Talen Energy Corporation (TLN) Earnings Call Transcript & Summary

May 8, 2025

NASDAQ US Utilities Independent Power and Renewable Electricity Producers earnings

Earnings Call Speaker Segments

Sergio Castro

executive
#1

Thanks, Michelle. Good day, everyone, and welcome to the Talen Energy conference call for the first quarter of 2025. Joining us today are Mac McFarland, our Chief Executive Officer; Terry Nutt, our Chief Financial Officer; and Chris Morice, our Chief Commercial Officer. Other senior Talen executives are also with us and will help field questions during the second part of today's call as needed. We put out our earnings release this morning, together with the presentation, and you can find both in the investor relations section of Talen's website, talenenergy.com. On this call, we will be making some forward-looking statements that rest on current expectations and assumptions. Actual results might differ because of risk factors and other considerations spelled out in our financial disclosures and other SEC filings. Today's discussion also refers to certain non-GAAP financial measures. In our earnings release and the appendix of our presentation, we have included information that reconciles our non-GAAP measures to the most directly comparable GAAP measures; with that, I will now hand the call over to Mac.

Mac McFarland

executive
#2

Alright, thanks Sergio, and welcome everybody to the call. We appreciate your ongoing interest in Talen Energy. Even in a market that's uncertain, our confidence in the strategic path ahead and in our investment thesis does not waver. We've seen some turbulence in the markets, and complications have arisen from tariffs and trade restrictions—take rare earth metals as one example—yet we remain dedicated to the straightforward pursuit of our business plan: keeping our focus on operations, turning our megawatts into commercial success, giving capital back to shareholders, and carrying out our growth strategy via the AWS contract at Susquehanna while applying that same approach to contracting megawatts at our remaining sites—thereby producing the greatest free cash flow per megawatt, which is the standard by which we measure ourselves; we hold the view that the long-term prospects for the IPP business, and for Talen in particular, stay strong. Our core view of power markets that continue to tighten has not changed. Our conviction regarding data center load that keeps growing has not changed. We still see Pennsylvania as a center for data center growth, and several of those convictions have actually strengthened. PPL just announced 11 GW of advanced data center development within its transmission territory, which is where our plants are located. Costs for new development and construction schedules continue to climb. Certain estimates for new CCGTs range from $2,200 up to $2,600 a kW, and uncertainty over supply chains, tariffs, and tax policy has likewise restrained renewable development. At the same time, hyperscalers continue to confirm or speed up their capital plans, and they show no indication of slowing down. Even so, when reports circulate about data-center rebalancing and soft power forwards, certain doubters have begun to challenge the core thesis for independent power producers and its connection to data centers. Our response to those doubters: our conviction is unchanged. Rebalancing means nothing more than rebalancing, and forward markets see thin trading and fail to capture the tighter power-market conditions that now define normal. Moving to slide two, our quarter was solid, supported by robust load and power prices along with excellent operations and performance from our fossil plants, Susquehanna, and the commercial team, all collaborating to produce $200 million of EBITDA and $87 million of free cash flow, surpassing our Q1 internal estimates that formed the basis of our 2025 guidance. I'd like to express gratitude to the women and men of Talen who achieved these results, working tirelessly through the winter cold snap to keep the lights on. Throughout Q1, we continued executing our share repurchase program, repurchasing $83 million in shares. Power is now flowing at the AWS Campus, and under the contract we already have in place, we're both supplying electricity and collecting revenue. AWS is continuing to develop the campus, with several buildings currently going up. We're enthusiastic about what lies ahead as we carry on performing under our present agreement within the approved 300-megawatt ISA. Our focus is on the road ahead, not on the past. We'd be glad to bring investors out to the site so they can witness the activity firsthand. Many of you are likely asking how and when we'll move past the 300 megawatts covered by our existing ISA. As I've said before, we don't talk about the commercial efforts we're pursuing. That being said, we're still sharply focused on securing the ideal answer for both our customers and Talen; but let me add one thing: the prior year ranked among the most thrilling in my whole career within the IPP sector, and I'd say Talen contributed to that. And 2025 looks set to beat last year now that the convergence of power and data centers is being proven out. Though it wasn't a Q1 item, we've lengthened the refueling outage at Susquehanna Unit 2 so we could carry out additional maintenance. We entered that outage intending to capture operational gains by recovering 27 MW via a condenser fix. We did the work and completed it; those are MW we anticipate getting back. Yet while carrying out that work, we spotted extra maintenance that we judged wise to take on during the spring stretch of cheap prices, so we stretched the outage by a bit more than 3 weeks at an added cost of about $20 million. We think this extra work will bring back megawatts beyond the 27 we'd initially targeted. All of this has us expecting payback of roughly 1.5 years at prevailing market prices as of today. That positions us nicely going forward with additional energy to sell, and in the end, this choice is the correct one to make at the correct moment. We've folded our strong first quarter results into our 2025 guidance and also factored in the extra maintenance we're performing, and because of that, we're tightening and reaffirming that guidance, while our 2026 outlook stays the same; let's go to slide three. Our read on the markets hasn't shifted. We keep seeing tighter markets, pushed by rising demand. During Q1, we observed 7 terawatt hours, roughly 3.5%, of added deliveries on a weather-adjusted basis across PJM versus the prior year; that led our fleet to be dispatched about 1.6 terawatt hours above the level in last year's same quarter. Every bit of that extra generation came from our fossil fleet, which backs our belief that energy demand will boost dispatch of our flexible fleet. As I noted, we've watched PPL announce still more data center load compared with earlier estimates from last year, and we see other demand categories getting stronger too. AI keeps advancing at a rapid clip, and hyperscalers keep lifting or reaffirming their capex plans. On top of that, cloud services and hosting activity keep posting substantial growth, as shown by multiple earnings reports issued over the recent weeks. Demand from data centers and AI are relatively new phenomena, and the markets are digesting numerous distinct data points—such as ship output and sales, lease cancellations, and fresh data center announcements amid the rebalancing I mentioned before. As we see it, there is no sign of a pullback. And while supply will eventually react to this growing demand, in the near term, steps like the ones I described to bring additional megawatts onto the grid at Susquehanna will be taken across the industry. Still, we don't expect meaningful new build to come online before late in the decade; and given tight supply chains plus tariff and trade restrictions taking effect while much equipment is sourced in Europe, new-build costs make additional supply even harder to bring forward in the near term; over the long term, we do believe supply will eventually show up in answer to market demand and signals. That said, there is some truth to the argument that present capacity pricing, along with the forward markets, fails to support new build investment and fails to reflect the tightening market. Chris will give more detail later on our hedging program showing that although we believe the forwards don't represent supply and demand fundamentals, we did seize the chance in the first quarter to add further hedges for 2026 and 2027 while the forward market was well bid. Moving to slide four, most of this came up in my opening remarks; we keep executing. AWS keeps building. We are delivering electrons and receiving dollars. And as a reminder, the plan across the year is to ramp to 120 MW; with that, I'll hand it to Terry on slide five. Terry.

