Ørsted A/S (ORSTED) Earnings Call Transcript & Summary
May 7, 2025
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, welcome to the Ørsted Q1 2025 earnings call. For the first part of this call, all participants will be listened on remote, and afterwards, there will be a question-and-answer session. Today's speakers are Group President and CEO Rasmus Errboe and CFO Trond Westlie. Speakers, please begin.
Rasmus Errboe
executiveGood day, everyone, and thanks for being here for today's presentation. In Q1, our attention has been on carrying out the business plan we laid out in February. Under that revised plan, we set four main business priorities for Ørsted, and these will be central as we put our strategy into action. The first is making our capital structure stronger. The second is delivering an offshore construction portfolio of more than 8 GW. The third is a disciplined, focused stance on capital allocation, prioritising value over volume. And last, we will make sure Ørsted becomes even more competitive going forward. We'll keep pushing forward on all four priorities so we deliver on our plan. Having said that, the offshore wind sector still faces near-term difficulties, with headwinds tied to the supply chain, regulatory uncertainty, and macroeconomic developments. We are monitoring closely the developments regarding additional potential tariffs and other regulatory changes. Even with substantial challenges in certain geographies, the long-term fundamentals for offshore wind remain strong, thanks to rising global electricity demand, a greater emphasis on energy security and affordability through renewables, and better framework conditions in several major markets.
Rasmus Errboe
executiveSo with that, I'll take you through where we stand on each of the four strategic priorities. In the first quarter, we've posted strong operational results, with reported group EBITDA up 18% versus last year. We're also continuing to deliver on our farm-down program, having closed two divestments since the year began. In the US, we completed the 50% farm-down of two of our solar farms, and only last week we closed a divestment of part of our West of Duddon Sands offshore wind farm in the U.K. Those transactions bring in total proceeds of around DKK 7 billion and support our capital structure. Our relentless focus on delivering the offshore construction portfolio continues, and in the first quarter we kept delivering on that with the successful commissioning of Gode Wind 3. That also means we have now installed more than 10 GW of offshore wind capacity. Given the short-term challenges facing the offshore wind industry and the adverse developments of recent years, we will take an even more focused approach to capital allocation, and we do see ample opportunities in our core offshore wind markets to leverage our distinct capabilities.
Rasmus Errboe
executiveGiven the range of opportunities in front of us, the most appealing investments are the only ones we'll choose and move forward. A central element of that is making it unmistakably clear that, for our shareholders, value matters more than volume. Because we allocate capital in this disciplined way, we have decided to halt work on developing our 2.4 GW Hornsea 4 project in the U.K. in the form it currently has. Since the award was made, the business case has run into a number of adverse developments, particularly rising costs throughout the supply chain and higher interest rates. Taken together, those developments have weakened the potential for value creation and raised the execution risk. All through the development phase, we have been very diligent about capital commitments and have adhered to our updated stage gate model. We sit well below our internal commitment thresholds, and this decision is being taken well ahead of the planned FID. I want to stress that Ørsted still regards the long-term fundamentals as strong and sees attractive prospects for offshore wind in the U.K. As we continue to hold the seabed rights, the development consent order, and a grid connection agreement, we will assess the options for developing the Hornsea 4 project in the future.
Rasmus Errboe
executiveHalting work on Hornsea 4 as it presently stands won't affect the strategic goals or financial targets we've set for the medium and long term. It's a pleasure to have added 2 new people to our Group Executive Team. Making our company more efficient and more focused as we move ahead is part of what it will take for us to grow ever more competitive down the road. Thanks to the recent appointments of Amanda Dasch and Godson Njoku, the whole offshore wind value chain — from development through construction to generation — is now represented on our Group Executive Team. These Group Executive Team changes show how sharply we are concentrating on our core business, on executing projects, and on becoming more competitive, and I'm very glad we could bring 2 such capable people onto the team. Let's go to slide 5, where I'll take you through a few of the operational highlights for the quarter. To begin, I'm happy with the operational earnings for the first quarter of the year, in which our EBITDA, excluding new partnerships and cancellation fees, comes to DKK 8.6 billion. That 14% rise versus last year keeps us on course to hit our full year guidance of DKK 25 billion-DKK 28 billion of EBITDA.
Rasmus Errboe
executiveA key factor behind our strong operational results was availability in the offshore segment. Availability rose by 9 percentage points relative to the same quarter a year earlier, and that makes it a major contributor to higher earnings, even with the weaker offshore wind speeds we saw in Europe. Running our 10 GW offshore wind fleet with a sharp eye on financial performance stays a top priority for us. In the quarter, we also advanced on the renewables portion of our generation. For several years we have aimed for renewables to make up 99% of our generation by 2025, and in the first quarter of the year, that is exactly what happened. The higher renewables share came about because we closed our final coal-fueled CHP plant in the second half of 2024, which was another significant milestone in our decarbonization journey. Finally, our sustained, unrelenting emphasis on safety carried on, and the total recordable injury rate for the first quarter of 2025 fell from 2.9 last year to 1.9 this year. That positive trend, though, was overshadowed by the two tragic fatalities among our contractor employees at the Plum Creek onshore wind farm earlier this year.
Rasmus Errboe
executiveWe extend our heartfelt sympathies to the families and friends of those affected. Our attention is on the ongoing investigation being carried out by the appropriate authorities, and we are coordinating closely with GE, WindCom, and those authorities. If we move to slide 6, you'll see an overview of our construction projects. As we said, as part of our February release, going forward we will offer more insight into how our construction portfolio is being executed. To make this as relevant as possible for you, we'll do this for the projects that are furthest along and most active in construction. Before I get into the detailed updates, allow me to make a few comments on the rest of our construction portfolio. In the first quarter, we successfully commissioned Gode Wind 3. That accomplishment boosts our operational capacity and also means we have now installed over 10 GW of offshore wind capacity. At Borkum Riffgrund 3, all foundations and turbines are in place, and we are waiting for the grid connection from the German transmission system operator. First power should come toward the end of this year, and commissioning of the project is expected at the start of 2026. The connection delay will be compensated under market regulation.
