WhiteFiber, Inc. (WYFI) Earnings Call Transcript & Summary
November 10, 2026
Earnings Call Speaker Segments
Analyst
analystHi everyone, and welcome to White Fiber's third-quarter 2026 earnings conference call. Thanks for being with us this afternoon; we'll start with prepared remarks from management, and after that we'll open things up for a question-and-answer session. If you'd like to ask a question during the Q&A, just press star one on your telephone keypad. And a reminder that today's conference is being recorded. At this point I'd like to hand the call over to your host, Cameron Schnier, Senior Vice President of Capital Markets and Corporate Strategy at White Fiber. Cameron, over to you.
Cameron Schnier
executiveThanks, and welcome everyone to the White Fiber third-quarter 2026 earnings call. With me today are Sam Tabar, our Chief Executive Officer, and Justin You, our Chief Financial Officer. Before we get started, I want to remind everyone that certain statements we make today are forward-looking in nature and subject to risks and uncertainties that could cause actual results to differ materially. Those risks and uncertainties include, but are not limited to, the factors described in today's earnings press release, in our Form 10-Q for the quarter ended September 30, 2026, which was filed today, and in other filings we make with the SEC from time to time. Our remarks today may also include non-GAAP financial measures. You can find reconciliations to the most directly comparable GAAP measures in our Form 10-Q and in the earnings press release posted on our website. After our prepared remarks, we'll open the call for questions. With that, I'll hand things over to Sam to discuss our performance. Sam?
Sam Tabar
executiveThanks, Cam. And thank you all for being here. At NC-1, we've hit two key milestones. First, the full 40 megawatts of contracted IT capacity is now up and running, and billing has started on the entire contracted capacity. As a reminder, that contract is worth roughly $865 million across 10 years. Second, we've closed a $300 million secured credit facility for the project. Third, since the last earnings call, we've also signed over $700 million in new cloud services contract value. That figure includes our first capital-light managed services agreements. Meanwhile, demand keeps strengthening materially for our next North Carolina sites, NC-2 and NC-3. Taken together, these developments leave us with a stronger foundation for growth in 2027. Our priority right now is execution: getting signed contracts operational, securing the capital behind them, and choosing our upcoming investments carefully. I'll start with NC-1. Completing this project marks a significant milestone. It proves our retrofit approach can deliver sophisticated AI infrastructure at scale. Even with the difficulties, we commissioned 40 megawatts of IT capacity in less than 11 months. Getting to full billing took more time than we expected. Let me explain why. Middle East conflict-related shipping problems delayed our original switchgear. To maintain momentum, we procured substitute equipment and modified the electrical design. Our team subsequently had to resolve integration and commissioning problems involving that equipment. Metering for the first 20-megawatt hall began in the middle of August. A software problem with the switchgear subsequently cut off service and invoicing. Service and billing were both restored on September 23rd. Further switchgear commissioning problems delayed the second hall, including the last 5 megawatts. As a result, the full contracted billing came in later than we had anticipated back in August. The issue with that final capacity has since been fixed. Full billing for the second 20-megawatt hall commenced on November 9th. Under the contract, all 40 megawatts are now being billed. Importantly, we do not expect late delivery penalties related to these matters; we anticipate development costs will come in slightly below $9 million per gross megawatt. That's inside the $7 to $9 million range we originally budgeted. Site acquisition cost isn't included in that figure, and it's net of non-recurring costs funded by customers. With NC-1, we've got an established US operating base plus a development model to build on. Lessons from procurement, testing, and commissioning are being applied to NC-2 and NC-3. We closed the $60 million purchase of those two Yadkin County sites recently; in our view, they fit our retrofit strategy exceptionally well. Existing industrial buildings, an on-site substation, and valuable electrical infrastructure are part of the package; we expect at least 60 megawatts of initial gross utility capacity. They also sit roughly 55 miles away from NC-1. That means we could tap our existing workforce and regional resources to support development and operations; these sites show why we favor retrofits. Having existing buildings and electrical infrastructure in place gives us a running start; versus constructing from scratch, those can compress delivery schedules and lower both construction and permitting risk. One of our strengths is locating sites that carry these advantages. The interest from customers that we are observing backs up our confidence in this acquisition. We see a chance to convert this infrastructure into assets that produce cash for many years; our target is initial capacity in late 2027. NC-2 and NC-3 are both already zoned for data center use, and that eliminates a significant hurdle. Getting these projects over the finish line will continue to depend on whether power is available, on customers following through on their commitments, on financing, and on the approvals that are still outstanding. In Madison, we're also applying the community engagement know-how we've built up. Having solid local relationships is essential to the way we bring these projects forward. All over North Carolina — sorry — throughout North Carolina, we're in late-stage talks with customers for approximately 105 megawatts of gross capacity to be delivered in 2027. That number covers roughly 45 megawatts of expansion at NC-1, together with 60 megawatts across NC-2 and 3. Demand for NC-2 and NC-3 is far more robust than it was twelve months back when we took the initial phase of NC-1 to market. We now have a broad array of interested buyers, a larger