Terry Nutt

executive
#3

Thanks, Mac, and good morning to everyone. Let's move on to the financial and operating results for the first quarter. From an operational standpoint, our team keeps delivering. Our fleet performed well through stretches of strong demand during the quarter, which shows the worth of having dispatchable generation. We produced 9.7 terawatt hours of power, with an equivalent forced outage factor of 1.2%. A bit under half of that generation came from our carbon-free Susquehanna nuclear facility, since our fossil fleet ran more during high-demand stretches. While runtimes at our fossil plants were higher, both our Montour and Brunner Island facilities posted significant generation increases for the quarter. Safety stays our top priority across the fleet, and our team worked safely through the busy winter run in cold conditions. Our Q1 recordable incident rate came in at just 0.4. That matches or beats our peers. Moving to slide six, I'll share a few more financial details; the year got off to a solid start, with results ahead of our estimates; we reported adjusted EBITDA of $200 million and adjusted free cash flow of $87 million. PJM weather was cold this quarter, and heating degree days in Philadelphia ran above the 10-year average. Colder-than-average temperatures in the first quarter of 2025 drove up demand, which pushed settled on-peak power prices higher than the prior year; on a comparative basis, last year's first quarter results gained significantly from roughly $165 million of realized hedge gains, while Q1 2025 included only a modest hedge impact. Our fleet delivered when called upon, as our low forced outage rate shows, and our fossil fleet produced approximately 20% more power than the same period a year earlier, even without our ERCOT assets. As you may recall from our investor day last September, earnings in the second half of 2025 will be higher thanks to the inclusion of 2025 to 2026 capacity pricing of approximately $270 a megawatt day and the Reliability Must-Run impacts at our Brandon Shores and Wagner facilities. As Mac said earlier, we are reaffirming and narrowing the 2025 guidance ranges we previously announced. The strong first-quarter performance and our expectations for the rest of the year should offset the impacts of the extended Susquehanna outage. Our narrowed Adjusted EBITDA range is $975 million to $1.125 billion, and our narrowed adjusted free cash flow range is $450 million-$540 million; near term, market uncertainty around trade restrictions and tariffs has no material effect on cost. Over the longer term, things are more uncertain as we assess tariffs and how they affect our supply chain. Our 2026 outlook is unchanged from what we disclosed at investor day last September. These ranges continue to highlight Talen's robust earnings and cash flow growth profile, which includes tripling adjusted free cash flow per share by 2026. Now on slide eight, our target remains returning 70% of adjusted free cash flow to shareholders. For excess cash, buybacks are viewed as the top priority, and we'll use that as the yardstick against which the return profile of any growth opportunity gets measured. As Mac said earlier, the equity market's pullback let us buy $83 million, roughly 452,000 shares, during the first quarter. From the beginning of 2024 through now, we've repurchased about $14 million, equal to 23% of our outstanding shares. Roughly $1 billion of buyback capacity is still available to us through year-end 2026, and the balance sheet gives us flexibility to run our program or act strategically should the right opportunities arise. Turning to slide nine, we stay committed to keeping net leverage under our three and a half times target, with ample liquidity as well. As of May 2nd, our forecasted net leverage ratio stood at about 2.6 times, comfortably beneath our target. Beyond that, liquidity is approximately $970 million, with more than $270 million of cash held on the balance sheet. During the quarter, we capitalized on falling rates by executing $550 million of interest rate swaps, and after the quarter closed we added another $150 million of swaps, which lowers our floating rate exposure and makes cash flows more predictable. With that, I'll hand the call over to Chris.

Chris Morice

executive
#4

Thanks, Terry, and good morning to everyone. Turning to slide 10, I want to draw attention to the hedging work we did over the past quarter. Our approach to hedging centers on keeping risk tolerances at suitable levels, with priority placed on safeguarding cash flows throughout our generation fleet; the graph on the left shows average around-the-clock pricing for calendar year 2026 and 2027 at PJM West Hub. Following a robust winter, prices climbed, and during that stretch our commercial team began layering in further hedges. As a reminder, our hedging approach is pragmatic rather than programmatic, and that gave the team room to add hedges when prices were higher, as the right-hand side lays out in detail. During Q1, we doubled our 2026 and 2027 hedges as prices were rising; through those moves we boosted certainty around near-term cash flows for the business while still keeping suitable exposure to the upward price fundamentals in 2027 and beyond. With that, I'll turn things back to Mac for closing remarks.

Mac McFarland

executive
#5

Thanks, Chris. It's still a thrilling period for IPP. The basics of the market are still extremely robust. Growth in data center load keeps showing up. We keep delivering on the AWS contract. All of this produces firm confidence in our investment thesis, and Talen is positioned well to power what lies ahead. We appreciate everyone's interest in Talen and for being with us on today's call. We'll now hand it back to the operator and open the line for questions.

David Arcaro

analyst
#6

Hi. Thanks so much. Good morning.