Rasmus Errboe
executiveAs we wait for the grid connection to be ready and for commissioning of the project to take place, we're making sure the assets keep their integrity through our service and inspection campaigns. Construction at Hornsea 3 in the U.K. keeps moving forward as planned. The onshore work remains on track, and the offshore scope got underway in Q1 2025, concentrating on pre-construction activities like removal of unexploded ordnances. We're collaborating closely with suppliers to handle the ramp-up and the delivery of components that will be installed offshore during 2026, with fabrication and monopiles as a key focus. Construction of the co-located battery storage solution is scheduled to begin in the second quarter of this year. After the final investment decision on our Baltica 2 project in January, we're advancing the first phases of construction work. At this stage, that involves preparation of the onshore substation along with manufacturing activities tied to the offshore substation. We're keeping a close watch on fabrication progress for the project's key components, and also on progress at the installation harbor in Poland, which will serve for loadout of the turbines. We'll keep advancing fabrication cable route preparation and will also kick off the offshore boulder removal campaign in the period ahead.
Rasmus Errboe
executiveAnd finally, building work on our onshore schemes throughout Europe and the U.S. is still moving forward as planned. If you go to slide 7, there's a fuller update on our Greater Changhua 2b and 4 project in Taiwan. Completion for that project stands at roughly 35%. That completion figure is among the metrics we use to track how a construction project's installation schedule is advancing, and it captures both scheduled progress and financial spend. As things stand, every foundation and export cable has now been manufactured. The great majority of the array cables are manufactured too, and output of the remaining turbines is on track per plan. The rest of the array cables, along with most turbine components, are being made in Europe, and when finished they'll be shipped to Taiwan for pre-assembly and installation. This is the first scheme in our portfolio where we're putting in the 14 MW wind turbines from Siemens, and that installation is going very well indeed. In the first quarter, we moved forward with manufacturing of key components and hit significant milestones as well, since we began offshore construction work by installing both foundations and turbines. Right now, we've put in roughly 30% of the foundations plus the first few turbines.
Rasmus Errboe
executiveThe vessels required to install the array cables have now reached Taiwan as well, and they're ready to start installation shortly. From a risk standpoint, the project is concentrating on controlling any possible schedule effects stemming from weather conditions. We've factored in an installation period during winter that is expected to run longer because of difficult weather throughout that season. In the same way, the project keeps tracking the sea routes required to transport the equipment that remains. Over the next stretch, the project will keep advancing foundation, turbine, export cable, and array cable installation. First power should come during the summer, and we anticipate commissioning the project at the very end of this year. Now, moving to slide 8 and an update on our Northeast program, beginning with Revolution Wind. Completion of the project stands at roughly 75%, and we've kept up solid progress both on building the onshore substation in Davisville, Rhode Island, and on installing monopiles and turbines offshore. At present we've installed close to half of the 65 turbines and about 80% of the monopiles, and we've finished all export cable installation.
Rasmus Errboe
executiveThe project is still centered on several critical items needed to deliver it under the revised timeline. At the onshore substation, we're putting the updated solution into practice, and that effort shows up in the project schedule. We assumed site management at the start of this year, and since then we've sped up the work, which means every building has now been erected and sealed against the weather. That was a key deliverable for reducing risk in the installation schedule for the onshore substation, which sits on the project's critical path. The next stage involves installing the equipment and commissioning, where risk management is mainly tied to safety and quality. As for monopile installation at one of the project's two offshore substations, work is also moving along well on the issue that came up last year. We'll carry out a fresh monopile installation for the offshore substation, and we anticipate that this installation will happen later this year, using the installation vessels already under contract that are performing work at Sunrise and Revolution. Finally, turbine installation continues at a good pace and is advancing in line with the updated plan. As you know, installing the turbines calls for a different local setup in the U.S.
Rasmus Errboe
executiveUp until U.S. installation vessels have been constructed and become available. What that means is the components get assembled and staged out of New London Port, then carried to the site by barge, after which they are installed with installation vessels. This scope has received the team's highest-priority attention and remains on course for completion later this year. The project is still on track to be commissioned in the second half of 2026. Now, if we move to slide 9 and our Sunrise Wind project. Sunrise Wind is being built alongside Revolution Wind as a single program, covering vessel arrangements as well as the wider offshore installation campaign. Sunrise's degree of completion stands at roughly 35%, with nearly half of the turbines fabricated, the onshore converter station close to finished, and monopile fabrication moving forward in line with the updated plan. During the quarter we started offshore construction, kicking off with boulder relocation and two horizontal drillings for the export cable, and we are applying the learnings built up on Revolution Wind. Those learnings show up in the installation schedule, as Sunrise Wind carries out monopile installations, with turbine installation to follow later this year as part of our U.S. Northeast program. The project's attention stays on a number of items that are critical for delivering the project under the updated schedule.
Rasmus Errboe
executiveWork on building the monopiles is moving forward as scheduled and will keep going through 2025. Because of seasonal limits on when they can be put in, the monopiles will be installed across two seasons. On the export cable side, things are going well — one section has now been produced, and the other two should be finished later this year, again on plan. Every section of the cables has come through all the critical checks, factory acceptance testing included. As for the jacket structures for the HVDC, they're in the last stage of quality control, with transport to the site planned for the summer. Commissioning in the second half of 2027 is still on track. With that, Trond, I'll turn it over to you.
Trond Westlie
executiveThanks, Rasmus, and good afternoon, everyone. Let me begin on slide 11 with the EBITDA for the quarter. As usual, unless I say otherwise, the figures I mention will be denominated in Danish kroner. During the first quarter, we achieved an EBITDA, including new partnerships, of DKK 8.9 billion — an increase, as Rasmus noted, of 18% versus last year. Excluding new partnerships, EBITDA came to DKK 8.6 billion. Allow me to take you through the key earnings developments for the quarter. For our offshore businesses, total earnings landed DKK 200 million above last year's level. Earnings from sites went up, driven by ramp-up generation, better availability, and higher prices on the green certificate and inflation-indexed assets. Our power trading activities also contributed a positive effect. This was partly offset by wind speeds that were significantly below the same period last year. Other costs — which cover unallocated overhead and fixed costs, along with expensed project development costs — rose versus last year, though in line with our expectations. That increase stems from a change in our cost allocation methodology and has no impact on the total EBITDA expectations for offshore. On the onshore side, EBITDA, excluding divestment gains, rose by approximately DKK 400 million, mainly driven by ramp-up generation from new assets commissioned during 2024.
