AIC Mines Limited (A1M) Earnings Call Transcript & Summary

October 16, 2025

ASX AU Materials Metals and Mining earnings

Earnings Call Speaker Segments

Operator

operator
#1

At this point I'd like to pass the conference to Mr. Aaron Colleran, our Chief Executive Officer. Please proceed.

Aaron Colleran

unknown
#2

Thanks, Darcy. I'll give you a quick run-through of the September quarter, and then we'll take questions. The September quarter was an excellent one. Eloise turned out 3,324 tons of copper and 1,722 oz of gold in concentrate, with an all-in sustaining cost of AUD 4.97, or $3.23 per pound of copper sold, and an all-in cost of AUD 5.29, or $3.44 per pound of copper sold. Eloise hit guidance for the ninth quarter in a row and generated net mine cash flow of AUD 11.8 million after Eloise's capital expenditure. AUD 11.8 million of free cash flow. From a realized copper price of AUD 6.72 per pound, a realized gold price of AUD 5,442 per ounce, and a realized silver price of AUD 63 per ounce. All great prices, but today's prices, as you're well aware, are 10%, 20%, and 30% higher respectively. Today's prices would have generated an extra AUD 7 million in free cash flow, a 60% increase. You can see why we're excited about what the December quarter might deliver. In fact, we're hugely excited about what the December quarter might deliver. At the close of the September quarter, we were 380 m from the J1 lens at Jericho. You know where that leaves us at the end of the December quarter.

Aaron Colleran

unknown
#3

Yeah, it could turn out to be a really nice Christmas. On page four of the quarterly, you'll also notice that we're going to mine a substantial amount of Lens 6 during the December quarter. We're looking for another solid quarter, with guidance of 3,200 tons to 3,400 tons of copper and 1,600 oz of gold in concentrate. Speaking of Lens 6, have a look at the drilling results for Lens 6 on page five of the quarterly. Those results extend as much as 50 m beneath the existing resource. Sensational results. Strong copper grades and strong gold grades as well. ED529, 5.2 m of estimated true width, grading 3.5% copper, 0.8 g per ton gold. ED547, 8.8 m estimated true width, grading 3.2% copper and 1.8 g per ton gold. ED548, 9.3 m, 3.4% copper, 1.2 g per ton gold. ED549, 3.4 m, 4.9% copper and 0.5 g per ton gold. Sensational results. Now, back to the quarterly result. The AISC may come in a bit above what some people expect, but you'll see that underground development costs ran relatively high because of the above-average capital development completed during the quarter. That's mostly a timing issue, and those costs ought to normalize over the rest of the year.

Aaron Colleran

unknown
#4

Capital spending came in pretty much where we told you it would. In other words, the majority of line items sat at roughly 25% of the full-year guidance. With one quarter of the year behind us, that's exactly where they ought to be. The CapEx items running ahead of budget are Eloise mine development, Eloise resource definition drilling, exploration expenditure, and corporate expenditure. Let me walk you through those exceptions. Eloise underground mine development carries guidance of AUD 25 million for the year, and we spent AUD 8.8 million in the September quarter, so 35% spent. As I just said, this will normalize over the rest of the year. Eloise resource definition drilling carries guidance of AUD 2.5 million for the year, and we've spent AUD 1 million, so 40% of full year guidance. That is effectively over budget, but what would you expect us to do when we're drilling holes like ED548? Let me repeat it. 16.2 m grading 3.4% copper and 1.2 g per ton gold in Lens 6. Exploration expenditure, that's at 33% of full year guidance. This will wind back as the wet season rolls in. It happens every year. Corporate expenditure is at 30% of the full year guidance. This will wind back as we continue to tighten our belts.

