Ørsted A/S (ORSTED) Earnings Call Transcript & Summary
May 2, 2024
Earnings Call Speaker Segments
Operator
operatorGood afternoon, everyone, and welcome to the Ørsted earnings call for Q1 2024. <<operator_script>> Joining us today are Group President and CEO Mads Nipper and CFO Trond Westlie. Gentlemen, over to you.
Mads Nipper
executiveThank you so much, and good day to all of you, and thanks for being on our earnings call. To start with, I'm delighted that you, Trond, are with me today — Trond Westlie, our newly appointed CFO. Trond brings solid skills and experience from his career as a CFO at several globally listed companies, including A.P. Møller - Maersk Group, Moller Maersk, Telenor and Aker Kvaerner. When I hand over for the financials, I'll give Trond the floor for some introductory remarks. At Ørsted, we chose to change and simplify the executive management structure so the company's focus on project execution, financial discipline and value creation becomes even sharper. Under the new management structure, we have set up a new commercial organization led by Rasmus Errboe, who has been appointed Deputy CEO and Chief Commercial Officer. And many of you met Rasmus over the past quarter in his capacity as Interim CFO. At the same time, Patrick Harnett, who heads our European offshore construction portfolio and has been responsible for the construction of Hornsea 2, has been appointed new Executive Vice President and Chief Operating Officer. From here on, the Ørsted Group executive team will be made up of Rasmus Errboe, Trond Westlie, Patrick Harnett, Henriette Ellekrog as CHRO and myself.
Mads Nipper
executiveAt our Annual General Meeting on March 5, there were also changes in Board of Directors leadership: our former Vice Chair, Lene Skole, moved up and took over from Thomas Thune Andersen, who had served as Chair for 10 years. Andrew Brown, who was our Interim COO until recently, has now been named Vice Chair. 2024 has gotten off to a promising start for us. Building on the updated business plan we presented at the beginning of February, we've made solid headway on carrying out that plan and have hit a number of key milestones. Let me walk you through the most important ones. To begin with, our Sunrise Wind project, at 924 megawatts, was chosen for an award under New York's fourth offshore wind solicitation. I'll go into the project and the road ahead in detail on the next slide. We put in a bid for the Taiwanese Round 3.2 auction with our Greater Changhua 3 project. We expect the auction result during the summer. We also filed a proposal for our Starboard project, at 1.2 gigawatts, in the Rhode Island and Connecticut solicitation, with a result anticipated in Q3. This week, we obtained licenses to develop 2 large-scale offshore wind projects off the coast of Gippsland, Victoria.
Mads Nipper
executiveWith these licenses, we gain site exclusivity for developing the 2 offshore wind sites, which have a potential combined capacity of 4.8 gigawatts. We'll move the projects forward through site investigation, environmental assessments, and supply chain development so that we can bid into future procurement processes, with the first auction expected to begin in late 2025. Under our partnership and divestment program, we have executed on 2 milestones. In the U.S., we've divested a share of 4 onshore wind assets to Stonepeak, which takes an equity ownership stake in a portfolio of 952 megawatts. In our European onshore business, we remain focused on the opportunities that create the most value. Consistent with that focus, we've agreed to divest our onshore platform in France to ENGIE and to concentrate our build-out in the U.K., Ireland, Germany, and Spain. This transaction was signed this week and is expected to close during this quarter. Both transactions align with the assumptions of our business plan and will serve to recycle capital in support of our execution. Let's turn to project execution and the construction completion of both South Fork in the U.S. and Changhua 1 and 2a in Taiwan. These are enormous milestones that our team can take great pride in, as many challenges have been overcome, and the projects are the first completed utility-scale offshore wind farms in each country.
Mads Nipper
executiveWe expect to complete final commissioning of South Fork, at 130 megawatts, along with Greater Changhua 1 and 2a, at 900 megawatts, during this quarter. During the first quarter, we signed a memorandum of understanding with Dillinger — Europe's biggest producer of heavy-steel plate — so we can secure access to lower emission steel plates for the offshore wind foundations we will build going forward. Through this agreement, we will lock in supply of a key raw material for upcoming projects, while also advancing our ambition of using lower emission steel to decarbonize our supply chain. We also signed a long-term lease agreement with Cadeler that secures offshore installation vessel capacity starting in 2027 and running right through the end of 2030. Locking in long-term capacity with strategic suppliers matters greatly to us, because it lets us build collaboration and, together, manage risks and execution of our offshore wind construction program toward 2030 and beyond. Our partnership with Cadeler shows how we can give suppliers the clarity and scale they need in order to invest in new technology and organizational capabilities. Turning to the financial side, EBITDA excluding new partnerships and cancellation fees for the first quarter came in line with our expectations, totaling DKK 7.5 billion, which is DKK 0.6 billion above Q1 of 2023.