Mac McFarland

executive
#7

Morning, David.

David Arcaro

analyst
#8

I want to pick up on a few things your peers mentioned this week — one of them pointed to a shift in customer interest toward front-of-the-meter deals. I suppose I was hoping you might go into more detail about the conversations you're having right now, given the backdrop of this FERC process? In your talks as well, has there been any change in tone, strategy, or appetite for going front-of-the-meter rather than behind-the-meter?

Mac McFarland

executive
#9

Thanks. I appreciate the question. Look, I'd begin by noting that we have an existing transaction, a contract with AWS, that we're carrying out under. And as I said in my remarks earlier, we are actively delivering megawatts, receiving revenues, and so on, with construction ongoing there. Since the point, I believe, when we signed that contract, we've told people that we've been examining every different form of opportunity when it comes to powering data centers and expanding our growth strategy. And you've seen plenty of activity, obviously, beginning with FERC's denial of the ISA extension, then the technical conference, and then the continuing back-and-forth dialogue with PJM. PJM is submitting eight different alternatives and essentially allowing options for ways to power data centers. We view that as highly supportive and we continue to support that process; in working with our counterparties, we're looking at a number of different ways to get megawatts delivered quickly, because it's about speed to market, and how to contract megawatts across the fleet. So we've been working actively on that for over a year, and that's pretty much it. Cole, anything you want to add?

David Arcaro

analyst
#10

Yeah, I believe that's correct, Mac. What I mean is, back in September at our analyst day, we mentioned that throughout our fleet we're considering a range of different options. Of course, we had the Susquehanna behind-the-meter arrangement with Amazon, but a front-of-the-meter approach is clearly the right answer in plenty of situations. So we've been developing those sorts of structures for some time now. And of course, after the FERC denial in November, we've been saying, I believe, on a regular basis that we're pursuing other commercial alternatives on that front too.

Mac McFarland

executive
#11

Perhaps just one more thing, which I brought up in the opening remarks, and I believe it deserves attention. You keep hearing PPL talk about the backlog growing from nine gigawatts to 11 gigawatts, and they've kept pushing that forward. So there will be multiple solutions across the territory where we have plants, land, water, access, transmission capability, and so on, to hook up to the grid. So I believe you'll see that activity emerge. And at this point it simply comes down to how its power gets sourced and where it originates from. And PPL is actively working with PJM and considering what the transmission system is going to need. So I believe all of that signals that the customers are there and how the contractual arrangements will take shape. That is going to develop. As I said, I believe 2025 is going to be a truly exciting period when this power data center intersection gets validated.

David Arcaro

analyst
#12

Yeah, understood. No, that all sounds reasonable. Thanks for the detail. And perhaps going into where things stand right now with the FERC process and colocation, what's your view on how that will unfold going forward? Do you think there's a possibility that a settlement process could open up?

Mac McFarland

executive
#13

So, yes — and difficult to forecast, I suppose, and I don't want to lead with that. Look, the FERC process keeps changing, right? But they've stated, and Chairman Christie has stated, that they're looking to get it resolved fast. I think you saw a conference took place at the Pennsylvania PUC — again, with an interest in encouraging the capability to serve big loads, data centers, and so on, wanting to move fast, since folks recognize there's an enormous amount of economic development tied to this. Pennsylvania recognizes there is an enormous amount of economic development and wants to turn into a hub, so to speak, for data centers. And so clearly we're paying attention to this, and I believe PJM's eight options that were submitted to FERC, and then FERC seeking to settle this matter speedily — we're very supportive of that; but again, much of that FERC process, and we are involved in the FERC process. We also have a legal matter pending in the Fifth Circuit concerning our ISA, and then all the commercial work that Cole and his team are doing keeps moving forward, since there are multiple different approaches for resolving how to get data centers powered, correct? And so all of those are developing and advancing.

David Arcaro

analyst
#14

All right. That's great. Yes. I really appreciate those remarks. Many thanks.

Mac McFarland

executive
#15

Thanks a lot.

Angie Storozynski

analyst
#16

Thanks. I'd like to pick up on what was said regarding PPL. I'm looking at the PPL zone right now. From what I can tell, peak load there is roughly seven gigs, with something like 13 gigs of installed capacity in that zone. And as you mentioned, PPL shows 11 gigs of potential incremental demand. And PPL doesn't supply generation, correct? So anyone coming in from that queue has to procure electricity, and presumably a lot of them would buy it from your plants; yet you're avoiding any comment on other assets, not Susquehanna; that's my first point. And second, given that, again, the existing load plus the queue together exceed the capacity currently available in the PPL zone, would you consider possibly expanding some of your assets under long-term contracts?

Mac McFarland

executive
#17

Yeah. Like I said, our growth. Well, first off, good morning, Angie. How are you? Good to hear from you; so look, as I mentioned, our strategy when we. It was only March of last year that we signed that contract. And from that day on, we've kept moving forward; and our growth strategy centers on leveraging our platform; so let me unpack that briefly, which is how do we use a platform? We have quite a few different assets. Beyond Susquehanna, the focus has been on Susquehanna and on how we expand there, which we've always said would require a change to that contract in some form of grid to deliver the same reliability. So we've been examining that. We've been examining how we use the remaining assets in our portfolio and deliver a platform solution; so with single assets, you don't necessarily get the same risk backstop that a portfolio gives you. You don't get the same balance sheet that a portfolio of assets gives you. So we've been examining how we leverage that portfolio and leverage the work and the, I'll call it IP, if you will, lessons learned, first mover advantage, whatever you'd call the contract with AWS. We've been examining how we leverage that across the fleet. So while I won't speak specifically, I hope that gives you a sense of what we're trying to do.

Angie Storozynski

analyst
#18

And nothing to add regarding expanding existing assets. I get that you'd rather not...

Mac McFarland

executive
#19

Oh, my apologies. Sorry about that. Right. I neglected to mention there's no comment on expanding existing assets.

Angie Storozynski

analyst
#20

All right, that sounds excellent.