number of non-binding letters of intent, and stronger potential counterparties. Some of these proposals come to us straight from investment-grade counterparties. Others come with investment-grade credit support, which gives us more flexibility in choosing agreements that we can finance and deliver successfully. Interest is also expanding past AI infrastructure providers. We are receiving direct interest from Fortune 100 companies for deployments under 50 megawatts, along with smaller purpose-built projects. Market sentiment has been soft, but the customer demand we see continues to rise. Enterprises increasingly seek purpose-built infrastructure to support their own AI initiatives. We're additionally observing possibilities connected to demand from government entities. As time goes on, we anticipate that enterprise and public sector clients will represent a bigger portion of the market; such customers desire dedicated compute capacity, command over sensitive data, and infrastructure sited within particular jurisdictions. Through our colocation, cloud, and managed service operations, we have several avenues for addressing those requirements. What we learned at NC-1 has further refined how we handle these new projects. At the project level, we insist on investment-grade credit, obtained either straight from the customer or via a full credit wrap; from the very beginning, we structure customer agreements and financing in tandem. Our goal is to reach delivery in 2027 at a fast pace, yet we won't compromise on those standards—even when doing so shifts the delivery date. Since power is getting harder to obtain, what counts more is whether a site offers potential capacity or power that can truly be used to serve a customer. In our view, electrical infrastructure already in place, paired with a believable delivery schedule, will keep gaining value. Over the last year, development costs have gone up. Still, under our present budgets, the pricing and terms contained in customer proposals would cover those increases with room to spare. That opens the chance to earn better yields on development costs than we did at NC-1. We also take financing costs and terms into account. In the end, whatever agreements we sign will be shaped by the return we earn on the capital we put in. As we look further out, we're getting ready to bring a lot more infrastructure online in 2028 and after. We're moving sites and power forward, making our teams and systems stronger, and working out financing options. Our aim is to be prepared for the right opportunities, while retaining flexibility on when we invest capital and how much. Moving to Canada, MTL-2 will be the home of the Prime Intellect deployment we announced last quarter. That agreement spans 576 Vera Rubin GPUs across the initial three-year term. This marks our first deployment that brings together our own data center and our cloud services. Completing the facility will take a budget of roughly $25 million. Development debt is accessible via our Royal Bank of Canada facility. We're aiming for the facility to be ready in early 2027, before GPU services begin in the second quarter. By joining facility design with GPU deployments, we gain greater control over delivery and operations. Most of the new data center capacity we add near term will keep serving pure colocation customers. We'll pair our facilities with cloud services selectively in cases where the economics make sense. Having ownership of facilities also leaves us with more options once GPU contracts expire. If there's spare capacity, we have the option to shift equipment there so it keeps earning revenue across a longer lifespan; it also lets us serve nearer-term needs when prices look good. Over at MTL-2, we're exploring behind-the-meter power solutions that could add capacity sooner.
Sam Tabar
executiveOn the utility side, we're still working to expand across our Montreal portfolio. Moving on to cloud services, we continue to turn demand into bigger multi-year deals. Since our last earnings call, we've signed about $750 million in new contract value with five customers. Those contracts span dedicated GPU services as well as managed services. They involve IG counterparties, new customers, and larger commitments from existing ones. They also give us a cloud presence in Sydney and Dublin. In each case, it's customer demand that's driving our expansion there. The new dedicated compute agreements run for an average of roughly 4.2 years and cover approximately 13,000 GPUs. With that, our total under-signed dedicated compute contracts now stand at around 20,000 GPUs. The fresh rollouts are set to go live somewhere between the tail end of Q4 and Q2 of 2027. When the cloud services agreements we've already signed are completely rolled out, we anticipate they'll produce roughly $365 million in yearly revenue. By the middle of 2027, we're aiming for that run rate. Timing hinges on equipment and data center availability, customer sign-off, and financing. Given the plan we're working to right now, Q4 cloud revenue should come in approximately level with Q3's $18.1 million. Continued growth in recurring services ought to make up for the one-time termination fee we booked in Q3. After that, we anticipate substantial quarter-over-quarter growth in Q1 and Q2 of 2027 as the contracted rollouts go live. Demand for compute is the strongest we’ve ever seen, and the pool of potential customers is wide-ranging, which gives us options. Our top priority is fulfilling the agreements already in place. When it comes to new deployments, we seek the right mix of customer credit quality, data center readiness, financing, and returns. We assess every deal so that it generates an acceptable return over the initial contract term. Whatever value we later derive from the equipment is extra upside. To reduce the capital White Fiber must put in, we rely on customer prepayments and equipment financing; for signed, dedicated compute deployments that haven’t yet begun service, contracted prepayment covers roughly 40% of estimated CapEx. How that funding is timed matters just as much as its size. Our goal is to have cash on hand whenever equipment prepayments are due. In conversations with new customers, we're also seeing proposed arrangements in which they would cover as much as 100% of deployment costs in advance. I'd