Mads Nipper
executiveOffshore operations brought in DKK 6.9 billion in earnings — that's DKK 1.1 billion more than the corresponding period a year earlier. Moving to Slide 4, let's take a closer look at Sunrise Wind. On the final day of February, Sunrise Wind secured a conditional award in New York's fourth offshore wind solicitation. Thanks to New York's ongoing offshore wind leadership, this accelerated procurement was both successful and competitive, which kept our project on schedule and helped New York keep pushing toward its decarbonization goals. After the award, we are now negotiating the final terms of a 25-year Offshore Wind Renewable Energy Certificate with NYSERDA. We expect those negotiations to wrap up and the new OREC to be signed during this quarter. I'm also very pleased that the project has received its federal record of decision and that we've taken the final investment decision on it, based on a business case with a positive life cycle NPV. The project is a 50-50 joint venture between us and Eversource. As Eversource finished its strategic review and chose to exit offshore wind, we negotiated a commercial agreement to assume full ownership of the project, contingent on signing the OREC agreement, receiving the construction and operations plan, and obtaining the relevant regulatory approvals.
Mads Nipper
executiveWe keep moving the project forward and are pushing ahead with onshore construction work. All relevant state entities have now reviewed and accepted the Sunrise Wind design, and the project has locked in project labor agreements plus all major supplier agreements, including turbines — we'll deploy 11 megawatt turbines from Siemens Gamesa. We expect final federal permits this summer, including the construction and operations plan, or COP, and after that we'll begin offshore construction, with completion expected in 2026. As you may remember from the Capital Market's update at the start of February, the outcome of the New York 4 Round stood as one of the absolute key milestones for our business plan. Following that award, we reversed part of the impairment relating to offshore — to Sunrise Wind. Let's go to Slide 5, where I'll walk through the status of our construction projects. We remain strongly focused on project execution and are working diligently to derisk the ongoing supply chain challenges so that we successfully deliver on our construction portfolio. Our current emphasis remains on mitigating challenges concerning monopile manufacturing and securing additional installation vessel availability. In the first quarter of this year, we have been constructing 7.6 gigawatts of offshore wind across our 3 regions.
Mads Nipper
executiveAs I said, construction at Greater Changhua 1 and 2a and South Fork is finished, and commissioning work is now being finalized. Turning to the German program and the Gode Wind 3 Project: all 23 foundations and cables are in place. Turbine installation is under way, and we anticipate first power production within the coming days or weeks, with commissioning of the project during summer of 2024. Borkum Riffgrund 3 is still moving forward on a tight schedule, mainly because the monopile supplier has faced continuing ramp-up issues. Key mitigations have been agreed and implemented in the installation schedule. Our focus areas remain progress on ramping up monopile fabrication and the potential need to secure an extension of installation vessel. Turbine installation is expected to begin during the coming months. For Greater Changhua 2b and 4, the final offshore construction permit application was approved by the Energy Administration at the end of last year, while the offshore substation topside has reached structural completion ahead of schedule. To ensure timely delivery of the project, we are examining numerous options to secure additional vessel capacity should there be a delay of the transport and installation vessel.
Mads Nipper
executiveRevolution Wind is moving forward with its execution. On monopile delivery, the supplier has given the project a fabrication schedule that supports the current commissioning date near the end of 2025. At the moment, our priority is the 2 monopiles for the offshore substations, which is essential for power transmission. After the recent FID, our Sunrise Wind project has moved into the construction phase. We keep working closely with the project's monopile suppliers to mitigate possible further ramp-up delays. Their monopile delivery has been descoped, and 2 additional suppliers have taken up the remaining capacity, and both are on track. And we have now secured installation vessels for the foundations and wind turbines, including a full replacement for the <<inaudible>>. Finally, in the U.K., we continue to advance our 2.9 gigawatt Hornsea 3 project according to plan following the FID in December last year. Onshore, our 4 U.S. construction projects totaling 1.4 gigawatts are showing good progress. Eleven Mile Solar Center, a solar and Battery Energy Storage System in Arizona, is conducting final testing, and commissioning remains on track for the summer of '24. In Texas, construction of our Mockingbird Solar Center is proceeding as planned, with COD expected in the second half of this year.
Mads Nipper
executiveRegarding the 2 solar projects, Old 300 and Sparta Solar, every module has now arrived in the U.S., and the last installations are underway. For both projects, we anticipate COD in 2024. In Europe, things are moving along nicely across our construction portfolio of roughly 200 megawatts, with COD expected over the next 3 years. We still feel at ease about our offshore and onshore construction portfolio. Although it brings challenges and risks, we keep working to manage and mitigate those risks so we can deliver on the renewable construction portfolio of more than 9 gigawatts. With that said, Trond, I'll pass it to you for the financials.
Trond Westlie
executiveGood afternoon, everyone, from my side too — and thanks, Mads. I'm very excited to be joining Ørsted as CFO and to begin delivering on the updated business plan, where we'll make sure financial discipline is maintained through a robust capital structure and through investments into value-creating renewable energy projects. I'm also looking forward to meeting and engaging with you over the coming months as our investor — in our investors and analyst meetings. So, if we then move to Slide 6 on the EBITDA for the quarter. We're using Danish kroner, so I won't repeat that for every number. For the group, we realized total EBITDA of DKK 7.5 billion, excluding new partnerships. No cancellation fees this quarter. That was around DKK 600 million above the same quarter last year, with offshore sites the key driver behind the increase. Let me walk through the main earnings development for the quarter compared to first quarter last year. For our offshore sites, earnings rose by DKK 1.1 billion. This was driven by ramp-up generation from Greater Changhua 1 and 2a and South Fork. Higher prices on our inflation-indexed CFDs as well as strong wind speeds. On the availability side in the first quarter, we had reduced capacity on the export transmission cables at Hornsea 1.
