German program.
Mads Nipper
executiveFor that project, the supplier is delivering 13 monopiles to us — 2 of those are destined for the offshore substations, and those 2 are what we're prioritizing. Rather than simply pressing for the whole lot, we're saying, "Pull forward those 2 that are essential for the offshore substations," since any delay then has an immaterial impact on the project economics. If, on the other hand, we couldn't install the offshore substations, we simply couldn't export the power. So that's one example of how we're also working in detail to make sure we proactively mitigate and manage some of the bottlenecks we face. Hornsea 3 — I'll do a special mini deep dive on that in a minute, because it's so big that it warrants special attention. Sunrise Wind, the first of our 3 awarded projects, so not yet FID'd — we have signed most contracts. As I'm sure most of you will be aware, we have bid that into the New York 4, so a rapid rebid round, where there were 3 bidders for a quite significant capacity. So we're optimistic about a good outcome from that without knowing anything, of course. We are expecting in Q1 the Record of Decision, which is the key federal permit, with all permits being in place no later than over the summer.
Mads Nipper
executiveA number of you are probably wondering whether a potential change of administration in the White House creates any regulatory exposure. That ought to be resolved well before then. And then, too, there's a very heavy emphasis here on monopile delivery, which again was set to come mostly from a supplier facing ramp-up difficulties. But we've already proactively descoped from 84 down to 28 monopiles, which means 2 other suppliers have taken up the remaining capacity, and both of them are on track. So from an execution standpoint, we believe this project is in a good spot, and here as well we've partly lined up backup capacity, though we're discussing whether we should also pursue 100% backup capacity, as we have for Revolution Wind. On Baltica 2, where we anticipate FID later this year, that's another project where most of the contracts are secured. Our breakaway costs are relatively low, assuming we reach FID not too far into the year. Out of prudence, we've raised the project contingencies without them being specifically tied to any known bottlenecks in the project. And lastly, for Baltica 3, which, as we've consistently said, is being reconfigured.
Mads Nipper
executiveThat remains true, since it's the single project where we still aren't confident about landing inside our guided range, though we're putting in serious effort on it. If not, we'll need to reassess later in the year what we intend to do with that project, but cancellation fees there are quite limited. Moving off this slide, 2 key messages. Most importantly, thanks to the mitigating actions we've taken and the deep dives we've carried out, we genuinely believe our risk profile is manageable and that we have strong visibility and are taking proactive mitigating actions. Secondly, apart from the 2 U.S. projects, both of which look very attractive from a forward-looking returns standpoint, the Asia-Pacific and Europe project portfolio sits inside the guided range of 150 to 300 basis points spread to WACC. That's an important piece of information, notwithstanding the turbulence we've witnessed and the extra cost of the mitigating actions we've undertaken. Let me address Hornsea 3 specifically — I won't spend much time on it, but as we've stated, this is a DKK 70 to 75 billion CapEx investment, so nearly 50% of the whole company's market cap, and so we felt it would be relevant for our investors to have that insight.
Mads Nipper
executiveWhat makes us comfortable with that risk profile? Let's begin with the regulatory framework conditions — this is a well-known and very attractive regulatory framework, and one illustration is that we have the chance to bid in the non-CFD capacity for Hornsea 3. That's an attractive opportunity for us to increase value and a key component in being able to bring it forward to FID. The timeline from award to FID is very short, which means some of the risks we've seen materialize in the U.S. market are very, very small compared to anything we've seen in other parts of the world. All permits are in place, so before we even bid in, we had all permits in place for Hornsea 3. We have CPI inflation-indexed CFD agreements, and we have a well-known and well-developed regional supply chain in Europe. We do have all major contracts in place, and we have very little doubt that the LCOE per megawatt is the lowest of any under construction project in offshore in the world, because they were secured at attractive levels. We do have a flexibility, and float in our schedules, and then we have also ensured that even though there are 2 relatively new-built vessels for the project, we are not the first offtake of those.
Mads Nipper
executiveThe teething problems that can come with newly built vessels will most likely be finished by the time we take delivery, and our start date is contractually committed while the end date stays flexible. So the installation scope is something we're comfortable with. Then when it comes to execution, this is our third project in a row. Hornsea 1, Hornsea 2, and now this project — it's one where the team is extremely experienced, probably the most experienced team we have, and from a cost perspective this project enjoys significant O&M synergies with Hornsea 1 and 2, and who knows, in the not-too-distant future, with Hornsea 4 as well. Moving to our portfolio review: the 3 key principles we applied when we carried out that review at the end of last year were, most importantly, value over growth. It's critical for us to be able to give a firm commitment that when we prioritize a project for investment, it delivers within our guided range, even if that means lowering our growth ambitions. The other thing is having a solid capital structure, where whatever we do across the totality of the portfolio supports a solid investment-grade credit rating.
Mads Nipper
executiveAnd then, finally, given the opportunities we can see, we want to focus in very sharply on the markets that matter most — our core markets plus a chosen handful of future markets with high potential. In the briefest possible terms, the result of that portfolio review was this: if we begin with U.S. offshore, which naturally draws a fair amount of attention, we continue to think the U.S. offers attractive offshore potential, and for the time being we are focusing even more narrowly, chiefly on the Northeast. You can see that in our hope to build 3 projects, among them Sunrise, subject to a positive award in New York 4, and also in our continued development of Lease Area 500 — our 4-gigawatt, highly attractive piece of real estate situated outside New England and New York. We have decided to leave certain offshore markets. It's very important to say offshore, since we still have onshore activity in Spain, but Norway, Spain, and Portugal are markets we are exiting, and we are also deprioritizing additional offshore development in a number of markets, Japan among them. Beyond that, we have adopted a considerably leaner approach to both Power-to-X and floating offshore wind. That isn't because we lack belief in those technologies or because they carry no strategic importance, but because we are holding our commitments on both development and expected CapEx up against market development that has been slower than anticipated.
Mads Nipper
executiveBasically, then, what that means is our commitments—regarding capacity, but also regarding the CapEx commitments we're planning toward 2030—now sit at a lower level, as a result of that portfolio review, driven by this development of the market, which is slower. And lastly, as we'll return to, and not least, Rasmus, we're speeding up our partnership and divestment program. Turning specifically to the U.S., let me just address the left-hand side of this slide. What are a few of the more concrete outcomes? Most of them I've already commented on: we have withdrawn our Skipjack OREC agreement in close dialogue with the state of Maryland and with support, and we're now examining the most value-creating path forward on that asset. We've submitted the OREC rebid for New York, and we've reached the agreement with Eversource regarding a conditional takeover of the project. That applies in the event of a positive award of the project. In the event of a negative award, we will still have an intact joint venture, meaning risk-sharing with our partner, Eversource. We'll keep developing our seabed leases toward the permits, so that this, in any event, raises the value of those assets.
Mads Nipper
executiveWe’ll go after appealing offtake chances in a selective and opportunistic way. So we’ll assess which upcoming opportunities arise through auctions, but with a very clear requirement: these must be auctions that permit the very limited pre-FID cap and capital commitments. If not, they don’t appeal to us. Still, we’re glad to see that New York and New Jersey have produced auction results with realistic offshore prices for offshore power, and also that the last 3 auctions either held or launched include inflation protection between award and FID—something critically important for our sustained commitment to the U.S. offshore market. And then, perhaps obviously, we’ll keep watching very closely the conditions under which we operate. Is there political support? Are the support regimes of the federal incentives and the permitting regime still intact? And we’ll also watch to see continued realistic offtake prices. Overall, a focused portfolio in U.S. offshore, but still a belief that this market offers attractive opportunities that we will, obviously, examine very selectively. Turning to our CapEx program, as I briefly mentioned, on a like-for-like basis, these 2, approximately 270, represent roughly a one-third reduction compared with what we presented at the Capital Markets Day.