also like to give you an update on the GPU deployments in Paris that we announced earlier. Problems with deliveries from the original equipment manufacturer caused us to switch suppliers, and that pushed the deployment back. The facility itself is ready, and we've received a full year of customer prepayments. Our target is to begin initial service in January and complete full deployment in February; we don't anticipate any customer penalties tied to this delay. Managed services is growing into a key element of our growth strategy. The opportunities we talked about on earlier calls are now becoming signed multi-year agreements. We have executed four managed services contracts whose combined value comes to roughly $58 million. When those are completely rolled out, we anticipate they will produce approximately $15 million of annual recurring revenue. These contracts carry an average initial duration of 3.9 years. Based on the pipeline as it stands now, we expect managed services to exceed $50 million in annualized recurring revenue by the end of the first quarter of 2027 — provided we execute the additional contracts and bring those deployments into service. The model is straightforward. The customer bears the cost of the hardware and the data center capacity, and White Fiber takes care of deployment, management, and operation of the infrastructure. Raising debt or equity to fund those assets isn't something we need to do. Nor do we need to take on equipment debt or bear the risk of what the hardware will be worth once the contract ends. Upfront deployment charges can be part of our agreements, covering implementation costs and delivering a margin. After that, we earn recurring fees for management and operations; these services leverage the engineering team, systems, and support capabilities already in place. More deployments will demand additional resources, but we anticipate revenue growing much faster than operating costs. That ought to underpin very high incremental margins along with meaningful cash generation. Pricing on our initial agreements sits at the lower end of the range we're targeting. As we establish a delivery track record, we see chances to command higher fees on new engagements. Those fees will hinge on the scope of work and the operating requirements. We're directing more commercial effort toward managed services. We also keep pursuing dedicated GPU services selectively, in cases where customer commitments, returns, and financing make for attractive economics. In September, we commercially launched White Fiber Continuum. Continuum links separate data centers together so they operate as one logical GPU cluster; this lets customers grow past the power and space that a single site can offer. The early response from prospective customers has been encouraging. With power getting harder to secure at any one location, we believe that combining capacity across sites will only grow more valuable. I'll now hand the call to our CFO, Justin, to go over the financial results. Justin?
Justin You
executiveAppreciate that, Sam. For Q3, revenue reached $24 million — up 19% compared with the same period last year — and colocation revenue drove that, climbing more than threefold to $5.6 million. That improvement came from Montreal number 3, which had no billing in place a year earlier, plus the initial contribution out of NC-1. Cloud revenue totaled $18.1 million, including $3.4 million connected to the customer termination we discussed before. Strip that figure out and cloud revenue dropped about 18% year over year, mirroring the move away from that customer toward new deployments set to begin service across the coming quarters. NC-1 added $1.1 million of lease revenue in the quarter, starting when the first 20-megawatt data hall went into service on September 23rd. Billings and installation fees that came earlier are deferred and recognized across the lease terms. Gross profit, excluding depreciation and amortization, was $13.7 million, a margin of approximately 57 million 15 57%, versus 59% last quarter, mainly because the termination fee was smaller. G&A fees were $18 million, down 16% year over year. That figure included $3.8 million of share-based compensation. Lower consulting and transition service fee were partly offset by start-up costs that cannot be capitalized. Adjusted EBITDA was approximately break-even, versus positive $2.3 million in prior-year quarter. Looking at it quarter over quarter, the results were shaped by a reduced termination fee as well as start-up expenses at deployments that aren't bringing in revenue yet. We posted a net loss of $101.4 million. That figure includes an $80.8 million induced conversion expense tied to our August repurchase of convertible notes, and that item is left out of adjusted EBITDA. Turning to liquidity, we ended September holding $138.5 million in cash and cash equivalents, along with $9 million in restricted cash. Deferred revenue, which is mostly customer prepayments, came to $306 million, compared with $80 million at year-end. During August we issued $310 million of 5% convertible notes maturing in 2032, and we applied a portion of those proceeds to retire the bulk of our 2031 notes, producing roughly $180 million net. Additionally, we kept our rights under the January zero strike call, which allow us to receive roughly 5.9 million shares, subject to the terms. Following the end of the quarter, borrowing under the digital facility hit $100 million; we finished the $60 million purchase of the NC-2 and NC-3 data center and signed a $300 million secured credit facility for NC-1. The initial funding is anticipated later in November or during December, subject to an extension the borrower and lenders may mutually agree upon and to the remaining funding conditions being satisfied. Moving to contracted revenue, remaining performance obligations stood at $729 million as of September 30. In the quarter, we determined that some colocation agreements — among them Montreal 3 and NC-1 — count as leases for accounting purposes. Those leases' future payments are left out of that number. At quarter-end, the payments still due under them come to roughly $421 million. That number leaves out the second 20 megawatt at NC-1, since as of September 30 that lease had not yet started. I'll now hand the call back to Sam. Sam?