Trond Westlie
executiveFor bioenergy and other, earnings from our combined heat and power plants came in above the prior year, thanks to stronger power prices and spreads. Gas business earnings rose, driven by higher offtake volumes plus a negative revaluation impact on gas at storages from last year that did not recur to the same degree in the first quarter of this year. Lastly, we booked an EBITDA gain of DKK 300 million tied to the 50% divestment of Eleven Mile and Sparta, our two U.S. onshore projects. Moving to slide 12. Net profit came to DKK 4.9 billion, a substantial rise versus last year. Higher EBITDA and lower tax expenses — stemming from the reversal of a previously expensed deferred tax liability — benefited net profit. During the first quarter, we recorded a net impairment reversal of DKK 300 million. The primary driver of that reversal was a decline in long-dated U.S. interest rates, which the impact of the imposed U.S. tariff partly offset. In March this year, the United States imposed a 25% tariff on imports of steel, aluminum, and certain products containing steel and aluminum. Those new tariffs have led to higher costs and contingencies on our Sunrise Wind and Revolution Wind projects, resulting in an additional impairment of DKK 1.2 billion.
Trond Westlie
executiveAlso, an executive order signed in April 2025 put a 20% tariff on goods imported into the United States from the European Union, with 10% of that in effect and the remaining 10% deferred. We have excluded any possible negative effect of those extra 10% plus 10% tariffs, given the uncertainties that persist. If an additional 20% import tariff were applied, our assessment is that its impact would be under half that of the steel and aluminum tariff. Turning to the effective tax rate, it was as low as 5%. But after adjusting for the reversal of unrecognized deferred tax assets, the underlying rate stood at 23%. Once impairments and the cancellation fear were adjusted for, return on capital employed reached 10.2%, down from last year, driven by higher capital employed. Reported return on capital employed was 4.6%, affected by the impairment recognized over the last 12 months. Our scope 1, 2, and 3 greenhouse gas intensity, excluding gas sales, fell 7% in the first quarter of this year versus last year. That decline came mainly from lower scope 1 and 2 emissions due to reduced fossil-based generation, partially offset by higher scope 3 emissions from capital goods.
Trond Westlie
executiveNow if we turn to slide 13, covering credit metrics and net interest-bearing debt. Net debt for us finished the first quarter of this year at DKK 68.4 billion, which is roughly DKK 10 billion higher across the quarter. Cash flow from operating activities added about DKK 600 million. Costs tied to building transmission assets in the U.K. partly offset our operational earnings, along with seasonality in other working capital items. Relative to last year, we received no material milestone payments connected to our construction projects, and no tax equity contributions either. Gross investments came to DKK 13.8 billion for the quarter, led by what we invested in constructing our renewable project portfolio. Cash flow from divestments of DKK 3 billion was mainly tied to the farm down of the 50% stake in our Eleven Mile and Sparta onshore projects. The West of Duddon Sands stake divestment, announced last week, isn't captured here, since it closed following the close of the first quarter and so will show up in our second quarter accounts. On our key credit metrics, FFO to adjusted net debt was approximately 14% at the close of the first quarter, a modest rise versus the end of last year, mainly because funds from operation were higher over the 12-month rolling period.
Trond Westlie
executiveFor the whole of 2025, those cancellation fee payments that were incurred across the past 12 months are going to roll off the metric, and that will therefore be a benefit to the FFO number. And then last, let's go to slide 14 and look at what we're expecting for 2025. Given a solid operational performance in the first quarter, we are reiterating our full-year EBITDA guidance, which excludes new partnerships and cancellation fees, of DKK 25 billion-DKK 28 billion. Because offshore wind speeds have come in under the norm, we now expect the EBITDA from our offshore sites to land below what was anticipated at the start of the year. Even so, we still expect EBITDA for our offshore segment to exceed last year's level. Changing the future of our Hornsea 4 project is going to carry financial consequences, and those will show up in our accounts during the second quarter of this year. For Hornsea 4, the plan had been to utilize the export cables from Ocean Wind 1, so going forward we will now assess what those cables are worth. Those export cables carry a book value of roughly DKK 1.5 billion. On top of that, we have to date spent approximately DKK 500 million on the offshore transmission assets, and we estimate around DKK 1 billion-DKK 1.5 billion of additional spend tied to a mix of expected contract cancellation costs and committed project spend.
Trond Westlie
executiveAltogether, that could have a potential negative effect on our EBITDA of roughly DKK 3 billion-DKK 3.5 billion in the next quarter or this quarter, Q2, in 2025. Regarding Hornsea 4, the capitalized construction cost is about DKK 700 million, and it will be written off below EBITDA in our accounts for the second quarter. As an additional piece of information, as a result of closing out the outstanding Ocean Wind cancellation contracts, we will also review the remaining provision level during the second quarter. On CapEx, we also maintain our gross investment guidance for 2025 of DKK 50 billion-DKK 54 billion. With that, we will now open for questions. Operator, please.
Operator
operatorThanks a lot. If you'd like to ask something, just hit star and one on your phone. Should you want to take your name off the list, press star and two. Peter Bisztyga from Bank of America is up first. Go right ahead.
Peter Bisztyga
analystGood afternoon, and thanks for taking my questions, Peter Bisztyga. I have a question about the stop work order on Equinor's Empire Wind project. I'm just wondering what reasons there might be — or that you're aware of — why your Sunrise Wind or Revolution Wind projects could be able to avoid similar stop work orders over the coming months. Thank you.
Rasmus Errboe
executiveThanks a lot, Peter. First off, I won't be speculating on possible regulatory shifts in the U.S. — that's beyond our control. Both of our projects have been through multi-year reviews and have complied with every state and federal procedure as well. We're building them as part of a single program in the Northeast, and that program is in a highly active construction stage at the moment, with completion standing at roughly 75% for Revolution Wind and roughly 35% for Sunrise Wind, as I noted earlier. To be specific on Revolution Wind, we've put in close to half of the turbines and 80% of the monopiles, installed one monopile for the project's offshore substation, fabricated all components, and so forth. On Sunrise Wind, we've more or less finished the onshore converter station and the array cables too. We've also fabricated over half of the nacelles for that project and kicked off offshore construction work in this quarter as well. And if I may add, both projects make sure hundreds of millions of U.S. dollars go into the domestic supply chain, backing shipbuilding and port investments, and they're generating jobs in over 40 states too. That's how we see our own U.S. projects.
Peter Bisztyga
analystAll right. Has there been any contact whatsoever with the Department of Interior or BOEM regarding that possible risk?
Rasmus Errboe
executiveIn the markets where we run our projects—and also those under construction, such as these—there is, as always, an ongoing conversation with the regulator. That holds true right now in the U.S. as well, where we remain in a constructive, ongoing dialogue with BOEM regarding how the projects are progressing.
Peter Bisztyga
analystRight, thanks.
Operator
operatorThe following question is from Alberto Gandolfi at Goldman Sachs. You have the floor.