Aaron Colleran

unknown
#5

We're out of Tim Tams at head office, unfortunately. But more significantly, the major item: the Eloise expansion project is moving along nicely, and while we're still at an early stage of construction, it's tracking both on budget and on schedule. Funding and expenditure for the expansion are laid out very clearly on page 15 of the quarterly, and I'd point analysts in that direction. As noted there, the project's funding parameters are still consistent with the sources and uses set out in the equity raise presentation we released on the 20th of June this year. Across the coming 15 months — that is, through to the 31st of December 2024 — we have AUD 69.2 million left to spend at the Eloise plant expansion, AUD 53.3 million needed to complete the Jericho link drive and begin mine development, and AUD 33.7 million left to spend on non-plant infrastructure, for a total funding requirement of AUD 156.2 million. Our current liquidity stands at AUD 128 million, comprising cash and the Trafigura facility, and we expect Eloise and Jericho to generate approximately AUD 70 million over the next 15 months. Funding sources remain a comfortable match to uses. As mentioned earlier, should current copper prices hold, sources are well in excess of uses.

Aaron Colleran

unknown
#6

Should any of those figures prove hard to work out, or if you run into trouble getting them through your model, give me or Duncan a call this afternoon—we'll clear things up and walk you through it. The resource definition drilling results from the Jolly shoot at Jericho deserve some attention. We put those out on Tuesday this week. Jolly remains at resource status, though it appears minable in the very near term. Decent grades, decent widths, and as of 30 September 2025, the Jericho access drive sat just 380 m off. That means we could be grade control drilling this shoot from underground during this quarter, and mine development might begin as early as the March 2026 quarter. The Eloise processing plant has spare capacity to treat any early Jericho material right away, and early mine production will also let us build a solid stockpile before the expanded processing plant is commissioned. That lowers the risk on our startup and accelerates our ramp-up. This is excellent news for shareholders. On regional exploration—I know plenty of people were eager for those holes. Sadly, there are no results to report this quarter, since we sent the Jolly samples through the lab ahead of the regional targets.

Aaron Colleran

unknown
#7

Expect to see outcomes within the coming four to six weeks, which means we'll probably issue a mid-quarter exploration update announcement. That wraps up my review, so I'll have the operator open the line for questions. Thank you.

Operator

operator
#8

Thank you. Should you want to pose a question, kindly press star one on your phone and then wait until your name is called. To withdraw that request, press star two instead. In case you are using a speaker phone, please lift the headset before asking. Our first question is from Richard Adams, Private Investor. Please go ahead. Hi, Aaron. Congratulations on the great quarter. I have a few questions. First, Deep's West. Why are we drilling so deep at the moment? I know there is an aspirational target of getting to 1.5 million tons per annum plant, which is going to cost an extra AUD 10 million. Is that part of it? Is that, you know, are we just going to go deeper as well as Jericho?

Aaron Colleran

unknown
#9

Richard, that's a fair question. I believe you sent me some questions roughly a week ago, and I apologize for not having replied to those yet. I will get back to you. The Deep's West was the hole we drilled for the downhole EM program. That is where we hit it. Yes, I understand, and I completely agree with what you're saying. That is deep. It would be nice to locate ore near the top of the mine instead of at the bottom. You know, we found ore at the bottom of the mine. It isn't very far from development, and the job is to trace it upward. When you look at the downhole EM we ran, that in-mine loop is already paying for itself. The EM plate does move upward and will keep doing so; we're planning to drill some additional holes up dip instead of down dip. Richard, the intersection is deep at present, yes, but where will it take us? Let's see whether we can trace it up dip. Okay. On. Sorry, sorry. The more important part, or the other component of your question, concerned 1.5 million tons per annum. Now, once fully developed, Jericho alone can achieve 1.5 million tons per annum. We do not depend on Eloise today or on future Eloise exploration success to reach a 1.5 million tons per annum run rate.