Sam Tabar
executiveThank you, Justin. Ahead of taking questions, I want to give everyone some context on the NC-1 financing. For White Fiber, putting this $300 million facility under signature represents a significant milestone. It required more time than we had anticipated, yet it positions us far better to finance the coming stage of growth. After funding occurs, this facility will allow us to recoup a portion of the capital we put into NC-1. That capital can subsequently be deployed toward our upcoming projects. This is our intended approach to scaling: secure project debt from the start, contribute equity alongside it, build out the infrastructure, and then recycle that equity into later deployments. With full contracted billing now in place at NC-1, that provides us a stronger foundation for growth; we've guided an existing industrial site through a complicated retrofit, customer delivery, and institutional financing in under a year. That's the model we're building on. We're taking that experience into NC-2 and 3; we're putting customer agreements and financing together from the outset. We understand more clearly what lenders need and how to incorporate those needs into our upcoming leases. clears throat The capital raised in August gives us room to keep moving the business forward through this process; it also made us less reliant on being able to access the markets at any given moment. Adding the NC-1 facility gives us more leverage in selecting what we invest in next and timing those commitments. Conditions in the market have been tough. Shares of AI infrastructure companies, ours among them, have dropped considerably. We recognize shareholders have felt that pain, and we do not treat it lightly. As we see it, the opportunity in front of us has only grown. Our signed cloud business is bigger. Interest from customers in our upcoming North Carolina developments is wider and more robust. Managed services offers us an additional route to expand recurring revenue, with the prospect of very strong incremental margins, while the underlying infrastructure is paid for by customers. Constructing and running this infrastructure is not easy. In this industry, operators will increasingly be set apart by their capacity to resolve issues and follow through. Today our platform is stronger, and the road before us is clearer. Delivering on business we have already signed comes first for us. With demand this strong, we have options regarding next steps. We will chase opportunities in which customer quality, returns, and financing all align; we are getting ready for more scale while retaining control over how fast we invest. White Fiber's foundation, in our view, is stronger and its growth prospects are better than they have ever been. What we must do now is convert that foundation into results, bring contracted capacity into service, turn it into recurring cash flow, and reinvest capital in attractive new opportunities. That is the approach we’ll use to create enduring value for shareholders. Now we’ll begin the Q&A portion. White Fiber President Billy Krasnokutsky and Michael Francisco, Vice President of White Fiber Cloud US, have also joined us to take questions. Operator, please open the line. Hello, Nick.
Nick Giles
analystGreat. Hi, everyone. Thanks for taking my questions. First, I just wanted to ask — given some of the supply chain issues at NC-1, what are the learnings from that, and what steps are you taking to de-risk the supply chain as we think about NC-2 and NC-3? Just any color on how much is already on order, that would be great. Thanks.
Sam Tabar
executiveBilly, the president of White Fiber, who's on the front lines of that, is going to take that question. Billy?
Billy Krasnokutsky
analystThank you, Sam. Hello, Nick. The construction schedule for NC-1 was extremely tight. Completing a project of that size in 10 months and a couple of days was a massive achievement for our team, even with the supply chain problems. What we took away from it: for comparable projects, the timeline and scope will be somewhat longer — getting long-lead item equipment ordered a bit further ahead of time, and making the project management team stronger both internally and externally with our contractors and subcontractors. The playbook we've talked about over the last few months is the very same one we intend to use on NC-2 and on NC-3.
Nick Giles
analystUnderstood. No, I appreciate you explaining that.
Sam Tabar
executiveI think it's also worth pointing out that there's considerable synergy between what we accomplished at NC-1 and NC-2 and 3. We're drawing on the same workforce and GC and so forth; the difference is that we can take many lessons from NC-1 and apply them straight away just 55 miles away at NC-2 and 3.
Nick Giles
analystAbsolutely. No, that makes sense, guys. Appreciate it. Then it's good to see the financing progress at NC-1. I guess my question was just how much capital would you intend to recycle from NC-1 as kind of equity for NC-2 and 3?
Sam Tabar
executiveCam, do you want to take that?
Cameron Schnier
executiveNick, I’m not sure we can give you an exact number on that. As you can probably imagine, most of the net proceeds from the facility we announced would be set aside for expanding the whole NC portfolio. In the end, how much equity is put in will hinge on the final debt financing and the related loan-to-cost ratio. On what we learned from NC-1, I believe we state quite clearly in the prepared remarks that we are working hard to put the financing together for the next contract far ahead of time and to make sure it is an investment-grade project, with every term fully nailed down, financeable, and able to be underwritten in advance. In the end, if we bring on all 105 megawatts, that comes to a little more than $1 billion for the project. Then, if you assume a certain LTV, assuming the credit markets don’t worsen drastically from here—broadly, I think they are in better shape than the headlines suggest. Completing our deal today, I think, is something of a testament to that. I think you can roughly infer from the potential LTC what the equity contribution will need to be.