Mads Nipper
executiveThe technology mix is pretty much the same as before — roughly 70% offshore, and that continues to be far and away the top strategic priority for the company, though strategically we remain very comfortable being a company that spans several technologies, including solar, battery technology, offshore and onshore wind. And if we translate that into what it means for our capacity? Well, the main takeaway from this overview, which adds up to approximately 35 to 38 gigawatts of installed capacity, is what we see as a really healthy balance between high visibility of investments and earnings, thanks to more than 25 gigawatts being either in operation or under construction. As I said, in our offshore portfolio, under construction with projects that are delivering the returns we target. But at the same time, we also benefit from what we consider good flexibility in these 11 to 14 GW of additional capacity. So that gives us the flexibility to deploy capital toward the most value accretive opportunities out there. As things stand right now, we estimate that split at roughly 50 to 50 between onshore and offshore, but this is clearly something where we still have flexibility. And if I go a bit deeper into offshore, we have 15.5 GW of operational and awarded capacity.
Mads Nipper
executiveAlso, just as a point, the 6.7 GW of capacity currently under construction is the largest amount this company has ever had — and it's also more than any other developer globally. So even though our plan now sits at a different level than the one we showed eight months ago, we're comfortable that our offshore leadership remains strong. We do hold 3.7 gigawatts of awarded capacity, though we still view that as flexible, since FID has not yet been taken on those projects. That also means, for instance with Baltica 3, that if we conclude it isn't a value-accretive opportunity delivering the returns we require, we see a meaningful chance to secure that through other options. We've pointed to a couple of named options, like Hornsea 4, which — given the far more realistic administrative strike prices in AR6 in the UK, and probably AR7 as well — is something where we believe there's an opportunity for healthy value creation. And similarly, with better frame conditions in the upcoming Taiwanese auction, where we didn't bid in the last one, Changhua 3 is also an opportunity we think could be strong. But we haven't made that decision yet, because from those 2, and also from the well over 20 gigawatts of relatively near-term upcoming solicitations, we'll simply choose the ones delivering the most value with the best risk-return perspective.
Mads Nipper
executiveSo all in all, roughly 20 to 22 gigawatts of offshore capacity installed. And when it comes to onshore, that's where we have 6.4 gigawatts operational and under construction. Because CapEx cycles are much shorter here, you'll notice that a larger share naturally still lies ahead of us. But this is also an area where we have not only highly attractive pipelines of nearly 30 gigawatts and some strong, experienced regional teams, we also have — which mattered particularly in very volatile markets — a market where the connection between CapEx cost levels and offtake price levels is much shorter, so something that essentially de-risks the commercial realities of these projects. But an estimated 5 to 7 being secured, with a roughly proportional split between Europe and the US. And to sum up, before I hand over to Rasmus, all of this leads to the updated guidance targets I already mentioned at the start, but let me repeat them. An unchanged industry-leading, value-creating target of a 150 to 300 basis point spread to WACC. Average 14%, return on capital employed. Please look at the shape of these curves, still with significant growth, with well over twice as much installed capacity as we have today being installed by 2030, so 35 to 38 GW, and then an EBITDA growth of these, with the strong starting point of 23.8% average to 39%-43% or billion DKK.
Mads Nipper
executiveSo with that said, Rasmus, I'll turn things over to you.
Rasmus Errboe
executiveThanks a lot. And a warm welcome and good afternoon to everyone from my side as well. Over roughly the next 30 minutes, I'll walk you through 4 things. First, I'll cover our earnings results for 2023. After that, I'll briefly run through the outlook for 2024. Then I'll devote most of my time to our short-term business plan, essentially 2024 to 2026. And last, I'll say a little about our long-term financials. Even with the substantial challenges we've faced in the U.S., which Mads has also discussed, 2023 turned out to be a comparatively strong year when it comes to how our business performed fundamentally around the world. Our EBITDA landed at DKK 24 billion, which was DKK 1 billion above the guidance we had issued of DKK 20 to 23 billion, and also DKK 3 billion above what we delivered in 2022. Looking at the main drivers behind that result, first, EBITDA from our assets — so from our offshore business, which we track closely — came in at DKK 20.2 billion. That was a significant increase, as you can see, compared with 2022, with the main driver obviously being that in 2023 we didn't have, you could say, the extraordinary hedging effects that we saw in 2022.
Rasmus Errboe
executiveAnd that also fueled the ramp-up we were hoping to see from our core offshore wind segment, with Hornsea 2 scaling up along with Changhua 1 and 2A. Wind speeds were a bit higher that year than in 2022, though they remained under what we refer to as a normal wind year. For our existing partnerships, the year landed at DKK 900 million, which is DKK 400 million lower than 2022. The primary factor for that DKK 900 million was a few one-off items in Q4, when we reversed provisions tied to wake and warranties across a couple of our farm-down agreements. Turning to onshore, we closed the year at DKK 3 billion, slightly below what we saw in 2022 as well. The key reasons were the lower prices we experienced, particularly in the UK but in the US too, plus somewhat reduced availability in the US. Within the portion of our earnings mix we label bioenergy and other, our CHPs delivered a significantly smaller EBITDA contribution in 2023 compared with 2022. Naturally, that was also shaped by 2023 being a more normal year, so we point to the lower power prices, and additionally the relatively high fuel cost feeding into the spread that we discussed at length during recent quarters.
Rasmus Errboe
executiveNow turning to what we see ahead for 2024. The guidance we're issuing today points to EBITDA for 2024 landing somewhere between DKK 23 billion and DKK 26 billion. That gives a midpoint of 24.5, a touch above what we earned in 2023, which, as you'll recall, was a fairly strong year in terms of underlying performance. Looking at the main drivers we anticipate over the year, starting with our own side, EBITDA — here too we're glad to see it, and we anticipate it rising by DKK 1.5 billion across the year, once again powered by the ramp-up in our offshore business, with Changhua 1 and 2A, plus South Fork in the US and Gode Wind 3 in Germany. When it comes to our existing partnerships, we don't anticipate those one-off effects I referred to earlier regarding the reversal of provisions, and that's the reason we're expecting earnings in 2024 to come in lower than in 2023. Under the category we refer to as CapEx and other, there are 2 effects worth keeping in mind. To begin with, this figure includes a one-off effect stemming from our internal hours — the internal time we spent connected to the cancellation and wind down of Ocean Wind 1.
Rasmus Errboe
executiveFor accounting reasons, you can't include this in your provision, so that's going to affect our 2024 earnings. On top of that, there's another effect: we've chosen to be a bit more — even more — prudent in how we expense our CapEx from overhead. So we're also doing somewhat more expensing, though this isn't caused by any underlying shift in our cost base. We anticipate a substantial ramp-up from our onshore business in 2024, driven by 4 solar farms coming on stream in the U.S. And finally, for bioenergy and other, we do expect DKK 500 million more in 2024, essentially bringing that part of our business back down to what you could call a more normalized level, also when it comes to pricing. Changing topics, moving to the short-term business plan. Given the events Mads has discussed, we've devoted considerable time to examining our capital allocation principles. Behind me are 3 key capital allocation principles for Ørsted. We've essentially chosen to revise 2 of those 3. Taking FFO to net debt first, under this plan we're targeting an FFO to net debt above 30%, which aligns with a solid investment grade rating.
Rasmus Errboe
executiveThat's higher than the 25% threshold we presented at the Capital Markets Day. The reason for this is that we recognize the agencies perceive greater risk in offshore wind as a sector, and in Ørsted in particular. Our dialogue with the rating agencies is very good — constructive and productive — and it isn't for me to say today whether a one-notch downgrade will or won't occur. What I can tell you, though, is that if it did happen, we would still, of course, hold a solid investment grade rating, which is what we're targeting as of today. And to be 100% clear, the plan we're presenting today doesn't depend on a particular rating of BBB+ or Baa-. With the plan we're presenting today, we could absorb that. On the capital structure and the metrics as well, we think that with this we've struck the right balance between a robust balance sheet and valuable growth. So we believe this metric we're setting out today, with a target above 30%, is the right level for Ørsted. Regarding dividends, as Mads also said, we've chosen to pause them for 2023, 2024 and 2025, meaning payouts come in the following year.