Mac McFarland

executive
#21

Angie, as you're aware — and I always value your questions — but I believe it's reasonable for questions to be asked, and it's equally reasonable for us to respond: "Look, we don't discuss M&A activity. We don't discuss commercial arrangements we are pursuing or not pursuing. We don't discuss MNPI — whether we possess it or don't possess it." All right? That simply isn't something we do as standard practice, since our focus is on carrying out our strategy; and whenever moments arrive when we're able to inform the market by having something completed, that's exactly what we'll do. It's purely standard practice on our part. While you're engaged in commercial activities — be they contracts, acquisitions, divestitures, anything of that sort — it serves nobody involved in that process to hold public discussion about it, because those are commercial activities, and you don't want to hand either party leverage. So as a matter of — apologies, it comes down to standard practice. Those subjects simply aren't ones we comment on.

Angie Storozynski

analyst
#22

All right, so just one final question. You've got a head start when it comes to contracting assets, if only because of Susquehanna. Granted, no one else holds a house contract, so it isn't as though you've lost it. But as time passes, do you worry that this head start—or that competitive edge—won't hold up, in the sense that the time-to-power benefit you have right now will simply disappear once your competitors announce additional deals?

Mac McFarland

executive
#23

First off, I genuinely believe we hold a first mover advantage. Hundreds of millions of dollars of infrastructure—transmission infrastructure—is sitting on the ground at Susquehanna. Hundreds of millions of dollars of buildings and other infrastructure is going in. Beneath that, we have a contract we're executing. Throughout the ramp-up, throughout billing, throughout all of it, we keep advancing what we know about powering data centers and what that looks like. Thanks to the 11-GW backlog, etc., the conversations we're having are expanding our knowledge. As I've said—and sometimes I regret it, and sometimes people enjoy throwing it back at me—I've always said I'd like to announce our second deal before somebody announces their first. I'll stick to that; that's true; but at the same time, a rising tide lifts all boats. And I think the more the industry can sign contracts and prove up this intersection, as I mentioned in my remarks, of data centers and power, and validate that, the better off the entire industry is. But we're competitive. So yes, we want to be announcing more deals and doing it before anybody else; but it's just how these things work. We could talk about complexity. We could talk about time and contracting and legalese and all that type of stuff; but at the end of the day, we are executing, and there's a lot of activity. So don't think that our lack of public discussion about what we're doing is a lack of effort or progress. Cole, anything you want to add?

Cole Muller

executive
#24

Yeah. I'll just build a bit on what was said about Susquehanna. We're a couple of years ahead, correct? Like Mac mentioned, we've got substations already in the ground, buildings that are actively drawing power, and the campus is expanding; so to keep growing that at a rapid pace, we don't have to wait for an announced next contract. And then regarding our other assets, they sit in an advantaged position, right? They've got the right characteristics: water, fiber, land, and so on. But also, as you pointed out, Angie, they're in the right location, right? There's 11 gigawatts potentially coming to this zone, whether it's contracted or not. Those assets are in a really good position, and we're able to and have been advancing opportunities to lock that in.

Mac McFarland

executive
#25

And let me just add to that, which is, I think, that Vince and the team at PPL have been very constructive. And they have a commercial mindset that is allowing data centers to flourish in their backyard, if you will. And we have a constructive relationship with them; and they also have a transmission system that can absorb a lot of these megawatts and, as they've said, not impact residential customers. So that's a big advantage. And we like the position that we're in, and we like who we're working with.

Angie Storozynski

analyst
#26

Good. Thank you.

Mac McFarland

executive
#27

Thanks, Angie.

Michael Sullivan

analyst
#28

Hey, good morning.

Mac McFarland

executive
#29

Morning, Michael.

Michael Sullivan

analyst
#30

Hey, Mac. I was hoping you could give us a bit more detail on that Susquehanna outage. I suppose the question is, how confident are we that it will be back within the next week or so? And then, regarding what's being improved here, how should we be thinking about that?

Mac McFarland

executive
#31

Yeah. Well, look, I'm glad you raised that. But from a scheduling perspective, obviously, when you head into a nuclear outage, you've got a schedule that's literally minute by minute. And that's what we've done with the extension. So mid-May is the target here. But like all things, schedules can shift. Still, we have confidence in the fix we're doing, which is that we went into the condenser and knew we had some maintenance, and that was planned; and that was to get us roughly 27 MW, which would bring us back to full capacity injection rates, which then would flow into the capacity market. But when we did the uprate over a decade ago, we actually got past that in terms of the plant's capability, that capacity injection rating. And so we identified incremental work. I could walk through the arcane engineering details of the extraction steam system between the condenser and the turbine, etc. Without getting into that, there were simply some other things we found that would further enhance, effectively, the steam flow. When we did that effective repair work, we anticipate getting incremental megawatts. That's why, when we put that in there and say the $20 million of incremental cost plus the, call it lost opportunity, albeit during a low-price environment in the spring here of the three and a half weeks, we say that we're going to get payback on that over time because we're going to get even more energy out of the system. That's the work we're doing. Hopefully, that answers your question. Happy to take a follow-up, Michael, if you have one.

Michael Sullivan

analyst
#32

Yeah. Yeah. Right, that's really useful; so it sounds like the issue is more on the generation side.

Mac McFarland

executive
#33

Yeah. No, I ought to have been much clearer on that; it's on the non — so what we do is call things the nuclear island and the non-nuclear island. It's on the non-nuclear island side of things; so essentially it comes down to balance of plant, which is how we'd put it internally.

Michael Sullivan

analyst
#34

All right, that's really useful, thanks; and my other question was — oh, apologies. Mac, did you want to say something there?

Mac McFarland

executive
#35

No. Nope. I was simply waiting for your following question.

Michael Sullivan

analyst
#36

Maybe just the degree of confidence you have now in that 2026 outlook you laid out back in September. I realize you've added a few hedges since then. Pricing keeps shifting, and now there's the cap floor structure in place for the auction that's coming.