Trond Westlie
executiveThe transmission cables have run into problems with the electrical infrastructure, so they've been curtailed during stretches when wind speeds are high. We're working closely with the owner of the transmission cable. And since we operate the assets, we managed to pinpoint the root cause fast and took part in the remedial work. Hornsea 2 uses a similar electrical infrastructure design, and curtailment of that wind farm has been limited in April, with possible curtailment ahead until the issue gets resolved. We expect the remedial work to be finished in full and both wind farms to be back at full capacity in the second quarter of '24. Earnings from our existing partnerships fell because of a minor adjustment to construction agreements completed in earlier years. And finally, other — and that's the last item for offshore — including development costs, landed around last year's level, mainly because of costs tied to halting development of Ocean Wind 1, which had a negative effect of DKK 157 million. Moving to onshore: earnings matched last year's level, with ramp-up generation from new assets in operation.
Trond Westlie
executiveU.S. weather in January came in worse than usual, and that led to reduced generation and availability for the period. Moving on to bioenergy and others: earnings at our CHP plants fell because of both weaker generation and market-based spreads. In our Gas business, earnings came in better than a year earlier, though the contribution remained slightly negative. A temporary negative revaluation effect on our gas storage showed up last year and did not recur to the same degree this year. Now to Slide 7. On the left side, reported net profit came to DKK 2.6 billion, roughly DKK 600 million below the prior year. Net profit got a boost from higher EBITDA and from the net impairment reversal tied to the Sunrise OREC award, partly offset by higher interest rates. Tax expense was impacted by recognition of a deferred tax liability of 800 — approximately DKK 800 million — connected to a tax equity contribution for our Eleven Mild project, while the underlying tax rate stood at 25%. So looking at net profit, excluding the impairment reversal and out-of-the-period tax corrections, both in the first quarter of '23 and '24, we achieved a rise in net profit of approximately DKK 400 million, or just under a 20% increase.
Trond Westlie
executiveMoving on to ROCE, after adjusting for impairments and the cancellation fee, our return on capital employed was 12.5%, down versus last year, and the reason was higher capital employed. The reported ROCE fell to a negative 12.2%, and that was mainly because of lower EBIT stemming from the impairments and also the cancellation fees. Equity at quarter-end was DKK 83 billion. That increase came from comprehensive income and from our hybrid capital issuance. Most of the negative hedge reserve was tied to hedges delivering during 2025. Now, Slide 8. Net debt at the close of the first quarter of '24 was DKK 49.9 billion, up roughly DKK 2.5 billion over the quarter. Cash flow from operating activity got a positive boost from EBITDA and collateral release, partly offset by DKK 2.4 billion of cancellation fee payments tied to Ocean Wind 1. Gross investment for the quarter came to DKK 7.6 billion, driven by what we put into building out our renewable project portfolio. The roughly DKK 700 million of divestments stems from a customary compensation paid to our partners at Hornsea 1 for the wake loss effects from Hornsea 2.
Trond Westlie
executiveTypically, in a farm down, the proceeds we get from the partner are based on an assumption that there will be no wake loss effects from wind farms that may be nearby. But at the moment of that farm down, we do set aside a provision reflecting our estimated wake cost. So later on, once we have clarity on what the actual wake effects turn out to be, we compensate the partner. Because that provision has already been made, this compensation carries no P&L effect. In the quarter, we issued new Green Hybrid capital of approximately DKK 5.6 billion, partly offset by buying back hybrids already issued that are callable later this year. Lastly, net debt was impacted by DKK 1.4 billion tied to exchange rate adjustment, lease obligation as well as hybrid coupon payments. The onshore divestments we signed in the first quarter in the U.S. and France were not closed in the quarter and therefore had no impact on the numbers. Moving up to our credit metric, FFO to adjusted net debt was 19% at the close of the first quarter. Versus last year, the decline comes from higher adjusted net debt as well as lower funds from operations over the 12 months rolling period.
Trond Westlie
executiveWe are still dedicated to reaching a level of roughly 30% in '25 and above 30% by '26, but we want to point out — we did point out at our Capital Markets update in February — that the ratio is anticipated to fall below 30% for '24 because of the cancellation payments. And I'd like to clarify that a little bit regarding the 19%, since as we pay all the provisions, hopefully over the course of '24, this 19% will probably decrease somewhat relative to — because this figure covers the last 12 months. Consequently, that number is going to drop. And likewise, if we assume payments happen within '24, the last 12 months in '25 won't reach the level of around 30% until the year's end. It's a bit complicated, but that is at least how we see this number developing going forward. Let's move on to Slide 9. For the first quarter of 2024, our taxonomy-aligned metrics matched expectations. The renewable share of energy came in at 97% versus 89% for the same period last year. That development was mainly driven by ramp-up generation in offshore, higher wind speeds and a larger share of generation from sustainable biomass, along with lower coal-based generation.