Rasmus Errboe
executiveWe have a goal of bringing dividends back for 2026, with the payout occurring in 2027. We completely understand and recognize how important it is to return dividends to our shareholders. However, we do think that, given the situation our company is in, achieving the greatest short-term visibility on our earnings during this crucial stretch from 2024 to 2026 means that pausing the dividend is the correct move for us. That said, I mentioned we aim to restore the dividend starting again in 2026 and going forward. Last, on value creation. This is the piece you could describe as unchanged. We do believe, however, that with this plan, we have even greater confidence in our capacity to keep delivering the industry-leading, value-creating target that Mads also discussed. And once more, the example Mads brought up — that in fact 5.8 of the 6.7 GW in our offshore constructed portfolio, European and APAC, falls inside our guided range as of today. With these capital allocation principles in mind, we have taken a very thorough review of our short-term business plan, and we are setting in motion the following changes. First, we have chosen to cut our CapEx by DKK 35 billion, compared with the figure we presented at the Capital Markets Day for this stretch of time, from 2024 to 2026.
Rasmus Errboe
executiveThree factors are behind this. First, clearly, the project cancellations — offshore wind being one example — but also the reprioritizations Mads brought up, with markets as examples, and last, the phasing of CapEx. A quick note on phasing. Our thinking on offshore wind projects is that ultimately, although we of course aim for and consider a specific year for a COD, what truly counts for us at the end of the day is value. So whether a project lands in 2028 or 2029 isn't critical to us. What truly counts is delivering the project in the best possible manner from a value standpoint. That also means we have considerable flexibility across our portfolio when it comes to phasing CapEx. Regarding our farm-down program, we're speeding that up somewhat compared with what we assumed at the Capital Markets Day, meaning we expect roughly DKK 15 billion of proceeds more across this period than what we assumed at the Capital Markets Day. I'll return to that in far greater detail. On CapEx, we've made a significant reduction here as well, cutting our CapEx for 2024 to 2026 by a total of DKK 3 billion.
Rasmus Errboe
executiveThen last, regarding fixed costs, we're committed to cutting our fixed cost base by DKK 1 billion, with full-year effect in 2026, relative to 2023 on a like-for-like basis. So clearly, the redundancy points Mads raised earlier today are, of course, part of this element of the updated business plan. Turning to the right-hand side, I'll say a bit more specifically about our rating metric. These charts are, of course, illustrative, and the starting point is, as you can see, the 29% FFO to adjusted net debt shown in our annual report today. The movement you then see is that during 2024, we'll see a significant drop, obviously, in our FFO, because of the cancellation fees. And from there onward, we expect FFO to rise steadily across this period of time. At the same time, we expect our adjusted net debt, you could say, from a high point in 2024, to remain roughly stable, edging slightly lower over this period of time. These developments lead us to expect that our FFO to net debt will be significantly below 30% in 2024. We expect it to be around 30, 30% in 2025, and then we expect it to be comfortably above 30% in 2026.
Rasmus Errboe
executiveOf course, the net debt side is also among the forces driving this development, along with how large the CapEx program is and how large the divestment program is, but also very much the strong underlying cash flows from our business. Moving on, still within the short-term business plan, a few words about the gigawatt growth we expect in this period. I think there are 2 takeaways on this slide. First of all, despite the changes we are making today, we are still growing by more than 50% in this period in terms of our installed gigawatts. And secondly, 2-thirds of that comes from assets already under construction across offshore and onshore. So it is all the projects Mads mentioned earlier, except for Hornsea 3, which is COD-ing in 2027. So that one is not part of this build-up, but all the others are from an offshore perspective. And then we have an awarded bucket here of 2 gigawatt, where half of that is Sunrise. So should we decide to move forward with that project on the back of a successful outcome of New York 4, then we would have only 1 gigawatt of onshore left, that we, in the awarded part of our build-up towards 2026.
Rasmus Errboe
executiveWhen it comes to investments, and again I'm giving you somewhat more detail than we usually would for this timeframe. We have an investment program — a set of DKK 130 billion of gross investments during this period. Taking them bucket by bucket, we expect to spend DKK 57 billion on our offshore wind farms that are under construction. So, as Mads said, this is a bucket that, to me, carries a very high degree of certainty, with sufficient contingencies, and we've been through the very detailed review over the coming months. So that's a bucket I expect to be basically very close to what I'm showing you here, with a high degree of certainty. The next bucket is DKK 35 billion on our awarded offshore portfolio. That's Baltica 2, Baltica 3, and Sunrise. You could say this is a different way of thinking about it. As Mads also said, Baltica 3, for instance, sits in here. That's a project where we said at the Capital Markets Day that we're reconfiguring it, and that still stands. And there's a scenario in which we don't move forward, because we don't see the value creation. But that's what we've assumed in the number — that we're moving these projects forward with DKK 35 billion during this period.
Rasmus Errboe
executiveWe’ve also earmarked DKK 5 billion for additional offshore opportunities. That might be Hornsea 4, it might be Changhua 3, or it could be a centralized European tender. Clearly, these are projects with a COD much later than the 2026 timeline I showed earlier, but they’re still projects where we have some headroom to invest within this same timeline as well. On the onshore side, you can see DKK 25 billion here. To me, this is different. Here, only DKK 5 billion is under construction. So that’s DKK 5 billion that is locked in, tied to, for example, the 4 U.S. solar farms I mentioned earlier. And then you have DKK 20 billion in your pipeline. So these are projects that we haven’t yet, you could say, locked in, where we haven’t yet reached FID. So also where we have a relatively high degree of flexibility, including from a CapEx deployment perspective, but where we’re very confident in our ability to deliver this, supported by the onshore pipeline across Europe and the U.S. that Mads showed earlier. And then finally, we plan to spend roughly DKK 8 billion on P2X and bioenergy during this period. The result of this is the EBITDA development you can see here, which is the expected EBITDA.
Rasmus Errboe
executiveRegarding 2024, 2023, and 2024, I covered those. Now, when it comes to 2026, the key point is that our visibility into that figure is quite strong, even though it sits further out in time. To start with, approximately 30 billion of the EBITDA in 2026, we expect will be generated by assets that today are either operating or under construction. Next, if you simply take — and connect this to the wind farms we've discussed, out of the entire 6.7 GW of offshore, with the exception of Hornsea 3, which arrives in 2027, and with the exception of Sunrise under the awarded, which will probably land during 2026, every other wind farm Mads mentioned that is under construction will contribute full-year effects in 2026 within this number. Bearing in mind that Changhua 2, 3, and 4, as Mads noted, is somewhat squeezed toward the back end of 2025. So visibility is strong. Farm downs. This is a subject I care deeply about. We've been engaged with farm downs at Ørsted for over a decade. We built this model quite a while ago, and it forms an integral part of how we conduct business.
Rasmus Errboe
executiveThis isn't a tactic we came up with overnight. We've been at it daily for a decade now. Whenever we evaluate our farm downs, we essentially examine 3 distinct factors in deciding whether to proceed with a farm down. We examine value creation, we examine risk diversification, and we examine capital recycling. More specifically, regarding value creation, the plan we're presenting relies on prudent assumptions. Robustness matters most, which means some farm downs within this program will probably show an NPV retention under 100, if you refer back to earlier figures. What we do promise is that across each and every single farm down, we anticipate them being aggressive from a returns standpoint. Over on the right-hand side of the slide, we've laid out 2, so to speak, categories for how we carry out farm downs. The first is the conventional approach, moving from 100% down to 50%. Usually we consolidate pro rata, and we can structure it either as an EPC wrap around FID, or as a shared risk arrangement, bringing the partner in a bit sooner.