Alberto Gandolfi
analystGood afternoon. Alberto Gandolfi here from Goldman Sachs, and thanks for taking my question. I'd like to ask whether you could spend a moment reflecting on slide 6 and slide 12. On the left side of slide 6, you discuss the 8.2 GW of offshore projects. And thank you for walking through each project and the completion rate. May I ask, on that page, how many of these projects overall have delivered an IRR above WACC since inception? Because Changhua was partly divested at book. We're aware of the situation in the United States, PGE's stocking up cost in Baltica. My question is whether we will see further dilution in the return on capital employed, which fell from 12.5% to 10% in one year. If the IRRs on these projects fall short of your original benchmark, where do you expect Return on Capital Employed to land on a three-year basis, in your view? Thank you so much.
Rasmus Errboe
executiveThank you, Alberto. I'll start on that. As you can probably understand, I won't go into much detail regarding the current spread relative to our cost of capital for each construction project in the portfolio. What I can tell you is that our confidence in the value creation we see across our committed offshore construction portfolio remains intact. For the projects where FID has been taken and where we're progressing, we will have secured, clearly, the contracts before FID and so forth. Our confidence in value creation across the offshore wind construction portfolio holds. On ROCE, it's the same story. We stand behind the guidance provided as part of the updated plan on the 6th of February, when we guided to a ROCE of around 13% for the period 2024 to 2030.
Trond Westlie
executiveTo build on that point, Alberto, capital employed went up by DKK 32 billion over the last year. A lot of that, of course, isn't producing returns yet, since we're in a growth phase, and we'll stay in a growth phase for that part. As we move through the coming couple of years, you'll naturally see a bit more pressure on ROCE. Regarding 2024 to 2030, and the average we provided for the overall plan — the average ROCE across those years — we're holding to that, because we'll then have a growth period running now for the next two to three years.
Operator
operatorCasper Blom from Danske Bank is our next questioner. Go right ahead. Mr. Blom, your line is now open.
Casper Blom
analystHi, I have a question on my end about the choice to stop developing Hornsea 4. I, at least, was taken aback by this, since the allocation came through no later than September last year. I get your points about increased cost, higher interest rates, and the possibility of delays, but is there also a piece of this where you want to adopt a more careful stance toward construction overall? In other words, is this likewise a reflection of your new value focus, where you perhaps cancel something a bit sooner to ensure you don't run into the same sorts of issues that you've seen before in the U.S.? If you could reflect on that a little, thank you.
Rasmus Errboe
executiveOf course. Thanks for that question, Casper. As you also hinted at, I had previously been clear regarding the more detailed factors behind the project case at Hornsea 4, and I can expand on that a bit further too. To address the heart of what you asked directly, first of all, this is clearly not something we decided casually. That much is obvious. We released a plan on February 6th containing four main strategic priorities. One of those involved placing a razor-sharp emphasis on value rather than volume. Regarding this particular project, we just did not identify enough value to satisfy our hurdle rate for a project of this type. Beyond that, as you also partly suggested, this decision should likewise be viewed as part of us becoming even sharper in our stage gate model and how we handle risk management. We reached this decision early, while clearly on the flip side, we made it early compared with a planned FID that had been anticipated by the close of this year, and so it also considerably reduces the financial consequences of halting the project in its present form.
Rasmus Errboe
executiveIt's also worth pointing out that the lease rights remain with us. The development consent order is still ours as well. And we continue to hold the grid connection agreement. What we'll do now is push toward advancing the project once more, but in a new configuration. Essentially, we're taking it back to development, so to speak. Our plan and expectation is that we'd carry the project ahead under a different configuration and according to a different timeline.
Operator
operatorHarry Wyburd from BNP Paribas has our next question. Go right ahead.
Harry Wyburd
analystHi, thank you. Here's another one about the U.S. I realize we keep going back and forth on Hornsea 4 in the US, but this is a very specific question about Sunrise and Revolution. Given that with Hornsea 4 you've shown you're trying to look a bit further ahead and make decisions a bit sooner, I'm sure you would have weighed the risk of Sunrise being cancelled. If it does get cancelled, what would that mean for Revolution? My sense is that Revolution is far enough along that cancellation seems less likely for that one. If Sunrise were cancelled, could you carry on with Revolution? Would it still clear your return hurdles if you did? Or would it be that if Sunrise is cancelled, the whole U.S. project starts to land in a difficult spot, and perhaps that's the end of your major operations in the U.S.? I just wanted to ask whether you could help us think through what might happen in that scenario. Thank you.
Rasmus Errboe
executiveHi, Harry. Thanks a lot. Harry, I won't speculate about what a cancellation would mean — as you mentioned — for either Sunrise or Revolution Wind. We're 100% committed to moving both projects ahead as part of our Northeast construction program. Like I said earlier, these are projects with completion levels of roughly 75% for Revolution Wind and 35% for Sunrise Wind. I'm not going to entertain, you could say, hypothetical scenarios involving project cancellations in this case. We're fully committed to moving forward.
Operator
operatorThe next question is from Ahmed Farman at Jefferies. Go ahead, please.
Ahmed Farman
analystYes, thanks for taking my question. I'd like to return to Hornsea 4 for a moment. Could you provide a bit more detail on the cost inflation you've encountered on this project since you were selected or secured the CFD contract over the last year? And say a little about precisely where in the supply chain that cost inflation has shown up? Then, related to that, is this cost inflation specific to Hornsea 4, or is there a read-across to Hornsea 3 and Baltica 2 that we should be thinking about as well? Thank you.
Rasmus Errboe
executiveThank you, Ahmed. To begin with Hornsea 4, as I mentioned, and as you've also noted, I understand there are three factors, so to speak, driving the business case's deterioration to a point where we've chosen not to advance it in its present form. One is supply chain cost increases. Another is the rise in long-dated U.K. interest rates of roughly 50 basis points since our participation in the auction. On the supply chain specifically, I won't single out particular scopes, particular contracts, or particular suppliers. That wouldn't be appropriate. What I can say is that when we prepare a bid such as this one, we of course build our bid on price quotes and similar inputs across the construction scope. What we've simply observed once, after bidding, we enter detailed contract negotiations with suppliers ahead of a possible FID is that both, you could say, the risk balance between developer and supplier has shifted compared with what we'd assumed in certain cases. More significantly, the original price quotes have simply gone up. I won't provide specific figures on the size of that increase, which is simply too commercially sensitive for us.