Mac McFarland

executive
#37

Yeah. Sure. Glad to do that, and Terry ought to weigh in here too, and Chris as well. But look, I think Chris nailed it. That's actually why we included it in this presentation—we spotted a chance to add some hedges; going in and hedging isn't strictly necessary for us. We do that when we're looking at tweaking our risk tolerances. What I'd say is the market was well bid in the term market, 2026, 2027, during that first quarter cold snap, right, as Chris mentioned; so we layered in some additional hedges. But looking ahead, the backwardation in the market doesn't make sense to us, I think, is how I'd put it. If you hold that fundamental view of tightening markets, the capacity market, I think, is supported. Terry, Chris, Terry, you want to.

Terry Nutt

executive
#38

Yeah. No, Michael, to put it bluntly, we feel really good about the 2026 outlook figure. As you said before, you've watched the forwards shift. We've clearly seen the commodity market, even in just the last few days, pick up a bid in some of those out years. So our confidence there is enormous; we still need to see how the upcoming auction turns out. Depending on the result, there might even be potential upside from it. But that ties in, perhaps, with a follow-up question from you or one of your colleagues about how we view the auction. But enormous confidence.

Michael Sullivan

analyst
#39

All right. Thank you so much. I really appreciate that.

Jeremy Tonet

analyst
#40

Hello there. Good morning to you.

Mac McFarland

executive
#41

Good morning.

Jeremy Tonet

analyst
#42

I just wanted to ask about capital allocation. I realize this has come up somewhat before regarding buybacks. But I'm curious whether you could share any thoughts on how fast buybacks might go in a particular quarter? There's been a lot of volatility in share prices, correct? And I'm wondering whether free cash flow in any given quarter affects the pace, or whether there are other factors we should consider, given the volatility we've been seeing out there and how that might shape the buyback pace.

Terry Nutt

executive
#43

Yes. Jeremy, I'm glad to address that. Good morning. From a pace perspective, clearly, you can look at what we did during the first quarter as an illustration. When opportunities in the market arise, we will step in, implement our share repurchase program, and get going. In the end, the more dollars per share we can generate from a free cash flow perspective, that's ultimately our objective, correct, which is to grow free cash flow per share and grow what that means for the customers we retain. We do have some seasonality in our cash. And I'd say there's a bit of that simply because of how our debt service operates, but not to a degree that it keeps us out of the market during any quarter or any period of time; so as I said earlier, we have more than $270 million of cash on the balance sheet, ready and willing to transact when we can.

Jeremy Tonet

analyst
#44

Understood.

Mac McFarland

executive
#45

Hi, Jeremy. This is Mac. Let me just add one thing: look, I believe our proxy was filed on the 19th of March, and if you had checked the share count in it, since it's a current filing, you'd have seen — because current numbers have to go in there — that compared with the 1231 share count, we had repurchased shares. So if you look back to the early March period, that's a couple of months back, we were in the market then, and we were executing trades at that time, buybacks at that time, and we simply felt that this was a good use of capital. We've consistently said that our benchmark is to return capital to shareholders before we would pursue other alternative uses of that cash; so, as Terry said, we're there, and we will support the stock whenever we can.

Jeremy Tonet

analyst
#46

Okay, understood — that clears it up. I simply wasn't sure whether the quarter might have allowed for more, considering how volatile things were, or whether there are any constraints I should know about to make sense of that response. So I appreciate the answer.

Mac McFarland

executive
#47

I'd love it if we'd managed to repurchase a billion dollars' worth at 185. That's meant as a bit of a joke, all right? Still, there are constraints on how much volume you can handle each day and similar matters. I believe some people wrote, when we fell to around that $185 level, give or take, that this was a kind of reflection — one that didn't even purely reflect fundamentals, before you factor in power plants, before you factor in layering data centers on top of that. Look, I think we've demonstrated our willingness to execute under the capital allocation program we have, and by now we've bought back roughly $1.9 billion.

Jeremy Tonet

analyst
#48

That comes to 23% of market capitalization.

Mac McFarland

executive
#49

Right, and once more, we'll keep assessing that approach, and it remains our benchmark.

Jeremy Tonet

analyst
#50

Understood. That helps; now I'd like to turn to PJM, the market, for a moment. Now that the PJM auction calendar has been given the green light, I'm curious how you believe that shapes the incentives, I suppose, for new construction over the coming few years. How do PJM's recent approvals and fast-tracked new generation factor into this? Any views and proposals around re-regulation in Pennsylvania, given, I suppose, some of the headlines we're seeing out there?

Terry Nutt

executive
#51

Yes. So Jeremy, that question covers a great deal. Perhaps we can work through it one piece at a time. From a constructive perspective on what we're seeing, and maybe let's briefly address the capacity auction, we believe the capacity auction coming up will be very constructive. Chris made a few remarks on that near the end regarding re-regulation and policy conversations in Harrisburg and similar matters. Naturally, we support what the IPP and merchant generation sector has accomplished across the past several decades in bringing generation online. Again, whenever you examine any tightening cycle, the first supply reaction is typically, I mean, it's a highly orderly affair. You'll see incremental upgrades at existing sites first and foremost. That tends to be the cheapest form of additional generation. After that, you'll see planned retirements that end up not happening. And we've already witnessed some of that, correct? So that supply response is visible. The matter of brand-new construction is a difficult one, since you now have two auctions in which a floor and a ceiling constrain the capacity outcome. And I'd say the mix of those capacity results plus current energy prices won't deliver an adequate return on putting $2,200 into a combined cycle generation plant per kW—and, heaven forbid, $2,600 or $2,700; therefore that new build, green build development faces headwinds on that basis, even before considering whether supply chain issues come into play. Chris, would you like to add something about the capacity auction?