Rasmus Errboe
executiveHornsea 3 would be an example of this in the plan, as would Changhua 4, and U.S. onshore as well. U.S. onshore, though, probably won't be consolidated on a pro rata basis. The program's other bucket is where we're doing things a bit differently than what we've done previously. So that's a bucket in which we're looking into going under 50%, so very likely down to 25%. I've listed 3 examples that we've assumed in the plan where we'll take this approach. Those are Revolution Wind, South Fork, and West of Duddon Sands on the U.K.'s West Coast. Again, as we look at this, we examine all the criteria on the left, and we assess where to go to 50, where to go to 25. These are instances, for example, in the US, where we think that from a footprint standpoint as well as a risk standpoint, you know, this is a sound assumption on our part. There will also be parts of the plan where we could go all the way to zero, for example a lease or something similar, but that doesn't make up a very large portion of our program. As for proceeds and the magnitude of this.
Rasmus Errboe
executiveSo the total proceeds we expect from 2024 through 2026 come to between DKK 70 billion and DKK 80 billion, as you can see, and that's higher than what we've been delivering over the last 3 years. The figure is here simply to give you a sense of the magnitudes involved. Again, at the risk of belaboring the point, we are very well advanced on a great many of these farm downs, which is also why we feel confident in putting out a relatively firm number here. So as we speak, we have 12 ongoing dialogues, ranging from early to very advanced, and we started these also well before the CMD, and we have a very good feeling for the way forward in them. Finally, just a few words on the long-term financials. So the DKK 130 billion, all the way to the left here, is something I have talked about. So this is the bucket carrying a relatively high degree of certainty, contingencies, but also some flexibility in parts of that bucket. The DKK 140 billion is, to me, a different story. That is from 2027 to 2030. This is where we have a very high degree of flexibility, where we can be razor sharp in going for the right and most value creating gigawatts in this period of time in the back end of the decade.
Rasmus Errboe
executiveMoving to the third item on this slide—and the final one—Mads covered this as well, but to restate it: the bulk of our CapEx will keep going toward offshore wind. What we're laying out today isn't a strategic shift. Yes, we've revised the plan, yet our core strategic stance remains the same, and so does the technology split, as you can see. Last, on sources and uses, again with some comparison to the Capital Markets Day. Taking the sources column first: back at the Capital Markets Day, we assumed 40% of sources would be cash flows from operations. Under this adjusted plan, that figure is 50%. Put differently, on the sources side we lean more on our comparatively safe underlying cash flow. Partnerships and divestment come to 35%—that's the program I mentioned earlier. Across the entire period through 2030, that totals DKK 115 billion, divided with DKK 70 billion-DKK 80 billion in the first stretch. Compared with the Capital Markets Day, that averages DKK 16 billion of proceeds over this period.
Rasmus Errboe
executiveDuring the CMD, we said 20 billion DKK, so this is a smaller program. When it comes to tax equity, our assumption is that 10% of our sources will come from there. At the Capital Markets Day, we assumed 15% of a much bigger figure. In this plan, we are actually going below 50% of the proceeds we assumed at the Capital Markets Day would come from tax equity. That is not because we have any lack of belief in the tax equity market. We do believe in it. We are well advanced on the projects we have, Revolution Wind being one example, but it is simply also a consequence of the portfolio decisions we have made in the U.S. Then the last point on the sources side: we are not relying on external debt to anything close to the same extent in this plan compared with the one we presented at the Capital Markets Day. As a matter of fact, we do not expect to issue senior debt until 2028 during this period under this plan, which again is a very different assumption compared with the Capital Markets Day. And then on gross investments, the DKK 270 billion that Mads talked about, and then again on hybrid coupon and dividends, roughly DKK 50 billion is assumed here, split roughly equally between dividends to our shareholders on the one hand and hybrid coupon payments and minority dividends on the other.
Rasmus Errboe
executiveOnce more, the premise behind that is that in 2027, for accounting year 2026, we'll bring the dividend back. Having said that, I'll pass things back to Mads for the closing remarks.
Mads Nipper
executiveThanks very much, Rasmus. Yes, I’ll handle that promptly. We want to reach your questions, but allow me to briefly recap where things stand. We’ve made an announcement, and it follows a year of real difficulty, in which we openly accept responsibility for the major negative developments that we know have caused pain. This is an industry we’re confident will prove attractive, and we’re observing some genuinely encouraging signals that offshore may be well on its way back to becoming an industry that is even more scalable. Despite the reduced ambition, we are a clear industry leader and will stay one... We’ve presented a plan that we think is highly realistic. It’s a plan that creates value, and it’s one where the events have taught us to manage, better and more proactively, the risks that will remain an inherent part of operating in this industry. We’re confident that our capabilities, notwithstanding a difficult year — in EPC, in farm downs, and in other absolutely critical elements of succeeding in this industry — remain clearly industry-leading, and we’re adjusting and adapting our operating models and making our company leaner so we can focus even more on drawing on those capabilities.
Mads Nipper
executiveAnd finally, the pipeline quality and the opportunity set. Both the proprietary assets we hold in core and high-potential markets, and also the opportunity set to be most selective about where the most value-creating opportunities are, is something we believe remains very attractive, both toward 2030 and beyond. With that, let us rearrange up here and get your questions. Thank you.
Rasmus Keglberg Hærvig
executiveWe’re at the point where we can take questions. Before we begin, here are a few quick reminders. If you’re asking a question, please keep it to just one per person. If you’re in the room with us here in Gentofte, put your hand up and wait for my colleague Valdemar to bring you the microphone, then say your name before asking. If you’re joining online, please use the dial-ins we’ve given you. With that out of the way, let’s get started with questions, and perhaps we can begin here at the front with a question from Tornøe.
Kristian Tornøe
analystThank you, Kristian Tornøe from SEB. Mads, during your presentation, when you were discussing the issues with Ocean Wind 1, you mentioned that installation capacity needs to be secured sooner, yet you also state that you won't commit capital ahead of FID to the same degree. That strikes me as a bit contradictory, so could you elaborate on how those 2 elements can be balanced?
Mads Nipper
executiveYes, so thank you, Kristian. And I apologize if that was how I put it — if that's the impression I gave. So securing installation capacity earlier isn't what's happening. What we do is this: if we see an under-construction situation on a project that's already been awarded running into difficulties, that's when we'll act proactively to either extend or book new installation capacity, in case there's a risk of a slip. But we're ready for that, since we'll give priority to projects with a more flexible COD deadline. In fact, we're willing to accept less firm capacity secured so that we have a lower capital commitment at FID than was the case previously. So forgive me if I gave that impression, because you're absolutely right — those two things would be very hard to reconcile.
Rasmus Keglberg Hærvig
executiveThanks. We’ll move on to the following question from the phone line. Operator?
Operator
operatorLadies and gentlemen, if you'd like to ask a question, you can press star one on your phone. We have a question from Harry Wyburd at BNP Paribas Exane. Please go ahead.
Harry Wyburd
analystHello, everyone. Many thanks for the presentation — I'll obviously stick to just one question. Could I ask why you ended up choosing the package of dividend cuts, cost reductions, and CapEx reductions instead of the option involving a capital raise? And, going a bit against the grain of the backward-looking picture, I'd say industry fundamentals seem to be showing some signs of improvement. How much headroom do you have if some of the extra opportunities you referenced in the presentation on NY4 and plenty of the other auctions turn out to be more plentiful and appealing than you anticipated? Is there some room on the balance sheet, perhaps after 2024/2025, to pursue some of those opportunities more aggressively, or would you effectively have to return to raising capital right away if you wanted to widen the growth envelope? Thank you.