Rasmus Errboe
executiveOn the other part of your question, how do we view this beyond the U.K.? Are there consequences inside the U.K. for Hornsea 3, as I understood you to ask? And does it affect Baltica 2 and similar projects? A few observations. First, it matters to distinguish assets being built from assets being developed. Clearly, those are fundamentally different situations. For Hornsea 3 and Baltica 2, we of course secured the full supply chain before reaching FID. So the higher costs and higher risks we've witnessed on Hornsea 4, which is under development, won't appear on those projects. Naturally, we have adjusted. We're seeing shifts in the underlying interest rate environment. That's simply how things are, of course. It sits beyond our control. The portion we can control — you shouldn't expect that to show up. The second part of your question: is this something occurring outside the U.K.? Just a handful of facts. Whereas offshore wind LCOE declined roughly 70% between 2015 and 2020, we've observed a rise in Europe of approximately 50% from 2020 to 2025. LCOE has moved the opposite way, driven in part by greater CapEx and in part by higher interest rates.
Rasmus Errboe
executiveNaturally, that uplift is what we've kept observing on Hornsea 4 as we go about securing the contracts. It's also a rise that you'd anticipate showing up on additional European projects that haven't been secured yet. Without question, offshore wind faces a tough environment in the near term, yet over the long run we stay 100% confident in and committed to offshore wind, including in Europe, where we have faith in the fundamentals.
Operator
operatorKristian Tornøe from SEB has the next question — go right ahead.
Kristian Tornøe
analystYes, thanks. My question concerns your guidance on the DKK 70 billion to DKK 80 billion in divestment proceeds. Could you elaborate on whether Hornsea 4 was meant to be included in that program, and if it was, what effect that has on the proceeds you expect?
Trond Westlie
executiveWhen it comes to how those proceeds are planned, the timeframe is, naturally, from 2024 through the close of 2026. As for Hornsea 4's timing, that sits further out. That piece was never included in this element.
Operator
operatorDominic Nash from Barclays has the next question. Go ahead.
Dominic Nash
analystHello there, and thanks so much for the questions. I have a kind of follow-up to that one, which is that I believe you're restating your medium-term guidance of DKK 210 billion to DKK 230 billion in gross investment. Hornsea 4 is going to make up a big portion of that. So the first question is, does that mean your medium-term guidance will probably have to come down, or does it follow from that that Hornsea 4 is likely to be able to re-bid into upcoming CFD rounds? If that's the case, could you give us some color on — I believe it has to jump one — or when do you think it will be in a position to go back into a CFD round? Thank you.
Rasmus Errboe
executiveThanks a lot, Dominic. To start with the investment program you're referring to: you're correct that, within the plan we laid out on February 6, we communicated a gross investment program running toward 2030 of DKK 210 billion-DKK 230 billion. Within that, as we've also mentioned, roughly DKK 40 billion-DKK 60 billion is what we call uncommitted capital. For projects where FID hasn't yet been taken, like Hornsea 4 — now that we aren't proceeding with Hornsea 4 in its current form and on the current timeline — we'll have somewhat more flexibility regarding how we plan to deploy those DKK 40 billion-DKK 60 billion toward the most value-accretive opportunities we can identify in our portfolio, probably with a strategic emphasis on offshore wind in Europe. On your specific point about the timing of a possible re-bid, it's a little too early for me to be very explicit on that. What I can say is that it won't be AR7 or AR8. Naturally, we'd need to see what the best way forward for the project will be, including for us in terms of delivering the necessary value creation for our shareholders.
Rasmus Errboe
executiveWe'll keep up a constructive conversation with the British government on this matter. I just want to emphasize that we have full confidence the framework we've observed — and are observing — in the U.K., along with the broad backing we encounter wherever we go from a regulatory standpoint for offshore wind, is genuinely, really there. So on the back of this decision, I'm certain we'll carry on having a productive exchange.
Operator
operatorOur following question is from Lars Heindorff at Nordea. Go right ahead.
Lars Heindorff
analystGood afternoon, and thanks for taking my question. It's perhaps more directed at Trond. In the presentation, you said that during the second quarter you'll carry out a more thorough review of provisions. Could you give us a bit more insight? Is there anything you feel is at risk, or what's the reason for this?
Trond Westlie
executiveThanks, Lars. No, nothing’s at risk. It’s simply that we’re finishing up the last contract, so to speak — winding down the Ocean Wind provisions. Because of that, there are more pieces of what the provision actually requires. It’s more the reverse than any kind of worry.
Operator
operatorOur next question is from Jenny Ping at Citi. Go ahead, please.
Jenny Ping
analystThank you very much. I just want to verify which amounts are actual cash and which are non-cash items expected to flow out, both for tariffs and for Hornsea 4. On tariffs, I believe, the DKK 1.2 billion — this is obviously an accounting item at the moment — but when does the cash actually leave? Is it simply included in CapEx? Likewise for Hornsea 4, the DKK 3 billion-DKK 4 billion EBITDA impact, I assume not all of that is cash, and some portion is. Some clarification there would help. Just a quick question on Hornsea 4. Have you considered or looked into the possibility of selling the asset, as Vattenfall has previously done with a CFD? Is that something you've examined and decided not to pursue? Thank you.
Trond Westlie
executiveBeginning with the first question about Hornsea 4's cash impact, as I mentioned, roughly DKK 1 billion to DKK 1.5 billion of that amount represents the cash effect going forward. The rest has already been paid. Ocean Wind is, naturally, simply internal pricing and is, quite literally, paid for within the Ocean Wind project itself. Turning to the tariffs, the DKK 1.2 billion book value you see taken this quarter is, naturally, the net present value impact of tariffs in the Sunrise and Revolution projects. The tariffs themselves — the gross tariff figure — will, naturally, be paid when the goods enter the United States. That stems from the pure logistics of the project. Such a payment is simply a payment and, as such, merely a negative cash flow item in the NPV calculation.
Rasmus Errboe
executiveRegarding the second and third parts of what you asked, Jenny, about Hornsea 4 — no, selling off our lease isn't something we intend to do. We regard it as a strategic asset, and we view Hornsea 4 as very much central to our U.K. business too. There are no plans on our side to sell that lease.
Operator
operatorOlly Jeffery from Deutsche Bank has our next question. The line is yours.
Olly Jeffery
analystThank you so much. I have a couple of questions. First, regarding possible additional impairments in Europe: I'm aware that Baltica 3 is, as I understand it, the clearest candidate — if that project doesn't move forward, you could take further write-downs. Can you update us on where things stand with it? And could you also tell us, if you canceled it today, what size of impairment we might need to see, what size of impairment might we see? My second question is much simpler: please update us on the sales process for Hornsea 3. Is it still on track as planned for this year? Thank you very much.