Mac McFarland

executive
#52

Sure. Basically, the situation remains constrained. We've received revised parameters: reliability requirements have gone up while ELCCs have come down. So there are both knowns and unknowns. Among the unknowns, demand response and wind participation will vary. It might be useful to revisit the auction. Since we're active in that space and trading bilaterally, you saw some prints come across that clearly didn't reflect where the auction cleared. As a result, the variability in price outcomes remains wide. With the collar in place, the curve is steep. And frankly, we're 1.5 to 1.6 gigs away from price in floor on outcomes. So once again, price variability is definitely heightened. Even so, considering the underlying fundamentals, conditions remain constrained and continue to appear so. Chris, in the bilateral market, where are you observing trades for 2026 and 2027? Perhaps that comes to $6.27.

Chris Morice

executive
#53

Yes. Once more, the picture varies. Following the most recent auction, roughly 300 prints came through; we are observing a somewhat different mix of three-year strips and two-year strips, with consideration of a high clear this year alongside some uncertainty in the back half. So once again, every indicator remains fairly constructive, though there are certainly some unknown variables regarding wind and DR that could affect that.

Jeremy Tonet

analyst
#54

Understood. That's really useful. I'll stop here. Thank you.

Terry Nutt

executive
#55

Thank you, Jeremy.

Julian Smith

analyst
#56

Hi, good morning, everyone. Thanks so much for making the time — I really appreciate it. Perhaps just to build on — hey, Mac, thanks. So maybe I'll just pick up a bit on that question Mr. Sullivan raised earlier. Could I dig a little further into the non-nuclear island? What precisely are you upgrading there? If you could give me a bit more detail. I mean, is it related to the blades, or where do things stand with the generator blades?

Julian Dumoulin-Smith

analyst
#57

No. What it is, is the extraction steam system that runs off the turbine, and from there the steam ultimately travels down into the condenser; we already knew there was work to do in the condenser — that accounts for the 27 megawatts we're discussing — but as you moved up river, so to speak, back in the direction of the turbine, there was some extra repair work and incremental maintenance on a few of the piping runs, essentially. So it comes down to the extraction steam system. That's really all it is. And when we carry out that incremental work, what it does is, to put it in layman's terms — I'm an engineer, though I stopped doing that roughly 30 years ago — it tightens the flow of the steam. And by doing that, using the same fuel, you extract more energy from the system. Got it. Okay. So is it the turbine blades and the generator system? It isn't. No, it's not the turbine. It's not the turbine.

Julian Smith

analyst
#58

Great.

Mac McFarland

executive
#59

I'm glad you asked that follow-up, because I should have made it clearer.

Julian Smith

analyst
#60

I appreciate you bringing that up several times.

Mac McFarland

executive
#61

Right. The turbine isn't the issue — it's the component around it.

Julian Smith

analyst
#62

Great, and correct. So because of that, your level of confidence regarding when the outage will be resolved and so on — I believe you mentioned it's about a week out at this point, and that confidence is quite high.

Mac McFarland

executive
#63

Yes. Well, I'd say heading into it, yeah. Again, you assemble the timelines, and you put together the best version of them using the best information you have. Still, we're feeling good about the mid-May timeframe.

Julian Dumoulin-Smith

analyst
#64

Got it. All right. Yeah. I don't want to press you too much on that. I appreciate it. All right. Great. All right. If I could turn things in a slightly different direction. I mean, Montour is a fascinating asset that you own. Obviously, a lot of attention is focused on your Susquehanna site, and there's a certain amount of proximity. How do you think about the concept of additionality in this case? I mean, some of your peers have weighed in on this, and certainly, you have an intriguing potential player in this area. Once more, I don't want to dig into what your commercial arrangements are, and I'm doing my best to consider how broadly you're viewing what might be coming down the road, particularly with all the increasing talk around additionality. Look, this is something I've brought up before: when I consider the markets and how they're tightening, I tend to break things out into a near-term view, a mid-term view, and a longer-term view. Also, in the short run—and I've mentioned this previously—what we've got is being confirmed by our numbers, since comparing Montour's runtimes with twelve months ago shows the system holds ample energy. Over the coming five years, our real task amounts to addressing a capacity problem that lasts between twenty and forty hours. So I believe that's the point where the industry has begun discussing how we address that 20 to 40 hours, and we have sufficient energy there. Regarding additionality, I think what you're saying—and I hope I've understood correctly—is that you mean additionality in terms of incremental megawatts or plants coming online. Yes; that falls at the end of the decade, in that following five-year stretch, 30 to 35; that's the time when we'll require new energy and capacity. From my perspective, there's a capacity shortfall—again, only 20 to 40 hours over the coming five years. With data center demand arriving, extra megawatts will need to be added; that's simply the reality of load growth. As I said, this is an exciting period because the industry is once more experiencing load growth, something that particularly hasn't happened in the Northeast. In the Gulf States—Texas, Louisiana, and so on—you've seen fairly substantial load growth driven by industrial demand; but data center demand reaching the Northeast, and Pennsylvania specifically, is what we're excited about. Still, yes, extra megawatts will need to be added. But once more, my view is that we're talking about a 2030 to 2035 window, provided that we—both as an industry and as a load—are able to address those 20 to 40 hours per year. And my belief is that demand response can get us there—say, by sourcing incremental energy from the megawatts already in place, which we're currently studying and actively chasing, be it installed capacity or capacity presently installed across the fleet. So on the subject of additionality, I'd say that's a discussion worth having, though in my opinion it's one for the later years. And again, as I said at the start, those construction costs continue to climb. Others have quoted a range of $2,200-$2,600 per kW, and it makes no difference whether it's greenfield or brownfield. What I mean is, costs are climbing due to materials and so forth, and there's a long lead time. Consequently, today's markets don't support that. So once again, we have pricing and megawatts at present, and for a great deal of this data center load it's about speed to market. It's about producing it now. Yet we still must resolve this short-term 20 to 40 hours a year problem. And I believe we, as an industry, are capable of doing so.

Julian Smith

analyst
#65

Yep. Absolutely. But just to set expectations regarding your portfolio here, again, I know you're racing to get this second deal completed; it wouldn't necessarily center on incremental megawatts at the Montour site or whatever. If I understand you correctly, that would focus on using the capacity we already have in a more conventional way.