Mads Nipper
executiveYes, thanks very much, Harry. So why did we pick this path? We looked at a lot of different scenarios regarding what makes the best plan both in terms of the plan's size and in terms of which levers are available for us to pull. And of course we assessed every opportunity and reached the fairly clear conclusion that this path — with CapEx, OpEx, DevEx facing and savings, with a dividend holiday, and also with an accelerated farm down program — was a more attractive path than raising fresh equity. There won't be a limitation requiring us to raise new equity in order to bid into new opportunities. We still believe that with this 5 to 7 GW flexibility we have in offshore, we'll be able to pursue the opportunities that are most value accretive. And even though you're absolutely right that we're seeing good signs in the industry, with more realistic prices coming, we do believe this is exactly the right plan, one that will make us able to select-
Rasmus Errboe
executiveWe’re focused on the opportunities that offer the most appeal instead of chasing faster growth. So we are staying with—and we will stay with—the plan that we have, and we’ll just choose the projects we have that add the most value.
Rasmus Keglberg Hærvig
executiveGreat. I believe we have time for one question from someone here in the front of the room.
Lars Heindorff
analystYes, thanks. This is Heindorff calling from Nordea. We really appreciate that you’ve now been clearer on both the CapEx program and, in particular, I think, the effect from the farm down, so we’re able to make some gross and net calculations. But regarding the EBITDA targets, for 2030 to 39 to 43, what would that figure be if no farm downs are carried out?
Rasmus Errboe
executiveAs you can surely understand, I won't be providing that figure, because the guidance we issued, Lars, covers existing partnerships, as you're aware. The new partnerships, then, haven't been factored in. So a large farm-down in 2030 wouldn't be included in it. That said, we don't give guidance separately with or without existing partnerships. I think a useful data point I shared on 2026 would be helpful here, where I essentially stated that approximately DKK 30 billion excludes existing partnerships. So we gave you a bit of a one-off there, to be fully transparent regarding the 2024 to 2026 period.
Rasmus Keglberg Hærvig
executivePerfect. We’ll now take the following question from the dial-in operator.
Operator
operatorOur next question is from Deepa Venkateswaran at Bernstein. Please go ahead.
Deepa Venkateswaran
analystSo I suppose my main question concerns the faster divestments. In the past, when it came to farm-downs, you followed a rule of keeping NPV neutral. Now you've moved that bar, saying it has to be return accretive, and obviously any farm-down would meet that test. So I'm just asking whether this change comes because the program is larger today? Is the interest rate environment behind it? And, you know, does this plan carry somewhat more risk? I mean, the size of the divestment is simply bigger compared with the previous one. So how would you perhaps offer us a little more reassurance? Because I think this is the one piece of the plan that may differ somewhat from the earlier version. Every other measure, it seems to me, clearly lowers risk.
Rasmus Errboe
executiveThanks a lot, Deepa. You're correct that we've discussed roughly 100 before. But keep in mind that's just a single metric among those we consider when doing farm downs. That's always been true. So we're also — we're examining capital recycling, and we're examining risk too, risk sharing. And on the whole, you could say, regarding risk to the program, I'd contend the program's risk hasn't risen compared with what we assumed at the Capital Markets Day. Actually, I'd contend there's greater certainty about our capacity to deliver this program. It's objectively smaller. You are — I saw your note — you're obviously right that the ratio of gross to net investment is shifting somewhat here, since we do speed up in the front-end years. But the program isn't bigger, and with the flexibility we've allowed ourselves also on, you know, in certain cases, moving to 25%. We have a very high level of flexibility within the program, so we can pursue the most value accretive opportunities, and also course correct within the parameters we've set along the way.
Rasmus Keglberg Hærvig
executiveThanks. We have another question from the dial-in lines.
Operator
operatorOur following question is from Rob Pulleyn at Morgan Stanley. Please proceed.
Rob Pulleyn
analystThank you very much, and yes, I appreciate the presentation. I wanted to go back to slide eight and ask what exactly went wrong. The main thing I'd like you to expand on is this: what happened on the risk management side that led to 2 supplier disappointments coming so late in 2023, on foundations and on vessels? That was, of course, quite a surprise coming from a developer with a track record as strong as yours. Second, and building again on what you said about that slide, could you tell us what more reassurance you can offer the market that whatever failed previously with supply chain risk management won't happen again? That really seems essential to delivering all of these projects in the future, particularly in new markets such as the U.S. Thank you very much.
Rasmus Errboe
executiveYeah, thanks a lot, Rob. You're correct that—what I mean is, back then and through the summer, we were aware Ocean Wind 1 had already taken on a lot of those headwinds, and it was tied to a timeline that was already strained. But when the information reached us at that point—those initial 20 monopiles and then a substantial further hold-up involving a vessel—that was new to us. And that's exactly where we're saying these were the, the, the monopile-
Mads Nipper
executiveThe facility itself was new, yet in our discussions with the supplier, nothing gave us reason to expect an impact of this magnitude. And then I think what we — where the learning is happening for us is that when such events coincide, and we're not pointing fingers at any suppliers, because that's precisely where our risk management framework needs updating: simulating exactly what occurs if a vessel delay and a foundation delay hit at pretty much the same time. That's what we're now upgrading substantially, and doing so well ahead of when we'd likely have the visibility to say, "If this happens, we can mitigate those." And I think the example we're executing right now at Sunrise, pending a positive outcome on New York 4, where we're proactively de-scoping from 84 to 28 monopiles, even though the supplier says we still believe in the plan — that's an illustration of how we're learning from this, even though it comes at an additional cost, which is also why we've raised the contingencies. So that's one example, and if I've understood your second question correctly, that is exactly how we'll avoid those.
Mads Nipper
executiveIt's a mix of running simulations on what could occur should certain major risks materialize — both more severely and also more simultaneously than we had factored into our earlier risk register. And beyond that, to say more proactively and with better timing, while there's still room for booking, backup, or mitigation capacity, what options do we have, and what would the cost of those be? That's the reason we think you should feel more at ease. We won't pretend that this industry is completely stable or free of risks — it isn't. Anyone claiming otherwise isn't being honest, but the real question is how we step up our risk management so we can deal far more proactively with situations that remain, in many instances, volatile.
Rasmus Keglberg Hærvig
executiveWe’re going to take one more question from the dial-in operator.
Operator
operatorAlberto Gandolfi from Goldman Sachs has the next question — go ahead, please.
Alberto Gandolfi
analystThank you, and I appreciate both the presentation and your patience. My question has 2 parts and is a little convoluted, but I'm trying to get a more detailed grasp of how FFO, CapEx, and EBITDA relate to one another. If I understand correctly, your FFO for 2024 to 2026 will be roughly comparable to your CapEx, and you don't pay any dividends. So is it right for me to think about free cash flow this way — I mean, the company remains somewhat free cash flow negative, but we shouldn't anticipate any meaningful rise in net debt by 2026. If you were able to give net debt guidance, that would likely settle the debate right here, since I believe the consensus figure that you circulated has 100, more than 100 billion DKK of net debt for 2026 in consensus. My suspicion is that it will be considerably lower. That covers the first part of my question. Now for the second part: it appears to me that the cut to EBITDA guidance is less than proportional to the cut in CapEx. So could you perhaps explain which power price assumption you applied and, or are you essentially conceding on the least profitable projects, meaning that what you are developing carries better returns, and that accounts for why EBITDA falls by less than CapEx?
Alberto Gandolfi
analystI really appreciate it.
Mads Nipper
executiveThanks a lot, Alberto. Let's go through them one at a time. You're definitely right—I take it you mean the adjusted net debt that feeds into the FFO-to-net-debt metric. You're definitely right that 100 billion DKK in 2026 is off. Looking at the charts, the underlying result behind what we're presenting on cash flows implies we expect to be roughly net cash flow neutral during this period. So if you take gross investments, the divestment program, and our underlying FFO from EBITDA, that comes out roughly neutral, as expected, across this period from 2024 to 2026, which obviously means you won't see adjusted net debt rise in 2026. We expect it to come in slightly below the 2024 level. On your point about EBITDA guidance, you're right. And you're also right to assume that it isn't us who have fundamentally changed our view on power prices, for example.
Mads Nipper
executiveSo this is essentially us, after reviewing the whole portfolio, ending up with only the most robust projects, including from a value standpoint.