Trond Westlie
executivePhasing out coal-based generation during '24 is still on schedule, and in March we hit a major milestone: for the first time ever at Ørsted, our CHP plant used no coal at all. On safety, unfortunately, performance falls short of the standards we expect. We've recorded more injuries — both among our own employees and among contractors. To boost safety awareness and lift overall safety performance, safety days will be held at our Ørsted locations this quarter. Also, a supplier safety day for the most critical suppliers will be hosted, and a program to strengthen safety leadership at every level of the organization has been launched. Finally, moving to Slide 10 on guidance: financial development in the first quarter came in as we expected. We reaffirm our full-year EBITDA guidance of DKK 23 billion to DKK 26 billion for 2024, along with gross investment guidance of DKK 48 billion to DKK 52 billion. To wrap up, I'll quote Mads from our quarterly report: all in all, we're off to an encouraging start to '24 and on track to deliver the targets we presented in February.
Trond Westlie
executiveAll right, with that said, let's take some questions. Operator, go ahead please.
Operator
operator<<operator_script>> Our first question this afternoon is from Harry Wyburd at BNP.
Harry Wyburd
analystFirst off, congratulations to Rasmus, Trond, and Patrick — and hello, Trond. I'll stick to just one question. Could I ask about the curtailments at Hornsea 1 and 2 that you brought up? What sort of earnings impact did those produce, or how much of an earnings gain could we see once they're resolved later in the year? What will fixing them cost? And how confident are you that they'll be fully fixed?
Mads Nipper
executiveYes. Many thanks, Harry. So on this — we aren't going to provide the exact figure, but as you could see, it's one that doesn't change the fact that we've delivered a quarter in line with expectations, with stronger offshore earnings, and it doesn't, in any way, affect the guidance for the full year. We're now heading into a low wind quarter. And with that, as I mentioned, since this is a transmission issue that only matters at the highest loads, we expect the extra impact to be minimal here, and we're highly confident that we'll be able to fix it. The costs aren't high. It should be a fairly straightforward fix, but we'll keep watching how things develop to make sure it gets fixed, and we'll do that during Q2.
Operator
operatorAhmed Farman from Jefferies has the next question.
Ahmed Farman
analystI wanted to ask about that slide where you laid out the projects and their timelines. Looking just at the commissioning dates, they haven't really shifted since the last update you gave us. But I wanted to check whether there's any extra detail you can offer on the progress made during first quarter — something that either strengthens your confidence in delivering against those targeted timelines, or any developments that have somehow made visibility meaningfully less clear. Specifically, I'm thinking about Revolution Wind, Greater Changhua 2b and 4, and Borkum Riffgrund 3.
Mads Nipper
executiveYes. Thanks very much, Ahmed. The brief response is no, we haven't seen any material movements. As I said, perhaps the clearest instance of a decision that's already been taken to derisk further is that we've now fully chartered a vessel rather than <<inaudible>>, where during the February Capital Markets update, we shared that a full descoping of Revolution had been completed, and partly of Sunrise as well. We've now made the decision and secured capacity for a different vessel, so <<inaudible>> won't be used at all, which represents additional derisking. Regarding Revolution, the plans remain unchanged. The schedule remains unchanged. As we stated, we're putting priority on the 2 offshore substation monopiles. And we're working to make sure that any slippage in monopile delivery gets mitigated through vessel extensions. That applies to Borkum 3 as well as to Revolution and Changhua 2b and 4. But there are no material changes to the expected commission date outlook, so we're not getting any closer, yet there's also nothing giving us material concern that they've been pushed further out.
Operator
operatorOur following question is from Kristian Tornøe at SEB.
Kristian Johansen
analystI actually had a question about that same subject. So perhaps a bit more on Borkum Riffgrund 3, to get a handle on where things stand with the monopiles and on what you said regarding locking in additional vessel capacity. If it turns out you do need more vessel capacity, who ends up bearing that cost? Because it sounds as though an issue like that would stem from delays on the part of your monopile supplier?
Mads Nipper
executiveYes. Thanks, Kristian. That's correct. What I mean is that we're monitoring the situation very closely, and we haven't stopped doing so. The thing that makes us quite pleased is that our main supplier's actual output of monopiles — for 3 of our projects — has now become stable. As a result, planning is now less risky. What we're doing at present is increasing capacity for the coating work itself, which, all else being equal, is a more straightforward process to carry out. So we genuinely anticipate that the predictability of those deliveries will keep becoming clearer over the months ahead. The single most important item we're concentrating on at this moment is making sure that extra potential vessel capacity is in place. Broadly speaking, that's how things stand — so the question now is whether we'll manage to pull off securing that capacity, should we need to do so in order to lock in the option. The cost generally falls on us, since the LDs we might impose on the suppliers won't cover at least the majority of it. So by and large, it's something we bear ourselves.
Mads Nipper
executiveKeep in mind that we already said at our CMD that contingencies had been raised to cover items like this, though it's true that in certain cases—for instance, the full descoping on the U.S. project—that has brought an extra CapEx cost, but nothing that worries us with respect to the targets in the plan we presented.
Kristian Johansen
analystAnd could you comment on this — since, as you noted, we've talked several times about how returns are being affected on the U.S. projects, but what about the European projects, specifically Borkum Riffgrund 3, and how sensitive value creation is there given the risk that remains? How should we think about that?
Mads Nipper
executiveRight. We won’t comment on returns for specific projects. But based on what we know at this point, there’s nothing that has a material impact on those projects’ returns.
Operator
operatorOur next question is from Deepa Venkateswaran at Bernstein.