Mac McFarland

executive
#66

I believe there are several ways to deliver power to data centers.

Julian Smith

analyst
#67

Understood. Very well, sir. Best of luck. I’ll be seeing you shortly.

Mac McFarland

executive
#68

All right. Julian.

Ross Fowler

analyst
#69

Good morning, Terry. Morning, Mac. How's everything? So for the first question, is there anything new regarding the Fifth Circuit litigation over the ISA, or are things just where they were?

Mac McFarland

executive
#70

Hey, John. Do you want to handle that, John, or should our General Counsel?

Analyst

analyst
#71

I'm glad to handle that one, Ross. We've been keeping an eye on it. Just a moment. Something else is on my mind. Give me a couple of seconds to work through it. Right. So, here's where things stand: the Fifth Circuit process is moving forward. Within the next 2 weeks, the briefing schedule should be issued; that appeal involves quite a few technical questions. And I don't want to put everyone to sleep with the legal technicalities. But the bottom line is that the FERC ruling hinged on theoretical worries regarding non-conforming provisions as applied to hypothetical future transactions. And our view is that FERC ought to have looked at our transaction rather than future transactions that may or may not happen. So that process will unfold over the next several months at the Fifth Circuit; and as Mac has noted more than once, we're handling that alongside other efforts.

Mac McFarland

executive
#72

So, Ross, let me add a bit of extra color on that. That option is being pursued since we felt the denial of the ISA incremental to 960 from 300 — which, incidentally, had been approved, amended, and approved, and then denied — was denied without prejudice, meaning no reasoning or argument was given for the denial. And what our Fifth Circuit case essentially seeks is to ask FERC, through the legal process, to state why — in layman's terms, not legal jargon — to essentially give a reasoned argument for why it was denied, because we believed that was the prudent course.

Ross Fowler

analyst
#73

That's totally clear. Then, building on what Julian asked and perhaps what Angie asked as well—I realize you won't address individual assets, and I realize we've kind of worn out the additionality topic; but when I think it through, you now have that AWS agreement tied to a nuclear facility on a co-located basis. When you shift that perspective from a 30,000-foot level over to natural gas, what strategic considerations or risk-related factors, the big-picture items, are on your mind regarding how a natural gas plant setup would need to operate differently than a nuclear one?

Mac McFarland

executive
#74

Yeah. Once more, I'll return to the reason it's so thrilling to be in the IPP space at this moment. If you look back—for those of us who can—a couple of decades to the early 2000s, trading floors weren't only handling real-time spot and, say, balance-of-month, balance-of-week, and so forth; there was also origination, meaning longer-dated contracting; and that capability has deteriorated considerably, alright, across the industry. Clearly, we're rebuilding it. And when you think it through, the behind-the-meter transaction, AWS, or any of the other solutions under consideration for how we power data centers are essentially origination structured-style transactions. To accomplish that, in my view, you need a platform such as the one Talen possesses, which is a trading floor, the capacity to source and contract for gas, schedule gas, be able to grasp the risks tied to it, being able to backstop. Suppose you went and sold, for instance—this is just an example. Suppose you went and sold a long-term contract off a single gas unit; that carries risk built into it for the counterparty and for the structure should that unit go down. Yet if that unit goes down and you have incremental megawatts throughout a fleet, you can portfolio that risk and backstop it; we're enthusiastic about Talen's platform for finding creative solutions and returning to the realm of origination and structuring where you had contracts for CNI, which—if you consider the Amazon contract—is a CNI-type customer; it simply happens to resemble an aluminum smelter operating 24 by 7. But those contracts ran one, three, five, seven, occasionally even 10 years or longer, similar to our AWS contract. Cole, do you want to chime in on this?

Julian Smith

analyst
#75

Yeah, so look, I mean, regarding how gas really differs from nuclear, if I can address that directly, I think we've been working on two broad categories, one fiscal and one financial. And one is simply the reliability dimension, right? We mention that Susquehanna has one unit backing up the other under our present behind-the-meter setup. And I think we've referred back to our analyst day last year. We've been saying a gas deal probably looks different. Grid support of some kind is required given the reliability features and so forth, so we'd already been developing this kind of arrangement long before FERC turned us down in November, and we have some ideas there as we engage with counterparties. Then on the economic front, it really comes down to price risk, correct? Clearly, with a long-term contract there's gas commodity risk, and the question is who warehouses it. There are various structures for handling that. As Mac was alluding to, we're certainly built to warehouse the right risk and manage it for the right return. That's where things stand in our talks with counterparties.

Mac McFarland

executive
#76

Yeah. That's a good point, since when we talk about things like warehouse risk, what we mean is handling it on behalf of our customers—and we believe we're well positioned to do that. Our balance sheet is strong. Beyond Susquehanna, we hold a diverse set of assets that lets us do that. So when people begin raising questions about—and by the way, front-of-the-meter is just shorthand on our part. Nobody has actually defined what front-of-the-meter or front-of-the-meter gas means. Yet when we treat that as a broad overarching idea, it implies someone must essentially act as a retail provider capable of delivering a complete solution across long-term managed risk while earning a suitable return. We are pleased with how we are positioned in that regard, and likewise with how we and our assets are situated.

David Arcaro

analyst
#77

Yeah. That's a really thorough response. And Mac, I'll put it this way — sadly, I'm old enough, or perhaps luckily, I'm old enough to take a break. Look after yourselves, everyone. Thanks.

Mac McFarland

executive
#78

That's a shame, I reckon. I'm going to believe it. But anyway, yes.

David Arcaro

analyst
#79

Ross, you're among friends here. Take care, everyone.

Craig Shere

analyst
#80

Morning. Appreciate you taking the questions.

Michael Sullivan

analyst
#81

Hi, Craig. Morning.