Rasmus Errboe
executiveI'll begin with Baltica 3, and after that I'll hand the Hornsea 3 sales process over to Trond. Hi, Olly. Some time ago we made a decision — and I suspect this is what your question is getting at as well — some time ago we decided to keep Baltica 3 in what we call reconfiguration, alongside our partner PGE. The reason for that is straightforward: we have not seen, and we are not seeing, sufficient value at this point to satisfy our investment requirements. So that remains the situation with Baltica 3, and we are working with our partner PGE to find a path forward, and I would also note here that we continue to be very happy with that partnership, and on Baltica 2 we are progressing really well together. I won't give you a specific figure regarding possible financial consequences if we were to decide not to take that project forward, but there would be cancellation costs. Those will, obviously, be lower than the ones we have discussed today. As for Hornsea 4, it is a considerably smaller project. We are involved in it with a partner and so forth. If we eventually decide one day not to take it forward, then yes, there will be financial consequences, but they are clearly going to be manageable.
Trond Westlie
executiveRegarding the farm-down sale processes we're pursuing, naturally, we aren't going to comment on any individual one. What I can tell you is that every one of them is making progress. Each is advancing. As we've stated, the timing of the various components — since we've referenced it, I believe it's now 18, two years back that we brought up Hornsea 3 — that too is proceeding in line with the earlier plans. There isn't much beyond what we've already said, namely that essentially we're advancing in accordance with the plan, and we'll return once we genuinely have more qualified material and, put simply, have blue ink on the paper concerning those elements.
Operator
operatorAnalysts, given the time constraint, I'd ask that each of you stick to a single question, and after that you're welcome to rejoin the queue for another one. Rob Pulleyn from Morgan Stanley has our next question. Go ahead, please.
Rob Pulleyn
analystThanks. There are always further questions. Could I just dig into something regarding Hornsea 4? Is this choice — and you've mentioned value over volume and, clearly, balance sheet resilience — a result of not being able to secure a farm-down CapEx partner for that project, when, of course, you're also seeking one for Hornsea 3? A second part, if you like, is whether we should also be thinking that in the U.K., there have been signals that the AR7 and AR8 auctions — and I appreciate it's probably AR8 that you're focused on — could have terms substantially better than AR6? From a value standpoint, is it preferable to cancel and re-bid into a stronger auction? I'd love to hear your thoughts on those two angles. Thank you.
Rasmus Errboe
executiveThanks, Rob. I’ll address both part A and part B of what you asked. Starting with your point about the farm-down of Hornsea IV: our thinking is that, as I’ve mentioned previously, the business case has worsened because of supply chain interest rates and also what we saw as this kind of greater pressure on the float in the project. I noted that an element of that was the rise in the interest rate as well. Naturally, our thinking is that we believe the prudent course for us, when deciding whether or not to proceed to an FID on a project the size and scale of Hornsea 4, is to factor in already now the value implications of a farm-down further down the line. We consider that the prudent approach. In that sense, it has formed part of how we have been making the decision, but there is absolutely no read across whatsoever to farm-downs that are ongoing, such as, for example, on Hornsea 3, which you are alluding to. On part B of your question, about our thoughts on taking the project forward in a different form and re-bidding at a later point in time, we would not be in a position to bid for AR6, sorry, AR7 and AR8.
Rasmus Errboe
executiveThat isn't something we're factoring in. More likely, it happens at some later stage. Naturally, our current plan is to push the project ahead, bring it back into development, and then, naturally, we'll do everything possible to be competitive once more in a future U.K. auction round. As I mentioned, we stay entirely committed to the U.K. and the Hornsea zone.
Operator
operatorOur following question is from Deepa Venkateswaran at Bernstein. Please proceed.
Deepa Venkateswaran
analystThanks for taking my question. Sorry, but I’ll keep my focus on Hornsea 4. We heard from one of your other peers that has an active contract in the same area that they’re still moving forward. They see value creation, and they mention a CapEx of DKK 3.5 billion per gigawatt ex-off to. Could you say what kind of CapEx you were assuming when you made the decision to discontinue? Second, just to note that a spokesperson for the U.K. government has said they plan to work with you to get Hornsea 4 back on track. I wonder how that fits with the earlier comment that you think you can’t really participate in AR7 or AR8. Could you perhaps elaborate on what the U.K. government might want to do? Thank you.
Rasmus Errboe
executiveHi, Deepa. Thanks a lot. Right now I won’t disclose CapEx multiples for Hornsea 4. That project is one we’ve chosen not to take forward. Beyond that, it isn’t my place to draw comparisons or to speculate about how our respected peers in the industry handle their projects when it comes to communication and similar matters. My preference is to concentrate on what we are doing ourselves, and I can’t share that multiple, Deepa. I’m certain you have your own perspective on what CapEx for a project of this size might be. Naturally, one starting point would be Hornsea 3, with an adjustment made because CapEx has risen since that point. Turning specifically to the second part of your question about the remarks that came out today from DESNZ and others: we very much welcome that, of course, and our view matches it. We’ll keep doing everything we possibly can to be the strongest partner we can be for the British government. Part of that also means it wouldn’t be appropriate for me to speculate about when and how we might return with Hornsea 4, including which rounds and so forth.
Rasmus Errboe
executiveWhat I can tell you is that we would clearly adhere to the frameworks, which, as I mentioned earlier, I think is the correct approach. We'll keep doing everything we possibly can to advance the project in a manner that creates enough value for our shareholders.
Operator
operatorOur following question is from Åsne Holsen at ABG. The line is yours.
Åsne Holsen
analystHello, and thank you for letting me ask something. My question concerns the U.S. tariff-related impairments. Is their scope limited just to the steel and aluminum parts, or does it reach other components as well?
Trond Westlie
executiveRegarding tariffs, the DKK 1.2 billion in impairments is tied solely to steel and aluminum. As we mentioned in the introduction, we have excluded the remaining tariffs of 20%, which currently breaks down as 10% plus 10%. The first 10% is in effect, while the second 10% is not. That said, the DKK 1.2 billion does not account for those other tariffs. In a scenario where the EU faces a 20% tariff from the U.S., our preliminary estimates — though we don't yet know what it would cover — if it were a blanket 20% on basically all goods entering the US, that would produce a bit less than half of the DKK 1.2 billion in impairments. That falls somewhat short of the DKK 600 million of impairment that would need to be added to Sunrise and Revolution.
Rasmus Errboe
executiveI completely agree. Looking at the fundamental drivers, to put it very simply, monopiles and turbines—which are obviously mostly steel—are the main reason behind the steel and aluminum tariffs. As for what would drive a possible further tariff beyond steel and aluminum more generally, cables and blades would account for the vast majority of that. Once again, the financial impact is precisely what Trond set out.