Nick Giles
analystAll right. I'm inclined to agree. Thanks, everyone. Thanks for the update.
Sam Tabar
executiveHello, Paul.
Paul Golding
analystHello, thank you very much for the question, and congratulations on all the progress. I'd like to ask about the cloud business, and maybe this one is for Michael. When we consider the commitments across these five contracts and the 750 million in revenue contracted, how should we think about who is bearing the risk across the various constraints involved in delivering that capacity, particularly regarding potential reliance on colocation partners beyond the deployment you're doing in Montreal? How should we view that risk profile for delivering the cloud agreements there? Then, perhaps as a follow-on, how is the GPU supply chain looking for the chips themselves, given Sam, you noted VR capacity, and I'm just trying to get a sense of the backdrop there. Thanks very much.
Michael Francisco
executiveThank you. The manner in which we run our business provides a degree of insulation from those risks. From our conversations with customers, we've learned that in the past they've faced difficulties with parties promising delivery dates without, at the deal's outset, putting everything together in a way that is fully transparent to them. Our approach to market is that we sign no customer agreements or MSAs until we have clear visibility into the RFS timeline for the data center colocation space, along with commitments regarding the GPUs from the selected OEM and the other components needed to stand up those clusters. Taking that approach sometimes means disappointing customers at the beginning by pushing our delivery date farther out than they might want it initially, but it does allow us to actually hit the dates we intend to go after. Things like Paris happen, but typically, for the most part, as we go out and sell these deals, we only sell things we are confident we can deliver in. Having a strong set of colocation partners where we have built trust and have confidence in their ability to deliver really helps us meet those timelines.
Paul Golding
analystGreat, thank you very much, Michael. I'd like to ask a brief follow-up about the supply chain, since the cloud business is carrying so much momentum right now. On the cloud-side build-out that falls under your responsibility, are you making any long-lead purchases ahead of time, or does that really depend on particular sites having a particular basis of design, meaning you must wait for greater clarity there? How should we think about long-lead items — whether networking, cooling, or anything else within your remit? Thank you.
Michael Francisco
executiveYeah, this year we've moved away from speculative purchasing. When we changed the business model, we ceased buying items with the plan of reselling them down the road. There are a few exceptions now and then. For instance, in one situation we placed orders for Nvidia networking fabric, because we needed to guarantee we could deliver Nvidia RA architectures to our customers. Apart from that, we buy only once the customer's prepayment has come in. That gives us a way to establish our timelines. To return to what I said about getting the various components lined up: frequently one element of that cluster has the long lead time, yet we can coordinate with our colocation partners to get the timing right. The brief answer is that we rarely do this, only in special cases. Nvidia fabric takes so long to arrive that we made that decision with complete awareness it would be snapped up the moment it landed.
Paul Golding
analystGreat. Thanks, and congrats again.
Michael Francisco
executiveThank you.
John Todaro
analystHi everyone, thanks for taking my question. Hey, Sam. What's your thinking on expected CapEx for NC-2 and NC-3? And specifically, would those costs be capped, or if it comes in a bit higher, is there a percentage that falls to the tenant or some other partner there?
Sam Tabar
executiveThat's probably one for Billy and Cam together. Can, do you want to give it a first shot, either of you?
Billy Krasnokutsky
analystWe are still in the early stages of putting the budget together, and the total project costs could shift depending on which clients are selected. Any customization or added costs that the end-user requires, we do expect the end-user to cover those through installation fees and prepayments.
John Todaro
analystOkay. Got it. My second question then is just about the regulatory environment. From what I understand, in North Carolina, the elections, the state legislature shifted somewhat further left, with the State House moving toward Democrats. Given the obviously large presence in North Carolina, could you give us a quick refresh on the regulatory environment there, whether that's power or permitting?
Sam Tabar
executiveGo ahead, Billy.
Billy Krasnokutsky
analystNC-2 and NC-3 already carry data center zoning; that's part of how we do diligence when picking these projects, to be sure we can get them done on time and keep the risks tied to them as small as possible. To repeat, this project has data center zoning. We don't have to go obtain any special permits or use authorizations for these projects. As for community pushback, here's an example of what we did in North Carolina 1: although nothing required us to do it, since we held full permits and were in fact producing at that point, we took the initiative and put together a community event as part of our dedication to fostering good ties with the community. Just over 200 people came to that event, and we walked them through our retrofit approach of repurposing an older warehouse, our closed-loop water system, which, incidentally, was already our standard practice before water use became a talking point in the media at all. We also talked about what we contribute to the community, and people were very appreciative of all of it. We intend to do the same in NC-2 and in NC-3.
John Todaro
analystOkay. Got it. Thanks for that, gentlemen. Appreciate it.
Sam Tabar
executiveHi, Michael.