Aaron Colleran

unknown
#10

That said, even though we don't depend on it, I figure Eloise is going to be around for quite a while. It might not run at 600,000 tons per annum, but 300,000 or 250,000 tons per annum of good high grade from Eloise, I believe, could persist for a very long time as we keep enjoying this kind of exploration success. Hopefully that covers your question fully now. It does, so if I may continue, apologies. Yes, of course. At the board level — and again, I don't need any detailed mechanics — what are the traffic lights and the roadblocks on the way to that 1.5? I'm aware that, yes, you'll be doing some underground drilling, which will be 206 m, 208 m lower than what would have been required previously, and you'll likely do that in the March quarter to infill and further define Jericho. You've got to be getting nearer to the point of committing to 1.5. You've previously said it would cost an extra AUD 10 million. Based on today's report, you have an additional AUD 25 million in the bank over the coming nine months.

Aaron Colleran

unknown
#11

What would get you and the board to actually commit or shift from 1.1 to 1.5? Isn't it smarter to do that sooner rather than later, or is it simply that you don't want to mill at 1.2 or 1.3? You'd rather have it at 1.5 once things reach that stage. What would push you to tip over and say — you know — fire off an ASX announcement at 8:24 A.M. that we've now committed to 1.5? Yeah, look, okay, great question. In case anyone isn't fully clear on this, we have effectively committed to 1.5, Richard. The moment we put those oversized items into what we're currently building, that was the commitment. We will ramp up to 1.5 million tons per annum. Nothing is stopping us. No decision is required. We have the ore in front of us to do that. Sorry, we have the mineral resource in front of us to do that. Just in case the JORC police are online, this is a decision based on the resource. What's holding us up is development. As simple as that. There's a ramp-up period to 2 million tons per annum. Sorry, of course, to 1.5 million tons.

Aaron Colleran

unknown
#12

I'm getting ahead of myself here—that came out as a bit of a Freudian slip. The whole thing centers on underground development. Right now at Jericho, we have a single jumbo, as everyone knows. It's working in the link drive, the access drive. As soon as we have the space and the ventilation, a second one becomes possible. And once space, ventilation, and funding are all in place, we could go to three, even four. That's the deciding factor. Capital is what limits us—that's the real constraint, not commitment. Richard, what you said about how much more money we'd make at these prices genuinely helps us accelerate that. The commitment doesn't need to be moved up. What needs to be moved up is the spending—the underground development that opens up the entire line of strike at Jericho. It isn't the case that the Jericho access drive hits J1 and—bang—we're mining at a rate of 1.5 million tons per annum. Apologies for belaboring this, but there are a number of years involved—I believe we've mentioned this before—regarding how fast we can reach that 1.5 million tons per annum rate from cash flow and lower copper prices. Under those conditions, it takes us quite a few years. With higher copper prices, we get there.

Aaron Colleran

unknown
#13

We can reach that point ahead of FY 2030 using low prices and funding it from cash flow. It lands roughly at FY 2030, perhaps slightly after. Everything hinges on capital. All right. May I squeeze in one final question before you continue. Kevin Downs. We're clearly still awaiting Arlington, Yukon, Defiance, Baghdad. Those seven holes look somewhat delayed, as you mentioned, you're giving Jolly priority. Could you share a bit more detail on Kevin Downs? I likely have to be careful here. I don't believe I can. I think you'll simply have to wait for us to report what those results turned out to be. Any hints or updates? The hole has been drilled. We know how it looks. We're awaiting the assays coming back. We need to issue a full release covering all those areas, walk through the MT, the results, what those results signify, how we're reading what the follow-up is. Some work remains there to make that clean and clear for you. To merely hint at those kinds of things just isn't appropriate on this call. Okay. Truly the last question, truly promised. The spend passing at Eloise right now, which you're likely to fill in during the March quarter, what percentage is that?