Deepa Venkateswaran
analystThis is Deepa Venkateswaran at Bernstein, and I have 2 questions. First, can you bring us up to date on how the farm-down process is progressing? In an interview today, Mads, you brought up farming down Sunrise Wind, so perhaps you could comment on that. And what is the situation in Taiwan as well? My assumption is that the exclusivity arrangement with Cathay has lapsed, so an update there would help. That covers my first question. For my second, regarding the auctions you have taken part in, it is clear that your U.S. ambitions have come down. I am therefore curious about the timeline for the U.S. Starboard project should you be successful in it. Also, can you confirm whether Hornsea 4 was entered into the AR 6 or not.
Mads Nipper
executiveYes. Thank you very much, Deepa. I failed to hit the button — my apologies for that. Yes, regarding the farm downs, things are broadly proceeding as planned. So the progress we've witnessed leaves us satisfied. And while we don't discuss individual transactions, the single exception we make to that rule is that we remain glad to confirm that, given how things are moving in Taiwan on Changhua 4, we still anticipate signing and closing that one within this year, and we're also seeing the progress with our partner, Cathay, that we had hoped for. On Sunrise, it's too early to give specifics regarding the timing of that one. We are getting ready for it, but we don't yet have the exact timing. On the auctions, there are 2 auctions where we've confirmed that we placed bids — that's in Taiwan. And then, to your point as well, with our 1.2 gigawatt Starboard project in the Northeast, we bid into Rhode Island and Connecticut since we think they provide the strongest framework for risk protection and COD flexibility, which was a critical element of our operating model. And we do expect that outcome during Q3 of this year.
Mads Nipper
executiveTurning to Hornsea 4 specifically, there isn't a great deal to add, other than confirming that it qualifies to bid into allocation round 6 — though we haven't yet decided whether we'll actually do so.
Deepa Venkateswaran
analystAll right, so suppose you land that U.S. project — wouldn't that push you past the targets you've set for the U.S.? Or do you see it as something much further out, later in the decade, if you do win in the U.S.?
Mads Nipper
executiveNo, that would involve every possible likelihood for a COD after 2030. So — and COD flexibility was among the main criteria we evaluated when determining where to bid and what to bid with. <<inaudible>>
Trond Westlie
executiveThose are just reasons, I'm sorry about that, but please bear with us somewhat since we're having a few difficulties reaching the operator. As a result, it's hard to actually move forward with the questions. So give us a little time, and then we'll attempt to return to you as quickly as we can.
Operator
operatorWe’re sorry for the trouble, ladies and gentlemen, and now we’ll go on to the following question, from Alberto Gandolfi at Goldman Sachs.
Alberto Gandolfi
analystI’m hoping you’re able to hear me.
Mads Nipper
executiveYes, we can.
Alberto Gandolfi
analystThanks, Mads. I’ve got one question and one point of curiosity. First, could you update us on what to expect this year and perhaps the first half of next year regarding announcements about divestment farm-downs? That’s a key part of your strategy. My guess is you’ll focus mainly on completed projects. So I wanted to ask whether you still see interest from potential buyers. Are buyers out there? What do you expect in terms of how liquid the market may be, and I don’t know whether you can name any specific assets. On the curiosity, I’ll keep this very brief. I haven’t heard you say anything about data centers or AI, which seems to be a very, very key topic, especially in the United States. And I was wondering whether you’ve already had any thoughts on how this might affect your business long term. Last night we saw a 10-gigawatt PPA from Microsoft, probably the biggest ever. And I was very curious whether you’ve had any thoughts on that?
Trond Westlie
executiveRegarding our farm-down progress, we're continuing just as planned. And what we're actually seeing in the market is that although asset pricing has been higher or lower owing to interest rates and how those have moved over the last 24 months, we see a somewhat better market situation in that respect, along with interest. So we remain on plan, and Alberto, we're not commenting on the individual assets. So that's not something we'll do. We're not commenting on the plan as such. But slightly positive vibes compared with how things were in February, yet we're still on plan, and we're also considering alternatives, as has always been the case, regarding the targets we've put in place.
Mads Nipper
executiveLet me also speak to data centers and AI, and we're saying as well that we'll supplement in that area. Broadly speaking, what we're seeing is that the appetite — at least among the bigger infrastructure funds — for quality assets is climbing pretty sharply. So for the PDP plan we have, that's genuinely an encouraging signal. On data centers and AI, you're completely right. That opportunity has us excited. It isn't something new. Keep in mind that across all corporate PPAs, the tech sector — with really large offtakers such as AWS, Meta, Microsoft and Google — is already the biggest sector we have in corporate PPAs. It comes to 2 gigawatts that we've sold, from both offshore and onshore. And this excites us, both because demand is growing very fast and because these are companies that tend to be strongly committed to transforming their footprint, which means the increase in renewables will be very targeted. So it's already a big sector for us — likely a double-digit percentage of our offtake already — and one that suits offshore particularly well too, because if we can place these data centers near the node of the offshore access point, then this can deliver high loads of attractive power.
Mads Nipper
executiveThat’s definitely an area we’ll dig into in both Europe and the U.S., examining that opportunity and figuring out the best way to monetize it.
Operator
operatorCasper Blom from Danske Bank has the next question.