Michael Donovan
analystHey, Sam. Hey, everyone. Appreciate you taking my question. On the last call, you talked about late-stage customer opportunities connected to Cranbourne. How have those talks moved along, and when do you think the first capacity will be ready to deploy?
Michael Francisco
executiveThose talks have moved along really well. We think the first deals will close in early Q1, possibly late Q4, with deployments taking place in Q1.
Michael Donovan
analystThanks for that. Turning to Continuum, now that it's launched, how would you describe the level of customer interest, and which kinds of customers are engaging the most?
Michael Francisco
executiveSo Continuum is a fascinating product, since it appeals to a fairly niche group that includes companies like ours, though we've also seen interest from certain enterprise customers. The majority of people we're encountering want to address the problem of distributed or fragmented power. We've spoken with colocation providers centered on regional data center configurations who want this technology so they can deliver those regional hub-and-spoke solutions, along with some enterprise customers who've examined it as a way to offer a more robust logical super cluster by drawing on, again, smaller power sets. My expectation is that the first deal we sign here will take a little while, simply because of what's required to deploy, plan, and actually bring it to life. Initial interest has been solid, and we've had some quite compelling discussions about scaling this as time goes on.
Michael Donovan
analystThat's useful. So do you plan to use that in order to connect NC-1, NC-2, and NC-3, or is it meant for other internal sites?
Michael Francisco
executiveThat's something we might do based on what customers want, though I'm not able to say anything about how our existing deals or ongoing negotiations are structured, or whether that would be part of them.
Michael Donovan
analystI appreciate that, and I wish you the best of luck going forward.
Michael Francisco
executiveThank you.
Sam Tabar
executiveHey there, George.
George Sutton
analystThanks. Sam, you said demand for NC-2 and 3 is much stronger than what you saw for 1. Could you give us some sense of whether that's a site-specific situation or a market dynamic? Does that give you confidence in your ability to deliver with a retrofit model? Just curious about that.
Sam Tabar
executiveI believe it's the first and third, but I'll let Billy field that one.
Billy Krasnokutsky
analystThere are several factors at play. What we accomplished with NC-1 struck a chord with a number of parties who had previously been examining the project. Being able to deliver power in 2027 matters a great deal. A lot of companies are pushing back or scrapping projects. We have demonstrated that we can execute with a very fast turnaround, and we intend to repeat that at our three North Carolina projects in 2027. Prospective customers value that, they recognize the proven track record, and that is what is fueling demand at those sites.
George Sutton
analystGot it. Sam, you shared a rather persuasive figure — that in certain cases you could see 100% upfront payments. I just thought it couldn't go unasked on this call what you meant by that.
Sam Tabar
executiveMichael, would you like to handle that?
Michael Francisco
executiveSure. As we watch the markets get tighter — or at least watch the headlines about tightening — I mostly share Cam's view that those headlines make things sound worse than they actually are. Several things are at play here. One is that plenty of customers now see owning that hardware on their own balance sheet as a plus. If you think about how traditional enterprise hardware has usually been acquired, keeping it on the balance sheet genuinely helps them on the taxes and depreciation side, and there's some accounting upside in that. At the same time — and we're seeing this with enterprises and with some of the bigger foundational labs — some of the larger, well-funded AI startups are showing that same trend, where they want to put some of the capital they've accumulated into their own hardware, to lock it in over time and make sure those assets are readily available to them. Beyond that, I believe customers are also grasping how the market really works and realizing that stepping in and helping with the prepayment actually speeds the transaction up, gets them up and online faster, and then somewhat lowers the OpEx cost over the life of the deal. A number of factors are driving that, and as the market keeps maturing and adjusting, I think we'll see more of this, but I also think people will work out some of the financing pieces too and get creative about how we deploy these things.
George Sutton
analystThat's a really helpful perspective. Thanks for sharing your thoughts.
Michael Francisco
executiveHappy to help.
Sam Tabar
executiveHi, Mike.
Mike Colonnese
analystHey there. Sam and team, good morning. Thanks for taking my questions. The first one from me — I was just curious whether you could give us more color on what the remaining milestones are that are still outstanding and need to be achieved before you can convert the existing LOIs at NC-2 and 3 into signed leases, now that the acquisition has closed.
Sam Tabar
executiveBilly, do you want to take that?
Billy Krasnokutsky
analystCertainly. The two main milestones we're discussing right now with prospective clients, in order to get a service agreement signed, are technical revisions to the basis of design for the customers we're presently in talks with, along with confirming delivery schedules for the long-lead equipment items.
Mike Colonnese
analystThat's useful context. Thanks for that. Earlier there was some discussion about how quickly you managed to deploy NC-1 — just over 10 months. I'm curious, given the basis of design currently under negotiation, what deployment timelines might look like for NC-2 and 3, particularly since the initial RFS is targeted for 2027 — just trying to get a better sense of when you could actually start monetizing potential contracts once a lease is signed.