Aaron Colleran

unknown
#14

Is it roughly 5% or 10% additional ore that can be fed in right now, or is it more or less than that? Yeah, it's in that ballpark. About 5%. What we have is that on a good day, a mill is capable of processing 725,000 tons per annum of Eloise ore. This is a fairly complex calculation, but allow me to walk you through it regardless. At present we are feeding in approximately 625,00 tons - 650,000 tons per annum of Eloise ore. That leaves somewhere in the range, measured annually rather than daily, but annually, of 75,000 tons- 100,000 tons of spare capacity. Jericho is somewhat harder than Eloise. It contains a bit more silica, which means it moves more slowly through the mill. We have somewhere between, in terms of spare capacity, 50,000 tons- 75,000 tons per annum of Jericho that could be pushed through. Past that point, you can begin considering displacing Eloise, because clearly, with any kind of build-up of Eloise ore, we have that wonderful high grade from the deeps and some of those lovely remnant stopes from the upper levels running near 3%, if not 4% copper. Nothing beats them. In other areas, when we are approaching the end of a stope, the end of a level, those kinds of situations, we are putting through 1.8%, 1.6%, perhaps 1.5% ore.

Aaron Colleran

unknown
#15

We can keep that in place and begin feeding some Jericho material through. It's nearer, possibly achieving 1.8%, improved gold recoveries, that kind of thing. As I mentioned, it's a complex calculation, so let's say roughly between 50,000 tons and 100,000 tons per annum of capacity, and additional capacity if required. Should the grades come in higher, we'll simply substitute it for Eloise ore. We'll accumulate our stockpile, which will be excellent. What that means is we'll have a stockpile sitting ready simply to push through once the expansion is finished, and we'll see whether it truly can operate at 1.1 million tons per annum and keep it running along, I'd suggest, at 1.2 million, and we'll see how things go if that stockpile has been built up. I trust that addresses your question, Richard. It absolutely does. Thanks once more. You've been extremely generous. Thank you. No, thank you, Richard. Those were great questions. It's useful that you raise them because, as you're aware, we're extremely close to this. Occasionally when we condense it or release it publicly, it's heavily condensed or high level, and perhaps it isn't as clear as it ought to be. I appreciate you asking those questions since they're all significant, significant points.

Aaron Colleran

unknown
#16

Everything's fine. Thanks. And thanks once more.

Operator

operator
#17

Appreciate it. As a reminder, if you'd like to pose a question, just hit star one on your phone. Our following question is from David Coates with Bell Potter Securities. The floor is yours.

David Coates

unknown
#18

Much appreciated, and hello there, Aaron. I'm grateful you reached out.

Aaron Colleran

unknown
#19

Morning there, David.

David Coates

unknown
#20

Appreciate you fitting us in this morning, and congratulations on the strong start to FY 2026. I have a couple of questions, though the main one for me concerns what you said about the Jolly shoot and securing access to Lens 6. Could you walk us through, I suppose, the kinds of mine development requirements needed in order to actually get that fired up?

Aaron Colleran

unknown
#21

Yeah. If you look closely at the diagram, it's likely number 1 or 2 on figure 1 — you really have to zoom in. You'll be able to see the link drive, where it turns out, and where it crosses J1. From there it goes north. As you know, we can go north to Jolly or south to Matilda. Ideally, we'll do both. We're just about to have stockpiles in place. After those stockpiles get used, they'll serve as drilling platforms for Jolly. In the upper few levels we can do grade control and drill. We reach the J1 lens, as stated in the quarterly, then turn out to the north, head up to Jolly and begin developing, and go south as well at the... That means we need a bit more equipment there. Either we need to miraculously invent that equipment or bring some over from Eloise — bring stuff over from Eloise where possible — and get ourselves into Jolly early if that's the decision we make at that point in time. Does that help? I'm probably a bit vague, but.

David Coates

unknown
#22

I'm guessing that space needs some additional ventilation, or is that already adequately handled at this point, or?

Aaron Colleran

unknown
#23

Right, so that ventilation shaft appearing on the same diagram — figure one — which internally we call JS3, you'll notice it sits just to the right of the Matilda North title. Yes, that's exactly where all the attention is going. You've put your finger on a crucial piece of upcoming work there, that vent shaft.

David Coates

unknown
#24

Alright, apologies — I feel like I ought to know this already, but what are the grades on those Jolly shoot lenses?

Aaron Colleran

unknown
#25

Honestly, you likely don't have that answer, since it's something I lack as well. As for those infill drill results we put out, the likely explanation for our not having it is the resource status.