Rasmus Keglberg Hærvig
executiveThanks. There’s someone here in the room with a question.
Lars Heindorff
analystYes, thanks. It's Lars Heindorff here from ODDO BHF. I've got a question — Matthew, I believe during your presentation you mentioned that you've been reviewing the whole supply chain, and one point you raised concerned installation vessels: there's a fixed start date, while the end date remains open. Those vessels aren't cheap nowadays. How does that affect project costs? Does it have any effect on the CapEx per megawatt, or anything along those lines?
Mads Nipper
executiveNo. No, it doesn’t, Lars. What does carry an extra cost — and often a meaningful extra cost as well — is when, say with Revolution, we actually end up with 2 contracts running in parallel. So we have one contract tied to a Jones Act compliant vessel, and we have no certainty about when we’ll receive it. Unfortunately, we know it’s delayed, yet we still lack fixed certainty, so we’ve now chosen to contract the entire scope with an additional vessel. That, of course, costs a lot of money. But negotiating those contracts is typically also, as by far the biggest contractor, something we can do at relatively limited cost, and also making sure, for risk management purposes, that we aren’t the first ones to get it, which has been painful in the U.S.
Rasmus Keglberg Hærvig
executiveExcellent. Operator, is there another question from someone online?
Operator
operatorOur following question is from Peter Bishtyga at Bank of America. Please go ahead.
Peter Bishtyga
analystYeah. Hi, good afternoon. So I just wanted to ask about U.S. policy risk. You know, the market's clearly concerned about the potential impact of another Trump administration. The Republicans have been quite vocal about wanting to repeal, parts of the IRA, about the unnecessary support for sort of mature technologies like onshore and solar. We also know from the previous Trump administration that there are a lot of bureaucratic obstacles thrown in the way of offshore wind, which he clearly doesn't like as a technology. So just want to hear a little bit about how you have thought about that in your sort of risk management, process and assessment, given that actually you still have quite a lot of your forward-looking CapEx, both onshore and offshore in that region. Thank you.
Mads Nipper
executiveYes, thank you very much, Peter. So the key point is that Trump has spoken quite openly about his opposition to offshore wind. A few remarks on that: our main focus has been making sure that, across the awarded portfolio — including a possible positive outcome for Sunrise — there's no exposure to a situation like the one we ran into during the prior administration, when the Bureau of Ocean Energy Management was nearly drained of resources and permitting therefore came close to a halt. We'll have the required federal permits secured, and in a Trump administration we see that as the largest risk. And by the way, the states we're prioritizing all lean blue, with substantial momentum and growing ambitions for offshore, plus a readiness to bear the cost. So for us the crucial thing is that it doesn't bring significant retrospective risk to any project we hold, whether onshore or offshore, and we don't believe it does. As for future projects, again beginning with offshore: we might end up bidding, for instance, into a New England solicitation — a combined one from Rhode Island, Massachusetts, and Connecticut, which, by the way, all provide inflation protection as well.
Mads Nipper
executiveIf we take that step, then clearly we'd make sure to reduce exposure on any commitments so we're proactively ready for the risks that could arise, both regarding federal support and, in particular, permitting. And if we go ahead with that, we'd also examine how much we want to depend on certain local tax credits tied to local manufacturing, as opposed to opting for a more stable global supply chain. On onshore, as we discussed, there's no pressure on us to accelerate any of those decisions. But if we found ourselves in a situation where — contrary to what we expect, I'll say there's a meaningful regime change, a meaningful negative impact on Inflation Reduction Act support for onshore — we'd have plenty of opportunity to redeploy that toward European opportunities as well, where we also have a very strong time, or where our pipeline is very strong. So the overall technology mix doesn't concern us, and we'll proceed cautiously to make sure we aren't exposed unnecessarily in the event of a regime change.
Operator
operatorMark Freshney from UBS has a question. Go right ahead.
Mark Freshney
analystHello, and thanks for taking my question. Rasmus, I’d like to ask about the credit rating agencies—obviously, you’d have been in close dialogue with them over recent days. Is it fair for us to expect them to come out—notwithstanding your comments about being able to manage triple B, or operate at triple B—but is it fair to say that we can expect them to come out and affirm you at triple B plus? And just further to that—clearly, cutting the dividend or passing the dividend for 3 years is a massive positive message to the credit community. Can you rule out restoring the dividend earlier, should your plan be exceeded or executed well? Thank you.
Mads Nipper
executiveThanks a lot, Mark. Like I said, speculating about what the rating agencies might do isn't the right thing for me to do today. As you pointed out too, our dialogue has been very good and very robust. And naturally, both S&P and Moody's had already, before today, moved ahead with a negative outlook as well as a credit watch on our ratings.
Rasmus Errboe
executiveSo naturally, a situation where we get downgraded by one notch is certainly a genuine risk. And as I mentioned, we can handle that quite comfortably within our plan, and also with the target we're setting out going forward — where we aren't committing to any particular rating, but we are committing to a solid investment-grade rating, which obviously, you could say, should also be viewed in that light. As for your question about whether we could choose some way to pay dividends early on, that isn't what we expect. We believe, for the reasons I gave, that our company benefits from the visibility we get by not paying dividends during the period 2024 to 2026. It's connected to the plan I've sort of walked through today. It all essentially comes together into a robust plan. So that isn't our expectation in any way. Thank you very much.
Operator
operatorOur next question is from Jenny Ping at Citi. Please go ahead.
Jenny Ping
analystHi, thank you so much. I just have one question about Ocean Wind 1, please. In the past, you've mentioned the $8 billion-$11 billion cancellation costs and the chance to reuse some of that equipment at some of the other sites you're developing. Could you give us an update on where things stand with that, and just give us a sense of how likely it is, the possibility, that this figure could come down? Thank you.
Rasmus Errboe
executiveSure, I’m glad to address that, Jenny. The broad takeaway is that we remain inside the overall range we previously laid out. That means DKK 9 to 11 billion, or, when you include the impairments we recorded, DKK 15 to 18 billion in total cancellation costs. We are still inside that range. Ceasing development and exiting these contracts is a highly complicated matter. There are roughly 270 contracts in all, which makes this a very large undertaking for a company. We are still in the middle of the technical assessment. Most contracts have been terminated, but a few are still being evaluated, and we have one favorable case in which cables are being reused in a project we expect in the future. Still, it would not be appropriate to suggest anything other than that we will remain within the DKK 15 billion–DKK 18 billion range. And perhaps one more point, Jenny, on the DKK 8 billion–DKK 11 billion as well. With the year now closed and reviewed, we finish at an EBITDA provision of DKK 9.6 billion. That is the figure you can regard as comparable with the DKK 8 billion–DKK 11 billion.
Rasmus Errboe
executiveWhen it comes to cash out, you'll naturally see the impact of the DKK 15 billion, meaning the cancellation fees sitting at that level right now. That cash out effect will show up during 2024, which is once again what's reflected in our FFO net debt.
Jenny Ping
analystI appreciate that.
Operator
operatorJames Brand from Deutsche Bank has the next question. Go right ahead.
James Brand
analystGood afternoon, and thanks for the presentation—it was quite useful. I've got a question about farm downs, and it may have 2 parts. First, you offered a few illustrations of farm downs you might pursue, and those involve onshore assets in the U.S., but then also all sorts of new offshore projects or ones under construction. I'm just wondering whether you'd look at selling a larger stake in offshore projects that are already operating. A lot of them you've already brought down to 50%, but could you go down to, say, a 25% stake in existing onshore projects? That's part one. Then you said there are 2 models for farm-downs: the one where you retain all the construction risk and give guarantees, and one where the risk is shared. In the past, you were much more inclined to keep the construction risk and maximize the farm-down. Are you hinting that going forward you might be more willing to have a bigger share of farm-downs in which the risk is shared? Thank you.