Casper Blom
analystAnd welcome aboard, Trond. I've got a question about what you announced this week regarding securing licenses over in Australia. From what I understand, Australia is a fairly immature market when it comes to offshore wind. And as things stand today, there isn't really a proper supply chain, et cetera. And of course, what I'd really hate to see is a repeat of what's played out in the U.S. across recent years. So how do you sort of protect yourself as you now begin getting involved in this newly emerging market and probably don't want to spend too much money on something that remains a bit uncertain. If you could perhaps expand a little on your thinking around these sorts of new market entries.
Mads Nipper
executiveYes, glad to address that. This isn’t a market where you should worry that we’ll wind up in a U.S.-style situation, in part because we’ve learned — and the whole industry has learned — that constructing a brand-new industry from nothing is definitely difficult. And I believe both our company and the broader industry are absorbing those lessons. We really do think it matters for companies such as ours to develop a long-term pipeline of opportunity. And we genuinely view Australia as a long-term offshore opportunity. In particular, this is a place where, for instance, grid connections exist because of coal power plants that have been decommissioned in the area where we would probably interconnect. Much of the infrastructure is already in place, but we’ll proceed with our eyes fully open regarding the risks that an entirely new market would bring and also the possibility of building a new supply chain there. So this isn’t something we’ll rush into. We’ll take an approach based on risk, but we strongly believe the long-term potential of the Australian offshore market is attractive.
Casper Blom
analystIf I could just come back on that, since we're still in the early stages and there are still a number of hurdles to get over before this could turn into a firm project — roughly how much CapEx, or what level of investment, would you need to make, say, to build a pipeline like that in Australia, if you're able to attach any figures to it at all?
Mads Nipper
executiveNo, I’m not able to attach numbers to it, but the amount is quite limited. As for how we obtain it, the process involves carrying out some site investigations—however, this is DEVEX only, and it’s limited.
Operator
operatorOur next question is from Rob Pulleyn at Morgan Stanley.
Rob Pulleyn
analystMany of the questions have already been covered, but if I may, I just had one additional one regarding the supply chain. And in light of the news from the New York 3 auction, the developers' bids were contingent on a future turbine model. May we ask what buying size Ørsted is assuming in its bids that you mentioned in Taiwan, in the U.S. for Starboard and in the U.K., if you were to submit Hornsea 4, of course, or at least could you clarify whether it's an existing model rather than a future model pending?
Mads Nipper
executiveYeah, Rob, it's going to be the second part of that. We can say for sure this isn't riding on some future model we're hoping will show up — it's on it. And it's a technology platform that's already well along in development. So there's no new, sort of upcoming technology platform carrying big uncertainty.
Operator
operatorMark Freshney with UBS has the next question.
Mark Freshney
analystFirst, Mads, I realize we covered this previously, but regarding the supply chain, many marginal participants have now — projects have exited, and companies have scaled back their ambitions. How are the conversations going with the supply chain concerning resource availability? You mentioned securing 2 additional vessels, but how did that come about? Second, on the U.S. elections: your difficulties in the U.S. can likely be traced back to defunding roughly 4 years, 5 years ago — 5 years ago from now. How are your projects currently under construction safeguarded if a future President chooses to step in? What risk does that pose? And what guidance have your lawyers given you? Lastly, if I may, on cost reduction: as some of the figures show, costs have dropped quite considerably. Could you — is there a number you can provide on how you're tracking against your cost-out plans and how much fixed cost has been removed from the business.
Mads Nipper
executiveSure. Thanks very much, Mark. So regarding availability, I'll begin by noting that the importance of continuing to lock in long-term capacity remains. That's also why we made a point, in today's introduction, of mentioning that signing the 4-year agreement with Carla on installation vessels, along with having heavy plate steel available for foundations, is something that stays really important and something we'll keep doing with our most strategic suppliers. Broadly, we do see that availability — partly because over the last several months we've had intense discussions with the vessel suppliers — means that vessels for backup, for instance with a somewhat prolonged installation schedule, are available. So we aren't seeing the same tightness we experienced, for instance, with Ocean Wind 1, where there was simply no vessel capacity to be had. That doesn't mean it isn't tight. It is, it is. Supply chains generally remain tight across offshore and especially in some capacity groups, but we are seeing better opportunities to, for example, extend lease agreements. On the U.S. risks, yes, you're right that there certainly are risks we are being very — that we are handling very explicitly, most importantly to make sure we have all permits in place, which we feel comfortable we will.
Mads Nipper
executiveFor the portfolio we already have, the only remaining COP is Sunrise's. We expect that over the summer of this year. In principle, that is the sole item we'll need from the federal agencies, BOEM included, on that existing portfolio. So that risk ought to be limited. Let me add a general point as well: it's quite clear that offshore is turning into an increasingly bipartisan industry. Despite some of the rhetoric, people are recognizing that a very high shared priority in both blue and red states is job creation, and we do see it acknowledged that offshore is generating jobs in Texas, the Carolinas and across the Gulf Coast generally. These are among the things we're working very hard to make visible. On our new bid, on Starboard, which we submitted — one reason, picking up the earlier question, that we emphasized COD flexibility on timing so much is precisely so we can absorb possible extended permitting delays, which we neither hope for nor expect, but we've prepared for in case it happens again.