Operator
operatorMark Freshney from UBS has our next question. The floor is yours.
Mark Freshney
analystHi there, and thanks for taking my question. I mean, this is about cancelling Hornsea 4, given all that's happening in the U.K. around Clean Power 2030. Some people might argue that it makes a very ambitious target for the U.K. even harder to hit. What I'd like to ask is, presumably you would have needed to speak with the Energy Minister or the Secretary of State last night or early this morning. So my question is, what have they said about this? And building on Deepa's question, how confident are you that the government can come up with a solution here and get Clean Power 2030 delivered?
Rasmus Errboe
executiveThanks for that question, Mark. I suspect what I say now may come across as somewhat of a letdown, but I won't be engaging with it — I'm really not going to approach this from that angle, meaning the political targets in the U.K. and so forth. That's not something for me to address. What I'd prefer is to keep our attention on our projects and on how we can keep helping the British government in the best way we can. As I mentioned earlier, when I was asked about a different matter, naturally, across every market where we operate — our core markets — we keep holding discussions with all the relevant stakeholders, though I won't get into specifics regarding particular conversations with anyone.
Operator
operatorHelene Brøndbo from DNB has our next question. Go ahead, please.
Helene Kvilhaug Brøndbo
analystYes. Hello. Thanks for taking my question. I was just wondering whether you might be able to provide a bit more detail on how you evaluate the chance of undertaking new offshore wind projects that turn a profit in Europe's present market. What do you believe would be needed for this industry to reach competitiveness, I suppose, both under existing subsidy regimes and without any subsidy at all?
Rasmus Errboe
executiveThanks so much, Helene. Let me start by being clear: although we are seeing short-term difficulties in offshore wind, including in Europe, we genuinely have faith in the market's long-term outlook. That confidence comes from the fact that electricity demand in Europe is clearly rising quite substantially. And at present, as has been true for some time, there is a much stronger emphasis on energy security as well as affordability. On top of that, we are observing meaningful enhancements to framework conditions across several of the main markets we look at. Over the long term, in our opinion, what the industry requires is predictability for developers and the supply chain, plus frameworks built around CFDs — in fact, precisely the way we see it in the U.K. The uncertainties we in the industry would need to tackle here are clearly the scale of electricity demand. They lie on the price side. They also concern the supply chain, which we have discussed previously. Then, clearly, there is converting targets into FID and, last, the bankability of the projects. We genuinely believe a path forward exists. As we recently published in an industry piece titled European Offshore Wind at a Crossroads, we are strongly focused on the need for predictability.
Rasmus Errboe
executiveOur view is that the proper approach, over the period ahead, is for the European government—broadly speaking—to put offshore wind out in what you could call a coordinated fashion, nation by nation, ideally with what you might call a guaranteed build-out of offshore wind of roughly 10 gigawatts from 2031 toward 2040 of CFDs, and then a top-on for merging projects with PPAs. Should that occur, we are convinced the industry will respond. We will. We also expect LCOE for offshore wind to begin declining significantly once again. Europe requires offshore wind. We do not see a relevant scenario in which we will not see a significant rise in volumes for offshore wind over the next decades. Together we need to break the curve.
Operator
operatorWe'll move on to a round of follow-up questions, and the first comes from Harry Wyburd at BNP Paribas. Go right ahead. Mr. Wyburd, your line is open.
Harry Wyburd
analystHello. Apologies — my question has already been addressed, so I'll simply pass it along to whoever is next. Thanks.
Operator
operatorThanks. Our next question is a follow-up from Alberto Gandolfi at Goldman Sachs. You have the floor.
Alberto Gandolfi
analystThanks. I’ll be quick. Thanks for letting me ask a follow-up. Here’s what I want to ask: do you have a view on whether zonal pricing might be introduced in the U.K.—on how likely it is to happen, on what timeline, and on how it would affect your current profitability, meaning the profitability of the portfolio you already have? Thank you very much.
Rasmus Errboe
executiveThank you, Alberto. It's clear the discussion about zonal pricing in the U.K. is something we're monitoring very closely, and engaging with both DESNZ and REMA continues to be a priority for us. The really key point for us here is that we see a need, clearly, for a substantial commitment to grandfathering of existing projects, which is also very much what we discussed with the senior officials as well as the public comments that we have seen coming out. We fully appreciate that zonal pricing is still under consideration. As such, we will not sort of, I will not put out a firm view on one model or the other. Of course, it is an uncertainty should you go there on the cost of capital for existing projects because of the increased uncertainty on the revenue line and the risk of the projects, which is also why we believe that the grandfathering of existing projects is absolutely essential.
Operator
operatorDavid Paz from Wolfe Research has our next question. The line is yours.
David Paz
analystHi there, thanks. Regarding Revolution Wind, could you clarify something for me? You mentioned that you're on schedule to finish the top-priority work before this year ends, including the installation vessels. So what remains to be done after that before you reach COD? As I recall, you're still targeting the second half of 2026. Could you just remind me what accounts for that gap?
Rasmus Errboe
executiveSure, David. If you look at what really gates Revolution Wind, it's the onshore substation. As we've discussed, what we're doing right now is, naturally, carrying on with the offshore build that I referenced earlier, where we stand at — as mentioned — roughly, or we've put in place roughly 50% of the 65 turbines along with roughly 80% of the monopiles. It's fair to say that every component for Revolution Wind has likewise been built and readied. What gates us, and what we'll be focused on through the rest of 2025 and 2026, is that offshore construction, plus getting the onshore substation finalized.
Operator
operatorPeter Bisztyga from Bank of America has our next follow-up question. The line is yours.
Peter Bisztyga
analystYeah, hi. Actually, I just have one more question about zonal pricing in the U.K. I'm wondering whether the uncertainty around that played any part at all in your decision to cancel Hornsea 4, and has it created any problems or disruption for the Hornsea 3 farm-down process?
Rasmus Errboe
executiveThanks, Peter. No on both counts. The discussion around zonal pricing in the U.K. played no part whatsoever in why we decided to discontinue Hornsea 4 as it currently stands. What drove that were the three factors I brought up earlier, plus what I said regarding a possible farm down. Consistent with the process we have underway on the Hornsea 3 farm down, and as Trond noted earlier, we won't get into specifics on a process that's still ongoing, though I can tell you that the zonal pricing debate does not feature in the conversations we're having.
Operator
operatorRob Pulleyn is up next with a follow-up question. Go right ahead.