David Coates

unknown
#26

Regarding where things stand with resources, yeah.

Aaron Colleran

unknown
#27

We are struggling to keep pace ourselves. Matt Fallon, if he happens to be listening in on this call, please hang up. That task is yours to handle, Matt. Listening to me discuss it isn't what you should be doing. That reserve work is now being run by Matt. Soon we'll place some stope shapes around it. Discussing it has been somewhat challenging because, from a genuine JORC standpoint, we cannot discuss Jolly since it isn't even included — everything there is inferred apart from all that drilling you witnessed, which we released on Tuesday. That lifts the status, and the grade control drilling we'll carry out from the JAD will bring us through to stope shapes around it. The likelihood is that we could be extracting mineralized material from there before we've even placed it into the reserve. Sorry, though, to answer your question, proceed using the average Jericho grade.

David Coates

unknown
#28

Absolutely. All right, thanks, Aaron. There's nobody better suited to be handling those reserves than Matt. Great, thank you so much.

Aaron Colleran

unknown
#29

Right, right. I'd bet almost anything he isn't on the call. He'll be at work — we'd have found him at his desk at 6:00 A.M. today. Thank you, David.

David Coates

unknown
#30

Thanks, Aaron.

Operator

operator
#31

Thanks. The following question is from Paul Kaner at Ord Minnett. You have the floor.

Paul Kaner

unknown
#32

Hi Aaron, thanks for taking my questions. On mill performance this quarter, throughput rose by about 20,000 tons. Is there anything worth highlighting that drove that increase compared with historical performance? Is it simply because a few extra stocks carried over from the prior quarter, given that you're not?

Aaron Colleran

unknown
#33

Right, right. Yes, yes. Paul, a straightforward response, honestly. When there's ore sitting on the ROM pad, we'll push it through aggressively, even to the extent of loosening the grind size somewhat to move it along, since, as you're aware, this chalcopyrite from the Eloise ore almost leaps into the concentrate—bubbles aren't even required to carry it there. On top of that, with respect to mill performance, we had 3 months. The shutdown began, I believe, on the 1st, 2nd, and 3rd, or the 2nd and 3rd of October. No shutdown occurred during the quarter, and it ran very well. Yes, simply a solid quarter.

Paul Kaner

unknown
#34

Yeah, that was pretty straightforward. Regarding the link drive — nice work getting that vent shaft completed. Could you perhaps explain how this might boost your productivity on the link drive and possibly Eloise too?

Aaron Colleran

unknown
#35

Right, that vent shaft worked out really well. Compared with the first one, it's almost like night and day, honestly. Given the piling we did with cement backfill, that was clearly the correct approach. The raised boring basically went off without a hitch and came straight through. It was good — no problems whatsoever. We sprayed it, a bit of water, and it has dried up. Everything's fine there. Ventilation went in fast, and we moved quickly to independent firing. What that means is blasting no longer follows the same schedule as Eloise. At Eloise we fire twice a day, once per shift. At Jericho we can now fire when ready, fire whenever a face is loaded, shut the area down, clear everyone out, and blast while Eloise keeps going. That accelerates development at Jericho. You asked about the effect on Eloise, which is interesting. Eloise actually gains from it, because its ventilation improves. As you know, strong ventilation at the bottom of that mine matters a lot. It isn't a benefit you can quantify, but Eloise does benefit too.

Aaron Colleran

unknown
#36

Generally speaking, Paul, we're achieving roughly 180 m of development per month with blasting occurring twice daily—at a rate of 2.2x to 2.4x per day. We ought to reach beyond 200 m, perhaps on the order of 220 m of development each month.

Paul Kaner

unknown
#37

Yes, that's excellent, and I appreciate the level of detail. One last question about the debt you have with Trafigura: I noticed you've hedged the currency on that. Do you have any thoughts about doing more currency hedging on your sales as you move through this expansion phase, or even on the commodity side?