Trond Westlie
executiveWhen it comes to cost takeout, we've obviously begun the programs tied to the 800 job reductions we announced in February. Roughly 250 people were made redundant during February and March. And the program we have for the year is really about executing most of it. So the cost effect, of course, won't show up in '24. It will arrive in '25 at the earliest. But we are seeing progress on this, and at least we have clear goals for a leaner, more efficient organization, and we're on the way to delivering that.
Mark Freshney
analystThanks, Nipper. One quick follow-up from me. Should we anticipate any one-time charges below the line tied to this cost reduction program? Or does all of it get absorbed within the continuing EBITDA line?
Trond Westlie
executiveHonestly, we’re not at the point where we can pin down that piece yet. The project simply hasn’t reached that stage. So as for whether it will be, you know, a single line or one line — I don’t think we can say at this point, or at least not how meaningful that figure will end up being. Once we know, we’ll be transparent about it.
Operator
operatorOur next question is from Jenny Ping at Citi.
Jenny Ping
analystI have a couple of questions, if you don't mind. On the wake effect — clearly, there have been multiple occasions when you actually took cash charges on assets that were sold. So may I just ask, out of the DKK 17 billion of provisions sitting on your balance sheet, what portion actually relates to potentially covering future wake effect? That's my first question. Then the second one goes back to the onshore assets for Hornsea 1 and 2. Could you help us grasp the specific problem? Is it the design? Is it the product itself? Or, thinking back to the time of the IPO, I believe many of the offshore discussions were set aside in the sense that it would be <<inaudible>> and operational risks tied to the transmission cable itself, and you receive compensation for that? So could you just clarify where things stand in that compensation process?
Trond Westlie
executiveI'm not entirely certain I caught that — hearing you was somewhat difficult. What I believe I picked up, though, is the question of how large our wake loss provisioning is compared with the overall provision of DKK 17 billion. Did I get that right?
Jenny Ping
analystYes. On the wake effect.
Trond Westlie
executiveOn the breakdown of the provisions, we won't disclose the components, because that would be rather difficult. But taking all of those provisions together — both the canceling provision and all the other provisions — we believe, as a general comment, that we're well covered, and progress has been made on many of the smaller issues as such. But on that point, we have evaluated that we will have that taken into consideration. And I can say more than just that. Regarding payment of the provision, we've done DKK 2.4 billion this year — this quarter — and we have settled quite a bit of the minor and the medium elements. And we sort of retained that our provision is sufficient as we see it now.
Mads Nipper
executiveOn your question about that offshore asset, Jenny — sadly, since we don't own it, there's only so much detail we're able to share. What it comes down to is the design of the electrical infrastructure. That said, because we operate it, we have a very good understanding of the problem, and I've also been actively supporting the effort to make sure the remedial work now being carried out in Q2 is something we feel confident about. So we know it well. It's also a situation where we're familiar with the technical solutions being put in place. Sadly, unlike in Continental Europe, there's no mechanism for compensation for outages on availability offered from offshore to the generation asset owner either. So that isn't something where we could look for compensation from <<inaudible>>
Operator
operatorOur next question is from Marc Tat Kuen at Berenberg.
Marc Ip Tat Kuen
analystI’ve just got one question. It concerns Greater Changhua 2b and 4. On Slide 5, a comment appears there saying that opportunities are being assessed to secure additional best capacity. I only wanted to check whether that is to stay ahead of schedule, or whether it is needed to keep the project on track, or whether it is simply backup capacity.
Mads Nipper
executiveYes. Thanks, Marc. That serves as backup capacity. The point is to make sure we're proactively ready in case component supply slips at all. Nothing has been decided on this yet, and it hasn't even been judged whether it's needed at this stage, but the aim is to guarantee that, should any of those events actually occur, we're set and can stretch that installation window out a bit. So it's a backup.
Operator
operatorDominic Nash from Barclays has the next question.
Dominic Nash
analystI have a couple of questions, if I may. The first concerns, roughly speaking, the capital cost of offshore wind, and it follows on somewhat from Mark Freshney's question about the supply chain, which may be easing as the ambitions of the players for. I would like to get your view on whether peak pricing for offshore wind has been reached, and whether we are in a deflationary environment. And could you give some kind of ballpark figure for an offshore wind farm excluding transmission costs in -- around the world? My second question is about Revolution Wind. I see that you will begin construction proper later this year. But could you give us some color on the court case that I believe is blocking construction of Revolution? And how and when do we think that will play out? And at what point does the 2025 COD they need to be moved back?
Mads Nipper
executiveYes. Thank you, Dominic. Regarding what offshore wind costs, as you're well aware, it really depends heavily on the direction interest rates take, since if the cost of capital does come down, that will of course show up directly in upcoming solicitations. Whether pricing has topped out is hard to claim, but one fact is clear: inflation — supply chain inflation — is far less steep than what we experienced before, though it's still too soon to tell if things are flattening or even turning deflationary; what we can see is markedly flatter inflation. So I won't offer specific figures on the expense of building generation assets globally. Still, we clearly anticipate smaller increases. Whether they've peaked and are now declining, though, can't be determined, as that will depend greatly on macroeconomic conditions and, in particular, rates. On the Revolution court case, I appreciate the question, because nothing is being blocked. There was an attempt. As you know, the American legal system permits these to occur, and several exist throughout the industry.