Rob Pulleyn
analystHello. Hello. Thanks. This may be somewhat obscure, but it concerns the U.S. projects. On May 2, there was what I believe we'd term a technical ruling from the Interior Department about offshore wind permitting. It took out a Biden opinion and put in a Trump one. According to the wording, department actions taken based on that earlier opinion would need to be reevaluated. Apologies, this is all quite clunky. My question is, I don't know if you've come across that May 2 ruling. I'm certain you have. Does it create an opening for permits on Sunrise and Revolution to be removed retroactively, given that those obviously come after what happened with Equinor's Empire project? I hope that question was clear.
Rasmus Errboe
executiveThanks, Rob, for that question. I won't get into speculating about, as you might put it, the regulatory framework surrounding Revolution Wind and Sunrise, as I mentioned earlier. All the permits we require are in hand. We've been through multi-year reviews, and we've also complied with every state and federal procedure. So I won't be discussing the details of technical rulings.
Operator
operatorAhmed Farman has our next follow-up question. The floor is yours. Mr. Farman, your line is open. We are unable to hear you.
Ahmed Farman
analystMy apologies — just two short questions, if I may. Sorry for that. Could you share your view on the U.K. government's proposed changes to the CFD? Specifically, whether you believe that will meaningfully shift the options or how attractive the market looks overall. You mentioned earlier that Sunrise and Revolution Wind both sit within one program. From what I understand, the learning from Revolution will probably carry over to Sunrise Wind. Could you say more about that? Which elements matter most when it comes to the lessons from Revolution that you'd expect to help the Sunrise Wind project? Thank you.
Rasmus Errboe
executiveSure, thank you, Ahmed. Regarding AR7 and the discussion that's happening right now—since we won't be taking part in it, I don't believe it's appropriate for me to delve deeply into that topic. Naturally, we're paying close attention to the dialogue currently under way within the AR7 framework. And we're also noting, for instance, the proposal being talked about concerning possibly having a CFD spanning 20 years rather than 15 years, and so forth. As I've mentioned previously in a broader remark about what's required over the long term for European offshore wind, any added predictability for developers—including on the revenue side—would, in our view, be appealing. Just as one example. On your question about Revolution Wind and Sunrise being carried out, executed as a single program, and your asking about the lessons learned, one illustration of that is the turbine installation rate. One of the difficulties I partly referenced earlier, which we encountered when we rebased the schedule for those projects, was the installation rate for the turbine, where we had to rely on a U.S.
Rasmus Errboe
executiveThe setup involves a jack-up alongside a barge, where you essentially sail one turbine out on the barge — the blades, the monopile, and so forth. After that, you install the complete turbine using a jack-up vessel. That approach isn't one we'd typically choose. So that's a case where the same method will also be applied for Sunrise. As a result, what we learn about turbine installation rates will carry over from one project to the next. For Sunrise specifically, we'll have two installation seasons spanning the winter. So, naturally, we'll also be complying with all pile banding requirements and so on. That also means the learnings — for instance, regarding turbine installation rates — will matter for Sunrise Wind too. That's one illustration of how lessons carry across projects when they're built as a single program.
Operator
operatorOur next follow-up question is from Helene Brøndbo at DNB. The floor is yours.
Helene Kvilhaug Brøndbo
analystRight, hi. I've got a follow-up question about the recent U.K. ruling on wake effects. I'd like to know how you expect that to affect your Hornsea 1 to 3 projects.
Rasmus Errboe
executiveThank you. Thanks, Helene. Yes, naturally we're tracking the ruling closely, and also the debate in the U.K. regarding wakes. I won't disclose particular figures regarding what it means for projects and so forth. My sense is that it's still quite early on this front. From what I understand of everything available out there at present, those wake effects figures get worked out by independent experts, and the estimates rest on assumptions that were known at the time, and so forth. As of now, it isn't my place to remark on what that ongoing process means for our existing projects in the west and in the east of the U.K.
Operator
operatorDominic Nash from Barclays has our next question. Go right ahead.
Dominic Nash
analystHello there. Yes, thanks. Some time back, we may have discussed Ørsted's capacity and readiness to borrow through SPVs inside projects, instead of doing all the raising at the balance sheet group level. I was just curious whether you are engaged in your debt-raising thinking as you look ahead, and whether the SPV route is something you would consider using more, and/or actually put in place. Thank you.
Trond Westlie
executiveOn that front, we’re involved in particular cases or in nations that we regard as advantageous. We’re pursuing that and examining it. In places such as Taiwan, we’ve been reviewing it because of both the projects themselves and the country risk aspect of it. Yes, we’re examining that, but more in particular cases.
Operator
operatorAnd our final question today is from Deepa Venkateswaran at Bernstein. Deepa, the floor is yours.
Deepa Venkateswaran
analystThanks. My question was going to concern your Greater Changhua project. As of right now it's 35% complete, yet you still expect COD to take place this year. I was just wondering whether that's a stretch goal, or whether there's any risk of it spilling into 2026 the way you previously flagged. Maybe you could just walk us through why the Taiwanese project can be built so quickly, even compared with other European projects, say. Thank you.
Rasmus Errboe
executiveThanks so much, Deepa. I have two questions. First, on the timeline: you're correct, and as we've mentioned, we anticipate COD from this project near the very end of 2025 — sorry. There's a risk, I'd say, that one or two turbines might slip into 2026. Again, that doesn't really affect the business case, because we'd clearly get the power as we ramp up the wind farm. It's a very different situation from, say, a project such as Revolution Wind, where the onshore substation is what's on the critical path. On your comment, which is very accurate regarding construction progress for Changhua 2b and 4, things are going quite well as of now. We're managing to install both the suction bucket jackets, which are here, and the turbines at a pretty good pace — better than we'd expected, I might add. Of course, also right now, as an example, we're seeing near-perfect weather conditions in Taiwan as of now. As part of that, obviously one of the uncertainties we have is, of course, that we don't expect that to simply continue.
Rasmus Errboe
executiveAt this moment, all the pieces are falling into place well. As you correctly note, we're building at a strong rate on these projects—a very solid installation pace.
Operator
operatorThat wraps up our question-and-answer portion, everyone. I'll now hand things back to the management team for any final comments they'd like to make.
Rasmus Errboe
executiveOkay. Thanks so much, everyone, for being with us. We always really value the chance to talk with you, and we appreciate your interest. And once again, should you have any additional questions, please don't hesitate to contact our IR team — sorry — who will be available to help with those. Thanks so much, everybody. Stay safe and have a wonderful day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ørsted A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ørsted A/S earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ørsted A/S or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.