Billy Krasnokutsky
analystYes. At the moment we're targeting the end of 2027, which gives us a bit more of a buffer on what is, again, already an aggressive schedule. I don't see many companies pulling off these kinds of deployments in under 12 months. We're aiming to follow the same playbook — even though the basis of design involves a newer generation of chips or an entirely different manufacturer, depending on who the end-user turns out to be — and we remain confident we can deliver a project within 12 months.
Cameron Schnier
executiveLet me just add to that: we're really not all that eager to optimize for speed. I think we're drawing a fairly firm line in the sand that what we're optimizing for is holistic project returns and the ability to finance a project very easily and cleanly; we're genuinely not eager to compromise for the sake of some artificial timeline we impose on ourselves. As for customer demand, we know how sought-after these assets are. We're really just trying to position ourselves as well as possible to monetize that and succeed over time, and to sort of mitigate any perceived risk factors surrounding it.
Mike Colonnese
analystThat makes sense. Thanks, and congratulations on all the progress, everyone.
Sam Tabar
executiveThanks a lot.
Sam Tabar
executiveHi, Ben.
Ben Sommers
analystHey there, good morning, and thanks, folks, for taking my question. You mentioned enterprises and government and so forth potentially becoming a larger piece of the demand mix going forward for colocation services. I'm just kind of curious how that dynamic might be shaping the way you're thinking about growing the power portfolio from here.
Sam Tabar
executiveIs that regarding cloud or colocation? I believe this refers to colocation?
Ben Sommers
analystFor either one or the other.
Sam Tabar
executiveIt simply hinges on whom you happen to be talking with; as far as colocation goes, our sights are set on Fortune 100 companies and public sector end-clients too. Is there anything further we could discuss, Billy, without revealing our ongoing negotiations? Most likely not.
Billy Krasnokutsky
analystIt's a bit tough, but once again, capacity scarcity is what's really driving things. The hyperscalers are absorbing these bigger chunks of capacity, along with the smaller colocation megawatts, so these clients end up stranded with no inventory available anywhere in the market. We've had a handful of prospective clients among the top Fortune 100 seeking smaller deployments of 10, 20 megawatts.
Ben Sommers
analystThat's really helpful. Moving to cloud services, you mentioned — I believe — an average contract length of roughly four years; how are you thinking about term length going forward, and how do you weigh contract duration against possible pricing differences tied to how long a contract runs? Thank you.
Michael Francisco
executiveA core principle guiding us is that we won't put together contracts lacking full payback inside the original contract's term. What customers are showing us is genuine interest in longer commitments than what we saw last year, or even earlier this year. There are a couple of forces at play. One key force is simply that people used to believe you could go negotiate a two-year contract for GPUs and then have an out after two years to renegotiate and get those prices down. What the market has shown us is that isn't actually the reality — sometimes, if you look at what the H100s cost now, those GPUs actually cost more today than at launch. Had I negotiated a contract for two years two years ago, I'd be paying more at the point of renegotiation; those dynamics aren't working out for the folks who wanted shorter-term deals. The other piece is that GPU capacity is hard to find, so the notion that you'd sign a shorter-term contract to go back through the process to maybe pay more or maybe not even be able to find that capacity three years from now isn't a risk many folks are willing to take. We're seeing them push for longer terms, and with those longer terms, we can be a little bit more creative with the contract's structure to make sure we get our payback, but then provide some relief in terms of the average cost for the customer across the term of that deal by kind of blending the rates across that life cycle.
Ben Sommers
analystThat's really helpful. Thanks for taking my questions.
Michael Francisco
executiveYou're welcome.
Brian Barotzian
analystHi everyone, and thanks for the opportunity to ask. Hey Sam. Great quarter — tremendous progress — and thank you for a really informative print. My main question concerns forward leases, which I fully agree with, by the way: when you talk about targeting more of an investment-grade wrapper as we think about your future capacity, maybe you could talk a little bit just so I understand. Is that the same format you have at NC-1, or do you mean that for the wrapper situation, it's separate from what we'd expect to see at NC-2 and NC-3? Because obviously these are triple net lease real estate assets, and your underwritten cap rates obviously are going to be lower for a higher IG offtake. Could you give a little color on that?
Sam Tabar
executiveI'll defer to Billy and Cam. I'm not sure I followed the question 100%, but perhaps Billy and Cam did.
Cameron Schnier
executiveSure, I can jump in here. Brian, this is Cam. When you look at it as a whole, our approach now is quite different from what we did with the first NC-1 lease, where, on a prevailing basis, there isn’t a complete investment-grade credit wrap and it isn’t directly with an IG counterparty. As you can see, placing the debt capital simply took longer, and that is obviously something we are aiming to address. One of our key objectives—something we really don’t want to compromise on—is making sure that the next lease we sign carries an investment-grade rating and that, before signing that lease, we have a certain level of comfort that some form of committed debt is available on attractive terms.