Aaron Colleran

unknown
#38

And regarding granularity, Paul—you know how we are. Granularity is something we're always up for. On hedging, yeah, that's a terrific question. Personally, I find this gold price hard to believe, though my board doesn't share that view. We aren't gold bulls, and we're not hedging copper. Naturally, hedging copper is not something we'd do. At present it's dirt cheap. In my view it stays dirt cheap right up to $6 a pound. With gold, yeah, perhaps, perhaps—but it's only a perhaps. Don't read too much into that. On currency, with the worry that it might reach AUD 0.70, you know, that matters when you lock in at something like 6x4. With 6x, we simply know what we're getting from the $40 million. So locking that in was helpful. Now we know—and I think the reason we reported it is also a signal. There are one or two people who believe we won't draw that debt, that we've just kept it sitting there. Of course we'll be drawing that debt, we certainly will. It's very cheap debt, you know, and Trafigura is a great partner. We now know what it's worth in Aussie dollars.

Aaron Colleran

unknown
#39

No, honestly, Paul, my guess is that's as far as our hedging goes. We're definitely mindful of how the gold price helps us. Frankly, the Aussie dollar working in our favor around those 65 levels is great. It's a strange market. You and the callers will each have your own opinions, and probably better informed than mine, but it just looks too good to be true. Right now it feels like a boom in everything. Oil is down, gold is up, copper is up, the Aussie is down, iron ore is up. They can't all be correct. Something will shift. We locked in the Aussie.

Paul Kaner

unknown
#40

Got it, yes. Appreciate it, Aaron. Nothing further from my side.

Aaron Colleran

unknown
#41

Thanks, Aaron.

Operator

operator
#42

Thanks. Just a reminder — to ask a question, hit star one. Our next question is from Paul Hissey at Moelis. Go ahead.

Paul Hissey

unknown
#43

Hello there, Aaron. I have a few brief questions. Please excuse me—I may have missed what you described earlier. I believe you mentioned being 35% full of the full year run rate, and I didn't catch it. Was that sustaining capital? If not, could you just comment a little on how the sustaining capital spend is pacing across the year?

Aaron Colleran

unknown
#44

Yeah. Yeah. So with the guidance we provide, the line items we break out — one of them is underground mine development. For FY 2026, that guidance was AUD 25 million. The September quarter came in at AUD 8.8 million actual. That's effectively 35% of the full-year guidance, and we're only 25% of the way through the year. I just walked through each of the items that are exceptions. Those exceptions were Eloise underground mine development, Eloise resource definition drilling, exploration expenditure, and corporate expenditure. The one you asked about, the 35% one, is Eloise underground mine development. We spent more capital. We did more development during the quarter, at a rate above normal. We expect that to pull back — you know, to normalize across the remainder of the year. Don't be worried that CapEx, or underground mine development CapEx, is over budget. What I'm telling you is that it's a timing issue. Is that clear?

Paul Hissey

unknown
#45

Right, no, that does address the 35% point you raised. As for FY 2026 sustaining guidance overall, I believe the figure comes to AUD 41 million once you total the, I suppose there are three line items involved. It appears you spent roughly AUD 12.9 million during the first quarter. It seems like perhaps that covers all sustaining CapEx, not only your underground development, and by that I mean I'm taking the cents per pound in your quarterly figure and grossing it back up.

Aaron Colleran

unknown
#46

Yes, you’re doing well.

Paul Hissey

unknown
#47

You're somewhat ahead — not only when it comes to development, but on other sustaining items too.

Aaron Colleran

unknown
#48

Right. You've got just three items on that list. Plant and equipment — that sits at 24%, which is pretty much spot on. Then there's underground mine development, the piece we've already discussed. And the last one was resource definition drilling. For FY 2026, guidance stands at AUD 2.5 million, and during the quarter we spent AUD 1 million.

Paul Hissey

unknown
#49

That was the other one. Yeah, yeah.