Mads Nipper
executiveAn attempt was made to get something like an injunction against how Revolution is being built, and that was turned down on April 30. So nothing stands in the way now. We've also received a new buy up. The new permit — the one that was fully customary — was opened following review, and we've now secured that once more. So we're waiting on the final permit formalities, which ought to arrive in a very short term, and after that offshore construction will begin.
Operator
operatorOur following question is from Louis Boujard at ODDO BHF.
Louis Boujard
analystYes, and maybe I have two questions myself. The first concerns onshore and the pipeline. Right now you have quite a few assets under construction, particularly in the U.S. and only a limited number in Europe, and since we lack visibility into the pipeline and development, I was wondering whether you intend to maintain a strong foothold in the U.S. and, if possible, keep that larger than Europe, or whether you plan to rebalance somewhat in this area going forward? My second question would perhaps be about the Danish tender. It's fairly large, 6 gigawatts, even if it isn't happening tomorrow by 2025, but it is 6 gigawatts. I was wondering, since it's perhaps a bit different from the usual ones and, of course, it's your home market: do you have any specific development you plan to tender here? And do you think this can be available by 2030 so we can also reach our 2030 target? Or is it already too late for that, and it will only be delivered after '30?
Mads Nipper
executiveThank you, Louis. Stop me if I’m answering something other than what you asked. On your first question, regarding the onshore pipeline and the opportunities in the U.S. compared with Europe: obviously, the U.S. is going to stay our largest onshore market. We do see — we do have a pipeline, and within it we also see a number of attractive opportunities, and we’re fairly excited about some of the chances that sit in combined generation and storage. So we’re pursuing that, on the development side as well as by examining whether there are any project-specific acquisition opportunities. Europe has many, much smaller opportunities in the pipeline. We have a strong pipeline, as you know, both with Brookfield Renewables and also with Austrian, which we acquired in Germany. That is now what remains to us from that one. We do have an attractive pipeline, but it consists of many and much smaller opportunities. Still, we’re confident that we have a strong and attractive onshore pipeline in both regions, and I hope that addresses the issue you raised. On the Danish offshore tender, you’re right, that one is big. It is 6 gigawatts minimum, and with overplanting it can likely be bigger.
Mads Nipper
executiveWe're digging deeply into the specifics of the tender documents right now. Industry and government have had solid market dialogue, but it's too soon to make any firm statement about how we assess this tender's appeal relative to other opportunities globally. On timing, yes, you're correct that it's tight, though at this point it isn't up to us to judge whether it's realistic or not.
Operator
operatorWe’re taking another question from Casper Blom.
Casper Blom
analystI figured I'd use this chance to ask. Has anything new come up regarding possibly repurposing equipment from Ocean Wind, and perhaps from Skipjack as well?
Mads Nipper
executiveRight, Casper, there isn’t much of an update. We are, in fact, still bringing those opportunities along and maturing them. And as we’ve mentioned previously, the largest one by far — where we have good grounds to think reuse opportunities exist — is on export cables. We’re seeing that on vessels as well. So we keep working at it. But when it comes to the larger scopes, it’s mainly export cable and vessel. Nothing here at this point alters the overall provision; we still feel comfortable that what we’ve set aside is a realistic figure for what we’re executing on.
Operator
operator<<operator_script>> We have one more follow-up question, this one from Mr. Mark Freshney.
Mark Freshney
analystCould I ask about the CC U.S. facility you're building in Copenhagen — I mean, the results don't include any commentary on it. How is it coming along so far?
Mads Nipper
executiveYeah, thanks, Mark. That work is coming along nicely. Just to remind everyone, we're constructing at 2 sites — the Asnæs and Avedore power plants — and our main supplier there is Aker Carbon Capture Norwegian. And despite the fact that this is a first of its kind, it's moving forward according to plan. As of right now, we see no reason to think we can't meet the COD deadlines for beginning to capture carbon in '25.
Operator
operatorDominic Nash.
Dominic Nash
analystPardon me, one more question from my side. Through 2024 so far, I believe valuations across most of your renewable peer groups have dropped pretty sharply. Obviously, your own performance has held up comparatively well too. What I'd like to ask, though, is this: as you evaluate pipeline construction and development, do you also weigh whether, in today's environment, purchasing assets might be the better route instead of building them? Or has that idea been ruled out entirely?
Mads Nipper
executiveYeah. I mean, what we do is develop, construct, and run wind farms as well as renewable farms. That's our core strength. And apart from certain projects—say, in onshore, where we purchase and then further develop—our focus is on developing, building, and operating. So no—I mean, take acquiring assets or platforms in offshore, which is our core business: at this point that isn't a priority, whereas in onshore, as you've seen, things work differently. We purchased 2 platforms and we also acquire projects from time to time. So 2 different approaches, but there's nothing we have any immediate plans to change.
Operator
operatorThat was the final question, ladies and gentlemen, and now I’d like to hand things back over to Mads Nipper for some closing remarks.
Mads Nipper
executiveYes. Thanks so much, and thanks to everyone for being here. I appreciate the excellent questions and I truly apologize for the technical difficulties we ran into partway through. As usual, if anything else comes to mind, please don't hesitate to contact our IR team. They're available to help with those. So thank you. Stay safe, and have a great day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.