Brian Barotzian
analystGreat. Thanks, Cam. Then there's another thing: with costs climbing in the supply chain that we're seeing throughout the industry, and a tougher AI infra backdrop, you brought up being able to pass costs through and get higher yields, or that spread between your cost of capital and your yield on cost — have customer conversations, or early customer conversations, been receptive to that? Like, "Hey, cost of capital is rising, our build costs are rising. Demand for power is so strong" — are they saying, "Hey, the dollar per kilowatt month you guys are charging is fine. We can pay an extra $5, $10, $15, $20 of rent." Has that gone over well with customers?
Sam Tabar
executiveBefore we answer that question, I just want to say that negotiations are ongoing right now, and we simply don't want to disclose the current postures of various counterparties — I would speak in generalities, either Cam or Billy, on that.
Brian Barotzian
analystThat's specifically what I mean.
Sam Tabar
executiveRight.
Billy Krasnokutsky
analystSure. Go ahead and use it. Broadly speaking, we aren't encountering any issues in that area. In fact, customers are stepping up with stronger prepayments and installation fees — again, essentially as a premium for capacity delivered in 2027, given where the industry stands right now regarding available capacity and inventory. Everyone recognizes that labor, equipment, electricity — all of those costs have outpaced typical increases over the last year, and that hasn't caused trouble in negotiations.
Cameron Schnier
executiveExcellent. I won't paint with too broad a brush, but the comparison we've drawn is this: year over year, when we assess customer proposals alongside our own budget for development at this point, the implied yields look more attractive than what we saw at the time we signed our initial North Carolina lease.
Brian Barotzian
analystFantastic. A truly remarkable quarter, and excellent headway, everyone. Eagerly awaiting the following quarter.
Sam Tabar
executiveSo are we.
Brian Barotzian
analystTake care, guys.
Sam Tabar
executiveOh, hi, Kevin.
Kevin Dede
analystHi, Sam. Appreciate the invitation to join, and it was really good seeing you in Singapore as well — thanks for the dinner over there. A pleasure. I'm interested in MTL-2. Congratulations on getting that project underway, I suppose. What amount of power you had available there isn't clear to me. I've lost track of it, so please forgive me. I believe you also said something regarding behind-the-meter, and I'm simply wondering how such a process would function, considering the fairly strict regulatory constraints in Quebec. dog barking in background
Sam Tabar
executiveIs it you asking that question, or is it the dog?
Kevin Dede
analystThat dog is the one making noise — not me. I suppose it’s a fair question. It all hinges on whom you ask.
Sam Tabar
executiveRight. (chuckles) Billy, would you like to handle that one, or Cam?
Billy Krasnokutsky
analystYeah. That one was a smaller deployment right from the start. At that site, there's only about 4 megawatts available, and we're looking at natural gas fuel cells to help us generate a bit more energy and a bit more heat we can recover, plus some heat reject projects we're considering in the area that would put us in a better spotlight for getting higher allocations from the utility company as well; implementing natural gas fuel cells at that facility is kind of a two-in-one solution for us.
Kevin Dede
analystOkay. Thanks, Billy. Thank you. Regarding the full 99 megawatts at NC-1, does the timeline for when that could possibly be delivered change at all? Maybe give some color on your negotiations with Duke and on taking NC-2 and 3 from 60 to 200?
Billy Krasnokutsky
analystNC-2 and NC-3 are still in preliminary talks with engineering regarding the expansion capabilities. As usual in our due diligence, we make sure there's a positive way forward to getting more power. Those remain initial talks with Duke. For NC-1, same thing; we're still looking at some supply chain issues on the Duke side where we're working together on where we can help and hopefully advancing that timeline. At the moment it's looking at end of 2027.
Kevin Dede
analystThis might be a sore topic, but I'll leave it to you, Sam, to add whatever you think is appropriate. Obviously, there were some struggles with Microsoft's dealings with Nscale, and I'm just wondering if any of that may have rippled through to you and to the prospect of Nscale filling out all the available power as it comes to NC-1.
Sam Tabar
executiveAll right. Go ahead, Billy, but that's not sore, go ahead.
Billy Krasnokutsky
analystHonestly, it's difficult for us to say much about a relationship we have no visibility into. What we do know is that Nscale is utilizing the capacity at NC-1. As for the expansion capacity, while for continuity and client relationship reasons we'd prefer it to be Nscale for the expansion, we are open to other users. As Cam said, securing IG type terms is the primary factor driving our selection process. What we do know is that Nscale is using the current capacity at NC-1.
Kevin Dede
analystPerfect. Thanks, Billy. Thanks for taking the questions, gentlemen.
Billy Krasnokutsky
analystThank you.
Sam Tabar
executiveThank you, everybody, for joining us today; we look forward to the next earnings call and have a wonderful day. Thank you.
Operator
operatorThis concludes today's call. Thank you for your participation. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete WhiteFiber, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to WhiteFiber, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in WhiteFiber, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.