Rasmus Errboe
executiveYes, thanks, James. Starting with your first point about whether we might sell down a larger stake in an operating offshore wind farm — you're correct that we could, and that's exactly, for example, what we've built into the plan for West of Duddon Sands, where the holding drops from 50% to 25%. That project sits on the U.K. West Coast, and we've reviewed our whole portfolio. As an illustration, we think that asset is well suited to a further farm down, both from an accounting standpoint and from an operational and strategic one, considering how it connects to other assets in the way we run our business. So we've gone through the entire portfolio, but you won't — you shouldn't expect much of that in our plan. On the second part of your question, regarding, you could say, the balance between shared risk and an EPC rep, we have not assumed a
Mads Nipper
executiveThere's no fundamental change in either direction compared with where we stood previously. We continue to think it makes sense for us to keep both options available, so to speak. Whenever we run our farm-down program, we examine the investor pools, we examine liquidity, we examine appetite, and sometimes, in a particular market, targeting a somewhat higher return requirement can work better for us. That usually leads you toward a shared risk arrangement, which clearly also means the partners bear more of the CapEx at an early stage, and so forth. So no, there is no fundamental shift away from our rep, which we still believe makes sense in many cases.
James Brand
analystThanks a lot — that's great.
Operator
operatorOur following question is from Marc lp at Berenberg. You have the floor.
Marc Lp Tat Kuen
analystHello, everyone, and thanks for taking my question. It concerns Hornsea 3. You mentioned that at the time FID was taken, it sat at the low end of the value creation range. I also understand that this depends on securing offtake in Allocation Round 6. Could you elaborate a bit more on the assumptions behind that decision — specifically, what percentage probability have you assigned to winning offtake there? And what is the outcome if offtake is not secured in AR6? Would it simply fall outside the value creation range? Thank you.
Mads Nipper
executiveSure, I’m glad to address that. As you’ll appreciate, we’re not able to speak in detail about the specific assumptions we’ve made here. What I can say is that this concerns the entire share not covered by the CFD. That also means we are assuming—we’ve built in conservative assumptions, so we aren’t pushing too hard. Still, with the new administrative strike price, our confidence that Hornsea 3 will be competitive, and given the failed Allocation Round 5, which was already at 44 to 45 GBP, we feel solid that it will land at a price within the value creation we’ve assumed.
Operator
operatorWe’ll take the next question from the room.
Kristian Tornøe
analystKristian Tornøe from SEB here. My assumption is that Hornsea 3 accounts for a fairly, fairly substantial portion of that DKK 70 billion to DKK 80 billion in near-term farm-down proceeds you're anticipating. Could you help us a bit with the base case assumption on timing? Should we be assuming that lands in 2025, or?
Mads Nipper
executiveYes. I completely get your question, Kristian, and naturally I also realize that when you build your model, it matters quite a bit whether you place it in one year or the other. What I'll tell you on that point, since it's a very, very large piece, is that you ought to assume we'll do it at some point in 2025.
Operator
operatorAhmed Farman of Jefferies has the next question. You have the floor.
Ahmed Farman
analystYeah, hi there, and thanks for walking us through the presentation. My question relates to slide nine, where you gave a really useful summary of the different projects. In your remarks, though, you mentioned a timely emphasis on monopile delivery a few times across a couple of projects. I was just hoping you might be able to offer us somewhat more detail regarding how big the issue actually is. What does the contingency planning look like, and what economic cost comes with it? Thank you.
Mads Nipper
executiveYes, thank you so much, Ahmed. I'm very glad to address that. The supplier in question is Danish, and they've been facing challenges with ramping up. The welding problems that existed are now being resolved—it's really the finishing, the coding, and similar areas where things are happening. Additional capacity is being brought online. So we're confident this isn't a structural problem; instead, it's a ramp-up challenge, and there's a plan in place that, at this moment, is fairly stretched for that specific supplier. We're observing that alternative suppliers—including both our current ones, like Steelwind and Haizea, and new suppliers we're developing so they can scale capacity—show a very high level of solidity. So if your underlying question is whether there's a structural, more fundamental problem regarding the industry's capacity to ramp up on monopiles, the answer is no. However, we're in a situation where, on that awarded portfolio, prior to the de-scoping, we carried fairly high concentration risk—and that's what we're de-scoping now. And as I said, under Revolution Wind, we're also making sure we prioritize the ones most critical for completing the projects on time.
Mads Nipper
executiveLooking at the economic side, the effect here isn't huge. It's not as— because when we descope, we'll also rework the agreement with the supplier already in place, while if we double book, going back to the question Lars raised earlier, doubling up on vessel capacity comes at a high cost. Yet when we move scope from one supplier to a different one because that supplier is facing ramp-up difficulties, the effect on project economics for those choices tends to be fairly marginal.
Ahmed Farman
analystI appreciate that.
Operator
operatorOur following question is from Klaus Kehl at Nykredit. Please proceed.
Klaus Kehl
analystOkay, hi there, gentlemen. To start off, here's a really straightforward question. You mention gross investments of 270 million — sorry, DKK 270 billion through 2030. But just so we're clear, you plan to divest roughly DKK 100 million, which leaves a net figure of about DKK 170 million. Is that right?
Mads Nipper
executiveYes, 155.
Klaus Kehl
analystAll right, that's a good one—and maybe a slightly harder question. Clearly, you're reducing the EBITDA guidance for 2030 because of cancellations, and also because of that lower power price. So what exposure would there be if the power price were to fall a further 20%? And on that point—and perhaps this is a little unfair to ask—but does setting 2030 targets really make sense when you don't know what the power price is going to be in 2030?
Mads Nipper
executiveGlad to address that. Keep in mind, Klaus, that even with the hit to our investment capacity caused by forward prices, the way we run our revenue line remains mainly built on a high share of fixed and contracted revenue. So roughly 80%. And although we did revise our hedging framework, moving away from what was a traditional 5-year staircase, we now use one where, depending on the power price and the outlook, we hedge somewhere between 0% and 70% of the remaining shorter-term expected production. We're in a position where our overall net exposure to power prices near term, meaning the EBITDA impact, is far more limited. And if you assume, for planning purposes, that on average we hedge, say, 50%-60%, then the nearer-term exposure from that is actually fairly limited, perhaps only a high single-digit exposure across our total revenue lines. While for the remainder, it's fixed, and then for most of that, even inflation indexed. So we mainly think about this in terms of our investment capacity, should forward prices decline, which is why we've also built in a cushion with the above 30% and, from 2026, even somewhat above 30% in our FFO to net debt metric.
Mads Nipper
executiveBut we do feel fairly comfortable putting out that DKK 39 to 43 billion range for 2030. I completely agree. Keep in mind, as we've also discussed, that power prices fell 40% in 2024 since our Capital Markets Day — the one we're in — and 30% for 2025. So what we've witnessed over the last 6 months in Denmark is a pretty dramatic drop.
David Paz
analystTake, for example, the DKK 70 billion to 80 billion you have for 2024 to 2026. So what average premiums are you assuming there? And have you — I believe you named certain additional farm downs above 50%, among them South Fork and Revolution. Would those happen alongside Eversource's pending sale, or are they separate and anticipated at some later point, though still before 2026? Thank you.
Mads Nipper
executiveYes. Thanks, David. Two questions. First, regarding the premium assumptions, that's not information we disclose. As you can surely understand, in this space, when you're involved in M&A and striking deals, that information is naturally quite sensitive. So even though I'd like to, I'm not at ease sharing it. On what you said about Eversource, whether our sale of the assets you referenced would happen alongside theirs, it isn't my place to speak to Eversource's sale process. I think they... I know their earnings call is scheduled for the thirteenth of February, and I'd expect them to provide an update there on the processes they have underway as well. Still, our collaboration with them is very strong across everything we do. So you can certainly assume that both of us have a solid sense of what's happening with our farm downs. All right. We'll take the next question from the online operator.
Operator
operatorOur next question is from Martin Tessier at Stifel. Please go ahead.