Aaron Colleran

unknown
#50

Right, that's accurate. Since it's quite small — AUD 2.5 million — we generally guide somewhere around there, and I'd call that a typical outcome. Now, we spent somewhat more during the September quarter than we likely will in the December quarter. We're also comfortable saying we ran slightly over budget on the res dev drilling. We're talking hundreds of thousands of dollars here, Paul — not really material. As I mentioned, the results coming through have been excellent; we keep stressing that. On top of that, with some of the drilling at the upper levels of the remnant drilling we carry out, portions of it are tricky and don't always work out — it isn't always present, and so forth. It's a hard one to pin down with real precision. As I said, full year guidance sits at AUD 2.5 million. Should it land at AUD 3.5 million, don't shoot the messenger. That wouldn't be a bad thing.

Paul Hissey

unknown
#51

No problem. The low 40s remains the correct figure. For part of your sustaining, low 40 is still the right number.

Aaron Colleran

unknown
#52

Yeah. That's right. Correct.

Paul Hissey

unknown
#53

Okay, let me just revisit this briefly — I don't want to attribute anything to you that you haven't said about already being committed to that one and a half million ton expansion. Taking it at face value, an additional AUD 10 million buys you another 300,000 tons to 400,000 tons of yearly capacity. Practically speaking, how would the timing of that AUD 10 million outlay actually play out? My assumption is that it's an incremental figure that gets absorbed along the way, rather than something where you reach the end and then spend AUD 10 million more.

Aaron Colleran

unknown
#54

Right, yes. In a single word, Paul, that's correct. To be honest, and to give you a bit more detail, it's non-material. You'll see that spread across three years. I could discuss the lead times for the equipment we require. I could mention that the equipment comes to AUD 10 million. There could be some knock-on effects for certain rooms in the camp and things of that nature. It might be somewhere around AUD 10 million, AUD 12 million, AUD 13 million. Across the coming three to five years, you'll hardly notice it.

Paul Hissey

unknown
#55

Absolutely. This last question relates to something you may have already addressed when you answered Paul earlier. At this point, would you say we're at a kind of normalized working capital, or, you know, concentrate inventory stockpile levels? I'm aware there's been some building up and drawing down across the last few quarters. Do you think we're at a somewhat normalized level now?

Aaron Colleran

unknown
#56

Paul, that’s a tricky one. I don’t believe a normalized figure exists. Keep in mind, the wet season really drives everything. Our strongest quarter for drying conditions—weather-wise—is the September quarter. Up there, the September quarter is absolutely gorgeous. As we move toward December, we’ve gotten some rain lately. Starting in November, conditions can become somewhat harder. You might see us carrying more concentrate on the pad by quarter-end, or ROM stocks sitting on the ROM pad when the quarter closes. That throws off certain reporting numbers. I understand that. It’s hard to prevent. It all hinges on weather. No perfect world exists. It’s much like what we’ve just finished with almost zero—nearly nothing remaining on the pad, whether the ROM pad or the con pad.

Paul Hissey

unknown
#57

Right, yeah — that's exactly the answer I was hoping to hear. Okay, that's everything from my side. Thanks.

Aaron Colleran

unknown
#58

Thanks, Paul — that's a big weight off my mind.

Operator

operator
#59

Thank you. At this point we have no more questions. I'll turn things back over to Mr. Colleran for his closing remarks.

Aaron Colleran

unknown
#60

Thanks, Darcy. As we just heard, honestly, the September quarter was a great quarter. Eloise again achieved guidance and produced good cash. FY 2026 is a transformational year for AIC Mines. The expansion to 20,000 tons per annum copper is underway. The Jericho access drive is progressing well. We're de-risking the mine ramp-up with infill drilling success. Our exploration drilling is showing that sizing the major plant upgrade items for 1.5 million tons per annum was absolutely the right decision. Question time drew that out nicely. Thank you to the questioners. Eloise is performing well, and commodity prices are providing a tailwind. What more could you ask for? Thank you for dialing in. That concludes the call.

Operator

operator
#61

Thanks. That brings today’s conference to a close. We appreciate everyone for joining. You’re free to disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete AIC Mines Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to AIC Mines Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in AIC Mines Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.