Mac McFarland

executive
#82

To go a bit deeper on what Angie raised about gas-fired and Julian's Montour question: a major midstream player has announced some fast-paced greenfield simple cycle data center builds that appear set to come online within the next 2 years. How do you square that with your 2030 to 2035 additionality timeline, since your remarks center more on efficient CCGTs, yet data centers seem content with what looks like endless simple cycle backup — does that alter your math in any way? No, not really, Craig. What I'd say is there's an interesting parallel from the shale boom. I don't know, perhaps 10, 15 years back, just after 2009 and 2010, back in 2008 when the forward strip traded at $11/MMBtu, West Texas had an electricity problem. Plenty of upstream folks said they were putting trailer 18-wheeler-mounted CAT systems out there to power rigs, pumps, compressors and the like. I see that as somewhat of a parallel. There was a data center, I believe in Memphis, that got dropped in, and some reciprocating machines were dropped in beside it — probably the least efficient option, but it delivered speed to market. All of that falls within the range of solutions for figuring out how to power data centers, so I don't view it as inconsistent. My remarks about 20, but you can do that at a smaller scale; once you're talking gigs, that's when I meant 2030 to 2035 for the CCGTs. Cole, Terry?

Terry Nutt

executive
#83

Yeah. No, Mac, I believe you've nailed it; it comes down to scale, correct? When you consider that technology and what it can be applied to, scale and size are significant, and then there's also the matter of what serves as your backup for it, and whether or not it's connected to the grid. I think that matters.

Mac McFarland

executive
#84

And another point on that. Look, other firms will discover pockets of opportunity to build in the near term for speed to market. Speed to market is already an advantage for us thanks to our existing assets, right? So we already have high heat rate machines, or higher heat rate machines, in Montour and certain other assets; so adding more of that just wouldn't be a natural fit for us. If anything, it would be adding the high-efficiency machines over the longer term. Yeah. Exactly, and again, I think, Craig, it comes back to this: it's going to take a portfolio to provide a portfolio of solutions.

Craig Shere

analyst
#85

Got it. Turning slightly to the auction and front-of-the-meter, it sounded like an industry peer expected meaningful demand response growth in the coming auction, which could open the door to more front-of-the-meter PPA solutions by essentially shaving peaks and letting IPPs access their unused gas-fired capacity. Would you share that view, both on how the front-of-the-meter market is progressing and on the pending auction?

Mac McFarland

executive
#86

Craig, what I believe you're getting at is a chorus that keeps getting bigger, and we've taken a fair number of trips down to DC and given thought to how that intersection functions with regard to — and without going into those private conversations — I think it's something across the industry that people are examining and saying, "Through backup generators, we have emergency response capability," just like the backup generators at your house. I'm not saying we should go out and aggregate every one of those, but it could be one way to address things that are large in size, and as I described, people are examining how to tackle this 20 to 40-hour issue rather than necessarily boiling the ocean and pursuing a bunch of new build when supply chains, etc., are a factor, when we have energy as Cole just mentioned — we have energy capacity at Montour. Three years ago we were running Montour at 7%, and in the first quarter we're now running it at 46%. It can ramp up, and it's a gas unit. Perhaps it operates at a 10-heat rate, making it less efficient, yet it reaches the market fast. It has the ability to ramp up, but it cannot address those 20 to 40 hours since that time was already included in the 20 to 40 hours. So when it comes to demand response and the capacity to handle that, we believe it needs to be — again, that's atrophy because the need wasn't there. We believe it has to return. Those muscles must be rebuilt, and we need solid rules within PJM governing how that functions, and we need to consider how we integrate that across the load, so to speak. Yet doing that doesn't let you alter how dependable the load is. Consider data centers and the demand they place—who really knows what they're up to? You can't dial back their load while they're carrying out, say, DOD operations, or work on behalf of hospitals, and so on. That's simply not an option. Still, we have to work out how to bring that together and fix this 20 to 40-hour problem system-wide over the coming five years. Right now I mean PJM specifically. Great, thank you. Hope that's useful. Hope it was very useful. Yes. Yeah, I believe we're nearly out of time. Do we have one more question?

Durgesh Chopra

analyst
#87

Morning, and thanks for fitting me in. I just wanted a quick clarification regarding the FERC PJM discussion from earlier in this call. So clearly, one of your peers has requested a settlement in the settlement talks between the parties. I'd just like your views on that, Mac and Terry. Apologies if this came up earlier during a couple of calls this morning, but I'd just like your take on the settlement. You spoke with Vistra yesterday. Their view was that a settlement actually delays the decision even more; so any thoughts you can share on that, and how do you see this unfolding?

Mac McFarland

executive
#88

Look, we weren't a party to the show-cause order; it was rejected, or rather firmly rejected, by PJM, and we aren't advocating for that show-cause order, nor did we, and so PJM has pushed back on it. In our view, the normal process of what's happening at present, absent that show-cause order, is the most effective route to reaching a resolution.

Durgesh Chopra

analyst
#89

And thank you, Mac, if I may. Also, on that point there isn't a timeline, correct? I mean, obviously you'd want a decision made as fast as possible, but FERC faces no time constraint—no fixed schedule exists for when FERC has to act.

Mac McFarland

executive
#90

No explicit timeline exists, but if you hear the White House, if you hear Chairman Christie, everyone is saying, "We need to figure out the AI dominance," which means data centers, which means we need to figure out this solution; so in practical terms, there's an overall guiding principle to solve this sooner rather than later. And so it's simply going to need to take its course. Again, we want to keep pursuing that because we believe that the eight options that PJM put forth need to be preserved; but that is not stopping us with respect to our other activities on the commercial front.

Durgesh Chopra

analyst
#91

Thanks a lot. I truly appreciate you making the time.

Mac McFarland

executive
#92

All right. Thank you, Durgesh. Wonderful. And thank you, everyone, for being with us today and for continuing to support Talen. Have a wonderful day.

Operator

operator
#93

This concludes today's conference call. Thank you for participating. You may now disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Talen Energy Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Talen Energy Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Talen Energy Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.