Martin Tessier
analystYes, good afternoon, and thanks for the presentation. My first question concerns slide 8, where you state that you wish to steer clear of large capital commitments and that you simply want to repeat the mistakes. Could you give us perhaps some concrete figures regarding how much CapEx you intend to spend ahead of FID? Would that be 10%, 20%, or 30% of the project's total investment cost? And my second question concerns point 2.3 — unless I'm wrong, you're aiming to secure 25% of the capacity in the corporate PPA. I haven't heard anything about that during the presentation, so could you give us an update on that topic? Thank you.
Mads Nipper
executiveThanks, Martin. My connection may be poor and my hearing is somewhat weak, so it was a bit hard to catch your question. If my answer addresses something other than what you asked, please speak up. So your question concerns what percentage of CapEx we would commit before FID?
Martin Tessier
analystThat is precisely right.
Mads Nipper
executiveI can't really give you a very precise figure, but it would be significantly lower and much more along the lines of a maximum of... This isn't a threshold or anything specific, but much, much closer to the 10-ish% range than what we would, than what we would do... For instance, on Hornsea, on Ocean Wind 1, where we were at a completely different level, much nearer to 30%-50%. So a dramatic reduction. And on Hornsea 3, that's where I have, I believe, a greater risk of not hearing the question. So if you heard it, Rasmus, please answer it.
Rasmus Errboe
executiveYes, absolutely. So Martin, what I believe I heard was you asking whether we anticipate potentially doing corporate PPAs on 25% of Hornsea 3. Is that right?
Mads Nipper
executiveThat's right, precisely.
Rasmus Errboe
executiveWe don't expect to take that route. As Mads said earlier, the plan is for us to participate in AR6. We do see ourselves as a price taker at that auction. Still, the nice thing about the U.K. setup is the considerable flexibility built into it, so if we chose to, we'd have the chance to pursue a corporate PPA — assuming we don't succeed in AR6, contrary to what we anticipate. Even so, AR6 is clearly our base assumption.
Mads Nipper
executiveThanks so much.
Operator
operatorOur following question is from Ida Carney with Pictet. You have the floor.
Ida Kehlet
analystHello. Hi. Hi, and thanks for the question. May I ask about your cash flow? It came in somewhat weak during the 4th quarter, and I'd like to understand what was behind that. More specifically, I believe your net debt went up by slightly more than DKK 4 billion during the quarter. Also, I know you've stated that by 2026 your net debt ought to be flat, but could we get somewhat more detail regarding what to expect starting next year? The reason I ask is that it seems to me you cut back your hedge book this year, which likely contributed quite a lot to your cash balance thanks to the collateral release. And clearly, working capital is lower too. Could you give us a sense of what underlying cash flow in 2024 will look like? And also, since I believe you'll face significant cash costs related to Ocean Wind. Thanks.
Rasmus Errboe
executiveYes. Thanks, Ida. Some of the specifics in your question are things we'd need to get back to you on, but... And as you're aware, we don't provide guidance on cash flow. Our guidance covers the metrics we've discussed today. So that applies to the portion of your question concerning 2024. And you're correct that regarding how our cash flow is affected, for 2023 we've seen a very favorable impact on cash flows compared with 2022, when we had those reverse margins booked for our hedging program, and with power prices having fallen, obviously that's no longer the situation. So that gives a significant, favorable effect on our cash flow. But the specifics, the additional specifics, we'd need to follow up with you on.
Ida Kehlet
analystDid that come to roughly DKK 4 billion?
Rasmus Errboe
executiveSlightly more, actually.
Ida Kehlet
analystAll right, and then, clearly, on the working capital side, I saw there was somewhat of a decrease in receivables. So you did have some success collecting, though of course, yeah, that's something they might begin pursuing next year. Which is exactly why I was wondering. And like I said, in Q4, we could actually see the cash burn go up.
Rasmus Errboe
executiveYes, I realize I'm repeating myself, but we'll need to get back to you on that. And just one point: part of the program we're examining for 2024 to 2026 also involves supply chain financing, and you'll notice that in the ratio on our... Or you'll notice it in our working capital, but its effect on our cash flows isn't very massive.
Ida Kehlet
analystAll right, thanks.
Operator
operatorMark Freshney from UBS has the next question. Go ahead, please.
Mark Freshney
analystHi, and thanks for taking my questions. Rasmus, if the Sunrise rebid doesn’t go your way, what total expected cash costs would you have? Clearly, that project would likely miss a number of windows, so if we could get a figure for that, please. Second, Mads, in your investor letter a year ago, you discussed hedging power exposure for renewables, which are mostly UK RO assets. Obviously, power market conditions have shifted over the last few weeks, and some companies have said it is much harder to earn money in that market. I’m wondering what you are seeing in current trading in the UK market and whether that helps or hurts your UK exposure via UK RO assets. Thank you.
Rasmus Errboe
executiveShould I go with the Sunrise one?
Mads Nipper
executiveYes.
Rasmus Errboe
executiveOkay, Mark — let's begin with the impairment portion of your question, and we'll get to the cash piece after that. In the impairment note, 3.2, we've essentially laid out the assumptions we're using for Sunrise as we head into New York 4. And if we were to win in that scenario, then, as stated there, we expect to reverse our impairment by DKK 1.8 billion, based on today's assumptions, by the end of the year. We've also stated that if we lose — something to which we assign a 25, we had a 75 to 25% probability when we prepared the annual report — then you'll see, you'll see an impairment on Sunrise of, we note — we write DKK 5.5 billion. And that, of course, reflects the fact that our forward-looking value for impairment testing is now a probability-weighted combination of a win scenario and a lose scenario. As for your — the way I read your cash comment, you're probably referring to the cancellation fees. And on Sunrise, drawing on the learnings from what we did on Ocean Wind, as mentioned earlier, having gone through the 270 contracts, et cetera, we have likewise scrutinized the cancellation fees on Sunrise.
Rasmus Errboe
executiveAnd we do anticipate that, because of that, but even more because of the passage of time since Q3 came out, we now expect — in the unlikely scenario where we lose — that we would today expect cancellation fees of expectedly DKK 6 billion-DKK 7 billion. So in that scenario, obviously, that would hit the P&L, should we decide to cancel the project. There are also other scenarios if we are not successful, and that is something we would need to assess together with our partner, Eversource, since the deal we have struck with Eversource basically only takes effect if we succeed in Sunrise, New York 4.
Mads Nipper
executiveAnd on your second question, Mark, on this point... So, when we hedge our exposure to power prices, our current strategy is fundamentally not to hedge that mainly, you know, to make money on it, but rather to secure a sort of floor in our production. So what we're seeing now, therefore, is that this is definitely still something that's possible. It's a liquid market. So in terms of, in terms of, let's call it speculative trading, that isn't a core part of our strategy, and we're seeing that it is indeed still possible to carry out the hedging that we consider right under our new framework of 0%-70%.
Rasmus Keglberg Hærvig
executiveGreat. One last question is available to us, and that one also arrives through a dial-in operator.
Operator
operatorJenny Ping from Citi has the last question. Go right ahead.
Jenny Ping
analystThank you so much. About your dividend — clearly it's on hold through 2026 — could you say more about how you're approaching the dividend after 2026? There's a footnote in your presentation on payout, I believe. Any detail on that would be great. Thanks.
Mads Nipper
executiveYes, that’s possible. So, also tying back to the earlier question, what we’re describing is a dividend plan over 3 years. Our aim is to bring it back at a meaningful level. That’s our target, and that’s what we’ll carry out. We can’t get too specific about what we’re assuming, but it would be at a meaningful level.
Rasmus Keglberg Hærvig
executiveAll right, that wraps up both the presentation and the Q&A. Mads, the floor is yours for closing comments.
Mads Nipper
executiveYes, and once more, many thanks for the excellent questions, as always. But also, a big thank-you to everybody here in the room who came, and management and the board will now concentrate on carrying out a plan we believe in very strongly. Have a safe day. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.